enhancing reliability through halt. introduction to halt benefits of halt the halt process
TRANSCRIPT
Objective
HALT - Highly Accelerated Life Test
TO IMPROVE RELIABILITY
reduce warranty claimsrelease product to market earlier
extend warranty periods
Benefits, Economic Rationale
Finding design weaknesses as early in the product design cycle as possible, can save a
substantial amount of money.
~ Hiroshi Hamada, Ricoh Chairman
£X design phase £5X before procurement £11X before production £486X before shipment £19,714X on customer site
If £X = £40 for example, the cost to find design weakness on customer site is …….
Benefits, Cost & Time
Product #1 -Product #1 -HALT ProcessHALT Process
• 3-5 days to complete
• 1 integrated test chamber • 3 test specimens• no vibration fixture
Product #2 -Product #2 -Traditional Traditional MethodsMethods• 7 months to
complete
• Misc test chambers• 2 test specimens• 2 vibration fixtures
Conclusion: HALT provided faster time to market (reduction in test time), reduced engineering costs, and better results than traditional testing methodologies.
Information from United Technologies Presentationby Ronald Horrell, Chief of Reliability
Benefits, Faster Market Release for LESS
Market Release
Time
1 2 3
SpendingRate
0
1
2
3
4
5
6
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Savings
HALT
Market Release
Benefits, Overview
• Quickly discover design & process flaws.• Evaluate & improve design margins.• Reduce development time & cost.• Eliminate design problems before
release to manufacturing.• Ship a mature product at market
introduction.• Use as a sustaining engineering tool to
evaluate impact of product modifications and cost reductions.
Definition of HALT
A process used during the
design stage of a product that provides a stringent
environment to force design and process maturity
Although normally
performed before manufacturing release, a HALT
can be beneficial in finding product
weaknesses at any point in a product’s life
Example
“No fault found” following product return
Dissatisfied client
Sample put through HALT which stresses the product
Identification of same failure as experienced by client
Equipment used
• Liquid Nitrogen Cooled rapid thermal transitions up to 60ºC/min on product
• Repetitive Shock Vibration
6 degrees of freedom 3 axes & 3 rotations, simultaneous broad frequency band (2-10,000 Hz)
• Combined Environment
Thermal and Vibration
• Liquid Nitrogen Cooled rapid thermal transitions up to 60ºC/min on product
• Repetitive Shock Vibration
6 degrees of freedom 3 axes & 3 rotations, simultaneous broad frequency band (2-10,000 Hz)
• Combined Environment
Thermal and Vibration
HALT Process
1 Test Plan Development (incorporate product specific stress sources,
develop functional tests with good coverage, define what constitutes a failure,...)
2 Determine method of attachment to vibration table3 Ensure adequate airflow within the product (modify the case if required)4 Verify Functionality5 Run HALT6 Failure Analysis7 Implement Corrective Action8 Verify corrective actions by repeating HALT
It is not just the testing - you also benefit from test plan development verification of the functionality and the analysis of the results
HALT Application
Apply Product Specific Stresses
oC
Hot thermal step stress.Begin at +30ºC, increase in 10º C steps. Continue until operating & destruct limits found.
Cold thermal step stress.Begin at + 20ºC, decrease temp in 10ºC stepsContinue until operating & destruct limits found.
6 DoF6 DoFVibeVibe
Vibration step stress.Begin at 5 Grms, step in 5 Grms incrementsContinue until operating & destruct limits found.Functional Testing
& Monitoring
Rapid thermal cycles between the operational limits
Combination of rapid thermal cycles and vibration
When failures occur during HALT
Stop test & record failure mode & stress level
Use isolation techniques to identify failure location
Determine root cause analysis ~ May require further investigation, or, Implement temporary fix
Continue testing to try to induce additional failures
Stop test & record failure mode & stress level
Use isolation techniques to identify failure location
Determine root cause analysis ~ May require further investigation, or, Implement temporary fix
Continue testing to try to induce additional failures
Not all examples of a product fail at the same level of stress, some are stronger than others. A distribution will
exist for each failure
Not all examples of a product fail at the same level of stress, some are stronger than others. A distribution will
exist for each failure
Distributions shown as Gaussian Distributions for illustrative purposes
only
Distributions shown as Gaussian Distributions for illustrative purposes
only
The above example could indicate where a ‘strong’ unit has been used during qualification and the results from this test has allowed market release but 5% of the units are weaker than the specification limit leading to a high early mortality
rate
The above example could indicate where a ‘strong’ unit has been used during qualification and the results from this test has allowed market release but 5% of the units are weaker than the specification limit leading to a high early mortality
rate
The example above shows how a failure distribution (A) is well above the product specification limit when new but due to aging, some of the product population becomes weaker
than the specification limit
The example above shows how a failure distribution (A) is well above the product specification limit when new but due to aging, some of the product population becomes weaker
than the specification limit
HALT Knowledge
HASSHASSHighly Accelerated Stress Screen
A process used in manufacturing, to allow discovery of process changes and prevent products with latent defects from getting into the field.
HASSHASSHighly Accelerated Stress Screen
The link with HASS
The application of HALT and HASS The application of HALT and HASS plays a critical role in improving the plays a critical role in improving the
in-service reliability of a product in-service reliability of a product through better, more robust, through better, more robust, designs and manufacturing designs and manufacturing
processes.processes.
Benefits, Overview
• Quickly discover design & process flaws.• Evaluate & improve design margins.• Reduce development time & cost.• Eliminate design problems before
release to manufacturing.• Ship a mature product at market
introduction.• Use as a sustaining engineering tool to
evaluate impact of product modifications and cost reductions.
Contact UsContact Us
TUV Product Service Ltd
Segensworth Road, Fareham, Hampshire, PO15 5RH, UK
Email: [email protected]
Web: www.tuvps.co.uk
Tel: +44 (0) 1329 443300
Fax: +44 (0) 1329 443421