For more information, visit MELINKTB.COM Energy Star Program Test & Balance Dec 2015 NUMBER OF STORES 42 stores PUNCHLIST ITEMS & RECOMMENDATIONS Total: 559 Avg: 14 per store TIMEFRAME 2015 Issues Caused By Unbalanced Restaurants: 1. Customer comfort issues 2. Employee comfort issues 3. 20-23% wasted energy costs 4. Slip hazard caused by condensation 5. Damage to walls, flooring, trim 6. Indoor air quality concerns 7. Shortened equipment life expectancy SCOPE OF WORK Melink is to rebalance existing sales floor RTU’s to improve humidity control in the store by reducing supply airflow/minimum outside airflow to the RTU’s. Measure and record the existing supply (total), return, outside air, fan rpms, and static pressures. Set unit totals (connected loads are not required) Balance to within 95% to 110% (-5% to +10%) of updated design numbers. Once each RTU is balanced to within design; lock each RTU into full cooling and record an entering & leaving coil temperature (include measurement in the full report). Measure a final building pressure at the main entrance & rear load- ing dock.

Upload: luci-feie

Post on 13-Apr-2017

134 views

Category:

Services


4 download

TRANSCRIPT

Page 1: Energy Star Test & Balance for National Retail Chain

For more information, visit MELINKTB.COM

Energy Star Program Test & BalanceDec 2015

NUMBER OF STORES42 stores

PUNCHLIST ITEMS & RECOMMENDATIONSTotal: 559Avg: 14 per store

TIMEFRAME2015

Issues Caused By Unbalanced Restaurants:

1. Customer comfort issues2. Employee comfort issues3. 20-23% wasted energy costs4. Slip hazard caused by condensation5. Damage to walls, flooring, trim6. Indoor air quality concerns7. Shortened equipment life expectancy

SCOPE OF WORK

Melink is to rebalance existing sales floor RTU’s to improve humidity control in the store by reducing supply airflow/minimum outside airflow to the RTU’s.• Measure and record the existing supply (total), return, outside air,

fan rpms, and static pressures.• Set unit totals (connected loads are not required)

• Balance to within 95% to 110% (-5% to +10%) of updated design numbers.

• Once each RTU is balanced to within design; lock each RTU into full cooling and record an entering & leaving coil temperature (include measurement in the full report).

• Measure a final building pressure at the main entrance & rear load-ing dock.

Page 2: Energy Star Test & Balance for National Retail Chain

Dirty Blower Wheel

Dirty Filters

OA Dampers Inoperable

Dirty Evaporator Coil

Dirty Return Grilles

Integrity. Service Excellence. Innovation.Integrity. Service Excellence. Innovation.

Call 513-965-7300 to speak to a representative

SAMPLE OF FINDINGS: