environmental impact assessment for the proposed …...environmental impact assessment for the...
TRANSCRIPT
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam and
Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-1
1.0 INTRODUCTION
M/s. Southern District Textile Processing Cluster (P) Limited (herein after
referred to as SDTPCPL) proposes to establish an Industrial estate exclusively for Textile
Processing, with a Common Effluent Treatment Plant (CETP) and a Captive Power Plant
(CPP) in the Pottalkulam and Tamaraikulam villages of Kariyapatti Taluk in Virudhunagar
District, Tamil Nadu. The total area of the proposed project is 40.65 hectares (100.46
acres). The estimated total cost of the project is Rs. 170 Crores.
As per the EIA Notification dated 14th September 2006, the proposed project falls under
the following Schedule. Nos. :
7(c)-Industrial estates/parks/complexes/areas, export processing Zones (EPZs), Special
Economic Zones (SEZs), Biotech Parks, Leather Complexes; 7(h) - Common Effluent
Treatment Plant and 1(d) - Thermal Power Plant less than 5 M.W Capacity. Considering
the project activities and capacity, the proposed project is categorized as Category B1.
In order to obtain Environmental Clearance from SEIAA and Consent for Establishment
(CFE) from the Tamil Nadu Pollution Control Board (TNPCB), Environmental Impact
Assessment (EIA) report with detailed Environmental Management Plan (EMP) is
essential as per the EIA notification and its subsequent amendments. The project was
presented in the 72nd TN-SEAC meeting held on 04.02.2016 and received ToR vide
letter No. SEIAA- TN/F.No.4778/2015/ToR-242/VRD/8 (b),7C&7h dated 09.07.2016 and
the EIA Report has been prepared in line with the TOR conditions obtained.
1.1 Details of Project Location
The proposed Textile Processing Cluster is intended to be developed in an area of 40.65
hectares (100.46 acres) at Virudhunagar District. The environmental setting of the
project is given in Table-1.2. The index map and study area of 10 km radius of the
proposed plant is shown in Figure- 1.1 and Figure-1.2 respectively. The aerial view of
the proposed project site is shown in Figure- 1.3. The Environmental setting of the
proposed project site is given in Table-1.1.
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam and
Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-2
TABLE- 1.1
ENVIRONMENTAL SETTING OF THE PROPOSED PLANT SITE (10 km RADIUS)
Sr.
No.
Particulars Details
1. Site - Coordinates
.
No
.
Latitude Longitude
A 9°36’28.09” N 78°11’51.80” E
B 9°36’36.53” N 78°12’08.52” E
C 9°36’22.08” N 78°12’16.52” E
D 9°36’20.34” N 78°12’04.34” E
2.
Elevation above Mean
Sea Level
73 m
3. Climatic Conditions As per IMD, Madurai:
Annual Max. Temperature : 39.9°C
Annual Min. Temperature : 19.9°C
Annual Average Rainfall : 873.3 mm 4. Land Use Unclassified Land Use as per DTCP 5. Nearest Highway Kariyapatti- Narikkudi Road, 4.71 km, NNE
Tiruchuli Road, 5.16 km, SW
SH-184 connecting Virudhunagar –
Krishnapuram, 5.48 km, WSW
SH-42 connecting Srivilliputhur – Parthibanur,
7.36 km, SSE
Thiruppuvanam – Narikkudi Road, 8.91 km, ENE 6. Nearest Railway Station Tiruchuli Railway Station, 7.5 km , South 7. Nearest Airport Madurai International Airport, 28.08 km, NNW 8. Nearest Seaport Tuticorin VOC port, 93.68 km, South 9. Nearest Town/ City Tiruchuli-7.81 km, South
Kariyapatti-12.81 km, NW 10. Hills/ Valleys Nil within 10 km Radius
11. Streams/ Rivers Gundar Stream, 4.72 km, WSW
12. Archaeologically
Important Places
Nil within 10 km Radius
13. National Parks/ Wildlife
Sanctuaries
Nil within 10 km Radius
14. Reserved/ Protected
Forest
Nil within 10 km Radius
15. Seismicity zone Zone II, as per IS1893: 2002 part I 16. Defence Installations Nil within 15 km radius 17. Nearby industries Nil within 10 km radius
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam and
Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-3
FIGURE-1.1
INDEX MAP
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam and
Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-4
FIGURE-1.2
STUDY AREA MAP
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam and Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu
Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-5
FIGURE-1.3
AERIAL VIEW OF THE PROPOSED PROJECT SITE
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam
and Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-6
2.0 NATURE OF THE PROJECT
The proposed project will provide Industrial plots and services to the 36 member units.
The facilities offered include Textile processing facility, Common Effluent Treatment
Plant, Captive Co- generation Power plant, Driers, Godown, Laboratory, Training
Institute, Business Centre and CETP Solid Waste Storage Yard. The textile processing
cluster will have provisions for Rain water harvesting and Green Belt. It will be a state-
of-the-art project with modern plant & machinery together with modern physical and
social infrastructure and would enable the entrepreneurs to produce high value added
products, enhance their productivity and meet international procurement standards. The
details of the project are given in Table-2.1.
TABLE-2.1
PROJECT DETAILS
Sr.
No.
Description Details
1 Location of the Proposed
project or activity
Pottalkulam: S.F. Nos. 2/3, 6/3, 4/1, 6/7,
4/2, 6/6, 4/3, 6/5, 3/1, 6/4, 6/2, 1/2, 1/3,
1/4, 1/5, 1/6, 1/7, 6/8, 6/9, 6/10, 1/8, 2/2,
3/2,1/9, 1/10
Tamaraikulam: S.F. Nos. 46/1, 48/1, 48/2,
48/3, 48/4, 49/1, 49/2, 50/1, 6/3A, 6/4,
6/5A, 6/6A, 6/7A, 6/7B, 7/2, 7/3, 7/5A,
7/5B, 46/2 Pottalkulam and Tamaraikulam
Villages, Kariyapatti Taluk, Virudhunagar,
Tamil Nadu
2 Power requirement for
CETP & Admin Office
Electricity Demand: 2.2 MW
Source: Co-generation Power Plant at
SDTPCPL
Power requirement of 3.6 MW for the 36
member units will be met from TANGEDCO.
3 Fuel requirement
(i) DG Set
(1000 KVA x 3 nos.)
250 Lit/hr/DG Set
Ultrapure low sulphur content diesel for
standby
DG-Set
(ii) Boiler (For CETP operation) 1 x 22 TPH
Fuel : Indian Coal
Coal Consumption: 28 TPD
4 Water Requirement Total Water requirement: 5721.0 KLD
Source: Proposed bore wells within plant site
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam
and Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-7
after obtaining necessary approval from
CGWA
5 Details of Land use/Land
Cover within proposed site
Area in ha Area in %
(i) Built-Up Area 13.98 34.36
(i) Industrial Training Centre 1.23 3.02
(iii) Power Room (EB) 0.71 1.74
(iv) Common Facilities:
Admin Office, Co- gen,
CETP, Chemical Godown
Area and CETP Solid Waste
Storage Yard
6.30 15.48
(v) Green Belt Development 13.63 33.5
(vi) Proposed Road Area 3.71 9.18
(vii) Future Purposes 1.09 2.68
Total Area 40.65 100.0
6 Total investment of the
project/activity.
Estimated total project cost for infrastructure
development under this project is Rs. 170
Crores
Textile Processing Cluster - Rs. 150
Crores
CETP & CPP - Rs. 20 Crores 7 Funds allocated for EMP
(capital cost and recurring
cost per annum)
Capital Cost : Rs. 850 Lakhs
CETP :Rs. 510 Lakhs
Storm Water Drainage :Rs. 42.5 Lakhs
Greenbelt Development :Rs. 127.5 Lakhs
Solid Waste Management:Rs. 42.5 Lakhs
Air Pollution Control :Rs. 127.5 Lakhs
Recurring Cost: Rs. 300 Lakhs
8 Estimated Employment 800 Employees
2.1 Production Details
Fabric dyed, Yarn dyed (both cold and hot wash process) wider width fabrics woven for
garments will be the specialty of this textile processing cluster. Out of 36 member units
proposed in the textile park, 25 units activities are fabric dyeing, 7 units activities are
Yarn dyeing through hot wash process and 4 units activities are Yarn dyeing through cold
wash process. The total production details of the 36 member units are listed in Table-
2.2.
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam
and Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-8
TABLE-2.2
PRODUCTION DETAILS
Sr. No. Activities to be carried
by Member Units
Operating Units
(No’s)
Production
Quantity
(Tonnes/ Day)
1. Fabric Dyeing 25 50
2. Yarn Dyeing (Hot) 7 7
3. Yarn Dyeing (Cold) 4 4
Total 36 61 Source: SDTPCPL
3.0 BASELINE ENVIRONMENTAL STATUS
Baseline Environmental status illustrates the description of the existing environmental
status of the study area with reference to the prominent environmental attributes. The
study area covers 10 km radius area around the proposed project site. The baseline
studies are carried out during 1ST June to 31st August, 2016 in various domains of
environment.
3.1 Meteorology
Meteorological data at the site was monitored during 1st June 2016 to 31st August, 2016.
It was observed that during the study period, temperature ranged from 22° C to 40° C.
The relative humidity recorded ranged from 22% to 94%. The predominant wind
directions during the study period are SW and WSW.
3.2 Ambient Air Quality
Ambient Air Quality Monitoring (AAQM) has been carried out at eight locations within the
study area. The maximum value for PM10 is observed as 48.6 μg/m3, with the minimum
value observed as 36.7 μg/m3 during the study period. The maximum value for PM2.5 is
observed as 17.5 μg/m3, with the minimum value observed as 15.4 μg/m3 during the
study period. The maximum and minimum values of SO2 were observed to be 7.1 and
5.3 μg/m3 respectively. The maximum and minimum concentrations of NOx were found
to be 9.0 and 6.3 μg/m3 respectively. The results obtained indicate that the
concentrations of PM10, PM2.5, SO2, and NOx, in the ambient air are well within the
National Ambient Air Quality (NAAQ) standards for industrial, residential and rural areas.
3.3 Water Quality
To assess the physical and chemical properties of water in the region, six ground water
samples were taken within the study area. No surface water sources were observed in
the region during the study period. Analyses of these samples indicated that the
parameters were generally conforming to the standards prescribed by IS: 10500.
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam
and Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-9
3.4 Soil Quality
Eight soil samples were collected in and around the proposed project area to assess the
present soil quality of the region. Based on the results, the soil in the region has been
found to have sufficient quantities of nutrients for crop growth.
3.5 Noise Levels
Ambient Noise levels were measured at eight locations around the proposed project site.
The daytime noise levels were found to be in the range of 42.7 dB (A) to 51.8 dB (A).
The night time noise levels were observed to be in the range of 38.9 dB (A) to 47.9 dB
(A). The noise levels were found to be well within the range specified by CPCB norms.
3.6 Ecological Environment
On the basis of field studies, records of Botanical Survey of India and Forest
department, Tamil Nadu state did not indicate presence of any endangered and or
vulnerable species in this area and there are no reserved, protected or village forests in
10- km from proposed project site. A comprehensive Central Legislation namely Wild
Life (Protection) Act was enforced in 1972 to provide protection to wild animals. No
species in the study area belongs to Schedule I of Wildlife protection Act, 1972 and
there are no endangered, threatened wild animal species in study area.
3.7 Social Environment
The study area (10 km radius) has a total population of 129544 according to 2011
census. The males and females constitute 50.33% and 49.67% of the total population.
The data of study area reveals that it has literacy rate of 65.86%.
3.8 Land use
Based on the census report, 10-km radial distance around this proposed site boundary
has been considered for the study. The irrigated land measures to about 2728.56 ha in
the study area while the un- irrigated land is about 1899.37 ha. The study area
comprises about 3.5% of cultivable wastelands. The land not available for cultivation is
around 68.45% of the study area.
Based on the satellite imagery, the built- up area occupies 2.60% of the total area.
Agricultural land occupies 40.97% of the total area. 8.61% of the study area is occupied
by water bodies. No forest lands were observed in the study area.
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam
and Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-10
ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
4.1 Impact on Air Quality
The sources of gaseous pollutants within the proposed project are captive Power Plant,
DG sets and vehicular movement within the premises. The emissions of Sulphur dioxide
(SO2) and oxides of Nitrogen (NOx) will be due to operation of DG sets, in case of the
failure of the power grid. The air quality modeling was done to assess the impacts of air
quality due to the operation of Co- generation plant and the DG sets of the proposed
project. The resultant concentrations of PM10, SO2 and NOx were found to be 49.01
μg/m3, 7.23 μg/m3 and 9.15 μg/m3 respectively. The results showed that the resultant
ambient air quality after considering the point source emissions, fugitive/ area source
emissions and line source emissions were well below the limits as per National Air
Ambient Air Quality Standards (NAAQS), 2009.
4.2 Impact on Water Quality
The total water requirement will be 5721 KLD. Out of the total water requirement,
388.5KLD will be fresh water, which will be met from the proposed bore wells within
proposed project site. The wastewater will be generated only from the sanitation
facilities and dyeing plants. The entire wastewater generated from the textile units will
be treated in CETP and the treated water will be reused for process house. The domestic
wastewater generated will be treated in CSTP and the treated water will be reused for
flushing and green belt development.
In order to conserve water resources and rainwater in the proposed project, efforts will
be made to recharge ground water resources by constructing appropriate rainwater
harvesting structures within the premises.
4.3 Impact of Solid Wastes
In order to avoid problems associated with solid waste disposal problems, an effective
solid waste management system will be followed. Composting yard will be developed for
composting the biodegradable waste. The compost generated will be utilized within
project area for plantation activities. The non-biodegradable waste, recyclable waste will
be given to authorized recyclers. Horticulture waste such as dried leaves, flowers etc.
shall be utilized as manure. The CETP solid waste generated will be collected, stored,
transported and disposed to TSDF, Gummidipoondi.
4.4 Impact on Noise Levels
The noise generating sources from the proposed project is DG sets, cooling tower,
conveyor belts, air cooled condenser and Captive Power generation. The noise
dispersion from the project site is computed based on mathematical modeling. The
predicted noise levels at the boundary due to various plant activities will be ranging in
between 30- 50 dB(A). It is seen from the modeling results that the incremental noise
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam
and Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-11
levels are within the CPCB standards. However, the greenbelt that is to be provided will
further attenuate the noise levels.
Recommendations
All the design/installation precautions as specified by the manufacturers with respect
to noise control will be strictly adhered to;
High noise generating sources will be insulated adequately by providing suitable
enclosures;
The noise control system will be designed to form an integral part of the plant;
Use of lagging with attenuation properties on plant components / installation of sound
attenuation panels around the equipment;
The air compressor, air cooled condenser, pneumatic valves will be provided with
acoustic enclosure;
4.5 Impact on Ecology
The incremental concentrations of the Air quality modeling shows that the resultant
levels of PM, SO2 and NOx were well within the permissible limits as per National
Ambient Air Quality Standards (2009). Hence no adverse impact is envisaged on the
Terrestrial ecology. Since the unit will be operating on zero discharge process, no impact
on aquatic ecology is envisaged.
4.6 Impact on Soil Quality
All the impacts related with soils are restricted to the construction phase only; hence
there will not be any impact of the proposed project on soils of the project site during
the operational phase. The topsoil removed during construction will be used for the
development of greenbelt. The entire wastewater from the project will be treated and
reused, thereby conserving water and minimizing pollution. The Solid wastes generated
from the proposed project will be properly collected and disposed. Hence, no soil
pollution is anticipated from the proposed project.
4.7 Impact on Public Health
The discharge of waste materials (wastewater and solid wastes) from the project can
have some adverse impacts on public health in the surrounding area, if appropriate
treatment procedures are not followed. As the project will be designed as per the
modern available technology for controlling the impacts, no adverse impacts on public
health in the area are anticipated.
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam
and Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-12
5.0 ENVIRONMENTAL MONITORING PROGRAMME
The environmental monitoring program is important in terms of evaluating the
performance of pollution control equipment installed in the project. The sampling and
analysis of the environmental attributes will be as per the guidelines of CPCB/TNPCB.
The frequency of air, noise, ground water sampling and location of sampling will be as
per the directives of Tamil Nadu Pollution Control Board.
5.1 Cost Provision for Environmental Measures
For environment protection, management, pollution control, treatment and monitoring
systems, appropriate budgetary provision would be made and provision for recurring
expenditure for environment management of the project would be made. The details of
budget allocation during functional phase are given in Table-5.1.
TABLE-5.1
BUDGET ALLOCATION FOR ENVIRONMENTAL PROTECTION
Sr.
No. Description
Budgetary Allocation
(Rs. In lakhs)
Capital cost Recurring
cost
1. Common Effluent Treatment Plant
(CETP)
510 180
2. Storm Water Drainage 42.5 15
3. Greenbelt Development 127.5 45
4. Solid Waste Management 42.5 15
5. Air Pollution Control 127.5 45
Total 850 300
5.2 Greenbelt Development
The main objective of the green belt is to provide a barrier between the textile
processing cluster and the surrounding areas. The green belt helps to capture the
fugitive emissions and to attenuate the noise generated in the project site apart from
improving the aesthetics of the site. In order to control the industrial pollutants, dense
tree plantations are necessary. The greenbelt shall be designed and implemented as per
the latest CPCB guidelines for an area of 13.63 ha, covering 33.5% of the proposed
project site.
6.0 DISASTER MANAGEMENT PLAN
To tackle the consequences of a major emergency inside the project premises or its
immediate vicinity, a Disaster Management Plan has been formulated and this planned
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam
and Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-13
emergency document is called “Disaster Management Plan”. The objective of the
Disaster Management Plan is to make use of the combined resources of the textile
processing cluster and the outside services to achieve the following:
Effect the rescue and medical treatment of casualties;
Safeguard other people;
Minimize damage to property and the environment;
Initially contain and ultimately bring the incident under control;
Identify any dead;
Provide for needs of relatives;
Provide authoritative information to the media;
Secure the safe rehabilitation of affected area; and
Preserve relevant records and equipment for the subsequent inquiry into the
cause and circumstance of the Emergency.
6.1 Occupational Health & Safety Measures
Large projects where multifarious activities are involved during construction, erection,
testing, commissioning, operation and maintenance, the men, materials and machines
are the basic inputs. Along with the benefits, the industrialization generally brings
several problems like occupational health and safety.
The industrial planner therefore has to take steps to minimize the impacts and to ensure
appropriate occupational health and safety in the proposed textile processing cluster.
The following measures are proposed:
Conducting awareness programs at regular intervals to the employees
Providing safety kits and prevention kits
Provision of Clinic at the project site to handle emergency situations that may
arise.
7.0 PROJECT BENEFITS
The proposed textile processing cluster is a momentous stride in the history of textile
industry to meet the objective of the Central and State Governments in expanding
textile exports from India and to meet the global demand in textile quality & quantity.
Successful implementation of this project would provide a replicable model for
development of other clusters across the country.
The project aims to ensure sustainable employment opportunities for the thousands of
labour force in the cluster. The manpower employed for the proposed project during
operation will be about 800 persons for direct activities and about 2000 persons for
indirect activities.
Environmental Impact Assessment for the Proposed Textile Processing Cluster by M/s. Southern District Textile Processing Cluster Private Limited at Pottalkulam
and Tamaraikulam Villages, Kariyapatti Taluk, Virudhunagar District, Tamil Nadu Executive Summary
VIMTA Labs Limited, Hyderabad/Coimbatore E-14
7.1 Corporate Social Responsibility (CSR) Policy
SDTPCPL has developed the CSR Policy in consonance with Section 135, Companies Act
2013 on CSR and in accordance with the CSR Rules notified thereof by the Ministry of
Corporate Affairs, Government of India in 2014. The budgetary allocation for the CSR
activities is given in Table- 7.1.
TABLE- 7.1
CORPORATE SOCIAL RESPONSIBILITY ACTION PLAN
Sr.
No.
Activity Investment
(Rs. In Lakhs)
1 Tree Plantation 30
2 Safe drinking water for Pottalkulam
and Tamaraikulam Villages
120
3 Bus Shelters at nearby villages 80
4 Community Hall for Public Use 130
5 A Clinic for Primary Health Awareness 65
Total 425
8.0 CONCLUSION
The proposed project has certain level of marginal impacts on the local environment.
However, development of this project has certain beneficial impact/effects in terms of
production & export of garments and providing employment opportunities that will be
created during the course of setting up and as well as during the operational phase of
the entire project.