energy audit report-rig-e-1400 s-3 rig - oilweb · 2013-05-29 · energy audit of rig e-1400 s-3,...
TRANSCRIPT
OF
Conducted By
(EASTERN REGION)
2, Gariahat Road South, Dhakuria
Kolkata – 700 068
Ph: 033 – 2414 5092, 2414 5088, 2414 5094;
Telefax: 033 – 2414 5091
e-mail: [email protected]
Website: http://www.pcra.org
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
2 | P a g e
Petroleum Conservation Research Association – Eastern Region
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
3 | P a g e
Petroleum Conservation Research Association – Eastern Region
RELEVANT INFORMATION
1 Name and address of the Industry M/s. Oil India Ltd.
Duliajan
Dist: Dibrugarh,
Assam– 786602
2
Name & Contact no. Installation Manager Mr. Rajib Baruah, Drilling-In-charge
9435038739 (M)
3 PCRA Team Members Mr. A.K. Mallick, Jt. Dir., PCRA, ER
Mr. D. Dutta, Jt. Dir., PCRA, ER
4 Period of Audit
Dec’2012
5 Total Estimated Fuel Oil (HSD)Requirement by
DGs / year
(considering 3 nos. site operation in a year)
582 KL
7 Specific Power Consumption
65.21 Ltrs. / Hour of engine running
9 Total Estimated Fuel Oil Cost
Rs. 291 Lakhs
10 Saving potential (HSD)/ Year
50.1 KL
11 Saving potential in % of Estimated Annual Fuel
Consumption
8.6%
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
4 | P a g e
Petroleum Conservation Research Association – Eastern Region
INDEX
Sec.
No.
Title
Page
1.0 Executive Summary
5
2.0 Summary of anticipated savings and
investment 8
3.0 Introduction
9
4.0 Total connected Load
17
5.0 Study of Fuel Consumption per unit drill depth
18
6.0 Study of DG Sets
26
7.0 Illumination Study 60
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
5 | P a g e
Petroleum Conservation Research Association – Eastern Region
1.0 Executive Summary:
1.1 Connected load and captive power generation capacity
Total connected DC load for the Rig operations is 4.113 MW and that of AC load is
0.880MW. Hence, total connected electrical load is 4.99 MW.
Total captive power generation capacity by 4 nos. DGs are 3.4MW. The normal operating
load or peak operating demand load is catered by single or joint operation by three nos.
DGs.
1.2 Study of fuel consumption per hour of engine running:
After analyzing the data for the entire drilling operation, we have derived that the
Fuel (diesel) Consumption = 65.52 Ltrs. / Hour of engine running
1.3 Study of load on DGs:
A detailed study reveals that during the drilling operations, the DGs were operated at part load. The
range of this part load varies from 4% to 39% in most of the operating days. The peak loads on DGs
have never crossed 50% and observation says, load on each of the four DGs were between 40% to
50% only for 3 to 4 days of entire drilling operations.
The derived average specific fuel consumption in relation to the present operating condition is 278
gm/kWh. The reason behind this higher specific fuel consumption is part load operation of the DGs.
Study of gen-set at different % loading along with load curve (actual vis-à-vis theoretical) is
shown here.
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
6 | P a g e
Petroleum Conservation Research Association – Eastern Region
DG Loads for S-3 Rig for one complete Drilling operation from 04 / 03 /12 to 12/05/12 with
a depth of 2690 meters
Hence, we have recommended the following:
Recommendation-1: Rationalize DG operations to ensure the load on DGs above 50% with
existing on line generators.
Total savings per drilling well = 16.7KL x Rs. 50,000 /KL = Rs.8,35,000/-
Considering 3 nos. drilling wells completed by a rig in a year
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
7 | P a g e
Petroleum Conservation Research Association – Eastern Region
Annual savings = Rs.8,35,000 x 3 = Rs.25,05,000/-
Recommendation-2:
The existing D399 engines may be replaced by energy efficient engines like D-3512B.
This is likely to result in saving of Rs. 2297529/- for one drilling well of 2960Mtrs completed in 70
days.
Considering 3 nos. of wells drilled by a rig in a year, total saving envisaged is Rs. 68.93 lacs
annually.
Recommendation-3:
Install a gen-set of lower capacity (KVA as required) to cater auxiliary AC load. This will
help in reducing the running hours of bigger DG Sets on low load condition and result in
substantial savings apart from increasing the life of the rig engines.
Since, many a times, it is a usual practice to operate necessary AC connected load
during the drilling operations. It is very difficult to rationalize the load with existing
higher size (1215 KVA) DGs when the load requirement is very low. Hence, it is justified
to install a smaller size DG to cater the AC-load as and when required. It is advisable to
use the lower capacity gen-set during production testing / waiting for allied services
etc. when only auxiliary and lighting load is required. [(Note: Such practice is
prevalent at the Rig of M/s. JAY BEE Energy (P) Ltd. The model of the Rig is DZ 315/9-S
and nominal drill depth of which is 3000 – 5000M).They have installed a 400 KVA DG of
VOLVO PENTA make.]
Recommendation-4:
Study of Illumination:
The Rig unit is using 66 nos. 36/40 W Fluorescent Tube light. At present context, it is
not energy efficient and use of T-5 FTL in place of 36 W FTL will produce more
illumination with lower energy input.
Hence, we recommend to replace all the 36/40 W FTLs with energy efficient T-5 lamps
with improvement in the lux level.
The implementation of above recommendations will give a savings of Rs.62550/- per
year with an investment of Rs.29,700/- and pay back of 6 months.
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
8 | P a g e
Petroleum Conservation Research Association – Eastern Region
2.0 Summary of anticipated savings and investment
Sl No Area of Savings
Savings of
HSD / Well
(KL)
Savings of
HSD / year
(considering
3 nos of
wells / rig)
(Rs.)
Investment
(Rs.) Payback
1
Rationalize Present
DG operations to
ensure more than
50% load with
existing on line
generators
16.7 KL 25 Lakhs NIL Immediate
2
Replacing D399
engines with new
D-3512B series
engines with 50%
loading.
45.95 KL 68.93 Lakhs
200 x 2 lacs
=400 lacs
(Considering 2
nos. of DGs
for
replacement)
5 years, 10 Months
3
Replace 66 nos.
40W FTL with
energy efficient T-5
FTLs
0.417 0.62 Lakhs. 0.29 Lakhs. 6 Months
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
9 | P a g e
Petroleum Conservation Research Association – Eastern Region
3.0 Introduction:
The story of Oil India Limited (OIL) traces and symbolizes the development and growth of
the Indian petroleum industry. From the discovery of crude oil in the far east of India at
Digboi, Assam in 1889 to its present status as a fully integrated upstream petroleum
company, OIL has come far, crossing many milestones.
On February 18, 1959, Oil India Private Limited was incorporated to expand and develop the
newly discovered oil fields of Naharkatiya and Moran in the Indian North East. In 1961, it
became a joint venture company between the Indian Government and Burmah Oil
Company Limited, UK.
In 1981, OIL became a wholly-owned Government of India enterprise. Today, OIL is a
premier Indian National Oil Company engaged in the business of exploration, development
and production of crude oil and natural gas, transportation of crude oil and production of
LPG. OIL also provides various E&P related services and holds 26% equity in Numaligarh
Refinery Limited.
The Authorized share capital of the Company is Rs. 2000 Crores. The Issued, Subscribed and
Paid share capital of the company is Rs. 601.14 Crores. At present, The Government of
India, the Promoter of the Company is holding 78.43% of the total Issued & Paid-up Capital
of the Company. The balance 21.57% of the Equity capital is held by others.
OIL has over 1 lakh sq km of PEL/ML areas for its exploration and production activities; most
of it is in the Indian North East, which accounts for its entire crude oil production and
majority of gas production. Rajasthan is the other producing area of OIL, contributing 10 per
cent of its total gas production.
Additionally, OIL’s exploration activities are spread over onshore areas of KG Basin,
Mahanadi Basin, Cauvery Basin, Andaman Basin and Gujarat-Kutch Basin etc. OIL also has
participating interest in NELP exploration blocks in Mahanadi Offshore, Mumbai Deepwater,
Krishna Godavari Deepwater, etc. as well as various overseas projects in Libya, Gabon, Iran,
Yemen, Nigeria, Sudan and Venezuela.
In a recent CRISIL-India Today survey, OIL was adjudged as one of the five best major PSUs
and one of three best energy sector PSUs in the country.
Objective of Energy Audit
With the advent of energy crisis and exponential hikes in the costs of different forms of
energy, Energy Audit is manifesting its due importance in Industrial Establishments. Energy
Audit helps to understand more about the ways energy and fuels are used in any
Establishment and helps in identifying areas where waste may occur and scope for
improvement exists.
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
10 | P a g e
Petroleum Conservation Research Association – Eastern Region
Energy Audit is the key to a systematic approach for decision-making in the area of energy
management as it attempts to balance the total energy inputs with its use and serves to
identify all the energy streams in a facility/ Establishment.
It was with this objective that Petroleum Conservation Research Association (PCRA) was
entrusted by OIL, the Energy Audit of E-1400-S-3 Drilling Rig at Makum, Assam.
3.1 Well Description:
The rig was deployed at Makum area in Assam.
Location: HVB
Rig Type: Electrical (E-1400)
Well No. Makum-44
Target Depth: 2960 Meter
Type of well: Deviated
Date of Spud-in: 05.03.2012
Process flow chart for the Rig is shown in Fig. 3.1.1. Types of drilling are as follows:
� Vertical drilling
� Horizontal drilling
� Inclined drilling(deviation)
Horizontal and inclined drilling increases the perforation area. The decision whether to
drill vertical, horizontal or inclined, is dependent on the strata and oil availability.
Complete drilling program is pre–decided and it is given in GTO for the well.
3.2 Drilling Fluid (Mud):
Mud has several roles while drilling the well; these are lubricant and coolant for the drill
bit, remove rock chips & cuttings from well, to soften the rock/soil. Therefore chemical
composition and specific gravity of the mud vary according to the depth and
requirement.
Constituents of the mud include lignite, Caustic soda, caustic potash, Causticities lignite
(Generally used up to 1300 m), Chrome lignite, Resin lignite (Generally used at last
depth), Barites, Bentonite, CMC (carboxyl methyl cellulose), Drilling detergent, Linseed
oil, Spoil- ting fluid, Sulphonated asphalt etc.
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
11 | P a g e
Petroleum Conservation Research Association – Eastern Region
3.3 Important Equipments / Attachments
1. Draw Works: This system provides drilling energy to the drill bit and all mechanical energy
requirements at the rig (e.g. operations like drilling, running-in, pulling-out) except
flow of the mud, which is powered by the mud pump.
2. Compressors: Compressed air is utilized for cranking of diesel engines, various pneumatic
controls and other support applications.
3. Supercharger: Mud pump is attached to centrifugal pump, which is also called as super-
charger (2 no’s of 100 hp each).
4. Mud pump: Mud Pump is used for pumping the drilling fluid (mud) at high pressure as per
the requirement of drilling operation.
5. Agitators: Mud is prepared with the help of number of agitators. Agitators are used for
agitation and also to prevent solidification or cake formation.
3.4 About Drilling Rig: E 1400 S-3
Presently the rig is located at HVB Site.
1) Rig Capacity: 1400 hp
2) Date of commissioning: 02.08.1985
3) Last Well drilled: Hapjan-56
4) Mast Height: 142 feet
5) Derrick Floor height: 25 feet
6) Asset Manager: Mr.
7) Installation Manager: Mr. Rajib Baruah
8) Engine/ sets: 4 nos.
9) Make/ Engine Model: Caterpillar / D-399
10) Engine Output: 972 hp at 1000 rpm
11) Alternator Capacity: 1215 kVA
.
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
14 | P a g e
Petroleum Conservation Research Association – Eastern Region
Fig 3.1.1:Process Flow Chart of Drilling Rig
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
15 | P a g e
Petroleum Conservation Research Association – Eastern Region
Fig 3.1.2 : GENERAL ARRANGEMENT OF THE RIG EQUIPMENTS
Sr. Equipment / Machine Capacity
1. DG – 1 1215 KVA
2. DG – 2 1215 KVA
3. DG – 3 1215 KVA
4. DG – 4 1215 KVA
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
16 | P a g e
Petroleum Conservation Research Association – Eastern Region
Fig. 3.1.3: DRILLING RIG ASSEMBLY
4.0 Total Connected Load in the Rig:
Connected Electrical load in the Rig are described below:
Connected DC load
Sl.No. Loads HP No. KW
1 D.C.Motor 900 5 3357
2 D.C.Motor 1000 1 746
3 ECB 10.5
Total 4113.5
Connected AC Load
A.C.Load
1 Blower Motors 7.5 6 33.57
2 Water Booster 30 2 44.76
3 Mud Agitators 10 12 89.52
4 Liner Flasher 3 2 4.476
5 Caller 3 1 2.238
6 BOP 15 1 11.19
7 Degasser 3 1 2.238
8 Fuel Pump 5 2 7.46
9 Shale shaker 5 3 11.19
10 Pill Chamber 10 1 7.46
11 Water Agitators 10 4 29.84
12 After Cooler 0.29
13 Trip Tank Motor 15 1 11.19
14 Air Compressor 40 2 59.68
15 Super Charger 75 2 111.9
16 Mud Mix 100 2 149.2
17 Desander/Desilter 75 2 111.9
18 Multistage 75 2 111.9
19 DCPR A/C 20
20 ACPR A/C 20
21 Area Lighting Load 20
22 Rig Lighting Load 20
Total 880.002
Total connected load = 4113.5 KW + 880 KW = 4993.5 KW = 5.0 MW (Approx)
Total Captive Power = 1215 KVA x 0.70(P.F.) X4Nos. = 3.4 MW
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
18 | P a g e
Petroleum Conservation Research Association – Eastern Region
5.0 Study of fuel consumption per unit drill depth:
Specific fuel consumption i.e. fuel consumption per meter of drilled depth is a prime objective of
this study. Hence, the complete activity of the drilling-rig starting from spud in to production testing
has been taken into consideration at Location: HVB. The well was spudded on 04.03.2012 and
handed over to production on 12.05.2012 after attaining the target drill depth and subsequent
necessary associated activities. Date wise details of drilling activity with DG- run, fuel consumption
and draw works/mud pump operation as recorded in the log book have been incorporated below:
Date of Spud-in: 04.03.2012 , Location: HVB Date Shift Depth
of
Drill
(M)
Operations Engine Run Hours DG -
1
DG -
2
DG -
3
DG -
4
Diesel
Cons
(Ltrs.)
DW
A
DW
B
MP
1
MP
2
E1 E2 E3 E4
04.03.2012 M 9 Spud- In 8 600 0 0 0 1385 3 3 1 1
05.03.2012 M 150 Circulation 21 3 500 0 300 0 2000 0 0 8 8
E 0 1650 0 0 8 0 7 0
N 0 1400 0 0 8 8
06.03.2012 M 150 BOP Planning 24 3 0 1130 0 450 2055 4 0 4 3
E 150 0 500 0 0 0 0 0 0
N 150 0 400 0 0
07.03.2012 M 150 BOP Planning 24 0 640 0 0 3260 0 0 0 0
E 150 0 640 0 0 0 0 0 0
N 150 0 690 0 0 4 0 0 0
08.03.2012 M 307 Drilling 20 21 0 1300 2210 3 3 3 0
E 0 1000 1200 300 8 7 8 0
N 0 0 0 1100 2 0 0 0
09.03.2012 M 307 Drilling 20 21 0 0 500 550 0 3 0 0
E 1030 650 1 2 3 2
N 1475 1475 0 7 7 0
10.03.2012 M 532 Drilling 15 20 9 1150 1330 5080 0 8 1 0
E NA
N 685 460 0 1 7 0 0
11.03.2012 M 532 Pull Out 24 18 1440 450 0 5 0 2 0
E 1695 1580 8 8 8 0
N 1020 1020 6 6 0 2
12.03.2012 M 712 Drilling/Pull
Out
20 21 3 1280 1280 360 3210 8 6 0 3
E 2950 2890 8 8 0 7
N 1460 1460 6 6 0 2
13.03.2012 M 783 Pullout/Drilling 19 17 5 1050 1050 835 2254 7 3 3 0
E 2700 3030 8 7 0 7
N 2000 1750 6 6 0 0
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
19 | P a g e
Petroleum Conservation Research Association – Eastern Region
Date of Spud-in: 04.03.2012 , Location: HVB Date Shift Depth
of
Drill
(M)
Operations Engine Run Hours DG -
1
DG -
2
DG -
3
DG -
4
Diesel
Cons
(Ltrs.)
DW
A
DW
B
MP
1
MP
2
E1 E2 E3 E4
14.03.2012 M 829 Drilling/Pull
Out/Recirculation
24 17 3 1560 1500 3176 6 0 2 3
E 1680 1420 580 8 1 6 0
N 1475 1250 5 5 0 0
15.03.2012 M Drilling 3 20 20 17 0 0 0 0 4370 0 0 0 0
E 1028 2800 2800 2800 8 8 8 0
N 1178 2250 2250 2250 8 8 8 0
16.03.2012 M 1281 Drilling/Pull
Out/Recirculation
10 24 23 3 850 1720 1720 870 3370 6 6 4 2
E 1960 2210 2210 8 8 5.5 0
N 1640 1560 6 6 0 0
17.03.2012 M 1452 Drilling 16 24 17 2 520 1960 500 900 8730 6 6 0 4
E 1960 1960 1960 8 8 0 6
N 2000 2080 2000 8 8 0 5
18.03.2012 M 1452 Drilling 8 16 11 17 1200 150 5 0 0 0
E 1513 1825 900 1825 7 4 0 4
N 1624 2400 2400 2400 8 8 0 8
19.03.2012 M 1652 Recirculation 9 15 24 12 2200 2200 2200 3545 8 8 0 8
E 1000 1000 1000 7 7 0 1
N 820 820 4 4 0 0
20.03.2012 M Pull out 16 8 24 21 1950 2250 1850 5179 8 8 6 0
E 3200 3200 3200 8 8 8 0
N 1800 1800 1800 8 8 4 0
21.03.2012 M 1753 Pull out(Logging) 6 8 7 24 600 1100 1300 2952 6 7 1 0
E 0 700 2 0 0 0
N 0 2300 1200 8 8 2 0
22.03.2012 M Casing/Recirculation 5 24 12 3 1250 1590 750 231`4 5 5 2 0
E 0 640 240 0 8 0 0 0
N 0 560 560 0 8 8 0 0
23.03.2012 M Casing 16 8 3 17 0 780 750 680 1760 7 7 0 0
E 900 200 0 1100 7 7 1 0
N 850 0 0 0 3 0 0 0
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
20 | P a g e
Petroleum Conservation Research Association – Eastern Region
Date of Spud-in: 04.03.2012 , Location: HVB Date Shift Depth
of
Drill
(M)
Operations Engine Run Hours DG -
1
DG -
2
DG -
3
DG -
4
Diesel
Cons
(Ltrs.)
DW
A
DW
B
MP
1
MP
2
E1 E2 E3 E4
24.03.2012 M Cementing 3 0 7 21 225 0 450 525 1540 3 3 0 0
E 0 175 625 0 0 0 2
N 0 480 0 0 0 0
25.03.2012 M Wetting cement 0 0 0 24 0 440 4 4 0 0
E 0 640 0 0 0 0
N 0 600 0 0 0 0
26.03.2012 M BOP Planning 0 15 3 6 0 100 310 2310 1 0 0 0
E 560 0 0 0 0
N 375 0 0 0 0 0 0
27.03.2012 M Riger Planning 0 8 16 0 600 1510 2 0 0 0
E 0 0 400 0 0 0 0 0
N 0 0 560 0 0 0 0 0
28.03.2012 M Recirculation/Drilling 0 15 19 0 0 0 560 0 2630 0 0 0 0
E 0 700 250 0 1 3 0 0
N 0 1850 1850 0 8 8 8 0
29.03.2012 M Cement/Cutting 20 24 4 0 850 1500 650 3530 8 8 8 0
E 2320 2320 8 8 3 2
N 2400 2400 8 8 8 0
30.03.2012 M 1812 Drilling 12 6 16 18 1988 1440 620 3910 7 7 3 1
E 350 1760 1390 7 7 0 1
N 750 1500 1500 8 8 0 2
31.03.2012 M 2271 Drilling 24 0 24 24 2030 2400 2400 14220 8 8 1 7
E 2000 2000 2000 8 8 8 0
N 2080 2080 2080 8 8 8 0
01.04.2012 M 2271 Pull out 6 18 24 24 1560 700 2640 2640 8 8 8 0
E 2000 2000 2000 8 8 8 0
N 2400 2400 2400 8 8 5 3
02.04.2012 M 2271 Recirculation 0 14 12 14 1180 1380 1260 6 6 0 4
E 0 0 240 0 0 0 0 0
N
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
21 | P a g e
Petroleum Conservation Research Association – Eastern Region
Date of Spud-in: 04.03.2012 , Location: HVB Date Shift Depth
of
Drill
(M)
Operations Engine Run Hours DG -
1
DG -
2
DG -
3
DG -
4
Diesel
Cons
(Ltrs.)
DW
A
DW
B
MP
1
MP
2
E1 E2 E3 E4
03.04.2012 M 2411 Circulation 1 24 17 23 0 1350 1140 1490 5160 7 7 5 1
E 0 2060 1200 1900 8 8 8 0
N 2400 3120 2400 8 8 8 0
04.04.2012 M 2411 Circulation 10 17 24 8 300 1420 1600 1200 5204 8 8 6 0
E 1600 1800 1800 8 8 4 0
N 720 4 4 0 0
05.04.2012 M 2411 Circulation 0 0 11 0 0 0 0 0 0 0 0 0
E 0 0 0 0 0 0 0 0
N 0 0 0 0 0 0 0 0
06.04.2012 M 2411 Running in/
Reaming
3 14 0 12 0 0 640 0 0 0 0 0
E 300 1050 0 750 5 5 0 0
N 1300 1300 6 6 4 0
07.04.2012 M Drilling 19 24 0 24 890 2350 2350 16266 8 8 1 5
E 2477 2540 2750 2750 8 8 0 8
N 2551 2750 2750 2750 8 8 0 8
08.04.2012 M 2686 Drilling/Pull out 18 14 16 24 2560 2800 2800 8 8 0 8
E 1050 2100 2450 2750 8 8 0 8
N 2560 2880 2880 8 8 0 8
09.04.2012 M 2690 Reaming/Drilling 13 14 24 10 1540 1600 1600 4086 8 6 4 0
E 1730 1940 1200 5 5 0 0
N 1240 2350 2360 0 8 8 4 0
10.04.2012 M 2716 Drilling 23 21 5 24 2350 2730 1330 1750 6727 8 8 8 0
E 2795 2800 3040 0 3200 8 8 8 0
N 2832 2400 2400 2400 8 8 8 0
11.04.2012 M 2888 Drilling/Pullout 23 21 7 17 2740 2820 0 2860 5986 8 8 8 0
E 2954 2800 3200 0 3200 8 8 8 0
DRILLING COMPLETED
N 1880 1960 1600 8 8 3 0
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
22 | P a g e
Petroleum Conservation Research Association – Eastern Region
Date of Spud-in: 04.03.2012 , Location: HVB Date Shift Depth
of
Drill
(M)
Operations Engine Run Hours DG -
1
DG -
2
DG -
3
DG -
4
Diesel
Cons
(Ltrs.)
DW
A
DW
B
MP
1
MP
2
E1 E2 E3 E4
12.04.2012 M Circulation 3 17 20 2 0 450 550 14087 1 1 0 0
E 250 400 150 1 1 0 0
N 80 1640 1600 600 7 7 0 2
13.04.2012 M Circulation 0 17 24 10 2000 2080 2200 8 8 0 6
E 1795 1795 600 8 8 0 0
N 600 0 0 0 0
14.04.2012 M Run in 0 11 24 0 600 0 0 0 0
E 180 490 2 2 0 0
N 900 900 2 2 0 0
15.04.2012 M Circulation 10 24 4 16 800 1800 1000 800 8 8 0 8
E 1550 1960 1960 7 7 2 1
N 1300 1050 3 3 0 0
16.04.2012 M Logging/Run
in /Pull out
17 24 13 0 525 825 5 3 0 0
E 1200 1200 750 8 8 5 0
N 1300 1400 1520 6 6 2 0
17.04.2012 M Casing Run
In
0 23 24 0 1000 1050 2184 5 5 0 0
E 1060 1060 6 6 0 0
N 2250 2250 8 8 0 0
18.04.2012 M Casing JOS 0 24 24 0 2400 2400 2101 8 8 0 0
E 1660 1660 8 0 7 0
N 1300 1300 8 8 0 0
19.04.2012 M Casing JOS 15 24 19 6 1500 350 1250 5705 6 6 4 0
E 2080 2480 2380 7 7 5 5
N 3200 3200 3200 8 8 8 8
20.04.2012 M Casing JOS 24 10 24 15 2000 2000 2080 3834 0 0 8 8
E 800 250 800 550 5 3 2 1
N 900 900 700 8 8 0 2
21.04.2012 M Casing
Pullout
3 0 24 21 900 2180 1280 4096 8 8 0 0
E 2400 2400 8 8 0 0
N 1140 1140 5 5 0 0
22.04.2012 M Casing
Pullout
0 7,5 24 1 1480 1480 8 8 0 0
E 1950 6 6 0 0
N 1300 1300 5 5 0 3
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
23 | P a g e
Petroleum Conservation Research Association – Eastern Region
Date of Spud-in: 04.03.2012 , Location: HVB Date Shift Depth
of
Drill
(M)
Operations Engine Run Hours DG -
1
DG -
2
DG -
3
DG -
4
Diesel
Cons
(Ltrs.)
DW
A
DW
B
MP
1
MP
2
E1 E2 E3 E4
23.04.2012 M Pull out 0 24 24 13 975 1095 520 4420 7 7 2 2
E 2150 2150 2150 8 8 4 4
N 1500 1500 5 5 0 0
24.04.2012 M Pull out/Run
In/Circulation/Pull
out
6 24 1 15 620 75 3325 0 4 0 0
E 2160 2160 6 6 0 0
N 1600 2100 2100 8 8 2 2
25.04.2012 M Pull out 9 24 0 19 1250 1490 1250 3745 6 5 0 0
E 400 1840 1300 8 8 2 0
N 2400 2400 2400 8 8 1 0
26.04.2012 M Casing 8 8 10 24 1660 1810 2155 8 8 0 0
E 900 4 4 0 0
N 1200 1200 8 8 0 0
27.04.2012 M Waiting for
Cementing
0 3 18 24 1200 1200 2605 8 8 0 0
E 1280 1280 4 4 0 3
N 200 200 680 0 0 2 0
28.04.2012 M BOP Dismantling 8 15 0 9 400 2890 0 0 0 0
E 400 850 5 5 0 0
N 380 700 0 0 0 0
29.04.2012 M Pipe breaking 0 24 13 0 680 0 2 0 0
E 655 500 6 4 0 0
N 630 550 0 4 0 4
30.04.2012 M Pipe breaking 0 17 20 0 865 530 4115 6 3 0 0
E 650 830 4 0 0 0
N 325 650 3 3 0 0
01.05.2012 M Production Tube
Joining
0 0 24 0 600 0 0 0 0
E 760 2 0 0 0
N 600 0 0 0 0
02.05.2012 M Tubing Run In 0 0 24 0 600 0 0 0 0
E 600 0 0 0 0
N 600 0 0 0 0
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
24 | P a g e
Petroleum Conservation Research Association – Eastern Region
Date of Spud-in: 04.03.2012 , Location: HVB Date Shift Depth
of
Drill
(M)
Operations Engine Run Hours DG - 1 DG - 2 DG - 3 DG - 4 Diesel
Cons
(Ltrs.)
DW
A
DW
B
MP
1
MP
2
E1 E2 E3 E4
03.05.2012 M Tubing Run
In
0 17 12 12 400 230 1835 4 4 0 0
E 1460 1460 6 6 0 0
N 950 950 5 0 1 0
04.05.2012 M Pull
out/Tubing
1 8 6 20 100 900 1030 1890 6 6 0 0
E 75 1155 4 3 2 0
N 720 400 5 5 0 0
05.05.2012 M Pull
out/Tubing
0 20 5 0 900 2410 2 0 0 0
E 1080 2 2 0 0
N 620 540 2 2 0 0
06.05.2012 M Run In 0 12 20 0 400 0 0 0 0
E 800 1200 4 4 0 0
N 755 435 3 3 0 0
07.05.2012 M Waiting for
Logging
0 21 0 8 540 620 1330 2 2 0 0
E 240 240 0 0 0 0
N 400 0 0 0 0
08.05.2012 M Logging 0 12 12 0 640 1105 0 0 0 0
E 320 0 0 0 0
N 525 0 0 0 0
09.05.2012 M Logging 0 0 8 5 150 150 250 875 0 0 0 0
E 200 0 0 0 0
N
10.05.2012 M Nitrogen
pumping
0 6 0 0 100 450 0 0 0 0
E
N
11.05.2012 M Nitrogen
pumping
0 0 5 0 200 456 0 0 0 0
E
N
12.05.2012 M Pipe Br. 0 2 8 0 1500 310 2 0 0 0
E 150 0 0 0 0
N
Total 2954 431 932 918 687 108713 182890 156960 143225 193538
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
25 | P a g e
Petroleum Conservation Research Association – Eastern Region
From the above study, it is found that starting from spud in to attain the target drill depth and
handing over to production the diesel consumption by Diesel Generators are 193538 Ltrs. = 193.548
KL.
Total running Hours = 431+932+918+687 =2968 Hrs.
Fuel Consumption per hour of Engine running = 193538/2968 = 65.21 L/Hr.
Total kWh generated by the DGs =591788 kWh
Total depth of drill hole = 2954 M
Fuel consumption per meter drill = 193538/2954 =65.52 Ltrs./Mtr.
Power generating cost: 9676900/ 591788 = Rs. 16.35/ kWh
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
26 | P a g e
Petroleum Conservation Research Association – Eastern Region
6.0 Study of DG Sets:
6.1 Details of DGs:
The rig is having four nos. identical DGs. The capacity of each DG is 1215 KVA and each connected to
a common bus to cater both AC and DC load. The DG operations are increased or decreased as per
the required demand. The details of each DG have been given below:
DG#1
Alternator Details
Make KATO Engg.
Sr. No. 17190-1
Yr. of Mfg. 2004
KVA 1215
Rated Voltage 600
Full load current 1169
P.F. 0.7
Engine Details
Make Caterpillar
Model 3512
Power 830 KW at 1000 RPM
Engine Type 4 Stroke, Turbocharged, V12 water cooled
No. of Cylinders 12
Sump Cap 318 L
Rated Speed 900-1800 RPM
Bore 6.7", Stroke 7.5"
DG#2
Alternator Details
Make BHEL
Sr. No. 4600126
Yr. of Mfg. 2004
KVA 1215
Rated Voltage 600
Full load current 1170
P.F. 0.7
Engine Details
Make Caterpillar
Model D399
Power 972 H.P.
Engine Type 4 Stroke, Turbocharged, V16 water cooled
No. of Cylinders 16
Rated Speed 1000 RPM
Bore 6.25", Stroke 8"
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
27 | P a g e
Petroleum Conservation Research Association – Eastern Region
DG#3
Alternator Details
Make KATO Engg.
Sr. No. 90169-8
Yr. of Mfg. 1984
KVA 1215
Rated Voltage 600
Full load current 1169
P.F. 0.7
Engine Details
Make Caterpillar
Model D399
Power 972 H.P.
Engine Type 4 Stroke, Turbocharged, V16 water cooled
No. of Cylinders 16
Rated Speed 1000 RPM
Bore 6.25", Stroke 8"
DG#4
Alternator Details
Make KATO Engg.
Sr. No. 90169-4
Yr. of Mfg. 1984
KVA 1215
Rated Voltage 600
Full load current 1169
P.F. 0.7
Engine Details
Make Caterpillar
Model D399
Power 972 H.P.
Engine Type 4 Stroke, Turbocharged, V16 water cooled
No. of Cylinders 16
Rated Speed 1000 RPM
Bore 6.25", Stroke 8"
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
28 | P a g e
Petroleum Conservation Research Association – Eastern Region
6.2 Single line diagram for electricity distribution:
6.3 Load on DGs:
The load on DGs have been calculated during the drilling operations. DG wise load have been sorted
from lowest to highest. The observations have been given as under:
DG#1:
Sl.No.
DG-1
Date Shift Depth of
Drill (M) Operations
Av.Load on
DG-1
Av.%Load
on DG-1 1 0 0 05.03.2012 E
2 0 0 05.03.2012 N
3 0 0 06.03.2012 M 150 BOP Planning
4 0 0 06.03.2012 E 150
5 0 0 06.03.2012 N 150
6 0 0 07.03.2012 M 150 BOP Planning
7 0 0 07.03.2012 E 150
8 0 0 07.03.2012 N 150
9 0 0 08.03.2012 M 307 Drilling
10 0 0 08.03.2012 E
11 0 0 08.03.2012 N
12 0 0 09.03.2012 M 307 Drilling
13 0 0 09.03.2012 E
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
29 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-1
Date Shift Depth of
Drill (M) Operations
Av.Load on
DG-1
Av.%Load
on DG-1 14 0 0 09.03.2012 N
15 0 0 10.03.2012 M 532 Drilling
16 0 0 10.03.2012 E
17 0 0 10.03.2012 N
18 0 0 11.03.2012 M 532 Pull Out
19 0 0 11.03.2012 E
20 0 0 11.03.2012 N
21 0 0 15.03.2012 M Drilling
22 0 0 15.03.2012 E 1028
23 0 0 15.03.2012 N 1178
24 0 0 16.03.2012 N
25 0 0 18.03.2012 M 1452 Drilling
26 0 0 18.03.2012 E 1513
27 0 0 19.03.2012 E
28 0 0 19.03.2012 N
29 0 0 20.03.2012 M Pull out
30 0 0 21.03.2012 E
31 0 0 21.03.2012 N
32 0 0 22.03.2012 E
33 0 0 22.03.2012 N
34 0 0 23.03.2012 M Casing
35 0 0 24.03.2012 E
36 0 0 24.03.2012 N
37 0 0 25.03.2012 M Wetting cement
38 0 0 25.03.2012 E
39 0 0 25.03.2012 N
40 0 0 26.03.2012 M BOP Planning
41 0 0 26.03.2012 E
42 0 0 26.03.2012 N
43 0 0 27.03.2012 M Riger Planning
44 0 0 27.03.2012 E
45 0 0 27.03.2012 N
46 0 0 28.03.2012 M Recirculation/Drilling
47 0 0 28.03.2012 E
48 0 0 28.03.2012 N
49 0 0 01.04.2012 E
50 0 0 01.04.2012 N
51 0 0 02.04.2012 M 2271 Recirculation
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
30 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-1
Date Shift Depth of
Drill (M) Operations
Av.Load on
DG-1
Av.%Load
on DG-1 52 0 0 02.04.2012 E
53 0 0 02.04.2012 N
54 0 0 03.04.2012 M 2411 Circulation
55 0 0 03.04.2012 E
56 0 0 03.04.2012 N
57 0 0 04.04.2012 N
58 0 0 05.04.2012 M 2411 Circulation
59 0 0 05.04.2012 E
60 0 0 05.04.2012 N
61 0 0 06.04.2012 M 2411 Running in/ Reaming
62 0 0 06.04.2012 N
63 0 0 09.04.2012 E
64 0 0 12.04.2013 M Circulation
65 0 0 13.04.2013 M Circulation
66 0 0 13.04.2013 E
67 0 0 13.04.2013 N
68 0 0 14.04.2013 M Run in
69 0 0 14.04.2013 E
70 0 0 14.04.2013 N
71 0 0 15.04.2013 N
72 0 0 17.04.2013 M Casing Run In
73 0 0 17.04.2013 E
74 0 0 17.04.2013 N
75 0 0 18.04.2013 M Casing JOS
76 0 0 18.04.2013 E
77 0 0 18.04.2013 N
78 0 0 19.04.2013 M Casing JOS
79 0 0 21.04.2013 E
80 0 0 21.04.2013 N
81 0 0 22.04.2013 M Casing Pullout
82 0 0 22.04.2013 E
83 0 0 22.04.2013 N
84 0 0 23.04.2013 M Pull out
85 0 0 23.04.2013 E
86 0 0 23.04.2013 N
87 0 0 24.04.2013 M Pull out/Run
In/Circulation/Pull out
88 0 0 24.04.2013 E
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
31 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-1
Date Shift Depth of
Drill (M) Operations
Av.Load on
DG-1
Av.%Load
on DG-1 89 0 0 26.04.2013 M Casing
90 0 0 26.04.2013 E
91 0 0 26.04.2013 N
92 0 0 27.04.2013 M Waiting for Cement
93 0 0 27.04.2013 E
94 0 0 27.04.2013 N
95 0 0 28.04.2013 M BOP Dismantling
96 0 0 29.04.2013 M Pipe pro
97 0 0 29.04.2013 E
98 0 0 29.04.2013 N
99 0 0 30.04.2013 M Pipe pro
100 0 0 30.04.2013 E
101 0 0 30.04.2013 N
102 0 0 01.05.2013 M Production Tube Joining
103 0 0 01.05.2013 E
104 0 0 01.05.2013 N
105 0 0 02.05.2013 M Tubing Run In
106 0 0 02.05.2013 E
107 0 0 02.05.2013 N
108 0 0 03.05.2013 M Tubing Run In
109 0 0 03.05.2013 E
110 0 0 03.05.2013 N
111 0 0 04.05.2013 E
112 0 0 04.05.2013 N
113 0 0 05.05.2013 M Pull out/Tubing
114 0 0 05.05.2013 E
115 0 0 05.05.2013 N
116 0 0 06.05.2013 M Run In
117 0 0 06.05.2013 E
118 0 0 06.05.2013 N
119 0 0 07.05.2013 M Waiting for pumpout
120 0 0 07.05.2013 E
121 0 0 07.05.2013 N
122 0 0 08.05.2013 M Logging
123 0 0 08.05.2013 E
124 0 0 08.05.2013 N
125 0 0 09.05.2013 M Logging
126 0 0 09.05.2013 E
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
32 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-1
Date Shift Depth of
Drill (M) Operations
Av.Load on
DG-1
Av.%Load
on DG-1 127 0 0 09.05.2013 N
128 0 0 10.05.2013 M Nitrogen
129 0 0 10.05.2013 E
130 0 0 10.05.2013 N
131 0 0 11.05.2013 M Nitrogen
132 0 0 11.05.2013 E
133 0 0 11.05.2013 N
134 0 0 12.05.2014 M Pipe Br.
135 0 0 12.05.2014 E
136 0 0 12.05.2014 N
137 50 6 04.05.2013 M Pull out/Tubing
138 75 9 04.03.2012 M 9 Spud-in
139 75 9 24.03.2012 M Cementing
140 80 9 12.04.2013 N
141 80 9 28.04.2013 E
142 95 11 28.04.2013 N
143 100 12 05.03.2012 M 150 Circulation
144 100 12 20.04.2013 E
145 106 12 23.03.2012 N
146 113 13 20.04.2013 N
147 120 14 04.04.2012 M 2411 Circulation
148 129 15 23.03.2012 E
149 131 15 16.04.2013 M Logging/Run in /Pull out
150 133 16 25.04.2013 E
151 150 18 06.04.2012 E
152 150 18 16.04.2013 E
153 167 20 12.04.2013 E
154 170 20 29.03.2012 M Cement/Cutting
155 183 21 12.03.2012 N
156 184 22 14.03.2012 N
157 193 23 09.04.2012 M 2690 Reaming/Drilling
158 195 23 14.03.2012 M 829 Drilling/Pull
Out/Recirculation
159 200 24 21.03.2012 M 1753 Pull out(Logging)
160 200 24 04.04.2012 E
161 200 24 15.04.2013 M Circulation
162 208 24 25.04.2013 M Pull out
163 210 25 14.03.2012 E
164 217 25 16.04.2013 N
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
33 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-1
Date Shift Depth of
Drill (M) Operations
Av.Load on
DG-1
Av.%Load
on DG-1 165 225 26 20.03.2012 N
166 232 27 12.03.2012 M 712 Drilling/Pull Out
167 238 28 15.04.2013 E
168 245 29 17.03.2012 E
169 248 29 09.04.2012 N
170 249 29 30.03.2012 M 1812 Drilling
171 250 29 13.03.2012 N
172 250 29 22.03.2012 M Casing/Recirculation
173 250 29 30.03.2012 N
174 250 29 31.03.2012 E
175 250 29 20.04.2013 M Casing JOS
176 254 30 31.03.2012 M 2271 Drilling
177 260 31 17.03.2012 M 1452 Drilling
178 260 31 31.03.2012 N
179 260 31 01.04.2012 M 2271 Pull out
180 267 31 24.04.2013 N
181 269 32 11.04.2012 N
182 275 32 19.03.2012 M 1652 Recirculation
183 283 33 16.03.2012 M 1281 Drilling/Pull
Out/Recirculation
184 286 34 17.03.2012 N
185 290 34 29.03.2012 E
186 297 35 07.04.2012 M Drilling
187 297 35 19.04.2013 E
188 300 35 18.03.2012 N 1624
189 300 35 29.03.2012 N
190 300 35 10.04.2012 N 2832
191 300 35 21.04.2013 M Casing Pullout
192 310 36 25.04.2013 N
193 318 37 07.04.2012 E 2477
194 320 38 08.04.2012 M 2686 Drilling/Pull out
195 320 38 08.04.2012 N
196 336 39 10.04.2012 M 2716 Drilling
197 338 40 13.03.2012 E
198 343 40 11.04.2012 M 2888 Drilling/Pullout
199 344 40 07.04.2012 N 2551
200 350 41 13.03.2012 M 783 Pullout/Drilling
201 350 41 30.03.2012 E
202 350 41 08.04.2012 E
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
34 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-1
Date Shift Depth of
Drill (M) Operations
Av.Load on
DG-1
Av.%Load
on DG-1 203 350 41 10.04.2012 E 2795
204 350 41 11.04.2012 E 2954
205 356 42 16.03.2012 E
206 368 43 12.03.2012 E
207 400 47 20.03.2012 E
208 400 47 19.04.2013 N
209 DRILLING
COMPLETED
11.04.2012
Observation: From the above exercise it is observed that the load on DG has varied from 6% to 47%
during its 72 shifts(24days) operations. Hence, the entire DG operations has been carried out at part
load, which is energy wasting. Normally, load about 75% on DG is considered optimised and rational.
However in case of drilling rig, where the operators have to often play a safe side, let us consider
that load between 40% to 60% is realistic.
In the above study, it is clear that the DG was operated above 40% only for 12 shifts i.e. for 4 days.
For the remaining 20 days, load on DG was below 40% and many a days at part load condition.
DG#2:
Sl. No.
DG-2
Date Shift Depth of
Drill (M) Operations Av. Load
on DG-2
Av. Load
on DG-2 1 0 0 04.03.2012 M 9 spud in
2 0 0 05.03.2012 M 150 Circulation
3 0 0 08.03.2012 N
4 0 0 09.03.2012 M 307 Drilling
5 0 0 09.03.2012 E
6 0 0 09.03.2012 N
7 0 0 10.03.2012 M 532 Drilling
8 0 0 10.03.2012 E
9 0 0 12.03.2012 M 712 Drilling/Pull Out
10 0 0 12.03.2012 E
11 0 0 12.03.2012 N
12 0 0 14.03.2012 M 829 Drilling/Pull
Out/Recirculation
13 0 0 14.03.2012 E
14 0 0 14.03.2012 N
15 0 0 15.03.2012 M Drilling
16 0 0 18.03.2012 N 1624
17 0 0 19.03.2012 M 1652 Recirculation
18 0 0 20.03.2012 E
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
35 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl. No.
DG-2
Date Shift Depth of
Drill (M) Operations Av. Load
on DG-2
Av. Load
on DG-2 19 0 0 20.03.2012 N
20 0 0 21.03.2012 M 1753 Pull out(Logging)
21 0 0 21.03.2012 E
22 0 0 23.03.2012 N
23 0 0 24.03.2012 M Cementing
24 0 0 24.03.2012 E
25 0 0 24.03.2012 N
26 0 0 25.03.2012 M Wetting cement
27 0 0 25.03.2012 E
28 0 0 25.03.2012 N
29 0 0 26.03.2012 M BOP Planning
30 0 0 27.03.2012 E
31 0 0 27.03.2012 N
32 0 0 28.03.2012 M Recirculation/Drilling
33 0 0 30.03.2012 E
34 0 0 30.03.2012 N
35 0 0 31.03.2012 M 2271 Drilling
36 0 0 31.03.2012 E
37 0 0 31.03.2012 N
38 0 0 02.04.2012 E
39 0 0 02.04.2012 N
40 0 0 04.04.2012 N
41 0 0 05.04.2012 M 2411 Circulation
42 0 0 05.04.2012 E
43 0 0 05.04.2012 N
44 0 0 06.04.2012 M 2411 Running in/ Reaming
45 0 0 08.04.2012 N
46 0 0 09.04.2012 M 2690 Reaming/Drilling
47 0 0 13.04.2013 N
48 0 0 14.04.2013 M Run in
49 0 0 20.04.2013 N
50 0 0 21.04.2013 M Casing Pullout
51 0 0 21.04.2013 E
52 0 0 21.04.2013 N
53 0 0 22.04.2013 M Casing Pullout
54 0 0 22.04.2013 E
55 0 0 26.04.2013 E
56 0 0 26.04.2013 N
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
36 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl. No.
DG-2
Date Shift Depth of
Drill (M) Operations Av. Load
on DG-2
Av. Load
on DG-2 57 0 0 27.04.2013 M Waiting for Cement
58 0 0 27.04.2013 E
59 0 0 28.04.2013 M BOP Dismantling
60 0 0 01.05.2013 M Production Tube Joining
61 0 0 01.05.2013 E
62 0 0 01.05.2013 N
63 0 0 02.05.2013 M Tubing Run In
64 0 0 02.05.2013 E
65 0 0 02.05.2013 N
66 0 0 04.05.2013 M Pull out/Tubing
67 0 0 04.05.2013 E
68 0 0 06.05.2013 M Run In
69 0 0 09.05.2013 N
70 0 0 10.05.2013 E
71 0 0 10.05.2013 N
72 0 0 11.05.2013 M Nitrogen
73 0 0 11.05.2013 E
74 0 0 11.05.2013 N
75 0 0 12.05.2014 E
76 0 0 12.05.2014 N
77 50 6 06.03.2012 N 150
78 50 6 07.05.2013 N
79 50 6 09.05.2013 M Logging
80 50 6 09.05.2013 E
81 50 6 10.05.2013 M Nitrogen pumping
82 63 7 06.03.2012 E 150
83 67 8 12.04.2013 E
84 70 8 22.03.2012 N
85 75 9 26.03.2012 N
86 75 9 27.03.2012 M Riger Planning
87 75 9 08.05.2013 N
88 78 9 24.04.2013 M Pull out/Run
In/Circulation/Pull out
89 79 9 29.04.2013 N
90 80 9 07.03.2012 M 150 BOP Planning
91 80 9 07.03.2012 E 150
92 80 9 22.03.2012 E
93 80 9 26.03.2012 E
94 80 9 07.05.2013 E
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
37 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl. No.
DG-2
Date Shift Depth of
Drill (M) Operations Av. Load
on DG-2
Av. Load
on DG-2 95 80 9 08.05.2013 M Logging
96 80 9 08.05.2013 E
97 82 10 29.04.2013 E
98 85 10 29.04.2013 M Pipe pro
99 86 10 10.03.2012 N
100 86 10 07.03.2012 N 150
101 88 10 28.03.2012 E
102 88 10 28.04.2013 N
103 90 11 14.04.2013 E
104 90 11 04.05.2013 N
105 94 11 06.05.2013 N
106 98 11 23.03.2012 M Casing
107 100 12 27.04.2013 N
108 100 12 03.05.2013 M Tubing Run In
109 103 12 19.03.2012 N
110 103 12 16.04.2013 M Logging/Run in /Pull out
111 108 13 07.05.2013 M Waiting for pumpout
112 108 13 30.04.2013 M Pipe pro
113 108 13 30.04.2013 N
114 113 13 14.04.2013 N
115 113 13 05.05.2013 M Pull out/Tubing
116 119 14 03.05.2013 N
117 121 14 28.04.2013 E
118 122 14 23.04.2013 M Pull out
119 124 15 05.05.2013 N
120 128 15 11.03.2012 N
121 130 15 30.04.2013 E
122 133 16 17.04.2013 E
123 135 16 05.05.2013 E
124 141 17 06.03.2012 M 150 BOP Planning
125 143 17 19.03.2012 E
126 143 17 17.04.2013 M Casing Run In
127 150 18 18.03.2012 M 1452 Drilling
128 150 18 12.04.2013 M Circulation
129 150 18 16.04.2013 E
130 163 19 08.03.2012 M 307 Drilling
131 163 19 06.04.2012 N
132 163 19 15.04.2013 N
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
38 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl. No.
DG-2
Date Shift Depth of
Drill (M) Operations Av. Load
on DG-2
Av. Load
on DG-2 133 163 19 18.04.2013 N
134 163 19 22.04.2013 N
135 167 20 08.03.2012 E
136 169 20 03.04.2012 M 2411 Circulation
137 175 21 05.03.2012 N
138 175 21 06.04.2012 E
139 178 21 04.04.2012 M 2411 Circulation
140 179 21 02.04.2012 M 2271 Recirculation
141 180 21 11.03.2012 M 532 Pull Out
142 183 21 03.05.2013 E
143 186 22 25.04.2013 M Pull out
144 188 22 29.03.2012 M Cement/Cutting
145 188 22 19.04.2013 M Casing JOS
146 188 22 23.04.2013 N
147 199 23 22.03.2012 M Casing/Recirculation
148 200 24 23.03.2012 E
149 200 24 06.05.2013 E
150 205 24 16.03.2012 N
151 205 24 12.04.2013 N
152 206 24 05.03.2012 E
153 208 24 18.04.2013 E
154 212 25 11.03.2012 E
155 215 25 16.03.2012 M 1281 Drilling/Pull
Out/Recirculation
156 224 26 13.04.2013 E
157 225 26 04.04.2012 E
158 225 26 15.04.2013 M Circulation
159 228 27 18.03.2012 E 1513
160 230 27 25.04.2013 E
161 231 27 28.03.2012 N
162 233 27 16.04.2013 N
163 237 28 26.04.2013 M Casing
164 240 28 30.03.2012 M 1812 Drilling
165 245 29 17.03.2012 M 1452 Drilling
166 245 29 17.03.2012 E
167 245 29 11.04.2012 N
168 245 29 15.04.2013 E
169 250 29 01.04.2012 E
170 250 29 13.04.2013 M Circulation
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
39 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl. No.
DG-2
Date Shift Depth of
Drill (M) Operations Av. Load
on DG-2
Av. Load
on DG-2 171 250 29 20.04.2013 M Casing JOS
172 250 29 20.04.2013 E
173 258 30 03.04.2012 E
174 260 31 17.03.2012 N
175 263 31 24.04.2013 N
176 269 32 23.04.2013 E
177 270 32 24.04.2013 E
178 276 32 16.03.2012 E
179 279 33 20.03.2012 M Pull out
180 281 33 15.03.2012 N 1178
181 281 33 17.04.2013 N
182 288 34 21.03.2012 N
183 290 34 29.03.2012 E
184 294 35 07.04.2012 M Drilling
185 294 35 09.04.2012 N
186 300 35 29.03.2012 N
187 300 35 01.04.2012 N
188 300 35 03.04.2012 N
189 300 35 10.04.2012 N 2832
190 300 35 18.04.2013 M Casing JOS
191 300 35 25.04.2013 N
192 300 35 12.05.2014 M Pipe Br.
193 310 36 19.04.2013 E
194 341 40 10.04.2012 M 2716 Drilling
195 344 40 07.04.2012 E 2477
196 344 40 07.04.2012 N 2551
197 346 41 09.04.2012 E
198 350 41 13.03.2012 M 783 Pullout/Drilling
199 350 41 13.03.2012 N
200 350 41 15.03.2012 E 1028
201 350 41 01.04.2012 M 2271 Pull out
202 350 41 08.04.2012 M 2686 Drilling/Pull out
203 350 41 08.04.2012 E
204 353 41 11.04.2012 M 2888 Drilling/Pullout
205 379 45 13.03.2012 E
206 380 45 10.04.2012 E 2795
207 400 47 11.04.2012 E 2954
208 400 47 19.04.2013 N
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
40 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl. No.
DG-2
Date Shift Depth of
Drill (M) Operations Av. Load
on DG-2
Av. Load
on DG-2 209 11.04.2012
Observation: From the above exercise it is observed that the load on DG has varied from 6% to 47%
during its 128 shifts(42 days) operations. Hence, the entire DG operations has been carried out at
part load, which is energy wasting. Normally, load about 75% on DG is considered optimised and
rational. However, in case of drilling rig, where the operators have to often play a safe side, let us
consider that load between 40% to 60% is realistic.
In the above study, it is clear that the DG was operated above 40% only for 15 shifts i.e. for 5 days.
For the remaining 37 days, load on DG was below 40% and many a days at part load condition.
DG#3:
Sl.No.
DG-3
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-3
Av.%Load
on DG-3
1 0 0 04.03.2012 M 9 Spud-in
2 0 0 05.03.2012 E
3 0 0 05.03.2012 N
4 0 0 06.03.2012 M 150 BOP Planning
5 0 0 06.03.2012 E 150
6 0 0 06.03.2012 N 150
7 0 0 07.03.2012 M 150 BOP Planning
8 0 0 07.03.2012 E 150
9 0 0 07.03.2012 N 150
10 0 0 08.03.2012 M 307 Drilling
11 0 0 08.03.2012 N
12 0 0 10.03.2012 E
13 0 0 11.03.2012 E
14 0 0 11.03.2012 N
15 0 0 13.03.2012 E
16 0 0 13.03.2012 N
17 0 0 15.03.2012 M Drilling
18 0 0 18.03.2012 M 1452 Drilling
19 0 0 21.03.2012 E
20 0 0 21.03.2012 N
21 0 0 22.03.2012 M Casing/Recirculation
22 0 0 23.03.2012 E
23 0 0 23.03.2012 N
24 0 0 24.03.2012 N
25 0 0 25.03.2012 M Wetting cement
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
41 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-3
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-3
Av.%Load
on DG-3
26 0 0 25.03.2012 E
27 0 0 25.03.2012 N
28 0 0 26.03.2012 E
29 0 0 26.03.2012 N
30 0 0 27.03.2012 M Riger Planning
31 0 0 29.03.2012 E
32 0 0 29.03.2012 N
33 0 0 30.03.2012 M 1812 Drilling
34 0 0 02.04.2012 N
35 0 0 05.04.2012 M 2411 Circulation
36 0 0 05.04.2012 E
37 0 0 05.04.2012 N
38 0 0 06.04.2012 E
39 0 0 06.04.2012 N
40 0 0 07.04.2012 M Drilling
41 0 0 07.04.2012 E 2477
42 0 0 07.04.2012 N 2551
43 0 0 08.04.2012 M 2686 Drilling/Pull out
44 0 0 10.04.2012 E 2795
45 0 0 10.04.2012 N 2832
46 0 0 11.04.2012 M 2888 Drilling/Pullout
47 0 0 11.04.2012 E 2954
48 0 0 15.04.2013 E
49 0 0 15.04.2013 N
50 0 0 16.04.2013 M Logging/Run in /Pull out
51 0 0 22.04.2013 E
52 0 0 24.04.2013 E
53 0 0 24.04.2013 N
54 0 0 25.04.2013 M Pull out
55 0 0 25.04.2013 E
56 0 0 25.04.2013 N
57 0 0 26.04.2013 M Casing
58 0 0 26.04.2013 E
59 0 0 28.04.2013 M BOP Dismantling
60 0 0 28.04.2013 E
61 0 0 28.04.2013 N
62 0 0 29.04.2013 M Pipe pro
63 0 0 03.05.2013 E
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
42 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-3
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-3
Av.%Load
on DG-3
64 0 0 03.05.2013 N
65 0 0 04.05.2013 N
66 0 0 05.05.2013 M Pull out/Tubing
67 0 0 05.05.2013 E
68 0 0 07.05.2013 M Waiting for pumpout
69 0 0 07.05.2013 E
70 0 0 07.05.2013 N
71 0 0 08.05.2013 M Logging
72 0 0 08.05.2013 E
73 0 0 08.05.2013 N
74 0 0 09.05.2013 E
75 0 0 09.05.2013 N
76 0 0 10.05.2013 M Nitrogen
77 0 0 10.05.2013 E
78 0 0 10.05.2013 N
79 0 0 11.05.2013 E
80 0 0 11.05.2013 N
81 0 0 12.05.2014 M Pipe Br.
82 0 0 12.05.2014 N
83 38 4 12.04.2013 E
84 50 6 27.03.2012 E
85 50 6 06.05.2013 M Run In
86 50 6 09.05.2013 M Logging
87 50 6 12.05.2014 E
88 58 7 03.05.2013 M Tubing Run In
89 60 7 02.04.2012 E
90 61 7 14.04.2013 E
91 67 8 26.03.2012 M BOP Planning
92 69 8 22.03.2012 E
93 69 8 12.04.2013 M Circulation
94 70 8 22.03.2012 N
95 70 8 27.03.2012 N
96 70 8 28.03.2012 M Recirculation/Drilling
97 75 9 13.04.2013 N
98 75 9 14.04.2013 M Run in
99 75 9 24.04.2013 M Pull out/Run
In/Circulation/Pull out
100 75 9 01.05.2013 M Production Tube Joining
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
43 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-3
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-3
Av.%Load
on DG-3
101 75 9 01.05.2013 N
102 75 9 02.05.2013 M Tubing Run In
103 75 9 02.05.2013 E
104 75 9 02.05.2013 N
105 75 9 04.05.2013 E
106 79 9 29.04.2013 N
107 80 9 06.04.2012 M 2411 Running in/ Reaming
108 81 10 30.04.2013 N
109 83 10 28.03.2012 E
110 83 10 29.04.2013 E
111 88 10 24.03.2012 E
112 88 10 19.04.2013 M Casing JOS
113 90 11 24.03.2012 M Cementing
114 90 11 04.04.2012 N
115 92 11 10.03.2012 N
116 95 11 01.05.2013 E
117 100 12 05.03.2012 M 150 Circulation
118 100 12 20.04.2013 E
119 100 12 27.04.2013 N
120 100 12 11.05.2013 M Nitrogen
121 103 12 19.03.2012 N
122 104 12 30.04.2013 E
123 108 13 05.05.2013 N
124 109 13 06.05.2013 N
125 113 13 14.04.2013 N
126 113 13 20.04.2013 N
127 125 15 09.03.2012 M 307 Drilling
128 129 15 09.03.2012 E
129 131 15 17.04.2013 M Casing Run In
130 133 16 17.04.2013 E
131 133 16 30.04.2013 M Pipe pro
132 137 16 23.04.2013 M Pull out
133 143 17 21.04.2013 N
134 143 17 19.03.2012 E
135 144 17 10.03.2012 M 532 Drilling
136 150 18 16.04.2013 E
137 150 18 26.04.2013 N
138 150 18 27.04.2013 M Waiting for Cement
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
44 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-3
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-3
Av.%Load
on DG-3
139 150 18 04.05.2013 M Pull out/Tubing
140 150 18 06.05.2013 E
141 160 19 08.03.2012 E
142 160 19 27.04.2013 E
143 163 19 18.04.2013 N
144 163 19 22.04.2013 N
145 167 20 13.03.2012 M 783 Pullout/Drilling
146 173 20 02.04.2012 M 2271 Recirculation
147 183 21 12.03.2012 N
148 183 22 21.03.2012 M 1753 Pull out(Logging)
149 184 22 09.03.2012 N
150 185 22 22.04.2013 M Casing Pullout
151 188 22 30.03.2012 N
152 188 22 23.04.2013 N
153 190 22 16.04.2013 N
154 200 24 11.03.2012 M 532 Pull Out
155 200 24 04.04.2012 M 2411 Circulation
156 200 24 09.04.2012 M 2690 Reaming/Drilling
157 208 24 18.04.2013 E
158 215 25 16.03.2012 M 1281 Drilling/Pull Out/Recirculation
159 217 25 29.03.2012 M Cement/Cutting
160 220 26 30.03.2012 E
161 223 26 16.03.2012 N
162 224 26 13.04.2013 E
163 225 26 20.03.2012 N
164 225 26 04.04.2012 E
165 229 27 11.04.2012 N
166 229 27 12.04.2013 N
167 231 27 28.03.2012 N
168 233 27 12.03.2012 M 712 Drilling/Pull Out
169 243 29 09.04.2012 E
170 245 29 17.03.2012 E
171 250 29 14.03.2012 M 829 Drilling/Pull Out/Recirculation
172 250 29 14.03.2012 N
173 250 29 17.03.2012 M 1452 Drilling
174 250 29 23.03.2012 M Casing
175 250 29 31.03.2012 E
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
45 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-3
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-3
Av.%Load
on DG-3
176 250 29 01.04.2012 E
177 250 29 15.04.2013 M Circulation
178 253 30 03.04.2012 M 2411 Circulation
179 260 31 31.03.2012 N
180 260 31 13.04.2013 M Circulation
181 260 31 20.04.2013 M Casing JOS
182 269 32 23.04.2013 E
183 273 32 21.04.2013 M Casing Pullout
184 275 32 19.03.2012 M 1652 Recirculation
185 276 32 16.03.2012 E
186 281 33 15.03.2012 N 1178
187 281 33 20.03.2012 M Pull out
188 281 33 17.04.2013 N
189 284 33 14.03.2012 E
190 286 34 17.03.2012 N
191 295 35 09.04.2012 N
192 300 35 18.03.2012 E 1513
193 300 35 18.03.2012 N 1624
194 300 35 31.03.2012 M 2271 Drilling
195 300 35 01.04.2012 N
196 300 35 03.04.2012 E
197 300 35 18.04.2013 M Casing JOS
198 300 35 21.04.2013 E
199 330 39 01.04.2012 M 2271 Pull out
200 333 39 10.04.2012 M 2716 Drilling
201 340 40 19.04.2013 E
202 350 41 15.03.2012 E 1028
203 350 41 08.04.2012 E
204 360 42 08.04.2012 N
205 361 42 12.03.2012 E
206 390 46 03.04.2012 N
207 400 47 20.03.2012 E
208 400 47 19.04.2013 N
209 11.04.2012
Observation: From the above exercise it is observed that the load on DG has varied from 4% to 47%
during its 125 shifts(41 days) operations. Hence, the entire DG operations has been carried out at
part load, which is energy wasting. Normally, load about 75% on DG is considered optimised and
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
46 | P a g e
Petroleum Conservation Research Association – Eastern Region
rational. However, in case of drilling rig, where the operators have to often play a safe side, let us
consider that load between 40% to 60% is realistic.
In the above study, it is clear that the DG was operated above 40% only for 8 shifts i.e. for 3 days.
For the remaining 38 days, load on DG was below 40% and many a days at part load condition.
DG#4:
Sl.No.
DG-4
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-4
Av.%Load
on DG-4 1 0 0 04.03.2012 M 9 Spud-in
2 0 0 05.03.2012 M 150 Circulation
3 0 0 05.03.2012 E
4 0 0 05.03.2012 N
5 0 0 06.03.2012 E 150
6 0 0 06.03.2012 N 150
7 0 0 07.03.2012 M 150 BOP Planning
8 0 0 07.03.2012 E 150
9 0 0 07.03.2012 N 150
10 0 0 08.03.2012 M 307 Drilling
11 0 0 10.03.2012 E
12 0 0 10.03.2012 N
13 0 0 11.03.2012 M 532 Pull Out
14 0 0 12.03.2012 E
15 0 0 12.03.2012 N
16 0 0 13.03.2012 M 783 Pullout/Drilling
17 0 0 13.03.2012 E
18 0 0 13.03.2012 N
19 0 0 14.03.2012 M 829 Drilling/Pull
Out/Recirculation
20 0 0 14.03.2012 N
21 0 0 15.03.2012 M Drilling
22 0 0 16.03.2012 E
23 0 0 16.03.2012 N
24 0 0 17.03.2012 E
25 0 0 17.03.2012 N
26 0 0 19.03.2012 N
27 0 0 22.03.2012 E
28 0 0 22.03.2012 N
29 0 0 23.03.2012 N
30 0 0 26.03.2012 E
31 0 0 26.03.2012 N
32 0 0 27.03.2012 M Riger Planning
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
47 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-4
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-4
Av.%Load
on DG-4 33 0 0 27.03.2012 E
34 0 0 27.03.2012 N
35 0 0 28.03.2012 M Recirculation/Drilling
36 0 0 28.03.2012 E
37 0 0 28.03.2012 N
38 0 0 29.03.2012 M Cement/Cutting
39 0 0 29.03.2012 E
40 0 0 29.03.2012 N
41 0 0 02.04.2012 E
42 0 0 02.04.2012 N
43 0 0 04.04.2012 E
44 0 0 04.04.2012 N
45 0 0 05.04.2012 M 2411 Circulation
46 0 0 05.04.2012 E
47 0 0 05.04.2012 N
48 0 0 06.04.2012 M 2411 Running in/ Reaming
49 0 0 09.04.2012 N
50 0 0 11.04.2012 N
51 0 0 12.04.2013 M Circulation
52 0 0 12.04.2013 E
53 0 0 13.04.2013 N
54 0 0 14.04.2013 M Run in
55 0 0 14.04.2013 E
56 0 0 14.04.2013 N
57 0 0 16.04.2013 M Logging/Run in /Pull out
58 0 0 16.04.2013 E
59 0 0 16.04.2013 N
60 0 0 17.04.2013 M Casing Run In
61 0 0 17.04.2013 E
62 0 0 17.04.2013 N
63 0 0 18.04.2013 M Casing JOS
64 0 0 18.04.2013 E
65 0 0 18.04.2013 N
66 0 0 19.04.2013 E
67 0 0 19.04.2013 N
68 0 0 20.04.2013 M Casing JOS
69 0 0 22.04.2013 N
70 0 0 23.04.2013 N
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
48 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-4
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-4
Av.%Load
on DG-4 71 0 0 24.04.2013 M Pull out/Run
In/Circulation/Pull out
72 0 0 28.04.2013 E
73 0 0 28.04.2013 N
74 0 0 29.04.2013 M Pipe pro
75 0 0 29.04.2013 E
76 0 0 29.04.2013 N
77 0 0 30.04.2013 M Pipe pro
78 0 0 30.04.2013 E
79 0 0 30.04.2013 N
80 0 0 01.05.2013 M Production Tube Joining
81 0 0 01.05.2013 E
82 0 0 01.05.2013 N
83 0 0 02.05.2013 M Tubing Run In
84 0 0 02.05.2013 E
85 0 0 02.05.2013 N
86 0 0 03.05.2013 M Tubing Run In
87 0 0 05.05.2013 M Pull out/Tubing
88 0 0 05.05.2013 E
89 0 0 05.05.2013 N
90 0 0 06.05.2013 M Run In
91 0 0 06.05.2013 E
92 0 0 06.05.2013 N
93 0 0 07.05.2013 N
94 0 0 08.05.2013 M Logging
95 0 0 08.05.2013 E
96 0 0 08.05.2013 N
97 0 0 09.05.2013 E
98 0 0 09.05.2013 N
99 0 0 10.05.2013 M Nitrogen
100 0 0 10.05.2013 E
101 0 0 10.05.2013 N
102 0 0 11.05.2013 M Nitrogen
103 0 0 11.05.2013 E
104 0 0 11.05.2013 N
105 0 0 12.05.2014 M Pipe Br.
106 0 0 12.05.2014 E
107 0 0 12.05.2014 N
108 48 6 26.03.2012 M BOP Planning
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
49 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-4
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-4
Av.%Load
on DG-4 109 50 6 28.04.2013 M BOP Dismantling
110 50 6 09.05.2013 M Logging
111 55 6 25.03.2012 M Wetting cement
112 60 7 24.03.2012 N
113 75 9 25.03.2012 N
114 78 9 24.03.2012 E
115 79 9 20.04.2013 E
116 80 9 25.03.2012 E
117 80 9 07.05.2013 E
118 85 10 27.04.2013 N
119 88 10 21.03.2012 E
120 88 10 24.03.2012 M Cementing
121 100 12 20.04.2013 N
122 100 12 04.05.2013 N
123 103 12 12.03.2012 M 712 Drilling/Pull Out
124 103 12 07.05.2013 M Waiting for pumpout
125 113 13 26.04.2013 E
126 119 14 03.05.2013 N
127 128 15 11.03.2012 N
128 129 15 04.05.2013 M Pull out/Tubing
129 130 15 09.03.2012 E
130 136 16 23.03.2012 M Casing
131 138 16 08.03.2012 N
132 138 16 09.03.2012 M 307 Drilling
133 138 16 23.03.2012 E
134 143 17 21.04.2013 N
135 143 17 19.03.2012 E
136 144 17 04.05.2013 E
137 150 18 06.03.2012 M 150 BOP Planning
138 150 18 08.03.2012 E
139 150 18 21.03.2012 N
140 150 18 26.04.2013 N
141 150 18 27.04.2013 M Waiting for Cementing
142 160 19 27.04.2013 E
143 163 19 21.03.2012 M 1753 Pull out(Logging)
144 163 19 06.04.2012 N
145 163 19 25.04.2013 E
146 166 20 10.03.2012 M 532 Drilling
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
50 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-4
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-4
Av.%Load
on DG-4 147 173 20 23.04.2013 M Pull out
148 174 20 16.03.2012 M 1281 Drilling/Pull
Out/Recirculation
149 183 21 03.05.2013 E
150 184 22 09.03.2012 N
151 185 22 22.04.2013 M Casing Pullout
152 186 22 03.04.2012 M 2411 Circulation
153 188 22 30.03.2012 N
154 188 22 06.04.2012 E
155 191 22 02.04.2012 M 2271 Recirculation
156 193 23 14.03.2012 E
157 198 23 11.03.2012 E
158 199 23 30.03.2012 E
159 200 24 09.04.2012 M 2690 Reaming/Drilling
160 200 24 15.04.2013 M Circulation
161 208 24 25.04.2013 M Pull out
162 225 26 20.03.2012 N
163 226 27 26.04.2013 M Casing
164 228 27 18.03.2012 E 1513
165 244 29 22.04.2013 E
166 245 29 15.04.2013 E
167 250 29 22.03.2012 M Casing/Recirculation
168 250 29 31.03.2012 E
169 250 29 01.04.2012 E
170 256 30 21.04.2013 M Casing Pullout
171 260 31 31.03.2012 N
172 263 31 24.04.2013 N
173 267 31 04.04.2012 M 2411 Circulation
174 269 32 23.04.2013 E
175 270 32 24.04.2013 E
176 271 32 03.04.2012 E
177 275 32 19.03.2012 M 1652 Recirculation
178 275 32 13.04.2013 M Circulation
179 281 33 15.03.2012 N 1178
180 294 35 07.04.2012 M Drilling
181 300 35 18.03.2012 M 1452 Drilling
182 300 35 18.03.2012 N 1624
183 300 35 31.03.2012 M 2271 Drilling
184 300 35 01.04.2012 N
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
51 | P a g e
Petroleum Conservation Research Association – Eastern Region
Sl.No.
DG-4
Date Shift Depth of
Drill (M) Operations Av.Load on
DG-4
Av.%Load
on DG-4 185 300 35 03.04.2012 N
186 300 35 10.04.2012 N 2832
187 300 35 12.04.2013 N
188 300 35 13.04.2013 E
189 300 35 21.04.2013 E
190 300 35 25.04.2013 N
191 308 36 20.03.2012 M Pull out
192 310 36 30.03.2012 M 1812 Drilling
193 313 37 19.04.2013 M Casing JOS
194 330 39 01.04.2012 M 2271 Pull out
195 344 40 07.04.2012 E 2477
196 344 40 07.04.2012 N 2551
197 344 40 08.04.2012 E
198 350 41 15.03.2012 E 1028
199 350 41 08.04.2012 M 2686 Drilling/Pull out
200 350 41 10.04.2012 M 2716 Drilling
201 350 41 15.04.2013 N
202 358 42 11.04.2012 M 2888 Drilling/Pullout
203 360 42 08.04.2012 N
204 400 47 20.03.2012 E
205 400 47 09.04.2012 E
206 400 47 10.04.2012 E 2795
207 400 47 11.04.2012 E 2954
208 450 53 17.03.2012 M 1452 Drilling
209 11.04.2012
Observation: From the above exercise it is observed that the load on DG has varied from 6% to 53%
during its 101 shifts(33 days) operations. Hence, the entire DG operations has been carried out at
part load, which is energy wasting. Normally, load about 75% on DG is considered optimised and
rational. However, in case of drilling rig, where the operators have to often play a safe side, let us
consider that load between 40% to 60% is realistic.
In the above study, it is clear that the DG was operated above 40% only for 13 shifts i.e. for 4 days.
For the remaining 29 days, load on DG was below 40% and many a days at part load condition.
6.4 Average specific fuel consumption by DGs:
As exercised earlier(ch.-3) the enrgy generated by DGs during the drilling operation = 591788 kWh
Diesel consumption for above generation = 193538 Ltrs.
Average specific fuel consumption by DGs = 193538 x1000x0.85/591788 = 278 gm /kWh
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
52 | P a g e
Petroleum Conservation Research Association – Eastern Region
(Specific gravidy of diesel = 0.85)
Designed specific fuel consumption of D-399 Caterpillar Engine:
% Load Sp Fuel Con. (gm/kWh)
25 297
50 254
75 242
100 247
Comments: The derived average specific fuel consumption in relation to the present operating condition is 278
gm/kWh. The reason behind this higher specific fuel consumption is part load operation of the DGs
during the drilling operation. Most of the days the load on all the DGs varied between 4% to 40%.
Recommendation-1: Rationalize DG operations to ensure the load on DGs above 50% with existing
on line generators.
Estimated savings:
Established specific fuel consumption at existing operating practice = 278 gm/kWh
Specific fuel consumption at 50% load on DGs = 254 gm/kWh
Savings = 278 – 254 = 24 gm/kWh
kWh generated by all the DGs for drilling one well = 591788 kWh
Savings for drilling of one well = 24 x 591788 gm =24 x 591788/0.85 cc =16709308 cc
= 16.7 KL (considering, density of diesel = 0.85)
Market price of 1 KL diesel = Rs.50,000/-
Savings for drilling one well = Rs.50,000 x 16.7 = Rs.8,35,000/-
Considering 3 nos. drilling wells are carried out by a rig in a year
Annual savings = Rs.8,35,000 x 3 = Rs.25,05,000/-
Recommendation-2: The existing D399 engines may be replaced by energy efficient engines like D-3512B.
This is likely to result in saving of Rs. 2297529/- for one drilling well of 2960Mtrs completed in
70 days.
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
53 | P a g e
Petroleum Conservation Research Association – Eastern Region
The fuel efficiency Vs load curve for D-3513B is as below:
Savings with new gen-set D-3512B and at 50% loading from the graph is
= (278-212) X 591788 x 50000/ (1000 x 850) = Rs. 2297529/-
Cost of one D-3512B engine = $ 396000 (USD) = 200 lacs (approx)
Therefore, by replacing 2 Nos. D399 engine with D3512B engines-
Pay back period will be = (200 x 2)/68.93 = 5.8 years= 5 years & 10 Months
Note: It was learnt that OIL is already in the process of replacing CAT-D399 engines with D-3512B
engines. It is suggested that the process may be expedited to achieve the desired savings as early as
possible.
Recommendation-3:
Install a gen-set of lower capacity (KVA as required) to cater auxiliary AC load. This will help
in reducing the running hours of bigger DG Sets on low load condition and result in
substantial savings apart from increasing the life of the rig engines.
Since, many a times, it is a usual practice to operate necessary AC connected load
during the drilling operations. It is very difficult to rationalize the load with existing higher
size (1215 KVA) DGs when the load requirement is very low. Hence, it is justified to install a
smaller size DG to cater the AC-load as and when required. It is advisable to use the lower
capacity gen-set during production testing / waiting for allied services etc. when only
auxiliary and lighting load is required. [(Note: Such practice is prevalent at the Rig of M/s.
JAY BEE Energy (P) Ltd. The model of the Rig is DZ 315/9-S and nominal drill depth of which
is 3000 – 5000M).They installed a 400 KVA DG of VOLVO PENTA make. ]
Investment:
Estimate cost of 400 KVA DG = Rs. 50,00,000/-
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
54 | P a g e
Petroleum Conservation Research Association – Eastern Region
6.5 General Maintenance Recommendations for DG Engines
Trouble shooting and Remedy for DG Sets is presented below:
Checkpoint
Cause of Trouble Remedy
Starter Defective Pinion Gear(teeth stripped)
Engine Piston, crank bearing seizure, or other damage Repair or repair the related
parts
Injection Nozzle Injection nozzle starting pressure too low.
Improper spray condition
Adjust or replace the
injection nozzle
Injection pump
Defective fuel injection nozzle resulting in fuel
drippage after the fuel injection
Replace the delivery valve
Defective injection pump control rack
operation
Repair or replace the
injection pump control rack
Injection pump plunger worn or stuck Replace the injection pump
plunger assembly
Injection pump
Injection pump drive shaft seizure or other
damage.
Replace the injection pump
drive shaft.
Injection pump governor spring seizure. Replace the injection pump
governor spring.
Engine stop
mechanism
Defective engine stop mechanism. Control
wire improperly adjusted(In-line-pump)
Replace the engine stop
mechanism, adjust the
control wire.
Defective fuel cut-off solenoid valve(VE pump) Replace the fuel cut-off
solenoid valve
Fuel piping Clogged or damaged fuel lines. Loose fuel line
connections
Repair or replace the fuel
filter overflow valve.
Fuel filter Fuel filter overflow valve does not close Repair or replace the fuel
filter overflow valve.
Clogged fuel filter element Replace filter
Fuel system
Air in the fuel system Bleed the air from the fuel
system
Clogged inline filter(located in the fuel inlet
banjo bolt on the fuel lift pump.(Inline
Injection Pump Models)
Remove banjo bolt and clean
debris from screen filter.
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
55 | P a g e
Petroleum Conservation Research Association – Eastern Region
Checkpoint Trouble Cause Remedy
Low idling system Low idling improperly adjusted. Adjust the low idling.
Low idling speed
control device
Defective low idling speed control
device.
Repair or replace the low idling
speed control device.
Throttle control
system
Throttle control system improperly
adjusted.
Adjust the throttle control
system.
Fuel System
Fuel system leakage or blockage. Repair or replace the fuel
system
Air in the fuel system. Bleed the air from the fuel
system.
Water particles in the fuel system. Change the fuel.
Clogged inline filter (located in the fuel
inlet banjo bolt) on the fuel lift pump.
(Inline Injection Pump Models)
Remove banjo bolt and clean
debris from screen filter.
Fuel filter Clogged fuel filter element. Replace filter.
Injection pump
Defective governor lever operation. Repair or replace the governor
lever.
Regulator valve improperly adjusted
(VE pump only)
Adjust or replace the regulator
valve.
Broken plunger spring. Replace the plunger spring.
Worn plunger. Replace the plunger assembly.
Worn camshaft (in-line pump only) Replace the camshaft.
Worn roller tappet (in-line pump only). Replace the roller tappet.
Worn cam disc (VE pump only) Replace the cam disc.
Valve clearance Valve clearance improperly adjusted. Adjust the valve clearance.
Compression
pressure
Blown out cylinder head gasket, Worn
cylinder liner, Piston ring sticking or
broken, Improper seating between the
valve and the valve seat.
Replace the related parts.
Unstable Low Idling
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
56 | P a g e
Petroleum Conservation Research Association – Eastern Region
Checkpoint Trouble Cause Remedy
Air cleaner Clogged air cleaner element Clean or replace the element
Fuel Water particles in the fuel Replace fuel
Fuel filter Clogged fuel filter element Replace filter
Fuel Feed Pump
Clogged inline filter (located in the fuel
inlet banjo bolt) on the fuel lift pump.
(Inline Injection Pump Models)
Remove banjo bolt and clean
debris from screen filter.
Defective fuel feed pump Repair or replace the fuel feed
pump.
Injection nozzle
Injection nozzle sticking Replace the injection nozzle.
Injection nozzle injection starting
pressure to low, Improper spray
condition.
Adjust or replace the injection
Fuel injection
pipes
Fuel injection pipes damaged or
obstructed.
Replace the fuel injection pipes.
Injection pump
Defective delivery valve Replace the delivery valve
Defective timer Repair or replace the timer.
Improper control lever operation Adjust or replace the control
lever.
Defective injection timing. Adjust the injection timing.
Repair or replace the injection
pump timer.
Weak governor spring. Replace governor spring.
Worn plunger. Replace plunger assy.
Worn camshaft (In-line pump only) Replace the camshaft.
Worn roller tappet Replace the roller tappet.
Turbocharger
Exhaust gas leakage from the exhaust
system, Air leakage from the intake
system.
Repair or replace the related
parts.
Defective turbocharger assembly Replace the turbocharger
Compression
Pressure
Blown out cylinder head gasket, Worn
cylinder liner, Piston ring sticking or
broken, Improper seating between the
valve and the valve seat.
Replace the related parts.
Valve clearance Valve clearance improperly adjusted. Adjust the valve clearance.
Valve spring Valve spring weak or broken. Replace the valve spring.
Exhaust system Exhaust pipe clogged. Clean the exhaust system.
Full load
adjusting screw
seal
Open and improperly set adjusting
screw seal
Adjust and reseal the adjusting
screw.
Insufficient Power
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
57 | P a g e
Petroleum Conservation Research Association – Eastern Region
Checkpoint Trouble Cause Remedy
Fuel System Fuel leakage Repair or replace the fuel
system related parts.
Air Cleaner Clogged air cleaner element Clean or replace the air filter
element.
Low idling speed Poorly adjusted low idle speed Adjust the low idle speed.
Injection nozzle Injection nozzle injection starting
pressure to low, Improper sprays
condition.
Adjust or replace the injection
nozzle.
Fuel injection
timing
Fuel injection timing improperly adjusted Adjust the fuel injection timing.
Injection pump Defective delivery valve resulting fuel
drippage after fuel injection
Replace the delivery valve.
Turbocharger
Air leakage from the turbocharger intake
side.
Repair the turbocharger intake
side.
Defective turbocharger assembly Replace the turbocharger
assembly.
Valve Clearance Valve clearance improperly adjusted. Adjust the valve clearance.
Compression
pressure
Blown out cylinder head gasket, Worn
cylinder liner, Piston ring sticking or
broken, Improper seating between the
valve and the valve seat.
Replace the related parts.
Valve spring Valve spring weak or broken Replace the valve spring.
Checkpoint Trouble Cause Remedy
Engine Oil Engine Oil unsuitable, Too
much engine oil
Replace the engine oil, correct the
engine oil volume.
Oil seal & gasket Oil leakage from the oil seal
and or gasket
Replace the oil seal and or gasket.
Air breather Clogged air breather. Clean the air breather.
Inlet and exhaust valve
stem seals
Defective valve seals, Worn
valve stems and valve
guides.
Replace the valve seals, the valves,
and the valve guides.
Piston rings Piston rings worn, broken or
improperly installed.
Replace the piston rings or properly
install.
Cylinders liners Cylinder liners scored or
worn
Replace the cylinder liners.
Excessive Fuel Consumption
Excessive Oil Consumption
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
58 | P a g e
Petroleum Conservation Research Association – Eastern Region
Checkpoint Trouble Cause Remedy
Cooling water Insufficient cooling water Replenish the cooling water
Radiator Defective radiator cap or
clogged radiator core
Replace the radiator cap or clean
the radiator core.
Water Pump Defective water pump Repair or replace the water
pump
Cylinder head and cylinder
body sealing cap
Defective sealing cap resulting
in water leakage.
Replace the sealing cap.
Thermostat Defective Thermostat Replace the thermostat
Cooling System Cooling system clogged by
foreign material.
Clean the foreign material from
the cooling system.
Fuel injection timing Fuel injection timing
improperly adjusted.
Adjust the fuel injection timing.
Checkpoint Trouble Cause Remedy
Fuel Water particles in the fuel Replace fuel
Fuel injection timing Delayed fuel injection timing Adjust the fuel injection timing.
Compression pressure Blown out cylinder head gasket,
Worn out cylinder liner, Piston
ring sticking or broken,
Improper seating between the
valve and the valve seat.
Replace the related parts.
Turbocharger Defective Turbocharger Replace the turbo
Inlet and exhaust valve
stem seals
Defective valve stem seals,
Worn valve stems and valve
guides.
Replace the valve stem seals, the
valves and the valve guides.
Piston Rings Piston rings worn, broken or
improperly installed.
Replace the piston rings or
properly install.
Cylinder liners Cylinder liners scored or worn Replace the cylinder liners.
Overheating
White exhaust Smoke
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
59 | P a g e
Petroleum Conservation Research Association – Eastern Region
Checkpoint Trouble Cause Remedy
Air Cleaner Clogged air cleaner element Clean or replace the air cleaner
element
Injection nozzle Injection nozzle injection
starting pressure to low
Improper spray condition.
Adjust or replace the injection
nozzle.
Fuel injection timing Fuel injection timing
improperly adjusted.
Adjust the fuel injection timing.
Injection Pump
Defective delivery valve
resulting in fuel drippage after
fuel injection.
Replace the delivery valve
Excessive injection volume Adjust the injection volume.
Dark Exhaust Smoke
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
60 | P a g e
Petroleum Conservation Research Association – Eastern Region
7.0 Illumination Study:
Total lighting load in the Rig Unit are incorporated below:
List of lamp fitting
Sl. No. Room Lamp Type Wattage Nos. Total
Wattage
1 Security Incandescent 100 10 1000
2 Engine House MLL 160 5 800
CFL 23 2 46
3 Pump House MLL 160 4 640
4 Generator House - - - -
5 Chemical House MLL 160 3 480
6 Material House/Store - - - -
7 Control Room FTL 36 21 756
8 Emergency House FTL 36 2 72
9 Fire House MLL 160 1 160
10 Street Area Light SON 400 14 5600
11 Installation Manager Room FTL 36 3 108
12 Office Room FTL 36 19 684
13 Supervisor/Operator Room FTL 36 23 828
14 Pumping Area MLL 160 1 160
15 Other Areas HPMV 250 7 1750
MLL 160 16 2560
CFL 23 23 529
FTL 36 2 72
Total 16245
From the above table, it is observed that the total lighting load = 16.245 KW
It is further observed that according to the classified areas , the lamps are almost rationalized
except few areas with FTL.
The Rig unit is using 66 nos. 40 W FTL. At present context, it is not energy efficient. Use of
29W T-5 FTL in place of 40W FTL will produce same illumination effect at lower energy
input.
Hence, we recommend replacement all the 40W FTLs with energy efficient T-5 lamps
without declining the lux level.
Energy Audit of Rig E-1400 S-3, Oil India Ltd.
61 | P a g e
Petroleum Conservation Research Association – Eastern Region
Calculation of energy savings by replacing FTLs with T-5 FTLs:
Energy consumption by each 40W FTL = 40 W
Energy consumption by the attached conventional ballast = 12W
Total energy consumption per tube light = 52 W
Energy consumption by each T-5 FTL including ballast = 29W
Savings by replacing one lamp = 52 – 29 = 23 W
No. of lamps recommended to be replaced = 66
Daily glowing hour of a lamp = 12Hrs.
Average working days to complete a drilling operation in a site = 70 days
Glowing hours in 70 days = 70*12 = 840 Hrs.
Energy savings to complete a drilling operation in a site = 23 x 66 x 840 /1000 = 1275 kWh
Specific fuel consumption to generate 1 kWh energy = 278 gm of diesel
Savings to complete a drilling operation = 278/0.85 x1275 =417000 cc = 417 Ltr.
Price of 1 ltr. Diesel = Rs.50/-
Total savings = 417 x 50 = Rs.20,850/-
Considering 3 nos. drilling operation is carried out by a rig in a year
Annual savings = Rs.20,850 x 3 = Rs.62,550/-
Calculation of Investment and Payback:
Cost of one no T-5 lamp with retrofit = Rs.450/-
Cost of 66 nos T-5 lamp = Rs. 29,700/-
Simple pay back period = 0.47 Years. ≈6 Months