Emerging Technologies Working Group Update to WMS August 06, 2014 1 Contents I.Update on NPRR 615 II.Update on PVGR Forecasting RFP III.Next ETWG Meeting

Upload: kineta

Post on 08-Jan-2016

38 views

Category:

Documents


3 download

DESCRIPTION

Emerging Technologies Working Group Update to WMS. Contents Update on NPRR 615 Update on PVGR Forecasting RFP Next ETWG Meeting. August 06, 2014. I. Update on NPRR 615. July 31 st TAC Meeting Agenda: http :// www.ercot.com/calendar/2014/07/20140731-TAC - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Emerging Technologies Working Group Update to WMS

Emerging Technologies Working GroupUpdate to WMS

August 06, 2014

1

Contents

I.Update on NPRR 615II.Update on PVGR Forecasting RFPIII.Next ETWG Meeting

Page 2: Emerging Technologies Working Group Update to WMS

I. Update on NPRR 615

• July 31st TAC Meeting• Agenda: – http://www.ercot.com/calendar/2014/07/20140731-TAC

• On 7/31/14, TAC voted to recommend approval of NPRR 615

as recommended by PRS in the 7/17/14 PRS Report

• Will likely be on next week’s BoD Agenda (12AUG)

2

Page 3: Emerging Technologies Working Group Update to WMS

II. Update on PVGR Forecasting RFP

SEE PVGR RFP DOCUMENT•RFP Released on July 16th

– http://www.ercot.com/about/procurement/rfp/index

•9 – 10 Vendors submitted Notice of Intent to Propose•Proposals are due by August 18th •Anticipated Contract Award by December 1st •“The objective of this RFP is to allow ERCOT to produce accurate and reliable forecasts of PVGRs to be used as an input into the Day-Ahead Reliability Unit Commitment (DRUC) and Hour-Ahead Reliability Unit Commitment (HRUC) and to provide ERCOT a look-ahead capability to maintain a satisfactory level of reliability.”

3

Page 4: Emerging Technologies Working Group Update to WMS

II. Update on PVGR Forecasting RFP

From the RFP: Figure 1 – Data Flow and Dependencies of Renewable Production (PVGR) Potential Forecast

4

Page 5: Emerging Technologies Working Group Update to WMS

II. Next ETWG Meeting August 27th

• Updates on responses received for PVGR RFP• Other items, TBD

5

Page 6: Emerging Technologies Working Group Update to WMS

APPENDICES

6

Page 7: Emerging Technologies Working Group Update to WMS

Requested WMS Motion