Enhanced Curtailment Calculator (ECC)Task Force

Joint Guidance Committee

Presentation and Motion to the OC & MICStanding Committee Meetings

March 27-29, 2012

Page 2: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

2

ECC Task Force Members

OC - Brenda Ambrosi – BC Hydro OC - Carl Dobbs – WAPA CA OC - David Lunceford - CAISO

MIC - Raj Hundal – Powerex MIC - David Lemmons – Xcel (Vice Chair) MIC - Doug Reese – Tri-State

WECC RC - Linda Perez (Chair) WECC RC - Jeff Sundvick (acting Chair)

Enhanced Curtailment Calculator, ECC

Page 3: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

3

o The MIC and the OC support the investigation into the development of an ECC tool with the following capabilities and associated budget estimate:  The ability to unload overloaded BES elements. The ability to identify every significant contributor to

BES facility or path loading, including contributing schedules and contributing generation.

The ability to be predictive in nature. The ability to integrate load and generation forecasts

into the solutions.

ECC Task Force Motion

Page 4: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

4

(Cont)

The ability to calculate Power Transfer Distribution Factors (PTDFs) and Outage Transfer Distribution Factors (OTDFs) based on real-time conditions.

- The creation and seamless integration with a centralized outage management tool.

The ability to add system elements as needed in real-time for analysis and possible mitigation.

The ability to ensure Transmission Priority is used in conjunction with TDFs for schedule curtailments.

The ability to incorporate sub-hourly schedules.

ECC Task Force Motion

Page 5: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

5

Objective

The ECC project seeks to improve the wide-area view of Reliability Coordinators (RCs) in the Western Interconnection such that they better understand the current operating state of the bulk electric system and are better equipped to assign relief obligations during periods of transmission congestion that are more representative of those actually contributing to the congestion.

Enhanced Curtailment Calculator, ECC

Page 6: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

6

Problem Statement

The ECC project was initiated in response to WECC members seeking to improve the tools used by the RCs to monitor the operation of the Bulk Electric System and thereby ensure reliability for the interconnection. The area identified as needing improvement is the ability to identify and then take appropriate actions to reduce loading on facilities when the facilities are at or very near their System Operating Limit (SOL).

Enhanced Curtailment Calculator, ECC

Page 7: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

7

Problem Statement (cont.)

The current congestion tool, webSAS, is only used to calculate curtailment responsibility on six Qualified Transfer Paths. It does not calculate tag curtailments with respect to transmission priority, account for sub-hourly or untagged schedules, determine generation for potential redispatch, or calculate distribution factors based on current system conditions and topology. As increased amounts of variable generation penetrate the interconnection it will be necessary for these calculations to interface with SCADA data to provide reliable analysis in near real-time.

Enhanced Curtailment Calculator, ECC

Page 8: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

8

Scope

The proposed ECC would calculate impacts on many more paths or distinct elements; potentially all rated paths; and some additional, currently unrated paths. The proposed enhancements would allow real-time updates of transmission system data to include actual generation and outages (currently the data is updated twice annually) and a more granular model of the physical system.

Enhanced Curtailment Calculator, ECC

Page 9: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

9

Benefits

- Accounts for all tagged and untagged system flows.

- Allows for real-time updates of transmission system data to include actual generation and outages.

- Facilitates pro forma tariff compliance by transmission providers to perform pro rata curtailment calculations based on transmission and/or generation priority.

- Provides greater accuracy and system topology for reliable congestion management decisions by the RC’s and Transmission Operators.

Enhanced Curtailment Calculator, ECC

Page 10: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

10

Benefits

- Accounts for all tagged and untagged system flows.

Enhanced Curtailment Calculator, ECC

Page 11: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

11

Benefits

- Allows for real-time updates of transmission system data to include actual generation and outages.

Enhanced Curtailment Calculator, ECC

Page 12: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

12

Benefits

- Facilitates pro forma tariff compliance by transmission providers to perform pro rata curtailment calculations based on transmission and/or generation priority.

Enhanced Curtailment Calculator, ECC

Page 13: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

13

Benefits

- Provides greater accuracy and system topology for reliable congestion management decisions by the RC’s and Transmission Operators.

Enhanced Curtailment Calculator, ECC

Page 14: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

14

Timeline

Enhanced Curtailment Calculator, ECC

No. Milestone Event Milestone Date

1 Visit one or more Reliability Coordinators in the East

12/31/2011

2 Proposal to Standing Committee(s) March 2012

3 Request Board Budget Inclusion June 2012

4 RFP/Contract Negotiations August 2012

5 FERC Budget Approval October 2012

6 Complete Negotiations October/November 2012

7 Begin Implementation November/December 2012

8 Begin Testing Phase Fall 2013

9 Parallel Testing Winter 2013/2014

10 Full Implementation Spring 2014

Page 15: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

15

WECC process going forward

- If the motion is approved by MIC & OC, this estimate will be included in draft Business Plan & Budget presented to the BOD.

- If the budget is approved by BOD and includes the ECC, it will then allow us to proceed to RFP.- If the RFP and staff costs are still below budget, no further approvals are necessary to proceed. - If costs exceed the budget estimate significantly, we will need to re-visit the proposal with the BOD and Task Force.

Enhanced Curtailment Calculator, ECC

Page 16: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

16

Roles & Responsibilities of BAs, TOPs, and RC

Enhanced Curtailment Calculator, ECC

Page 17: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

17

Implementation testing and training

Enhanced Curtailment Calculator, ECC

Page 18: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

18

Task Force status evaluation/determination by JGC after completion of deliverables.

Enhanced Curtailment Calculator, ECC

Page 19: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

19

-Process to determine which nominated elements can be included in the ECC Tool. (ECCTF)

-Process to use the Qualified Devices during a UFMP. (UFAS)

- Ability to add elements on the fly. (ECCTF)

- Modeling of specific elements (including source/sink points) for TDF calculation. (ECCTF, e.g. continue using seasonal WECC planning model with monthly updates relative to any 100kv or higher element. Or, use WWSM, six-week uploads with real-time updates.)

ECCTF & UFAS Roles

Page 20: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

20

- Determination of minimum TDF and physical impact thresholds and how they are used for curtailment evaluation. (UFAS is addressing, ECCTF can review)

- Impacts, quantification, and treatment of non-tagged system uses. (ECCTF)

-Training process for WECC RC and WECC BA on new procedures. (ECCTF)

- Process to update and provide real time information on outages and disturbances. (ECCTF)

ECCTF & UFAS Roles

Page 21: Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,

Craig L. Williams

WECC Market Interface Manager

Cell 801-455-9812

[email protected]