engineering law

Upload: danial-zaman

Post on 08-Oct-2015

14 views

Category:

Documents


0 download

DESCRIPTION

Engineering Law

TRANSCRIPT

  • 2014-01-05

    1

    LAW AND ETHICS IN ENGINEERING PRACTICE

    Nov 2010

    (CEN 800)

    FACULTY OF ENGINEERING AND APPLIED SCIENCE

    RYERSON UNIVERSITY

    A2G: 1196343v7

    HOW IS THE LAW APPLICABLE TO ME?

    Gas Fired Power Project Gas Fired Power Project Project Management Civil Electrical Mechanical

    Computer Computer Aerospace Industrial

    Complex Contractual Arrangements

  • 2014-01-05

    2

    COURSE OUTLINE Canadian Legal System Business Organizations Torts Torts Contracts Security for Payment Bonds and Performance Guarantee Lien Legislation Consulting/Construction Agreementsg g Insurance Intellectual Property Alternate Dispute Resolutions

  • 2014-01-05

    3

    CANADIAN LEGAL SYSTEMB d E li h C L Based on English Common Law Equity Common Law

    Theory of Precedent Basis of Predictability Apply Legal Principles Established in Previous

    Court Decisions Factual Distinctions and Equitable Relief Provide

    for Flexibility

    CATEGORIES OF LAW Common Law Common Law

    Judge Made Legislative

    Government-Made codification of existing common law or enactment of new law

    Federal Federal Provincial Municipal

    Statutes are Supplemented by Regulations Theory of Precedent

  • 2014-01-05

    4

    JURISDICTION BETWEEN FEDERAL AND PROVINCIAL

    GOVERNMENTS Parliamentary Supremacy

    British North America Act 1867 S#91 Federal Jurisdiction S#92 Provincial Jurisdiction

    Ultra Vires

    JURISDICTION BETWEEN FEDERAL AND PROVINCIAL

    GOVERNMENTS (contd)( ) Constitution Act, 1982 and Charter of Rights

    and Freedoms Guarantees Fundamental Freedoms Constitution is Supreme Law Reduced Effect of Parliamentary Supremacy

    Reasonable Limits S#33 Override

  • 2014-01-05

    5

    COURT SYSTEMHOUSE OF

    LORDSOther - 1949SUPREME COURT

    OF CANADA LEAVE REQUIRED

    Criminal - 1933

    B.C. ONTARIO COURT OF APPEALALBERTA

    FEDERAL COURTOF APPEAL

    DIVISIONALCOURT

    FEDERALCOURT

    -PATENTS-TRADEMARKS-COPYRIGHT COURT

    OF ONTARIOSUPERIOR COURT OF JUSTICE ONTARIO COURT OF JUSTICE

    SMALL CLAIMS COURT

    COPYRIGHT

    -maximum of $25,000

    (6 Peopleon Jury) Criminal Family(12 People on Jury) Provincial Offences

    COURT PARTICIPANTS Original Trial Original Trial

    Plaintiff Defendant

    Appeals Appellantpp Respondent

  • 2014-01-05

    6

    CIVIL COURT CASE PROCESS Issue Statement of Claim (Plaintiff) Issue Statement of Claim (Plaintiff) Respond with Statement of Defence

    (Defendant) Discoveries

    DocumentsDocuments Oral

    Trial

    BUSINESS ORGANIZATIONS Corporation Corporation

    Share Capital Non-Share Capital

    Partnership General Limited Liability

    Sole Proprietorship Unlimited Liability Company

  • 2014-01-05

    7

    SALOMON V SALOMON & CO. LTD.1897 HOUSE OF LORDS

    MR. SALOMON MRS. SALOMON SON SALOMON

    SALOMON & CO. LTD.LOAN

    SECURED

    MATERIAL SUPPLIER

    MATERIAL SUPPLIER

    UNSECURED CREDITORS

    Issue: Did Mr. Salomon rank before the Unsecured Creditors by virtue of being a secured Debenture Holder?House of Lords recognized Salomons Corporation as a separate and distinct entity from himself there was no evidence of intent by Salomon to deceive or defraud.

    FERN BRAND WAXES LTD. V PEARL1972 ONTARIO COURT OF APPEAL

    PEARL (DIRECTOR OFFICER &(DIRECTOR, OFFICER &ACCOUNTANT OF FERN)

    CO#1 CO#2

    - Pearl transferred unauthorized funds to 2 companies controlled by him by loaning them monies from Fern Brand.

    - Some of the funds were used to purchase shares in Fern Brand Waxes Ltd.

    FERN BRAND WAXES LTD.

    - Court stated that the Defendant should not be allowed to profit from his breach of trust.

  • 2014-01-05

    8

    LIMITED PARTNERSHIPPARTNER #1 PARTNER #2

    GENERAL PARTNER

    CORPORATION

    SHAREHOLDERS

    1%PARTNERSLIMITED

    PARTNERSHIP

    49.5% 49.5%1%

    NON DISTINCT TYPES OF BUSINESS ORGANIZATIONS

    Joint Venture Joint Venture Consortium

  • 2014-01-05

    9

    CONSIDERATIONS IN SELECTING A BUSINESS ORGANIZATION

    Duration Duration Simplicity/Complexity Taxes

    Canadian Controlled Private Corporation (CCPC)( )

    Liability Separate Identity

    CONSIDERATIONS IN SELECTING A BUSINESS ORGANIZATION

    (contd)(cont d) Personal Guarantees Property Ownership Registrations

  • 2014-01-05

    10

    CORPORATIONS Articles of Incorporation/Letters Patent Articles of Incorporation/Letters Patent Jurisdiction of Incorporation Objects By-laws

    R l ti Resolutions Public vs. Private

    CORPORATIONS (contd) Participants Participants

    Shareholders Directors Officers Employees

  • 2014-01-05

    11

    DIRECTORS AND OFFICERS DUTIES

    Manage the Corporation Manage the Corporation Act honestly and in good faith In best interests of corporation Exercise the care, diligence and skill that a

    reasonably prudent person would exercise in a comparable circumstance

    GLOBAL CONSIDERATIONS Form of Business Organization Form of Business Organization Political Risks Foreign Legal Systems Licensing Requirements

    Fi i l Ri k Financial Risks Contract Forms

  • 2014-01-05

    12

    SECURITY OF PAYMENT AND PERFORMANCE

    Bonds Bonds Letters of Credit Guarantees Subcontractor Default Insurance

    Bonds guarantee by a surety that contractor will guarantee by a surety that contractor will

    perform obligations not insurance bonding company will seek compensation

    from contractor Contractors shareholders usually provide

    guarantees

  • 2014-01-05

    13

    Types of Bonds Bid Bond Bid Bond

    forfeited if Contractor fails to enter contract Performance Bond

    guarantees to owner that contract will be performed

    L b d M t i l P t B d Labour and Material Payment Bond guarantees payment to subcontractors and

    suppliers

    BONDING RELATIONSHIPOWNER

    EQUIPMENTSUPPLIER

    SURETY(BONDING

    CO )AGREEMENTINDEMNITY

    BOND

    CO.)SUB-

    SUPPLIER

  • 2014-01-05

    14

    Letters of Credit More common outside of Canada More common outside of Canada May be close to a blank cheque Usually affect contractors credit capacity Often referred to as Performance

    Guarantees in international workGuarantees in international work

    LETTER OF CREDIT

    LETTER OF CREDIT

    OWNER

    EQUIPMENTSUPPLIER

    AGREEMENT

    BANK SUB-SUPPLIER

    AGREEMENT

  • 2014-01-05

    15

    GUARANTEE

    GUARANTEEOWNER

    EQUIPMENTSUPPLIER

    PARENTCOMPANY

    SUB-SUPPLIER

    CONSTRUCTION LIEN ACT Lien Lien Holdback -10% Trust Provisions Priority of Mortgages

  • 2014-01-05

    16

    $

    Time SubstantialPerformance

    Substantial Performance Two Part Test Two Part Test

    1. the work must be ready for the purpose intended (the Qualitative Test)

    2. the cost of completing incomplete items and rectifying known defects must be less than an amount calculated as:

    ) 3% f h fi $500 000 f C P i la) 3% of the first $500,000 of Contract Price, plusb) 2% of the next $500,000 of Contract Price, plusc) 1% of the remainder of the Contract Price

    (the Quantitative Test)

  • 2014-01-05

    17

    EXAMPLEContract Price = $3 500 000Contract Price = $3,500,000

    Quantitative Calculation:3% of $500,000 = $15,0002% f $500 000 $10 0002% of $500,000 = $10,0001% of 2,500,000 = $25,000

    $50,000

    $

    Sub Perf. Publication of the Certificate of Sub Perf.

    45 days

    TIME

  • 2014-01-05

    18

    $

    Sub Perf.TIME Completion

    COMPLETIONThe completion of incomplete items andThe completion of incomplete items and rectification of known defects is less than the lesser of:

    1) $1,0002) 1% of the Contract Price) % C

  • 2014-01-05

    19

    $

    CompletionSub Perf

    TIME

    45 days

    Owners Questions How much input does the owner wish to

    have in the design of the project? Is the owner interested in a unique design or

    one that will be relatively generic? Is the completion date of the project critical

    h ?to the owner? Is overall cost critical to the owner?

  • 2014-01-05

    20

    Owners Questions (contd) How experienced is the owner? How risk adverse is the owner? Does the owner have its own in-house

    administrative staff? Are there performance guarantees that are

    important to the owner?important to the owner? How is the project being financed? Is there any equipment that has a long lead

    time for delivery?

    Owners Questions (contd) Are there particular designers, equipment

    suppliers or trade contractors that the owner wishes to utilize?

    How much construction experience does the owners consultant have?Will h i i Will the owners expectations require unique construction experience?

  • 2014-01-05

    21

    Project Structures Traditional project structure Construction management project structure Contractor/construction manager project

    structure Multi-designers project structure Engineering, procurement and construction

    management (EPCM) project structure Design/build project structure

    TRADITIONALOwner Consultant

    Contractor Sub Consult Sub Consultant

    Sub #1 Sub #2

  • 2014-01-05

    22

    Advantages of the Traditional Project Structure

    Single point responsibility of the Single point responsibility of the consultant and contractor

    The owner can keep its involvement fairly limited

    Easier to acquire a fixed price from the t tcontractor

    Cooperative relationship between the owner and the consultant

    Advantages of the Traditional Project Structure (contd)

    The number of contractor initiated change The number of contractor initiated change orders which affect the price should be relatively limited

    The consultant and the contractor bear any risks of non-performance of the subconsultants and the subcontractors, respectively

  • 2014-01-05

    23

    Disadvantages of the Traditional Project Structure

    Not conducive to fast-trackingg Until prices are received from contractors

    pursuant to the tendering procedure, the owner is not fully aware of its final costs

    Not conducive to having input from the contractor during the designcontractor during the design

    If the project fails to perform in accordance with the owners expectations, it is necessary to assess responsibility between the consultant and the contractor

    CONSTRUCTION MANAGEMENT

    C lt t O Construction Consultant Owner Manager

    Trade #1 Civil Trade #2 Mech Trade #3 Elec

  • 2014-01-05

    24

    Advantages of the Construction Management Project Structure

    Very conducive to fast-trackingy g Because the construction manager is not taking

    on any direct liability for the trade contractors, the construction managers fee does not need to incorporate any risk with respect to the particular trade contractorsp

    The construction manager can be retained early in the design development process and provide very advantageous construction advice during the design.

    Disadvantages of the Construction Management Project Structure

    Because the construction manager does not have Because the construction manager does not have privity of contract with the trade contractors, not only does the owner not have the advantage of looking to the contractor as the party with single point responsibility, but the construction manager does not have the same level of control over such trade contractors

  • 2014-01-05

    25

    Disadvantages of the Construction Management Project Structure

    (contd) The ultimate cost to be paid by the owner will The ultimate cost to be paid by the owner will

    not be determined until such time as the last component of work is tendered for construction

    Pursuant to the Occupational Health and Safety Act, once the owner enters into more than one contract for the construction of a project, the owner becomes the constructor

    CONTRACTOR/CONSTRUCTION MANAGEMENT

    Owner ConsultantOw e Co su

    Contractor/ConstructionManager

    Sub #1 Sub #2 Sub #3

  • 2014-01-05

    26

    Advantages and Disadvantage of the Contractor/Construction

    Management Project Structure Advantages

    The contractor/construction manager becomes involved in the project very early in the design process

    Conducive to fast-trackingConducive to fast tracking Disadvantage

    It may not be possible to seek a fixed price at the time of retaining the contractor/construction manager

    Diagram #4Multi-Designer Project Structure

    Owner A hi

    General Contractor

    Architect

    StructuralEngineer

    MechanicalEngineer

    ElectricalEngineer

  • 2014-01-05

    27

    Advantage and Disadvantage of the Multi-Designer Project Structure

    Advantage Advantage Since no one particular designer takes on the

    responsibility or liability for all other designers, the cumulative fees payable to all designers should be lower than those payable to a single designer

    Disadvantage Requires the owner to assume overall

    coordination responsibilities

    Diagram #5Engineering, Procurement and

    Construction Manager StructureOwner Engineer/

    ConstructionManager

    Prime Contractor

    Prime Contractor Supplier

  • 2014-01-05

    28

    Advantage and Disadvantage of the Engineering, Procurement and Construction

    Management Project Structure Advantage

    One entity takes an active role in both the design and construction of the project

    DisadvantageAs is the case in the construction management project As is the case in the construction management project structure, the EPCM party is usually only an agent of the owner and as such does not take on any direct liability for the trade contractors or equipment and material suppliers

    Diagram #7Design/Build Project Structure

    OwnersOwner s Consultant Owner

    Design/Builder

    Consultant

  • 2014-01-05

    29

    Advantages of the Design/Build Project Structure

    Where time of delivery performance or Where time of delivery, performance or output of the project is critical to the owner, single point of responsibility makes one person responsible for such matters

    Conducive to fast-tracking

    Advantages of the Design/Build Project Structure

    The designer and the contractor work The designer and the contractor work together as a team

    The single point of responsibility is important to lenders in project financing projects

  • 2014-01-05

    30

    Disadvantages of the Design/Build Project Structure

    It is very difficult to adequately and fully define th f th d i /b ild bli ti ithe scope of the design/builders obligations prior to the design being completed

    Price for the design and construction of a project cannot realistically be determined with precision until the design is finalizeduntil the design is finalized

    The designer will no longer have the same interest in satisfying the owners expectations if those expectations will result in additional construction costs to the design/builder.

    Forms of Contract Stipulated Price Stipulated Price Unit Price Cost Plus

    Cost Plus Percentage Cost Plus Fixed FeeCost Plus Fixed Fee Cost Plus Lump Sum Bonus

    Guaranteed Maximum Price plus Share of Savings

  • 2014-01-05

    31

    Unit Price often found in excavation and municipal often found in excavation and municipal

    servicing contracts use where quantity of work is not well

    defined defined method of measurement is essential

    Cost - Plus more appropriate where design is not more appropriate where design is not

    complete other situations where significant

    uncertainties exist bonus arrangements may provide incentive g y p

    to reduce costs

  • 2014-01-05

    32

    Guaranteed Maximum Price Hybrid between Stipulated Price and Cost Hybrid between Stipulated Price and Cost

    Plus plus Share of Savings adds incentive to

    reduce costs design must be reasonably completeg y p

    Insurance1) Property) ope ty2) Liability3) Errors & Omissions

    Professional Liability- Cap of Limit- Deductibles- Exclusions (i.e., Liability excludes faulty workmanship and faulty design)

  • 2014-01-05

    33

    Intellectual Property Patents of Invention Patents of Invention Trademark Passing Off Copyright

    I d t i l D i Industrial Designs Trade Secrets

    Patents of Invention Inventions must be

    New and useful art, process, machine, manufacture or composition of matter

    Novel Reduced to something physical/tangible

    Term: 20 years from date of application Patent rights can be assigned to others or used

    under a license agreement Exclusive right to use or license the invention Can be assigned

  • 2014-01-05

    34

    Patents of Invention (contd) Is it the employers invention or the

    l ?employees? Remedies

    Damages sustained by patent holder Injunction Recovery of profits obtained by infringer

    Trade-mark Used to distinguish wares or services manufactured,

    sold, leased, hired, or performed by someone from those of others

    Owner has exclusive right to use trade-mark Mark must be distinctive Registered trade-marks are effective for a period of

    15 years: can be renewed for unlimited 15-year periodsCan be licensed Can be licensed

    Remedies Restraint on future use Liable for damages

  • 2014-01-05

    35

    Passing Off A type of legal action against someone who

    t d k i il t d k tuses your trade-mark or a similar trade-mark to yours

    Unregistered trade-mark You must show that customers purchase from

    someone else because they mistakenly believe h h d li i hthat they are dealing with you

    Remedies Restraint on future use Liable for damages

    Copyright Subsists in original literary, dramatic, musical,

    artistic work, communication signals, sound recordings, performances

    Right to produce or reproduce something; perform and deliver it in public; publish

    Term: life of the author + 50 years Includes engineering plansc udes e g ee g p a s Assignment must be in writing moral rights: right of identification as author,

    integrity of the work (i.e., Eaton Centre art)

  • 2014-01-05

    36

    Industrial Designs Designs (shape, pattern, ornament) that are

    ornamental or aesthetic in nature Not mechanical construction or method of

    manufacture Design must be novel and original Term: exclusive right to use design for 10 years g g y

    from registration Assignment must be in writing

    Trade Secrets Formula , pattern, device, compilation of info

    used in ones business which gives advantageused in one s business, which gives advantage over competitors, i.e., formula for a chemical

    Some rely on this as opposed to patents Legal action:

    Show info was confidential Show secret information was communicated to the Show secret information was communicated to the

    person at fault in circumstances implying a duty of confidence

    Degree of secrecy Duty of confidence: employer and employee

  • 2014-01-05

    37

    Dispute Resolution1. Partnering Dispute Avoidance. a t e g spute vo da ce2. Negotiation3. Dispute Review Boards4. Mediation5. Arbitration

    a) Mandatoryb) Binding

    6. Private Court7. Litigation

    Mediation Independent third party attempts to bring Independent third party attempts to bring

    parties together Very useful if all parties want to settle

  • 2014-01-05

    38

    Characteristics of Arbitration Choose the tribunal may be expert if Choose the tribunal - may be expert if

    desired May be quicker and cheaper Less public Usually binding Usually binding Parties must agree to participate and be

    bound by decision

    Arbitration Agreements usually a clause in a larger contract usually a clause in a larger contract may be a stand alone agreement agreement should define:

    arbitrator(s) - number, identity, qualifications, how chosen

    rules and procedure timing

  • 2014-01-05

    39

    Arbitration Act Philosophy to encourage arbitration Philosophy to encourage arbitration Courts must almost always enforce

    arbitration agreements Rights of appeal are limited prevents arbitration being simply a delaying prevents arbitration being simply a delaying

    tactic

    ADR on International Projects Arbitration Clauses usual Arbitration Clauses usual in Ontario the International Commercial

    Arbitration Act applies provides even less flexibility to courts to

    intervene Contracts encourage non-binding ADR

    methods