  • 7/31/2019 End User Presentation 1

    1/21

    03/06/2012

    WELCOMETO

    UNIQUE

  • 7/31/2019 End User Presentation 1

    2/21

    03/06/2012

    ENVIRONMENT OF USAP IN BREL

    PS (Project

    System)

    MM (Material

    Management)

    FICO (Finance &

    Controlling)

    SD (Sales &Distribution)

    REFX (Flexible

    Real Estate)

    Project Planning Project CostPlanning Resource Planning Expenditure

    Budget Planning Date Planning Progress Analysis Smart Execution Monitoring &Controlling

    RFQProcessing

    TenderProcessing SmartProcurement Project StoreManagement StockInventory

    Process

    InvoiceVerifications Auditing AccountsPayable Accounts

    Receivable. AssetAccounting

    ProductSalesManagement

    SmartCustomerManagement RecoveryManagement

    StandardPortfolioManagement Asset BusinessManagement.

  • 7/31/2019 End User Presentation 1

    3/21

    SAP ERP

  • 7/31/2019 End User Presentation 1

    4/21

    03/06/2012

    PURCHASEREQUISITION

    BIDINVITATION

    VENDORSELECTION

    RFQPROCESSING

    POPROCESSING

    GOOD RECEIPT /SERVICE

    RECEIPT/ GOODSISSUE ANDINVENTORY

    PROJECTPLANNING

    INVOICEVERIFICATION/AUDITAND FINAL PAYMENT SA

    P

  • 7/31/2019 End User Presentation 1

    5/21

    03/06/2012

    ProjectInitiation &

    ConstructionPlanning

    Feasibilities Study

    Drawing DesignFinalizing

    Detail Estimating & EffectiveCost Planning

    Work Sequence

    PlanningRealistic Date

    Planning

    Construction

    Budgeting

    ConstructionOperation &

    SignificantExecutionActivitiesPlanning

    MaterialProcurementPlanning

    PurchaseRequisitionCreating

    ActivitiesStart &FinishingDateEnsuring

    QualityControl

    Monitoring,Controlling &

    Project EvaluatingPR

    Evaluating

    JobAuditing

    ExpenditureEvaluating

    WorkProgressEvaluatin

    g

    Revise

    Planning

    SmartReporting

  • 7/31/2019 End User Presentation 1

    6/21

    03/06/2012

  • 7/31/2019 End User Presentation 1

    7/21

    03/06/2012

    PLANNING OF WORKING ACTIVITIES

    CREATE WORKABLE

    SPECIFIC ACTIVITIES

    PLANNING ACCORDING

    TO THE WBS MASTER

    PLANNING.

    PROVIDE ACTIVITIES

    SCHEDULE START & END

    DATE WITHIN THE WBSMASTER SCHEDULE.

    PROVIDE INDIVIDUAL

    ACTIVITIES DETAIL

    ESTIMATE WITH

    REQUIRED MATERIALS

    BREAKDOWN.

    CREATE ACTIVITIES

    PLANNING MINIMUM ONE

    MONTH BACK OF START

    DATE.

  • 7/31/2019 End User Presentation 1

    8/21

    03/06/2012

    PROVIDE START & END DATE ON ACTIVITIES TOMAINTAIN THE WORK SCHEDULE DATE.

  • 7/31/2019 End User Presentation 1

    9/21

    03/06/2012

    PROVIDE THE RELATIONSHIP BETWEEN TWO OR MULTIACTIVITIES TO START THE WORK SMARTLY WITHIN THETIME SCHEDULE

    RELATIONSHIP SCENARIOON SAP PLANNING BOARD.

  • 7/31/2019 End User Presentation 1

    10/21

    03/06/2012

    ACTIVITIES RELATIONSHIP OVERVIEWFOR MANAGEMENT MONITORING.

  • 7/31/2019 End User Presentation 1

    11/21

    03/06/2012

    PURCHASE REQUISITION CREATE FORPLANNED ACTIVITIES ON TIME EXECUTION

    CREATE

    REQUISITION WITH

    RELEVANT FIELDS

    FOLLOWING SAP

    STANDARD.

    CREATE

    REQUISITION WITH 01

    MONTH LEAD TIME.

    MONITOR THEPURCHASE PROGRESS

    ON SPECIFIC

    REQUISITION.

  • 7/31/2019 End User Presentation 1

    12/21

    How Authority

    & Project In-

    Charge Can

    Check/Track

    The Purchase

    Progress?

  • 7/31/2019 End User Presentation 1

    13/21

    03/06/2012

    PLANNED ACTIVITIES EXECUTIONPROCESS.

  • 7/31/2019 End User Presentation 1

    14/21

    03/06/2012

    PLANNED ACTIVITIES PROCRESSOVERVIEW TO TOP MANAGEMENTSMONITORING.

  • 7/31/2019 End User Presentation 1

    15/21

    03/06/2012

  • 7/31/2019 End User Presentation 1

    16/21

    03/06/2012

    SAP Transaction Code: S_ALR_87013558

    (Budget/Actual/Commitment/Rem.Plan/Assigned/Available)

  • 7/31/2019 End User Presentation 1

    17/21

    03/06/2012

    SAP Transaction Code: CNMM (Project Oriented Procurement)

  • 7/31/2019 End User Presentation 1

    18/21

    03/06/2012

    SAP Transaction Code: CJ2C (Project Planning Board)