eneva corporate presentation ? august 2014

Upload: mpxeri

Post on 03-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    1/22

    August, 2014

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    2/22

    Company Overview

    1

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    3/22

    One of the largest private sector power generators in Brazil

    ENEVA currently operates 2.4GW in coal and gas-fired power plants (2.9 GW until

    Integrated energy platform, with privileged access to natural resources

    Only private power generator in Brazil with access to onshore gas

    Ongoing restructuring initiatives

    - Reorganization of the companys structure and continuous TPPs operation stabiliz

    - Strengthening of the companys capital structure

    Competitive greenfield portfolio

    Licensed coal, gas and wind power generation projects

    Company Overview

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    4/22

    A Brazilian thermal generator with asset exposure to energy fossil fuels (natural gas

    ENEVA at a Glance

    2.9GW inflation-protected, long-term PPAs

    o 2.4GW in operation

    o 517MW under construction

    Long-term PPAs guarantee R$2.2 billion in annual inflation-adjusted

    capacity payments

    PPAs provide hedge against commodity price exposure

    Integrated gas E&P assets supply up to 8.4MM m/day to ENEVAspower

    plants

    Competitive portfolio of licensed greenfield wind, coal and gas fired

    capacity

    Company Description

    ENEVA ownership structure

    Geographic Footp

    Amapari EnergiaENEVA 51% / Eletronorte 49%

    Diesel - 23MW

    ItaqENEVCoal

    Natural GasExploratory

    blocksContracted production

    of 8.4MM m3/day

    Free Float (37.1%)

    42.9%20.0%

    Other

    ENEVA ParticipaesENEVA/E.ON

    Joint Venture

    50%

    50%

    BNDES

    8.6%

    EikeBatista

    Controlling Block

    28.5%

    Note: 1) Ownership structure assumes future ENEVA Participaes (JV ENEVA/E.ON) incorporation, as disclosed on the Material Fact Notice as of July 3, 2013

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    5/22

    Pecm I

    Capacity: 720MW

    Fix. Rev.: R$600.3MM /year

    CVU: R$99/MWh

    Auction: A-5/2007

    COD: Dec, 2012

    Capacity: 360MW

    Fix. Rev.: R$317.3MM/year

    CVU: R$103/MWh

    Auction: A-5/2007

    COD: Feb, 2013

    Itaqui

    Note: (1) Fixed revenues are indexed to inflation index IPCA (Database: Nov, 2013)

    Capaci

    Fix. Re

    CVU: R

    Auctio

    COD: O

    Coal Generation Portfolio Overview1.4 GW of installed capacity in full operation

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    6/22

    Parnaba II2 GE GTs x 168,8MW+ 1 GE ST x 181MW

    Parnaba I4 GE GTs x 168,8MW

    Parnaba III1 GE GT x 168,8MW

    + 1 Wrtsil GM x 7,3MWParnaba IV

    3 Wrtsil GMs x 18MW

    Capacity: 56MW

    46% efficiency

    Fix. Rev:R$54MM/year

    CVU: R$69/MWh

    Free market

    COD: Dec, 2013

    Capacity: 178MW

    38% efficiency

    Fix. Rev: R$98MM/year

    CVU: R$160/MWh

    Auction: A-5/2008

    COD: Dec, 2013

    Capacity: 676MW

    37% efficiency

    Fix. Rev: R$443MM/year

    CVU: R$114/MWh

    Auction: A-5/2008

    COD: Apr, 2013

    Parnaba IV Parnaba III Parnaba I

    Notes: (1) Bertin project developed by ENEVA; (2) Fixed revenues indexed to infl ation index IPCA (Database: Nov, 2013)

    Parnaba Complex OverviewA unique case in Brazil power generation sector with 910MW already in operation

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    7/22

    Outstanding management capabilities

    Financial strength and discipline

    Sector know-how: E.ON E&P looks at a volume delivery of +170k

    barrels/day and +60 licenses in GB and Norway

    Tried and tested Parnaba experience, know-how of Parnaba Complex

    rooted within PGN

    Strong Shareholders

    All Parnaba gas-fired power plants are supplied by Parnaba Gs Natural,

    owner and operator of 8 onshore exploration blocks

    ENEVA has a direct interest in PGN as key supplier of its TPPs

    Declaration of commerciality with Development Plan for 3 gas fields:

    Gavio Real, Gavio Branco and Gavio Azul

    Gas supply agreements secured for 8.4MM m/day

    R$250 million capital injection concluded in Feb, 2014

    Highlights

    Integrated Natural Gas E&PStrong competitive position in gas-fired generation

    Parnaba Gs Natural

    18.2%9.1% 72.7%

    Geographic Foo

    Note: 1) Ownership structure after execution of the sale and purchase agreement between OGP and Cambuhy, subject to approval by OGPs creditors, under its judicial recovery procedur

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    8/22

    Operating & Financial Performance of Power

    2

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    9/22

    Operating Costs

    Operational Performance (Itaqui)

    EBITDA (R$MM)

    Availability Variable Revenue X Variable Cos

    Sources: ONS & Company

    Higher unavailability offset lower operating costs

    1Q14

    Operating Costs1(R$ million) 121.0

    Gross Energy Generated (GWh) 583

    Operating Costs per GrossEnergy Generated (R$/MWh)

    207.7

    NOTE: 1) Does not include Depreciation & Amortization.

    63%

    83% 84% 87%

    75%

    62%

    1Q13 2Q13 3Q13 4Q13 1Q14 2Q14

    Availability reduction in 2Q14 due to mainly fan equipment and

    emissions control systems

    36.1-22.1

    5.50.6

    20.1

    EBITDA 1Q14 Net OperatingRevenues

    OperatingCosts

    OperatingExpenses

    EBITDA 2Q14

    261

    232

    144159

    128149

    112

    141

    108 10

    107 106 103 102 102 100 104 108 10711

    Variable Cost Gross

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    10/22

    Operational Performance (Parnaba I)

    EBITDA (R$MM)

    Availability Variable Revenue X Variable Cost

    Sources: ONS & Company

    OBS: Dispatch margin captured by Parnab

    Operating costs per MWh followed Henry Hub prices decrease and reflected lower unacosts

    NOTE: 1) Does not include Depreciation & Amortization.

    Operating Costs

    1Q14

    Operating Costs1(R$ million) 221.9

    Gross Energy Generated (GWh) 1,411

    Operating Costs per GrossEnergy Generated (R$/MWh)

    157.2

    N.A.

    91%97% 96% 99% 98%

    1Q13 2Q13 3Q13 4Q13 1Q14 2Q14

    44.8

    -20.625.3

    0.7

    50.3

    EBITDA 1Q14 Net OperatingRevenues

    OperatingCosts

    OperatingExpenses

    EBITDA 2Q14

    77 74 65 7580

    68 77 78 7479

    80 8294 99 100 96 93 99 95 92

    Variable Cost Gross V

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    11/22

    Operating Costs

    Operational Performance (Pecm I)

    Availability

    NOTES: 1) Figures consider 100% of Pecm I; 2) Does not include Depreciation & Amortization; 3) 1Q14 unavailability figure considers ONS review (previously

    Variable Revenue X Variable Cos

    Lower Operating Costs per MWh mainly offset by higher fuel and unavailability costs

    Sources: ONS & Company

    1Q14

    Operating Costs2(R$ million) 230.2

    Gross Energy Generated (GWh) 1,014

    Operating Costs per GrossEnergy Generated (R$/MWh)

    227.1

    EBITDA1(R$MM)

    72%

    41%

    66%

    51%

    83%3

    77%

    1Q13 2Q13 3Q13 4Q13 1Q14 2Q14

    48.8

    9.6

    -26.1

    0.3

    32.5

    EBITDA 1Q14 Net OperatingRevenues

    OperatingCosts

    OperatingExpenses

    EBITDA 2Q14

    71% 151127 118

    136154

    117

    139 138

    109119

    107

    111 105 104 100 99 99 97 102 105 106110

    Variable Cost Gross Va

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    12/22

    Operational Performance (Pecm II)

    Variable Revenue X Variable CostAvailability

    Sources: ONS & Company

    EBITDA negatively impacted by higher outsourced services and unavailability costs

    EBITDA (R$MM) Operating Costs

    1Q14

    Operating Costs (R$ million) 99.4

    Gross Energy Generated (GWh) 720.8

    Operating Costs per GrossEnergy Generated (R$/MWh)

    137.9

    N.A. N.A. N.A.

    85%97% 96%

    1Q13 2Q13 3Q13 4Q13 1Q14 2Q14

    46.3

    -7.1

    -6.0 0.3

    33.5

    EBITDA 1Q14 Net OperatingRevenues

    OperatingCosts

    OperatingExpenses

    EBITDA 2Q14

    NOTES: 1) Figures consider 100% of Pecm II; 2) Does not include Depreciation & Amortization.

    92 99111

    99 106

    114 118 122125 125

    Variable Cost Gross V

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    13/22

    Operating Costs

    Operational Performance (Parnaba III)

    NOTES: 1) Figures consider 100% of Parnaba III; 2) Does not include Depreciation & Amortization.

    Availability Variable Revenue X Variable Cost

    Sources: ONS & Company

    OBS: Dispatch margin captured by Parnab

    Operational dispatch adjustment impacted Operating Costs

    1Q14

    Operating Costs2(R$ million) 61.9

    Gross Energy Generated (GWh) 344

    Operating Costs per GrossEnergy Generated (R$/MWh)

    179.6

    EBITDA1(R$MM)

    N.A. N.A. N.A.

    100% 99%

    77%

    1Q13 2Q13 3Q13 4Q13 1Q14 2Q14

    14.4 -19.6

    -3.30.04

    -8.4

    EBITDA 1Q14 Net OperatingRevenues

    OperatingCosts

    OperatingExpenses

    EBITDA 2Q14

    75 71 69 69

    161 161 161 161

    Variable Cost Gross V

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    14/22

    Regulatory Update

    3

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    15/22

    Part of 1.4GW Parnaba Thermoelectric Complex, a unique gas

    to wirecase in Brazil

    450MWavg sold in the 2011 A-3 Auction. PPA started in March,

    2013

    Lowest variable cost (R$59/MWh) among gas-fired projects in

    Brazil

    Investments of up to R$1.4 billion

    All gas turbines already commissioned. Steam turbine to be fully

    tested on the coming 4 months

    Plantsconstruction and gas supply infrastructure delayed

    o Lack of LT financing due to PPA signature difficulties

    o OGX Maranho restricted financial capabilities before rescue plan

    captained by Cambuhy Investimentos and E.ON

    Project Overview

    Adjusted proposal presented to Aneel,

    o Completion of the construction of Parna

    o Postponement of PPAs start date to J

    whichever occurs first;

    o Penalty amounting to approx. R$310MM

    the term of Plants PPAs, through th

    revenues; and

    o Renewal of execution guarantees of R$6

    ENEVA proposed to Aneel to run a Parnaba Thermoelectric Complex byParnaba III and 2 gas turbines from

    from Parnaba II, as soon as it becomes

    Additionally, ENEVA commits to close up to 5 years, subject to certain condit

    o Sale of energy in the regulated market

    and

    o Availability of long-term financing for the

    ENEVA Proposal to Aneel

    Ongoing Regulatory Discussions (1)Parnaba II Delay

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    16/22

    Filed in Jan, 2014 a lawsuit against Aneel questioning

    hourly-based unavailability charges

    On Jan 24, 2014, a Federal Court granted an injunction

    halting unavailability charges as measured, establishing

    the methodology provided for in PPAs (60-month rolling

    average)

    The lawsuit also claims the reimbursement of amounts

    paid since PPAsbeginning

    Petition for revision of ADOMP methodology presented to

    Aneel

    o A technical note has already been released considering

    Companyscontractual understanding

    Itaqui and Pecm I

    On Jun 26, 2014 filed a request f

    Federal Court aiming to get tpresented to Aneel

    Pecm II and Parnaba I & III

    Plant 100%

    Itaqui R$105.2M

    Pecm I R$250.2M

    Pecm II R$38.9M

    Parnaba I R$52.2M

    Parnaba III R$6.9MM

    Total R$453.3M

    +R$310MM already paid for un

    Ongoing Regulatory Discussions (2)ADOMP / Unavailability Charges

    Notes: 1) Consider hourly-based methodology for unavailability charges until June, 2014; 2) Does not consider amounts paid since injunction effectiveness.

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    17/22

    Brazilian Power Market and Greenfield Por

    4

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    18/22

    Southeast Reservo

    ~70% of total storage ca

    Source: ANEEL

    Brazils Generation Capacity: 136 GW

    Breakdown by source April, 2014

    Brazil is highly dependent on hydro generation with increasingly faster depletion of re

    Brazilian Energy Matrix

    63.5%10.5%

    2.5%

    1.5%

    2.2%

    19.8%

    Hydro Gas Coal Nuclear Wind Others

    Dry Sea

    67%

    76%

    38%

    40%

    35%36%

    39%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    Jan Feb Mar Apr May Jun Jul

    Average 2007-2011 2012

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    19/22

    Source: ONS

    Autonomy = Storage Capacity / (Load Thermal Generation)

    Economic growth will boost

    leading to a supply defi

    Water storage capacity has stagnated,

    leading to decreased system autonomy

    65

    65

    60

    65

    70

    75

    80

    85

    90

    2013 2014 2015 2016 201

    GWavg

    2016-on: New generatio~8 GWavg required un

    Electric System ReliabilityNew thermal plants are necessary to guarantee reliable power supply

    0

    5

    10

    15

    20

    25

    30

    1970

    1972

    1974

    1976

    1978

    1980

    1982

    1984

    1986

    1988

    1990

    1992

    1994

    1996

    1998

    2000

    2002

    2004

    2006

    2008

    2010

    2012

    ReservoirsAutonomy(Months)

    2013

    Current reservoirautonomy ~6 months

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    20/22

    ParnabaComplex

    Integrated to natural gas resources

    Located in a tax-advantaged region

    Ventos WindComplex

    Located in one Brazilsbest wind resource areas

    Attractive load factor

    Just 30km from grid connection

    Land ownership assured

    Au(Coal + Gas)

    Located at a port with a regasification terminal buildlicense

    150km from Campos Basin natural gas accumulations

    Environmental licensed to both coal and gas operations

    Sul & Seival Integrated to the Seival Mine (proven reserves: 152 M ton)

    Low operation costs

    Power

    supply-demand

    unbalanced

    Hydropower

    concentrated

    matrix

    Spot prices at

    historical highs

    Demand for base-

    load generation2 3 4 51

    Sul727 MW

    ParnabaComplex

    2,166 MW

    Se600

    Solar 1 MW

    ENEVAs Greenfield PortfolioAttractive licensed greenfield projects in various development stages

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    21/22

    Disclaimer

    The material that follows is a presentation of general background information about ENEVA S.A. and its subsidiaries (collectively, ENE

    the date of the presentation. It is information in summary form and does not purport to be complete. No representation or warranty,

    concerning, and no reliance should be placed on, the accuracy, fairness, or completeness of this information.

    This presentation may contain certain forward-looking statements and information relating to ENEVA that reflect the current view

    Company and its management with respect to its performance, business and future events. Forward looking statements include, with

    that may predict, forecast, indicate or imply future results, performance or achievements, and may contain words like may, p

    expect, envisages, will likely result, or any other words or phrases of similar meaning. Such statements are subject to a numb

    assumptions. We caution you that a number of important factors could cause actual results to differ materially from the plans, object

    and intentions expressed in this presentation. In no event, neither the Company, any of its affiliates, directors, officers, agents o

    placement agents shall be liable before any third party (including investors) for any investment or business decision made or ac

    information and statements contained in this presentation or for any consequential, special or similar damages.

    This presentation does not constitute an offer, or invitation, or solicitation of an offer, to subscribe for or purchase any securities.

    Neither this presentation nor anything contained herein shall form the basis of any contract or commitment whatsoever.

    Recipients of this presentation are not to construe the contents of this summary as legal, tax or investment advice and recipients shou

    in this regard.

    The market and competitive position data, including market forecasts, used throughout this presentation were obtained from intern

    publicly available information and industry publications. Although we have no reason to believe that any of this information or these

    material respect, we have not independently verified the competitive position, market share, market size, market growth or other dat

    by industry or other publications. ENEVA, the placement agents and the underwriters do not make any representation as to the accurac

    This presentation and its contents are proprietary information and may not be reproduced or otherwise disseminated in whole or i

    written consent.

  • 8/11/2019 ENEVA Corporate Presentation ? August 2014

    22/22

    Thank you.www.eneva.com.br