emergency response plan [compatibility mode]
TRANSCRIPT
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
1/32
Emergency Response
Plan (ERP)
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
2/32
Emergency - Definition
An event at the site which may affect several
other work areas within and may cause serious
injuries, loss of life, serious affliction to health or
serious damage to property.
This may demand the rescue and relief
measures on a war footing and at short notice.
External resources may also be required to
handle the situation.
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
3/32
Objective
Preserving the life, property and environmentfrom the consequences of emergencies arising
within the site.
Systematic coordination of emergency controlaction to arrest escalation of emergency,
To evacuate personnel within or outside the site
where necessary and to rehabilitate them. Restoring normalcy in site operation with
minimum loss of time.
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
4/32
Emergency Response Committee
A committee for providing an orderly response
to an emergency situation. Typical constitution may be
Project Manager (Emergency controller) Nominated in-charge ( one who acts in absence of the PM)
Accounts & Administration In charge
HSE In charge
Plant & Machinery In charge Section / Area In charges
Time office In charge
Store keeper
Surveyor
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
5/32
Roles & Responsibility - Project
Manager
Responsible for activating the emergency plan and
assuming overall command
Immediately arrange for on-spot meeting
Take on-spot decision on the procedure to be
adopted
Arrange required facilities
Communicate to client, and other concerned off icials
at Head quarters / Regional office.
In his absence nominated in charge shall act
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
6/32
Roles & Responsibility
Accounts & Administration In charge
Attend the on-spot emergency meeting.
Ensure first aid facilities
Ensure arrangements for medical evacuationCoordinate with external agencies
Plant & Machinery In charge
Make arrangement for P&M, Operators and drivers
required for rescue operations.
Arrange Illumination as required
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
7/32
Roles & Responsibility
HSE In charge
Inform Clients.
Act as a co-ordinator for the ERC.
Organize rescue team with rescue apparatus like
(SCBA), gas detectors, stretchers etc
Time Office in charge
Collect details of manpower
Ensure the availability of first aid facilities andemergency vehicle.
Carry out head count at assembly point.
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
8/32
Roles & Responsibility Storekeeper
Arrange materials like tools & tackles for rescueoperation
Assist accounts and administration In charge.
Responsibility of Surveyor Assist the ERC to identify the exact location of
emergency
Responsibility of Security Personnel
Responsible to control the traffic on the road and keep
clear from obstruction
Temporarily suspend the entry of visitors and other
workmen
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
9/32
Emergency Control Room (ECR)
A room to be identified as Emergency
Control Room (ECR).
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
10/32
Emergency Control Room (ECR) Shall be equipped with:
Site layout showing assembly points and exit routes
Road maps leading to the site
List of telephone nos of key personnel & other externalagencies
Dedicated telephone line
List of safety equipment. List & location of fire fighting equipment.
Emergency power
Emergency hand lamps
Hand operated alarm / siren
Public announcement system Self contained breathing apparatus (SCBA)
Gas Detectors
Log book and stationery items
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
11/32
333.306m(1
093'6")
ToDevarbi
sanahalli
3no'sDEWATERINGPUMP
WATERCOLLECTIONPIT
Main
Gate
Approach Road
SRR2 Entry
Safe Path Way
First Aid
Emergency Assembly Point
Canteen
SITE LAY OUT
Toilet
You are Here @
EHS Training
Center
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
12/32
Any ERC Member
receiving in formation of
an incident
Project Manager organizes
to in form other ERC
members to proceed to ECR
Asses the situation and
decide activation of ERP
Alert all concerned as per
the established
communication system
Decide on the action plan
EnsureSituation
under control
HSE In charge
Investigate with
Section in charge
and submit
report
Procee
dtoE
merge
ncy
Contr
olRoo
m
ProceedtoEmergency
ControlRoom
ERC member start their activity like
Medical Evaluation / arrangement ofrequired machineries / control assemblypoint and head count transfer of injured
after rescue / information to client &
regional office etc.
Yes
No
Any ERC Member
receiving in formation of
an incident
Project Manager organizes
to in form other ERC
members to proceed to ECR
Asses the situation and
decide activation of ERP
Alert all concerned as per
the established
communication system
Decide on the action plan
EnsureSituation
under control
HSE In charge
Investigate with
Section in charge
and submit
report
Procee
dtoE
merge
ncy
Contr
olRoo
m
ProceedtoEmergency
ControlRoom
ERC member start their activity like
Medical Evaluation / arrangement ofrequired machineries / control assemblypoint and head count transfer of injured
after rescue / information to client &
regional office etc.
Yes
No
Emergency
Management
Flow Chart
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
13/32
HSE In charge
Investigate with
Section in chargeand submit
report
Termination of
Emergency and
Debrief
Ensure Workplace
Safe for Working
ERC decide
on seeking
external
help
Situation Under
Control
Follow up of action
taken
ERC member start their activi ty like
Medical Evaluation / arrangement ofrequired machineries / control assembly
point and head count transfer of injuredafter rescue / information to client &
regional office etc.
Take
precautionary
measure to make
the workplacesafe
No
No
Yes
Yes
Yes
HSE In charge
Investigate with
Section in chargeand submit
report
Termination of
Emergency and
Debrief
Ensure Workplace
Safe for Working
ERC decide
on seeking
external
help
Situation Under
Control
Follow up of action
taken
ERC member start their activi ty like
Medical Evaluation / arrangement ofrequired machineries / control assembly
point and head count transfer of injuredafter rescue / information to client &
regional office etc.
Take
precautionary
measure to make
the workplacesafe
No
No
Yes
Yes
Yes
Emergency
Management
Flow Chart
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
14/32
Declaration of Emergency
Chairman of ERC declares the emergency.
Declared by the established communication
system such as alarm or siren.
People have to stop the work and move
towards assembly point.
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
15/32
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
16/32
Assembly point
To be identified & clearly marked withsign boards
Sign boards to be placed to indicate the
direction to the assembly point fromdifferent work areas
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
17/32
1)TCS office
2)D.G. Room
3)L&T Office
4)Staff Canteen
5) Batching Plant
6)Workers Canteen
7)stores
8)P&M office
9)Time office
10) First aid centre
11)Workers canteen
12)Safety office
13) Workers toilet
14) Emergency assemblyt point
15) Parking area.
1
7
2 43
5
5
6
813
11
9
EB-6
EB-5
EB-4 FORM
YARD
ASSEMB
LY YARD
STEEL
YARD
GENERALSERVICEBUILDING
MOCK UP
YARD
UTILITY BUILDING AREA
12
14
14
Compound
Entrance
Roads for site use
Main road
Escape route
ESCAPE ROUTE
15
14
10
Typical Escape
Route with
assembly
points marked
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
18/32
Head Count
A system for accounting
for personnel following
an evacuation
Shall be taken by the
time office personnel inassembly point
Method for accounting
for suppliers andcustomers
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
19/32
Emergency Communication
System A standard emergency communication
procedure to be developed and communicatedto all concerned
Shall give clear guidelines on how
To alert workers in case of emergency To evacuate or take other action
To report emergencies
Communication shall be through Siren, PublicAddress System or any other suitable system.
The alarms shall be distinctive and recognized
by all.
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
20/32
Emergency Contact
Information
NO NAME DESIGNATION MOBILE OFFICE RESIDENCE
Key Personnel of L&T
Project Manager
Nominated In charge
Accounts & Admin In-
charge
HSE In charge
Time Office In-charge
P&M In-charge
Section / Area In charge
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
21/32
Key Personnel of Client & Consultant
Emergency Agencies
Police station
Fire
Department
State
Electricity
Board Office
CycloneWarning
Centre
Regional
Meteorologic
al office
Emergency Contact
Information
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
22/32
Local Authorities
District Collector
Councillor
Statutory Authorities
Electrical
Inspectorate
Factories
Inspectorate
State Pollution
Control Board
Regional Labour
Commissioner
Emergency Contact
Information
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
23/32
Hospitals
Hospital 1
(Distance from site
in Kms)
Hospital 2
(Distance from site
in Kms)
Hospital 3
(Distance from site
in Kms)
Others
Local Railway
Station
Local Bus Terminus
Nearest Airport
Emergency Contact
Information
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
24/32
Fire Fighting Facilities List shall be readily available at
Emergency control room Time office
Other conspicuous locations.
Location Type Capacity Numbers
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
25/32
Emergency Safety Equipment List & their storage locations shall be
readily available at Emergency control room
Time office
Other conspicuous locations.
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
26/32
Emergency Safety Equipment
Self contained
Breathing Apparatus(SCBA)
Oxygen Resuscitator
Hard Stretcher Portable Gas
Detector
High Power searchlight
Hand tools (Axe,
shovel)
First Aid Equipment
Full Body Harness
Mega Phone
Manual siren Ring buoys
Explosimeter
Oxygen indicator
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
27/32
Emergency Handling Strategies for
different Scenarios
Typical Emergency situations
Occupational Injury & Illness Fire & Explosion
Release of toxic gas
Security breaches Civil Disturbances / Political Emergency Evacuation
Earthquake
Flood
Storm/Cyclone
Other situations specific to the site to be included
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
28/32
Training
Training for emergency response shall address,
Function and elements of emergency action plan Types of potential emergencies
Notification, warning, and communicationsprocedures
Emergency response procedures
Evacuation, shelter, and accountability procedures
Location and use of common emergency equipment
Any other special hazards onsite such as flammable materials,
toxic chemicals,
radioactive sources.
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
29/32
Mock drills
Shall be carried out at regular intervals Objective
to ensure continued familiarity of the
personnel to check if the hardware infrastructure is in
good condition.
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
30/32
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
31/32
Head count being taken
Head count being taken
HSE Engineer explains the need of mock drill
Mock drill conducted at site
-
8/12/2019 Emergency Response Plan [Compatibility Mode]
32/32