Federico Ronchetti INFN, Laboratori Nazionali di Frascati. EMCAL: project update - Italy -. LNF - Frascati Fixture production Module assembly (proto) WLS fibers processing Lead procurement (proto) CT- Catania APD characterization and test SM Crates production. LNF status. - PowerPoint PPT PresentationTRANSCRIPT
EMCAL: project update- Italy -
LNF - Frascati• Fixture production
• Module assembly (proto)• WLS fibers processing
• Lead procurement (proto)
CT- Catania• APD characterization and test
• SM Crates production
Federico Ronchetti INFN, Laboratori Nazionali di Frascati
LNF status• Module production
– design fixed recently (25-26 june)• Universal fixture production
– Completed: Base, tool-plates, sleds, cylindrical rails– Ongoing: center-blocks, load cell plates, cross-beam
• Vacuum chamber for WLS fibers processing– Magnetron gun finally delivered and installed– Chamber closed– Out gassing chamber (10-8 bar)
• WLS fiber polishing – First bundles ice-polished– Quality checks underway
• Lead procurement– Lead tiles for prototype delivered– Ongoing reshuffling (from by-measure to by-module packs)
LNF universal fixture
Design by eng. Mario Del Franco
4Design by Mario Del Franco
Module front plateIs the governing dimension
Fixture parts
Fixtures realization progress
Picture not up-2-date: more components than shown have been machined
U. Fixture• All components
materials for missing parts are at hand
• Design for proto is module finalized (WSU EMCAL meeting last 25-26 of June)
• Full fixture production (2xLNF) over by the end of July.
Compression Table
Fiber processing chamber
At present: out gassing phase
WLS fibers polishing
APD / light guide coupled side
Side to be aluminized
Fiber module insertion tools
Modified WSU design by M. D. F.
Lead tiles metrological tests
Tile thickness
Lead tiles metrological testsHole diameter
Lead tiles metrological tests
Inter-hole distance
Short term schedule LNF TIME
Lead retooling mid July
Bond Paper Received from WSU
Fibers Aluminization Aug 1st
Test conical holes scintillator
AL2024 plates + pins + bushing
Aug 1st
(outsource?)
Plastic fiber collars Received from WSU
Washers ordered
Guiding rods From WSU (next week)
Black shroud From WSU (mid july)
Fixture full assembly Aug 1st
CT work in progress
• Undergoing activity in CT:– EMCAL Super-Module Crate Prototype– Installation of universal module stacking
fixture (delivered by LNF)
• Activity in CERN– Mechanical Integration of SM-crate– Load Tests
The crate prototype
• Design– blueprints– materials– safety
• Realization– The SM-
crate proto has been tested at 0° angle
SM crate load test @ CERN
SM crate load test @ CERN
Dummy strip modules
Additional testing phases
Mechanical work summary for 2007
Work in progress @ CT:– Installation of 1 universal stacking fixture and 1
compression table.– Procurement of ancillary equipment (load cells,
amplifiers, etc)
Work in progress @ CERN:– Load Test of the SM crate proto at 90°– Insertion test SM– Construction of the insertion plane
Catania planning for 2007-8
(mechanical)
Catania activity electronics, offline New lab space available for massive APD tests
Procured all the cards of the standard PHOS/EMCal electronic chain to be used for the APD test. This standard CERN set-up is almost ready (work is in progress on the software installation).
Draft for protocol for APD test established
First prototype for APD characterization as a function of the temperature is ready. Characterization of ALL 85 APD+CSP is done.
First version of track-matching ready and in CVS.
Alice-jet1 Catania
First set-up for APD characterization
LED flasherBox cointaing APD
Alice-jet1 Catania
First prototype for APD characterization as a function of the temperature
Standard –EMCal electronic chain
Light from LED flasher
Fluid from a chiller at a fixed temperaure
Alice-jet1 Catania
Alice-jet1 Catania
Barrel to EMCAL track matchingTrack matching efficiency and contamination for PHYTHIA minimum bias events
First version of track-matching ready and in CVS.
Presented to ACAT07
Aim: To clean the cluster sample for photon analysis (jets)adding PID information from EMCAL to high momentum charged tracks
Catania planning for 2008
(electronics, offline)
• APD procurement
• Test setup optimization
• start of massive APD testing
• Test beam data and cosmic ray data analysis
• Track-matching optimization and simulation studies on jet and electron showers.