Nuku‟alofa Urban Development Sector Project
Implementing Agency, PUMA / NSPAO, MLSNR
ADB GRANT-0264 TON
ENVIRONMENT AND SOCIAL UNIT ESU BI-ANNUAL REPORT – N0. 4. May 2015 – October 2015
October 2015
ESU Bi-Annual Report No 4 October 2015
Project title Nuku‟alofa Urban Development Sector Project
Document title ESU Bi-Annual Report
Date October 2015
Author(s) Sonia CHIRGWIN
Reference n° ESU-4
Quality control
Version Date Written by: Checked by:
Draft v1 21/10/15 Sonia CHIRGWIN John GILDEA
Distribution
Sent to:
Name Company Sent on:
Maria PANIAGUA ADB, Fiji 29/10/15
Grace KING ADB, Fiji 29/10/15
Taniela Faletau Safeguards Specialist, ADB Fiji 29/10/15
Saia Faletau ADB, Tonga 29/10/15
Kathleen BOMBELL DFAT Australia 29/10/15
Sally PERRY DFAT Australia 29/10/15
Copy to:
Name Company Sent on:
Tukua TONGA Project Manager, PMU NUDSP 29/10/15
Tatafu MOEAKI Ministry of Finance National Planning - EA 29/10/15
Malakai SIKA CEO, WAL 29/10/15
Saimone HELU CEO, TWB 29/10/15
„Asipeli PALAKI CEO MECCDMMIC 29/10/15
Laurent DENIAU Project Director (EGIS) 29/10/15
Seventeen TOUMO‟UA Deputy Team Leader, PIAC NUDSP 29/10/15
Dick WATLING Environmental Specialist, PIAC NUDSP 29/10/15
Kaati HAKAUMOTU ESU Member and Planner, PMU NUDSP 29/10/15
Tevita FOTU ESU Member and Urban Planner, PUMA 29/10/15
Meli FALETAU ESU Member and Planner PMU NUDSP 29/10/15
Elisipeti VEIKOSO ESU Member and Urban Planner, PUMA 29/10/15
Andrea TALI‟ULI ESU Member, PIAC Environmental Specialist 29/10/15
ESU Bi-Annual Report No 4 October 2015
Acronyms and Abbreviations
AB Affected Business
APs Affected Persons
ADB Asian Development Bank
AusAID Australian Agency for International Development
BME Benefit Monitoring and Evaluation
CDTA Capacity Development Technical Assistance
CSS Country Safeguard System
DP Displaced Person
EA Executing Agency
EIRR Economic Internal Rate of Return
EMA External Monitoring Agency
ESU Environment Social Unit
EU European Union
FGD Focus Group Discussions
GAP Gender Action Plan
GDP Gross Domestic Product
GFP Grievance Focal Point
GIS Geographic Information System
GoT Government of Tonga
GRC Grievance Redress Committee
Ha Hectare
HH Households
IA Implementing Agency
ISA Initial Social Assessment
IUDP Integrated Urban Development Project
IUDSP Integrated Urban Development Sector Project
IMA Internal Monitoring Agency
Km Kilometre
LAR Land Acquisition and Resettlement
MOH Ministry of Health
MOI Ministry of Infrastructure
MLSNR Ministry of Lands, Survey and Natural Resources
NGOs Non-Government Organizations
NSPAO National Spatial Planning Authority Office
NUDSP Nuku‟alofa Urban Development Sector
Project
O&M Operation and Maintenance
PAM Project Administration Manual
PIA Project Implementation Assistance
PIU Project Implementation Unit
PMU Project Management Unit (in PUMA)
PPMS Project Performance Management System
PSA Poverty and Socio Economic Assessment
PSC Program Steering Committee
RP Resettlement Plan
RRP
Report and Recommendation of the President (to the board of Directors)
SPS Safeguard Policy Statement
SES Socio Economic Survey
SW Solid Waste
SWM Solid Waste Management
TA Technical Assistance
TNIIP Tonga National Infrastructure Investment Plan
TNA training needs assessment
TOP Tongan Pa‟anga
TOR Terms of Reference
TSDF Tonga Strategic Development Framework
TUIDP Tonga Urban Infrastructure Development Plan
TWB Tonga Water Board
WAL Waste Authority Limited
WB World Bank
WS Water Supply
ESU Bi-Annual Report No 4 October 2015
iii
TABLE OF CONTENTS 1. INTRODUCTION ....................................................................................................................... 1
1.1 Project Background .............................................................................................................. 1 1.2 Environment and Social Unit ................................................................................................ 2 1.3 Institutional Arrangements .................................................................................................... 3
2 ESU ACTIVITIES - ENVIRONMENT .......................................................................................... 4
2.1 Introduction ........................................................................................................................... 4 2.2 Works in Progress ................................................................................................................ 4 2.4 Tapuhia Groundwater Monitoring ........................................................................................... 4
3 ESU ACTIVITIES - SOCIAL ........................................................................................................ 5
3.1 Resettlement Planning and Implementation ......................................................................... 5 3.2 Grievance Redress Mechanism – Resettlement Plan .......................................................... 5 3.3 Other Social Issues in Project Implementation ..................................................................... 5 3.4 Gender Action Plan .............................................................................................................. 6
4. SUMMARY AND CONCLUSIONS ............................................................................................. 9 ANNEX A : ESU TERMS OF REFERENCE (Updated September 2014) ..................................... 11 ANNEX B – GROUNDWATER MONITORING REPORTS ............................................................ 13 ANNEX C – ENVIRONMENTAL MONITORING TWB-01 CONTRACT.......................................... 36 ANNEX D – GENDER TRAINING WORKSHOP PROGRAMME ................................................... 64 ANNEX E – GAP WITH NOTES FROM ESU WORKSHOP ........................................................... 65
ESU Bi-Annual Report No 4 October 2015
1
1. INTRODUCTION
1.1 Project Background The Asian Development Bank (ADB) and the Australian aid programme, through the Department of Foreign Affairs and Trade (DFAT), jointly fund the Nuku‟alofa Urban Development Sector Project (NUDSP). The NUDSP is a multi-sector urban development project that is expected to contribute to Tonga‟s sustainable economic development by improving the standard of living in Nuku‟alofa. The outcome of the project will be effective, efficient, and sustainable urban services. Project outputs are:
(i) Output 1 – Strengthened policy environment for delivery of urban services:
The project will strengthen the policy environment for delivery of urban services in Tonga by (a) building capacity within Planning and Urban Management Agency (PUMA) to develop urban planning and management policies and to implement the Strategic Planning and Management Act for improved planning and coordination of urban services and urban infrastructure development; (b) reforming Tonga Water Board (TWB) and Waste Authority Limited (WAL) tariffs for recovery of water supply and solid waste services operations and maintenance costs; and (c) mandating the development and implementation of urban infrastructure asset management plans.
(ii) Output 2 - Effective, efficient, and sustainable water supply services in Nuku’alofa: The core subproject will (a) increase the water production at the Mataki‟eua Tongamai wellfield; (b) increase the raw water storage capacity; (c) improve the management of the water supply network through the creation of supply zones and improved bulk supply metering; (d) reduce unaccounted-for- water (UFW) from the current level, estimated at about 50% to less than 25%; (e) develop consumer water meter replacement policies and replace defective consumer meters; and (f) revenue collection, billing, and financial management capacity.
(iii) Output 3 - Sustainable solid waste services in Nuku’alofa: This core
subproject will assist WAL to improve its service delivery to the residents of Nuku‟alofa by: improving waste disposal operations at the Tapuhia landfill, improving and expanding solid waste collection services, and strengthening financial management capacity in WAL.
(iv) Output 4 - Other municipal services within Nuku’alofa: Other municipal
services will be improved through the implementation of selected high-priority urban infrastructure components identified in the Urban Infrastructure Development Plan (UIDP) and the National Infrastructure Investment Plan (NIPP) (candidate subprojects) and could include upgrading of sanitation, construction of drains, upgrading of roads, and replacement of overhead power lines with underground electricity cables. Candidate subprojects will be selected in accordance with the criteria and due diligence requirements and approved by the project steering committee (PSC) and Asian Development Bank (ADB).
(v) Output 5 - Raised community awareness of municipal services: The project
will raise community awareness of municipal services issues such planning and development consent requirements, household responsibilities for managing solid waste (reduce, recycle, re-use), and public health benefits of safe waste handling and disposal. The project will improve customer complaints mechanisms in TWB and WAL, and conduct public consultation on service standards, water conservation and demand management. The community awareness programs will also highlight the responsibilities of the Nuku‟alofa community as beneficiaries of
ESU Bi-Annual Report No 4 October 2015
2
urban services such as the need to pay for services. Women‟s groups and community associations will be consulted and encouraged to participate in urban planning and design issues.
(vi) Output 6 - Effective project management: The project management unit (PMU),
supported by project implementation assistance consultants will provide project design and supervision, monitoring, reporting, quality and cost control, screening and preparation of resettlement plans, and initial environmental evaluations for candidate subprojects, contract administration services and monitoring of the gender action plan.
1.2 Environment and Social Unit A key requirement of the Project is to adhere to the Government of Tonga environmental regulations and the ADB Safeguards Policy (2009). To achieve this, the Project Management Unit (PMU) formed the Environment and Social Unit (ESU). The ESU is responsible for implementing all environmental and social monitoring and reporting processes. The ESU ensures that safeguards are integral to all aspects of project works. This report is the fourth Bi-Annual Environment and Social Unit (ESU) Monitoring Report to be submitted to the ADB. It provides an overview of all activities that have been undertaken in the reporting period of April 2015 to the end of October 2015. During this reporting period, the key areas of ESU focus have been:
Implementation of environmental safeguards and monitoring processes for the TWB wellfield development project
Groundwater monitoring of Tapuhia
Review of complaint management system at WAL, and development of complaint management system for TWB
Review of gender aspects of project The Deputy Project Manager, who was also the Chairperson of the ESU, has not been replaced by the NSPAO. However, one of the key urban planners has returned after an 18 month period undertaking a Masters in Urban Planning in Australia. This team member is invaluable due to her focus on environmental aspects of planning. The ESU team currently has three permanent members, with additional NSPAO staff joining team activities when available.
ESU Bi-Annual Report No 4 October 2015
3
1.3 Institutional Arrangements
Ministry of Finance
Executing Agency (EA) Ministry of Lands, Survey, and Natural Resources
Project Steering Committee (See membership below)
1. Ministry of Finance and Planning (MFP) 2. Ministry of Lands, Survey, Natural Resources (MLSNR) 3. Ministry of Environment and Climate Change 4. Ministry of Education, Women„s Affairs and Culture (MEWAC) 5. Tonga Water Board (TWB) 6. Waste Authority Limited (WAL)
7. PUMA (secretariat)
National Spatial Planning
Authority Office (NSPAO)
Implementing Agency (IA) and Project Management Unit (PMU)
Project Implementation Assistance (PIAC) Coordination Office
ESU
PMU Staff assisted by PIAC
Tonga Water Board
Waste Authority Ltd
Assistance
Assistance
Community, pro-poor and
gender activities
Core Subprojects
Candidate Subprojects
The ESU is a team based in National Spatial Planning Authority Office (NSPAO) with the responsibility to ensure all Project activities are undertaken in line with the ADB Safeguards Policy Statement (2009). It comprises of staff from the PMU, the National Spatial Planning Authority Office (NSPAO) and the Project Implementation Assistance Consultants (PIAC). The ESU has not regularly met during this reporting period, due to the reduced size of the unit. However, regular informal discussions are held to continue to implement the responsibilities of the ESU. The Terms of Reference for the ESU is attached as Appendix A.
2 ESU ACTIVITIES - ENVIRONMENT
2.1 Introduction All sub-projects and works under the NUDSP are undertaken in accordance with; (i) the NUDSP Environmental Assessment and Review Framework which ensures that the environment is considered an integral component of sub-project assessment and implementation processes, (ii) and the NUDSP Resettlement Framework for ensuring that impoverishment risks are mitigated and sustainable livelihood and opportunities are offered to people affected by the project. The ESU operations during the period of April to October 2015 focused on the following:
Solid Waste Core Sub-project (i) Groundwater Monitoring for Tapuhia Landfill- During this reporting period,
the ESU worked with WAL, the Geology Division of MLSNR, and Department of Environment, to undertake two rounds of groundwater testing and analysis. The testing rounds took place in May and August 2015. The two groundwater monitoring reports are attached as Annex B.
Water Supply Core Sub-project
(i) The ESU worked with the PIAC Environmental Specialist to review all
environmental aspects of the proposed works. The Contractors Environmental Management Plan (CEMP) was reviewed, and two initial site environmental monitoring audits were undertaken. These reports are attached as Annex C.
2.2 Works in Progress The civil works at the Mata ki „Eua and Tongamai wellfields is in the early stages. The focus has been on the road clearance and surfacing, and the mobilisation activities.
2.4 Tapuhia Groundwater Monitoring The Tapuhia Groundwater Monitoring Program is now well established, with quarterly testing undertaken by WAL in collaboration with the ESU, Geology Division of MLSNR and the Environment Division of MEECCDMMIC.
WAL – Groundwater Monitoring at Tapuhia WMF
5
During this reporting period, groundwater monitoring was undertaken in May and August 2015. With the groundwater testing now programmed into WAL‟s operations, the role of the ESU has decreased. However, ESU continues to participate in the programme to learn about groundwater testing and analysis. Whilst this is no longer a core function of the ESU, at this time the group wishes to continue their involvement. The key issues in the groundwater testing during this reporting period are the ongoing monitoring of the elevated ammonia and nitrate levels in the vicinity of the septage treatment beds and truck washdown facility. The May results were elevated, but the August results were much lower. The ESU looks forward to the activities under the Sanitation Sub-project, which are proposed for implementation in 2016. This will bring a focus to investigating groundwater testing results with technical expertise from wastewater treatment specialists. It is also an opportunity to improve water treatment processes and increase the environmental safeguards in place at the landfill.
3 ESU ACTIVITIES - SOCIAL The ESU has a direct role in social safeguards for project implementation through resettlement planning and also monitoring the implementation of the Gender Action Plan.
3.1 Resettlement Planning and Implementation There were no resettlement planning activities during the reporting period.
3.2 Grievance Redress Mechanism – Resettlement Plan There were no formal complaints received by the ESU or GFPs in relation to the resettlement process or payments.
3.3 Other Social Issues in Project Implementation During the road construction works at the Tongamai site, there was „chance grave discovery‟ in a raised area of the existing road reserve. The contractor had been levelling an area as a part of the road upgrading, and saw some sandy soil and human skeletal remains. The driver immediately stopped work and informed the Engineer through the Clerk of Works. Following this, the project‟s social safeguards specialist was informed and the next day she visited the site with the appropriate Matapule, Na‟ahokonga, and had a discussion on site with adjacent landowners. The road is a registered public road. All present agreed that the bones needed to be treated with respect and appropriate cultural practices. Following this meeting and further discussions with the Noble (Lavaka), the Town Officer, the Minister of Lands, and the Matapule (Na‟ahokonga), it was determined that the road would be diverted around the burial site, leaving the grave in-situ and
WAL – Groundwater Monitoring at Tapuhia WMF
6
intact. The diverted road remains within the road reserve, without any encroachment onto private land. The burial site has been marked.
3.4 Gender Action Plan The ESU also monitors the implementation of the project‟s Gender Action Plan (GAP), and makes recommendations for how to achieve the indicators. From the 9th to the 12th June 2015, an ADB gender specialist worked with the Project and the ESU to provide gender training and review implementation of tangible actions to improve gender equity outcomes. Initial Workshop A workshop was delivered on the 9th of June 2015, targeting partner Ministries, Government Enterprises, and ADB project consultants. Titled ADB Gender Awareness and Capacity Building Support, the workshop explored the concepts of:
Gender mainstreaming in development;
The Tongan Government‟s gender policy;
Good practice examples;
Lessons learned; and
Addressing gender in infrastructure development in Tonga. See Annex D for workshop programme. The workshop provided an excellent forum for discussion, and was particularly successful at highlighting the challenges and successes in Tonga. One of the main challenges is that the Office for Women, now within the Ministry of Internal Affairs, suffers from chronic under-resourcing. With only one professional staff member, it is difficult to achieve Government gender policy, particularly given the frequent obligation to travel and participate in regional and international discussions. There was a positive case study presented by Tonga Power Limited demonstrating the benefits of gender equity in workplaces. During the Ha‟apai reconstruction process, TPL were asked by ADB to target the employment of local people from Ha‟apai, and women in non-traditional roles. Lines people historically have been sourced from the local technical training college in Tongatapu, and these graduates have traditionally been male. To employ local women in this role TPL needed to instead provide on the job training. The initiative was a success, with the women more than capable of the work, and lifting the performance outcomes of the whole crew. The employment of women as lines-people is successful from both a workplace outcome perspective, but also providing a visible challenge to social norms about traditional roles for women. Tonga Water Board Gender Training Following on from this workshop, the gender specialist conducted smaller strategic workshops with TWB and WAL. These focussed participants on current employment patterns, gender roles within the workplace, and identification of barriers for women to be engaged in non-traditional roles. The TWB discussion was attended by the CEO (male), the Manager of HR (female), the Head of Engineering Section (male), and three employees from the Customer Service and Finance Section (2 female and 1 male).
WAL – Groundwater Monitoring at Tapuhia WMF
7
At the TWB workshop, it was identified that there are no women working in technical or meter reading roles. There had been women employed as meter readers in the past, but despite a good work performance they left for personal reasons. There was a good discussion on barriers for women in TWB non-traditional roles. As meter readers, there can be a perception issue amongst more conservative sectors that the women walking around alone and speaking to males in households was not acceptable. This is clearly a barrier for women whose employment choices are limited by conservative males within the family structure. To address this, TWB staff agreed that women should be actively encouraged to apply, and over time with more women in this role, those barriers will gradually change. A barrier to women undertaking technical roles is the lack of women who have undertaken the relevant training. However, this is also changing with more women entering technical training courses. Again, TWB management staff agreed that encouraging women to apply and aiming for improved gender balance is an important step in the change process. The other item of discussion with TWB staff was that women are more impacted by water disruptions or poor supply of water, given their roles in raising children and caring for elderly and sick. Water disconnections can impact women more, yet bill paying decisions are sometimes made by men. It was agreed that, given the uneven impacts of poor water services for women, that women need to be more proactively targeted in any consultation efforts by TWB. Awareness raising efforts on water conservation and TWB services needs to target women and ensure that the messages are reaching this audience. WAL Gender Training The WAL workshop was held at Tapuhia to ensure that the Manager of Operation (waste collection and landfill management) was present for the discussion. The other participants were the Community Team Leader (female) and the Communications Officer (male). At the Tapuhia Landfill Site, there are 10 staff, who are all male. Recently a female administrative worker was asked to work at the gatehouse whilst that staff member was on leave. Her father did not approve of this, as she would be the only woman in what he perceives to be an isolated site. This highlighted one of the barriers to changing the gender balance at the site. However, the Supervisor of Tapuhia agreed that there is no reason why women could not work at the site, provided they could gain the skills from on the job training. Women as heavy machinery operators in the mining sector in Australia was discussed as a case study that demonstrates potential for lower operating costs with greater care taken. The Supervisor agreed that again this was possible for WAL. Looking at the collection trucks, it was agreed amongst WAL staff that the work is too physically demanding for women. There is also a status issue with working as a waste collector, with the role already viewed by many as an undesirable job, which would be even stronger as a consideration for women working as a waste collector. However, it was agreed there is potential for women to be employed as truck drivers. The main barrier to opening non-traditional roles for women is the current recruitment practices. For these waste collection and landfill operations positions, recruitment has only ever been done by word of mouth. Usually employees are given their job through an informal process. This actively excludes women from these opportunities.
WAL – Groundwater Monitoring at Tapuhia WMF
8
It was agreed that this barrier could be removed by WAL always advertising their posts, with “men and women encouraged to apply” included on all advertisements. WAL will be undertaking a new function of operations and maintenance for public toilets in Nuku‟alofa. It was agreed that ideally the teams should have a mixed gender balance. Cleaning roles should not follow gender stereotypes that this is a job for women, and having mixed teams would ensure that cleaning crews could work in male and female toilets respectively without necessitating temporary access closures. As with TWB, it was agreed that poor waste management places an uneven burden on women in the household. Sickness through poor sanitation and waste management places a greater burden on women. Therefore they are likely to place a higher priority on these urban service issues. It is vital that awareness campaigns and consultation processes ensure that women are effectively included. ESU Gender Workshop
The final workshop was with the ESU, looking specifically at the NUDSP Gender Action Plan. It was agreed that the GAP was not well targeted to achieve outcomes on the ground, particularly in relation to the work of TWB and WAL. The group revised the GAP, which is presented in Annex E. Areas are also highlighted where the targets are not possible, or outside the influence of the project. It was determined that the proposed revisions will be discussed with ADB at the next project review. It needs to be explored whether this more practical GAP can be implemented, and what would be the steps for modifying the Plan.
WAL – Groundwater Monitoring at Tapuhia WMF
9
4. SUMMARY AND CONCLUSIONS During this reporting period, the ESU has commenced new responsibilities in the environmental auditing of the TWB wellfield and reservoir upgrade contract. The group has also continued with groundwater monitoring at Tapuhia and oversight of social safeguards issues as they arise. The Sanitation Sub-project commenced in the final quarter of 2015. This will provide new responsibilities for the ESU, as well as increased resourcing. Over the 2 years of project implementation, there will be a Social, Community, Gender Safeguards Specialist with the project for 18 months. There will also be an additional Environmental Specialist on board, who will play a key role in undertaking ESU responsibilities. The main project components which require ESU involvement will be:
Input into green waste processing and septage sludge composting development;
Input into the contract to increase septage disposal facilities at Tapuhia (including environmental monitoring of the civil works contract);
Involvement in developing the criteria and selecting households for improved sanitation grants;
Input into gender and social issues for school and household sanitation improvements;
Input into policy discussions, ensuring gender and other social issues are mainstreamed.
Area Actions Undertaken Focus of Next Reporting Period
WAL Sub-Project Environmental monitoring of Tapuhia Construction Contract
No further audits Major civil works completed. Awaiting arrival of materials and final corrective action on site before final environmental audit.
Groundwater monitoring Two rounds undertaken. May and August 2015
Continued support of quarterly testing
TWB Sub-Project
Resettlement Planning All payments made and resettlement process complete
No further actions required unless complaint arises through the grievance process.
Environmental monitoring of construction contract(s)
Developed environmental monitoring checklists
Undertook pre-construction audits (#1)
Undertook second monthly site audit
Followed up all corrective actions issued, and closely monitored critical environmental issues
Monthly audits
Close supervision of contaminated soil remediation works.
WAL – Groundwater Monitoring at Tapuhia WMF
10
Sanitation Sub-project
Planning Input into IEE
Input into Feasibility Study
Input into work planning, and discussions, ensuring safeguard policies are met by Project at all times
Technical Aspects None to date Input into discussions on groundwater issues and requirements for upgraded treatment system.
Research into sanitation systems appropriate for flood prone areas, that are culturally acceptable in Tonga. Best practice case studies.
Social Aspects None to date Input into developing criteria for selecting households for grant scheme. Prioritise women headed households, families with special needs, and those living below poverty line.
Participation in application assessments.
Awareness None to date Ensure messaging is appropriately targeted and is effective for women and men
Ensure any consultation actively involves women and marginal sectors of the community.
Others
Gender Action Plan Participated in 4 gender training workshops / discussions
Worked with gender specialist to review GAP and ways to improve the effectiveness of ESU in this area.
Discussion with ADB on proposed changes to GAP
Follow up with proposed establishment of gender focal points
WAL – Groundwater Monitoring at Tapuhia WMF
11
ANNEX A : ESU TERMS OF REFERENCE (Updated September 2014)
INTRODUCTION
The ESU is a team based in NSPA with the responsibility to ensure all Project activities are undertaken in line with the ADB Social Safeguards Policy (2009).
The ADB recommend that an ESU comprises of a minimum of three members; the Unit Head or Chairperson, a Social Focal Point, and an Environmental Focal Point. In the NUDSP ESU, there are additional members, as it is seen as an opportunity for capacity building with PUMA staff. There have been a number of staff changes within NSPA in the past year. Two planners, including the ESU Environmental Focal Point have taken up study opportunities overseas. The Deputy Project Manager of the PMU who was the ESU Chairperson, has recently left the position. A replacement recruitment process is underway, but is expected to take at least one month. The PIAC team are also undergoing a process of change, with key support consultants of the ESU completing their inputs assigned for the project. As such there is a need to re-focus on the roles and responsibilities of ESU members, and determine ongoing support requirements. At this time, the level of ownership has waned and the sustainability of the ESU needs to be strengthened. The review of the TOR is a part of this process.
SUGGESTED STRUCTURE / ROLES
ESU Chairperson Deputy PM
Environment Focal Point Lolo Fotu
Social Focal Point Kaati Hakaumotu
Team Members Meli Faletau Motei Tapaa
PIAC Advisors
WAL – Groundwater Monitoring at Tapuhia WMF
12
ESU RESPONSIBILITIES Whilst to date the ESU have been managing the environmental auditing process at Tapuhia, and the resettlement planning for the wellfield, there are some additional tasks that are required. The following is a summary of all tasks for the ESU:
Finalisation and implementation of Resettlement Plan for TWB sub-project
Environmental monitoring for civil works at Tapuhia Landfill
Environmental monitoring for civil works at Tongamai wellfield (when works commence)
Support for groundwater monitoring for Tapuhia Landfill (in collaboration with Waste Authority Ltd)
Monitoring of the Gender Action Plan and recommending activities to achieve the indicators
Implementation of any further environmental monitoring or resettlement activities for any new core sub-projects funded under NUDSP
The ESU has four main roles:
Assessment
Implementation
Monitoring
Reporting Assessment
All new sub-projects must have potential social and environmental impacts identified, minimised and mitigated, through Initial Environmental Examination reports and/or Resettlement Plans. This work is likely to be undertaken by Project consultants, but ESU may play a support role in these activities.
In the case of unforseen impacts occurring during implementation, such as a court dispute over land use or an environmental incident, the ESU must report this immediately to ADB, and prepare a Corrective Action Plan.
Implementation
The ESU is responsible for implementing the Resettlement Plan, ensuring all entitlements are paid, and that affected persons are kept well informed.
The ESU undertakes monthly environmental site audits for any civil works, such as the construction contracts at Tapuhia, and at the TWB wellfield development.
Monitoring
The ESU must monitor the implementation of the project Gender Action Plan, and make recommendations for how to achieve the indicators.
Reporting
On a quarterly basis, all environmental monitoring and other activities of the ESU must be summarised into a brief report, which is included as an annex in each Quarterly Project Report (QPR) for the ADB. This quarterly report is to be submitted to the PIAC Deputy Team Leader.
Twice a year, this information is collated and presented as a Safeguards Monitoring Report and submitted to the ADB. This is a public report and will be disseminated via the ADB website.
WAL – Groundwater Monitoring at Tapuhia WMF
13
ANNEX B – GROUNDWATER MONITORING REPORTS
Waste Authority Ltd – Groundwater Testing at
Tapuhia Waste Management Facility
Report to Stakeholders
Round 5 – May 2015 Testing
May 2015
WAL – Groundwater Monitoring at Tapuhia WMF
14
Quality Information
Quality Control
Version Date Written by: Check by:
Draft 20/5/15 Sonia CHIRGWIN Tapu PANUVE
Addresses
Sent to :
Name Company Sent on:
Tapu PANUVE Interim CEO Waste Authority Ltd 04/06/15
Talita HELU WAL Community Advisor 04/06/15
Tevita KAUFUSI WAL Technical Officer 04/06/15
Akapei VAILEA MLSNR Geology Division 04/06/15
Filimone LAPAOO MECCDMMIC Environment Division 04/06/15
Tukua TONGA Project Manager, NUDSP PMU 04/06/15
Tevita Lolo FOTU Environment and Social Unit, PMU 04/06/15
Motei TAPAA Environment and Social Unit, PMU 04/06/15
Kaati HAKAUMOTO Environment and Social Unit, PMU 04/06/15
Meli FALETAU Environment and Social Unit, PMU 04/06/15
John GILDEA PIAC, NUDSP 04/06/15
WAL – Groundwater Monitoring at Tapuhia WMF
15
Table of Contents Chapter 1 Introduction ............................................................................................ 16
1.1 Background ................................................................................................... 16 Chapter 2 2nd Quarter Testing 2015 ....................................................................... 17
2.1 Preparation for the May 2015 Testing Round ............................................... 17 2.2 Aims of Testing Round .................................................................................. 17 2.3 Methodology ................................................................................................. 17 2.4 Results .......................................................................................................... 18 2.5 Analysis......................................................................................................... 20
Chapter 3 Discussion ............................................................................................. 24 Chapter 4 Recommendations ................................................................................ 25
WAL – Groundwater Monitoring at Tapuhia WMF
16
Introduction
Background
In April 2014, the Nuku‟alofa Urban Development Sector Project (NUDSP) provided
the Waste Authority Ltd (WAL) with equipment and materials to reinstate a regular
groundwater testing programme at the Tapuhia Landfill Facility. In the absence of
regular water testing by a regulatory authority, conducting in-house indicator testing
provides some level of risk management for WAL.
To date. WAL have undertaking the testing in a collaborative manner, working with
representatives from the following agencies:
Department of Environment (under Ministry of Environment, Energy, Climate
Change, Disaster Management, Meteorology, Information and
Communications – MEECCDMMIC)
Ministry of Land Survey and Natural Resources, Geology Division
Environment and Social Unit, Project Management Unit of Nuku‟alofa Urban
Development Sector Project.
This approach was undertaken to maximise capacity building opportunities, and to
establish open dialogue around ground water issues and mitigation strategies.
The past rounds of testing have been facilitated and led by NUDSP. As this is an in-
house testing programme, WAL have taken over the organisation and reporting
functions, with support from NUDSP.
To date, four rounds of groundwater testing were conducted on:
15th May 2013
9th June 2014
3rd October 2014
18th February 2015
This is now the fifth round of testing, and it was conducted on the 7th May 2015. The
water testing has been established by WAL to be undertaken on a quarterly basis.
This report presents the results of groundwater testing for the second quarterly round
of testing for 2015.
WAL – Groundwater Monitoring at Tapuhia WMF
17
2nd Quarter Testing 2015
Preparation for the May 2015 Testing Round
WAL organised the testing round with the Environment and Social Unit (ESU) and Project Implementation Assistance Consultants (PIAC) of NUDSP. As has occurred to date with the testing, representatives from the Pollution Control Division of MECCDRMIC, and the Geology Division of MLSNR were invited to participate. Samples were taken on 7th May 2015, with water testing taking place on the same day.
Aims of Testing Round
The following aims were set for the water testing:
1. To test samples from 7 groundwater monitoring bores, and raw and treated
samples of the landfill leachate.
2. To compare results from this round and the previous rounds
3. If required, to develop mitigation strategies
Methodology
Samples were taken from 7 groundwater monitoring wells by WAL staff. Two samples of the leachate were taken to measure the water quality both before and after treatment in the waste water treatment system. The before sample was taken from the first holding tank, with the final sample taken from the treated leachate storage pond. In the Tapuhia office building, a testing area was established. Tests were undertaken for each sample, analysing for pH, electrical conductivity (EC), total dissolved solids (TDS), salinity, nitrate, ammonia, iron and COD. Results were recorded in the data sheet and then entered into an excel spread sheet.
Results
WAL – Groundwater Monitoring at Tapuhia WMF
19
Notes on indicative limits for parameters
Parameter Tolerance Limit Notes
pH 6.0 – 8.5 WHO Drinking Water Guidelines
EC Less than 1000 1000 – 2000 Over 2000
Relatively pure water Medium, and may be typical of groundwater on limestone Implies possible leachate
TDS 2000 No WHO health based guideline. Viewed to be unpalatable in drinking water when over 1000.
Salinity 1500 SPREP tolerance level for fresh water is 1000.
Nitrate 40 WHO Drinking Water Guidelines
Ammonia less than 1 1 – 10 over 10
background leaching indication of mild to moderate contamination with leachate or septage indication of probable severe contamination
Iron 3 WHO Drinking Water Guidelines
COD 40 SPREP tolerance for treated water release. Note that these guidelines are developed for release of water from a waste water treatment plant, which requires a much higher standard than at Tapuhia, which only has primary treatment so cannot reach this level. Also the water is not being released into the environment but kept on site. However, the SPREP tolerance limit provides some context for the results.
Analysis
Groundwater Monitoring Bore Positions The following map and explanation of expected water flow is extracted from the 2008 hydrogeological explorations undertaken by Coffey Environment Pty Ltd. This provides the context for analysing samples from the Tapuhia testing programme.
The Tapuhia landfill approximate layout of filling trenches and proximity to the near field monitoring wells. Wells 7, 1 and 8 are well placed to intercept groundwater from the main filling area. Well 2 is adjacent to the septage drying beds and is likely to catch effluent from these facilities. Wells 5, 4 and 3 tend to be "upgradient" of the filling and are likely to represent background water quality. Groundwater Monitoring Well Results All sample results from the Groundwater Monitoring Wells were within the expected range for each testing parameter, with the exception of the ammonia results. The COD readings were elevated in GWM wells 1 and 2, as compared to previous months. The COD levels were reduced in other sample readings. GWM 2 had a COD reading higher than the indicator tolerance limit. The chart below shows the COD data for this round and the previous three rounds.
WAL – Groundwater Monitoring at Tapuhia WMF
21
Figure 1: Data for COD over four Testing Rounds
Nitrate and ammonia parameters are closely linked, and there is a history of some elevation of these readings around GWM 2 since the very early days of testing. The following charts portray the data for nitrate and ammonia parameters over four rounds of testing. Figure 2: Data for Nitrate over three Testing Rounds
0
5
10
15
20
25
30
35
40
Jun-14
Oct-14
Feb-15
May-15
WAL – Groundwater Monitoring at Tapuhia WMF
22
Figure 3: Data for Ammonia over three Testing Rounds
The main issue of concern from this testing round, as per the previous testing round, is the elevated ammonia in GWM 2. This bore is located next to the septage beds, and close to the leachate treatment plant. The level of ammonia at GWM 2 has increased from 4.92 in the Febuary round, to 8.87 in this latest reading. However, there is also elevated ammonia in GWM 4 and 5, which are both “upgradient wells” and should be seen as indicators of the background levels in the groundwater prior to the landfill activities. It is unknown what could cause this elevation in the upgradient wells. All wells downgradient of GWM 2 have very low levels of ammonia (levels as expected for natural groundwater). In comparing the data over the four testing rounds, there are clearly elevated levels of nutrient in GWM 2. However, there is no elevation recorded in the downgradient wells (GWM 1, 7 and 8), indicating that the plume is not rapidly moving. In order to provide a longer term analysis of data for these parameters in GWM 2, earlier laboratory test results have been compared in the following table.
Testing Date Nitrate Ammonia
11-Apr-06 0.01 0.085
14-Aug-07 18.2 0.011
10-May-13 na 0.74
9-Jun-14 40 0
13-Oct-14 13 0.79
18-Feb-15 12 4.92
7 May 15 16 8.87 This demonstrates that in June 2014, there was a significant elevation of nitrate in GWM 2, and in February and May 2015, a significant elevation of ammonia.
0123456789
10
Jun-14
Oct-14
Feb-15
May-15
WAL – Groundwater Monitoring at Tapuhia WMF
23
Treated and Untreated Leachate Results
Leachate
Parameter Units Tolerance Limits
Untreated Treated
pH 6.0 - 8.5 7.66 8.86
Electrical Conductivity
µS/cm 2000 2000 1070
TDS (PPM) 1000 1390 480
Salinity µS/cm 1000 1000 520
Nitrate (PPM) 50 11 0
Ammonia (PPM) 1 >10 0
Iron (PPM) 3 0.61 0
COD (PPM) 40 76 87
The results of this round of testing demonstrate effective water treatment. The pH of the final effluent pond is on the high side, as is the COD reading. The colour of the pond suggests elevated nutrients and lack of oxygen.
WAL – Groundwater Monitoring at Tapuhia WMF
24
Discussion
GWM 2 – Mitigation Strategy Under the proposed sanitation project, funded as a sub-project in NUDSP, there will be a major upgrading of the wastewater treatment and septage bed area at Tapuhia. As a first stage in investigating and mitigating any pollution from the septage beds, it is recommended that a separate groundwater monitoring bore be sunk in close vicinity to GWM 2. This will provide the opportunity to verify testing results, and understand whether there is groundwater contamination taking place. The new septage treatment beds will be constructed with geo-synthetic lining to provide a higher level of groundwater protection. If the second monitoring bore demonstrates contamination from the existing beds, it is proposed that these beds are rehabilitated and lined to prevent any further contamination as a second stage in the mitigation strategy.
WAL – Groundwater Monitoring at Tapuhia WMF
25
Recommendations
1. Submit report to WAL Board, MECCDMIC (Environment Division) and
MLSNR (Geology Division)
2. Continue to closely monitor the ammonia and nitrate readings for GWM 2 to
determine the trends over time, and inform future action.
3. Construct new monitoring bore in the vicinity of GWM 2 as the first stage in
improving environmental safeguards at the site.
4. If the data from the new bore continues to demonstrate elevated nitrate and
ammonia, rehabilitate existing septage beds and washdown area with a geo-
synthetic lining system to provide additional groundwater protection.
WAL – Groundwater Monitoring at Tapuhia WMF
26
Waste Authority Ltd – Groundwater Testing at
Tapuhia Waste Management Facility
Report to Stakeholders
Round 6 – August 2015 Testing
17th
August 2015
WAL – Groundwater Monitoring at Tapuhia WMF
27
Quality Information
Quality Control
Version Date Written by: Check by:
Draft 17/8/15 Sonia CHIRGWIN Tapu PANUVE
Addresses
Sent to :
Name Company Sent on:
Tapu PANUVE Interim CEO Waste Authority Ltd 17/08/15
Talita HELU WAL Community Advisor 18/08/15
Tevita KAUFUSI WAL Technical Officer 18/08/15
Akapei VAILEA MLSNR Geology Division 18/08/15
Filimone LAPAOO MECCDMMIC Environment Division 18/08/15
„Atunaisa Fetokai Acting Project Manager, NUDSP PMU 18/08/15
Tevita Lolo FOTU Environment and Social Unit, PMU 18/08/15
Kaati HAKAUMOTO Environment and Social Unit, PMU 18/08/15
Meli FALETAU Environment and Social Unit, PMU 18/08/15
John GILDEA PIAC, NUDSP 18/08/15
WAL – Groundwater Monitoring at Tapuhia WMF
28
Table of Contents Chapter 1 Introduction ............................................................................................ 29
1.1 Background ................................................................................................... 29 Chapter 2 3rd Quarter Testing 2015 ....................................................................... 30
2.1 Preparation for the August 2015 Testing Round ........................................... 30 2.2 Aims of Testing Round .................................................................................. 30 2.3 Methodology ................................................................................................. 30 2.4 Results .......................................................................................................... 31 2.5 Analysis......................................................................................................... 33
Chapter 3 Discussion ............................................................................................. 34 Chapter 4 Recommendations ................................................................................ 35
WAL – Groundwater Monitoring at Tapuhia WMF
29
Introduction
Background
In April 2014, the Nuku‟alofa Urban Development Sector Project (NUDSP) provided
the Waste Authority Ltd (WAL) with equipment and materials to reinstate a regular
groundwater testing programme at the Tapuhia Landfill Facility. In the absence of
regular water testing by a regulatory authority, conducting in-house indicator testing
provides some level of risk management for WAL.
To date WAL have undertaken the testing in a collaborative manner, working with
representatives from the following agencies:
Department of Environment (under Ministry of Environment, Energy, Climate
Change, Disaster Management, Meteorology, Information and
Communications – MEECCDMMIC)
Ministry of Land Survey and Natural Resources, Geology Division
Environment and Social Unit, Project Management Unit of Nuku‟alofa Urban
Development Sector Project.
This approach was undertaken to maximise capacity building opportunities, and to
establish open dialogue around ground water issues and mitigation strategies.
The past rounds of testing have been facilitated and led by NUDSP. As this is an in-
house testing programme, WAL have taken over the organisation and reporting
functions, with support from NUDSP.
To date, five rounds of groundwater testing were conducted on:
15th May 2013
9th June 2014
3rd October 2014
18th February 2015
7th May 2015
This is now the sixth round of testing, and it was conducted on the 4th August 2015.
The water testing has been established by WAL to be undertaken on a quarterly
basis.
This report presents the results of groundwater testing for the third quarterly round of
testing for 2015.
WAL – Groundwater Monitoring at Tapuhia WMF
30
3rd Quarter Testing 2015
Preparation for the August 2015 Testing Round
WAL organised the testing round with the Environment and Social Unit (ESU) and Project Implementation Assistance Consultants (PIAC) of NUDSP. As has occurred to date with the testing, representatives from the Pollution Control Division of MECCDRMIC, and the Geology Division of MLSNR were invited to participate. Samples were taken on 4th August 2015, with water testing taking place on the same day.
Aims of Testing Round
The following aims were set for the water testing:
1. To test samples from 7 groundwater monitoring bores, and raw and treated
samples of the landfill leachate.
2. To compare results from this round and the previous rounds
3. If required, to develop mitigation strategies
Methodology
Samples were taken from 7 groundwater monitoring wells by WAL staff. Two samples of the leachate were taken to measure the water quality both before and after treatment in the waste water treatment system. The before sample was taken from the first holding tank, with the final sample taken from the treated leachate storage pond. In the Tapuhia office building, a testing area was established. Tests were undertaken for each sample, analysing for pH, electrical conductivity (EC), total dissolved solids (TDS), salinity, nitrate, ammonia, iron and COD. Results were recorded in the data sheet and then entered into an excel spread sheet.
Results
WAL – Groundwater Monitoring at Tapuhia WMF
32
Notes on indicative limits for parameters
Parameter Tolerance Limit Notes
pH 6.0 – 8.5 WHO Drinking Water Guidelines
EC Less than 1000 1000 – 2000 Over 2000
Relatively pure water Medium, and may be typical of groundwater on limestone Implies possible leachate
TDS 2000 No WHO health based guideline. Viewed to be unpalatable in drinking water when over 1000.
Salinity 1500 SPREP tolerance level for fresh water is 1000.
Nitrate 40 WHO Drinking Water Guidelines
Ammonia less than 1 1 – 10 over 10
background leaching indication of mild to moderate contamination with leachate or septage indication of probable severe contamination
Iron 3 WHO Drinking Water Guidelines
COD 40 SPREP tolerance for treated water release. Note that these guidelines are developed for release of water from a waste water treatment plant, which requires a much higher standard than at Tapuhia, which only has primary treatment so cannot reach this level. Also the water is not being released into the environment but kept on site. However, the SPREP tolerance limit provides some context for the results.
WAL – Groundwater Monitoring at Tapuhia WMF
33
Analysis
Groundwater Monitoring Well Results All sample results from the Groundwater Monitoring Wells were within the expected range for each testing parameter. There was an overall improvement in water quality, particularly at GWMW #2, which had previously shown elevated COD and ammonia readings. Treated and Untreated Leachate Results
Leachate
Parameter Units Tolerance Limits
Untreated Treated
pH 6.0 - 8.5 8.28 8.3
Electrical Conductivity
µS/cm 2000 2400 1532
TDS (PPM) 1000 1740 1100
Salinity µS/cm 1000 1210 780
Nitrate (PPM) 50 44 11
Ammonia (PPM) 1 0 0
Iron (PPM) 3 5.28 1.95
COD (PPM) 40 5 53
The results of this round of testing demonstrate effective water treatment. The COD of the final effluent pond is on the high side, which will be useful data to provide as a background to the design of the wastewater treatment plant upgrade at Tapuhia. The colour of the pond suggests elevated nutrients and lack of oxygen.
WAL – Groundwater Monitoring at Tapuhia WMF
34
Discussion
This round of test results shows no adverse indicators for groundwater quality in the vicinity of the Tapuhia Landfill. In this round, there was no contamination indicated in GWMW #2, despite elevated COD and nitrate in earlier testing rounds. As discussed in the previous report, the indicator testing provides a consistent data set to be used for analysis in the design of the upgraded septage treatment beds and wastewater treatment plant at Tauphia, both of which will be funded under the Sanitation Sub-project of the Nuku‟alofa Urban Development Project. Increasing the capacity of the treatment plant is important to address the risk of off-site contamination. The indicator testing provides an important risk management tool for the Waste Authority. However, there is no external testing undertaken from a regulatory or environmental protection perspective. Discussions with the regulator, MECCDMMIC, will be undertaken to discuss this gap, and look at longer term improvements to the testing regime.
WAL – Groundwater Monitoring at Tapuhia WMF
35
Recommendations
1. Submit report to WAL Board, MECCDMIC (Environment Division) and MLSNR
(Geology Division)
2. Continue to closely monitor indicator results, particularly for GWM #2. This will
continue to determine the trends over time, and inform future action.
3. When discussing design of the waste water treatment plant upgrade, the indicator
test results will inform suppliers of the current performance of the water treatment
system, and potential improvements required.
4. Commence discussions with the regulator, MEECCDMMIC, to look at ways to
improve the testing programme over time.
WAL – Groundwater Monitoring at Tapuhia WMF
36
ANNEX C – ENVIRONMENTAL MONITORING TWB-01 CONTRACT
TONGA: Nuku’alofa Urban Development Sector Project
Rehabilitation and Extension of Borefields at Mataki’eua and Tongamai and Construction of
4,000m3 Reservoir at Mataki’eua, Nuku’alofa, Kingdom of Tonga
Construction Environmental Management
Monitoring Report # 1: August 2015
Prepared by Environment and Social Unit (National Spatial Planning Office and NUDSP PIAC)
For the Asian Development Bank (ADB) Project Number: TON 42394
Grant Number: 0264 – TON (SF)
Mataki’eua CEMP Report
37
Mateki’eua Contract
Construction Environmental Management Monitoring Report # 1: August 2015
INTRODUCTION
Background to this Document
The Nuku’alofa Urban Development Sector Project is co-funded by the Asian Development Bank and the Australian Government (through DFAT), with the support of the Government of Tonga. One of the priorities identified to improve the urban environment in Nuku’alofa is to provide assistance to the Tonga Water Board to upgrade water supply, production, storage and distribution.
As set out in the Tonga Water Board Act 2000 TWB is governed by and functions in accordance with the Act to provide water supply services for domestic, stock, horticultural, industrial, commercial, recreational, environmental and other beneficial uses, in any area in which it may be appointed to do so under this Act. The town of Nuku’alofa is currently served from the Mataki’eua and Tongamai well fields and managed by TWB.
The bore field for the urban water supply currently comprises 39 wells with 29 at Mataki’eua and 11 on the Tongamai extension. The current works will provide an additional 12 bores and replace 6 collapsed bores as well convert all remaining diesel pumps to electrical pumps. Ancillary works will include road upgrading and services installation (power and water) as well as the construction of a 4,000m3 reservoir. During the works, soil contaminated with hydro-carbons will be removed, and remediated on site.
Site Values
Site values or qualities which have been identified that require protection at Mataki’eua-Tongamai include:
Groundwater Roadside trees, and trees at the new bore sites
Environmental Issues
In undertaking the Mataki’eua Civil Works Contract the following environmental issues need to be addressed:
Unnecessary removal of mature trees and vegetation during road works and new well siting;
Contamination of the groundwater during the works; Poor construction waste management; Inappropriate sanitary arrangements; Poorly implemented soil remediation works; Dust generation during roadworks; Absence of traffic management during roadworks; Excessive noise from construction plant; and, Non-compliant health and safety measures.
Purpose of this Document
The purpose of this document is to fulfill NUSDP’s monitoring requirements of the Mataki’eua Civil Works Contract – Contractor’s Environmental Management Plan, for the Asian Development Bank.
Mataki’eua CEMP Report
38
Circulation of this Document - This report is circulated by the NUDSP PMU to the following: TWB - Saimone Helu (CEO), Quddus Fielea (Engineering Manager TWB) PMU -ESU Team – Peti Veiksos (Urban Planner), Lolo Fotu (Urban Planner) PIAC - Seventeen Toumoua (Engineer to the Contract), Sonia Chirgwin (Waste Management Advisor), Dick Watling (Environmental Advisor) Contractors – Ghao Dong, Zhao Xing (CCECC)
Mataki’eua CEMP Report
39
Mataki’eua CEMP Report
40
MATAKI’EUA CIVIL WORKS CONTRACT CONSTRUCTION ENVIRONMENTAL MANAGEMENT MONITORING REPORT
Date of Inspection: 19 August 2015
Recorder: Dick Watling
Inspection Team: PUMD ESU/NUDSP: EV, SC, DW, TP, SH, VP Contractor: GD, ZX Other: NT (TWB)
Nature of Inspection: 1st Monthly Report
Weather Conditions: Fine & Sunny
Site Condition: Firm – no significant rain in preceding week
Extent of Works: Just starting works – construction of site office and clearing the road footprint
General Comment and Observations:
1. Initial site inspection was undertaken to coincide with the official start of the contract, and followed a gathering on site with representatives of TWB, NUDSP (Engineer and staff; consultants); PUMA ESU rep and contractor;
2. Inspection comprised a drive along all the roads to be upgraded and a view of all the existing and new bore sites which will form the works, stopping at several of these to discuss specific issue, and the remediation site, initial pictures of the works‟ sites were taken;
3. Works had just started with clearing of the road footprint following marking of survey point, and the contractor‟s site office had been erected;
4. Photographic record made (Note on photographs: Contractor is required to take progress photos and include in monthly reports. Any ESU photos to be stored by PIAC team
5. The contractor‟s CEMP has been completed but has yet to be officially submitted and approved by the Engineer. As such this site visit was primarily and introductory one for all the agency members and no corrective actions are identified here. These should start from next month‟s site inspection. Issues which were apparent were discussed with the contractor on the site.
6. The „chance grave discovery‟ in the road footprint was visited. The contractor had been levelling an area as a part of the road upgrading, and saw some sandy soil and human skeletal remains. The driver immediately stopped work and informed the Engineer through the Clerk of Works. Following this the project‟s social safeguards specialist was informed and the next day she visited the site with the appropriate Matapule and had a discussion on site with adjacent landowners. The road is a registered public road. At the time of the visit the outcome of the find remained to be finalised. All present agreed that the bones needed to be treated with respect and appropriate cultural practices. The options are to move the bones and re-bury adjacent to the road, or re-route the road around the cemetery area. At this time it is unknown whether there are more remains on the site. The road reserve area provides adequate space to resolve the issue without encroaching on the area of private land.
7. Litter dumping is a problem on the project roads near the Tongamai main road junction, especially in the small track just behind Well Site 130. Clearing this is not part of the contractor‟s responsibility, but finding a solution in removing this small dump and some more waste along the other project roads would be very useful.
Mataki’eua CEMP Report
41
INSPECTION CHECKLIST
Action/Mitigation Measure
Mitigation Implementation
Impacts Observed/Location Action Required
(Corrective Action # &
Date)
Contractor Response/Comment
Yes/No Effectiveness
(1 to 5)
1. Contractor environmental awareness, inspection and reporting
Aware of environmental management requirements
Has copy of IEE, EMP;
Delivering training and/or awareness to staff (staff induction, tool box meetings)
Daily/weekly inspections
Reporting
Yes
Yes
Not yet
Not yet
3 CEMP has been completed but yet to be officially submitted and approved by the Engineer.
Discussions have been undertaken with the contractors as to the requirements of the CEMP. Formal CAs when CEMP is approved.
2. Vegetation Management
No vegetation to be removed outside of the road survey area.
No character trees removed from the bore sites without approval of the engineer.
Yes
n/a
4 Existing road, so very few large trees in or near footprint. A bit untidy in places with soil and brush piled up; but no character trees removed and evident avoidance in some places of good sized trees.
3. Groundwater Quality Control
Careful construction around drill sites;
Protocols for safe water well drilling being implemented
No fuel or hazardous chemical storage at the worksite as per CEMP
n/a No works at the drill sites yet, other than an exploratory soil removal exercise at a collapsed well 131 with NUSDP staff, TWB and contractor. Issues were discussed on the site and „Guidance Notes‟ are being prepared
4. Waste management
Construction waste disposed of correctly to Tapuhia
Waste bins present at site office and work sites
Prior to disposal, store all waste in suitable areas/receptacles to prevent hazards such as fires, attraction to vermin, dissemination of dust, leachate to groundwater
Mobile toilets in use as office site and work site
Yes
No
3
1
One waste bin at the site office.
No mobile toilets on site as yet. Discussed with contractor.
5. Noise Control
Minimise sound generated by civil works by use of appropriate construction design, equipment and materials;
Where possible, program work such that high noise levels occur at times of least impact. I.e. 0700 to 1830 hrs, Monday to Saturday only as no work is allowed on Sunday;
Where necessary and possible, fit plant and equipment with acoustic canopies and/or exhaust suppressors
Yes
4
No plant working at the time of the visit. However, some diesel powered pumps in operation were noisy !
Mataki’eua CEMP Report
42
Action/Mitigation Measure Mitigation
Implementation Impacts Observed/Location
Action Required
(Corrective Action # &
Date)
Contractor Response/Comment
6. Dust Control Use water trucks, when required, to wet areas that generate dust;
Restrict construction activities to the minimum possible area;
Stabilise disturbed areas as soon as practicable;
Cover trucks that transport dusty materials;
n/a No dust issues at present. Adequate rain in past week.
7. Contaminated Soil Remediation
Soil remediation being undertaken in accordance with specification
All contaminated or possibly contaminated soil being conveyed to remediation site
Remediation site with secure vegetation bunds preventing leakage of soil
Biosol Green 2000 being used
Yes
Yes
No
4
4
1
Soil remediation has been initiated, with one load of soil taken to the site.
The vegetation bund is not adequately constructed and a much more robust bund is required.
Biosol not yet being used. Information on Biosol has been sent to the contractor
A vegetation bund according to specs to be put in place
Issue has been discussed with the contractor and an understanding reached.
8. General Site Management
Install traffic barriers around work sites;
Provide and maintain adequate warning signs at site boundaries and along excavations;
Provide suitable enclosed storage areas for construction materials and locate away from drainage lines;
Manage all spoil to minimize blockage of drainage lines, dust generation, and to use as back-fill where appropriate;
Minimise waste generated through reduction, reuse and recycling;
Maintain site office and amenities in good condition and keep surrounding areas clean and tidy.
n/a
No
n/a
n/a
yes
1
4
No road signs around road work clearing
Road signs indicating road construction works in progress need to be put in place
Not discussed on site but issue and other health and safety issues raised at the Site Meeting – same day as the Inspection
9. Community Disruption and Health Control
Inform community and local authorities of project plans and schedule and location of proposed works;
Provide appropriate signage and control to ensure safety;
Where appropriate, provide opportunities for local householders (or community members) to be engaged in the construction activities. Particular attention should be given to providing work opportunities for women (as per the NUDSP Gender Action Plan)
?
No
?
1
Discuss communications and clarify responsibilities
One major sign for the project is required and road signs indicating road works needed as above
Effectiveness rating; 1 = non-compliant - corrective actions required; 2 = partial compliance – corrective or alternative actions required; 3 = adequately implementing CEMP measures; 4 = more than adequately implementing CEMP measures; 5 = excellent compliance, incl. measures in addition to CEMP
Mataki’eua CEMP Report
43
CORRECTIVE ACTION REGISTER
# Corrective Action Required Ref # &
Date (from Engineer)
Actions Implemented Date
Checked
Effectiveness/ Comments
1
A vegetation bund at the remediation site to be constructed according to specs and „guidance notes on remediation‟ currently in draft form.
Official Ref # from the Engineer required
2
Traffic signs need to be put in place during the road works – sufficient would be a sign at all entrance points from main public roads to the works roads. And cones close to the operational area.
3
One large Project Sign to be erected.
Mataki’eua CEMP Report
44
PHOTOGRAPHS OF SITE INSPECTION – 20 AUGUST 2015 – 1ST SITE INSPECTION
Photo 1: Well Site 216 – very heavily contaminated site Photo 2: Well Site 131- collapsed bore and used for initial site remediation
Photo 3: Well Site 133 – very heavily contaminated site Photo 4: Well Site 133 – very heavily contaminated site
Mataki’eua CEMP Report
45
Photo 5: Well Site 123 – no visible contamination, but dead grass indicative Photo 6: Well Site 128 – highly contaminated site
Photo 7: Road footprint clearing – large trees avoided Photo 8: Soil remediation site
Mataki’eua CEMP Report
46
Photo 9: Grave discovery site – cordoned off and detour in place Photo 10: Bones exposed in chance grave find in road footprint
Photo 11: Chance grave find – NUSDP staff, social safeguard specialist, adjacentlandowners and Matpule on site.
Photo 12: Litter dumping in side road behind Well Site 130
Mataki’eua CEMP Report
47
RECORD OF CONDITION OF EXISTING WELL SITES JUST PRIOR TO PROJECT COMMENCEMENT
Well Site #
216
Mataki’eua CEMP Report
48
132
133
Mataki’eua CEMP Report
49
121
Mataki’eua CEMP Report
50
123
125
Mataki’eua CEMP Report
51
127
128
Mataki’eua CEMP Report
52
130
Mataki’eua CEMP Report
53
TONGA: Nuku’alofa Urban Development Sector Project
Rehabilitation and Extension of Borefields at Mataki’eua and Tongamai and Construction of
4,000m3 Reservoir at Mataki’eua, Nuku’alofa, Kingdom of Tonga
Construction Environmental Management
Monitoring Report # 2: September 2015
Prepared by Environment and Social Unit (National Spatial Planning Office and NUDSP PIAC)
For the Asian Development Bank (ADB) Project Number: TON 42394
Grant Number: 0264 – TON (SF)
Mataki’eua CEMP Report
54
Mateki’eua Contract
Construction Environmental Management Monitoring Report # 2: September 2015
INTRODUCTION
Background to this Document The Nuku’alofa Urban Development Sector Project is co-funded by the Asian Development Bank and the Australian Government (through DFAT), with the support of the Government of Tonga. One of the priorities identified to improve the urban environment in Nuku’alofa is to provide assistance to the Tonga Water Board to upgrade water supply, production, storage and distribution.
As set out in the Tonga Water Board Act 2000, TWB is governed by and functions in accordance with the Act to provide water supply services for domestic, stock, horticultural, industrial, commercial, recreational, environmental and other beneficial uses, in any area in which it may be appointed to do so under this Act. The town of Nuku’alofa is currently served from the Mataki’eua and Tongamai well fields managed by TWB.
The bore field for the urban water supply currently comprises 39 wells with 29 at Mataki’eua and 11 on the Tongamai extension. The current works will provide an additional 12 bores and replace 6 collapsed bores as well convert all remaining diesel pumps to electrical pumps. Ancillary works will include road upgrading and services installation (power and water) as well as the construction of a 4,000m3 reservoir. During the works, soil contaminated with hydro-carbons will be removed, and remediated on site.
Site Values
Site values or qualities which have been identified that require protection at Mataki’eua-Tongamai include:
Groundwater Roadside trees, and trees at the new bore sites
Environmental Issues
In undertaking the Mataki’eua Civil Works Contract the following environmental issues need to be addressed:
Unnecessary removal of mature trees and vegetation during road works and new well siting;
Contamination of the groundwater during the works; Poor construction waste management; Inappropriate sanitary arrangements; Poorly implemented soil remediation works; Dust generation during roadworks; Absence of traffic management during roadworks; Excessive noise from construction plant; and, Non-compliant health and safety measures.
Purpose of this Document
The purpose of this document is to fulfill NUSDP’s monitoring requirements of the Mataki’eua Civil Works Contract – Contractor’s Environmental Management Plan, for the Asian Development Bank.
Mataki’eua CEMP Report
55
This is the second CEMP monitoring report. The Environment and Social Unit (ESU) of the Project Management Unit will undertake these inspections on a monthly basis for the duration of the contract period.
Circulation of this Document - This report is circulated by the NUDSP PMU to the following: TWB - Saimone Helu (CEO), Quddus Fielea (Engineering Manager TWB) PMU -ESU Team – Peti Veiksos (Urban Planner), Lolo Fotu (Urban Planner) PIAC - Seventeen Toumoua (Engineer to the Contract), Sonia Chirgwin (Waste Management Advisor), Dick Watling (Environmental Advisor) Contractors – Ghao Dong, Zhao Xing (CCECC)
Mataki’eua CEMP Report
56
Mataki’eua CEMP Report
57
MATAKI’EUA CIVIL WORKS CONTRACT CONSTRUCTION ENVIRONMENTAL MANAGEMENT MONITORING REPORT
Date of Inspection: 19 August 2015
Recorder: Dick Watling
Inspection Team: PUMD ESU/NUDSP: EV, SC, KU Contractor: GD Other:
Nature of Inspection: 2nd
Monthly Report
Weather Conditions: Fine & Sunny
Site Condition: Firm – no significant rain in preceding week
Extent of Works: Just starting works – little change in progress since initial inspection undertaken. Drilling has not commenced. Roadworks 20% complete (all clearance complete, but surfacing and grading still underway).
General Comment and Observations:
8. Site inspection was undertaken one month since the initial site investigation, and followed a gathering on site with representatives of TWB, NUDSP (Engineer and staff; consultants); and the contractor;
9. Physical inspection was not undertaken as there has been little physical change since the initial meeting. Drilling works have not commenced, or any further work on the soil remediation. The inspection was based on a discussion of each of the issues, with no further photographs taken;
10. The only change on site is that the road works have further progressed and the geotechnical investigation in the reservoir area has commenced. There has been some difficulty getting access to the grader, with the progress of road works estimated at 20% by the Contractor (although all clearance complete);
11. The contractor‟s CEMP has been completed but at the time of the monthly inspection has yet to be officially submitted and approved by the Engineer. This must be completed as a matter of urgency.
12. Litter dumping is a problem on the project roads near the Tongamai main road junction, especially in the small track just behind Well Site 130. Clearing this is not part of the contractor‟s responsibility, but finding a solution in removing this small dump and some more waste along the other project roads was discussed at the meeting, and the Contractor is willing to assist with removal of waste stockpiles as the roadwork over-burden is cleared and removed off site. The ESU team will discuss with Waste Authority the option of waiving the disposal fee for this illegally dumped waste.
13. Discussion at the meeting also focussed on working with neighbours and the relevant Town Officers to provide information about the schedule of works, as well as creating broader publicity about the works.
14. The grave discovery issue has now been largely resolved, with the determination made to leave the grave in situ, and divert the road around the burial mound. This is still within the lease area. The grave is to be marked and left as is.
Mataki’eua CEMP Report
58
INSPECTION CHECKLIST
Action/Mitigation Measure
Mitigation Implementation
Impacts Observed/Location Action Required
(Corrective Action # &
Date)
Contractor Response/Comment
Yes/No Effectiveness
(1 to 5)
1. Contractor environmental awareness, inspection and reporting
Aware of environmental management requirements
Has copy of IEE, EMP;
Delivering training and/or awareness to staff (staff induction, tool box meetings)
Daily/weekly inspections
Reporting
Yes
Yes
Yes
Not yet
3 CEMP has been completed, with comments for improvements submitted to the Contractor by DW (PIAC Environmental Specialist). The final CEMP is yet to be officially submitted and approved by the Engineer.
Contractor reports that all staff have now been briefed on the CEMP.
Inspections had not commenced at time of this audit.
Final submission and approval of CEMP (before next inspection on 14
th October)
Contractor recommends that inspections will be undertaken internally, with all issues summarized in monthly report. This will be adequate provided that all issues are discussed with supervising engineer as they arise.
2. Vegetation Management
No vegetation to be removed outside of the road survey area.
No character trees removed from the bore sites without approval of the engineer.
Yes
n/a
4 Existing road, so very few large trees in or near footprint. All land clearing (which was minimal) has been completed. Will dispose of at Tapuhia, unless TWB request soil for re-use on site. As reported in the first audit, no character trees removed and evident avoidance in some places of good sized trees.
3. Groundwater Quality Control
Careful construction around drill sites;
Protocols for safe water well drilling being implemented
No fuel or hazardous chemical storage at the worksite as per CEMP
n/a No works at the drill sites yet.
4. Waste management
Construction waste disposed of correctly to Tapuhia
Waste bins present at site office and work sites
Prior to disposal, store all waste in suitable areas/receptacles to prevent hazards such as fires, attraction to vermin, dissemination of dust, leachate to groundwater
Mobile toilets in use as office site and work site
Yes
No
3
1
One waste bin at the site office. Checked if there are bins / bags in work vehicles. Contractor will check (need to follow this up at next audit).
Contractor installed one temporary toilet. However, in discussion with supervising engineers, it was decided that this was not appropriate in the water catchment area, and that the Contractors would instead use the existing toilet at the TWB workshop.
Contractor to
Mataki’eua CEMP Report
59
Action/Mitigation Measure Mitigation
Implementation Impacts Observed/Location
Action Required
(Corrective Action # &
Date)
Contractor Response/Comment
Minimise potential for illegal waste disposal in the roads. No At the site there are a number of instances of illegal dumping along the access roads. Whilst this is not the contractors responsibility (as it was pre-exisitng), it would be good to utilize the equipment on site to remove this material. Also discussed the possibility of getting some signage to warn people not to illegally dump waste in the area (PIAC to discuss with TWB and WAL)
remove waste when removing over-burden and vegetation from road work areas. Contractor to provide PIAC with estimated volume, and arrangements will be made to waive the disposal fees on this waste.
5. Noise Control
Minimise sound generated by civil works by use of appropriate construction design, equipment and materials;
Where possible, program work such that high noise levels occur at times of least impact. I.e. 0700 to 1830 hrs, Monday to Saturday only as no work is allowed on Sunday;
Where necessary and possible, fit plant and equipment with acoustic canopies and/or exhaust suppressors
Yes
4
No plant working at the time of the visit.
6. Dust Control Use water trucks, when required, to wet areas that generate dust;
Restrict construction activities to the minimum possible area;
Stabilise disturbed areas as soon as practicable;
Cover trucks that transport dusty materials;
n/a No dust issues at present. Adequate rain in past week.
7. Contaminated Soil Remediation
Soil remediation being undertaken in accordance with specification
All contaminated or possibly contaminated soil being conveyed to remediation site
Remediation site with secure vegetation bunds preventing leakage of soil
Biosol Green 2000 being used
n/a Soil remediation has been initiated, with one load of soil taken to the site. However, no further works since this initial work in August.
The soil remediation work needs to commence sooner rather than later in the contract in order for their to be enough time for effective bio-remediation to occur.
The vegetation bund is not adequately constructed and a much more robust bund is required. No further improvements have been made since the initial inspection.
A vegetation bund according to specs to be put in place
Discussed with Contractor the need to commence bio-remediation works sooner rather than later.
Contractor to check on procurement of
Issues have been discussed with the contractor and an understanding reached.
Mataki’eua CEMP Report
60
Action/Mitigation Measure Mitigation
Implementation Impacts Observed/Location
Action Required
(Corrective Action # &
Date)
Contractor Response/Comment
Biosol not yet being used. Information on Biosol has been sent to the contractor. Discussed procurement of Biosol and the necessity to ensure the product is available when required.
Biosol.
8. General Site Management
Install traffic barriers around work sites;
Provide and maintain adequate warning signs at site boundaries and along excavations;
Provide suitable enclosed storage areas for construction materials and locate away from drainage lines;
Manage all spoil to minimize blockage of drainage lines, dust generation, and to use as back-fill where appropriate;
Minimise waste generated through reduction, reuse and recycling;
Maintain site office and amenities in good condition and keep surrounding areas clean and tidy.
n/a
No
n/a
n/a
yes
1
4
No road signs around road work clearing
Road signs indicating road construction works in progress need to be put in place
Not discussed on site but issue and other health and safety issues raised at the Site Meeting – same day as the Inspection
9. Community Disruption and Health Control
Inform community and local authorities of project plans and schedule and location of proposed works;
Provide appropriate signage and control to ensure safety;
Where appropriate, provide opportunities for local householders (or community members) to be engaged in the construction activities. Particular attention should be given to providing work opportunities for women (as per the NUDSP Gender Action Plan)
No
No
No
1
Discussed at the meeting. Landowners have been informed of the 18 month – 2 year time schedule for the contract works. However, it was agreed that it would be beneficial to provide them with more detailed information about the schedule of works.
Agreed that it would also be beneficial to publicise the works into the broader community. PIAC will discuss with TWB about providing information about the works schedule on their regular radio programme.
One major sign for the project is required and road signs indicating road works needed as above
Effectiveness rating; 1 = non-compliant - corrective actions required; 2 = partial compliance – corrective or alternative actions required; 3 = adequately implementing CEMP measures; 4 = more than adequately implementing CEMP measures; 5 = excellent compliance, incl. measures in addition to CEMP
CORRECTIVE ACTION REGISTER
Mataki’eua CEMP Report
61
# Corrective Action Required Ref # &
Date (from Engineer)
Actions Implemented Date
Checked
Effectiveness/ Comments
1
A vegetation bund at the remediation site to be constructed according to specs and „guidance notes on remediation‟ currently in draft form.
Official Ref # from the Engineer required
no 16/9
2
Traffic signs need to be put in place during the road works – sufficient would be a sign at all entrance points from main public roads to the works roads. And cones close to the operational area.
no 16/9
3
One large Project Sign to be erected. yes 16/9
Tapuhia -ESU Environmental Monitoring Report
62
PHOTOGRAPHS OF SITE INSPECTION – 20 AUGUST 2015 – 1ST SITE INSPECTION . NO ADDITIONAL
PHOTOS TAKEN IN SEPTEMBER AUDIT DUE TO LACK OF CHANGES
Photo 13: Well Site 216 – very heavily contaminated site
Photo 14: Well Site 131- collapsed bore and used for initial site remediation
Photo 15: Well Site 133 – very heavily contaminated site
Photo 16: Well Site 133 – very heavily contaminated site
Photo 17: Well Site 123 – no visible contamination, but dead grass indicative
Photo 18: Well Site 128 – highly contaminated site
Photo 19: Road footprint clearing – large trees avoided
Photo 20: Soil remediation site
Tapuhia -ESU Environmental Monitoring Report
63
Photo 21: Grave discovery site – cordoned off and detour in place
Photo 22: Bones exposed in chance grave find in road footprint
Photo 23: Chance grave find – NUSDP staff, social safeguard specialist, adjacent landowners and Matpule on site.
Photo 24: Litter dumping in side road behind Well Site 130
Tapuhia -ESU Environmental Monitoring Report
64
ANNEX D – GENDER TRAINING WORKSHOP PROGRAMME
Asian Development Bank Gender Awareness and Capacity Building Support Workshop
Tuesday, 9th June 2015, from 9:00am to 1pm, at Moulton Hall
Program
Time Activities Responsible Person
9:00am Tea and Coffee All
9:15am Opening Prayer Welcome and official opening
9:20am Overview of Workshop Purpose and Agenda Ms Kate Nethercott Wilson
9:25am What is Gender and Why is gender relevant to ADB assistance for Developing Member Countries? Group Exercise and Presentation on ADB policy on gender mainstreaming in grant/lending operations and GAP requirements
Kate
10:00 Summary of Tonga Gender Policy Presentation on Tonga policy on gender and development (linking to infrastructure)
Women‟s Affairs Division
10:20 Why is gender relevant in urban water and sanitation and energy sectors? Group exercises and presentation Natural Resources, Geology Division, Director: to talk on fresh water resources of Tongatapu, water use, factors freshwater resources and water resources management measures.
Kate Kate Mr Taniela Kula
11:00 Tea break
11:15 Good Practice Examples and Lessons Learned Good practice examples from ADB and elsewhere of gender considerations in urban sector water and sanitation and energy projects Lessons learned from NUDSP Good practice and lessons learned from TPL recruitment of female lines people (presentation) Good practice and lessons learned Fokololo (tertiary training on mechanics)
Kate Ms Monalisa Tukuafu TPL Fokololo
12:15 How to address gender in infrastructure in Tonga Opportunities and challenges for addressing gender in infrastructure programs in Tonga (group exercises, and discussions)
Kate
1:10 Workshop Close
Lunch
Tapuhia -ESU Environmental Monitoring Report
65
ANNEX E – GAP WITH NOTES FROM ESU WORKSHOP
Gender Action Plan – Review Notes by ESU June 2015 Green text – Targets are outside of project influence and suggest removing them during the GAP update process
Outputs Activity / Strategy Performance/Target Indicators Recommended Changes to
Performance/Target Indicators
Preparatory Stage : To ensure due consideration of gender issues and analysis in program planning, design and implementation procedures.
Strengthening
women’s
involvement in
urban planning
and decision
making
Hiring of a mid-level female planner
into PUMA for 2 years. (responsible
for reporting against the GAP
throughout the project period).
2012
The position is created, and filled. Planner appointed in PUMA
Planner reporting periodically on progress with GAP
implementation.
Planner established gender focal points (GFP) and coordination with
the Office of Women‟s Affairs, Longafonua, Civil Society Forum of
Tonga and other relevant organizations.
x x
Establish Gender Focal Points in TWB
and WAL.
Undertake capacity building with
Gender Focal Points (in coordination
with Office of Womens Affairs in MIA)
Seek further capacity building
opportunities
Explore establishment of multi-
agency gender group to regularly
meet for networking and discussion
(quarterly)
Providing Gender
and
Social Safeguards
Support to the
PMU and
PUMA
Establishment of GFP in PUMA
involving the networking and
support activities (seminars,
information sharing) of a wide range
of women and men across
government ministries about gender
mainstreaming. At least 40% of
participants are men.
2012-2016
GFP is established in PUMA
GFP has representation from at least 8 departments
GFP consists of at least 40% men
GFP has conducts at least 5 seminars a year with at
least 40% attendance by men
Women comprise at least 30% of the Project Steering
Committee in 2014
x x x x x
As above
Recommend to remove target for
women on Project Steering
Committee (outside of project control
as representation based on positions)
Providing Gender
and
Social Safeguards
Support to the
PMU and
PUMA
Gather baseline sex-disaggregated
data and gender analytical
information for preparatory surveys,
feasibility studies and assessments.
2012
Studies and reports include reference to gender-
disaggregated data and gender analytical information.
Analysis of Complaints received by
WAL and TWB and disaggregate by
gender. Then analyse if there are any
differences in the types of complaints
and issues brought forward by
women.
Tapuhia -ESU Environmental Monitoring Report
66
Providing Gender
and
Social Safeguards
Support to the
PMU and
PUMA
Equal participation and consultation
of women affected by and involved
in the project during preparatory
surveys, studies, assessments and
other consultative mechanisms.
2012
Number of women's groups and representatives
consulted during preparatory surveys, studies,
assessments and other consultative mechanisms.
1. Strengthened
policy environment
for delivery of urban
services
Establish National Spatial Planning
Authority advisory committee and
promote the women‟s
representation in it to provide
feedback and advice on all outputs
in GAP.
Facilitate the equal participation
women and men in consultation
meetings.
Provide training on gender equality
to government staff (especially
those who are in charge of the
project) to improve their
understanding about gender
concerns in urban services
(including water supply and waste
management) and increase their
capacity to implement the project‟s
gender action plan.
NSPA advisory committee provides
feedback and advice
2012-2017
At least 40% of the advisory committee are women.
PUMA reports showing % of women involved in the
urban task force
Gender sensitive strategy prepared
At least 30% of facilitators of community groups and/or
MOH delivering campaign seminars are men.
By 2015, women represent 50% of participants at general meetings.
(baseline 2011: limited consultation
and/or participation) providing feedback and suggestions for
improvement.
At least 40% of participants in community seminars are men.
At least 50% of government trainees are men.
X X
If the Advisory Committee is
established through EOI process
(rather than Ministerial
appointment), encourage women to
apply, through initiatives such as
advertisement wording and
workshops to support women
applicants.
Tapuhia -ESU Environmental Monitoring Report
67
2.Effective, efficient
and
sustainable water
supply services in
Nuku‟alofa (core
subproject) provided
by TWB; and
3.Sustainable solid
waste services in
Nuku‟alofa (core
subproject provided
by WAL)
Strategy to pro-actively identify and
address ongoing gender concerns
and targeting women as customers
prepared by TWB and WAL (with
assistance of PUMA)
TWB and WAL target women as
individual customers and involve
them in planning, managing and
promoting utility/service use and
conservation.
Design and deliver a program of
community water safety,
conservation and hygiene education
and awareness raising campaign
using appropriate media and
delivered through existing Ministry
of Health campaigns and
facilitators.
Establish targets for female
employment
generation and regulate adherence
to core labor codes.
Facilitate the equal participation
women and men in consultation
meetings.
2012-2014
At least 30% of customers (identified on bill) of TWB and WAL are
women.
Gender sensitive media and support materials are
developed in conjunction with women and men (50:50
mix).
All women‟s groups in Nuku‟alofa are covered by the
campaign.
At least 30% of facilitators of community groups and/or
MOH delivering campaign seminars are men.
By 2015, women represent 50% of participants at
general meetings. (baseline 2011: limited consultation
and/or participation) providing feedback and suggestions for
improvement.
Employment and pay targets for women reviewed through the
payroll statements of the construction and
the beneficiary organizations.
At least 40% of participants in community seminars are men.
At least 50% of government trainees are men.
X
Delete highlighted targets as they
are outside of scope of project
Work with WAL and TWB to
improve recruitment processes so
that women are not excluded (by
practices of direct appointment).
Advertised posts encourage women
and men to apply.
In awareness campaigns under
Clean Green Tonga, test materials
on mixed audiences and ensure
that materials targeting households
are clear and relevant for women
Tapuhia -ESU Environmental Monitoring Report
68
4.Other municipal
infrastructure is
upgraded
and well maintained
Provide opportunities for all DP‟s
and women to apply to be trained to
undertake TWB and WAL field and
office positions supported during the
project (truck drivers, garbage
collection, water meter maintenance
and readers, accounting staff etc.)
and recruitment of women and men
participating
Establish targets for female
employment generation and
regulate adherence to core labor
codes.
2012-2014
At least 20% of labor on contracts are women with
specific provisions for equal pay included in the bidding
documents and project covenants.
Employment and pay targets for women reviewed through the
payroll statements of the construction and the beneficiary
organizations.
X
X
For the Sanitation Project, in the
contracts to construct household
sanitation facilities, seek 20% labor
to be women (through contract
documents)
5. Community is
aware of efficient
use of municipal
services
Design and deliver a series of
gender awareness training
workshops for local district and town
leaders, PSC members,
management and staff of relevant
departments and agencies
(including TWB, WAL) and project
area residents at the start of the
project by project staff.
Information campaigns (written
materials, local TV and
newspapers) about the project are
developed that incorporate
messages outlining the benefits and
methods for participation for both
men and women.
Facilitate the equal participation and
consultation of women and men
participating in the program.
2012-2014
Gender inclusive media and support materials are
developed in conjunction with women and men (50:50
mix).
All women‟s groups in Nuku‟alofa are covered by the
campaign.
Perception surveys of project stakeholders show awareness by both
men and women of the benefits of including men and women in
urban infrastructure planning, decision making; sexual harassment,
gender based violence and other problems that may emerge during
project implementation and how to detect, intercept, respond to and
prevent it.
At least 50% of women‟s groups and community associations are
consulted and encouraged to participate in urban planning and
design issues.
Sanitation project to implement
gender training as a component of
awareness on improving sanitation.
Tapuhia -ESU Environmental Monitoring Report
69
6.Effective project
management
services
Recruit a project Gender Specialist
or social development specialist
consultant with gender expertise
who can provide guidance for
implementation of the GAP.
Develop the project performance
and management system (PPMS)
to include sex disaggregated data
and information, utilizing the
baseline information collected
during the PPTA and earlier studies
for longitudinal analysis.
Gather baseline sex-disaggregated
data and gender analytical
information as part of any
preparatory surveys, feasibility
studies or assessments.
Develop a feedback mechanism in
which both male and female
beneficiaries have a voice and are
informed of results (through existing
district and women‟s committees).
Proactively encourage and promote
women's employment in the urban
infrastructure sector.
Include responsibility for gender
issues and gender analysis in
Terms of Reference for all
consultants, wherever relevant.
Recruit a female mid-level planner
into PUMA for 2 years of the
project.
2012-2014
Gender Specialist secures proper attention to all gender elements of
project and all project reports cover implementation of the GAP.
Sex-disaggregated data is collected on a regular basis
as part of all surveys and reported on in all reports.
Number of instances where sex-disaggregated data is
discussed at project meeting is at least 30%.
GAP implemented; gender inclusive training materials
developed; and awareness training delivered with sex-
disaggregated attendance records.
At least 30% of newly appointed/hired professional staff are female.
By 2012, a minimum of 20% of mid-level staff and above from
relevant agencies (TWB, WAL, PUMD, Finance) are women.
By 2015, at least 30% of senior urban planning and management
positions are held by women. (Baseline 2011: 0%)
Gender-related substantive content reflected in all PUMD training
materials where appropriate.
All female PUMD staff members participate in relevant capacity
development activities.
Terms of Reference for all consultants include responsibility for
gender issues and gender analysis wherever relevant.