engineering and commercial infrastructure - transport ...€¦ · achieved. specific attention has...

13
1 [Type the document title] Engineering and Commercial Infrastructure - Transport & Drainage Monthly Review December 2017 - January 2018

Upload: others

Post on 19-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

1  [Type the document title] 

Engineering and Commercial Infrastructure -

Transport & Drainage

Monthly Review December 2017 - January 2018

Page 2: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 2

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

OVERVIEW ............................................................................................................................. 3 

SAFETY ................................................................................................................................ 4 

1.1.  Incidents and Injuries .................................................................................................. 4 1.2.  Lost time Injuries & Days Lost ..................................................................................... 5 

FINANCE .............................................................................................................................. 6 

2.1.  Operational Financial Report - 1 July 2017 - 31 January 2018 ................................... 6 

MAINTENANCE ACTIVITIES ......................................................................................... 7 

3.1  Road and Drainage Maintenance Activities ................................................................ 7 3.2  Unsealed Road Maintenance Activities ....................................................................... 7 3.3  Open Drainage Maintenance ...................................................................................... 8 3.4  Cyclone Debbie – REPA Repairs ................................................................................ 9 3.5  Bridge Management .................................................................................................. 10 

CLIENT SURVEYS .......................................................................................................... 11 

4.1  Requests for Maintenance Work ............................................................................... 11 

Projects ............................................................................................................................. 12 

5.1  Significant Projects .................................................................................................... 12 

 

Page 3: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 3

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

OVERVIEW

This report is for Transport and Drainage activities during the months of December 2017 and January 2018. Significant items in this period include:

There was one LTI recorded in January 2018 where a foot injury occurred as a result of a wacker packer

Businesses Cases are being prepared for the Transport and Drainage Advisory Board's first meeting for 2018

The Region’s schools were notified of a Program of Works for School’s Project commencing - schools notified of works to be completed over 3 years

Significant progress has been made with maintenance grading in conjunction with NDRRA unsealed road repairs. The Central Area Maintenance Grading Team is up-to-date with programmed works and has been assigned to the Southern Area to assist with the delivery of works.

Works on the Capital Program are continuing to be a focus for the Civil Projects Team to deliver the amended capital budget

A review of the Transport and Drainage structure based on the new Capital Directorate is being undertaken to assess how resources will be allocated between the Directorates

Previous advice had been provided in relation to the delayed delivery of finalised Terrestrial LIDAR data. Veris (formerly RPS) had been engaged via tender to generate and provide this data and product, however, ongoing accuracy tolerance issues had been experienced in data provided. Council staff had rejected the data provided as unsuitable and outside required tolerances when undertaking Quality Assurance Assessments of the data provided. While delays are considered unacceptable, the provided product for the 42 survey zones covering all residential and rural residential areas within the LGA now meets accuracy tolerances which will enable flood and drainage study modelling and all other purposes to be undertaken with a high level of confidence in the collected data.

Director Engineering & Commercial Infrastructure  

Page 4: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 4

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

SAFETY

1.1. Incidents and Injuries

The incident statistic details a summary of the Transport and Drainage safety incident performance. Transport and Drainage aspires to achieve zero harm with a stretch target of zero injuries

December 2017 - January 2018 Summary:

No. of Incidents

Mechanism of injury Injury Type

1 Rollover Fatality

3 Exposure to heat Near miss

9 Vehicle Incident Near miss

1 Being hit by moving objects

Lost time injury

1 Being hit by moving objects

Non treatment injury

1 Being hit by moving objects

First aid injury

2 Being hit by moving objects

Near miss

2 Falls from a height First aid injury

1 Muscular stress Non treatment injury

4

6

9

2

4

7

16

6

9

7

54

15

0 0 0 0 0 0 0 0 01 1

01

01

0 0 0

2 21

0

3

10

10

12

0 0

4

6

1

43

21

5

0

2

4

6

8

10

12

14

16

18

Total Incidents Lost Time Injuries Total Recordable Injuries All Injuries

Page 5: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 5

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

1.2. Lost time Injuries & Days Lost

Transport and Drainage aspires to achieve zero Lost Time Injuries by improving safety performance by developing a proactive safety culture and implementing best practice safety management across all business areas

November Summary:

One (1) Lost Time Injury was sustained in January 2018. The Officer was struck on top of the right foot with a wacker packer. The table below shows the Lost Time Injuries over previous years. There has been three LTI’s recorded in the first three months of the FY so there has been a strong focus in meeting with staff and reinforcing the safety outcomes focus for all employees.

 

 

 

 

 

 

61

233

158

0

21

4

11

5

0

3

0

2

4

6

8

10

12

0

50

100

150

200

250

2013‐14 2014‐15 2015‐16 2016‐17 2017‐18

TADAB Total Days Lost TADAB Total LTIs

Page 6: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 6

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

FINANCE

2.1. Operational Financial Report - 1 July 2017 - 31 January 2018

 

 

 

 

 

The Transport & Drainage operational budget continued to track in-line with the YTD budget for the first seven months of the financial year due to wages and plant being utilised for NDRRA and Works for Queensland (W4Q) projects.

The final Roads Improvement Rates Levy income was received during the month of January 2018 and this has also contributed to the budget surplus shown as at 31 January 2018.

Page 7: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 7

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

MAINTENANCE ACTIVITIES

3.1 Road and Drainage Maintenance Activities

The following chart details maintenance activities completed during the period as recorded in DeltaS, our electronic Maintenance Management System (MMS).

3.2 Unsealed Road Maintenance Activities

During the period, medium formation grading works were undertaken on some roads to address the significant backlog of roads meeting the intervention level, allowing more roads to be graded prior to the Christmas break.

1024

12 7 4 13 617 17 8 6 6 11

34

138

237

1427 30

50

50

100

150

200

250

December ‐ January Completed Works

3.40 

22.50 

38.50 

17.40 13.20 

 ‐ 5.00

 10.00 15.00 20.00 25.00 30.00 35.00 40.00 45.00

NDRRA REPARepairs

Heavy FormationGrading

Medium FormationGrading

Roadside Drainage Shoulder Grading

December ‐ January Unsealed Road Maintenance

Kl of 

road 

graded 

Completed 

works 

orders 

Page 8: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 8

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

3.3 Open Drainage Maintenance

Drainage crews worked through the Christmas Closedown Period to continue the essential maintenance on the open drains network. Coupled with the favourable weather, considerable work outcomes were achieved. Specific attention has been given to high visibility drain areas.

100 ha of drainage mowing was completed during the December 2017 – January 2018 period.

Works on repairing and cleaning the stormwater pipeline that runs from Baxter Drive to the concrete drain outlet beside Emmanuel and Holy Spirit Schools is work in progress. It was initially suspected that there was a conflict with a sewer pipe contributing to the stormwater flow restrictions, however, excavation revealed that the sewer pipe was installed directly below the stormwater. Significant root intrusions were removed.

Page 9: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 9

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

3.4 Cyclone Debbie – REPA Repairs

Category B

The last submission under Category B has been forwarded to QRA for assessment and approval. This submission, for works value of $2.2M, primarily covers restoration works for landslips on Mt Blackwood Access Road, Chelmans Road and Dalrymple Road.

The grading and gravelling of the Unsealed Road Network is continuing. These works are being undertaken in conjunction with routine maintenance works. Drainage repairs have also been completed on Mark Andrew Terrace and on Tara Creek Road in Sarina.

The only other outstanding submission, mainly for restoration works on sealed roads, has received preliminary approval from QRA. Final approval should be received in mid-February 2018.

The tenders for Sichter Street have been assessed and will be awarded mid-February 2018. The lowest tenderer has indicated that works will be completed by the end of April 2018.

Category D

Detailed design on two of the three proposed Betterment Projects (Sievers Road in Oakenden and Hinton Road, Koumala) is continuing and will be completed in February 2018. The design for Graham Road has been completed.

It is planned to commence work on Sievers Road at the end of February 2018, Hinton Road in April 2018 and Graham Road in July 2018.

Approval has been received for restoration works, to pre STC Debbie condition, on beaches at Grasstree Beach, McEwens Beach, Blacks Beach, Cape Hillsborough, Ball Bay, Haliday Bay, Seaforth and Midge Point. The value of these works is $2.3M and is in addition to the earlier approval for works on Lamberts Beach, Cape Hillsborough Beach and Armstrong Beach totalling $1.0M.

Council’s application for further works, totalling $4.6M, at Midge Point and Lamberts Beach to restore the beaches to their condition 10 years ago, and at St Helens Beach to strengthen the existing groynes, is being assessed by QRA and would be funded by the State Government separate to NDRRA.

Quotation documentation has been prepared to engage an Engineering Consultant to undertake the detailed design of the works at Lamberts Beach and Midge Point. It is anticipated that these works will be completed by September 2018. The works at the other beaches will be undertaken between April 2018 and August 2018.

Page 10: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 10

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

3.5 Bridge Management

Rehabilitation/strengthening works on the Head-Vassallo Road Bridge is now complete. A 2-coat seal was laid on 24 January 2018 to complete the project.

Planning of rehabilitation works on Bell Creek Bridge on Munbura Road is in progress with preliminary works to be completed prior to April 2018 and the major works scheduled for completion prior to end of June 2018. These works predominately involve replacement of piles and girders.

Page 11: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 11

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

CLIENT SURVEYS

4.1 Requests for Maintenance Work

Civil Operations Results of Survey Nov'17 - Dec'17)

Representative Comments Trends

Very good.

Excellent.

I was not contacted about my request.

This was a weekend callout and the service provided was both prompt and successful.

Job was done within 4 days. Very neat job. The operator did a great job

under Charlies guidance. Incomplete.

Efficient.

Thank you, Mackay Regional Council, for your prompt attendance to the safety issue that I addressed in my email to you recently. I am new to the Mackay region and really happy with the quick response to my email.

Needs to be attended to much quicker.

Very friendly and helpful.

1

2

3

4

5

Jan‐Feb Mar‐Apr May‐Jun Jul‐Aug Sep‐Oct Nov‐Dec

V. P

oor               V

. Good

Overall rating trends

2015 2016 2017

Target

Page 12: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 12

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

PROJECTS

5.1 Significant Projects

Significant Projects are assessed considering the Project Cost, the Project Risk and/or Community Interest. The following information was current as of Friday, 2 February 2018.

Council Project Management Phases

1. Planning (Plan) 2. Design (Des) 3. Procurement (Proc) 4. Construction (Con)

Indicators

On Track Potential Issue Definite Issue

PROJECT PHASE PHASE %

COMPLETE INDICATORS

ORIGINAL BUDGET DETAILS

COMMENTS

Land Acquisition and Drain Construction Ferris Gully

Con 65%

Schedule

Scheduled Completion Date:

August 2018

Original Budget:

$6.7M (over multiple years)

Excavation of the drainage works are approximately 90% completed. Drainage works are well over schedule due to poor ground conditions. The planting of the environmental drain is programmed to commence in April after the wet season (approx. value $2M)

Budget

Other Issues/Risk

Vincent Street Con 100%

Schedule Schedule

Completion date: December 2017

Original Budget:

$779K

Works were completed in December. Over budget due to unsuitable subgrade material. Additional scope added at the English street entrance to repair existing seal and footpath.

Budget

Other Issues/Risk

Pioneer River – Nelson Street Levee Repairs

Con 40%

Schedule Scheduled

Completion Date:

January 2018

Original Budget:

$1.45M

Rock works are 90% complete. Footpath and drainage works are in progress with early March completion date. Schedule has been affected by changes to water infrastructure and delivery time of class 4 stormwater pipes.

Budget

Other Issue/Risk

Page 13: Engineering and Commercial Infrastructure - Transport ...€¦ · achieved. Specific attention has been given to high visibility drain areas. 100 ha of drainage mowing was completed

 

 

Page 13

Engineering & Commercial Infrastructure Monthly Review > December 2017 - January 2018

Glenella Connection Road

Con 90%

Schedule Scheduled

Completion Date:

October 2017

Original Budget:

$1.9M

Works are now completed. Minor repairs required to the pedestrian bridge.

Delivered under budget and time for original scope. Pedestrian bridge additional scope.

Budget

Other Issues/Risk

Armstrong Beach Road Rehabilitation

Con 100%

Schedule

Scheduled Completion Date:

December 2017

Original Budget:

$0.7M

Works complete. 2 sections completed – approach to Armstrong Beach township and area near Railway yard lookout.

Budget

Other Issues/Risk

Cape Hillsborough

Con 5%

Schedule

Schedule Completion date: June 2018

Original Budget:

$2.2M

Works have commenced on widening and strengthening the narrow section on Cape Hillsborough road.

Budget

Other Issues/Risk

Ferries Terrace Con 5%

Schedule

Schedule Completion date: May 2018

Original Budget:

$586k

Retaining wall and gabion wall construction and watermain works commencing in February.

Budget

Other Issues/Risk