Engaging Subcontractors Using NEC4 Contracts
Robert GerrardNEC Users’ Group Secretary
Ben WalkerNEC4 Drafter and Consultant
![Page 2: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/2.jpg)
2
Housekeeping
• Audio must be connected via your computer audio
• Please ask your questions through the questions tab in your control panel
• This webinar is recorded
![Page 3: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/3.jpg)
3
In today’s webinar we will discuss……
• Deciding on the best NEC4 subcontract• Preparing high quality NEC subcontract documents• Effective management of a Subcontractor
![Page 4: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/4.jpg)
4
Deciding on the best NEC4 subcontract
![Page 5: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/5.jpg)
3.2 Client Design under ECC
Client
ContractorECC
Subcontractor ECS or ECSS
SupplierSC or SSC
Dispute Resolver
DRSC
Consultant(designer)
PSC
SupervisorPSC or PSSC
Typical Client designed arrangement
Project Manager PSC or PSSC
![Page 6: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/6.jpg)
Client
Contractor ECC
Subcontractor ECS or ECSS
SupplierSC or SSC
Dispute Resolver
DRSC
Subcontractor(designer) PSS
SupervisorPSC or PSSC
Project Manager PSC or PSSC
Typical Design and Build arrangement
3.2 Design and Build under ECC
![Page 7: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/7.jpg)
7
Deciding on the best NEC4 subcontract
Approach similar to any contract strategy - consider the1. nature of the works or services,2. complexity and scale of the works or services,
![Page 8: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/8.jpg)
Intro to the NEC4 Engineering and Construction Contract V4 01/18 © 2017 NEC 8
![Page 9: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/9.jpg)
9
Deciding on the best NEC4 subcontract
Approach similar to any contract strategy - consider the1. nature of the works or services,2. complexity and scale of the works or services,3. flow down constraints (if any) from the main contract Scope and4. the 3 Rs: risk allocation, resourcing, reporting…
![Page 10: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/10.jpg)
10
What is important to the Contractor?• price certainty,• value for money or• a mix of both?
What are the Client’sobjectives?
What are the Contractor’sknown risks?
Which of these is it appropriate for the Subcontractor to carry?
![Page 11: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/11.jpg)
11
What resources do we have access to?
What contracting strategies and ‘Options’ do these open up?
How far can we empower these resources?
Are there governance issues or other local context that we need to allow for?
![Page 12: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/12.jpg)
12
How will we report on the contract? What’s expected by when?
Do we need to capture certain records in a particular way?
What format to receive and provide programme, forecasts, applications, CE quotations etc.?
What does Scope and Subcontract Scope say?
![Page 13: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/13.jpg)
13
Deciding on the best NEC4 subcontract
Consider synergies:• Best subcontracting strategy may be influenced by how the main
contract is setup and the resources already established for it.• Repetition and consistency likely to reduce overhead (e.g. not operating
two schedules of cost components)• Key dates (more on these later)
![Page 14: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/14.jpg)
14
Preparing high quality NEC subcontract documents
Use the applicable
Volume 2: User Guideon preparing your contract
[User Guides are for main contracts. A chapter deals with the differences between main and subcontract forms – they are applicable in every other respect.]
![Page 15: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/15.jpg)
15
Preparing high quality NEC subcontract documents
Example: Engineering and Construction Subcontract[Chapter 7 of User Guide, Volume 2 preparing an ECC]
• Terminology table• contract = subcontract
• Contract Data = Subcontract Data
• Completion Date = Subcontract Completion Date
• Subcontractor = Subsubcontractor
• Provide the Works = Provide the Subcontract Works
• language of the contract = language of the subcontract
![Page 16: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/16.jpg)
16
Preparing high quality NEC subcontract documents
Example: Engineering and Construction Subcontract[Chapter 7 of User Guide, Volume 2 preparing an ECC]
• Subcontract Data checklist• No main Option F, W3 or X22• The works, Client, Project Manager, Supervisor etc. should be the same as the
equivalent entries in the main contract• Subcontract Scope likely to comprise elements from the (main contract) Scope• period for reply – remember here the general differences in timings between main
and subcontracts to allow them to work together• and so on…
![Page 17: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/17.jpg)
17
Effective management of a subcontractor
Use the applicable
Volume 4: User Guideon managing your contract
[User Guides are for main contracts. A chapter deals with the differences between main and subcontract forms – they are applicable in every other respect.]
![Page 18: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/18.jpg)
18
Effective management of a subcontractor
Example: Engineering and Construction Subcontract[Chapter 1 of User Guide, Volume 4 managing an ECC]
• Terminology recap on works, starting date, Completion Date and Scope• Reinforces these are all prefixed ‘subcontract’ to avoid confusion• Subcontract time periods adjusted to allow for associated actions under the
main contract• Time limits for subcontractor sending information to Contractor reduced
• Time limits for decisions or payments increased
![Page 19: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/19.jpg)
19
Effective management of a subcontractor
![Page 20: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/20.jpg)
20
Align main and subcontract intervals for programme, early warning meetings, forecasts of Defined Cost and payment
Supervisor may attend tests and inspections
Slick notification of Defects
Consider use of a communication system / CDE
Project Bank Account
![Page 21: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/21.jpg)
21
Multi-contract projects are coordinated through use of Key Dates, by which stated conditions have to be met
If Contractor decides (25.3) work does not meet Condition stated for a Key Date by the date stated then
Additional cost in carrying out work, or paid to Client / Others
Is paid by Subcontractor
Optional – no obligation to use Key Dates
![Page 22: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/22.jpg)
22
Multi-contract projects are coordinated through use of Key Dates, by which stated conditions have to be met
If Contractor decides (25.3) work does not meet Condition stated for a Key Date by the date stated then
Additional cost in carrying out work, or paid to Client / Others
Is paid by Subcontractor
Optional – no obligation to use Key Dates
Key Date
Key Date
Key Date
![Page 23: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/23.jpg)
Questions?
![Page 24: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/24.jpg)
![Page 25: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/25.jpg)
25
![Page 26: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/26.jpg)
![Page 27: Engaging Subcontractors Using NEC4 Contracts...1. nature of the works or services, ... • Best subcontracting strategy may be influenced by how the main contract is setup and the](https://reader030.vdocument.in/reader030/viewer/2022040908/5e8019e7a0b0502bbe56ade9/html5/thumbnails/27.jpg)
Contact us +44 (0)20 7665 2446 [email protected] Great George Street, London SW1P 3AA
• neccontract.com