environmental and social management...
TRANSCRIPT
FINAL DRAFT MAY 2019
MINISTRY OF HOUSING AND LANDS | GOVERNMENT OF THE COMMONWEALTH OF DOMINICA
ENVIRONMENTAL AND SOCIAL
MANAGEMENT FRAMEWORK DOMINICA HOUSING RECOVERY PROJECT
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
TABLE OF CONTENTS ACRONYMS ............................................................................................................................................... 3
FOREWORD............................................................................................................................................... 4
EXECUTIVE SUMMARY ........................................................................................................................ 5
SECTION 1: INTRODUCTION ......................................................................................................... 15
SECTION 2: PROJECT DESCRIPTION ......................................................................................... 16
2.1 Background ................................................................................................................................. 16
SECTION 3: POLICY FRAMEWORK FOR ENVIRONMENTAL AND SOCIAL ISSUES ..... 19
3.1 National Laws and Regulations .................................................................................................. 19
3.2 World Bank Safeguard Policies .................................................................................................. 20
3.2.1 Environmental Policies ....................................................................................................... 20
3.2.2 Social Policies ..................................................................................................................... 20
SECTION 4: PROJECT IMPLEMENTATION ARRANGEMENTS............................................ 22
SECTION 5: ENVIRONMENTAL AND SOCIAL CONDITIONS IN THE PROJECT AREA . 26
5.1 Environmental Conditions and Issues ......................................................................................... 26
5.2 Social Conditions and Issues....................................................................................................... 29
SECTION 6: ENVIRONMENTAL & SOCIAL MANAGEMENT - ADDRESSING SFEGUARD
ISSUES 38
6.1 Beneficiary Selection Process ..................................................................................................... 38
6.2 Informal Occupancy ........................................................................................................................ 42
6.3 Environmental and Social Management Plan (ESMP) for House Construction ............................. 42
6.4 Grant Agreements with Beneficiary Households ............................................................................ 43
6.5 Indigenous People – The Kalinago ................................................................................................. 45
6.6 Forest and Timber Resources .......................................................................................................... 46
6.7 Cultural Heritage ............................................................................................................................. 47
SECTION 7: COMMUNICATION: CONSULTATION, INFORMATION DISSEMINATION 48
SECTION 8: CAPACITY BUILDING .............................................................................................. 50
SECTION 9: GRIEVANCE REDRESS MECHANISM (GRM) ..................................................... 51
9.1 GRM Scope and Summary ............................................................................................................... 51
9.2 World Bank Grievance Redress System ......................................................................................... 53
SECTION 10: MONITORING AND REPORTING ...................................................................... 54
SECTION 11: BUDGET REQUIRMENTS FOR ESMF IMPLEMENTATION ........................ 56
Annex 1: Relevant National Legislation, Policies, and Plans ................................................................. 57
Annex 2: Map of Dominica’s Health Districts ....................................................................................... 61
Annex 3: Map of Dominica’s Village Districts ...................................................................................... 62
Annex 4: Guidelines for World Bank Code of Conduct for Contracted Entities .................................... 63
Annex 5: Role of Direct Players and Key Partners in the Implementation of Safeguards...................... 65
Annex 7: HRP Application Form ........................................................................................................... 67
Annex 8: HRP Environmental and Social Management Plan (ESMP) for Small Construction and
Rehabilitation Activities ......................................................................................................................... 72
Annex 9: Project Results Framework – Dominica Housing Recovery Project....................................... 93
Annex 10: ESMF Mitigation Table ........................................................................................................ 94
Annex 11: Housing Recovery Project ESMF: Consultations ............................................................... 106
3 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
ACRONYMS
need to cross check on final review
BDA Building Damage Assessment
CCA Copper Chrome Arsenate (timber treatment chemical)
CDEMA Caribbean Disaster Emergency Management Agency
CPA Country Poverty Assessment
CREAD Climate Resilient Emergency Agency for Dominica
DSWMC Dominica Solid Waste Management Cooperation
EC$ East Caribbean Dollar
EIA Environmental Impact Assessment
ESMF Environmental and Social Management Framework
ESMP Environmental and Social Management Plan
EU European Union
FM Financial management
GDP Gross domestic product
GRM Grievance Redress Mechanism
GoCD Government of the Commonwealth of Dominica
HH Household
HRP Housing Recovery Project
HTF Housing Task Force
ICT Information and Communication Technology Unit (the Ministry of
Information, Science, Telecommunications and Technology)
IST Implementation Support Team
M&E Monitoring and evaluation
MIS Management Information System
MoF Ministry of Finance
MoHL Ministry of Housing, Lands and Water Resources
MoKA Ministry of Kalinago Affairs
MoP Ministry of Planning and Economic Development
NGO Nongovernmental organization
NP National Park
PAD Project Appraisal Document
PDNA Post‐Disaster Needs Assessment
PDO Project Development Objectives
PID/ISDS Project Information Document/Integrated Safeguards Datasheet
PIU Project Implementation Unit
PPD Physical Planning Division (Ministry of Planning and Economic
Development)
TAC Technical Assistance Center
ToR Terms of Reference
VNA Vulnerability Needs Assessment
4 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
FOREWORD
Adamant to resolve the people’s housing needs on island, the Honorable Prime Minister of Dominica with
Cabinet set forth an agenda to build the destination better with resilient homes, particularly for the more
vulnerable people. This would form part of the Housing Revolution set forth by the Government of the
Commonwealth of Dominica (GoCD) to accommodate residents who lost their homes following Tropical
Storm Erika in 2015, where villages in high risk locations were swept away from flooding and massive
landslides. The World Bank (WB) joined in this effort with a grant subsidy for a Housing Recovery Project
(P166537) to focus on home-owner driven rebuilding in-situ of destroyed houses for 1,700 of the most
vulnerable households, who will be mandated to apply the WB’s environmental and social safeguards in
light of constructing resilient homes. The Housing Recovery Project (HRP) complements the role of relief
and humanitarian partners who have been addressing the first phase of housing recovery with a focus on
temporary and transitional shelter, roof repairs, and minor repairs conducted by house owners.
The Environmental and Social Management Framework (ESMF) is one of many documents that guides the
implementation of Dominica’s Housing Recovery Project. It outlines the inclusion of environmental and
social safeguards of the World Bank from the preparation and readiness phase to the complete closure phase
of the project. In essence, the objective of the ESMF is to serve as a practical tool during project
implementation and monitoring, that will provide operational guidance regarding the management of
environmental and social issues in housing reconstruction to ensure compliance with the relevant laws and
regulations of Dominica and World Bank safeguards policies.
The ESMF overarching context remains applicable with the following supporting HRP main documents:
Project Appraisal Document (PAD); Project Operations Manual (POM); Indigenous People’s Plan (IPP);
Grievance Redress Mechanism (GRM); and a Communication Strategy. Numerous direct players and key
partners at the institutional and community levels are noted in the ESMF.
This document is the result of consultations between various government ministries and departments,
particularly the Ministry of Housing and Lands, the Physical Planning Division, the Kalinago Council, the
World Bank HRP Team and Consultants including the WB safeguards consultants and the IST Senior
Safeguards Advisor, CREAD, direct players and key partners. The ESMF was finalized based on review of
all feedback received by the HRP – Project Implementation Unit. Gratitude is extended to all who
contributed to this framework.
--------------------------------------------------------------------------------
PROJECT NAME: HOUSING RECOVERY PROJECT - HRP
PROJECT ID: P166537
DOCUMENT NAME: HRP ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK –
ESMF
PROJECT SLOGAN: REBUILD HOUSE, STRENGTHEN HOMES - AIDE’ WAGER KAI
5 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
EXECUTIVE SUMMARY
This document presents the Environmental and Social Management Framework (ESMF) for the Dominica
Housing Recovery Project (P166537), which is open to all residents of Dominica. The project overall
development objectives are to contribute both to the recovery of housing for households affected by
Hurricane Maria, and to improve the application of resilient building practices in the housing sector. The
objective of the ESMF is to serve as a practical tool during project development, implementation,
monitoring and reporting, that will provide operational guidance regarding the management of
environmental and social issues in housing reconstruction to ensure compliance with the relevant laws and
regulations of Dominica and World Bank safeguards policies.
Background
The Commonwealth of Dominica is a small upper‐middle‐income country covering 751 km2 with a
population of about 73,500 (2011 Census). On September 18, 2017, Hurricane Maria hit Dominica as a
Category 5 storm with catastrophic effects. A Post‐Disaster Needs Assessment (PDNA) from November
2017 estimated total damages at US$931 million and losses at US$382 million, amounting to 226 percent
of Dominica’s 2016 GDP. The identified needs for reconstruction and resilience interventions to ‘build
back better’ amount to US$1.37 billion. The storm affected 90 percent of the housing stock, with more
than 4,500 houses destroyed and over 20,000 partially damaged. The sector sustained US$354 million in
damages and US$28.5 million in losses, and the PDNA identified US$519.7 million in recovery needs.
The Need for ESMF in Housing
Critical to house stability or vulnerability is the type of structure, design, location and other environmental
and social considerations. It is for this reason that the World Bank environmental and social safeguards
alongside the nation’s governing framework form a fundamental role throughout the project development
and implementation phases. More specifically, the implementation of the ESMF will reduce grievances,
improve project design and implementation efficiency, and reduce excessive cost to the home owner.
Project Components
The Housing Recovery Project (HRP) complements the role of relief and humanitarian partners who have
been addressing the first phase of housing recovery with a focus on temporary and transitional shelter, roof
repairs, and minor repairs conducted by house owners.
The project has three components. Component 1 (US$3.5 million) provides support for housing recovery
systems and capacity building. This includes (i) the establishment of regional Technical Assistance Centers
(TACs) to provide both technical advisory services to homeowners on demand and planning control
functions, and (ii) development of management information and monitoring systems. Component 2
(US$33.5 million) will provide subsidies in the form of small grants for owner‐driven reconstruction or
replacement of houses that were classified as ‘destroyed’. Eligible homeowners would use the grant and
their own resources, if necessary, to undertake the rebuilding to a design of their choice. Approximately
1,700 households with completely destroyed homes (of which 35 percent are expected to be female‐headed)
will receive financial support in the form of a subsidy from the project toward a future house. Component
3 (US$3 million) will finance a Project Implementation Unit (PIU) under the Ministry of Housing and
Lands (MoHL) to be responsible for the overall implementation and coordination of the project activities
(including safeguards, procurement and financial management). It will also finance an Implementation
6 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
Support Team (IST) within the Ministry of Finance (MoF) to provide implementation support on
procurement and safeguards to the PIUs of all World Bank‐funded projects in Dominica.
Policy Framework for Environmental and Social Issues
The Government’s legislation, policies, plans (Annex 1), and guidelines applicable to the project fall into
three broad categories comprising (i) legislation, policies, and strategies related to overall environmental
protection, climate change mitigation, and disaster management, (ii) legislation, policies, and guidelines
related to land and physical development, and (iii) World Bank (WB) environmental and social safeguards,
including for indigenous peoples (the Kalinago). During project appraisal, the following WB safeguard
policies were found to apply to the project. Environmental safeguards are: OP/BP 4.01 Environmental
Assessment, OP/BP 4.09 Pest Management, and OP/BP 4.11 Physical Cultural Resources. Social safeguard
is: OP/BP 4.10 Indigenous Peoples.
OP/BP 4.10 Indigenous Peoples is triggered since the Kalinago are recognized as indigenous people by the
Government of Dominica, and also meet the World Bank criteria for applying the Indigenous Peoples
Policy. Consultations have been held in the Kalinago Territory, and an Indigenous Peoples Plan for the
Kalinago Territory has been drafted, and has informed this ESMF.
Project appraisal found that OP/BP 4.12 on Involuntary Resettlement is triggered on a precautionary basis
to address instances of economic displacement and/or temporary involuntary resettlement. Nevertheless,
currently there has been no justification to apply it. The project will be providing grants to households based
on an ‘owner-driven’ housing reconstruction model, where the beneficiary is involved in and agrees to the
specifics of the design and siting of reconstruction activities in-situ, and not requiring temporary relocation,
and has the option of choosing not to receive project assistance. The project’s housing reconstruction
activities are all demand-driven, thus totally voluntary, and will therefore not involve involuntary land
acquisition or resettlement. Similarly, the instances of economic displacement and/or temporary
involuntary resettlement that could potentially require application of the Policy are not possible to
materialize. This could be the case where a new core house is to be built on a different footprint on the
same site to mitigate site hazards, since this could affect its own crops or other assets. Under a demand-
driven approach where a house owner is voluntarily agreeing to reconstruct a house on his/her own land,
the potential affectation of its own crops or economic trees is not considered economic displacement eligible
for compensation. If a house owner considers the requirement to site a new house for safety reasons in a
different location on his/her land to be onerous, he/she has the option to refuse project assistance to rebuild
the house.""
Project Implementation Arrangements
The Government of Dominica has the overall responsibility for implementing the project, including its
social and environmental management, with the PIU guiding project activities. The PIU will include
environmental and social specialists for providing oversight of and compliance with environmental and
social requirements of the contracted entities, project beneficiaries and contractors. This will be aligned
with the housing construction laws of Dominica as per requirements and processes of the Physical Planning
Division and their supporting framework in the Ministry of Housing and Lands. Where feasible, they will
be supported by the IST and guided by the Climate Resilient Emergency Agency for Dominica (CREAD)
with high level oversight by the Housing Task Force.
7 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
In the localities where the project financed housing reconstruction activities will take place, the institutional
counterpart will be Village Councils (in the Kalinago Territory the Kalinago Council and Hamlet
Development Committees). The councils are popularly elected bodies empowered by law to regulate and
administer affairs in their respective areas. Health and Village Districts island wide are mapped in Annexes
2 and 3 respectively. Contracted entities under the project and beneficiaries have various roles in the
execution of safeguards throughout the project implementation that are outlined in this framework. Major
contracted entities to support implementation include: (i) Technical Services (architects, engineers) who
will support eligibility screening processes prior to construction, and will also facilitate the home owner
driven process once the beneficiaries are identified; (ii) the firm responsible to set up a database to support
the housing program through MIS and other services, who will commence before and continue during
construction phases; and (iii) the Design and Supervision Firm who will commence once beneficiaries are
known and throughout decommissioning of site/closure of construction. Other key partners include but are
not limited to government departments, statutory bodies, banking institutions, NGO and civic organizations,
religious, and academia/professionals. All consulting entities will follow a code of conduct directed by the
PIU noted in Annex 5.
Environmental and Social Conditions in the Project Area
Environmental Conditions and Challenges
Environmental conditions and challenges of relevance for the housing reconstruction activities derive in
part from Dominica’s vulnerability to natural disasters from weather-related and geophysical events due to
its topographic features and location within the Atlantic hurricane belt. This is compounded with the seismic
and volcanic risks associated with tectonic plates bordering the island chain. Moreover, the island’s
mountainous, rugged landscape and extensive hydrological system creates significant engineering
challenges to reducing infrastructure vulnerability to natural disasters and climate change.
Separate from this important challenge that results for instance in landslides and flooding are important
risks that must be minimized on location of houses. In addition, important environmental challenges involve
disposal of debris including the possibility of safe handling and disposal of asbestos and access to aggregate.
Another important challenge includes pest control. Though least likely, chance finds of physical cultural
resources as well as buried bodies may be found.
Hurricanes. The project’s support for ‘building back better’ through technical assistance and advice on
hurricane resilient building techniques for both the house reconstruction directly funded by the project, and
for home owners undertaking repairs on their own, will contribute to mitigate the destructive impacts of
future hurricanes and tropical storms. Separate from this, during the hurricane season, there is the possibility
of a storm occurring during construction which may cause temporary disruption on project implementation.
Volcano and Seismic Risks: In addition to risks associated with hurricanes, volcanic activity and
earthquakes present a historically minor, but continuous hazard to the housing sector.
Geotechnical and Hydrological Risks (landslide or flooding). The exposure of specific housing sites to
geotechnical and hydrological risks (landslide or flooding) will be appraised during the building
assessments to determine potential eligibility for housing reconstruction assistance, and if the risk is
assessed as unacceptable, even after site remediation, the house owner will be referred to other housing
programs.
8 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
Access and Sustainable Use of Aggregate and Timber (use of forest and river resources). Dominica
has the most extensive forests in the entire Eastern Caribbean covering about 60 percent of the island and
365 rivers. National Parks and Forest Reserves cover about 22 percent of Dominica, and approximately 27
percent of the island’s forests are designated as protected, inclusive of a UNESCO World Heritage Site,
Morne Trois Pitons National Park. Hurricane Maria’s winds and intense rainfall caused widespread damage
to the forest system and increased material deposit throughout the island river bed. An estimated 10 to 20
percent of the forest trees were knocked down.
Timber is one of the basic construction materials used in the more remote rural areas. Use of downed trees
or local logging for housing reconstruction must be guided by the Forestry, Wildlife and National Parks
Division to reduce the risk of unregulated deforestation, and would at the same time reduce dependency on
imported lumber and create local employment.
To avoid negative environmental impacts from quarrying in the vicinity of the communities where project
activities take place, the aggregate (sand and gravel) required for house construction will only be supplied
from existing approved quarries. Another natural resource at risk during the construction is the use of river
stones. Following the hurricane, the GoCD embarked on extensive dredging of some rivers. Material
removed in the dredging of rivers may be used, provided that government approves the quality and quantity
by the respective entities. The Forestry, Wildlife and National Parks Division is a key partner in this process.
Debris Management. Disposal of the debris from damaged and destroyed houses, as well as the debris that
will be generated during reconstruction, will need to be managed through arrangements involving the
Dominica Solid Waste Management Corporation, private waste disposal contractors, and the communities
receiving assistance, to ensure that all debris is disposed of at the Fond Cole sanitary landfill (or other
location approved by the GoCD and the PIU).
Pest Control and Asbestos Handling. Pest control and the potential of safe handling and disposal of
asbestos are possible environmental issues that may arise during the demolition and construction of the
houses. For safe handling, the necessary channels to address pest control depends on the nature and may
require partners like Forestry, Wildlife Division, Pest Control Board and approved pest management
companies.
Chance Finds (Physical Cultural Resource and Skeletal Remains): While the civil works undertaken
under the project are small scale, and while most house reconstruction will be undertaken in situ, the
possibility nevertheless exists of archaeological chance finds from both pre-Colombian and later colonial
and Creole settlements in Dominica. There is as yet no archaeological legislation in Dominica, but the
project will apply chance find procedures to ensure that any finds are reported and handed over to Dominica
Museum in Roseau (the national museum of Dominica). In addition, in situ works may result in chance find
of skeletal remains, which will require reporting to the Dominica Police Force Central Investigation
Department.
Social Conditions and Challenges
Damage Assessment. A Building Damage Assessment (BDA) conducted in December 2017 showed that
medium‐size houses (500 to 1,200 sq.ft) dominate the housing stock with 9,825 units, and of these 40
percent sustained major or total damage. However, small house units (less than 500 sq.ft), which comprise
31 percent of the housing stock (7,525 units), sustained a higher level of major or total damage, affecting
62 percent of that group. Of the destroyed houses, only 2 percent were insured. When the project starts
implementation during 2019, the damage status of many homes will have changed due to repairs undertaken
9 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
by the owners or with support from other programs, though likely less so for destroyed homes that were
occupied by the vulnerable households that are the primary target group for the project. Updated
information on same will be captured during the demand-driven application process and the subsequent site
assessment to determine beneficiary eligibility selection.
Home Ownership. There are no recent data on private land ownership, but available information indicates
that about 80 percent of residents have either a registered title, a registered deed, or an unregistered deed.
Among the remaining 20 percent are households who have not been able to pay registration costs to obtain
a title document, and others who reside under informal arrangements as tenants or leaseholders in houses
they do not own, or in houses they own, but on land owned by somebody else. Eligible households will
need to source these documents and the project may facilitate same where required. The project will not
support tenants or leaseholders since there are other housing programs suited to this need and the project
does not support commercial property.
Poverty and Vulnerability. Rural poverty continues to represent a major challenge, with 75 percent of the
poor living in rural areas. The project’s prioritization criteria for identification of eligible beneficiaries for
housing reconstruction assistance include (i) households that are still in hurricane displacement centers, and
(ii) particularly vulnerable households comprising single parent households with children under 15 years,
households with a disabled household head, and households with an elderly household head. Women
represent 39 percent of the heads of households in Dominica, and the Vulnerability Needs Assessment that
was prepared after the hurricane highlighted, that there were over 1,100 single mothers with uninsured
houses that had either been destroyed or severely damaged. Female headed households with dependent
children include grandmothers as caregivers for grandchildren, and they make up a large proportion of those
still in temporary shelters. Since these categories of prioritized beneficiaries are likely to have limited
access to information about the project, and also limited ability to act on such information, the HRP
Communication Strategy will seek to disseminate information on the project including social services, local
government and shelter managers to create awareness and engage these persons in the self-driven
application.
Construction Labor Agreement. While the owner-driven model for house reconstruction will involve
beneficiary house owners/occupants in reconstruction activities assisted by other community members with
appropriate skills, the house reconstruction will also involve pre-qualified building contractors along with
modest labor influx. To manage the community-contractor relationship, the project will follow an approach
which has been successfully applied in other civil works projects in Dominica using local contractors. It
involves a meeting held before the start of physical works between the concerned local governance entity
and the contractor, where the PIU will be represented, and where issues related to the work and the
contractor’s presence are discussed and agreed upon in writing.
Indigenous Kalinago. Dominica was originally populated by Amerindian peoples, known as Caribs or
Kalinago, and is the only island in the Caribbean still to possess distinct communities of these indigenous
people. The Kalinago inhabits a territory of 3,782 acres stretching over 9 miles on the East coast of
Dominica with eight hamlets and a 2011 population of 2,145 consisting of 652 households. A Carib
Reserve Act was enacted in 1978, the year of Dominican independence, and its name amended to the
Kalinago Territory Act in 2015. A Department of Carib Affairs was established in 2000 and upgraded to a
Ministry of Kalinago Affairs in 2014. The Kalinago Territory Act describes the establishment of the office
of the Kalinago Chief and the powers of the Kalinago Council. All land in the Territory is under the custody
and management of the Kalinago Council, and no individual can buy or sell parcels of land or use land as
collateral for loans. The Council is solely responsible for allocating land for all purposes. Hurricane Maria
10 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
wrought very extensive damage on housing in the Kalinago Territory, which has a much higher poverty
rate (at 49.8 percent) compared with the national level (at 28.8 percent). Figures on the damage level varies
between different assessments, but there is agreement that the proportion of totally destroyed houses is
more than twice as high as the national level. The BDA will be used to verify and validate such information
in the selection of beneficiaries, as well as decisions regarding the choice of locations where the project
will start physical implementation.
Addressing Environmental and Social Safeguard Issues
Rather than separate the consideration of environmental and social issues as they relate to beneficiary
selection, house design and planning, and civil works, these issues and the associated measures to mitigate
and manage them are dealt throughout the project implementation process. The implementation cycle will
commence with outreach and communication on the environmental and social safeguards, the intake and
application process that progresses to the beneficiary selection and then to the civil works for housing
reconstruction and closure.
Outreach and Communication on Safeguards: The HRP Communication Strategy will inform of the
ESMF and its’ application on safeguards throughout the project cycle. It will also include capacity building
to homeowners, contractors and government entities on same that will improve planning processes to
mitigate and manage environmental, social, health and safety risks.
Eligible Beneficiary Application Process: A call for application will be made using the HRP
Communication Strategy. The HRP Application Form (Annex 7) will include the eligible criteria on
environmental safeguards to ensure that homes will be constructed in safe conditions away from flood and
landslide prone areas. The application form will also include socio-economic criteria to be completed by
the applicant. The process is demand-driven.
Beneficiary Selection: To enable the selection of individual beneficiary households for reconstruction
assistance, four preparatory activities will have to be undertaken: (i) a national information campaign to
inform the population about the project approach, the criteria for beneficiary selection, the deployment of
technical services/TACs and building contractors, and the Grievance Redress Mechanism, (ii) set up of a
Beneficiary Selection Review Committee, (iii) set up of a Grievance Committee to address complaints on
the Project, and (iv) a site visit to assess the environmental risks.
The eligibility criteria that will be applied in the beneficiary selection process (Section 6.1) involve both
environmental and socio-economic considerations. The selection will comprise three ‘steps’, with Step 1
covering a set of eligibility criteria that determine whether home-owner applicant meets the physical and
socio-economic criteria of the project as a potential beneficiary, and which involve on-site assessments.
Step 2 will enable a categorical prioritization among the potentially eligible beneficiaries based on socio-
economic and demographic vulnerability criteria, which address protracted displacement, poverty status,
gender, and disability considerations. Step 3 will consist of verification and validation involving a review
of the final list of the beneficiaries by the HRP Beneficiary Selection Review Committee, who will produce
a list of confirmed beneficiaries. This list will be made public locally and on-line (project website at MoHL)
as a final step in the validation and confirmation.
The HRP Beneficiary Selection Review Committee will comprise no more than seven members, involving
representatives from local government, religious, NGO or other civic group, prominent local citizen, and
professional/academia. Specifically, the composition of the will include:
11 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
Grant Agreements with Beneficiary Households: The project will enter into a Grant Agreement with the
selected beneficiary households regarding the reconstruction of their house. Prior to the finalization of the
Grant Agreement, the PIU supported by the Design & Supervision Firm will inform each beneficiary of the
procedures involved in the housing reconstruction support under the project, will assist with a house design
within their individual financial resources, and will assist with obtaining a building permit and title
documentation, if needed. A subsidy of EC$50,000 will be provided to the eligible home owner. In addition
to technical assistance that will be provided to the home owner, the financial support will cover the cost to
build a small future home approximately 500 sq. ft in size.
Environmental and Social Management Plan (ESMP): During the assessment of environmental hazard
risks for potential beneficiary housing sites that was undertaken during Step 1 of the beneficiary selection
process, all destroyed houses found to be exposed to such risks have been excluded as ineligible for
reconstruction assistance (unless they could be re-sited to a location without environmental hazard risks on
the beneficiary’s property). The environmental impacts to be considered during construction therefore
involve only those related to good practice management measures for small-scale construction works. To
manage these impacts, along with health and safety issues and social risks, a standard house level ESMP
will be developed based on a standard ESMP for small civil work (Annex 8). Compliance monitoring of
ESMPs inclusive of standard operating procedures will be done by the Design & Supervision Firm and
managed by the PIU. In addition to the individual house site specific social risk management activities
indicated in the ESMP, the project will engage at the community level with the Village Councils to manage
broader social risks such as those regarding the presence of building contractors.
Indigenous Peoples Plan – The Kalinago: All consultations regarding the preparation and implementation
of the Housing Recovery Project in the Kalinago Territory will be conducted through the elected Kalinago
Council and the Ministry of Kalinago Affairs. Thus, the institutional framework exists for ensuring free,
prior, and informed consultation resulting in broad community support to the project by the Kalinago people
as required by OP 4.10 on Indigenous Peoples, and such support has been expressed during the initial
consultations already held in the area. The project’s overall approach to community engagement would
also, with a few adaptations, suit conditions in the Kalinago Territory. Adaptations that would need to be
agreed by the Kalinago involve inter alia the beneficiary selection criteria and process, and the GRM
arrangements and process. An Indigenous Peoples Plan (IPP) will be prepared to support the unique needs
of the Kalinago in Dominica under the HRP.
Beneficiary Selection Review Committee
Representative of the Village / Kalinago Council
Representative of Religious Organisation
Representative of a Credit Union, Financial Institution or Cooperative Association
Representative of any NGO's or other Civic Group in the region
Other Prominent Citizen e.g. Justice of Peace, community activist
Professionals/Academia
Shelter Managers
12 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
Communication: Consultation, Information Dissemination
During the preparation of this ESMF, consultations were held about the project’s environmental and social
aspects with relevant departments of the Government, potential beneficiary groups, and with the Kalinago
Council and MoKA. Prior to that, initial consultations were held with the Kalinago community during
project preparation in February 2018, and by the Government in connection with preparation of a draft
Indigenous Peoples Plan.
Project implementation will be preceded by nation-wide information campaigns on the project and its
approach using radio and/or television among other media channels. Following the deployment of project
staff to the geographical locations where village level activities will take place, consultations will take place
with Village Councils regarding the project approach, procedures and work plan, the beneficiary selection
process, the GRM, and the presence and mandate of the PIU contracted entities, and building contractors
with a ‘code of conduct’ for contractor staff. Subsequently, a meeting with the HRP Beneficiary Selection
Review Committee will be held to review, verify and validate the list of identified beneficiaries of the
housing grant.
Follow-up meetings between local government entities (and interested beneficiaries), contractor(s), the
PIU, and staff from TAC/Design & Supervision Firm will be held at regular intervals to review the status
of construction, and to discuss and if possible, resolve complaints received through the GRM. In the
Kalinago Territory, similar meetings will be held at the level of the Kalinago Council and with the Hamlet
Development Committees in locations where project implementation is taking place.
Capacity Building
Capacity building will be important for the implementation of the safeguard-related activities described
above, and will be required at different levels of the institutional set-up for the project. Safeguards staff
from the PIU (supported by their counterparts from the IST) will provide safeguards related capacity
building for the entities contracted by the PIU, beneficiary homeowners, contractors and the workers,
including their designated safeguards staff, as well as to relevant staff of the Physical Planning Division
and the Division of Housing in the form of orientation meetings and trainings. The meeting and training
sessions will take place before construction and during construction. Local government entities comprising
the Village Councils, and the Kalinago Council and Hamlet Development Committees in the Kalinago
Territory will also be oriented on the safeguards implementation process outlined in the HRP
Communication Strategy. Overall, capacity building on the construction of houses that are stronger and
more resilient to multiple risks will be conducted through orientation meetings, workshops and training
sessions prior and during construction works. Capacity building in the: implementation of: safeguards;
handling of complaints and resolutions; free prior and informed consent; improved planning processes
including data recording and analysis will form part of project implementation.
Grievance Redress Mechanism
The project will establish a GRM to receive and process complaints and grievances related to project
activities, and to provide the public with an avenue to provide feedback on the reconstruction activities
supported by the project. The PIU will manage grievances and resolutions based on the HRP GRM
document. This includes administrative responsibility for the GRM, including the formation and
management of a Grievance Committee(s).
13 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
Further, the PIU will conduct orientation sessions on the GRM with all entities contracted under the HRP,
as well as the beneficiaries, the GRM Committee(s), direct players and key partners. The Design &
Supervision Firm will be responsible to set up a database to record complaints and appeals and the decisions
taken on them for GRM management and reporting. Training sessions on same will be conducted by the
Design & Supervision Firm to PIU staff and other appropriate personnel identified by the PIU. It is
expected that the bulk of complaints will be received at the local level particularly during construction or
otherwise filed on the Grievance Complaints and Logging System that will be established under the project,
and that a large portion of these can be resolved at that local level by the Design & Supervision Firm through
regular meetings with local government entities and appropriate stakeholders in accordance with evolving
complaints. The PIU Grievance Committee will address all complaints that could not be resolved at the
local level with a clear process for decisions taken. The proposed HRP Grievance Redress Committee
structure will comprise representatives from the following but not limited to:
The diagram below describes the process that will be used to resolve any grievances:
Details on the system to log complaints and to resolve them are noted in the HRP Grievance Redress
Mechanism document.
HRP Grievance Redress Committee
Representative of the Village / Kalinago Council
Representative of Religious Organisation
Representative of a Credit Union, Financial Institution or Cooperative Association
Representative of any NGO's or other Civic Group in the region
Other Prominent Citizen e.g. Justice of Peace, community activist
Professionals/Academia
Follow up and Close out
Act
Investigate
Acknowledge
Screen
Record
Receive Grievance
14 | P a g e | E S M F F i n a l D r a f t 3 M a y 2 0 1 9
Monitoring and Reporting
The overall monitoring and evaluation (M&E) for the project will be managed by the PIU, with high level
oversight by the Housing Task Force. A project Management Information System (MIS) will house the
data to be used in the generation of periodic reports and updating of indicator results. The core of this MIS
will be a registry database, which will contain the data from the housing recovery program including the
beneficiary selection and the physical planning and implementation process as well as the grievance
complaints and resolutions. The primary data for the MIS will be collected on site using tablets for direct
data entry by the Technical Services (engineers, architects) hired by the PIU and subsequently by the Design
and Supervision Firm for generation of consolidated reporting covering the entire project. Support for the
project implementation will also be provided at the level of each of the communities (Village Councils and
Hamlet Development Committees). The MIS would contain the data for progress reporting by the Design
& Supervision Firm on achievement of construction targets and possible bottlenecks in reaching these. It
would also allow comparisons between results in different Districts, and between the Kalinago territory and
elsewhere in Dominica. Separate from the database, site visits will also be conducted by the PIU to verify
safeguards implementation. At critical stages throughout the project, including key milestones, reporting
by each contracted entity is required as guided by the PIU.
Budget Requirements for ESMF Implementation
The budget requirements for implementation of the ESMF are covered by (i) the funding allocated for the
project components that include the planning, technical assistance, consultation and information
dissemination, and monitoring of housing repair and construction (Sub-Component 1.1, 1.2, 2.2 and
Component 3), and (ii) the costs of construction of individual house undertaken in compliance with the
house-level ESMP (Sub-Component 2.1).
SECTION 1: INTRODUCTION
The Environmental and Social Management Framework (ESMF) is developed to protect people and the
environment in investment projects supported by the World Bank (WB). It responds to new and varied
development demands and challenges that have arisen overtime. It makes important advances in areas such
as transparency, non-discrimination, public participation and accountability, including expanded roles for
grievance mechanisms.
This document presents the ESMF for the Dominica Housing Recovery Project (P166537). The objective
of the ESMF is to serve as a practical tool during project implementation and monitoring, and to provide
operational guidance on both what needs to be done, and how what is needed should be done regarding the
management of environmental and social issues in housing reconstruction. The framework is intended to
ensure that for all activities financed by the project, efforts are made to identify and avoid or minimize
adverse environmental and social impacts, and where these cannot be avoided, that necessary mitigation
measures are developed and implemented following the relevant laws and regulations of Dominica and
World Bank safeguards policies. The ESMF provides information about the project, its environmental and
social context, social and environmental risks and mitigation measures, institutional arrangements,
monitoring indicators, and capacity building and training requirements to ensure that the potential negative
environmental and social impacts of project activities are minimized or mitigated, and positive impacts are
encouraged and enhanced.
Other documents of the HRP aligned with the ESMF are: Project Appraisal Document (PAD); Project
Operations Manual (POM); Indigenous People’s Plan (IPP); Grievance Redress Mechanism (GRM); and a
Communication Strategy.
SECTION 2: PROJECT DESCRIPTION
2.1 Background
The Commonwealth of Dominica is a small upper‐middle‐income country, which is one of the Windward
Islands in the Lesser Antilles archipelagos. Dominica’s land area is 751 km2, and its population in 2011
was about 73,500. With a gross domestic product (GDP) of US$581.48 million, Dominica’s economy
depends predominantly on agriculture and tourism. Poverty remains a pervasive development issue, with
a poverty headcount of 28.8 percent at the time of the last Country Poverty Assessment (CPA) conducted
in 2009.
Dominica is particularly vulnerable to natural disasters from weather-related and geophysical events. Due
to its location within the Atlantic hurricane belt, high-intensity weather events such as high wind, excess
rainfall and hurricanes, continue to have adverse effects on vulnerable populations and the productive
sectors of the country’s economy. Moreover, the island’s mountainous, rugged landscape creates significant
engineering challenges to reducing infrastructure vulnerability to natural disasters and climate change.
On September 18, 2017, Hurricane Maria (Category 5) hit Dominica with sustained winds of 170 mph that
resulted in catastrophic effects. As the hurricane passed over the center of the island, Dominica was
exposed to extraordinary winds for more than three hours, accompanied by intense rainfall, which triggered
flash floods and landslides. According to official sources, 30 persons lost their lives and 34 persons were
declared missing. The Prime Minister declared a state of emergency on September 20, 2017.
A Post‐Disaster Needs Assessment (PDNA) led by the World Bank in collaboration with the United
Nations, the Eastern Caribbean Central Bank, the Caribbean Development Bank, and the European Union
(EU) estimated total damages at US$931 million and losses at US$382 million, amounting to 226 percent
of Dominica’s 2016 GDP. The identified needs for reconstruction and resilience interventions to ‘build
back better’ amount to US$1.37 billion. The hurricane affected 90 percent of the housing stock, with more
than 4,500 houses destroyed and over 20,000 partially damaged. The sector sustained US$354 million in
damages and US$28.5 million in losses, and the PDNA identified US$519.7 million in recovery needs.
2.2 Project Description
The Housing Recovery Project (HRP) complements the role of relief and humanitarian partners who have
been addressing the first phase of housing recovery with a focus on temporary and transitional shelter, roof
repairs, and minor repairs conducted by house owners.1 It also leverages the Bank’s global experiences in
post‐disaster housing reconstruction in Haiti, Nepal, the Philippines, Tonga, and Indonesia as well as post-
hurricane emergency recovery loans in small island states. The project will contribute strategically to the
housing sector in Dominica and address critical gaps by focusing on rebuilding destroyed homes and
supporting the resilience of the housing stock against a Category 5 hurricane standard.
The Project Development Objectives (PDOs) are to contribute both to the recovery of housing for
households (HH) affected by Hurricane Maria and to improve the application of resilient building practices
in the housing sector. Direct project beneficiaries are expected to make up approximately 50 percent of the
households which experienced some level of damage, and comprise approximately 12,000 households
1 The partners include the United Nations Development Programme (UNDP), the International Organization for
Migration, the International Federation of the Red Cross, Samaritan’s Purse, Is There Not A Cause, Caritas, Catholic
Relief Services, All Hands and Hearts, Emergency Architects, IsraAid, Caribbean Disaster Emergency Management
Agency, and the United Nations Children’s Fund.
17 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
(32,400 persons, of whom 15,500 are women), who will be assisted through a package of technical services
for resilient rebuilding of houses. Of these, approximately 1,700 households with completely destroyed
homes (of which 35 percent are expected to be female‐headed) will receive financial support in the form of
a subsidy from the project toward a future house.
Project components: The HRP consists of three major components with sub-components. Environmental
and social safeguards fall mainly under Component 2 of the HRP. Equally important to effect efficiency
on reconstruction of houses is the incorporation of safeguards in Components 1 and 3 in order to set the
processes in place and to build capacity routed in the environmental and social elements.
Component 1: Support for Housing Recovery Systems and Capacity Building (US$3.5
million) This component will set up systems to manage, expedite, and monitor the housing recovery program and
will build capacity and a sustainable framework for development planning in the housing sector. For sub-
components 1.1 & 1.2, safeguards will form part of work processes, reporting and capacity building. For
sub-component 1.3, safeguards will be incorporated in the technical design.
Subcomponent 1.1: Development Planning Support to Technical Assistance Centers and the Project at the
Local Level (US$2.7 million). This sub‐component will support the establishment and operation of regional
Technical Assistance Centers (TACs) which have a dual function of technical advisory services and
planning control functions. The TACs will provide technical advisory services to homeowners on demand,
facilitate processing of planning and building controls, conduct building assessments, facilitate technical
training on the application of resilient building practices, and monitor the compliance with building codes
and processing permits. The purpose of the TACs are to guide and encourage resilient practices in
construction and to strengthen planning control capacity at a local level. Where feasible, the TACs may
also support the Project Implementation Unit (PIU) in the collection of demographic information required
for administering eligibility under the project. The project will provide support to expand the staffing and
the number of TACs and sustain operation through the project implementation period. This support will
include contracting of a consulting services firm to support the TACs and the Physical Planning Division
(PPD) under which the TACs operate.
Subcomponent 1.2: Development of Management Information Systems to support planning and monitoring
processes in project agencies (US$0.6 million). Management information and monitoring systems will be
developed under the project to support the housing recovery program and the physical planning process.
The systems will provide support to Ministry of Housing (MoHL) and Ministry of Planning (MoP) and will
be implemented in conjunction with the Information and Communication Technology (ICT) Unit for
ongoing technical support and operation. A consulting firm will be engaged to supply and install IT
services, and this will include development of electronic systems for (i) a registry of households and
homeowners, including demographic and personal identification data, aligned inter alia with verification
from the Building Damage Assessment (BDA) and other relevant databases for social support, vulnerability
assessment, and Government services; (ii) administration of beneficiaries eligible for support under the
project; (iii) M&E of project activities, outputs, and results; (iv) project and MoHL communication
strategies; and (v) project financial management and reporting.
Subcomponent 1.3: Technical Design of a New Physical Development Planning Office (US$0.2 million)
will finance the preparation of detailed designs of a new building for the Physical Development Planning
Office on the same site of the previous building which was completely destroyed by the hurricane.
Environmental and social consideration will be incorporated in the design.
18 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Component 2: Support for Reconstruction of Houses (US$33.5 million).
This component will provide subsidies in the form of small grants for owner‐driven reconstruction or
replacement of houses that were classified as ‘destroyed’. Eligible homeowners would use the grant and
their own resources, if necessary, to undertake the rebuilding works to a design of their choice. Safeguards
form part of the eligibility criteria for risk mitigation and for socio-economic vulnerability assessment under
subcomponent 2.1, while subcomponent 2.2 focused on monitoring of safeguards.
Subcomponent 2.1: Support for Reconstruction of Houses (US$31.45 million). This sub‐component will
provide Housing Grants to eligible homeowners for reconstruction or replacement of housing destroyed by
Hurricane Maria. A subsidy up to a US$18,500 (approximately EC$50,000) fixed grant will be provided to
around 1,700 homeowners for either reconstruction or replacement of the destroyed building. Eligible
homeowners will select the scope and approach to reconstruction and fund the activity with the support of
the fixed grant and own resources. The grant will be conditional on the construction having a valid building
permit, certified Physical Planning Division (PPD) inspections, and a completion certificate verifying that
the building complies with the applicable Building Code and Guidelines. The grant would be disbursed to
the homeowner’s banking institution in tranches, aligned with major stages of completion, for payment to
the home owner who undertakes the house construction.
Subcomponent 2.2: Design and Supervision of House Reconstruction (US$2.05 million). This
subcomponent will provide design and supervision services for the reconstruction works for eligible
beneficiaries, including inter alia, those needed for the construction to meet building guideline requirements
for resilience to Category 5 hurricane events and applicable environmental, social, and health and safety
safeguards requirements. A consulting firm will provide support for design and supervision services for
the house reconstruction works by eligible beneficiaries undertaken under Subcomponent 2.1.
Component 3: Project Management and Coordination (US$3 million)
This component will finance the establishment and operation of the Project Implementation Unit (PIU)
under MoHL to serve as the unit responsible for the overall implementation and coordination of the project
activities, and for the associated safeguards, procurement and financial management (FM) responsibilities.
Component 3 will also finance the setting up of an Implementation Support Team (IST) to be established
within the Ministry of Finance (MoF). The IST will provide close implementation support on procurement
and safeguards to the PIUs of all World Bank‐funded projects. The Project will finance (a) incremental
dedicated staff for the establishment and operations of the IST and the PIU; (b) the hiring of other technical
experts needed for project preparation and implementation; (c) the preparation of environmental and social
safeguards studies and instruments including development of a communication strategy, and a complaints,
feedback and grievance system; (d) the carrying out of the fiduciary aspects of the project including audits;
(e) the provision of training and workshops; (f) the financing of the necessary goods, equipment, and
operating costs; and (g) the implementation of safeguards instruments.
This initiative augments and bolsters the GoCD drive for improved planning controls and increased
compliance to resilient construction practices. Further, it supports the GoCD’s long-term plan for
improving the coordination between services relating to development and physical planning, land
management and housing by advancing the design of a new building which would co-locate the relevant
services.
SECTION 3: POLICY FRAMEWORK FOR ENVIRONMENTAL AND
SOCIAL ISSUES
3.1 National Laws and Regulations
The GoCD has introduced legislation, policies, plans, and guidelines, and has signed international treaties
and conventions, that have provisions regarding social development and safeguards issues relevant for the
Housing Recovery Project. The existing national legislation and international agreements related to social
development and safeguards of Indigenous Peoples (IPs) have been reviewed to streamline the safeguard
requirements of the government regarding the Kalinago People for this project. The national legislation is
the Kalinago Territory Act of 2015, and the international agreements are the ILO Convention No.169 on
Indigenous and Tribal Peoples enacted in 1989 and ratified by Dominica in 2002, and the United Nations
Declaration on the Rights of Indigenous Peoples (2007) ratified in 2007.
The legislation, policies, plans, and guidelines relevant to safeguards in the context of this project can be
categorized broadly into the following three groups:
1. Policies, strategies, and legislation related to overall environmental protection and climate change
mitigation, and disaster management.
2. Legislation, policies, and guidelines related to land and physical development.
3. Safeguards for Indigenous Peoples.
The key policies, strategies, and legislation related to overall environmental protection are the Dominica
Climate Change Adaptation Policy of 2002, the National Climate Change Adaptation Strategy of 2009, and
the Climate Change, Environment, and Natural Resources Management Bill of 2014, which has been
approved but not yet adopted by the House of Assembly. The planning related to emergency management
include the National Emergency Management Policy of 2009, and the Disaster Management Plan of 2009.
Regulation of physical planning and land tenure are covered by the Physical Planning Act of 2002, the Title
by Registration Act of 1980, the Solid Waste Management Act of 2002, and the National Land Use Policy
of 2014. Land acquisition is regulated by the Land Acquisition Act of 1946;2 and resettlement to mitigate
climate hazards by the Dominica Resettlement Strategy of 2015. With regard to housing reconstruction,
the Guide to Dominica’s Housing Standards of 2018 updates and amends earlier building regulations
(Building Code and Building Guidelines). The Kalinago Territory Act of 2015 defines the rights of the
Kalinago People,3 and gender issues are addressed by the National Policy and Action Plan for Gender
Equity and Equality of 2006. These acts and regulations, as well as the international agreements on
indigenous peoples together provide an overall regulatory framework that defines both process and
procedures for environmental and social protection, mitigation, and management (see Annex 1 regarding a
description of the relevant legislation).
Enforcement of legislation is a problem throughout all sectors. Some of the constraints being experienced
are linked to insufficient financial and human resources. Additionally, in some cases responsibilities for
enforcement is not clearly mandated or spread over two or more ministries.
2 The Act has been amended in 1966, 1971, and 1986. 3 The Kalinago Territory Act of 2015 is an amendment of the Carib Reserve Act of 1978, which in turn reaffirmed the
territorial boundaries first established by colonial authorities in 1903, and which legally established common
ownership of land within the reserve.
20 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
3.2 World Bank Safeguard Policies
The applicability of the following World Bank policies identified during project appraisal is considered
below: OP/BP 4.01 Environmental Assessment, OP 4.09 Pest Management, OP/BP 4.10 Indigenous
Peoples, OP/BP 4.11 Physical Cultural Resources, and OP/BP 4.12 Involuntary Resettlement. All activities
financed by the project will comply with safeguards requirements. In addition, activities without direct
adverse safeguard impacts including the detailed technical design of a new Physical Development Planning
Office financed under Subcomponent 1.3, and ToR for any studies to be conducted under the project will
consider relevant environmental and social issues in order to reflect the principles of World Bank
safeguards.
3.2.1 Environmental Policies
OP/BP 4.01 Environmental Assessment: Given the nature of the proposed program, this policy is triggered.
The overall project is classified as Category B, based on the potential level of impact as it involves the
reconstruction of houses that were classified as ‘destroyed’. The civil works will take place in different
locations across Dominica, and impacts will be small scale, site-specific, and temporary for the house
reconstruction. The small-scale construction works will have minor risks related to health and safety.
Negative impacts and risks will be listed in a house-level Environmental and Social Management Plan
(ESMP), and mitigated through the application by the works contractor(s) of good construction and
management practices, with close supervision from the PIU, and the Design & Supervision Firm. Since
extraction of construction material (sand, gravel) will only take place from approved active quarries, there
would be no risk of increased local vulnerability to landslides and soil erosion in project areas. Disposal of
debris including the possibility of asbestos from destroyed houses and debris from construction will be to
Dominica’s principal landfill in Fond Cole near Roseau (or other approved by the GoCD and the PIU). The
requirement to acquire aggregate from approved active quarries, and disposing all debris to the Fond Cole
(or other approved by the GoCD and the PIU) landfill, as well as managing other environmental issues
noted in the ESMF will be included in works contracts, and compliance will be monitored by the PIU and
the Design & Supervision Firm.
OP 4.09 Pest Management: This policy is triggered as pesticides may be required for pest control (termites)
during demolition and in the rehabilitated or newly constructed houses. Proper procedures for storing and
applying small quantities of termite control pesticides are included in the house-level ESMP, and will be
included in the works contracts with building contractors, so that such activities are only undertaken by
licensed and registered pest control professionals. Compliance will be monitored by the PIU and the Design
& Supervision Firm.
OP/BP 4.11 Physical Cultural Resources: While no significant impacts are expected on physical cultural
resources, the policy has been triggered as a precaution and the project will include a ‘chance find’
procedure in all works contracts with building contractors.
3.2.2 Social Policies
OP/BP 4.10 Indigenous Peoples is triggered since the Kalinago are recognized as indigenous people by the
Government of Dominica, and also meet the World Bank criteria for applying the Indigenous Peoples
Policy. Consultations have been held in the Kalinago Territory, and an Indigenous Peoples Plan for the
Kalinago Territory has been drafted, and has informed this ESMF.
OP/BP 4.12 Involuntary Resettlement: . OP/BP 4.12 on Involuntary Resettlement was triggered in the PAD
on a precautionary basis to address instances of economic displacement and/or temporary involuntary
21 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
resettlement. Nevertheless, currently there has been no justification to apply itThe project will be providing
grants to households based on an ‘owner-driven’ housing reconstruction model, where the beneficiary is
involved in and agrees to the specifics of the design and siting of reconstruction activities, and has the
option of choosing not to receive project assistance. The project’s housing reconstruction activities will
therefore not involve involuntary land acquisition or resettlement. . Under a demand driven approach
where a house owner is found eligible for project assistance to reconstruct a hurricane destroyed house
located on his/her own land, the decision to alter its footprint/location due to environmental hazard
considerations would be made voluntarily by the house owner/beneficiary as part of the agreement
regarding the assistance. This should therefore not – even if crops or economic trees are affected by the
new location - be considered economic displacement eligible for compensation. If a house owner considers
the requirement to site a new house for safety reasons in a different location on his/her land to be onerous,
he/she has the option to refuse project assistance to rebuild the house. 4
Moreover, the World Bank’s use of the concept of ‘temporary impacts’ was historically conceived and used
for very different situations such as adverse impacts in connection with dam projects, where people on the
periphery of a reservoir could lose access to land every few years as a result of high flooding – that is a
situation where the impact is the result of decisions made by external actors and beyond the decision-making
powers of those affected.
4 The argument for not triggering OP 4.12 for the Housing Recovery Project would also reflect practice in World Bank
supported disaster housing reconstruction projects. Thus, while the recent Nepal Earthquake Housing Reconstruction
Project (P155969) did trigger OP 4.12, it was not to address the kind of impacts identified in the PAD and PID/ISDS
for the HRP, but to deal with situations where: “Land taking maybe needed due to limited relocation of
settlements/households that are no longer habitable due to ground fissures and high risks of seismic and landslide
hazards” (PID/ISDS). Moreover, regarding the scope of land acquisition and involuntary resettlement, the
Resettlement Policy Framework for the Nepal project states that: “Since the project will be providing grants to
households based on ‘owner-driven’ housing construction modality, project activities are not expected to cause
involuntary resettlement as defined by the World Bank’s OP/BP 4.12.” (p. 11).
SECTION 4: PROJECT IMPLEMENTATION ARRANGEMENTS
The MoHL has overall responsibility for the implementation of the project through the Project
Implementation Unit. At the highest level, the Housing Task Force will provide strategic oversight and
ensure policy coordination, guided by a housing reconstruction strategy that aims to coordinate efforts in
the sector and standardize approaches to recovery. This strategy is being implemented by the MoHL in
collaboration with the MoP. Under the strategy and in addition to the Housing Recovery Project, the
Government has an ongoing housing revolution to carry out major housing reconstruction projects,
including the construction of 1,000 housing units in new sites, and is also receiving support from
international agencies and nongovernmental organizations (NGOs) for housing repair. These are the
programs and projects that households can be referred to, when they are not found eligible under the
beneficiary selection criteria of the Housing Recovery Project.
World Bank: The World Bank will serve to guide the design of the project in accordance with the needs
of Dominica in the application of environmental and social safeguards for investment financing of the HRP.
The Bank is responsible to provide “no objection” on project implementation at appropriate milestones.
Project Implementation Unit: A PIU established under MoHL with the Housing Division as the Focal
Point of the project, will serve as the unit responsible for the overall implementation and coordination of
project activities, including fiduciary (procurement and financial management) and safeguards
responsibilities. The PIU’s safeguards responsibilities comprise oversight and advise on safeguards
compliance, management of the GRM, capacity building in safeguards management for TACs, local
government entities, contractors and other key players and partners and support regarding the project’s
communication with beneficiary communities and the public. In addition, the PIU’s role in selection of
beneficiaries for housing reconstruction assistance also includes safeguards responsibilities (see Section 5).
If needed, the PIU can access assistance from an Implementation Support Team (IST), that will be housed
within the Ministry of Finance (MoF), and will provide implementation support to the PIUs of all World
Bank‐funded projects in Dominica as a shared service in the areas of procurement, safeguards, and fiduciary
aspects. The project will provide the necessary implementation support by bringing experts to the IST
through an international recruitment process.
Districts and Technical Assistance Centers: The MoHL plans to coordinate repair and reconstruction
activities within each of Dominica’s seven Health Districts (see Annex 2 - Map of Health Districts), which
will serve as the zones for housing recovery assistance. Each District will have one TAC, with the exception
of the Roseau District, which due to its size and population will have two additional satellite TACs, and the
Castle Bruce District which will have one satellite TAC for the Kalinago Territory. The TACs will serve
as a decentralized extension of PPD to support and improve community outreach and provision of technical
advice, guide construction practices, and strengthen development control capacity. Thus, the TAC will
have a dual function comprising both technical advisory services and building controls. In addition, the
TACs may also support the PIU in the collection of demographic information required for administering
eligibility under the project. By focusing on the setup of the overall delivery mechanism, the project ensures
that all activities are scalable so that other donors could easily adopt or contribute to the program.
Through the TACs, the project will address existing capacity gaps in planning controls and compliance,
and assist homeowners as follows:
1. Streamline the building permit application and approval processes through the use of electronic
systems.
23 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
2. Streamline the site inspection and compliance evaluation processes with field and office electronic
systems.
3. Shift much of the technical responsibility for ensuring compliance with required building standards
upstream to field supervision consultants employed under the project.
4. Provide technical advisory services to homeowners on demand, and facilitate technical training on
the application of resilient building practices.
Local Governance Entities: In the localities where the project financed housing reconstruction activities
will take place, the institutional counterpart will be Village Councils (in the Kalinago Territory the Kalinago
Council and Hamlet Development Committees). The councils are popularly elected bodies empowered by
law to regulate and administer affairs in their respective areas, and their responsibility for development
work include the construction and maintenance of local infrastructure. In addition, they serve as the central
Government’s agents for the distribution of public assistance to destitute community members, and as a
channel through which information on Government policies and programs are conveyed to the local
communities (see Annex 3 - Map of Village Districts).
Meetings with Village Councils, and the Kalinago Hamlet Development Committees/Kalinago Council will
be held (i) before start of implementation to provide information on the project, the approach to beneficiary
selection, the GRM, and to agree on a ‘code of conduct’ for building contractors, (ii) participate in the
beneficiary selection committee to review, verify and validate the list of eligible beneficiaries, and (iii) to
conduct recurrent follow-up meetings involving project representatives and the contractor to review
progress, complaints submitted through the Grievance Redress Mechanism (GRM), as well as any other
issues that might arise in connection with the project activities.
HRP Committees: Two committees will facilitate work on safeguards: (i) Beneficiary Selection Review
Committee and (ii) Grievance Redress Committee. The Beneficiary Selection Review Committee will
review the listing of applicants who have met the criteria with a view of verifying same at the local level,
while the Grievance Redress Committee will focus on solving recurring complaints.
The HRP Beneficiary Selection Review Committee structure will comprise no more than seven members,
involving representatives from local government, religious, NGO or other civic group, prominent local
citizen, and professional/academia. Specifically, the composition of the will include:
Similarly, the proposed HRP Grievance Redress Committee structure will comprise representatives from
the following but not limited to:
HRP Beneficiary Selection Review Committee
Representative of the Village / Kalinago Council
Representative of Religious Organisation
Representative of a Credit Union, Financial Institution or Cooperative Association
Representative of any NGO's or other Civic Group in the region
Other Prominent Citizen e.g. Justice of Peace, community activist
Professionals/Academia
Shelter Managers
24 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
The current HRP Grievance Mechanism (GM) is included in the PIU Operations Manual and the
Environmental and Social Management Plan (ESMP) with the objective to formalize the management of
grievances at the PIU level, to minimize the environmental, health, safety and social risks to the Project and
avoid triggering the Bank’s corporate Grievance Redress System (GRS). Consult the HRP GRM document
for details.
Project Consulting Entities: Through the project implementation period, the project will provide support
to expand the staffing and the number of TACs. In the absence of this support at the initial implementation
of the project, the contracting of Technical Services (architects, engineers) consultants will screen for
eligible criteria as part of the beneficiary selection process at the initial stage of the HRP before
reconstruction works. A checklist will be prepared by the WB Flood Hazard Experts to support the work
of the Technical Services. The Technical Services consultants will also facilitate eligible home owners in
executing the project.
In addition, a consulting services firm (Design & Supervision Firm) will provide support to the TACs and
the PPD. The firm’s services will include building design specialists, building construction specialists, and
specialists on environmental, social, health, and safety matters. The firm will provide for each eligible
homeowner (i) a review of the building and site assessment, and of the documentation certifying eligibility,
land title and financial capacity; (ii) a customized design, scope of works, and cost estimate in compliance
with requirements of the Building Guidelines for resilience to Category 5 hurricane events; (iii) technical
supervision of site works and building works to ensure that the contractor has obtained the requisite
compliance certifications at various stages of work, and also complies with applicable environmental and
social safeguards as specified in the ESMP; and (iv) certification of satisfactory completion following the
completion of works at each site.
In addition to the safeguards staff at the PIU, specialists on environmental and social safeguards will be
part of the Design & Supervision Firm staff at the District level. However, the Design & Supervision Firm
will not have personnel to staff each TAC. To ensure adequate day-to-day safeguards management at the
implementation level of Village Councils and Hamlet Development Committees, each TAC or satellite
TAC will need to have one of its staff designated as responsible for these issues. The ongoing support for
such designated staff by the Design & Supervision Firm’s specialists on environmental and social
safeguards will contribute to build capacity within PPD to manage safeguards and social development
matters in housing reconstruction beyond the project period.
Separate from this, another firm will be hired to implement the management information system (MIS) to
set up a database to collect and manage beneficiary data.
All consulting entities will follow a code of conduct directed by the PIU based on WB guidelines noted in
Annex 4.
HRP Grievance Redress Committee
Representative of the Village / Kalinago Council
Representative of Religious Organisation
Representative of a Credit Union, Financial Institution or Cooperative Association
Representative of any NGO's or other Civic Group in the region
Other Prominent Citizen e.g. Justice of Peace, community activist
Professionals/Academia
25 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Key Partners: Meetings with various key partners to discuss and agree serve to guide sustainable use of
resources and safe practices in accordance with national legislation, policies and plans for managing
environmental, social, health and safety risks for HRP implementation. The multitude of key partners at
the institutional and community levels, as well as direct players are noted in Annex 5-Table 1 comprise the
direct players and their role and Annex 5-Table 2 lists key partners, their role, and a list of respective
Standard Operating Procedures to follow.
Implementation Stages: Implementation of the environmental and social safeguards of the World Bank
under the HRP requires three main stages throughout the entire project process with reporting at key stages.
This involves:
1. Before Construction – Preparation and readiness for (i) safeguards screening for eligibility as a
beneficiary before construction and (ii) safeguards monitoring and implementation during and close of
construction.
2. During Construction – Monitoring, supervision, evaluation and reporting of compliance with the
ESMP.
3. Closure of Construction – Decommissioning of each construction site as per adhering to the ESMP
requirements.
SECTION 5: ENVIRONMENTAL AND SOCIAL CONDITIONS IN
THE PROJECT AREA
This Section describes environmental and social conditions and challenges relevant for the housing
reconstruction activities. Implications for the project’s approach to managing and mitigating environmental
and social conditions and impacts are briefly noted, and will be fully described reflecting Government and
World Bank policies noted in Section 6 on approaches to address environmental and social safeguard issues.
In brief, the environmental conditions include: hurricanes, earthquake and volcano risks; geotechnical and
hydrological risks; access and sustainable use of natural forest and river resources for construction; debris
management; pest control, asbestos handing; and chance finds involving physical cultural resource and
skeletal remains. Social issues relate to: current damage assessment; home ownership; poverty and
vulnerability assessment and verification; construction labor; and indigenous people, the Kalinago.
5.1 Environmental Conditions and Issues
Like most of the islands in the Eastern Caribbean, Dominica is geologically young. The island has nine
active volcanoes, which accounts for its rugged topography. A chain of mountains extends through the
center of the island, creating ridges and steep river valleys. The geological character of Dominica’s
mountains poses unique challenges for slope stability because of their high clay content and easily erodible
nature, which increase local landslide hazard level. The shape and orientation of the island combined with
its elevation results in a rainfall distribution that ranges from 1,500mm on the west coast to over 8,750 mm
annually in parts of the interior. As a result of its location and topography, Dominica as a whole and
therefore potentially all project locations are exposed to several natural hazards, including extreme
precipitation and flooding, strong winds, and landslides. Estimates anticipate that a potential increase in
the severity and frequency of such events is likely.
Hurricanes: The island has experienced several damaging hurricanes and tropical storms since formal
monitoring began in the 1970s: Hurricane David (1979), Hurricane Luis (1995), Hurricane Dean (2007),
Tropical Storm Erika (2015), and most recently Hurricane Maria (2017). During these events extremely
strong winds, flooding, and landslides damaged buildings, agricultural outputs, and road infrastructure.
During hurricanes, coastal zones are vulnerable to storm surge of 3-5 meters, causing flooding and erosion
from wave energy and throughout the island’s interior as a result of the steep topographical landscape and
expansive hydrological network. Mindful that the project will carry into a few hurricane seasons over the
course of implementation, disruption may occur to construction works temporarily.
The project’s support for ‘building back better’ through technical assistance and advice on hurricane
resilient building techniques by the entities contracted by the Project, the Physical Planning Division and
Ministry of Housing and Lands including TACs for both the house reconstruction directly funded by the
project, and for home owners undertaking repairs on their own, will contribute to mitigate the destructive
impacts of future hurricanes and tropical storms.
Volcano and Seismic Risks: In addition to risks associated with hurricanes, volcanic activity and
earthquakes present a historically minor, but continuous hazard. The last recorded eruption was a 1997
steam (phreatic) eruption in the Valley of Desolation, near the active Boiling Lake, but the last eruption of
lava occurred approximately 500 years ago. Earthquakes of a magnitude large enough to be recorded by
27 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
seismographs on nearby islands occur at an average rate of one to two per year.5 A major earthquake of
magnitude 6.5 in 2007 collapsed a church tower in the town of Portsmouth and resulted in damage of at
least twenty houses.
Geotechnical and Hydrological Risks (flooding, erosion, slope stability and landslide risks): Most
landslides and soil erosion events are triggered by high intensity rainfall, which can happen without a
hurricane, volcano or seismic activity. After Hurricane Maria, an inventory of landslides caused by the
hurricane recorded a total of 9,960 landslides. These landslides stripped the soil of productivity and
sedimentation, and resulted in siltation of rivers and debris obstruction of natural drainage and waterways.
Almost all rivers flooded due to intense precipitation, inundating an area of 13.03km2, or 1.74 percent of
Dominica’s total land area. Although substantial infrastructure damage was caused by flooding and heavy
debris flows in the rivers, the distribution of damage to housing was fairly similar across risk and non‐risk
areas. From a high‐level analysis, it is estimated that 25–30 percent of houses could be located in flooding
or landslide‐risk areas, with little variation across house sizes and in the incidence of levels of damage. The
preferred approach under the project will be to mitigate any site hazards identified using project or home
owner resources. In cases where public works are required to mitigate the site or relocation is the only
option, the house and site will not be eligible for project assistance, and the Government will assume
responsibility under another housing program. Of the 4,503 totally destroyed homes, 70–75 percent are
expected to be located in areas with low flood or landslide risks. With a funding allocation of US$31.45
million for works for about 1,700 affected households, the project could cover up to 56 percent of all
destroyed houses in low‐risk areas, or 82 percent of small destroyed houses in low‐risk areas.
Geotechnical and hydrological risks do not derive from the civil work activities themselves, but from the
characteristics of the construction site. The susceptibility of specific housing sites to geotechnical and
hydrological risks (landslide or flooding) will be appraised during the building assessments that will be
conducted by the Technical Services team of architects/engineers. The project’s eligibility criteria for
destroyed homes exclude house sites from receiving housing reconstruction assistance, if the risk is assessed
as unacceptable even after site remediation. In that case, the house owner would be referred to other housing
programs.
However, within the area of a particular village, the landslide and flooding risk may vary between the
different house sites that make up the village, and may even vary within particular properties. If a destroyed
house was located in a risk spot on a particular property, but if the property is large enough to enable the
siting of a replacement house that mitigates the risk, it would be potentially eligible for assistance. In this
context, two additional aspects need to be considered when assessing eligibility vis-à-vis hazard risk. First,
if an otherwise eligible home owner with a destroyed house on a site deemed ineligible due to environmental
hazard risk can self-identify an alternative site, which is risk free and for which he/she can document
ownership, this should suffice for eligibility. Second, in the Kalinago Territory land is not private property,
but subject to allocation by the Kalinago Council. Thus, where the hurricane destroyed house is on a plot
with environmental hazard risk, the Council may be able to allocate a different risk-free house plot to a
beneficiary who would otherwise be excluded.
Aggregate: Sand and gravel will be required for construction of house foundations, and there are three
approved active quarries for aggregate in Colihaut, and one for sand (and pumice) in Layou, all on the west
coast north of Roseau. The Physical Planning Division is responsible for the periodic monitoring of quarry
operations in the country and is the focal point of the cabinet-approved quarry monitoring team, which is
also made up of representatives of the Fisheries, Forestry, Environmental Health Division as well as the
5 http://www.dpsninc.org/index.php/seismicity
28 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Environmental Coordinating Unit. Opening a new quarry requires approval by PPD following a process
involving an environmental impact assessment and consultations with affected communities.
To the extent possible, recycling of material dredged from the river if desired and feasible must only be
used if there are approved government processes in place, given the wide array of dredging of rivers that
continues to take place following the hurricane to avoid negative environmental impacts from excavation
and to ensure the use of good quality aggregate in construction.
Forest and River Damage: Dominica has the most extensive natural forests in the entire Eastern Caribbean
covering about 60 percent of the island, and ranging from dry scrub woodland on the west coast to lush
tropical rain forest in the interior. There are four National Parks and two Forest Reserves which together
cover about 22 percent of Dominica, 6 and approximately 27 percent of the island’s forests are designated
protected areas. Dominica is therefore home to the most diverse assemblage of wildlife among the smaller
Caribbean islands with 179 bird species and 18 species of mammals. In 1994 the Government ratified the
UN Convention on Biological Diversity. However, threats to the forest cover and biodiversity continue
and include deforestation, hunting and capture of wildlife, agro-chemical pollution, and invasive species.
Added to this is the threat of extreme weather events. Hurricane Maria’s winds and intense rainfall
produced widespread damage to the forest system. Much of the forest was stripped of leaves, and trees
were extensively damaged and downed throughout the island. It is estimated that 10 to 20 percent of the
trees in the forests were completely flattened. For the remaining 80 percent of the forest area, it is expected
that the trees that survived the hurricane will be able to re-establish a closed canopy. Any use of local
timber either from downed trees or logging must follow the management procedures of the Forestry,
Wildlife and National Parks Division.
This would reduce the risk of unregulated deforestation, and would at the same time reduce dependency on
imported lumber and create local employment through the conversion of downed trees into building
materials if feasible. This is particularly relevant in the Kalinago Territory.
Building Debris: As Hurricane Maria passed over Dominica, the extreme winds, landslides, flash floods
and storm surges all contributed to wreak havoc on buildings and other structures generating large amounts
of debris. For houses receiving project assistance, this debris will have to be disposed of, both because it
may present a health risk,7 and because its negative aesthetic impacts affect quality of life. Dominica has
its principal landfill in Fond Cole near Roseau. The Dominica Solid Waste Management Cooperation
(DSWMC) provides waste collection services throughout the island and operates the Fond Cole sanitary
landfill.8 Due to the distances and the lack of transfer and storage facilities, the service is costly by
international standards. The PDNA found that before the hurricane, the service was in a critical situation
with severely depleted equipment, unreliable private contractors, and lack of storage containers or transfer
facilities.
For the project, disposal of the debris from damaged and destroyed houses as well as the construction debris
that will be generated during reconstruction constitutes one of the more significant environmental
6 Dominica National Biodiversity Strategy and Action Plan 2014-2020, Ministry of Environment, Natural Resources,
Physical Planning and Fisheries, December 2013. The four National Parks (NP) are Morne Trois Piton NP (a
UNESCO world heritage site), Morne Diablotin NP, Cabrits NP, and Soufriere Sulphur Springs NP. The two Forest
Reserves are Central and Northern Forest Reserve. The total area covered by the NPs and Forest Reserves is 16,716
hectares. 7 Stagnant water in building and household debris such as fridges and stoves can be a source of mosquito borne illness. 8 The Fond Cole sanitary landfill of 18 acres is inter alia designated to receive (i) industrial waste including
construction and demolition waste, (ii) green waste including wood, and (iii) commercial waste including metals. The
Fond Cole landfill is filled near capacity, and a new landfill location for building debris is being considered.
29 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
challenges, that have to be managed during implementation. This will require arrangements that involve
the DSWMC, private waste disposal contractors, and the communities receiving assistance that are best
suited for various locations of project implementation best suited to easily dispose and recycle the waste.
Pesticide Application: Pesticides may be required for pest control (termites) in the rehabilitated or newly
constructed houses. If termite treatment or vector control treatment is to be utilized, appropriate chemical
management measures must be used to prevent contamination of surrounding areas, and only licensed and
registered pest control professionals with training and knowledge of proper application techniques can be
engaged. Any use of pesticides shall be approved by the Design and Supervision Firm to the area in
question, and all pesticides to be used shall conform to the list of acceptable pesticides that are not banned
by the relevant authority.
Asbestos Handling: Asbestos may be present in destroyed homes. The safe handling and disposal
procedure during the demolition will be applied with respective authorities including the Environmental
Health Department and the Dominica Solid Waste Management Corporation.
Chance Finds:
Physical Cultural Resources. While the civil works undertaken under the project are small scale, and while
most house reconstruction will be undertaken in situ, the possibility nevertheless exists of archaeological
chance finds from both pre-Colombian and later colonial and Creole settlements in Dominica. There has
been little research on and documentation of pre-Colombian settlements in Dominica, and only one known
site near the village of Soufriere in southern Dominica appear to have been excavated.9 However,
archaeological reconnaissance surveys in 2009 involved some excavation and systematic collection of
surface artifacts at six sites located across Dominica, and in 2010 more intensive investigations were
undertaken in the area around Castle Bruce on the east coast. Thus, pre-Colombian artefacts may be found
across the island as may physical cultural remains of later occupation. There is as yet no archaeological
legislation in Dominica, but the Physical Planning Act of 2002 states that PPD may impose conditions on
a grant of development permission (building permit) to arrange for “the preservation of any buildings or
sites of importance to the cultural heritage of Dominica.” In case of archaeological chance finds during
housing reconstruction activities, the location of the find will be reported to PPD and to the Dominica
Museum in Roseau (the national museum of Dominica), to which the find will be handed over.10 Should
the find appear to be part of a larger archaeological site, both PPD and the Museum in Roseau should be
consulted before civil works progresses.
Handling Skeletal Remains. The small-scale construction may result in a chance find of skeletal remains
on site. A chance find procedure will be used for handling the remains found with the Dominica Police
Force Central Investigation Department to take over the matter and construction would continue thereafter.
5.2 Social Conditions and Issues
Population: The 2011 census in Dominica found the total population to be 71,293, which represents a
decline of 0.6 percent since the 2001 census. The cause of this decline is an estimated out-migration of
9 Benoit Berard: The "South-Dominica" archaeological mission: the Soufrière site, Paper presented during the XXIIth
Conference of the International Association of Caribbean Archaeology, 23-29 of July 2007, Kingston, Jamaica. 10 The Dominica Museum is located at Dame Mary Eugenia Charles Boulevard in Roseau.
30 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
about 4,000 persons per year. This out-migration may also explain the sex ratio of 104.4 with 36,411 males
and 34,882 females. The census found that the total number of households in the country was 26,085
representing an 8.5 percent increase over the previous census. The reason for this increase is a decline in
the average household size from the 3 persons per household in 2001 to 2.7 persons per household in 2011.
Due to Dominica’s mountainous terrain, about 62 percent of the population are settled along its
approximately ninety miles of coastline.11
Housing Damage by Hurricane Maria: The Building Damage Assessment (BDA) conducted in
December 2017 covers about 24,300 private, commercial, and public buildings. The data shows that of
private homes, 18 percent (4,503 houses) were totally destroyed and requiring rebuilding, while 26 percent
(6,284) sustained major damage needing full roof replacement. A further 29 percent (6,996 houses)
sustained minor damage requiring minor roof and other repairs, and 27 percent (6,514 houses) sustained
only minimal or superficial damage, as shown in the table below. Medium‐size houses (500 to 1,200 sq.ft)
dominate the housing stock with 9,825 units, and of these 40 percent sustained major or total damage.
However, small house units (less than 500 sq.ft), which comprise 31 percent of the housing stock (7,525
units), sustained a higher level of major or total damage, affecting 62 percent of that group. Although only
a small percentage of large houses were totally destroyed, 30 percent sustained major roof damage.
Insurance penetration varied significantly. Of the destroyed houses, only 2 percent were insured; whereas
for all other damage categories, 15–20 percent were insured.
Distribution of Level of Damage and House Size for Private Houses and Home/Business Units
House footprint
House size
sq.ft
Destroyed Major
Damage
Minor
Damage
Negligible
Damage
Sub-Totals
Extra small
<200 836 304 271 248 1,659
Small
200 < 500 2,179 1,381 1,417 889 5,866
Medium
500 < 1200 1,225 2,740 3,059 2,801 9,825
Large
1200 < 2500 211 1,362 1,717 1,919 5,209
Extra large
> 2500 52 497 532 657 1,738
Subtotals
4,503 6,284 6,996 6,514 24,297
Source: HRP Project Appraisal Document based on the BDA database, MoHL, and UNDP,
January 2018.
In terms of the regional distribution of hurricane damage, the East Coast including the Kalinago Territory
and the South of the island were extremely impacted by the hurricane based on the percentage of damage.
These locations include some of the places with the highest rates of poverty and people still in emergency
11 The PDNA (p.16) assesses that 90 percent of the population lives along the island’s coastline.
31 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
centers as visualized in the map of Dominica showing the geographic distribution of buildings damaged
from Hurricane Maria.
Geographic Distribution of Building Damages
The BDA data were received from the UNDP in January 2018. It should be noted that when the project
starts implementation of housing reconstruction activities in 2019, the damage status of many homes will
have changed due to repairs undertaken by the owners or with support from other programs, though likely
less so for destroyed homes that were occupied by the vulnerable households that are the primary target
group for the project. The data is considered representative as a basis to cross-check the damage status
combined with site inspection checks of potentially eligible applicants. Moreover, the project could
consider to start implementation in one or two initial implementation areas with the highest levels of
destruction of houses below 500 sq..ft, and high levels of vulnerability and poverty (e.g. the Kalinago
Territory). This is charted in the following map showing damage disparities by building size and geographic
location.
32 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Damage Disparities by Building Size and Geographic Location
The future home of 500 sq.ft, which is an option for households selected as beneficiaries of reconstruction
assistance, would adequately serve as initial replacement housing for those selected from the 3,015
households, who lived in hurricane destroyed homes smaller than 500 sq.ft. Moreover, with a national
average household size of 2.7 persons, the small home should provide basic accommodation for most
beneficiary families from this sub-set.
Land Ownership: There are no recent data on private land ownership, and the only available information
dates back to 2003.12 It describes access to private land as more widespread in Dominica than in other East
Caribbean nations, although the distribution of land is uneven. Of the farming population, 74 percent owned
parcels of land of 5 acres or less, but accounted for only 23 percent of the agricultural land. At the other
extreme, 1.3 percent of the farming population controlled about 35 percent of the agricultural land in parcels
exceeding 50 acres.
12 Dominica: Land Policy, Administration and Management: Country Experience by Allan N. Williams. In: Land
in the Caribbean – Proceedings of a Workshop on Land Policy, Administration and Management in the English
Speaking Caribbean, Land Tenure Center, University of Wisconsin-Madison, USA, October 2003.
33 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
While squatting on private land is relatively uncommon, squatting on state lands for farming and housing
has confronted Dominica’s Governments for many years. The number of squatter settlements on the island
is not known, but the majority of residential squatter areas are on state lands close to the two main urban
centers of Roseau and Portsmouth. State lands remain the primary source of land distribution, and the
Government actively regularizes squatters or works to prevent squatting from occurring. The State Lands
Act vests the President with the power to dispose of state lands by grant, sale, exchange or lease, and the
legislation has provisions for recognizing squatter rights (twelve years of undisturbed / unchallenged
occupation of land). Since the 1980’s, there has been regular interventions by successive Governments to
regulate squatter settlements. Under a public sector ‘Housing Revolution Program’ squatter settlements
have been regularized and the land sold at the concessionary price of EC$1.00 per square foot to
beneficiaries, notwithstanding the much higher open market value of land in the localities.
About 80 percent of residents including regularized (former) squatters have either a registered title, a
registered deed, or an unregistered deed. 13 Among the remaining 20 percent are households who have not
been able to pay registration costs to obtain a title document, and others who reside under informal
arrangements as tenants or leaseholders in houses they do not own, or in houses they own, but on land
owned by somebody else. The BDA recorded 418 households who were tenants or leaseholders, but the
PPD considers that the number is likely higher. Of these 418 households, about 25 percent had totally
destroyed homes. Tenants or leaseholders, who are likely to be among the poorer and more vulnerable, are
not included as potential project beneficiaries and would revert to other government housing programs.
Disadvantaged and Vulnerable Groups. Rural poverty continues to represent a major challenge, with 75
percent of the poor living in rural areas. Poverty rates are similar among men (28.8 percent) and women
(28.9 percent). The indigenous Kalinago people that represent 3 percent of the total population have a
particularly high incidence of poverty at 49.8 percent (approximately 1,600 individuals).
The specific focus of the project in terms of prioritization criteria is on (i) households that are still in
hurricane displacement centers, (ii) households that are recipients under the Public Assistance Program,
and (iii) particularly vulnerable households comprising single parent households with children under 15
years, households with a disabled household head, and households with an elderly household head. The
circumstances of these households are discussed below. Since these categories of prioritized beneficiaries
are likely to have limited access to information about the project, and also limited ability to act on such
information, the HRP Communication Strategy outlines multiple media channels to reach them and the
local government will be included to ensure they are aware of the project in order to apply. Further, a
Beneficiary Selection Review Committee will be set up to verify that home owners selected are the most
vulnerable who require assistance under the HRP.
Single Parent Households: While this section speaks to statistics on women, it is equally important that
men also fall into the category of single parent homes, taking into consideration the vulnerability factors.
There needs to be a careful balance with the household composition while women are prioritized. Women
represent 39 percent of the heads of households in Dominica. Although Dominica has made significant
strides towards gender equality, the impact of Tropical Storm Erika and Hurricane Maria have exacerbated
the challenges the country faces in this context. These challenges include increasing levels of gender-based
violence especially in lower socio-economic sectors. The PDNA notes that observational evidence suggests,
that there is a predominance of women, elderly persons, and children in the temporary shelters. Most of
13 The most recognized and common forms of tenure are (i) sole proprietor, (ii) joint tenants and tenants in common,
(iii) land held in common (family land), (iv) Communal land (Kalinago Territory), (v) qualified and possessory
proprietor, (vi) reserved encumbrance, and (vii) lease.
34 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
these elderly women (over 65) are also the head of household, and these households comprise five persons
on average. Most of the elderly men in the shelters were on their own. Site visit interviews highlighted
that many women, particularly the elderly women head of households, did not have housing insurance, and
they also were unable to move out of the shelters because they did not have access to housing material,
knowledge of where to source the material, or money to pay the labor needed to rebuild. Many of these
women are caregivers for grandchildren. Overall, the Vulnerability Needs Assessment prepared following
the storm highlighted that there were over 1,100 single mothers with uninsured houses that had either been
destroyed or severely damaged.
The project’s eligibility procedure prioritizes female headed households with dependent children. The
procedure comprises two steps, with the second step including criteria that accord priority in terms of
eligibility to households that are still in shelters and to single parent households with children below 15
years of age. In light of the situation reported from the shelters where grandmothers are caregivers for
grandchildren, the criteria should be tweaked to assign the same priority to such households. When the
HRP site verification is made to determine the level of house damage, effort should be made to identify
completely destroyed houses that were occupied by single parent households with children below 15 years,
including those still in shelters, and including households where grandmothers are caregivers for
grandchildren. The situation of elderly men in shelters noted by the PNDA may also call for an assessment
in terms of vulnerability.
Persons with Disabilities: Roughly 5.2 percent of Dominicans reported some kind of disability, of which
approximate 86 percent were medically diagnosed. A Disability Statistics Publication (2018) prepared by
the Central Statistics Office indicates that among people with disabilities, mobility (37.8 percent) and sight
(32.1 percent) are the most prominent forms of disability. When disaggregated, there is no significant
gender difference, but persons aged 35 and over are mostly challenged (79 percent). Chronic lifestyle
diseases, including hypertension, diabetes, obesity, and cancers were reported by 14.1 percent of males and
21 percent of females.
As in the case of households that are still in shelters and single parent households with children below 15
year of age, disability is also prioritization criteria. Applicants will be required to provide supporting
documents, including certification of a severe disability from a doctor, so that the presence of the disabled
person is flagged for attention at the outset. Notably, for beneficiaries with either mobility and sight
disabilities, the design of replacement houses need to accommodate their specific needs.
Health and Safety: Project activities will have potential impacts on the health and safety of the local
inhabitants, laborers and others involved in the housing reconstruction. Although the construction works
will be small in scale and distributed across the island, accidents can happen in connection with
transportation and storage of construction materials and debris, felling of trees, and construction activities
at house sites, and there are associated but minor impacts regarding increased levels of dust, noise, and
vibration. Therefore, appropriate personal protective equipment (PPE) must be used on site, and must be
provided to authorized visitors. In addition, on determination by the PIU, contractor camps need to be
provided with adequate sanitary/toilet facilities to avoid pollution, among other standard requirements. In
addition, workers will be required to follow a Code of Conduct to avoid conflict with neighbor
communities.
To minimize the risk of accidents on construction sites, access need to be restricted and controlled through
fencing and oversight (in particular, children should not be able to access building sites). Use of protective
clothing/equipment appropriate to the different activities associated with the housing reconstruction will be
defined in the Operational Manual and included in the contract with building contractors. Measures to
35 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
reduce construction related levels of dust, noise, and vibration are prescribed in the ESMP, which will be
part of the Operational Manual and also will be included in the contract with building contractors.
A specific issue concerns timber treated with Copper Chrome Arsenate (CCA), which acts as a preservative
and anti-pest (termite) treatment. CCA is found in the older timber housing stock, and is also used for new
construction in communities that prefer timber construction (e.g. Kalinago). Persons are not at risk of
arsenic poisoning from casual contact with CCA, as the level of arsenic exposure is not significant enough
to cause harm. However, care must be taken when working (sawing, sanding, machining, etc.) with CCA-
treated timber in a way that produces saw-dust. Appropriate personal protective equipment should be worn,
and these activities should take place outdoors. Disposal of CCA-treated timber debris from destroyed
houses and from construction should be done under the arrangements described above in the section on
‘building debris’ involving disposal at the DSWMC operated sanitary landfill at Fond Cole (or other
approved by the GoCD and the PIU).
Measures to deal with the health and safety issues and the handling/disposal of CCA-treated timber are
described in the ESMP, which will be included in the contracts with building contractors and contractors
disposing of debris.
Labor Influx. Although the owner-driven model for house reconstruction will involve beneficiary house
owners/occupants in reconstruction activities assisted by other community members with appropriate skills,
the house reconstruction will also involve pre-qualified building contractors along with modest labor influx.
Some of these contractors may come from other islands in the Caribbean. To manage the community-
contractor relationship, the project will follow the approach which has been successfully applied in other
civil works projects in Dominica using local contractors. This approach involves a meeting held before the
start of physical works between the Village Council14 and the contractor, where the PIU and the Building
Design & Supervision Firm if where feasible, TAC, will be represented, and where issues related to the
work and the contractor’s presence are discussed and agreed upon in writing. At this orientation meeting,
the Village Council is also informed about the HRP Grievance Redress Mechanism (GRM), and how
complaints relating to activities by the contractor and staff can be submitted and acted on by the PIU. As
a follow-up, quarterly meetings will be held involving the Village Council (and interested beneficiaries),
the PIU, and staff from the consulting firm that will support design and supervision services.
With regard to contractor ‘camps’, these will not be needed where contractors operate close to their home
base. If a ‘camp’ is needed, this would either be on Government or private land. Where suitable
Government land is available, an agreement is entered into between the contractor and Ministry of Housing
and Ministry of Public Works. If the ‘camp’ is located on private land, the agreement is between contractor
and land owner, and is submitted to the PIU. Due to the small size of Dominica, local contractor staff in
‘camps’ will be able to go home daily. When closing and dismantling work ‘camps’, contractors will
remove all equipment, dispose of debris (to the landfill at Fond Cole, or other approved by the GoD and
the PIU), and restore the site to the extent possible to pre-occupancy conditions. These requirements will
be included in works contracts and are included in the ESMP.
Indigenous People: Dominica was originally populated by Amerindian peoples, known as Caribs or
Kalinago, and is the only island in the Caribbean still to possess distinct communities of these indigenous
people. The Carib Reserve Act was enacted in 1978, the year of Dominican independence. It reaffirmed
the territorial boundaries first established by colonial authorities in 1903, and legally established common
14 In the Kalinago Territory, such meetings will involve the relevant Hamlet Development Committee and
representatives from the Kalinago Council.
36 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
ownership of land within the reserve. In March 2015, an amendment was made that changed the name to
the Kalinago Territory Act. Prior to that, the Government of Dominica had ratified the Indigenous and
Tribal Peoples Convention (ILO 169), and signed the UN Declaration on the Rights of Indigenous Peoples
in 2007. 15 A Department of Carib Affairs was established in 2000 and upgraded to a Ministry of Kalinago
Affairs in 2014.
The Kalinago Territory comprises 3,782 acres stretching over 9 miles on the East coast of Dominica in the
Parish of St. David. There are eight hamlets with a 2011 population of 2,145 consisting of 652 households
with an average size around 3 persons. 16 The population exhibits an even more pronounced imbalance
between males (56.5 percent) and females (43.5 percent) than Dominica in general.
The Kalinago Territory Act describes the establishment of the office of the Kalinago Chief, the Constitution,
and powers of the Kalinago Council. All land in the Territory is under the custody and management of the
Kalinago Council, and no individual can buy or sell parcels of land or use land as collateral for loans. The
Council is solely responsible for allocating land for all purposes including housing, public conveniences,
Government projects, and community projects.
Hurricane Maria wrought very extensive damage on housing in the Kalinago Territory. In addition, a much
higher poverty rate (at 49.8 percent) compared with the national level (at 28.8 percent) diminishes the
capacity of the Kalinago to undertake repairs with their own resources, and access to finance is practically
non-existent since land cannot be used as collateral for loans. Figures on the exact level of damage from
Hurricane Maria varies between the BDA and a housing damage assessment in the Kalinago Territory by
the Caribbean Disaster Emergency Management Agency (CDEMA), but both find the proportion of totally
destroyed houses to be more than twice as high as the national level. The BDA and the CDEMA assessment
also differ regarding the number of homes (and by implication households) in the Kalinago Territory. With
an increase in the number of households at 10 percent comparable to the growth recorded by the Census
between 2001 and 2011, the total households in 2018 would be around 700.
Damage Assessments for Kalinago Territory and Nationally
Impact on houses
BDA CDEMA Assessment BDA National
Houses % Houses % Houses %
Negligible damage
89 10 131 17 6,514 27
Minor damage
181 20 108 14 6,996 29
Major damage
128 14 169 22 6,284 26
Destroyed
487 56 363 48 4,503 18
TOTAL
885 771 24,297
15 http://www.ilo.org/dyn/normlex/en/f?p=1000:11200:0::NO:11200:P11200_COUNTRY_ID:103311 16 The hamlets are Sineku, Gaulette River, Mahaut River, St. Cyr, Salybia, Crayfish River, Bataka and Touna Concord.
In addition, the village of Atkinson outside the Kalinago Territory is also inhabited by Kalinago.
37 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
The discrepancies between the BDA and CDEMA assessments highlight the need to conduct verification
of house damage level that will be conducted by the Technical Services (architects/engineers) consultants
hired under the HRP during the beneficiary selection assessment process that inform the selection of
beneficiaries. This update should serve as the basis for an allocation of the number of houses to be
reconstructed in the Kalinago Territory, and this should consider the very high level of damage together
with the constraints described above that limit local capacity for housing repair. It should further be
considered to deploy the Technical Services consultants and the Design and Supervision Firm early to the
Kalinago Territory to expedite the start of civil works.
As mentioned above, the Kalinago Council is responsible for allocating land for all purposes including
housing. An implication of this is, that the exclusion clause in the beneficiary eligibility criteria regarding
house site hazard risks can be amended for the Kalinago Territory for cases where the Council can allocate
an alternative housing plot without hazard risks for the reconstructed house. As required by OP 4.10 on
Indigenous Peoples, this and other issues regarding the selection of beneficiaries, and the practical
implementation arrangements (e.g. involvement of local labor, location of contractor camp(s), and disposal
of debris) should be decided in consultation with the Kalinago Territory Housing Committee. 17
17 The Kalinago Territory Housing Committee comprises representatives from the Kalinago Council, the Ministry of
Kalinago Affairs, and the Ministry of Housing & Lands.
SECTION 6: ENVIRONMENTAL & SOCIAL MANAGEMENT -
ADDRESSING SFEGUARD ISSUES
Both the environmental and social impacts and risks of the project are related to Support for Reconstruction
of Houses (Component 2), which will take place in different locations across Dominica. Project activities
will involve new construction of about 1,700 destroyed houses, and technical advisory services to the
beneficiaries of these houses, and to homeowners undertaking repairs without project financing. The
selection of beneficiaries for housing reconstruction assistance, the house design and agreements with
beneficiaries on construction of replacement houses, and the subsequent civil works all involve
consideration of environmental and social issues. Therefore, rather than separate the consideration of
environmental and social issues as they relate to beneficiary selection, house design and planning, and civil
works, these issues and the associated measures to mitigate and manage them are dealt with below as part
of the implementation process that progresses from beneficiary selection to the civil works for housing
reconstruction. The link between the predicted environmental impacts, the needed mitigation measures
identified during the screening and assessment process, provisions for budgeting the costs of such measures,
and the roles of those responsible for ensuring that the mitigation measures are carried out are summarized
in Annex 6 – Mitigation Table, Responsibilities and Costs.
6.1 Beneficiary Selection Process
Before the selection of individual beneficiary households for reconstruction assistance can be done, the
following activities have to be undertaken.
• Communication and outreach on the project, the application process, and the call for application.
First, an information campaign island wide should be conducted to inform the population about the
project approach, the criteria for beneficiary selection, and the deployment of the Technical
Services (architects/engineers) consultants to conduct the site assessment for eligibility, the
responsibility of the Design and Supervision Firm and that of both the building contractors and the
homeowner, as well as the GRM available to address complaints and resolutions. The information
campaign should inter alia use a range of media channels such as radio, village meetings (Village
Council / Hamlet Development Council), and printed materials with an easily understandable
rendering of the approach from beneficiary selection through construction (e.g. a flyer/leaflet)
where suitable. Since the project intends to refer households that were not eligible under its
beneficiary selection criteria to other projects and programs providing housing reconstruction
assistance, it is important that the result of this effort is also made public at the Village Council
office and on-line at the end of the selection.
• Intake and registration of applicants.
• Application by interested persons with required supporting documents.
• Cross-checking of the eligibility criteria 2 in Step 1 based on the physical damage and the
production of list of applicants that meet these criteria (using the existing BDA and other
databases).
• A preliminary identification of ‘destroyed’ residential houses will be done by the PIU based on
BDA data.
• In cases where applicant’s information could not be cross-checked and where hazard risk needs be
cross-checked, on-site building assessments will be conducted by the Technical Services
(architects/engineers) consultants to verify their status as ‘destroyed’. A report on flood hazard
39 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
assessment conducted by the World Bank Flood Hazard Assessment Specialists will be submitted
to the PIU for use by the Technical Services consultants to inform further assessment on same at
the specific applicant’s home. These assessments also need to include the eligibility criteria under
Step 1 and 2 in the table on the following page, such as environmental hazards involving slope
stability, landslide and flooding risks, and demographic data on household composition. Effort
need to be made to establish whether any ‘destroyed’ homes were occupied by households that are
still in displacement centers (of which the PDNA found many were female headed with
dependents).
• Cross-checking of eligibility criteria based on the data in the application form (Annex 7 – HRP
Application Form) and supporting documents on socio-economic vulnerability, including
verification of public assistance support on the Public Assistance Program that the homeowner is a
beneficiary among other criteria.
• List of eligible applicants compiled. Based on the assessments and information collected by the
Technical Services (architects/engineers) consultants, the PIU will compile a list of eligible and
prioritized homeowners after completing the Beneficiary Household Score for each applicant.
• Verification and validation by a Beneficiary Selection Review Committee which includes no more
than seven members, involving representatives from local government, religious, NGO or other
civic group, prominent local citizen, and professional/academia representatives for the respective
area. This list will be subjected to a verification and validation by the Beneficiary Selection Review
Committee who will produce a list of confirmed beneficiaries. Section 4 under HRP Committees
lists the specific composition of the said committee.
• Publication and notification of selected beneficiaries. The beneficiary list will be made public at
the Village Council office and on-line (project web-site at MoHL) as a final step in validation and
confirmation.
• Processing of appeals and other grievances.
If construction will be implemented sequentially, another planning activity should involve identification of
the Districts and project implementation locations, where the Design & Supervision Firm and contractors
will start operations based on considerations of the relative severity of housing damage in different areas
drawing on the results from the beneficiary HRP application assessment.
The eligibility criteria that will be applied in the beneficiary selection process including the household score
sheet involve both environmental and socio-economic considerations. The selection will comprise three
‘steps’, with Step 1 covering a set of eligibility criteria that determine whether home-owner applicant meets
the physical and socio-economic criteria of the project as a potential beneficiary, and which involve on-site
assessments. Step 2 will enable a categorical prioritization among the potentially eligible beneficiaries
based on socio-economic and demographic vulnerability criteria, which address protracted displacement,
poverty status, gender, and disability considerations. Step 3 will consist of verification and validation
involving a review of the final list of the beneficiaries by the HRP Beneficiary Selection Review
Committee, who will produce a list of confirmed beneficiaries. This list will be made public locally and
on-line (project website at MoHL) as a final step in the validation and confirmation.
40 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Houses/households that comply with all eight eligibility criteria would be potentially eligible, and would
be considered in terms of the prioritization criteria under Step 2. However, if criteria #5 under Step 1 on
‘low hazard risk’ receives a ‘no’, the site should be assessed to determine whether a potential re-siting
within the property could mitigate the risk and make the house/household eligible. For households in the
Kalinago Territory, the question to be asked if criteria on ‘low hazard risk’ receives a ‘no’, is whether the
Kalinago Territory’s Housing Committee can allocate an alternative housing plot without hazard risks for
the reconstructed house.
Criteria under Step 2 will be used to prioritize selection of the potential beneficiaries that complied with all
the criteria under Step 1. With the exception of 1.a and 1.b , the attributes under Step 2 are not mutually
exclusive. Thus, a household may still be in a hurricane shelter, be a recipient of the Public Assistance
Program, and be either a single parent or caregiver (e.g. grandparent) with a household including children
below 16 years, or have a disabled or elder head of the household. Households that meet eligibility criteria
for each of the three attributes would obviously qualify for prioritization. However, since the listing of the
three attributes does not signify a ranking in terms of priority, a decision is required on how to rank
households that do not meet eligibility criteria for all three attributes. The simplest solution would be to
group household into four descending levels of priority and apply numeric weights to the criteria: (1)
households that meet eligibility criteria for each of the three attributes, (2) households that meet eligibility
criteria for two attributes, (3) households that meet eligibility criteria for one attribute, and (4) households
that do not meet the eligibility criteria for any attribute. With respect to applying numeric weights, for
instance, more weight is given to persons in shelters, more weight to households with children, and so forth.
The weights can be expanded to also include another category for household composition. Hence, in
addition to weights for the household head (an indicator of capacity difficulty to finance their own home
reconstruction – captured in 3a 3b and 3c); a new vulnerable subcategory can be added on household
composition to weight households with children, a disabled member (certified severe disability) and
elderly). This is outlined in a separate prioritization scoring sheet and beneficiary ranking table not included
in this document.
It is critical that the first two steps of the beneficiary selection process, and in particular the attributes and
eligibility criteria for prioritizing and ranking potential beneficiaries, is communicated in a transparent,
clear and understandable terms to the public. This will eliminate (or at least significantly reduce) uncertainty
about who gets selected as beneficiaries. As a result, the outcome of the verification and validation under
Step 3 would be less challenged, and the volume of complaints to the Grievance Redress Mechanism
(GRM) regarding beneficiary selection would be reduced.
41 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
ELIGIBILITY CRITERIA, PRIORITIZATION & VERIFICATION
STEP 1: APPLICATION OF ELIGIBILITY
CRITERIA
STEP 2: CATEGORICAL PRIORITIZATION
AMONG ELIGIBLE HOUSEHOLDS
STEP 3: VERIFICATION
AND VALIDATION
PHYSICAL
Attributes Criteria Complia
nce
Attributes Prioritization Complia
nce
Activit
y
Source
Y
E
S
N
O
Y
E
S
N
O
1. House si
ze
Up to 500 sq. ft. 1. Protract
ed
displace
ment
a. Household is still living in a shelter
Verific
ation
List of eligible beneficiaries
(criteria verified by
local
inter‐sector committee)
2. Damage
Level
Completely destroyed
(BDA or site visit
where needed)
b. Household is still
living with others
Validat
ion
Information on the
application from
homeowner
3. Primary
Residen
ce
House is primary
residence prior to
hurricane
2. Demogra
phic
Vulnera
bility
a. Single parent hous
ehold with childre
n under the age of 16
Validat
ion
Final list is publish
ed for
transparency and feedback
4. Right to
the land
Ownership of the
property or
documented permission to use the property
b. Disabled head of h
ousehold
(including sight, mobility, speech,
mental)
5. Locatio
n
and risk
Low hazard risk area c. Elderly head of household
6. Not
impacti
ng
protecte
d area
or forest
reserve
Location must not be in protected area (PA) or
within 200 metres of
the PA
d. Existence of elderly dependent
SOCIO-ECONOMIC
7. Prior su
pport
Applicant has not recei
ved direct
reconstruction/structural
restoration of their
homes through Government or
donor housing program
3. Poverty
Status
a. Household is a reci
pient of
any Public Assistance
Program
8. Insuran
ce
coverag
e
Home is uninsured b. Part of house was
used as a source of livelihood/income
c. Unemployed due
to Hurricane Maria
6.2 Informal Occupancy
According to the BDA, of the 418 households who were tenant or leaseholders, about 25 percent had been
tenants in homes that were totally destroyed. Consultations with villagers have confirmed that there are two
distinct situations of tenancy. One is where the tenant/occupant owned neither the house or the land, and
the other where he/she owned the house but not the land. The HRP does not provide support to tenants
who do not have titles to house or property. Further, the project does not support commercial property. The
project however supports owners of the house who may not own the land, provided that the homeowner
can furnish official documents to proof ownership of the house. An agreement would be required between
house owner and the land owner.18
The intended beneficiary of project assistance must also be the occupant of the house as his/her primary
dwelling at the time of the hurricane. In addition, there is the need to define some form of secure home
owner in the replacement house. This period cannot be the economic life of the house (e.g. about 30 years),
because that would amount to expropriation of the land from the owner, and trigger OP 4.12 on Involuntary
Resettlement. The alternative is an agreement between the land owner and the home owner regarding
security of occupancy in the reconstructed house for a period considered long enough for the home owner
to recover economically and socially from the hurricane (e.g. 4-5 years), and occupancy during that period
should be under the same conditions as in the original arrangement of the house prior to the hurricane (that
is, if there is a rental fee for use of land, the fee should not suddenly increase beyond the existing fair market
rate in the area).
An agreement must be drawn between the land owner and home owner regarding legal ownership of the
reconstructed house after the period of secure occupancy. In the situation where the tenant had owned the
hurricane destroyed house, but not the land, he/she would also own the reconstructed house. At the
expiration of the period of secure occupancy, the landholder would negotiate with the tenant as to whether
(a) he/she continues occupation of the land, or (b) the landholder purchases the building at the fair market
value of the building at the time of the eviction. Moreover, in the second scenario where the beneficiary
owned the hurricane damaged house, he/she would at the planning stage be able to have the new
replacement house constructed on a different self-identified plot of land (e.g. a plot of land assessed as
hazard free, that he/she owns somewhere else in situ). This would need to be in good standing with the
current applicable laws in Dominica.
6.3 Environmental and Social Management Plan (ESMP) for House Construction
The houses/households that have been selected for the project housing reconstruction grant will receive
technical assistance from the project (the TACs with support from the Design & Supervision Firm funded
under Sub-Component 2.2) to decide on a house design that is within their financial resources (the project
grant and the beneficiary’s own resources), and to prepare the building design along with specifications and
cost estimate. The value of the grant will be equivalent to the estimated cost of building a modular core
house (about EC$50,000), with basic specifications and an area of approximately 500 sq. ft. The technical
standards to be applied under the project are based on a revised version of the Guide to Dominica’s Housing
Standards (2018) which are applicable to seismic and Category 5 hurricane events. 19 These standards will
be applied by the TACs/Design & Supervision Firm and the contractors to all rebuilds receiving direct
support under the project. Achievement of the standards will also be evaluated and monitored by the
18 Consultations with villagers also suggested that many land owners live abroad, and would need to be contacted
there concerning their consent to an agreement on reconstruction and security of home occupancy arrangements. 19 The Guide to Dominica’s Housing Standards updates and amends the building regulations (Building Code and
Building Guidelines) and the Physical Planning Act of 2002 to adequately and effectively respond to the need for
recovery in the housing sector. The 303 sq.ft area is defined as adequate for a basic modular core house.
43 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
TACs/Design & Supervision Firm. The design options comprise reconstruction of the existing house
incorporating design features to make it hurricane resilient, a prefabricated structure erected on site, a
modular house model (partially prefabricated or standardized) erected or built on site, and a fully custom-
designed house.
During the assessment of environmental hazard risks for potential beneficiary housing sites that was
undertaken during Step 1 of the beneficiary selection process, all destroyed houses found to be exposed to
such risks involving erosion or slope stability and landslide risks have been excluded as ineligible for
reconstruction assistance (unless they could be re-sited to a location without environmental hazard risks on
the beneficiary’s property). The environmental, social, health and safety impacts to be considered during
construction therefore involve only those related to good practice management measures for small-scale
construction works.
For the houses/households that have been selected, verified and validated, and for which the hurricane
resilient building design has been finalized and agreed to, the format for a simple environmental and social
management and plan (ESMP) guided by the HRP PIU safeguards specialists outlined in Annex 8 will be
used. The Design & Supervision Firm will be required to conduct compliance monitoring of the ESMP
before, at start, during and upon closure of site/decommissioning of site.
The Design & Supervision Firm will discuss and manage issues, including the Code of Conduct related to
the Contractor’s work with Village/Kalinago Councils and the beneficiaries. The Code of Conduct and
other standard operating procedures will be included in the ESMP. At this meeting, the Village Council
will also be informed about the Grievance Redress Mechanism (GRM), and how complaints regarding the
project including those relating to activities by the contractor and staff can be submitted and acted on by
the PIU.
Moreover, before construction activities start in selected implementation locations, the Design &
Supervision Firm will provide training and awareness to the beneficiaries (if involved in house
construction), skilled labor (e.g. masons, carpenters), and unskilled laborers on (i) the use of construction
equipment and the associated risks and safety issues, (ii) safety precautions when working on demolition,
debris removal, and housing construction activities, and (iii) other activities required to ensure compliance
with the ESMP.
If a ‘camp’ is needed, this would either be on Government or private land. As noted in Section 5.2 on
Health and Safety, Contractor ‘camps’ will not be needed where contractors operate close to their home
base. Where suitable Government land is available, an agreement is entered into between the contractor
and Ministry of Housing and Ministry of Public Works. If the ‘camp’ is located on private land, the
agreement is between contractor and land owner, and is submitted to the PIU. When closing and
dismantling work ‘camps’, contractors will remove all equipment and dispose of debris (to the landfill at
Fond Cole or other approved by the GoD and the PIU), and restore the site to the extent possible to pre-
occupancy conditions. These requirements will be included in works contracts.
6.4 Grant Agreements with Beneficiary Households
The project will enter into a Grant Agreement with selected beneficiary households regarding the
reconstruction of their house. This agreement will record:
• Names and unique identifier of all project beneficiaries and contact information
• The location data of the house (including geo-reference data), the type of title document, and that
a building permit has been obtained.
44 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
• Copies of accompanying documents of proof of identification and ownership / right to occupy
site/property.
• Acceptance letter.
• Site assessment report.
• Agreement regarding any re-siting of the replacement house on the beneficiary’s property to
mitigate natural hazards, which posed a risk for reconstruction in the original site.
• Banking details. Information on the beneficiary’s banking institution, the National Bank of
Dominica, a mandatory requirement specific to the HRP.
• The contribution committed by the beneficiary towards the construction in terms of funding, labor,
and materials, as well as the financial ceiling to be applied to the house reconstruction and site
works. A beneficiary may choose an option costing more than the grant, and the agreement will
verify that the resources available including the project grant are sufficient to construct the selected
house design.
• The mode of payment of the project grant in two or three tranches, and the milestones in the design
and construction of the house that will trigger payments.
• Design/construction documents. The beneficiary’s choice regarding the design of the house to be
built (type, size, features). A full set of construction drawings, and as the project advances, the
agreement should be amended to include change orders, and then upon completion the as-builts
should be included.
• The beneficiary’s choice of construction approach. That is whether construction by building
contractor, or managed by the beneficiary with local labor.
• Copies of all communications (electronic communication, call logs, meeting notes, etc.)
• Associated filed grievances.
Prior to the finalization of the Grant Agreement, the Technical Services (architects/engineers)
consultants/Design & Supervision Firm will inform each beneficiary fully of the procedures involved in the
housing reconstruction support under the project, the design and supervision assistance, and the options
available to them. Alternatively, it may be simpler to have enrollment sessions in each district with selected
beneficiaries, at least to convey the essential information initially. The assistance to be provided by the
project will include:
• Consultation with each beneficiary on the house design options available within their individual
financial resources, and preparation of a design, specification and cost estimate for the preferred
option (utilizing simplified documentation as much as possible).
• For disabled beneficiaries, the chosen design must include features that make the house disabled
friendly.
• Compilation of available legal information on the beneficiary’s property (a registered title, a
registered deed, or an unregistered deed), and if neither of these are available, assistance to the
beneficiary to obtain a title document (if not waivered for beneficiaries of the housing
reconstruction project, registration costs may be paid from the grant). Particular effort may be
required to assist beneficiary households headed by single parent, disabled, and elderly.
• For selected beneficiaries that are house owners on land that is owned by someone else, assistance
with contacting the land owners to obtain their consent to the reconstruction, and to the
conditionalities regarding security of home ownership.
• Assistance to the beneficiary to apply to PPD for the required building permit (free of cost).
45 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
• Where required, assistance to the beneficiary to shop for quotations from certified (pre-qualified)
building contractors or certified suppliers of building materials, and with review of a draft contract
or supply arrangement, prior to signing by the beneficiary.
• Assistance and information to the beneficiary regarding construction supervision comprising
regular site inspections and supervision of building works (including instructions for remedial
actions) and ESMP compliance, certification at key stages to ensure compliance with the design
specifications and resilience requirements, and reporting on the progress and stage compliance to
the beneficiary’s banking institution, and the PIU. This would also include assistance with the final
inspection for the Certificate of Completion from the PPD, and explanation of the rights of the
beneficiary during the Defects Liability Period. Here too, particular effort may be required to assist
beneficiary households headed by single parent, disabled, and elderly.
6.5 Indigenous People – The Kalinago
As described in Section 3.2, the Kalinago Territory Act of 2015 vests ownership of the Kalinago Territory
with the Kalinago people. All consultations regarding the preparation and implementation of the Housing
Recovery Project will be conducted through the Kalinago Council and the Ministry of Kalinago Affairs
(MoKA). The Council comprises seven elected members including the elected chief. Moreover, all land
within the territory is communally owned by the Kalinago, and under the Kalinago Council, the Kalinago
Territory Housing Committee, which comprises representatives from the Council, MoKA, and MoHL, is
responsible for allocation of land for housing. The Kalinago Territory of 3,782 acres comprises eight
hamlets organized into seven Hamlet Development Committees (two hamlets are covered by one
committee). In addition, the village of Atkinson, which is populated by Kalinago, but is not part of the
Kalinago Territory, is also included under the charge of MoKA.
Thus, the institutional framework exists for ensuring free, prior, and informed consultation resulting in
broad community support to the project by the Kalinago people as required by OP 4.10 on Indigenous
Peoples, and such support has been expressed during the initial consultations already held in the area. The
project’s overall approach to community engagement would also, with a few adaptations, suit conditions in
the Kalinago Territory:
1. The Kalinago Council and MoKA are the principal counterparts during preparation and
implementation of the project in the Kalinago Territory.
2. Hamlet Development Committees instead of Village Councils would be the entry-point for the
project’s information dissemination and local operational arrangements in the Kalinago Territory.
3. While the three-step selection process for project beneficiaries appear to suit conditions in the
Kalinago Territory, it should be reviewed in consultation with the Kalinago Council and MoKA,
and be adapted as required.
4. There are three areas where the beneficiary selection criteria and also the Grant Agreement with
beneficiaries would need to reflect Kalinago land tenure arrangements (consult the IPP for land
tenure process).
a. Under Step 1 of the beneficiary selection criteria, households would be excluded if their
destroyed house is located on a site assessed to have high hazard risk (and where it cannot
be re-sited within the property). Such cases would need to be referred to the Kalinago
Housing Committee, which would then confirm whether an alternative plot without hazard
risk can be allocated to the household.
b. Whereas the housing reconstruction Grant Agreement applicable to the rest of Dominica
will require confirmation from PPD that the beneficiary has documentation of ownership,
the requirement in the Kalinago Territory would be confirmation from the Housing
46 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Committee that the plot where the replacement house will be constructed was duly
allocated to the occupant (or ancestors) at some point in the past.
c. The Housing Committee normally reviews and approves building permits in the Kalinago
Territory, and it would likely also see a role for itself regarding review and clearance of
the application for building permit under the project.
5. Finally, the project’s GRM arrangements and process would also have to be discussed with the
Kalinago Council and MoKA to ensure that they fit with the culture and governance arrangements
in the Kalinago Territory.
An initial activity in the engagement with the Kalinago Council and MoKA should be to review and agree
on the beneficiary selection criteria and process that would apply in the Kalinago Territory. During
consultations, both the Kalinago Council and MoKA have made the point that since poverty is widespread,
and since even the preliminary damage data indicate that the proportion of totally destroyed houses in the
Kalinago Territory was more than twice as high as the national average, consideration should be given to
an early start of project implementation in the Kalinago Territory.
Finally, the Kalinago Council has emphasized that as much as possible the housing reconstruction work
should be done involving local labor, which would help address the high unemployment in the area. In this
regard the project could assist with training and technical assistance.
6.6 Forest and Timber Resources
Dominica does not have any large-scale forest operations. The island’s steep topography limits access to
its forests, and timber processing is largely for local consumption. Hurricane winds and intense rainfall
produced widespread damage to the forest system, and the PDNA estimates that 10 to 20 percent of the
trees in the forests throughout the island were completely knocked down. For the remaining 80 percent of
the forest area, it is expected that the trees that survived the hurricane, although stripped of leaves, will be
able to re-establish a closed canopy.
Total forest damages are estimated to amount to EC$80.24 million (US$29.72 million). The forest area
with trees usable for construction is estimated to cover 9,552 ha (23,593 acres). Based on a PDNA field
visit in October 2017 it is estimated that approximately 20 commercial trees species were blown over or
destroyed by the Hurricane. These figures suggest that there would be about 47,000 hurricane destroyed
trees of which a proportion would be useable for construction lumber, where they can be accessed.
Timber is one of the basic construction materials used in the remote rural areas. The reconstruction of
houses will increase demand for timber, and measures to make use of available downed trees and manage
the risk to Dominica’s extensive forests could include:
• In addition to the re-use of salvaged timber from demolished buildings, the project could wherever
possible, promote the re-use of trees downed by the hurricane (removal and salvage clearing of
fallen forest trees to supply construction timber). The quality of such timber should be verified with
the Forestry, Wildlife and National Parks Division.
• The Government could consider facilitating a distribution and selling process of fallen trees in the
various forest areas of the country for the reconstruction to simplify the supply of necessary timber.
At a consultation in the Kalinago Territory, members of the Kalinago Council proposed that a
process be established to enable that fallen trees in nearby forest areas are utilized for house
47 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
reconstruction (they argued that most of the hurricane destroyed houses in the area were built with
imported lumber which was inferior to that harvested locally).
• A practice commonly used in Dominica to salvage fallen trees and to convert round logs into
building material is chain-saw lumbering.20 The Forestry Division maintains a list of 120 chainsaw
operators, to whom it has sold trees in the past. The PDNA suggests that chainsaw operators could
be encouraged to salvage as much wood as possible, and that operators who do not have a saw
could be provided with one through a lease agreement. Upon completion of any such task the saw
and sawmill would be returned to the Forestry Division in order to establish management control
of the milling activity beyond the project.
6.7 Cultural Heritage
The likelihood of archaeological chance finds is limited since most houses will be reconstructed on the
original foot-print. However, pre-Colombian artefacts may be found across the island as may physical
cultural remains of later occupation. There is as yet no archaeological legislation in Dominica, but the
Physical Planning Act of 2002 states that PPD may impose conditions on granting a development
permission (building permit) to arrange for “the preservation of any buildings or sites of importance to the
cultural heritage of Dominica.” In case of archaeological chance finds during housing reconstruction
activities, the location of the find will be reported to PPD and to the Dominica Museum in Roseau (the
National Museum of Dominica), to which the find will be handed over. Should the find appear to be part
of a larger archaeological site, both PPD and the Museum in Roseau should be consulted before civil works
progresses.
20 This is done by so-called Alaskan mill lumbering, which involves cutting boards with a frame-mounted chain-saw.
SECTION 7: COMMUNICATION: CONSULTATION,
INFORMATION DISSEMINATION
During preparation of this ESMF, consultations were held about the project’s environmental and social
aspects with relevant ministries and departments of the Government, potential beneficiary groups, and with
the Kalinago Council and MoKA. Notes from these consultations are attached in Annex 11 of this
document. Prior to that, initial consultations were held with the Kalinago community during project
preparation in February 2018, and by the Government in connection with preparation of the draft
Indigenous Peoples Plan.21 The finalized Indigenous Peoples Plan was disclosed and can be found at the
following link: http://dominica.gov.dm/notices/870-indigenous-peoples-plan-housing-recovery-project .
Nation-wide Information Campaign: Project implementation should be preceded by nation-wide
information campaigns using radio, television, online media, and community information sessions and
other communication channels.22 The focus should be on informing the public about the scale of the project
(1,700 destroyed houses to be reconstructed), the geographical locations where TAC/Design & Supervision
Firm staff will be deployed to start implementation, the eligibility criteria and beneficiary selection process,
application procedures and locations; the technical assistance and advice that will be available to project
beneficiaries, and the Grievance Redress Mechanism (GRM). A brief (preferably one page) flyer/leaflet
giving a simple illustrated portrayal of the approach from beneficiary selection through construction should
also be considered.
Local Level Consultations: Following the deployment of TAC/Design & Supervision Firm staff to the
geographical locations where village level activities will take place, consultations will take place with
Village Councils as follows:
• A meeting should be held before the start of physical works with participation by the Village
Council, the contractor(s), the PIU (including environmental and social staff), and the TAC/ Design
& Supervision Firm. Issues related to the work and the contractor’s presence should be discussed
and agreed upon in writing. This would inter alia include (i) agreement on a ‘code of conduct’ for
contractor and staff, (ii) a commitment to conduct activities which generate noise or involve
movement of heavy trucks during the periods of the day that will result in the least disturbance, and
(iii) location of the contractor camp, if a camp is required.
• At this meeting, the Village Council should also be informed about the GRM, and how complaints
can be submitted and will be acted on by the project.
• After the project’s identification of beneficiaries, a meeting of the Beneficiary Selection Review
Committee involving representatives of the Village Council, religious, civil society, among other
groups, will be held to review, verify and validate the list and agree on the confirmed beneficiary
households. This list, which will include both project beneficiaries and households referred to
assistance from other projects and programs, will be made public at the Village Council office and
on-line (project website at MoHL) as a final step in validation and confirmation.
• Follow-up meetings between Village Council (and interested beneficiaries), contractor(s), the PIU,
and staff from TAC/Design & Supervision Firm should be held at least monthly to (i) report on the
21 Finalization of the ESMF will require further consultations with the relevant stakeholders including the Kalinago
Council and interested members of the public. 22 The Project Results Framework stipulates three information campaigns in the first year of implementation, and at
least one campaign a year in the following years.
49 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
status of construction, (ii) discuss and if possible, resolve complaints received through the GRM,
and (iii) deal with any other issues of importance for implementation progress and project-
community relations.
In the Kalinago Territory, similar meetings should be held at the level of the Kalinago Council and with
the Hamlet Development Committees where project implementation is taking place. Consultations held
before the start of civil works between the project and the Kalinago Council and MoKA include:
• As described in Section 5.5, consultations should be held with the Kalinago Council and MoKA
before the start of civil works to agree on the modifications that may be required for the beneficiary
selection criteria and process to ensure compatibility with the decision-making processes and land
tenure arrangements in the Kalinago Territory. Additionally, it should be considered in which areas
the project’s GRM would need to be modified to fit with the Kalinago culture and governance
arrangements.
• Another early exercise to be undertaken before the start of civil works comprises collaboration on
updating and verifying the information on housing damage (the BDA), in order to enable the
identification and selection of beneficiaries based on the project methodology (or a modified
version of this).
• Meetings to review, validate, and confirm the list of selected project beneficiaries that met the
criteria of Step 1 and 2 will take place at the level of the Hamlet Development Committee with
representation from the Kalinago Council. Here too, the list will include both project beneficiaries
and households referred to assistance from other projects and programs, and will be made public at
the Hamlet Development Committee’s office and on-line.
• Issues related to the contractor’s presence and work should be discussed and agreed upon in writing
at the level of the Kalinago Council and MoKA. Where needed, the Kalinago Council should help
identify locations for contractor ‘camps’.
Similar to elsewhere in Dominica, consultations should be held at the start of project implementation at the
level of the Hamlet Development Committees, and with participation of representatives from the Kalinago
Council, to inform about the agreements reached concerning the approach to beneficiary selection,
grievance redress procedures, and the presence and conduct of contractors and workers. Follow-up
meetings on the progress of civil works, complaints, and other issues similar to those involving Village
Councils should be held at regular intervals.
SECTION 8: CAPACITY BUILDING
Capacity building will be important for the implementation of the safeguard-related activities described
above, and will be required at different levels of the institutional set-up for the project. Safeguards staff
from the PIU (supported by their counterparts from the IST) will provide safeguards related capacity
building for the TACs, for local government entities comprising the Village Councils, and the Kalinago
Council and Hamlet Development Committees in the Kalinago Territory. The capacity building in
environmental and social safeguards will cover three aspects.
Project Safeguards Staffing: In addition to the PIU level safeguards staff, each of the TACs and satellite
TACs will, as described above in Section 8, need to have one of its staff designated as responsible for day-
to-day safeguards management at the implementation level of Village Councils and Hamlet Development
Committees. The tasks of such designated TAC safeguards staff will include (i) collection of demographic
data on potential beneficiary households to assist updating of the BDA, (ii) participation in meetings that
will be held at different stages with Village Councils and Hamlet Development Committee (on the project
approach, on verification and validation of beneficiaries, on project progress and issues), (iii) participation
in the monitoring of ESMP compliance, and (iv) being the local focal point for the GRM and responsible
for data entry into the GRM database on complaints and complaints resolution within the area of the TAC
or satellite TAC in question.
Training Materials: Based on the Operations Manual and this ESMF, three types of training programs on
safeguards and social development will need to be developed:
1. An overall introduction to all staff at the PIU and TAC levels on the project’s approach to
management of environmental and social issues with focus on the process and criteria for
beneficiary selection (including adaptations to address conditions in the Kalinago Territory), the
grant agreement with beneficiary households, the ESMP, and the GRM.
2. A training course for the designated TAC safeguards staff, which covers the same topics as the
overall introduction, but with much more detail to make the participants fully conversant with the
approach to management of environmental and social issues, and with the MIS databases (registry
and GRM) that they will be working with.
3. An introduction to local government entities comprising the Village Councils, and the Kalinago
Council and Hamlet Development Committees in the Kalinago Territory, and other beneficiary
selection committee members identified previously on the project approach covering the process
and criteria for beneficiary selection, the grant agreement with beneficiary households, the GRM,
and the meetings at different stages between the project (the TACs/Design & Supervision Firm)
and the local government entities on verification and validation of beneficiaries, relations with
contractors, grievance redress, and overall project status and issues.
Community Level Technical Training: The TAC/Design & Supervision Firm will provide two types of
training in the selected implementation locations:
• Free technical advisory services to homeowners on demand, including technical training on the
application of resilient building practices.
• Training and awareness before start of construction activities to beneficiaries involved in house
construction, skilled laborers (e.g. masons, carpenters), and unskilled laborers on (i) the use of
construction equipment and the associated risks and safety issues, (ii) safety precautions when
working on demolition, debris removal, and housing construction activities, and (iii) other activities
required to ensure compliance with the ESMP.
SECTION 9: GRIEVANCE REDRESS MECHANISM (GRM)
9.1 GRM Scope and Summary
The project will establish a Grievance Redress Mechanism (GRM) to receive and process complaints and
grievances related to project activities, and to provide the public with an avenue to provide feedback on the
reconstruction activities supported by the project. A well-functioning GRM is central to the project’s ability
to be responsive to the population in general and the hurricane affected population in particular.
Purpose: The GRM will formalize the management of grievances of external stakeholders to minimize
the environmental, health, safety and social risks resulting from the Housing Recovery Project (HRP).
The grievance process, outlined in the document, provides an avenue for external stakeholders to voice
their concerns and gives transparency on how grievances will be managed internally, which aims to
reduce conflict and strengthen relationships between internal stakeholders and external stakeholders. T 2.
The Grievance Redress Mechanism (GRM) applies to all external and internal stakeholders of the HRP’s
operations during project implementation, including during selection of beneficiaries, reconstruction and
monitoring activities.
Process & Responsibilities: For grievances filed, there will be a normal response time of 5-10 working
days for each case starting from the date the grievance is officially received by HRP, however high-level
cases may require 10-20 working days for a response. The Project Implementation Unit (PIU) shall meet
and discuss, inter alia, grievance and resolutions to determine the level of the complaint (level 1, level 2,
level 3). This process is led by the project’s Social Safeguards Specialist with support from the relevant
team members including: Environment Specialist, Implementation Support Team (IST) Safeguards
Adviser and Project Implementation Unit (PIU) Project Manager. For grievances classified as level 2 and
3 cases, the Social Safeguards Specialist will direct the matter to the Project Manager with the support of
the IST. The internal (PIU and IST) team will meet regularly to work through the outstanding and
difficult grievances and decided jointly on the actions required and communications to the complainant.
If, this group are not able to resolve the matter they can seek guidance from the Climate Resilient
Execution Agency of Dominica (CREAD) and the Permanent Secretary, Ministry of Housing and Lands.
If the grievance continues to be unresolved, a grievance committee meeting will be initiated with the
following participants who make up the HRP Grievance Redress Committee comprising no more than
seven persons who are representatives of:
• Village Councils
• Religious Organisation
• Credit Union, Financial institution or cooperative Association
• NGO's or other civic groups in the region
• Other prominent citizens e.g. Justice of Peace, community activist
• Professionals/academia
If the grievances are extensive, the PIU will explore establishing more than one grievance committee per
region, to ensure that there are sufficient committees established to address grievances in a timely
manner. These committee members will be identified and sensitized on the GRM by the HRP PIU.
The current Grievance Mechanism (GM) is included in the PIU Operations Manual and the
Environmental and Social Management Plan (ESMP) with the objective to formalize the management of
grievances at the PIU level, to minimize the environmental, health, safety and social risks to the Project
and to avoid triggering the Bank’s corporate Grievance Redress System (GRS).
The following is a flowchart illustrating the GRM.
Categories of Complaints: The following general categories of complaints/grievances will be considered
to be within the scope of the project’s GRM:
Complaint Category Grievance Detail
Awareness Complaint On lack of information on various components of the project.
Eligibility Grievance These may require revisiting the beneficiary selection assessment for
verification of the data supporting the original decision to classify the
complainant as ineligible.
Administrative Complaint Such as missing application forms, lack of supporting documentation, etc.
Title| Permit Delay In confirmation of land title (or informal occupancy status), or issuing of
building permit.
Payment Delay Regarding the scheduled release of installments for the project’s housing
reconstruction grant.
Fiduciary Complaint Involving allegations of fraud, collusion, and corruption.
Compliance & Inspection
Complaint
Involving dissatisfaction with results of the building inspection by the
Design & Supervision Firm/TAC, complaints regarding the timing of
inspections, or their conduct (behavior, attitude, absenteeism), environmental, health and safety concerns.
Construction Complaint Regarding either the quality of work by building contractors, the quality of
materials, or their conduct (behavior, attitude, absenteeism).
Community Complaint On lack of implementation of social and environmental safeguards.
The instrument used to detail how complaints will be received, assessed and solved is the HRP Grievance
Redress Mechanism. This tool will be used by the HRP PIU and their direct players and key partners
included contracted entities in managing grievances and resolutions.
Consult the HRP Grievance Redress Mechanism for further details.
9.2 World Bank Grievance Redress System
Communities and individuals who believe that they are adversely affected by a World Bank supported
project may submit complaints to existing project-level grievance redress mechanisms or the World Bank’s
Grievance Redress Service (GRS). The GRS ensures that complaints received are promptly reviewed in
order to address project-related concerns. Project affected communities and individuals may submit their
complaint to the World Bank’s independent Inspection Panel which determines whether harm occurred, or
could occur, as a result of World Bank non-compliance with its policies and procedures. Complaints may
be submitted at any time after concerns have been brought directly to the World Bank's attention, and Bank
management has been given an opportunity to respond. For information on how to submit complaints to
the World Bank’s corporate Grievance Redress Service (GRS), visit www.worldbank.org/grs. For
information on how to submit complaints to the World Bank Inspection Panel, please visit
www.inspectionpanel.org.
.
SECTION 10: MONITORING AND REPORTING
Progress in the achievement of the Project Development Objectives (PDO) will be measured through the
following three indicators: (i) direct project beneficiaries, (ii) the number of households with resilient
housing recovered using Project subsidies (the housing grant), and (iii) the number of households that
accessed general advisory service from TACs and benefit from a streamlined permitting process. All three
indicators have been disaggregated by gender. Other secondary level intermediate results indicators also
measure achievement of social outcomes (a summary of the Results Framework is in Annex 9). The
monitoring and supervision of compliance with the World Bank applicable safeguards will be implemented
through supervision of the ESMPs during the construction of the households.
Management Information System (MIS): The overall monitoring and evaluation (M&E) for the project
will be managed by the PIU, with high level oversight by the Housing Task Force (HTF). A project
Management Information System (MIS) will house the data to be used in the generation of periodic reports
and updating of indicator results. The core of this MIS will be a registry database, which will contain the
data from the housing recovery program including the nominee and beneficiary databases (inclusive of
names and unique identifier of all project beneficiaries and contact information; copies of accompanying
documents of proof of identification and ownership / right to occupy site/property; copy of signed
acceptance letter; copy of agreement; banking details; financing details; copies of PPD applications,
inspections, responses, notices; copies of all communications (electronic communication, call logs, meeting
notes, etc.); site assessment report; design/construction documents; associated filed grievances) and the
implementation process, including designated access levels and measures to ensure confidentiality.
Data collection process: The primary data for the MIS will be collected at the level of each of the
communities (Village Councils and Hamlet Development Committees), before the data are aggregated for
the District in question by the TAC / Design & Supervision Firm, and forwarded to the PIU for generation
of consolidated reporting covering the entire project. The Project Results Framework stipulates semi-
annual reporting. However, project management by the PIU, would require more frequent reporting (e.g.
monthly) from the District level in order to assess the status of the project, and identify the bottlenecks that
need to be addressed to advance implementation progress
Registry database: For the MIS to have optimal operational usefulness, it will be important that the registry
database is set up so that it will have data on23 the suggested following modules:
(i) a module on applicant households with their associated application information (home and
demographic), documentation presented, eligibility status etc
(ii) a module for beneficiary households with info on construction type, etc, and to support
payment, compliance monitoring etc.
(iii) A grievance module to record complaints and their outcomes
Specific data entries or a specific subsidiary version of the registry database would have to be created to
accommodate the adaptations of the beneficiary selection process and confirmation of land usage (as
distinct from ownership), that will apply to the Kalinago Territory. Modifications in the registry database
23 The ToR for the consultant, that will be engaged to assist the Information and Communication Technology (ICT)
Unit and the development of the registry database, should address these data requirements.
55 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
would also need to be made to capture the particular characteristics of beneficiaries under informal
occupancy arrangements (tenants).
An MIS centered on the registry database, that would include the type of data listed above, would be able
to generate data on achievement of the PDOs and intermediate results indicators. In addition, it would
enable reporting on these and other results at different levels from that of individual villages (Village
Council areas) to the national level, including results regarding coverage of priority beneficiaries including
women headed households, households with disabled head of household, and households with elderly head
of household, as well as data on ineligible households referred to other projects and programs. The MIS
would contain the data for progress reporting by the Design & Supervision Firm on achievement of
construction targets and possible bottlenecks in reaching these. It would also allow comparisons between
results in different Districts, and between the Kalinago territory and elsewhere in Dominica.
To enable upstream data entry for each beneficiary household (as part of the registry database) regarding
(i) eligibility under the beneficiary selection criteria, (ii) Grant Agreement, (iii) disbursements for house
construction, (iv) physical implementation progress, (v) compliance with the ESMP, and (vi) completion
certification, it should be considered to develop an App that can be used by TAC / Design & Supervision
Firm field staff to record the information as soon as it is available. This would also assist the project’s
transparency goals by providing timely information for the envisioned online access to data on beneficiary
selection down to the household level.
Reporting: At critical stages throughout the project, including key milestones, reporting by each contracted
entity is required as guided by the PIU.
SECTION 11: BUDGET REQUIRMENTS FOR ESMF
IMPLEMENTATION
The budget requirements for implementation of the ESMF are covered by the funding allocated for the
project components excluding sub-component 1.3. Costs will include: (i) the planning, technical assistance,
consultation and information dissemination, capacity building, and monitoring of replacement housing -
Sub-Components 1.1, 1.2, 2.2 and Component 3; and (ii) construction of individual house undertaken in
compliance with the house-level ESMP - Sub-Component 2.1. Expenses associated with environmental and
social safeguards fall into three major categories.
• Cost of Environmental and Social Personnel: All environmental and social personnel at the PIU
under MoHL, the IST within MoF, and the Design & Supervision Firm and TAC staff will be part
of the overall human resources for the project. Hence, no separate budget allocation is needed for
the environmental and social staff. The Beneficiary Selection and Grievance Redress Review
Committees will also be facilitated to fulfil their respective duties. Personal protective equipment,
is required for staff of PIU and IST for site inspections, which may fall under the operations budget.
• Cost of Environmental and Social Monitoring. The Technical Services (architects/engineers)
consultants will conduct site visits during the beneficiary selection assessment screening process.
Monitoring by the PIU and collection of primary monitoring data by the Design & Supervision
Firm is covered under the overall program supervision and monitoring. Development of
Management Information Systems to support planning and monitoring processes in project
agencies including development of a registry database is funded under Sub-component 1.2. Some
costs involve transportation, telecommunication, meeting venues, and tablets for field work.
• Cost of Environmental and Social Capacity Building and Communication. These activities
will be combined with other trainings, awareness and information activities. Hence meetings,
handbooks, website development and maintenance, cost of implementing and facilitating
grievances are some expenses covered in respective allocations in the HRP budget. The PIU will
develop national information campaigns, and an environmental and social training for staff in the
TACs. Awareness and communication / information dissemination at the local level will be
planned and implemented by the PIU, with support by the Technical Services consultants in the
beneficiary selection process, and by the TACs/Design & Supervision Firm throughout the project
as part of their engagement with Village Councils / Hamlet Development Committees, Contractors,
and beneficiaries of housing reconstruction assistance.
Further to the cost of the HRP PIU, the household beneficiaries will need to consider in their budget the
following underlying expenses that may arise in implementing the ESMP and this should be conveyed to
them by the Design & Supervision Firm. They include but are not limited to transportation, debris
management, asbestos handling, pest control, tree felling or trimming fee, aggregate from official quarries
and initial application expenses.
ANNEXES
Annex 1: Relevant National Legislation, Policies, and Plans
Legal / Policy Document and Description Relevance to the Project Responsibility Dominica Climate Change Adaptation Policy (2002)
The Policy mandates establishment of legal and institutional
frameworks for environmental management and climate change
adaptation.
The project incorporates climate
change adaptation by:
• Only providing house
reconstruction grants for
locations not exposed to risks
from slope stability, landslides,
and flooding.
• Requiring the design of all
houses funded by
reconstruction grants to be
resilient to Category 5 storm
events.
• Providing technical assistance
and advice on demand to all
homeowners to ‘build back
better’ with hurricane resilient
building techniques.
Climate Change, Environment and Natural Resources
Management Bill (2014)
The Bill is currently being reviewed by a Parliamentary Committee
prior to presentation to the House of Assembly for adoption.
The Bill would establish a Department of Climate Change,
Environment, and Development with a mandate to implement and
coordinate government policies and programs relating to climate
change, and to integrate climate change into the Environmental
Impact Assessment and physical planning process.
Physical Planning Act (2002)
• The Act provides for the orderly and progressive development of
land in both urban and rural areas, for the grant of permissions to
develop land, and for other powers of control over the use of
land. The Act details the application and approval process which
is executed through the Physical Planning Division of the
Physical Planning and Development Authority.
• The Act states that: ‘No person shall carry out any development
of land except under and in accordance with the terms of a
development permission granted in that behalf prior to the
commencement of such development,’ and makes provision for
the Authority to consult with local authorities where such
consultation is desirable in the interests of good planning.
• ‘Every application for permission to develop land, made by the
owner of the land, shall be accompanied by a certified copy of
the applicant’s certificate of title or other relevant title document
in respect of the land to which the application relates.’
• ‘Unless the Authority otherwise determines, environmental
impact assessment shall be required in respect of any application
for development permission where the Authority finds that
‘significant environmental harm could result’.
• The Authority may impose conditions on a grant of development
permission to arrange for ‘the preservation of any buildings or
sites of importance to the cultural heritage of Dominica.’
Any housing development to be
carried out in Dominica requires (i)
an application including relevant
title documentation, and (ii) a
development permission (building
permit) granted prior to the
commencement of the development.
Construction that may cause
‘significant environmental harm’
would require an environmental
impact assessment. The housing
reconstruction under the project will
be mostly done in situ, and the
project’s ESMP identifies the likely
environmental risks to be managed.
The project’s archaeological chance
find procedure accommodates the
requirement to safeguard the
cultural heritage of Dominica.
Physical Planning
Division
Title by Registration Act (1980)
The act defines title to land as a Certificate of Title issued in two
copies by the Registrar of Titles. One copy is to be archived in the
Government’s Register of Titles, and the other kept by the land
owner.
The Act lays out the requirements for obtaining a Certificate of Title
for land not yet registered under the Act, which can be based on
different forms of documentation such as (i) a good documentary title
As described above, a condition for
the development permission
(building permit) is relevant title
documentation, and assistance from
the project to obtain this for selected
beneficiary households without a
Certificate of Title will be critical to
remove a potential bottleneck for
Registrar of Titles
58 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Legal / Policy Document and Description Relevance to the Project Responsibility of ownership for a least thirty years, (ii) deeds or other documentation
of an undisturbed possession or ownership for twelve years, (iii)
acquisition by descent or will or deed from somebody who would
have been entitled to have the land registered, or (iv) if the land has
been in the sole and undisturbed possession of the applicant alone, or
as executor, administrator or trustee for 30 years.
physical implementation of housing
reconstruction.
Solid Waste Management Act (2002)
The core functions of the Solid Waste Management Corporation, whose
functions are inter alia:
• Provide storage facilities for solid waste.
• Procure equipment for the collection, transportation and disposal
of solid waste.
• Convert existing dumps into sanitary landfill sites.
• Develop and manage new sanitary landfill sites and other disposal
methods.
• Provide facilities for the treatment and disposal of biomedical and
hazardous wastes.
• Encourage recovery of recyclable items from solid waste.
• Prepare plans and programs to address the problems of solid waste
management in Dominica.
• Oversee the management of all solid waste collection and disposal
systems in Dominica.
The Act informs the procedures to
be followed or guide to the
management of building debris from
damaged and destroyed houses as
well as construction debris:
• Both types of debris will be
moved to and deposited at the
Fond Cole sanitary landfill (or
other approved by the GoCD
and the PIU). This requirement
will be included in contracts
with building contractors.
• Effort should be made by the
project to support DSWMC to
place recycle bins for different
types of debris in villages
where reconstruction takes
place.
Dominica Solid
Waste
Management
Corporation
(DSWMC)
Forestry and Wildlife Act
The Forestry Act provides the Forestry, Wildlife and National Parks
Division with the tools for examination and control of forest use.
National Parks and Protected Areas Act
The National Parks and Protected Areas Act gives the National Parks
Unit In the Forestry, Wildlife and National Parks Division the
authority to govern and manage the use of PAs in Dominica,
particularly the UNESCO World Heritage Site, the Morne Trois
Pitons National Parks where homes are adjacent to the park where at
times illegal activities occur that relate to local livelihood.
Any forest or river resources used
must be approved, and restricted use
in protected areas (PA) as well as
near the borders of PAs must follow
the management arrangements of
the Forestry, Wildlife and National
Parks Division
Forestry, Wildlife
and National
Parks Division
Pesticides Control Act
Dominica has signed the UN Convention on Persistent Organic
Pollutants. At the local level, the Pesticides Control Act governs the
types, use and management of pesticides to control pests on island.
Any use of pesticides must be in
line with approved pesticides to
control pest as governed by the
Pesticide Control Board.
Pesticide Control
Board
Approved pest
control companies
Dominica Building Code (1996)
The Building Code provides the physical planning authorities with the
tools for examination of development proposals to ensure that all
developments are in concert with the physical, social and economic
requirements of the Organization of East Caribbean States.
Any housing development to be
carried out in the country must
comply with the Building Code.
Physical Planning
Division
Guide to Dominica’s Housing Standards (2018)
The Guide is a derivative from the Dominica Building Code and the
Dominica Building Guidelines, and is intended to serve as an easy
reference tool for all stakeholders involved in roofing
repairs/reconstruction, and partial or complete reconstruction of
residential buildings post Hurricane Maria. The guidelines aim to
meet the minimum standards in accordance with ‘Build Back Better’
principles catering to housing structures which are resilient to weather
and seismic events.
Any housing development to be
carried out in the country must be
done in accordance with the
Building Code and meet the
Housing Standards. This is the
basis for informing the housing
reconstruction activities under the
project.
Ministry of
Housing and
Lands
59 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Legal / Policy Document and Description Relevance to the Project Responsibility Dominica National Land Use Policy (2014)
Dominica has a strong tradition of protecting its natural resources
including through a system of National Parks and protected areas
which cover a significant portion of the island. The long-term vitality
of these systems contributes to resilience against natural hazards and
the impacts of climate change, and contributes to high quality soil for
agricultural production.
The project’s criteria for eligibility
for the housing reconstruction grant
excludes any house in a National
Park or Forest Reserve.
Hurricane Maria caused extensive
destruction of forest trees, and
salvage and use of fallen trees as
lumber for house reconstruction
could be considered.
Division of
Forestry
National Policy and Action Plan for Gender Equity and Equality
(2006)
The policy is guided by Government’s recognition that the
development of Dominica hinges on the creation of an environment
free from institutional and ideological barriers of gender which
impinge on human development, and by extension national
development. The national gender policy of Dominica seeks to apply
a gender perspective to the key sectors of health, education, training,
housing, and the provision of basic amenities, poverty reduction and
the generation of sustainable ESMPloyment opportunities toward the
creation of an equitable and just society to assist all Dominicans, of
both sexes, in reaching their full potential.
The project’s prioritization criteria
for eligibility for the housing
reconstruction grant includes
female-headed households with
children below 15 years of age, and
the target is that 35 percent of the
1,700 households with totally
destroyed homes, who receive the
housing grant, should be female
headed.
Bureau of Gender
Affairs in the
Ministry of Social
Services, Family,
and Gender
Affairs
Kalinago Territory Act (2015)
The Carib Reserve Act was enacted in 1978, the year of Dominican
independence. It reaffirmed the territorial boundaries first established
by colonial authorities in 1903, legally established common
ownership of land within the reserve, and the office and powers of an
elected chief and council. A department of Carib affairs was
established in 2000 and upgraded to a Ministry of Kalinago Affairs in
2014. In March 2015, an amendment was made that changed the
name of the Carib Reserve Act to the Kalinago Territory Act, and
replaced the word ‘Carib” with ‘Kalinago’, and ‘Reserve’ with
‘Territory’. Other than that, the content of the 1978 Act remains
unchanged.
The Act provides the institutional
framework to ensure free, prior, and
informed consultation resulting in
broad community support to the
project by the Kalinago people as
required by OP 4.10 on Indigenous
Peoples, and such support has been
expressed during the initial
consultations held in the area. The
project’s overall approach to
community engagement would also,
with a few adaptations, suit
conditions in the Kalinago
Territory.
Kalinago Council
and Ministry of
Kalinago Affairs
Dominica Land Acquisition Act (1946, amended in 1986) The Land Acquisition Act, Chapter 53:02 deals with the acquisition
of land by the state, and outlines procedures in acquiring private land
for a public purpose.
The Land Acquisition Act is largely consistent with the requirements
of OP 4.12 on Involuntary resettlement, except with regard to the
timing of compensation payments. OP 4.12 requires that
compensation must be made prior to use of acquired land, whereas the
Land Acquisition Act allows for compensation after land has been
acquired.
OP 4.12 and the Land Acquisition
Act will not be triggered by the civil
works under the Housing Recovery
Project.
The Lands and
Survey Division
in MoHL and the
Property
Valuation Unit
within the
Ministry of
Environment,
Natural
Resources,
Physical Planning
and Fisheries.
Dominica Resettlement Strategy (no date)
A comprehensive approach to the resettlement process undertaken by
the Government of Dominica after Tropical Storm Erika in 2015. The
strategy intends to guide the process to resettle communities and
families that cannot continue living where they used to live –
Guided by the Dominica
Resettlement Strategy, the
Government aspires to carry out
major housing reconstruction
projects, including the construction
Responsibility for
planning and
implementation is
not described, but
would likely
60 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Legal / Policy Document and Description Relevance to the Project Responsibility regardless of whether or not their houses were destroyed or damaged
by Tropical Storm Erika - because the land on which they were settled
is highly vulnerable to natural hazards. It establishes the principles
and main guidelines for the resettlement process, assesses the main
issues to be addressed, and drafts a broad timeline for its
implementation.
of 1,000 housing units in new sites
for households living in areas highly
vulnerable to natural hazards. This
is one of the programs that
households found ineligible under
the Housing Recovery Project may
be referred to.
include the
entities involved
in implementation
of the Land
Acquisition Act.
Annex 2: Map of Dominica’s Health Districts
Annex 3: Map of Dominica’s Village Districts
Annex 4: Guidelines for World Bank Code of Conduct for Contracted Entities
The objective of the Worker’s Code of Conduct is to avoid or minimize as much as possible, any negative
impact that could be produced as a consequence of interrelations between the workers inside the local areas
of influence and the outskirts of the Project Area. The Contractor shall implement a Code of Conduct
consistent with the guidelines included herein to assist all employees to:
o Understand expected standards of conduct and behavior;
o Comply with relevant laws and policies;
o Demonstrate and promote good ethical work practice;
o Respect colleagues, supervisors and community members.
Contractors shall ensure that each worker receives a written copy of this Code as part of the induction
process and as part of the Contract. As a requirement to be hired, all workers must sign a copy of this Code,
where they acknowledge it and certify they have read it and accepted its terms, promising to comply with
its terms thoroughly and at all times. Additionally, copies of this Code shall be made available at a visible
location at the project site.
Under the Code of Conduct all workers shall:
o Consider people equally without prejudice or favor;
o Act professionally with honesty, consistency and impartiality;
o Take responsibility for situations, showing leadership and courage; and
o Place the public interest over personal interest.
o Observe standards for safety.
o Be fiscally responsible and focus on efficient, effective and prudent use of resources.
The workers are obliged to comply with the rules and procedures indicated in the Code, so as to maintain
good relations with the local community in the direct area of influence of the Project. Any worker may be
subject to disciplinary actions and/or may be fired if their behavior while he/she is employed on the project
goes against the rules stated in the Code. However, workers shall have access to the Grievance Mechanism
for the Project (see section 19).
Under the Code of Conduct, as a minimum, workers shall comply with the following rules:
Rules Regarding the Local Population
The local population is defined as all people that live within the direct area of influence of the Project,
or in the areas used for the transportation of equipment and materials required for the activities of the
Project.
All workers are expected to behave adequately at all times and must avoid improper relations with the
local population. The Contractor will not tolerate any form of harassment or discrimination, including
behavior, comment, jokes, slurs, email messages or any other social media, pictures, photographs, or other
conduct that contributes to an intimidating, disrespectful or offensive environment.
All workers shall avoid any discriminatory conduct based on gender, age, disability, race, language,
culture, political affiliations, philosophy, religion, or any other basis.
All workers must comply, at all times, with all applicable environmental and health and safety rules
and regulations.
64 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Should the worker fail to comply with the Code or behave in such a way that he/she creates a problem
with the local population, the corresponding action must be communicated to the Contractor, detailing what
happened, so that the Company can carry out an investigation.
Rules regarding the Construction
All Workers are required to show at all times a transparent and honest behavior, and a high level of
personal responsibility and professionalism, either in or out of the Project Area.
All Workers shall comply with all applicable laws, rules and regulations.
Workers shall immediately inform management about any kind of sickness or symptom that may affect
their ability to carry out their work-related obligations properly.
Workers shall use adequate personal protection equipment during their activities within the Project Area,
including Project Vehicles.
Workers are not allowed to smoke or make an open fire within or in the surroundings of the Project Area
or near any Project Property, including Project Vehicles.
Workers are not allowed to engage in gambling while at work and using company assets for gambling
are prohibited, including during breaks. For purposes of this standard, “gambling” is defined as playing a
game for money or property or betting on an uncertain outcome. Prohibited gambling activities include, but
are not limited to: Games (e.g., cards, dice, and dominoes) played for money or property, including
electronic games (online poker, roullete, etc,); betting on sporting events, bingo, etc.
Workers are forbidden to possess, use or carry any kind or illegal drugs, medical paraphernalia,
narcotics or alcoholic beverages within the Project Area or any Project property, including Project
Vehicles.
Workers are not allowed to possess or carry weapons, such as firearms, explosives, ammunitions, knives,
clubs, etc., within the Project Area or any Project Property, including Project Vehicles.
All Workers shall not receive or hand over money, goods or other objects of value in order to obtain
benefits, receive favors or influence decisions, third parties, or themselves.
Workers shall not use Project funds or equipment, or other articles provided for the Project for their
personal benefit or any other unauthorized use.
Pets are not allowed in the Project Area.
Fishing, hunting and deforestation is also forbidden within the Project Area and its immediate
surroundings.
For security reasons, Workers may not abandon the Project Area without permission.
Annex 5: Role of Direct Players and Key Partners in the Implementation of Safeguards
Operating arrangements throughout the safeguards management journey requires transparent processes and
roles among the players and partners at various stages in the implementation of the HRP. Direct players
under the project focused on supporting the three construction stages lie within the management of the PIU.
Table 1 lists the direct players and their work focus that supports the safeguards. Table 2 lists the key
partners, areas of cooperation and supporting procedures to follow aligned with WB operational polices.
Table 1. Direct Players and Work Focus to Support Environmental & Social Safeguards
Direct Player Work Focus
World Bank (WB) Team For no objection of the ESMF, EA-ESMP and other actions, where
required.
WB & IST Environmental
& Social Counterparts
To support work development processes and implementation, where
appropriate.
WB Consultants/Firms To make recommendations, to provide technical support and to implement
consultancy work that adheres to environmental and social safeguards
processes in alignment with PIU overarching management processes.
Technical Assistance
Center (TAC) Consultants
/ Team
To provide technical support that adheres to environmental and social
safeguards processes in alignment with PIU management processes.
HRP PIU To integrate cross border implementation and management of work plans
aligned with grant disbursements.
Ministry of Housing To support the PIU processes as the Focal point of the HRP.
Physical Planning
Division
To approve the housing site based on national legislation including
environmental law and WB safeguards triggered under the HRP.
Homeowners To champion adherence to the work required under environmental and
social safeguards.
Added to the direct players are the key partners for specific areas of cooperation and support processes to
support environmental and social safeguards predominantly throughout the project noted in Table 2.
Table 2. Key Partners & Procedures to Support Environmental & Social Safeguards
Partners Area of Cooperation Support Process WB-OP
Roseau Market Trust Chance Find – archeological ‘Chance Find’
Procedure
OP4.11
Dominica Police Force – Central
Intelligence Department (CID)
Chance Find – skeletal remain N/A
Environmental Health
Department (EHD);
Pesticide Control Board;
Official pest control companies
Pest management Pest Management
Procedure
OP4.09
Dominica Solid Waste
Management Corporation
(DSWMC);
Other support identified by
DSWMC
Waste management Waste Management
Procedure
OP4.01
Forestry, Wildlife & National
Parks Division – Timber
Utilization Unit
Downed trees management
(promoted) / last resort -
Lumber Salvaging
Activity (use of
OP4.01
66 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
private land felling of trees
management
Alaskan saw mill at
site)
Environmental Health
Department
Environment, Health & Safety Health & Safety
Plan
OP4.01
Contractor;
Design & Supervision Firm
TAC support (if required)
Labour & working conditions Code of Conduct
OP4.01
Contractor;
Design & Supervision Firm
TAC support (if required)
Environment, Health & Safety Personnel Protective
Equipment
OP4.01
Contractor;
Design & Supervision Firm;
TAC support (if required)
Job hazard management Job Hazard Analysis
& Procedures to
Follow
OP4.01
Contractor;
Design & Supervision Firm;
TAC support (if required)
Emergency management Contingency &
Emergency
Management Plan
OP4.01
Dominica Police Force Traffic
Department
Traffic management Traffic Management
Procedure
OP4.01
Ministry of Kalinago Affairs;
Kalinago Council
Indigenous management Indigenous Peoples
Plan (IPP)
OP4.10
Beneficiary Selection
Committee
Beneficiary selection Beneficiary
verification &
prioritization
OP4.01
Grievance Redress Committee;
HRP PIU
Grievance Redress
Mechanism
Grievance Logging
& Complaints
System
Cross
border
The safeguards implementation journey and work plan outline the steps per work area with respective
procedures, human resources and schedule for implementation of the environmental and social safeguards.
Annex 7: HRP Application Form
GOVERNMENT OF THE COMMONWEALTH OF DOMINICA
“AIDE WAGER KAI”
APPLICATION
This section is for official use only
Individual Application No.
HRP Application Approval No.
Date of Approval
Beneficiary Score
Beneficiary Application (Please mark X where applicable and N/A where not applicable)
Section A. Personal Details
First Name:
Middle Name(s):
Surname:
Maiden or Former Name:
Identification Type: Identification Number:
Address at the time of the Hurricane:
Current Address:
If your current address is different than that of the damaged home please indicate whether you are
living:
In a shelter
With relatives or friends
Renting
Marital Status:
Single: Married:
68 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Widow/Widower: Divorced:
Age:
Sex: Male: Female:
Do you have any form of disability? Yes: No:
Please state the form of disability:
Do you have any dependents? (Include details in Section B Yes: No:
Number of dependents:
How many of them are elderly?
How many of them are disabled?
This section to be completed by residents of Kalinago Ethnicity ONLY
Are all of your dependents Kalinago? Yes: No:
If no, state the number of dependents who are Kalinago: Non-Kalinago:
If married, is your spouse Kalinago? Yes: No:
Section B: Household Members (Please list all who live with applicant)
Full Name Relationship
to Applicant
Ag
e
Form of
disability (if
applicable)
Total Number:
Section C: Employment Status (Please mark X where applicable)
Unemployed
Self-employed
Employed
Retired
69 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Basic Monthly Income:
<$500
$501 to $1000
>$1000
If above EC$1000 state amount
Section D: Receipt of Assistance (Government/Donor Agency)
(Please mark X where applicable)
Has your household received any
direct reconstruction/structural restoration of your home
through Government or Donor Housing Program?
Yes: No:
If yes, please select the appropriate option:
Provided a new home in a different location
Rebuilding home in the same location
Construction of a temporary structure
Partial repairs to existing structure
Grant for rebuilding and/or repair
State grant amount:
Who provided the support?
Social Safety Net Support:
Are you or any household member the recipient of any of the following programs?
Public Assistance
Over 70 Allowance
Education Trust Fund
Section E: Details of Citizenship
Are you a Dominican Citizen? Yes: No:
If not, have you obtained permanent residency? Yes: No:
Date Permanent Resident Certificate was issued:
Section E: Details of Property
Name of Home-owner
Applicant Relationship to Owner of the Home
District/Parish
Address of Property
Registered/Permission to Occupy
70 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Damage to Home (Please mark X where applicable)
Minor damage
Partially destroyed
Completely destroyed (entire structure uninhabitable)
Was the home insured? Yes: No:
Was part of your house being used for your livelihood? Yes: No:
Size of House in square feet (sq. ft.)
The application form must be submitted with the following documents:
1. One official picture ID (passport, driver's license)
2. Permanent Resident Certificate (if applicable)
3. Property Deed
4. Certificate of disability from a medical professional (if applicable)
5. Certificate/proof confirming the right to occupy land
6. Birth certificate(s) of applicant’s dependent(s)
7. Proof of Address (eg. Copy of Utility Bill prior to September 2017)
Kindly submit the application form with the required documents listed above to the following
address:
Project Manager
Housing Recovery Project - Project Implementing Unit
Old Street, Roseau
Commonwealth of Dominica
Signature: Date:
For Official Use Only
The following Documents were received and attached
71 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Received in
good
condition
If any of the
documents listed
above has been
lost or damaged
(Please indicate)
1. Certified copy of birth certificate of applicant
2. One official picture ID (passport, driver's license)
3. Permanent Resident Certificate (if applicable)
4. Property Deed
5. Certificate of disability from a medical professional
(if applicable)
6. Certificate/proof confirming the right to occupy land
7. Certified copy of birth certificate(s) of applicant’s
dependent(s)
8. Proof of Address (eg. Copy of Utility Bill prior to September
2017)
Process Record
Name Signature Date
Application received
Procedural Check
Application returned for correction
MIS captured data
Data verified
Review completed/Data validated
Filed
72
72 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Annex 8: HRP Environmental and Social Management Plan (ESMP) for Small
Construction and Rehabilitation Activities
General Guidelines for Use of ESMP
For low-risk topologies, such as a small house rehabilitation activity or small-scale works in building construction
(around 500 sq. ft.), the HRP safeguards team developed a brief Environmental and Social Management Plan (ESMP)
checklist-for a more streamlined approach to prepare ESMPs. The checklist has been developed to be user friendly
and compatible with World Bank’s safeguard requirements.
The ESMP covers typical core mitigation approaches to civil works contracts with small, localized impacts. It may
not contain socio-economic parameters regarding vulnerability identified in ESMF and Mitigation Table such as single
or disabled head of households. This checklist provides the key elements of an ESMP to meet World Bank’s
Operational Policies:
OP 4.01 Environmental Assessment
OP 4.09 Pest Management
OP 4.10 Indigenous Peoples Plan
OP 4.11 Physical Cultural Resources
The intention of this checklist is that it would be applicable as guidelines for the small works contractors, the
TAC/Technical Services (architects, engineers) consultants and the Design and Supervision Firm carrying out small
civil works under Bank-financed projects. Monitoring on same would be stored and managed in the management
information system (MIS).
The ESMP checklist has four sections:
Part 1: Includes a descriptive part that characterizes the project, specifies institutional and regulatory aspects,
describes technical project content, and outlines any potential need for capacity building. This section should
indicatively be up to two pages long. Attachments for additional information may be supplemented as needed.
Part 2: Includes a screening checklist of potential environmental and social impacts, where activities and potential
environmental issues can be checked in a simple Yes/No format. If any given activity/issue is triggered by
checking “yes”, a reference to the appropriate section in the table in the subsequent Part 3 can be followed,
which contains clearly formulated environmental and social management and mitigation measures.
Part 3: Represents the environmental and social mitigation plan to follow up proper implementation of the measures
triggered under Part 2. It has the same format as required for management plans produced under standard
safeguards requirements for Category B projects.
Part 4: Contains a simple monitoring plan to enable both the Contractor as well as authorities and the World Bank
specialists to monitor implementation of environmental management and protection measures and detect
deviations and shortcomings in a timely manner.
Parts 2 and 3 have been structured in a way to provide prescriptive and enforceable environmental and social measures,
which are understandable to non-specialists (such as Contractor’s site managers) and are easy to check and enforce.
Part 4 has also been designed intentionally simple to enable monitoring and reporting protocol of key parameters with
simple means and non-specialist staff.
73
73 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
ESMP Implementation Timeline
ESMP
Activities
Responsibilities Time Periods
Part 1 ▪ Content reviewed by the MIS firm to incorporate the ESMP in the Management Information System
(MIS) where appropriate
▪ Executed by the Technical Services (architects, engineers) Consultants | TAC
▪ Reviewed by the Design & Supervision Firm and reported to the PIU
▪ Approved by the PIU
▪ After beneficiary
selection
Part 2 ▪ Content reviewed by the MIS firm to incorporate the ESMP in the MIS where appropriate
▪ Executed by the Technical Services (architects, engineers) Consultants | TAC
▪ Monitored by the Design & Supervision Firm and reported to the PIU
▪ Monitored and approved by the PIU with support from the IST Safeguards Specialists
▪ Screening stage of
beneficiary selection
▪ Design & site preparation
stage
Part 3 ▪ Content reviewed by the MIS firm to incorporate the ESMP in the MIS where appropriate
▪ Executed by the Contractor
▪ Supervised by the Design & Supervision Firm and reported to the PIU
▪ Supported by the Technical Services (architects, engineers) Consultants | TAC
▪ Monitored and approved by PIU with support from the IST Safeguards Specialists
▪ Design and site
preparation stage
▪ Construction stage
Part 4 ▪ Content reviewed by the MIS firm to incorporate the ESMP in the MIS where appropriate
▪ Executed by the Contractor
▪ Supervised by the Design & Supervision Firm and reported to the PIU
▪ Supported by the Technical Services (architects, engineers) Consultants
▪ Monitored and approved by PIU with support from the IST Safeguards Specialists
▪ Construction stage
▪ Completion of
construction &
demobilization stage
74
74 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
ESMP for Small Construction and Rehabilitation Activities
PART 1: General Project and Site Information
INSTITUTIONAL & ADMINISTRATIVE
Country Commonwealth of Dominica
Project Title Housing Recovery Project (P166537)
SITE DESCRIPTION FOR EACH BENEFICIARY
Name of the Beneficiary
Address of Beneficiary Location (Street
Name and Number of lot/houses,
settlement name/ neighborhood name,
and other details as applicable
Site Map Yes No
Who owns the land?
Description of geographic, physical,
biological, geological, hydrographic,
nearby protected area or indigenous
peoples (if applicable), and socio-
economic context, including:
Altitude (in meters)
Nearest access road /highway/
Proposed Date of Commencement of
works:
Other information, as applicable
75
75 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Locations and distance for potential
material sourcing
Sand
Stone
Gravel
Distance to Fond Cole or other waste
and debris authorized disposal site
LEGISLATION
Identify national & local legislation &
permits that apply to project activity
[see Annex 1 in ESMF for guide listing relevant legislation and include the permits that apply]
Have all legally required permits been
acquired for the works?
Yes No
If No, works should not proceed
ENVIRONMENTAL & SOCIAL AWARENESS
Will there be any awareness? Yes No
If Yes, Attachment 1 includes the capacity building program
COMMUNICATION AND DISCLOSURE
76
76 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Have the local construction and
environment inspectorates and
communities been notified of upcoming
activities?
Yes No
If No, works should not proceed until notification is done.
Has the public/neighbor communities
been appropriately notified of the
works?
Yes No
If No, works should not proceed until notification is done.
Part 2: Environmental, Social, Health & Safety Safeguards Screening
Will the site activity
include/involve any
of the following?
1. Risks related to property rights including in the
Kalinago Territory.
[ ] Yes [ ] No See Part 3/ Section A below
2. Potential for conflict with neighbors [ ] Yes [ ] No See Part 3/ Section B below
3. Removal of existing debris, trees and vegetation,
earth works [ ] Yes [ ] No See Part 3/ Section C below
4. Traffic and pedestrian safety [ ] Yes [ ] No See Part 3/ Section D below
5. Chance Finds (PCR, skeletal remains) [ ] Yes [ ] No See Part 3/ Section E below
6. Typical impacts from
construction/reconstruction
of small houses (dust, noise, erosion, sedimentation,
etc.)
[ ] Yes [ ] No See Part 3/ Section F below
7. Impacts on forests and/or protected areas [ ] Yes [ ] No See Part 3/ Section F below
8. Re-location in situ [ ] Yes [ ] No See Part 3/ Section F below
9. Re-location ex-situ within the Kalinago Territory [ ] Yes [ ] No See Part 3/ Section F below
77
77 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
10. Individual wastewater treatment system [ ] Yes [ ] No See Part 3/ Section F below
11. Pest control [ ] Yes [ ] No See Part 3/ Section G below
12. Hazardous or toxic materials [ ] Yes [ ] No See Part 3/ Section H below
13. Demobilization of work site [ ] Yes [ ] No See Part 3/ Section I below
OP. 4.01 – Environmental Assessment (EA)
A. Is the proposed construction/reconstruction project
likely to have only small scale adverse environmental
impacts that would be classified as Category B under
WB OP 4.01 Policy?
[ ] Yes [ ] No
If Yes, check Mitigation Measures on Part 3.
B. Are the above-mentioned adverse environmental
impacts only small-scale, site-specific, temporary,
reversible, and limited to the
construction/reconstruction or replacement time
frame and for which mitigation measures are readily
known and easily implemented (as Category B under
WB OP 4.01 Policy)?
[ ] Yes [ ] No
If Yes, check Mitigation Measures on Part 3.
C. Will an Environmental and Social Management Plan
(ESMP) be available for the nature and scale of the
proposed works, including all measures needed to
prevent, minimize, mitigate, or compensate for
adverse impacts and improve environmental and
social performance?
[ ] Yes [ ] No
If Yes, check Mitigation Measures on Part 3.
OP. 4.11 – Physical Cultural Resources
D. Is the proposed activity located in, or in the vicinity
of, cultural sites?
[ ] Yes [ ] No
If Yes, check Part 3/ Section E.
E. Is the proposed activity located in an area where
known Physical Cultural Resource (PCR) or burial
site exist?
[ ] Yes [ ] No
78
78 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
If Yes, check Part 3/ Section E.
F. Will the proposed activity use any public PCR? [ ] Yes [ ] No
If Yes, check Part 3/ Section E.
G. Will the proposed activity apply and develop a
Chance Finds Procedure for the construction phase?
[ ] Yes [ ] No
If Yes, check Part 3/ Section E.
OP 4.09 – Pest Management
H. Will there be a need to control existing pests in the
site proposed for the construction/reconstruction of
the new house?
[ ] Yes [ ] No
If Yes, check Part 3/ Section G.
I. Will the use of pesticides be used only in small
limited quantities within one single housing unit to
control mainly rodents and termites?
[ ] Yes [ ] No
If Yes, check Part 3/ Section G.
J. Will the pesticides be purchased from authorized
dealers and be approved by the Dominica Pesticides
Control Board, within the Ministry of Agriculture
and Fisheries?
[ ] Yes [ ] No
If Yes, check Part 3/ Section G.
OP 4.10 – Indigenous Peoples
K. Will the activity (house construction/reconstruction)
take place within the Kalinago Indigenous People
Territory?
[ ] Yes [ ] No
If yes, check Mitigation Measures on Part 3
L. Will the design and planning be conducted in
consultation with and consented by the elected
Kalinago Council and Kaliago beneficiary?
[ ] Yes [ ] No
If yes, check Mitigation Measures on Part 3
M. Will an Indigenous Peoples Plan (IPP) to support the
unique needs of the Kalinago be implemented in the
HRP?
[ ] Yes [ ] No
If yes, check Mitigation Measures on Part 3
79
79 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
PART 3: Mitigation Measures
ACTIVITY POTENTIAL
IMPACTS
PARAMETER MITIGATION MEASURES CHECKLIST24
DESIGN STAGE AND SITE PREPARATION
A. Site
Investigation
Potential risks related
to property rights
Property rights (a) Researching and clarifying site ownership
(b) Ensuring owner’s written consent before accessing site
(c) Ensuring Kalinago Council’s written consent of owner’s right to
land in the Kalinago Territory inclusive of relocation ex-situ within
the Kalinago Territory, noted in the HRP Indigenous People’s Plan
(IPP).
(d) Notification of owners and in the Kalinago Territory, the head of
household and the Kalinago Council of commencement of works, if
required, prepare and sign a works completion handover protocol
(e) Notification of owners and in the Kalinago Territory, the head of
household and the Kalinago Council of all activities and any site
damages
Potential risks related
to natural hazards
Location and risk (f) All legally required permits for relocation in-situ have been acquired
for reconstruction at the new site approved by the owner, and in the
Kalinago Territory, by the head of household and the Kalinago
Council
B. General
Works
Preparation
Conflicts with
communities due to
upcoming expected
nuisances
Formal community relations,
including the Kalinago
Council and the Hamlet
Development Committees
stipulated in the IPP:
notifications/communications;
workers’ Code of Conduct
(a) The local construction and environment inspectorates and
communities have been notified of upcoming activities
(b) The public has been notified of the works through appropriate
notification in the media and/or at publicly accessible sites
(including the site of the works)
(c) All local stakeholders shall be informed of the works to be executed,
inclusive of its description, the accurate commencement time,
estimated completion time and any potential impact that may occur
(updates shall be given as work progresses).
(d) Local stakeholders will be informed of the Code of Conduct that
shall be applied to the workers.
2424 These are Best Management Practices (BMPs) that should be applied at all sites, as possible.
80
80 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
(e) All workers will be oriented on the workers’ Code of Conduct by the
Design & Supervision Firm and the Contractor.
(f) All legally required permits have been acquired for construction
and/or rehabilitation
(g) The Contractor formally agrees that all work will be carried out in a
safe and disciplined manner designed to minimize impacts on
neighboring residents and environment.
Unlawful
construction/penalties
Permits and authorizations
(e) The contractor/beneficiary shall be responsible for ensuring that he or
she has all relevant legal approvals and permits required to commence
works, including those specific to the Kalinago Territory.
SITE CLEARING/CLEANING AND EARTH WORKS
C. Removal of
debris, trees
and vegetation,
earth works
Increased dust
Air quality (a) During dry periods when dust is a nuisance it shall be mitigated by
spraying of water onto work surfaces along the work area.
(b) At all sites, the surrounding environment (including sidewalks,
roads if located adjacent) shall be kept free of debris to minimize
dust.
Risk of accidents
with community
members or other
unauthorized persons
Site Security (c) The Contractor/Beneficiary shall be responsible for maintaining
security over the construction site including the protection of stored
materials and equipment and maintain access control to avoid
liabilities associated with accidents involving unauthorized people
in the site.
(d) Access to the construction/works site by unauthorized persons shall
be restricted. Persons wishing to enter the construction site must first
report to the Design & Supervision firm/person in charge at the
entrance of the site.
(e) If trees are to be removed, Contractor shall specify how many and
the detailed mitigation measures to be adopted
(f) The necessary permits must be secured prior to starting to clear the
site.
(g) The removal of vegetation in sensitive areas will be discouraged and
when absolutely required must be limited to the authorization issued
by applicable authorities in Dominica (Physical Planning
Division/Forestry, Wildlife and National Parks Division, DOMLEC,
81
81 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
DOWASCO) and according to a suppression plan where all
elements will be identified and cataloged (specie, girth and DBH25);
(h) The areas or the elements to be suppressed shall be previously
identified and marked with colored tape in order to allow quick
visualization and avoid cutting unauthorized trees.
(i) Tree cutting shall be performed by specially trained staff. The team
shall count with the PPEs and the appropriate equipment and tools.
(j) The use of fire or hazardous material is strictly prohibited.
(k) If required, a certified copy of the authorization to suppress
vegetation, including, when applicable, the map of the boundaries of
the area of intervention must be maintained onsite.
Risk of health hazard
from debris/waste
accumulation
Debris/waste management (l) Debris at the site should be separated such as white goods (washing
machines and refrigerators), metal, general trash and disposed at the
official locations based on the waste management plan.
(m) There will be no burning of debris/waste.
CONSTRUCTION PHASE
D. Transportation
and storage of
construction
materials
Increased dust Air quality (a) Unpaved, dusty access roads should be compacted and/or wet
periodically.
(b) There will be no excessive idling of construction vehicles at sites;
(c) The bins of all haulage vehicles transporting aggregate or building
materials must be covered on all public roads.
(d) Materials such as sand, cement, or other fines should be kept
properly covered and bunded and be moistened with sprays of
water.
(e) Cement should be kept stored within a shed or container.
(f) There will be no open burning of debris / waste material at the site.
Direct or indirect
hazards to public
traffic and
pedestrians by
construction
activities
Traffic and Community
Safety
(a) The Contractor or Design & Supervision Firm will enforce a generic
Traffic Management Plan approved by the Dominica Police Force
Traffic Department for activity on public road.
(b) The Contractor or the Design & Supervision Firm will timely disclose
service disruptions to community where applicable;
(c) Traffic control strategy will be implemented as to minimize the
impact to the surrounding community.
25 Diameter at Breast Height (DBH)
82
82 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
(d) The traffic management plan to be developed by the Design &
Supervision Firm and implemented by the contractor shall include:
alternative routes to be identified in the instance of extended road
blockages; the public to be notified of all disturbance to their normal
routes; signposting, warning signs, barriers and traffic diversions
must be clearly visible and the public warned of all potential hazards;
provision must be made for the safe passages and crossings for all
pedestrians where construction traffic interferes with their normal
route; there must be active traffic management by trained and visible
staff at the site or along roadways as required to ensure safe and
convenient passage for the vehicular and pedestrian public;
(e) Adjustment of working hours to local traffic patterns, e.g. avoiding
major transport activities during rush hours.
(g) Contractor/Beneficiary will ensure that the construction site is
properly secured, and construction related traffic regulated as per
Traffic Management Plan.
E. Small-scale
excavations of
foundations
and other
earth
movements
Potential Chance
Finds of Skeletal
remains
Chance Finds (a) It shall be ensured that provisions are put in place so that skeletal
“chance finds” encountered in excavation or construction are noted
and registered, responsible officials contacted notably the Dominica
Police Force Central Investigation Department, and works activities
delayed or modified to account for such finds.
Potential Chance
Finds of PCR
(Physical Cultural
Resources)
Chance Finds (a) Contractor/Beneficiary will be required to follow a Chance Finds
Procedure, communicating any cultural archaeological findings to
the Roseau Market Trust for the National Museum in Roseau or any
natural cultural findings to the Forestry, Wildlife and National Parks
Division (FWNPD). Similar in the Kalinago Territory,
communicating Chance Finds to the Kalinago Council and the
Ministry of Kalinago Affairs.
(b) Ensure that any cultural artifacts or other possible “chance finds”
encountered during field works are noted and registered, and
secured, and the Roseau Market Trust and the FWNPD, and in the
Kalinago Territory, the Kalinago Council are contacted.
(c) Ensure that activities are stopped or modified until proper guidance
from the relevant authorities.
F. General small-
scale
construction
activities
Risk of health and
safety accidents with
workers
Workers Health and Safety (a) Contractors and workers will be trained on basic standard operating
procedures for small civil works.
(b) Measures to control dengue and other water-borne diseases by
eliminating the breeding grounds of Aedes aegypti will include the
following: covering or boring tires; using coarse sand in dishes of
flower pots; bagging and throwing in the trash cans that can
83
83 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
accumulate water; emptying bottles and turning upside down before
discarding; covering the water tanks, etc.
(c) The Contractor/Beneficiary must designate a person responsible for
Occupational Health and Safety (OHS) who will ensure that the
requirements and procedures are followed by all and at all levels of
execution.
(d) All working sites must be equipped with First Aid kits and a
responsible person trained in administering first aid measures.
(e) The Contractor/Beneficiary shall ensure that all workers operate
within a safe environment. Sanitation facilities shall be provided for
all site workers.
(f) The Contractor/Beneficiary must provide all workers with the
necessary protective gear as per their specific tasks such as hard hats,
overalls, gloves, goggles, boots, etc.
(g) The Design & Supervision firm shall develop and implement a basic
Occupational Health and Safety plan that must be approved by the
PIU.
(h) The Occupational Health and Safety Plan will include the following
minimum content:
• Job Hazard Analysis
• Manual of safe work procedure26 (SWP) for key activities (site
clearing, tree removal, trench and excavation, access /egress,
installing scaffolds, working on ladder, working on heights,
lockout-tagout (LOTO), housekeeping and materials storage,
manual and mechanical lifting, lifting and hoisting, confined
space entry, fall-arrest rescue, and others, as applicable)
• Training
• Reporting and investigating Accidents, identifying Root Cause,
and acting upon prevention and corrective measures.
• Emergency Preparedness and Response Plan addressing as a
minimum, fire, medical emergencies and natural hazards
emergencies such as floods and landslides
(a) The appropriate posting of information within the site must be done
to inform workers of key rules and regulations to follow.
Risk of
contamination when
working (sawing,
Workers’ Health and Safety (a) Care must be taken when working (sawing, sanding, machining,
etc.) with CCA-treated timber in a way that produces saw-dust.
Appropriate personal protective equipment should be worn, and
these activities should take place outdoors.
26 Also known as Standard Operating Procedures.
84
84 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
sanding, machining)
timber treated with
Copper Chrome
Arsenate (CCA)
(b) Disposal of CCA-treated timber debris from destroyed houses and
from construction should be done under the arrangements described
above in the section on ‘debris/waste management’ involving
disposal at the DSWMC operated sanitary landfill at Fond Cole (or
other approved by the GoCD and the PIU).
Increased level of
noise
Noise (c) Construction schedule will be limited to the restricted times
established in legislation and in the permit.
(d) When neither exist, and where noise management is a concern, the
contractor(s) shall schedule activities during normal working hours
(between 8am and 5pm).
(e) During the operation of engines, covers of generators, air
compressors and other powered mechanical equipment shall be
closed, and equipment placed as far away from residential areas as
possible
(f) Where noise is likely to pose a risk to the surrounding community,
the contractor(s) shall inform the Design & Supervision firm and shall
develop a public notification and noise management plan for approval
by the Dominica Police Force and PIU
(g) No night works or delivery of materials at night shall be permitted.
(h) Excessive noise level posed by workers on site such as loud music
will be managed.
Potential pollution of
surface or
underground water
bodies, water
courses, etc.
Water Quality (a) Protect surface waters, groundwater resources, springs and
watercourses from siltation and pollution with temporary devices.
(b) Wastewater systems will be designed and installed according with
technical requirements by the Design & Supervision Firm
(c) Liquid wastes will not be allowed to accumulate on or off the site,
or to flow over or from the site in an uncontrolled manner or to
cause a nuisance or health risk due to its content.
(d) Liquid and hazardous wastes will be stored in appropriate containers
separated from the general refuse;
(e) Site work vehicles and machinery will only be permitted to be
washed on site in case of spill of construction works material e.g.
mixed cement; in these cases, it will be washed only in designated
areas where runoff will not pollute natural surface water bodies.
(f) Portable toilets, or other appropriate option, will be installed during
construction, as directed by the Design and Supervision Firm
Waste Management (a) Contractor/beneficiary must ensure regular removal and disposal of
all site wastes
85
85 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
(b) All waste will be collected by licensed collectors and disposed of
properly at Fond Cole or other approved locations by GoCD and the
PIU, and the records of waste disposal shall be maintained as proof
for proper management as designed.
(c) Whenever feasible the contractor will reuse and recycle appropriate
and viable materials.
(d) Temporary storage of wastes should be away from watercourses and
springs.
(e) Under no circumstances shall the contractor(s) allow construction
wastes to accumulate as to cause a nuisance or health risk due to the
propagation of pests and disease vectors.
Potential impacts to
forests, rivers,
wetlands and/or
protected areas or
other sensitive areas
Biodiversity (a) Establish barrier area to protect sensitive area
(b) Verify that drainage and siltation do not affect the sensitive area.
(c) All recognized natural habitats, wetlands and protected areas in the
immediate vicinity of the activity will not be damaged or exploited;
(d) All workers will follow a Code of Conduct that strictly prohibits
from hunting, foraging, logging or other damaging activities in
surrounding areas.
(e) Project will develop communication and awareness among workers
(f) Adjacent wetlands and streams shall be protected from construction
site run-off with appropriate erosion and sediment control features,
including but not limited to silt fences
(g) There will be no unlicensed borrow pits, quarries or waste dumps in
adjacent areas, especially not in or adjacent to protected areas.
(h) Extraction of construction materials will follow authorization from
applicable authorities.
(i) Construction materials will only be purchased from authorized
dealers.
G. Pest control Potential impacts to
environment and to
workers’ health and
safety
Pest management (a) Construction sites must ensure that control of rodents and other
pests is performed safely by registered pest control companies.
(b) Small quantities of pesticides must be stored in a locked, well
ventilated cupboard in a storeroom, away from food and water
supplies, out of the reach of children, and in covered properly
labelled, intact bottles or packages.
(c) Pesticides will not be purchased in, or transferred to, unlabeled plastic
containers or plastic bags.
86
86 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
(d) Pesticides will not be transported together with food, animal feed or
drinks
(e) Workers should always wear protective clothing as necessary while
using pesticides (gloves, eye, shields, respirators, overalls, boots)
(f) Use the proper application equipment for applying pesticides
(g) Always ensure that pesticides spray equipment is properly
maintained and calibrated
(h) Empty pesticides containers shall not be used to store water or
drinks, but instead shall be disposed of together with the hazardous
wastes.
(i) Pesticides equipment and containers shall not be washed in water
bodies (rivers, lakes, sea, streams).
H. Use of Toxic
Materials
Potential
contamination with
asbestos
Asbestos management
(a) If asbestos is located on the project site, it shall be marked clearly,
and treated and disposed of as hazardous material in collaboration
with the DSWMC using international best practices
(b) When possible, the asbestos will be appropriately contained and
sealed to minimize exposure
(c) The asbestos prior to removal (if removal is necessary) will be
treated with a wetting agent to minimize asbestos dust
(d) Asbestos will be handled and disposed by skilled & experienced
professionals
(e) If asbestos material is to be stored temporarily, the wastes should be
securely enclosed inside closed containments and marked
appropriately. Security measures will be taken against unauthorized
removal from the site.
(f) The removed asbestos will not be reused.
Toxic / hazardous
waste management
(a) Temporarily storage on site of all hazardous or toxic substances will
be in safe containers labeled with details of composition, properties
and handling information
(b) The containers of hazardous substances shall be placed in a leak-
proof container to prevent spillage and leaching
(c) The wastes shall be transported by specially licensed carriers and
disposed in a licensed facility.
(d) Paints with toxic ingredients or solvents or lead-based paints will not
be used.
(e) All paints and preservatives shall be used only with the approval of
the Design and Supervision Firm and the PIU.
(f) Storage, use, and disposal of excess paints and preservatives shall be
managed in conformance with the manufacturers’ recommendations
and as approved by the Design and Supervision Firm and the PIU.
87
87 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
(g) The contractor shall provide the Design and Supervision Firm and
the PIU. with a list of hazardous materials and estimated quantities
to be used, storage, spill control and waste disposal plans to be
observed during the execution of the contract.
COMPLETION OF CONSTRUCTION AND DEMOBILIZATION
I. Demobilization
of activities and
equipment
Potential impacts to
natural environment
Protection of natural
environment
(a) Notification of owners of termination of works, and prepare and
sign a works completion handover protocol
(b) Restoring surface and vegetation where it has been significantly
disturbed
(c) Taking out all waste after completion of the construction and
disposing of it according to approved procedures by the PIU/GoCD.
(d) Removal of all signage from site?
88
88 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
PART 4: Monitoring Plan
Parameter
Verification of Mitigation Measure Monitoring
location
Monitoring
method Frequency
Agents
Responsible for
ensuring
compliance
Phase
Drainage
Verify good drainage to avoid water release into
stream and neighboring properties.
At site
Visually and
where
applicable,
proof of
receipts
Each site
visit:
minimum 3
visits per
household
Design &
supervision firm
Verify good drainage around completed house by
channels and ditches.
Sedimentation
When necessary, verify that temporary devices are
used to reduce/prevent off-site sediment transport
during heavy rainfall.
Pest prevention
and control
Verify good drainage and waste management
implementation to avoid disease vector breeding
sites.
Erosion and
other
environmental
degradation
Verification that aggregate (sand and gravel) was
obtained at the two approved active quarries in
Colihaut, and the one in Layou and other approved
by the GoCD/PIU.
Re-use salvaged materials (particularly timber)
Air quality
Verify dust suppression techniques during site
clearing, demolition, excavation and construction
activities.
Waste
management
Verify that all building and construction debris is
waste segregated, and dispose it at the Ford Cole
sanitary landfill (no local disposal or burning of
89
89 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Parameter
Verification of Mitigation Measure Monitoring
location
Monitoring
method Frequency
Agents
Responsible for
ensuring
compliance
waste material) or other approved location by the
DWSMC.
Potentially hazardous wastes (e.g. used machinery
oils, lubricants, solvents, pesticides, paints or
cleaners) are appropriately stored, handled,
transported, and disposed of in a manner that
prevents environmental contamination.
Verify good house-keeping practices on site, such
as sorting and placing loose construction materials
or demolition debris in established areas.
Wastewater
Verify that sanitation facilities for the house have
adequate sewage disposal that will not contaminate
drinking water sources, streams, or neighboring
properties.
Workers’ health
and safety
practices
Use appropriate Personal Protection Equipment
such as safety glasses with side shields, face
shields, hard hats, and safety shoes.
Conduct sawing, cutting, grinding, sanding,
chipping or chiseling with proper guards and
anchoring as applicable.
Use temporary fall protection measures in
scaffolds and out edges of elevated work surfaces
Ensure access to adequate toilet/latrine facilities.
90
90 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Parameter
Verification of Mitigation Measure Monitoring
location
Monitoring
method Frequency
Agents
Responsible for
ensuring
compliance
Controlled
access to site
Verify that restrict access to the construction site is
enforced (particularly children)
Traffic
management
Verify that traffic procedure has been approved by
the Dominica Police Force Traffic Department Access roads
Social
Management
Provide opportunities for employment and training
of labor from the host community
At site
No employment of labor under the age of 16 or
labor that will prevent attendance at school.
Provide Consultation on Code of Conduct and
verify that contactors are aware of and willing to
adhere to it.
No forced labor. All immigrants must present valid
work permits)
Site
decommissioning
Waste
management
Verify that site is cleared and cleaned of all
construction wastes and debris by project
completion.
At site
The Design and Supervision Firm will use the Monitoring Plan in Part 4 of the ESMP to develop and prepare a
monitoring report for monitoring each beneficiary home during each site visit. The checklist will have a section to
include comments for each mitigation measure of the parameters during each visit (see sample template). These can
be compared to determine environmental and social patterns for each site visit based on the following reports:
▪ Individual site progress per visit – to identify challenges in light of solving them early and to identify good
practices that can be applied in other households.
▪ Individual site progress overtime – to identify recurring or new challenges in light of solving them early
and to identify good practices that can be applied in other households.
▪ Development planning districts – to inform current and future physical planning in the various districts,
including the Kalinago Territory.
All reports will be submitted to the PIU as agreed.
Sample Monitoring Report Template:
HRP ESMP Compliance Monitoring for Beneficiary ID #_____in the ____ District, site visit #
Phase: e.g. Site preparation or Construction or Decommissioning
Site visit: e.g. #1 or #2 etc
Date of visit: day-month-year
Parameter Compliance Comments
Yes No
Site assessment conducted by:_________________
Date of submission to PIU: ____________________
Report received at PIU by: _____________________
Date received by Safeguard Specialist: ___________
Follow up action required: _______________________
The final ESMP monitoring report will be completed by the Design and Supervision Firm on site
closure/decommissioning, which will include a comparison of all site visits per household beneficiary.
HRP ESMP Comparative Compliance Monitoring for Beneficiary ID #_____in the ____ District
92
92 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Phase: e.g. Site preparation or Construction or Decommissioning
Site visit: e.g. #1 or #2 etc
Date of visit: day-month-year
Parameter Compliance Comments
Visit #1 Visit #2 Visit #3
Yes No Yes No Yes No
Site assessment conducted by:_________________
Date of submission to PIU: ____________________
Report received at PIU by: _____________________
Date received by Safeguard Specialist: ___________
Follow up action required: _______________________
93
93 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Annex 9: Project Results Framework – Dominica Housing Recovery Project
Indicator Name Frequency Data Source/Methodology Responsibility for
Data Collection Direct project beneficiaries Semi annual Project's progress report (based
on TAC progress reports) PIU/MoP/MoHL
Percentage of which are Female Semi annual Direct beneficiaries are people or groups who directly derive benefits from the Project including a subsidy or utilizing
services from the TACs. Assumes 2.7 people per household per 2011 census data. Number of households with resilient
housing recovered using project
subsidies27
Semi annual Project's progress report (based
on TAC progress reports and
PPD database)
PIU/MoP/MoHL
Percentage of female‐headed households
(primary beneficiaries) Semi annual
This indicator is defined as the number of households that received project subsidies and have a completion certificate for
resilient housing reconstruction. It is meant to track progress made to increase stock of houses built to resilient standards. Number of households that accessed
general advice service from TACs and
benefit from streamlined permitting
process
Semi annual Project's progress report (based
on TAC progress reports and
PPD database)
PIU/MoP/MoHL
Number of female‐headed households
(primary beneficiaries) Semi annual
This indicator measures the number of households that accessed general advice service from TAC and benefit from
streamlined permitting process. It also denotes level of public awareness of project activities. Number of on-demand building
assessments performed by TACs Semi annual Project's progress report (based
on TAC progress reports)
PIU/MoP/MoHL
This indicator measures the uptake of TAC’s building assessment services. Number of building permits issued Semi annual Project's progress report (based
on TAC progress reports and
PPD database)
PIU/MoP/MoHL
This indicator measures uptake of TAC’s building permitting streamlining services Number of subsidies disbursed Semi annual Project's progress report (based
on TAC progress reports and
PPD database)
PIU/MoP/MoHL
This indicator measures progress made on tranche disbursement to beneficiaries (3 tranches per household) Share of grievance cases resolved within
6 weeks of submission Semi annual Project's progress report (based
on TAC progress reports) PIU/MoP/MoHL
This indicator measures the efficiency of the Government in addressing the registered complaints. Number of communication campaigns
delivered to affected communities and
general public
Semi annual Project's progress report (based
on TAC progress reports) PIU/MoP/MoHL
This indicator measures the roll‐out of communication campaigns related to resilient building practices and project
activities which will be identified in the Communication Strategy. There will a minimum of three campaigns in the first
year to ensure effective communication, and at least one campaign a year in the subsequent years
27 The beneficiary selection criteria for allocation of the house reconstruction grant assign priority to beneficiaries,
who meet a range of vulnerability characteristics (see Section 6.1). These primary beneficiaries are not confined to
female-headed households. Therefore, to capture the achievement of this prioritization, project monitoring needs to
report the percentage of three sub-sets of vulnerable beneficiaries, namely (i) female-headed households with
children below 15 years of age, (ii) households with disabled head of household, and (iii) households with elderly
head of household.
Annex 10: ESMF Mitigation Table
HRP ENVIRONMENTAL, SOCIAL, HEALTH & SAFETY MITIGATION TABLE, RESPONSIBILITIES AND COSTS
ACTIVITY POTENTIAL
IMPACTS
MITIGATION ACTION/S
AGENCY or
OTHER AGENT
RESPONSIBLE
FOR
MITIGATION
AGENCY
RESPONSIBLE
FOR
MONITORING/
SUPERVISION
FREQUENC
Y
MEANS OF
VERIFICATIO
N
COST OF
MITIGATION/
SOURCE OF
FUNDS
Component 1 – Support for Housing Recovery Systems and Capacity Building (US$3.5 million)
Project Design phase
1. Preliminary
selection of
beneficiaries of
the subsidy
among a
demand-driven
base of
applications
1. Potential
politicizing of
the selection
process, with
risk of not
addressing
poverty and
vulnerability,
and/or not
reaching the
most needed.
1.a - Establishment of clear
selection criteria – included in
this ESMF and in the Project
Operational Manual (POM)
with prioritization given to (i)
households that are still in
hurricane shelters, and (ii)
single parent households with
children under 16 years; (iii)
households with a disabled
household head, and (iv)
households with an elderly
household head.
Four preparatory activities
will be undertaken: (i) a
national information campaign
to inform the population about
the project approach, the
criteria for beneficiary
selection, the deployment of
technical services/TACs,
Design & Supervision Firm
and building contractors, and
the Grievance Redress
Mechanism, (ii) set up of a
Beneficiary Selection Review
Social Specialist in
the PIU (Ministry of
Housing and Lands -
MoHL) and HRP
Beneficiary
Selection Review
Committee.
Social Specialist
in the PIU
(MoHL) with
support from the
Implementation
Support Team
(IST) within
Ministry of
Finance (MoF)
Once during
Project design
Project Progress
Report,
Public online
listing
Included in
Project
Cost/Componen
t 3 (US$ 3
million) –
Project
Implementation
and
Administration
95
95 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
Committee, (iii) set up of a
Grievance Committee to
address complaints on the
Project, and (iv) a site visit to
assess the environmental risks.
The eligibility criteria that will
be applied in the beneficiary
selection process (Section 6.1
of this ESMF) involve both
environmental and socio-
economic considerations. The
HRP Beneficiary Selection
Review Committee will
review and validate the list of
beneficiaries and produce a
list of confirmed
beneficiaries. This list will be
made public locally and on-
line (project website at
MoHL) as a final step in the
validation and confirmation.
1. b - The HRP Communication
Strategy will seek to disseminate
information on the Project,
including social services, local
government and shelter
managers to create awareness
and engage the most needed in
the self-driven application (e.g.,
female headed households with
dependent children, including
grandmothers as caregivers for
grandchildren, which make up a
large proportion of those still in
temporary shelters; these will
benefit from the communication
and outreach strategy, since
these categories of prioritized
beneficiaries are likely to have
Social Specialist in
the PIU (Ministry of
Housing and Lands -
MoHL) and HRP
Beneficiary
Selection Review
Committee.
Social Specialist
in the PIU
(MoHL) with
support from the
Implementation
Support Team
(IST) within
Ministry of
Finance (MoF)
Once during
Project design
Project Progress
Report,
HRP
Communication
Strategy on HRP
website
Included in
Project
Cost/Componen
t 3 (US$ 3
million) –
Project
Implementation
and
Administration
96
96 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
limited access to information
about the project, and also
limited ability to act on such
information.
2. Screening of
potential
beneficiaries’
site for
suitability for
resilient home
reconstruction
(focusing on
beneficiaries
who lost
homes less
than 500 sqft)
- assess
adequacy of
land based on
site hazards
and natural
disasters risks.
2. Lots
potentially
located in
unsuitable
areas (risks of
flooding,
landslides,
degraded
environment,
etc..) or to be
relocated in
same lot but
affecting
owner’s own
crops or other
assets.
2. Screening criteria established in
the ESMF and the POM and
coordination with other
Government programs to deal
with ineligible applicants under
this Project
The demand driven approach
allows owners to decide if they
want to lose some crops or
assets to build/rebuild their
homes (not involuntary) and to
avoid removal of trees
particularly on the border of
forest and protected areas.
Technical Services
(architects/engineers)
and National
Parks/forest reserve
officials.
Environmental
and Social (E&S)
Specialists in the
PIU (MoHL)
with support
from the IST
within MoF, and
if needed,
Forestry, Wildlife
& National Parks
Division.
Individually to
each potential
beneficiary, on
a first-
come/first
serve basis
Project Site Risk
Assessment
Report on
Potential
Beneficiaries
Included in
Project
Cost/Sub-
component 1.1 -
Planning and
Support to
Technical
Assistance
Centers (TACs)
(US$ 2.7
million) and
Component 3
(US$ 3 million)
– Project
Implementation
and
Administration
3. Implementation
of housing
reconstruction
in the Kalinago
Territory
3. Potential lack
of
compliance
with Bank
Policy 4.10
(Indigenous
People)
3.a - Preparation and
implementation of the Project
in the Kalinago Territory will
be conducted through the
elected Kalinago Council and
the Ministry of Kalinago
Affairs, including ensuring
free, prior and informed
consultation, and a broad
Kalinago people’s support for
the project.
Social Specialist E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
4 consultations
held during
project design
Consultation brief
inclusion in the
IPP
Included in
Project
Cost/Componen
t 3 (US$ 3
million) –
Project
Implementation
and
Administration
97
97 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
3.b – Preparation of an Indigenous
Peoples Plan (IPP) to support
the unique needs of the
Kalinago in Dominica under
the HRP.
Social Specialist E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
Once during
project design
Project Progress
Report,
IPP disclosed
online
Included in
Project
Cost/Componen
t 3 (US$ 3
million) –
Project
Implementation
and
Administration
4. Proof of
ownership of
land through a
registered title,
a registered
deed or an
unregistered
deed.
4. Potential
difficulties for
beneficiaries
to obtain proof
of ownership.
4. The Project will facilitate,
when required, through the
Ministry of Housing and Lands
acquiring legal evidence of
land ownership, but will not
finance tenants or leaseholders,
since there are other programs
suited to this need. The Project
does not support commercial
properties either.
Home owner
Registry
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
Individually to
each
beneficiary, on
a first-
come/first
serve basis
Project Progress
Report
Copy of title/deed
on file
Included in
Project
Cost/Componen
t 3 (US$ 3
million) –
Project
Implementation
and
Administration
5. Project design
of individual
houses for the
beneficiaries
selected
through 1 and 2
above.
5.a –Design of
houses that
are
potentially
above the
individual’
s financial
resources
(Project
grant plus
individual
resources).
5.a - The Design and Supervision
Firm hired by the Project will
ensure that design is appropriate to
beneficiaries’ financial means
The Design and
Supervision Firm
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
Individually to
each
beneficiary, on
a first-
come/first
serve basis
Project Progress
Report on Design
& Supervision
Included in
Project
Cost/Componen
t 3 (US$ 3
million) –
Project
Implementation
and
Administration
5.b – Design of
houses that
are
potentially
unsuited for
the
topography
or other
physical
5.b - The Design and Supervision
Firm hired by the Project will
ensure that design is appropriate to
the physical characteristics of the
beneficiaries’ lot and specific site
characteristics will be flagged in
the initial site assessment by the
technical support team.
The Design and
Supervision Firm &
Technical Support
Teams
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
Individually to
each
beneficiary, on
a first-
come/first
serve basis
Project Progress
Report on Design
& Supervision
Included in
Project
Cost/Componen
t 3 (US$ 3
million) –
Project
Implementation
and
Administration
98
98 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
features of
the lot.
6. Technical
Design of a
New Physical
Development
Planning
Office in the
same site of the
previous
building that
was destroyed
by the
hurricane.
6. – Although the
Project will only
finance the
detailed design of
the new building,
the future
construction (even
if not financed by
the Bank) could
incur potential
EHS impacts if
these aspects are
not incorporated
in the design
phase.
The design of the building will
also include an ESMP to address
the EHS impacts and risks of the
future construction of the building
and such ESMP should be
incorporated into the bidding
documents for the design.
Design Firm to be
contracted through a
competitive process
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
Upon
implementation
of Sub-
component 1.3
Project Progress
Report
RFP,
Completed design
demonstrating
inclusion of EHS
elements
Included in
Project
Cost/Sub-
component 1.3 –
(US$0.2
million) and
Component 3
(US$ 3 million)
– Project
Implementation
and
Administration
Component 2 - Subsidies to homeowners on a demand-driven basis (US$ 33.5 million)
Construction phase
7. Small
construction
activities for
individual
houses (up to
500 sqft)
7.a – Civil works
may require
the removal
of existing
debris with
potential for
inadequate
disposal
leading to
pollution of
water and
soil, or health
hazard in the
nearby
community.
7.a – Each Contractor or owner
(when self-construction) will be
required to follow an
Environmental and Social
Management Plan (ESMP) for
individual small construction,
including Debris Management
requirements to dispose of debris
in the Fond Cole sanitary landfill
or other location approved by
GoCD and the PIU.
The Contractor or
the Beneficiary
through his own
building personnel
(self, relatives and/or
community
members).
The Design and
Supervision
Firm, Dominica
Solid Waste
Management
Corporation, the
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
As a minimum,
every other
week
supervisions by
the Design &
Supervision
Firm
Project Progress
Report on ESMP
implementation
Individual ESMP
Inspections and
supervisions
included in
Project
Cost/sub-
component 2.2 –
Design and
Supervision of
House
Reconstruction
(US$ 2.05
million) and
Component 3
(US$ 3 million)
– Project
Implementation
and
Administration
7.b – Civil works
may require
removal of trees
7.b - Each Contractor or owner
(when self-construction) will be
required to follow an ESMP for
The Contractor or
the Beneficiary
through his own
The Design and
Supervision
Firm, the E&S
As a minimum,
every other
week
Project Progress
Report on ESMP
implementation
Included in
Project Cost/
sub-component
99
99 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
in very small
quantities, which,
however, if
unregulated may
lead to
environmental
degradation.
individual small construction, that
may include the need to consult
with Forest, Wildlife and National
Parks Division and follow specific
measures for trimming or removal
of individual trees only if
necessary on site.
building personnel
(self, relatives and/or
community
members).
Specialists in the
PIU (MoHL)
with support
from the IST
within MoF, and
if required,
Forestry
Division.
supervisions by
the Design &
Supervision
Firm
Individual ESMP 2.2 – Design
and Supervision
of House
Reconstruction
(US$ 2.05
million) and
Component 3
(US$ 3 million)
– Project
Implementation
and
Administration
7.c – Civil works
may require use
of aggregate
(sand, stone and
gravel) in small
quantities, given
the size of the
houses, which
however, if
unregulated may
lead to
environmental
degradation,
erosion,
sedimentation of
water bodies.
7.c - Each Contractor or owner
will be required to follow an
ESMP for individual small
construction, including
requirements to use only aggregate
from existing quarries approved by
GoCD (Physical Planning
Division) and the PIU.
The Contractor or
the Beneficiary
through his own
building personnel
(self, relatives and/or
community
members).
The Design and
Supervision
Firm, the E&S
Specialists in the
PIU (MoHL)
with support
from the IST
within MoF.
As a minimum,
every other
week
supervisions by
the Design &
Supervision
Firm
Project Progress
Report on ESMP
implementation
Individual ESMP
Included in
Project Cost/
sub-component
2.2 – Design
and Supervision
of House
Reconstruction
(US$ 2.05
million) and
Component 3
(US$ 3 million)
– Project
Implementation
and
Administration
7.d – Civil works
may require the
use of very small
to minimal
quantities of pest
control products
(given the small
size of the homes)
to control termite
in building
foundations and
7.d - Each Contractor or owner
(when self-construction) will be
required to follow an ESMP for
individual small construction,
including requirements for use of
small quantities of pest control
products authorized by the
Dominica Pest Control Board, and
in consultation with Forest,
Wildlife and National Parks,
Environmental Health Department
The Contractor or
the Beneficiary
through his own
building personnel
(self, relatives and/or
community
members).
The Design and
Supervision
Firm, the E&S
Specialists in the
PIU (MoHL)
with support
from the IST
within MoF, and
when required
the Forestry
Division and
As a minimum,
every other
week
supervisions by
the Design &
Supervision
Firm
Project Progress
Report on ESMP
implementation
Individual ESMP
Included in
Project Cost/
sub-component
2.2 – Design
and Supervision
of House
Reconstruction
(US$ 2.05
million) and
Component 3
(US$ 3 million)
100
100 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
control of rodents,
ants, and other fly
animals and
common
household pests
that if unregulated
may lead to fauna,
flora and water
contamination, as
well as health and
safety risks to
workers and
surrounding
communities.
and the PIU and to be done
through licensed registered
professional contractors.
Environmental
Health
Department.
– Project
Implementation
and
Administration
7.e – Although
remote, the
possibility exists
for civil works to
uncover
archaeological
finds of pre-
Colombian and
later colonial and
Creole
settlements, or
skeletal remains.
7.e - Each Contractor or owner
(when self-construction) will be
required to follow an ESMP for
individual small construction,
including requirements to follow a
Chance Finds Procedure
(communicating any
archaeological physical cultural
findings to Roseau Market Trust
for the National Museum in
Roseau, any natural cultural
findings to the Forestry, Wildlife
and National Parks Division and
skeletal remains to the Dominica
Police Force Central Investigation
Department (CID).
The Contractor or
the Beneficiary
through his own
building personnel
(self, relatives and/or
community
members).
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF
in collaboration
with the Roseau
Market Trust or
the Forestry
Division or the
CID.
As a minimum,
every other
week
supervisions by
the Design &
Supervision
Firm
Project Progress
Report on ESMP
implementation,
Individual ESMP
Included in
Project Cost/
sub-component
2.2 – Design
and Supervision
of House
Reconstruction
(US$ 2.05
million) and
Component 3
(US$ 3 million)
– Project
Implementation
and
Administration
7.f – Although
most of the
construction will
likely be made by
beneficiaries
themselves,
relatives, friend
and community
members, it may
7.f - Each Contractor or owner
(when self-construction) will be
required to follow an ESMP for
individual small construction,
including requirements to follow a
Workers’ Code of Conduct. In
addition, the project will follow an
approach which has been
successfully applied in other civil
The Contractor or
the Beneficiary
through his own
building personnel
(self, relatives and/or
community
members).
The Design and
Supervision
Firm, and the
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
As a minimum,
every other
week
supervisions by
the Design &
Supervision
Firm
Project Progress
Report on ESMP
implementation,
Construction
Labor Agreement,
Workers’ Code of
Conduct
Included in
Project Cost/
sub-component
2.2 – Design
and Supervision
of House
Reconstruction
(US$ 2.05
million) and
101
101 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
also involve pre-
qualified building
contractors in a
small scale, thus
potentially
involving
minimal labor
influx, potentially
resulting in
conflicts with
existing
communities.
works projects in Dominica using
local contractors. It involves a
meeting held before the start of
physical works between the
concerned local governance entity
and the contractor, where the PIU
will be represented, and where
issues related to the work and the
contractor’s presence are discussed
and agreed upon in writing
(Construction Labor Agreement).
Component 3
(US$ 3 million)
– Project
Implementation
and
Administration
7.g – Inadequate
consideration of
environmental,
social, health and
safety (ESHS)
aspects during
construction, such
as air pollution,
increased noise,
potential traffic
increase and
increase of risk of
traffic accidents
involving
community
members, etc.
7.g.1 – Prior to finalization of each
individual Grant Agreement, the
Design & Supervision Firm will
inform each beneficiary of the
ESMP requirements during
construction and will assist with
obtaining a building permit, if
needed.
The Design and
Supervision Firm
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
Prior to each
Grant
Agreement
Project Progress
Report on ESMP
implementation
Included in
Project Cost/
sub-component
2.2 – Design
and Supervision
of House
Reconstruction
(US$ 2.05
million) and
Component 3
(US$ 3 million)
– Project
Implementation
and
Administration
7.g.2 – The ESMF includes a
generic ESMP (in Annex 8) to
address the potential ESHS of
small construction activities,
including, but not limited to,
Construction Waste Management,
Waste and Hazardous Waste
Management, Effluents
Management, limit construction
hours to 7am-7pm week days,
comply with noise standards, and
promote this publicly; use dust
suppression techniques, use dust
The Contractor or
the Beneficiary
through his own
building personnel
(self, relatives and/or
community
members).
The Design and
Supervision
Firm, and the
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
As a minimum,
every other
week
supervisions by
the Design &
Supervision
Firm
Project Progress
Report on ESMP
implementation
Included in
Project Cost/
sub-component
2.2 – Design
and Supervision
of House
Reconstruction
(US$ 2.05
million) and
Component 3
(US$ 3 million)
– Project
Implementation
102
102 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
control measures such as, for
example, enclosures and covers,
increase of moisture contents of
materials, install sewage systems
for workers, etc.
and
Administration
7.h – Potential
health and safety
risks for workers
during building
activities, such as
cave-ins during
excavations, falls
from heights, slip
and trips,
dismembering
when working
with electrical or
mechanic
equipment, etc.
7.h – The ESMF includes a
generic ESMP (in Annex 8) to
address the potential HS of small
construction activities, and the
Design & Supervision Firm will
review and supervise the use of
adequate PPEs and
implementation of standard
operating procedures for key
activities on small construction,
such as excavation, working on
heights, scaffolding, etc
The Contractor or
the Beneficiary
through his own
building personnel
(self, relatives and/or
community
members).
The Design and
Supervision
Firm, and the
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
Prior to
launching of
the Project and
every other
week
supervisions by
the Design &
Supervision
Firm
Project Progress
Report on ESMP
implementation,
Site visit during
construction,
SOPs for key
activities on small
construction
Included in
Project Cost/
sub-component
2.2 – Design
and Supervision
of House
Reconstruction
(US$ 2.05
million) and
Component 3
(US$ 3 million)
– Project
Implementation
and
Administration;
cost of
implementing
the ESMP must
be included in
the cost of the
construction, as
estimated for the
Grant
7.i- Potential
impacts and risks
to communities
from
transportation of
heavy equipment
and building
materials.
7.i- The ESMF includes a generic
ESMP (in Annex 8) to address the
potential ESHS of small
construction activities, and the
Design & Supervision Firm will
review and supervise the
implementation of a Community
Safety Management Plan,
including traffic plan, adequate
signage to call attention to traffic
risks, limiting vehicle speed in
The Contractor or
the Beneficiary
through his own
building personnel
(self, relatives and/or
community
members).
The Design and
Supervision
Firm, and the
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
As a minimum,
every other
week
supervisions by
the Design &
Supervision
Firm
Project Progress
Report on ESMP
implementation,
Traffic Plan
Site visit
Included in
Project Cost/
sub-component
2.2 – Design
and Supervision
of House
Reconstruction
(US$ 2.05
million) and
Component 3
(US$ 3 million)
– Project
103
103 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
access roads, limiting hours for the
delivery of building materials, etc.
Implementation
and
Administration;
cost of
implementing
the ESMP must
be included in
the cost of the
construction, as
estimated for the
Grant
7j. Inadequate and
poorly managed
community
relations leading
to psycho-social
tensions towards
the project,
contractors and
staff and design
and supervision
firm.
7j Social Management
Components of ESMP:
Inform the local authorities and
community about construction
and work schedules, interruption
of services, traffic detour routes
and provisional bus routes, as
appropriate.
Social sensitivity should be
applied in communities within the
Kalinago Territory and other
minority demographic groups.
The Code of Conduct is
established and should be
followed.
The Design and
Supervision Firm,
The Contractor
The Design and
Supervision firm,
The PIU
Safeguards
specialists
Throughout the
construction
phase as
required by
monitoring
schedule
Project Progress
Report on ESMP
implementation,
Community
meeting
Cost of
implementing
the ESMP must
be included in
the cost of the
construction, as
estimated for the
Grant
104
104 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
7k. Poorly
Managed Solid
Waste/Debris
Disposal around
construction sites
leading to
potential
community health
and
environmental
health risks.
There is also the
potential impact
of material spills
that poses safety
risks to the wider
community where
construction
works are being
conducted. This
may include
vector borne
diseases and
generally affect
the aesthetics of
the community’s
natural and built
environment
7k Proper disposal of construction
waste through a waste
management plan which will
include and in accordance with the
national regulations:
Ensuring that there are
daily site clean-up procedures,
including maintenance of adequate
disposal facilities for construction
debris.
Utilizing reduce reuse recycle
principle for all demolition debris
generated; and where not feasible,
the carrying of this debris to
designated and approved sites.
This will ensure that there is
restoration of the affected area to
its original state to the satisfaction
of the HRP PIU and/or delegated
agencies and local communities.
The Design and
Supervision Firm,
The Contractor
The Design and
Supervision
Firm,
The PIU
Safeguards
specialists
Throughout the
construction
phase as
required by
monitoring
schedule
Project Progress
Report on ESMP
implementation,
Waste
Management
Procedure,
Site visit
Cost of
implementing
the ESMP must
be included in
the cost of the
construction, as
estimated for the
Grant
7. l. Reduced
Water quality,
liquid and solid
waste discharge
7.l Whenever possible, the
amounts of wastewater that need
to be discharged must be
minimized and alternative means
of disposal must be identified.
Liquid spills of lubricant, fuel and
oil within the site should be
attended at the earliest in order to
minimize land & groundwater
contamination.
The Design and
Supervision Firm,
The Contractor
The Design and
Supervision
Firm,
The PIU
Safeguards
specialists
Throughout the
construction
phase as
required by
monitoring
schedule
Project Progress
Report on ESMP
implementation,
Site visit
Cost of
implementing
the ESMP must
be included in
the cost of the
construction, as
estimated for the
Grant
105
105 | P a g e E S M F F i n a l D r a f t 1 4 M a y 2 0 1 9
(Procedures are included in the
ESMP)
7m. Poor
sanitation within
and around
construction sites
7.m The necessary training shall
be conducted for contractors and
their employees and this will be
ensured by the D&S Firm with
further validation by the PIU
safeguards specialists.
Elements of any Health and Safety
Management plan developed will
include a checklist which should
be monitored and evaluated
periodically.
The Design and
Supervision Firm,
The Contractor
The Design and
Supervision
Firm,
The PIU
Safeguards
specialists
Throughout the
construction
phase as
required by
monitoring
schedule
Project Progress
Report on ESMP
implementation,
Site visit
Cost of
implementing
the ESMP must
be included in
the cost of the
construction, as
estimated for the
Grant
8. Closure and
decommissioning
of construction
sites
8.– Potential for
contamination
and pollution
from construction
materials left
behind; risks of
accidents with:
holes left
unprotected,
rebars
unprotected from
impalement risks,
wood uncleared
from steel nails,
etc.; risks of
contamination
with hydrocarbon
and/or chemical
spills.
8. The ESMF includes a generic
ESMP (in Annex 8) to address the
potential ESHS of small
construction activities, and the
Design & Supervision Firm will
review and supervise the
implementation of the procedures
for Site Decommissioning,
including decontamination of the
site, when required.
The Contractor or
the Beneficiary
through his own
building personnel
(self, relatives and/or
community
members).
The Design and
Supervision
Firm, and the
E&S Specialists
in the PIU
(MoHL) with
support from the
IST within MoF.
Inspection
prior to
authorizing the
last installment
to the
Contractor or
to the
Beneficiary.
Project Progress
Report on ESMP
implementation,
The cost of
implementing
the ESMP must
be included in
the cost of the
construction, as
estimated for the
Grant.
Annex 11: Housing Recovery Project ESMF: Consultations
Kalinago Council - October 11, 2018 in Saint Cyr Village
Persons met: Charles Williams, Chief
Jacqueline Corbette, Clerk
Jumadine Frederick, Councilor (Housing)
Issues raised and information provided by the Kalinago Council:
• Reconstruction of houses destroyed/damaged by Hurricane Maria will require approval by the
Council (whether the reconstruction/repair is done in situ or in a different location due to hazard
considerations).
• The Council has a list of houses that were totally damaged or compromised by Hurricane Maria,
and requests information on the number of new houses that will be constructed/financed under the HRP in
the Kalinago Territory. This information will enable the Council to determine the allocation of the housing
reconstruction assistance to those most in need.
• The Council has authority to allocate land for housing within the Kalinago Territory. For eligible
beneficiaries with a damaged house located on a hazard plot, the Council can identify and allocate a
different non-hazardous house plot.
• The Council know of renters/tenants (= non-owners) who resided in houses destroyed by Hurricane
Maria, but does not have a complete inventory of all such cases. Renters/tenants can apply to the Council
for an alternative plot for construction of a replacement house in the same way as an eligible beneficiary
with a damaged house located on a hazard plot.
• The Council requested that (a) as much as possible the housing reconstruction work should be done
with local labor, and (b) that the large number of hurricane-destroyed trees should be made use of for the
replacement houses (it was asserted that most of the hurricane destroyed houses in the Kalinago Territory
were built with imported lumber, whereas houses built with local timber has held up better).
Colihaut Village Council – October 19, 2018
Persons met: 14 female and male council members and villagers.
Issues raised and information provided:
Regarding HRP grievance redress arrangements, the Village Council members made the point that the
Councils should not be tasked as the direct recipients of complaints from the residents in their areas.
Members of these local governance bodies already have a range of responsibilities on top of their daily
work to make a living. The work associated with receiving and logging complaints could potentially
become quite time-consuming and burdensome, especially if community members engage in discussions
of their case in the expectation of an immediate decision, or advocacy by the Village Council when the case
is discussed with the project.
The other issue discussed during the meeting concerned families – some of whom were present at the
meeting - who lived under some form of tenancy arrangement in hurricane destroyed houses. It was argued
that such families should also be able to be considered as eligible for housing reconstruction assistance. It
was further suggested that in cases where an eligible family, who had been tenants in a hurricane destroyed
house, owned land elsewhere, the replacement house should be built on this land (assuming it was found to
be hazard-free). In cases were the replacement house had to be built in situ, there should be some form of
security of tenancy (at least for a defined period), and rents for the replacement house should not be allowed
to exceed the existing fair market rate in the area.