SOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency Project April 2012 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: trancong

Post on 10-Mar-2018

230 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

SOCIALIST REPUBLIC OF VIETNAM

VIETNAM ELECTRICITY

ENVIRONMENTAL MANAGEMENT

FRAMEWORK

For

Vietnam Distribution Efficiency Project

April 2012

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb350881
Typewritten Text
E3035
Page 2: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

i

ABBREVIATIONS

CIPR Construction Investment Project Report

DARD Department of Agriculture and Rural Development

DONRE Department of Natural Resource and Environment

DPC District People‟s Committee

EA Environmental Assessment

ECOP Environmental Codes of Practice

EIA Environmental Impact Assessment

EMF Environmental Management Framework

EMP Environmental Management Plan

EPC Environmental Protection Commitment

EVN Electricity of Vietnam Corporation

MOIT Ministry of Industry and Trade

MONRE Ministry of Natural Resource and Environment

MARD Ministry of Agriculture and Rural Development

PC Power Corporation

PPC Provincial People‟s Committee

TOR Terms of Reference

Page 3: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

ii

TABLE OF CONTENTS

1. INTRODUCTION…………………………………………………………...…………….…...1

2. CLASSIFICATION OF COMPONENT 1 AND 2 SUBPROJECTS…………...….……….2

3. LEGAL FRAMEWORKS…………………………………………………………………… 3

3.1 Applicable Vietnamese Legislations……………………………………………….…...…….. 3

3.2 World Bank Safeguard Policies…………………………………………………...…..…… .…..4

4. ENVIRONMENTAL SCREENING…………………………………………….………… …5

5. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES…………….….......... 6

5.1. Potential Impacts …………………………………………………………………… ………..6

5.2. Mitigation Measures ………………………………………………………………. ………...6

6. PROCESS FOR PREPARATION OF EMP AND APPROVAL……..…………………..... 7

6.1 Overall Guidance for Developing EMP………………………………………………........ …..7

6.2 Specific Guidance for PCBs Management……………………………………..……......... ……9

6.3 Specific Guidance for Public Consultation and Information Disclosure……….…........... …..10

6.4 Institutional Arrangement for the EA Process……………………………..…..…………. …..11

6.5 Implementation, Supervision, Monitoring, and Reporting………………………...…….…….11

6.6 Stafing Requirements and Capacity Building…………………….……………….…………. .12

6.7 Consultation During EMF Preparation……………………...………………....…………....... 12

6.8 Budget for EMF Implementation……………………………………………………………. 12

ANNEXES

Annex 1: Rapid Environmental Assessment Checklist………………………………………… ...13

Annex 2: Environmental Consultation Summary…………………………………… ……………16

Annex 3: Environmental Monitoring Plan………………………………………….. ……………16

Annex 4: Institutional Arrangements for EMP Implementation…………………….. …………...17

Annex 5: Reporting Procedures……………………………………………………… ……………19

Annex 6: Cost Estimate………………………………………………………………. …………...19

Annex 7: Guidance for Preparing EMP for Subprojects…………………………….. ……………20

Annex 8: TOR for Construction Supervision Consultant (CSC)……………………………… ….23

Annex 9: Environmental Codes of Practice (ECOP) .. …. ………………………………………...25

Page 4: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

1

Environmental Management Framework for

Distribution Efficiency Project

1. INTRODUCTION

The project development objective of the Distribution Efficiency Project is to strengthen reliability,

quality of supply and enhance demand side efficient use of electricity to improve the efficiency of

power distribution and retail supply services of Vietnam‟s Power Corporations (PCs), and reduce

greenhouse gas (GHG) emissions..

The project objective would be achieved through: (i) the reinforcement and expansion of the

distribution networks of the 5 PC‟s from 110 kV voltage down to 0.4 kV system; (ii) the introduction

of smart grid technologies focusing on advanced metering systems and automation to improve the

efficiency of distribution services, integrate renewable generation, and implement load response

programs; and (iii) provision of technical assistance and capacity building to PCs, as well as technical

assistance to the Electricity Regulatory Authority of Vietnam (ERAV) in the Ministry of Industry and

Trade (MOIT) to enhance the tariffs and efficiency regulatory framework and the monitoring systems.

The project will comprise three components:

a) Component 1: System Expansion and Reinforcement. This component will cover

construction and reinforcement of 110 kV, medium voltage (MV) and LV networks, including

distribution lines and substations of 110 kV, 35 KV, 22kV, and to 0.4 kV. The investments

under this component will help the PCs to efficiently meet load growth, address load supply

constraints due to distribution system congestion, reduce losses, and improve reliability and

quality of power supply. The project areas would be scattered all over the country.

b) Component 2: Introduction of Smart Grid Technologies in Distribution. This component will

focus on the automation of distribution network operations and introduction of advanced

metering infrastructure systems (AMI) at key substations and electricity consumers of PCs.

The AMI will include tools for the systematic gathering, storing, processing, analyzing and

monitoring of consumption data, as well as two-way communication between the PC control

centers and their customers.

c) Component 3: Technical Assistance and Capacity Building. This component will include

technical assistance and capacity building for the five PCs, and for ERAV to develop and

implement new and enhanced regulations for promoting efficient use of electricity, and

monitoring and communication frameworks.

The three components will be implemented by the five PCs, and Component 3 also by ERAV in

MOIT. To maximize initial impact, Component 2 will start by focusing on key distribution substations

and the larger electricity customers.

The Project is proposed to be Environmental Category B according to World Bank environmental

assessment policy OP/BP 4.01.1 The Project may bring both negative and positive impacts to the

1 For details on the classification of projects, see OP/BP 4.01: Environmental Assessment.

Page 5: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

2

Project areas. The negative impacts will occur during pre-construction, construction, and operation.

Most negative impacts will be minor, due to their temporary and/or small-scale nature. The positive

impacts will occur mostly during operation. Positive impacts will likely be significant and positive due

to their long term nature at both the local and regional level.

Siting of substations, access roads, distribution right of way (ROW), towers etc. should follows the

guidance described in Section 4 in order to avoid adverse socio-environmental impacts.

In order to present a more detailed evaluation of the Project‟s negative and positive impacts,

environmental screening should be conducted early in the Project cycle, i.e. soon after the information

become available. Guidance on conducting an environmental screening for the DEP Project is found in

Section 4. If the screening shows that a sub-project may cause adverse impacts on socio-environmental

sensitive areas, then instructions given in Section 4 will be followed. If the screening reveals that

negative impacts are minor, then the sub-project is confirmed to be environmental Category B and the

focus of safeguard work should turn to developing an Environmental Management Plan (EMP).2

Guidance on developing an EMP for Category B for the DEP Project is found in Section 6. Further

guidance on assessment methodologies and common impacts associated with transmission and

distribution projects are found in:

World Bank, 1991. Environmental Assessment Sourcebook, Volume 3; and

IFC, 2007. Environmental, Health, and Safety Guidelines on Electric Power Transmission and

Distribution.

In addition to the guidance given in the main text of this Framework, this document contains 9 annexes

with examples and forms that can be used as reference for environmental screening and various steps

during the preparation of EMPs for Distribution Efficiency Sub-Projects within Vietnamese contexts.

2. CLASSIFICATION OF COMPONENT 1 AND 2 SUBPROJECTS

The subprojects are classified into groups based on types of investment and construction items. Groups

include: (i) Subproject group of new construction and installation and rehabilitation of 110kV voltage

lines and substations; (ii) Subproject group of new construction and installation and rehabilitation of

medium and low voltage power networks; and (iii) Subproject group of introduction of advanced

metering systems and establishing SCADA systems and remote control facilities.

Most activities of the Component 1 subprojects will involve construction and installation of sub-

transmission and distribution lines, substations including transformers, power towers, poles, and

wiring. Some subprojects under Component 1 may also include access roads, clearance of right of way

(ROW), etc. Component 2 includes installation and adaptation of advanced metering and specialized

Supervisory Control and Data Acquisition (SCADA) systems software and equipment which are not

associated with significant environmental issues.

3. LEGAL FRAMEWORKS

2 If significant negative impacts are identified in the screening process, then an EIA report will be required, following guidance of OP/BP 4.01.

Page 6: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

3

3.1. Vietnamese Legislations

The following Vietnamese legislations are applicable to the Project:

Environment Protection Law 52/2005/QH11 passed by the National Assembly dated on November

29, 2005, regulating responsibilities of individuals and organizations regarding environmental

protection.

Law on Forest Development and Protection No. 29/2004/QH11,

Law on Cultural Heritage No. 28/2001/QH10,

The Law on Water resources No. 08/1998/QH10 dated May 20, 1998.

Government Decree N0 80/2006/ND-CP dated August 9, 2006, by Vietnamese Government on

detail regulations and guidance on the implementation of some Articles of the Environment Law.

Decree 29/2011/NÐ-CP dated 18 April 2011 regarding regulations on strategic environmental

assessment, environmental impacts assessment and environmental protection commitments, and

Circular 26/2011/TT-BTNMT dated 18 July 2011 detailing some articles of that Decree.

Decree 106/2005/ND-CP dated August 17, 2005, on detailed regulations and guidance on

implementation of some Articles of the Law on Electricity related to safe protection of high

voltage networks.

Decree 81/2009/ND-CP dated October 12, 2009, on revision and addition of some Articles of

Decree 106/2005/ND-CP on detailed regulations and guidance on implementation of some Articles

of the Law on Electricity related to safe protection of high voltage networks.

Circular 12/2011/TT-BTNMT dated April 14, 2011, regarding the management of hazardous

wastes.

National Technical Regulations: QCVN01:2009/BYT - National technical regulations on quality of

drinking water; QCVN02:2009/BYT - National technical regulations on quality of domestic water;

QCVN08:2008/BTNMT - National technical regulations on quality of surface water;

QCVN09:2008/BTNMT - National technical regulations on quality of groundwater;

QCVN05:2009/BTNMT - Air quality – Standards for ambient air quality; QCVN06:2009/BTNMT

- Air quality – Maximum allowable concentration of hazardous substances in the ambient air.

EVN Guidance 2623/CV-EVN – KHCN&MT, dated 28 May 2007 regarding the management and

pollution prevention and exposure to PCBs.

3.2. World Bank Environmental Safeguard Policies

Environmental Assessment (OP/BP 4.01): Preliminary environmental screening has been carried out

by the World Bank Environmental Team based on the experiences of the other similar projects and the

list of the proposed subprojects furnished to the Bank by PCs. The impacts are likely to be site-

specific, not sensitive or irreversible, and in every case, mitigation measures can be designed and

implemented to reduce the negative impacts. Therefore, the Project has been proposed to be

Environmental Category B.

Due to their similar nature, the Environmental Guidelines of the Rural Distribution Project were

adapted for this project‟s Environmental Management Framework. The lessons learned from

implementation of the Rural Distribution Project and the updated Vietnam environmental regulations

have been taken into count. The Environmental Management Framework (EMF) sets out the

requirements and provides guidance for the preparation of environmental safeguard tools applicable to

Page 7: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

4

each subproject. As the subprojects are scattered over 44 provinces of Vietnam and their impacts

would be minor and sub-project specific, it is not proposed to carry out a stand-alone environmental

impact assessment. All Component 1 subprojects will be clearly defined and with safeguard

instruments prepared by the project appraisal. Safeguard documents for Component 2 subprojects will

be prepared in accordance with the guidelines provided in the EMF during project implementation.

Natural Habitats (OP/BP 4.04): Subprojects involve distribution system expansion and upgrading.

Rehabilitation of portions of the existing PC system, distribution lines and substations usually would

be along existing right-of-ways (ROW). System expansion, which involves the construction of new

lines, on the other hand, involves construction activities. The distribution lines or substations are

expected to take place along existing roads. There would be no natural habitats or critical natural

habitats along the existing or proposed works. The subprojects would not cause any significant loss or

degradation of any important natural habitats. Therefore, this policy is not triggered. All possible

efforts shall be made to avoid site selection in sensitive areas, which might cause impacts on natural

habitats. An exclusion list has been developed to exclude any subproject that could have significant

adverse impacts on natural habitats.

Forests (OP/BP 4.36): The project investment activities including distribution lines or substations are

expected to take place along existing roads or power lines and will not involve forests or their

management, protection or utilization. As a result, this policy is not triggered.

Pest Management (OP/BP 4.09): The project will not use herbicides or any other pesticides for right-

of-way vegetation maintenance, or chemical products for wood preservation for poles and associated

wood construction materials. Therefore, this policy is not triggered.

Physical Cultural Resources (OP/BP 4.11): There are not expected to be any impacts on cultural

property as the location of substations and design of the ROW will avoid all objects of known

archaeological, paleontological, historical, architectural, religious or cultural significance within the

project area. The policy is, therefore, not triggered. Nevertheless, chance find procedures are included

in the EMF that detail the steps and process that will be undertaken in case where objects of

historical/cultural values are discovered during construction phase.

Safety of Dams (OP/BP 4.37): No dams involved in this project.

Projects on International Waterways (OP/BP 7.50): This project is not located within international

waterways.

Projects in Disputed Areas (OP/BP 7.60): This project is not located in or near disputed areas.

4. ENVIRONMENTAL SCREENING

To avoid adverse environmental impacts which cannot be adequately mitigated by the Project, an

initial screening would be carried out to identify proposed subprojects that may cause serious impacts

which would not be easily mitigated with the project‟s current set of safeguard instruments, and

therefore not eligible for the Project financing. Any proposed subproject that can create significant loss

or damage to physical cultural resources, including sites having archeological (prehistoric),

paleontological, historical, religious, cultural and/or unique natural values will not be eligible for the

Project.

Page 8: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

5

The criteria for exclusion of subprojects have been developed with reference to Annex III of Decree

No.29/2011/ND-CP (listing the projects subject to appraisal by MONRE) as detailed below:

i) Subprojects that use land of national parks, natural reserves, nationally protected landscapes,

biosphere conservation sites;

ii) Subprojects that use land of world heritage, archaeological, paleontological, historical,

architectural, religious or cultural significance such as reserved areas recognized by traditional

local communities (e.g. sacred groves), etc; and

iii) Subprojects that cause conversion of natural forests including mangrove forests, watershed

protection forests, waves/wind shield forests, etc;

During the eligibility screening, careful selection of the possible subprojects should be made

considering the above-mentioned criteria. Once the subprojects are selected, the applicable Bank

safeguard policies should be determined for each subproject identified.

The Project Management Unit (PMU) of each PC, or consultants hired by the PMU, carries out

environmental screening, using the Rapid Environmental Assessment Checklist shown in Annex 1. For

most of the subprojects, screening should show no significant environmental problems and the sites

are eligible for inclusion in the Project. An EMP can be prepared and this is sufficient for the purpose

of environmental assessment (EA) of the projects (see Section 6).

5. POTENTIAL IMPACTS AND MITIGATION MEASURES

5.1. Potential Impacts

The overall impact of the project is positive and includes improved reliability and quality of PCs‟

distribution services (reduced frequency and duration of interruptions in electricity supply caused by

distribution), reduction of PCs losses, and reduction in consumption of targeted electricity consumers.

Potential negative impacts of the project include (i) land acquisition; (ii) tree cutting associated with

construction of substations and distribution lines; (iii) increased levels of dust, noise, and other

emissions from excavation activities, land clearing activities, material stockpiles, heavy equipment,

and truck traffic; (iv) construction site waste generation; (v) rural traffic disturbance and road damage

due to the transportation of building materials and equipment; (vi) soil erosion, sediment, and landslide

risks; (vii) unexploded ordnance risks; (viii) leakage or disposal of polychlorinated biphenyls (PCBs),

sulfur hexafluoride (SF6), and fuels; and (ix) health and safety issues for workers and community

during both construction and operation phases.

5.2. Mitigation Measures

Given that most of the key impacts will occur due to small civil works and transportation of

construction/waste materials, many of the potential negative impacts on physical, biological, and

social environment could be mitigated through a set of general measures that are typically applied to

most of construction projects to minimize impacts such as noise, dust, water, waste, etc. As part of the

Environmental Management Plan (EMP) for the project these general measures have been translated

into a standard environmental specification namely the Environmental Codes of Practice (ECOPs)

(Annex 9) and it will be applied to mitigate typical impacts of small civil works.

Page 9: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

6

The ECOP describes typical requirements to be undertaken by the contractors and supervised by the

construction supervision engineer during construction. They have been designed for this project to be

applicable to the range of small to medium sized civil works. The ECOPs will be included as an annex

in the bidding and contract documents during detailed design stage. Scope and content of the ECOPs is

as follows:

Scope: Construction activities for small works governed by these ECOPs are those whose impacts are

of limited extent, temporary and reversible, and readily managed with good construction practices.

The typical mitigation measures have been identified for the following aspects:

– Dust generation

– Air pollution

– Impacts from noise and vibration

– Water pollution

– Drainage and sedimentation control

– Management of stockpiles, quarries, and borrow pits

– Solid waste

– Management of dredged materials

– Disruption of vegetative covers and ecological resources

– Traffic management

– Interruption of utility services

– Restoration of affected areas

– Worker and public safety

– Communication with local communities

– Chance findings

However, there may be site-specific impacts that require site-specific measures both during

construction and operation stages such as site-specific mitigation measures for UXO clearance, for

impacts on irrigation canals, wiring of underground cable, etc. These measures are to be identified and

incorporated into the subproject EMPs.

6. PROCESS FOR PREPARATION OF EMP AND APPROVAL PROCESS

6.1 Overall Guidance for Developing the EMP

Considering the nature of the Project, one of the important steps is preparation of an appropriate EMP.

The integration of mitigation and environmental monitoring measures into project implementation and

operation is supported by clearly defining the environmental requirements within the EMP. The EMP

will include a brief description of the subproject; environmental and social background of the

subproject area, including a good map showing locations of the subproject and site specific activities

and/or process as appropriate; the potential impacts and proposed mitigation measures; and the

implementation and monitoring arrangement and budget. Public consultation is to be carried out as

part of the EMP preparation.

At a minimum, the EMP will include the standard ECOP. All site-specific impacts that are either not

covered in the general ECOPs or of an order of magnitude that require mitigation measures not

covered in the ECOPs, are described in more detail in the EMP. Activities to be carried out to mitigate

Page 10: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

7

impacts due to land acquisition and resettlement or impacts that relate to ethnic minorities are

presented separately (RP, RPF, EMDP) and these will be carried out and monitored separately. Annex

7 provides a sample content of the EMP as well as technical guidelines for EMP preparation,

consultation and information disclosure.

Subproject activities and associated impacts and mitigation measures are grouped into (i) new

installation and rehabilitation of distribution lines, (ii) new installation and rehabilitation of

substations, and (iii) small construction activities. This would make it easier for identifying alignment

and area impacts and mitigation measures. The table below provides specific occupational health and

safety in working with power lines and electric magnetic field.

Live Power Lines - Prevention and control measures associated with live power lines include: - Only trained and certified workers are allowed to install, maintain, or repair electrical equipment.

- Deactivating and properly grounding live power distribution lines before work is performed on, or in close

proximity, to the lines.

- Ensuring that live-wire work is conducted by trained workers with strict adherence to specific safety and

insulation standards. Qualified or trained employees working on transmission or distribution systems should

be able to achieve the following:

Distinguish live parts from other parts of the electrical system.

Determine the voltage of live parts.

Understand the minimum approach distances outlined for specific live line voltages.

Ensure proper use of special safety equipment and procedures when working near or on exposed

energized parts of an electrical system.

- Workers should not approach an exposed energized or conductive part even if properly trained unless:

The worker is properly insulated from the energized part with gloves or other approved insulation; or,

The energized part is properly insulated from the worker and any other conductive object; or,

The worker is properly isolated and insulated from any other conductive object (live-line work).

- Where maintenance and operation is required within minimum setback distances, specific training, safety

measures, personal safety devices, and other precautions should be defined in a health and safety plan.

(Recommended minimum safety setbacks for workers are as below:

o 2-15 kV: 0.6 m

o 15.1-35kV: 0.71 m

o 72.6-121 kV: 1.01 m

Working at height on poles and structures

Prevention and control measures for working at height include:

- Testing structures for integrity prior to undertaking work.

- Implementation of a fall protection program that includes training in climbing techniques and use of fall

protection measures; inspection, maintenance, and replacement of fall protection equipment; and rescue of

fall-arrested workers, among others;

- Installation of fixtures on tower components to facilitate the use of fall protection systems.

- Safety belts should be of not less than 16 millimeters (mm) two-in-one nylon or material of equivalent

strength. Rope safety belts should be replaced before signs of aging or fraying of fibers become evident.

- When operating power tools at height, workers should use a second (backup) safety strap.

- Signs and other obstructions should be removed from poles or structures prior to undertaking work.

- An approved tool bag should be used for raising or lowering tools or materials to workers on structures.

Electric and magnetic fields (EMF)

Occupational EMF exposure should be prevented or minimized through the preparation and implementation of

Page 11: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

8

an EMF safety program including the following components:

- Identification of potential exposure levels in the workplace.

- Training of workers in the identification of occupational EMF levels and hazards.

- Establishment and identification of safety zones to differentiate between work areas with expected elevated

EMF levels compared to those acceptable for public exposure, limiting access to high risk zones.

- Personal exposure monitoring equipment should be set to warn of exposure levels that are below

occupational exposure reference levels (e.g. 50 percent). Action plans to address occupational exposure may

include limiting exposure time through work rotation, increasing the distance between the source and the

worker, when feasible, or the use of shielding materials.

To ensure effective implementation of the EMP, the following actions will be carried out during the

implementation of the Project:

a) During detailed design and preparation of bidding contract documents

- During the detailed design of technical specifications and preparation of bidding and contract

documents, the technical design consultant will incorporate into these bidding and contractual

documents the parts of the ECOPs specific to that contract, as well as the specific measures

identified in the EMP.

- In preparing the bidding and contract documents, make an effort to ensure that the contractors

are aware of the safeguard obligation and commit to comply.

b) During Construction stage

The PMU will assign the Construction Supervising Consultant (CSC) and/or field engineer to be

responsible for supervision of safeguard performance of contractor on a daily basis. A generic Terms

of Reference (TOR) is provided in Annex 8. The CSC and/or field engineers will carry out, but not

limited to, the following tasks:

- Before the commencement of the construction, confirm that all compensation for land and

facilities are provided and relocation and/or land acquisition/donation has been completed.

- Closely supervise the implementation of safeguard measures throughout the construction period.

- Confirm the compliance with the agreed environmental plan and inspect any damages incurred

by the contractor. If necessary, prepare an order to compensate/restore the construction sites as

specified in the contracts. Contractor safeguard performance will be included in the subproject

progress report.

The annexes in this document provide detailed guidelines for preparing some key sections of a typical

EMP:

Annex 1: Rapid environmental assessment checklist

Annex 2: Environmental consultation summary

Annex 3: Environmental monitoring plan

Annex 4: Institutional arrangements for EMP implementation

Annex 5: Reporting procedures

Annex 6: Cost estimate

Annex 7: Guidance for Preparing EMP for Subprojects

Annex 8: TOR for Construction Supervision Consultant (CSC)

Page 12: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

9

Annex 9: Environmental Codes of Practice (ECOP)

6.2 Specific Guidance for PCBs Management

Polychlorinated Biphenyls (PCBs) were widely used as a dielectric fluid to provide electrical

insulation, although their use has been largely discontinued due to potential harmful effects on human

health and the environment. Under the DEP project, it is not allowed to use PCBs. However,

rehabilitation works of the Project may involve the replacement of old transformers containing PCBs.

At the time this Framework is prepared, official guidelines on the handling and management of PCB in

Vietnam is not yet available. The EVN Guidance no. 2623/CV-EVN – KHCN&MT, dated 28 May

2007, regarding the management and pollution prevention and exposure to PCBs will be used for the

project.

In no case liquid wastes containing PCBs are allowed to be discharged into water or sewer systems.

All of the equipment being replaced and liquid waste containing PCBs shall be stored in areas that

meet the following requirements:

Adequately roof and walls to prevent rainwater from reaching the stored PCBs.

Adequate flooring made of an impervious material such as cement concrete with a continuous,

6-inch high minimum curbing. The floor and curbing must provide containment volume of at

least two times or 25 percent of the internal volume of the largest PCBs item or container

stored, whichever is greater.

Warning signs shall be placed at storage area to prevent leakage or spillage.

No drain valves, floor drains, expansion joints, sewer lines, or other open areas that would

permit liquids to flow from the curbed area.

Facility should not be located below the 100-year floodwater elevation.

PCBs items and containers in the storage area must be inspected for leaks at least once every 30 days.

Removal of the equipment from the storage is not allowed unless test results confirm that PCB

concentration is below 5 ppm.

The equipment having PCB concentration greater than 5 ppm shall be stored safely until there is

official guidance from EVN regarding safe disposal of such equipment.

In cases where PCB leakage occurs, the following procedures shall be applied:

Any leaking PCBs items must be transferred to non-leaking containers.

Any spills or leaks must be cleaned up immediately using sorbents like sand.

PCBs contaminated area needs to be cleaned by using suitable solvents such as kerosene and

turpentine.

EVN and PCs shall ensure that during the implementation phase, GOV/EVN‟s legal updates on PCBs

handling management shall be timely incorporated into the Project‟s policy and practices.

6.3 Specific Guidance for Public consultation and Information Disclosure

The Bank‟s safeguard policies require the Client/PMUs to facilitate public consultation and

information disclosure. Accordingly, consultation with project affected people (PAPs) and local NGOs

is recommended for Category B projects.

Page 13: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

10

During the preparation of EMP document, public consultation must be carried out in a form

convenient to the local people (e.g. survey, meeting, leaflet, signboard etc.) and information on the

main findings of environmental impacts and proposed mitigation measures must be provided in the

local language understandable for the majority of the affected people. Records of feedback from public

consultation should be attached to final draft EMP while the main EMP should include a section

summarizing public concerns and suggestions. The EMP should clearly state that environmental

concerns and suggestions for environmental improvement made by the public have been incorporated.

It is required that EMPs include a summary table (see Annex 2) to show the number of meetings, the

place, the number of PAPs attended meetings.

The PCs should confirm with the Bank that copies of draft EMP (in Vietnamese) are displayed at the

subproject area accessible to the public and the time for such disclosure. The PCs should also confirm

the release of EMP for disclosure at the Vietnam Development Information Center (VDIC) in WB

Hanoi office, and in the Info Shop.

6.4 Institutional Arrangements for the EA Process

The responsibility of preparation of the subproject specific EIA/EPC/EMP documents is with the PMU

on behalf of its PC. The PMUs reviews the documents to ensure compliance with National

Environmental Guidelines and the World Bank's relevant Safeguard Policies. Thereafter, the EMP is

forwarded to the World Bank for review and clearance. The PMUs are also responsible for ensuring

close coordination with DPC/DONRE/MONRE during project preparation. PMUs will supervise the

preparation of EIA/EPC report until written approval by relevant environmental management authority is

granted.

Each subproject will be stand-alone, and will therefore require separate review of the safeguards issues

through preparation of EIAs/EPCs/EMPs. By appraisal, the EMPs of the first phase subprojects have

been reviewed by the Bank. Second phase subprojects will have EMPs prepared according to the

guidelines in the EMF, and will be individually appraised by the PMUs and EVN before being accepted

for financing with provisions for random review by the Bank.

The table below presents the environmental clearance process of the DEP project.

Table 1: Environmental Clearance Process

Steps Environmental Clearance Procedure

1 Basic investment report (feasibility study) submitted to PMUs and then to EVN

2 EIA/EPC are prepared by the PCs in accordance with Decree 29/2011/ND-CP dated 18

April 2011 and Circular 26/2011/TT-BTNMT dated 18 July 2011 guiding the

preparation of strategic environmental assessment, environmental impact assessment,

and environmental protection commitment. Public consultation on main findings of

EIA/EPC/EMP is conducted

3 Draft EIA/EPC are submitted to relevant Vietnamese authority for approval

4 Draft EMPs (and where necessary EIA or other documents) are submitted to WB for

comments

5 EMPs are revised taking into the Bank‟s comments

Page 14: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

11

6 WB provides clearance and No Objection letter to EMP

7 Disclosure of EMP locally at project sites and at Info Shop in Hanoi or in Washington

6.5. Implementation, Supervision, Monitoring, and Reporting

The overall responsibility for implementation of environmental safeguard policies rests with the PCs

as implementing agencies. EVN is responsible for overall coordinator and monitoring, as well for

training PMUs staff on environment management.

During Project implementation, the PMUs is responsible for its subprojects ensuring effective

implementation of safeguard measures (RAPs, EMDPs, EMPs/ECOP) in close consultation with local

authorities and local communities. The PMU will assign at least one full time staff (as the safeguard

focal point) to be responsible for forging effective implementation of RAP, EMDP, EMP/ECOP of the

subproject. During construction, The PMU will assign the Construction Supervising Consultant (CSC)

and/or field engineer to be responsibility for monitoring and supervision of contractor performance on

a daily basis. The results will be part of the subproject progress report and the safeguard focal point

will be responsible for ensuring proper documentation of safeguard activities.

The Bank will conduct regular safeguard supervision, monitoring, and post review both at the

subproject and Project levels.

6.6 Staffing Requirements and Capacity Building

As overall coordinator, EVN will ensure appointment of a project environmental staff. Together with

consultants, EVN‟s project environmental staff will provide training to the PMU‟s environmental staff

in environmental planning and programming process. Environmental staff will carry out spot-checks

during the course of project implementation to ensure that the procedures set out in this Framework are

being applied.

The project will be implemented by an existing PMU in each PC, which have experienced staff.

Except Hanoi PC Hanoi, the other four PCs have long working experience with the Bank since 1995

including on safeguard issues. As for Hanoi PC, though this is the first Bank‟s project, it has

experiences with projects funded by international donors, including ADB. EVN have experience in

implementation of several projects funded by the Bank and other donors. Additional training will be

provided to the PMU staff for the implementation of World Bank safeguard policies.

6.7 Consultation During EMF Preparation

Two public consultations were carried out in the process of preparing this EMF, one in September

2011 and the other in December 2011. Participants included staff of implementing PCs,

representatives of MoIT, EVN, and local consultants. Consultation with people and households

directly or indirectly affected by the Project, local authorities, central and local state agencies, and

mass organizations will be done at the subproject level. Opinions and concerns provided during the

consultations were taken into account in the preparation and finalization of the EMF.

6.8 Budget for EMF Implementation

The EVN will be responsible for overall coordination of the subproject implementation, including

coordination of safeguards implementation and safeguard training for the subproject staff.

Page 15: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

12

The cost for implementation of mitigation measures during construction, including consultation with

local communities, environmental monitoring by contractors, and compensation for damage (if any)

will be part of the subproject construction cost. The cost for supervision of contractor performance will

be part of the subproject supervision cost. The budget for safeguard training of staff will be part of the

project management cost.

Page 16: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

13

ANNEX 1 – Environmental Rapid Assessment Checklist

Sub-Project:

Province:

District:

Commune:

Screening Question Yes No Remarks

1. Project's sitting:

Is the Project site adjacent to or within any

of the following environmental sensitive

areas?

- In the case select "yes", describe detailed

information such as: name of historical

property, nature resource, nearest distance from

the sensitive area to the Project site etc.

Cultural heritage site

Protected areas such as National

Parks, Nature Reserves,

Bioconservation areas, bird yards,

mangrove forest etc.

Wetlands

Forests

Estuaries

Buffer zone of Protected areas

Rivers and reservoirs

- Name of main water bodies (rivers), lakes,

reservoirs and nearest distance to the Project

site

Canals and irrigation system - Assess the density of the canal system in the

Project's area

Agricultural land

2. Potential environmental impacts

Will the Project cause:

If select " yes", please describe and briefly

assess impact's level

Encroachment on historical/cultural areas

Encroachment on critical ecosystem (e.g.

sensitive or protected area, national park,

nature reserve etc....)

Disfiguration of landscape and increase

waste generation

Removal of vegetation cover or cut down of

trees resulted from clearance at the sub-

station and along ROW?

Change of surface water quality or water

flows

If select " yes", please list of main reasons

Increase water turbidity due to run-

Page 17: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

14

Screening Question Yes No Remarks

off and erosion

Waste water from camping sites is

directly discharged to the surface

water resources or not?

Construction waste is directly

discharged to the surface water or

not?

Increase the dust level? If select " yes", please list of main reasons

Increase noise and/or vibration? If select " yes", please list of main reasons

Permanent land acquisition If select " yes", please list of land area for

permanent acquisition, type of soils, and

purpose of acquisition

Temporary land acquisition If select " yes", please list of land area for

permanent acquisition, type of soils, and

purpose of acquisition, duration of acquisition

Resettlement of households? If yes, how

many households?

Would the resettlement site is

environmentally and/or culturally sensitive

If select “yes” briefly describe the potential

impacts

Is there any risk of disease dissemination

from construction workers to the local

peoples (and vice versa)?

- Estimated number of groups of workers to be

hired for project construction in the

commune/district

Is there any potential for conflict between

construction workers and local peoples (and

vice versa)?

Are explosive and hazardous chemicals used

within the Project?

- If select "yes", please list of these materials

In the past, there was any accident incurred

due to landmines or explosive materials

remaining from the war?

Will Project's construction cause disturbance

to the transportation in the Project's site?

- If select "yes", please assess the impact level:

+ Significant impact

+ Medium impact

+ Minor

Project's construction will cause any damage

to the existing local roads, bridges or other

rural infrastructures?

Will soil excavation during Project's

construction cause soil erosion?

- If select "yes", please assess the impact level:

+ Significant impact

+ Medium impact

+ Minor

Will Project need to open new access roads? - If select "yes", please briefly estimate number

of temporary access roads and their locations

Page 18: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

15

Screening Question Yes No Remarks

Will Project cause fragmentation of habitat of

flora and fauna?

- If select "yes", please describe

Will Project cause impact on air quality?

Will Project cause accident risks for workers

and community during construction phase?

Will Project generate hazardous wastes

including PCBs from the replacement of

transformers?

Will Project cause risk to safety and human

health (electric and magnetic fields, electric

shock etc.)?

If select “yes” ", please describe

Page 19: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

16

ANNEX 2 - Environmental Consultation Summary

No. Sub-Project Location where

Consultation took

place

Date and

Time

Number of

Participants

List of Local authority

and household

representatives

attended*

Summary of Issues or

concerns discussed/raised

*Attached a separate list of people consulted

ANNEX 3 – Environmental Monitoring Plan

Impacts Parameter to be monitored Where to monitor How is the

parameter to

be monitored

When is the parameter

to be

monitored/frequency

of measurements or

continuous

Cost Responsibility

Construction Phase

I. Effects on

Vegetation

Clearing technique and scope Along ROW Observation Weekly in the first

month, then monthly

Contractors

Supervisor of

PMU Removed vegetation disposal

method

At disposal site

II. Effects on

rural

Traffic

Road surface condition and traffic

density

Quantity, loads and intensity of

project vehicles/construction

plants used

Along transportation

route

Observation,

interview

locals

Weekly when materials

& equipment are

mobilized to the site

intensively, then

monthly

Contractors

Supervisor of

PMU

Community

Page 20: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

17

Impacts Parameter to be monitored Where to monitor How is the

parameter to

be monitored

When is the parameter

to be

monitored/frequency

of measurements or

continuous

Cost Responsibility

III. Effects on

runoff,

sedimentati

on and

erosion

Drainages, sedimentation traps

weather condition (season) , level

of vegetation clearance and slope

Within the sub-station

boundary, along ROW

, nearby water sources

and slops within

project areas

Observation During and after heavy

rain

Contractors

Supervisor of

PMU

IV. Air

Pollution

Tightness of truck bottom and

whether sand/soil on trucks are

covered properly

Check the uncovered spoils

Along transportation

route and nearest

house

Observation Before departure of

filled trucks, in hot, dry

and windy days

Contractors

Supervisor of

PMU

V. Noise Noise level generated from

construction plants and activities,

Time of the day when

materials/equipment are unloaded

or construction is going on

nearest house,

community centre

along the route

Listen and

interview

While construction

activities is generating

high noise level /when

there are complaints

Contractors

Supervisor of

PMU

VI. Sanitation Municipal and construction wastes

and disposal method

Drainage, camps and

waste disposal site

Observation Weekly and before

acceptance of works

Contractors

VII. Safety Briefing on workplace safety

regulations, availability of first aid

kits, storage of danger materials,

warning signboards,

At the sub-station,

camps, unfinished pole

foundation, wire

installation along road

Observation,

interview,

check site log

book

Contractors

Operation Phase

1. Electric and

Magnetic Field

Electric and Magnetic Field

Intensity

At house nearest to

ROW

Electro-

magnetic

meter

There are

report/complaints about

noise impacts

PCs

Community

2. Noise Noise level, distance to

complained household

house owned by

complainer

Noise

measurement

instrument

There are complaints PCs

3. Safety Frequency of inspection and

maintenance works

Fire fighting instruments equipped

at the administration

building and within the

sub-station

check log

book, plan,

observation

six-monthly or annually PCs

Page 21: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

18

ANNEX 4 – Institutional Arrangements for EMP Implementation

Role Responsibilities Organizati

on Project Owner - Ultimately responsible for overall project management, including

environmental management.

EVN, PCs

Environmental

Officer - Specific responsibility and point of contact for

environmental issues.

PMU

Project Implementation

and management

Agency

- Responsible for coordination and management of overall project implementation, including guiding and supervising implementation

of the EMP.

- Planning and implementation of environmental management

activities during construction

- Coordinating with other parties in relation to

environmental management activities.

- Carrying out internal monitoring and supervising

- Supervising and providing budget for monitoring activities.

- Reporting on environmental information to concerned parties

PMU

Project Operator - Responsible for operation of the project including operation stage environmental management and monitoring activities.

PCs

Consultant - Responsible for preparation of EMP documentation.

Construction

Supervision

consultant

- Responsible for supervision of civil works contractors during

construction, including implementation of environmental

management activities under the EMP

Supervisors of

PMU

Construction

Contractor

Responsible for construction works and following contractor specifications outlined in the EMP. This includes:

- Take actions to mitigate all potential negative impacts in line with the

objective described in the ECOP.

- Actively communicate with local residents and take actions to prevent

disturbance during construction.

- Ensure that at least a staff is assigned to monitor EMP compliance during

the preconstruction and construction periods.

- Ensure all the construction activities having sufficient documents from

the related organization.

- Ensure that all staff and workers understand the procedure and their tasks

in the environmental management program.

- Report to the PMU on any difficulties and their solutions

- Report to local authority and PMU if environmental accidents occur and

coordinate with agencies and keys stakeholders to resolve these issues

Contractor

chosen by

PMU

Page 22: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

19

ANNEX 5 – Reporting Procedures

Report Prepared by Submitted to Frequency of Reporting

1 Contractor to the Employer PMU Once before construction

commences and monthly thereafter

2 Construction Supervision consultant PMU Monthly

4 Community Monitoring (if available) PMU If any complains

5 Power Corporation EVN Six-monthly

6 EVN WB Six-monthly

ANNEX 6 – Cost Estimate

Activity Construction Phase Operation Phase

1 Implement Mitigation Measures* The costs are covered in

Contract with Construction

Contractors

The cost is covered in

production cost of the

provincial power service

2 Environmental monitoring during

construction phase by Construction

Supervisor*

3 Capacity Building

Etc.

Total Cost

* Costs of mitigation measures in construction phase and environmental monitoring by construction

supervisors are included in relevant construction/supervision contracts.

Page 23: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

20

ANNEX 7 - Guidance for Preparing EMP for Subprojects

This appendix is prepared as a technical guideline to provide the environmental specialists with the

tools to prepare the EMP report for different subprojects that require EMP report for submission to the

World Bank. Public consultation and public disclosure are also required by the World Bank and are

considered mandatory. They must be conducted during preparation of subproject specific EMP and

EIA/EPC (to be submitted to the Vietnamese relevant authorities).

I. Introduction

In the introduction, the consultant should provide a brief description of the objectives of the EMP; the

role of EMP, that is to summarize the environmental mitigation measures proposed in the subproject

EIA process; present monitoring and institutional measures to be considered during project

implementation and operation to avoid or control adverse environmental impacts; and to recommend

actions that are believed to be necessary for implementation of proposed measures. This section should

also provide a description of how it is related to the EMF and the subproject as a whole.

II. Policy, Regulations, and Institutional Frameworks

2.1 GoV’s environmental regulations

Provide a brief description (preferably in bullet form) of GOV regulations related to subproject EIA

and standards that have been applied to the proposed subproject.

2.2 WB’s safeguard policy

List the Bank safeguard policies that have been triggered by the proposed subproject.

III. Project Description

Provide a detailed, but to the point, description of subproject including a location map showing the

location of subproject in relation of the project area as well as details at the subproject level for the

reader who is not familiar with the project to have a better understanding of the subproject. It is

important to recognize that EMP is a stand-alone report and should be self contained.

IV. Environmental Background (Baseline data)

Provide significant information on the environmental background of the subproject as well as its

relation to the main project. Provide clear data on topography, water resources (surface and

groundwater), soil types, water flow direction, water quality, pollution level, vegetative cover, etc. It is

also important to provide a brief description of socioeconomic status in the subproject area and

whether there are any ethnic minorities who might be affected or benefited by the subproject activities.

V. Potential Impacts and Mitigation Measures

Using results of the completed safeguard Screening Checklist (Appendix 1) for the sub-project,

identify the potential positive and negative impacts of the subproject on biophysical and social

environment and state the appropriate mitigation measures. The impacts should be identified and

subdivided for pre-construction, construction, and implementation/operation stages. Using a ranking

Page 24: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

21

matrix should assist the one preparing the report and the reader to better understand the relationship

and relevance of the impacts and proposed mitigation measures for minimizing/preventing the effects

of subproject activities on the environment.

VI. Environmental Management Plan (EMP)

6.1. Mitigation measure: Describe in some detail the mitigation plan to be implemented. The proposed

EMP should include as a minimum, the mitigation measures to be implemented during different

phases of the subproject development (engineering design, pre-construction, construction and

implementation/operation). Details of relevant ECOP and monitoring should be provided as an annex

to the EMP report or included in the main text. The EMP should also clearly indicate the impacts,

proposed mitigation measures, who will be assigned to implement the proposed mitigation or

monitoring activities and who will be responsible to ensure the proposed mitigation and/monitoring

activities are actually implemented (responsible agency).

6.2. Environmental monitoring: Specify which issues and parameters to be monitored, where and

when and who to carry out the monitoring, frequency of monitoring and related costs. In this Project,

the contractor, construction supervisors, and environmental staff of the PMUs will be the key people

who directly carry out environmental monitoring in construction phase. Community and local

authorities are encouraged to be involved in monitoring activities. Use Annex 3 as reference for

preparing the Environmental Monitoring Plan.

VII. EMP Implementation Arrangement and Training Needs

In this chapter, the responsibilities and the required capacity of the responsible agency to carry out the

EMP activities should be clearly stated.

Responsibility for EMP implementation: Specify the responsibilities of: (i) Contractor / Construction

Supervisors / Local community and authorities; (ii) Power Corporations / DONRE and other relevant

authorities at provincial and district levels / EVN; and (iii) WB. Use Annex 4 as reference for

preparing the institutional arrangements for EMP implementation.

The performance of the tasks within the EMP includes:

o Implementing mitigation measures.

o Monitoring the implementation of mitigation measures in construction phase

o Carrying out environmental inspections.

o Coordinating activities during the implementation of EMP and ensure the cash flow for

operations.

o Organizing/attending training courses, seminar etc.

Capacity Building for EMP Implementation: If current capacity of the institutions identified for

carrying out the EMP related activities or the responsible authority are not adequate for full

implementation of the proposed mitigation and monitoring measures in the EMP, the training needs

should be clearly identified and the cost tables for training programs should be provided as well as

implementation schedule and the process to ensure EMP activities are fully integrated into subproject

activities. Propose training course, seminars, topics to be covered, timeframe, trainees and costs.

Page 25: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

22

Reporting Procedures: Specify the types of reports to be prepared, who responsible for preparing and

submitting the report, whom to submit to and frequency of reporting. Use Annex 5 as reference for

presenting the information in the EMP.

Cost Estimates: Estimate the costs for (i) implementing major mitigation measures; and (ii) training

activities. Use Annex 6 as reference for presenting the information in the EMP.

Notes: (i) Cost estimate for training activities should also cover venue renting, hiring trainers, training

document and handouts preparation, handouts, travel costs, accommodation if applicable, and per

diems for participants etc; (ii) Total estimated costs for EMP implementation (mitigations, training,

monitoring etc) must be included in the Project Total Estimated Cost prepared by the FS consultant.

VIII. Public Consultation and Information Disclosure

In this chapter, a summary of consultation activities with relation to the EMP at subproject level with

stakeholders and affected people should be provided, preferably in tabular form. The table should also

include a column to indicate the concerns raised, if any, and the responses to address the issues raised.

The dates and locations where the EMP will be disclosed should also be provided in this chapter. It is

recommended that table in Annex 2 is presented in the EMP to summarize the results of public

consultation.

Public Consultation. The WB requires that for project category B at least one consultation with the

local actors, including the community will be carried out. This consultation should provide

information on the following aspects: a) purposes of the project; b) results of the environmental

evaluation; and c) presentation of the complementary studies required in the case that they apply. The

results should be presented in the EMP report. Consultation through a community outreach or relations

program during implementation is considered a good practice to ensure that the potential negative

impacts and concerns are properly addressed during construction and operation of a project. Details on

consultation can be found in the guideline for consultation in investment lending (Consultations in

Investment Lending: Guidance Note, World Bank March 2010). Extensive consultation (many times,

in various forms) with affected population and ethnic minority are required when the activities involve

relocation, land acquisition, and ethnic minority.

Information disclosure. Disclosure of safeguard documents is required throughout the project cycle.

All the RAPs, EMDPs, and EMPs will be made available to the public in the local languages.

Disclosure of information in advance of at least 60 days before construction is considered a good

practice.

Attachments: (i) Maps – drawings; (ii) A copy of environmental certificated issued by local

environmental authority; (iii) Copies of some consultation meeting minutes including a list of people

participating in consultation meeting; (iv) Relevant Pictures and sketches.

Page 26: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

23

ANNEX 8 - TOR for Construction Supervision Consultant (CSC)

General

In order to prevent harm and nuisances on local communities, and to minimize the impacts on the

environment during the construction of the civil works under the Distribution Efficiency Project,

Environmental Code of Practices (ECOPs) and subproject EMP (if available) have been prepared and

should be adhered to the Contractors and his employees.

The Construction Supervision Consultant (CSC)) is to provide professional technical services (“the

Services”) to help ensure effective implementation of the ECOP and subproject EMPs.

Scope of Services:

The general services to be provided by the CSC are to inspect, monitor the construction activities to

ensure that mitigation measures adopted in the ECOPs/EMP are properly implemented, and that the

negative environmental impacts of the project are minimized.

On behalf of the PMU, the CSC will conduct the following tasks:

- Conduct regular site inspections;

- Review the status of implementation of environmental protection measures against the EMP and

contract documents;

- Review the effectiveness of environmental mitigation measures and project environmental

performance;

- As needed, review the environmental acceptability of the construction methodology (both

temporary and permanent works), relevant design plans and submissions. Where necessary, the

CSC shall seek and recommend the least environmental impact alternative in consultation with the

designer, the Contractor(s), and PMU;

- Verify the investigation results of any non-compliance of the environmental quality performance

and the effectiveness of corrective measures; and

- Provide regular feedback audit results to the contractor‟s Chief Engineer according to the

procedures of non-compliance in the EMP;

- Instruct the Contractor(s) to take remedial actions within a specified timeframe, and carry out

additional monitoring, if required, according to the contractual requirements and procedures in the

event of non-compliances or complaints;

- Instruct the Contractor(s) to take actions to reduce impacts and follow the required EMP

procedures in case of non-compliance / discrepancies identified;

- Instruct the Contractor(s) to stop activities which generate adverse impacts, and/or when the

Contractor(s) fails to implement the EMP requirements / remedial actions.

- For contracts that Site Environmental Management Plan (SEMP) are required, the CSC shall

provide the final review and recommend clearance of all Site Environmental plans which may

affect the environment. These include, but are not limited to: dredging areas, borrow pits and

disposal sites, worker‟s camp plans. The CSC will review and approve the SEMP presented by the

Contractors. Where these plans are found not to comply with the EMP, EIA or RAP, the CSC shall

work with the PMU and Contractor to establish a suitable solution.

Page 27: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

24

- Addressing Complaints: Complaints will be received by the Contractor‟s Site Office from local

residents with regard to environmental infractions such as noise, dust, traffic safety, etc. The

Contractor‟s Chief Engineer or his deputy, and the CSC shall be responsible for processing,

addressing or reaching solutions for complaints brought to them. The CSC shall be provided with

a copy of these complaints and shall confirm that they are properly addressed by the Contractors in

the same manner as incidents identified during site inspections.

- Certification for Monthly Payments: The CSC shall confirm the monthly payments for

environmentally related activities implemented by the Contractor.

- Reporting: the CSC shall prepare the following written reports:

o Bi-weekly report of non-compliance issues

o Summary monthly report covering key issues and findings from reviewing and

supervision activities

o At the end of the project the CSC shall prepare a final report summarizing the key

findings from their work, the number of infringements, resolutions, etc. as well as

advice and guidance for how such assignments should be conducted in the future.

Page 28: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

25

ANNEX 9:

Environmental Codes of Practice (ECOPs) for the Distribution Efficiency Project

The World Bank Operational Policy (OP) on Environmental Assessment (OP 4.01) requires

environmental assessment (EA) of Bank-financed projects to ensure they are environmentally sound

and sustainable. EA is a process of analyzing potential environmental risks and of the identification

and adoption of measures to avoid or mitigate such impacts.

As a part of EA, the Environmental Management Plan (EMP) is a safeguards instrument that is

typically used in many projects and which consists of information on and guidance for the process of

mitigating and managing adverse environmental impacts throughout project implementation.

Environmental codes of practice (ECOPs) are mitigation measures for generic impacts from project

activities during the construction phase and are intended to be included in the bidding documents as

requirements directed to the construction contractor. ECOPs are not a formally recognized World

Bank safeguards instrument but their use, as part of an EMP, is a convenient and effective way to

ensure that generic and typical construction impacts are adequately mitigated during project

implementation.

If impacts require site-specific mitigation measures that are not adequately covered in these generic

ECOPs, they must be addressed separately in the EMP. These ECOPs also do not cover impacts from

worker camps (assuming they would not generally be needed for small urban works projects), impacts

from large works (bridges, tunnels, big roads). Social impacts caused by involuntary resettlement or

involving ethnic minorities are addressed in other safeguard instruments. The ECOPs cover dredging

operations producing relatively small amounts of sludge, whilst very large amounts or seriously

contaminated sludge would need to be handled through a separate set of procedures outside of the

scope of these ECOPs.

MAIN ENVIRONMENTAL AND SOCIAL ISSUES DURING CIVIL WORKS CONSTRUCTION

Construction activities for small works governed by these ECOPS are those whose impacts are of

limited extent, temporary and reversible, and readily managed with good construction practices. The

environmental and social issues covered in this document are:

Dust generation

Air pollution

Impacts from noise and vibration

Water pollution

Drainage and sedimentation control

Management of stockpiles, quarries, and borrow pits

Solid waste

Chemical and hazardous wastes

Disruption of vegetative covers and ecological resources

Traffic management

Interruption of utility services

Restoration of affected areas

Page 29: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

26

Worker and public safety

Communication with local communities

Chance findings

VIETNAMESE LEGAL AND REGULATORY FRAMEWORK

There are a number of Government of Vietnam (GoV) regulations, standards, code of practices, etc.

related to environmental and safety aspects that are relevant to construction activities and

environmental quality. The principal ones related to issues covered by these ECOPs are listed below

(not an exhaustive list):

Vietnamese Environment Standards: including standards on sampling and sample preservation;

analysis methods; standards on quality of air, surface water, groundwater, soils, standards on

emission, waste water, standards on dumps, and standards on incinerators. These include:

(i) QCVN 05:2009/BTNMT: National technical regulation on Ambient Air Quality ;

(ii) QCVN 06:2009/BTNMT: National technical regulation on hazardous substances in

ambient air;

(iii) QCVN 08:2008/BTNMT – National technical regulation on quality of surface water

(iv) QCVN 09:2008/BTNMT: Water Quality: National Technical regulation on

underground water quality;

(v) QCVN 14:2008/BTNMT: National technical regulation on domestic wastewater

(vi) QCVN 03:2008/BTNMT: National technical regulation on the allowable limits of

heavy metals in the soils;

(vii) QCVN 26:2010/BTNMT: National Technical Regulation on Noise

(viii) QCVN 27:2010/BTNMT: National technical regulation on vibration

Basics for Safety/Construction: Location of the disposal sites and other use purposes shall be

agreed with the local authorities and all earth works shall comply with:

(i) Law on traffic and transportation No. 23/2008/QH12

(ii) Law on construction No. 16/2003/QH11

(iii) Decree No. 73/2010/ND-CP on administrative penalization security and society issues

(iv) Decree No. 12/2009/ND-CP on management of project

(v) Decree No. 59/ND-CP on management of solid waste

(vi) Decree No. 1338/NĐ-CP on technical guidelines for construction within weak

foundation area

(vii) Decree No. 22/2010/TT-BXD on regulation of construction safety;

(viii) Circular No. 12/2011/TT-BTNMT on management of hazardous substance

(ix) Decision No. 35/2005/QD-BGTVT on inspection of quality, technical safety and

environmental protection;

(x) Instruction No. 02 /2008/CT-BXD on safety and sanitation issues in construction

agencies

(xi) TCVN 5308-91: Technical regulation on safety in construction

(xii) TCVN 4447:1987: Earth works-Codes for construction

Page 30: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

27

(xiii) Air, noise, and vibration control requirements stipulated in the TCVN4087: 1985-(Use

of building plants-General requirements);

Chance find procedure

(i) Law on Cultural Heritage (2002)

(ii) Law on Cultural Heritage (2009) for supplementary and reformation

(iii) Decree No. 98/2010/ND-CP for supplementary and reformation

MONITORING AND REPORTING REQUIREMENTS

Non-compliance by the contractor could result in suspension of works, financial penalties, or other

penalties, as must be clearly spelled out in the EMP and in the contract.

Contractors are responsible for implementation of ECOPs. The responsibilities for monitoring ECOPs

implementation are typically shared between the contractor, the PMU, and the Construction

Supervision Consultant (CSC). The Contractor‟s Work Plan should incorporate the guidelines

provided in these ECOPs as well as the Environmental Management Plan (EMP) created for the sub-

project. The designated Technical Officer(s) and Safeguards Officer(s) of the PMUs are responsible

for supervising the adherence to the agreed EMP by the selected contractor(s). The World Bank may

periodically supervise implementation activities of Bank-financed projects.

At a minimum, the contractor should prepare a monthly report on adherence to ECOPs which should

be submitted to the CSC and to the PMU. Project-specific or contract-specific reporting requirements

are described in the EMP. CSC is responsible for monitoring overall environmental performance of the

project and submit to PMUs quarterly monitoring reports.

Page 31: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

28

ENVIRONMENTAL CODES OF PRACTICE (ECOPs)

ENVIRONMEN

TAL – SOCIAL

ISSUES

MITIGATION MEASURE VIETNAM

CODE/REGULATION

1. Dust

generation The Contractor is responsible for compliance with relevant Vietnamese legislation with respect to

ambient air quality.

The Contractor shall implement dust suppression measures (e.g. water spray vehicles, covering of

material stockpiles, etc.) as required;

Construction vehicles shall comply with speed limits and haul distances shall be minimized.

Material loads shall be suitably covered and secured during transportation to prevent the scattering of

soil, sand, materials or dust.

The Contractor shall be responsible for any clean-up resulting from the failure by his employees or

suppliers to property secure transported materials.

Exposed soil and material stockpiles shall be protected against wind erosion and the location of

stockpiles shall take into consideration the prevailing wind directions and locations of sensitive

receptors.

Dust masks should be used where dust levels are excessive.

- QCVN 05:

2009/BTNMT: National

technical regulation on

ambient air quality

2. Air

pollution All vehicles must comply with Vietnamese regulations controlling allowable emission limits of

exhaust gases.

Vehicles in Vietnam must undergo a regular emissions check and get certified named: “Certificate of

conformity from inspection of quality, technical safety and environmental protection” following

Decision No. 35/2005/QD-BGTVT.

There should be no burning of waste or construction materials or cleared vegetation on site.

Cement processing plants should be far from residential areas.

- TCVN 6438-2005: Road

vehicles Maximum

permitted emission limits

of exhaust gas.

- No. 35/2005/QD-

BGTVT on inspection of

quality, technical safety

and environmental

protection;

- QCVN

05:2009/BTNMT:

National technical

regulation on ambient air

Page 32: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

29

ENVIRONMEN

TAL – SOCIAL

ISSUES

MITIGATION MEASURE VIETNAM

CODE/REGULATION

quality

3. Impacts

from noise

and

vibration

The contractor is responsible for compliance with the relevant Vietnamese legislation with respect to

noise and vibration.

All vehicles must have appropriate “Certificate of conformity from inspection of quality, technical

safety and environmental protection” following Decision No. 35/2005/QD-BGTVT; to avoid

exceeding noise emission from poorly maintained machines.

When needed, measures to reduce noise to acceptable levels must be implemented and could include

silencers, mufflers, acoustically dampened panels or placement of noisy machines in acoustically

protected areas.

Avoiding or minimizing transportation though or material processing near community areas.

QCVN

26:2010/BTNMT:

National technical

regulation on noise

QCVN

27:2010/BTNMT:

National technical

regulation on vibration

4. Water

pollution The Contractor must be responsible for compliance with the relevant Vietnamese legislation relevant

to wastewater discharges into watercourses.

Portable or constructed hygienic toilets must be provided on site for construction workers. Wastewater

from toilets as well as kitchens, showers, sinks, etc. shall be discharged into a conservancy tank for

removal from the site or discharged into municipal sewerage systems; there should be no direct

discharges to any water body.

Wastewater over standards set by relevant Vietnam technical standards/regulations must be collected

in a conservancy tank and removed from site by licensed waste collectors.

Using techniques as berming or diversion during construction to limit the exposure of disturbed

sediments to moving water.

Before construction, all necessary wastewater disposal permits/licenses and/or wastewater disposal

contract have been obtained.

At completion of construction works, wastewater collection tanks and septic tanks shall be safely

disposed or effectively sealed off.

QCVN

09:2008/BTNMT:

National Technical

Standard on

underground water

Quality

QCVN

14:2008/BTNMT:

National technical

regulation on

domestic wastewater;

QCVN 24:

2009/BTNMT:

National technical

regulation on industrial

wastewater;

TCVN 7222: 2002:

General requirements

on centralized

wastewater treatment

Page 33: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

30

ENVIRONMEN

TAL – SOCIAL

ISSUES

MITIGATION MEASURE VIETNAM

CODE/REGULATION

plant;

5. Drainage

and

sedimentati

on control

The Contractor shall follow the detailed drainage design included in the construction plans, intended

to prevent storm water from causing local flooding or scouring slopes and areas of unprotected soil

resulting in heavy sediment loads affecting local watercourses.

Ensure drainage system is always maintained cleared of mud and other obstructions.

Areas of the site not disturbed by construction activities shall be maintained in their existing

conditions.

Earthworks, cuts, and fill slopes shall be properly maintained, in accordance with the construction

specifications, including measures such as installation of drains, use of plant cover.

To avoid sediment-laden runoff that could adversely impact watercourses, install sediment control

structures where needed to slow or redirect runoff and trap sediment until vegetation is established.

Sediment control structures could include windrows of logging slash, rock berms, sediment catchment

basins, straw bales, storm drain inlet protection systems, or brush fences.

Site de-watering and water diversions: In the case that construction activities require that work be

carried out within the watercourse (e.g. culvert or bridge crossing construction, retaining wall

construction, erosion protection works), the work area must be dewatered to provide for construction in

dry conditions. The sediment laden water pumped from the work area must be discharged to an

appropriate sediment control measure for treatment before re-release to the stream.

TCVN 4447:1987:

Earth works-Codes for

construction

Decree No.

22/2010/TT-BXD on

regulation of

construction safety

QCVN

08:2008/BTNMT –

National technical

regulation on quality

of surface water

6. Managemen

t of

stockpiles,

quarries,

and borrow

pits

Large scale borrow pits or stockpiles will need site-specific measures that go beyond those in these

ECOPs.

All locations to be used must be previously identified in the approved construction specifications.

Sensitive sites such as scenic spots, areas of natural habitat, areas near sensitive receptors, or areas

near water should be avoided.

An open ditch shall be built around the stockpile site to intercept wastewater.

Stockpile topsoil when first opening a borrow pit and use it later to restore the area to near natural

conditions.

If needed, disposal sites shall include a retaining wall.

If the need for new sites arises during construction, they must be pre-approved by the Construction

Engineer.

Page 34: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

31

ENVIRONMEN

TAL – SOCIAL

ISSUES

MITIGATION MEASURE VIETNAM

CODE/REGULATION

If landowners are affected by use of their areas for stockpiles or borrow pits, they must be included in

the project resettlement plan.

If access roads are needed, they must have been considered in the environmental assessment and

EMP.

7. Solid waste Before construction, a solid waste control procedure (storage, provision of bins, site clean-up

schedule, bin clean-out schedule, etc.) must be prepared by Contractors and it must be carefully

followed during construction activities.

Before construction, all necessary waste disposal permits or licenses must be obtained.

Measures shall be taken to reduce the potential for litter and negligent behavior with regard to the

disposal of all refuse. At all places of work, the Contractor shall provide litter bins, containers and

refuse collection facilities.

Solid waste may be temporarily stored on site in a designated area approved by the Construction

Supervision Consultant and relevant local authorities prior to collection and disposal through a

licensed waste collector, for example, URENCO in urban areas or local environment and sanitation

companies.

Waste storage containers shall be covered, tip-proof, weatherproof and scavenger proof.

No burning, on-site burying or dumping of solid waste shall occur.

Recyclable materials such as wooden plates for trench works, steel, scaffolding material, site holding,

packaging material, etc shall be collected and separated on-site from other waste sources for reuse, for

use as fill, or for sale.

If not removed off site, solid waste or construction debris shall be disposed of only at sites identified

and approved by the Construction Supervision Consultant and included in the solid waste plan. Under

no circumstances shall the contractor dispose of any material in environmentally sensitive areas, such

as in areas of natural habitat or in watercourses.

Decree No.

59/2007/ND-CP on

solid waste

management

8. Chemical or

hazardous

wastes

Chemical waste of any kind shall be disposed of at an approved appropriate landfill site and in

accordance with local legislative requirements. The Contractor shall obtain needed disposal

certificates.

The removal of asbestos-containing materials or other toxic substances shall be performed and

disposed of by specially trained and certified workers.

Decision No.

23/2006/QD-BTNMT

with list of hazardous

substance

Circular No.

12/2011/TT-BTNMT

Page 35: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

32

ENVIRONMEN

TAL – SOCIAL

ISSUES

MITIGATION MEASURE VIETNAM

CODE/REGULATION

Used oil and grease shall be removed from site and sold to an approved used oil recycling company.

Used oil, lubricants, cleaning materials, etc. from the maintenance of vehicles and machinery shall be

collected in holding tanks and removed from site by a specialized oil recycling company for disposal

at an approved hazardous waste site.

Used oil or oil-contaminated materials that could potentially contain PCBs shall be securely stored to

avoid any leakage or affecting workers. The local DONRE must be contacted for further guidance.

Unused or rejected tar or bituminous products shall be returned to the supplier‟s production plant.

Relevant agencies shall be promptly informed of any accidental spill or incident.

Store chemicals appropriately and with appropriate labeling.

Appropriate communication and training programs should be put in place to prepare workers to

recognize and respond to workplace chemical hazards.

Prepare and initiate a remedial action following any spill or incident. In this case, the contractor shall

provide a report explaining the reasons for the spill or incident, remedial action taken,

consequences/damage from the spill, and proposed corrective actions.

on management of

hazardous substance

9. Workforce,

Camps and

Site

Managemen

t

Workers„ camps will be located at least 200 m away from schools and health care centres and not be

located on steep slopes. The workforce shall be provided with safe, suitable and comfortable

accommodations and safe portable water. They have to be maintained in clean and sanitary conditions.

Site offices, camps, mixing stations, and workshops shall be located NOT within 100m from any

water courses, 500 meters of existing residential area.

Engineers and workers shall register their temporary residence with the local authority.

Allocate officer to be the Contractor„s Workplace Safety and Environment Officer responsible for

environmental and safety issues including training for workers.

Septic tank toilets must be provided at all construction camp areas where there will be concentration

of labor.

First aid boxes shall be provided in each construction camp site.

10. Disruption

of

vegetative

cover and

The Contractor shall prepare a Clearance, Revegetation and Restoration Management Plan for prior

approval by the Construction Engineer, following relevant regulations. The Clearance Plan shall be

approved by Construction Supervision Consultant and followed strictly by contractor. Areas to be

Law on Environment

protection No.

52/2005/QH11

Page 36: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

33

ENVIRONMEN

TAL – SOCIAL

ISSUES

MITIGATION MEASURE VIETNAM

CODE/REGULATION

ecological

resources

cleared should be minimized as much as possible.

Site clearance in a forested area is subject to permission from Department of Agriculture and Rural

Development.

The Contractor shall remove topsoil from all areas where topsoil will be impacted on by rehabilitation

activities, including temporary activities such as storage and stockpiling, etc; the stripped topsoil shall

be stockpiled in areas agreed with the Construction Supervision Consultant for later use in re-

vegetation and shall be adequately protected.

The application of chemicals for vegetation clearing is not permitted.

Prohibit cutting of any tree unless explicitly authorized in the vegetation clearing plan.

When needed, erect temporary protective fencing to efficiently protect the preserved trees before

commencement of any works within the site.

No area of potential importance as an ecological resource should be disturbed unless there is prior

authorization from CSC, who should consult with PMUs, and the relevant local authorities. This could

include areas of breeding or feeding of birds or animals, fish spawning areas, or any area that is

protected as a green space.

The Contractor shall ensure that no hunting, trapping shooting, poisoning of fauna takes place.

11. Traffic

managemen

t

Before construction, carry out consultations with local government and community and with traffic

police.

Significant increases in number of vehicle trips must be covered in a construction plan previously

approved. Routing, especially of heavy vehicles, needs to take into account sensitive sites such as

schools, hospitals, and markets.

Installation of lighting at night must be done if this is necessary to ensure safe traffic circulation.

Place signs around the construction areas to facilitate traffic movement, provide directions to various

components of the works, and provide safety advice and warning.

Employing safe traffic control measures, including road/rivers/canal signs and flag persons to warn of

dangerous conditions.

Avoid material transportation for construction during rush hour.

Passageways for pedestrians and vehicles within and outside construction areas should be segregated

and provide for easy, safe, and appropriate access. Signpost shall be installed appropriately in both

Law on traffic and

transportation No.

23/2008/QH12

Law on construction

No. 16/2003/QH11

Decree No.

22/2010/TT-BXD on

regulation of

construction safety

Page 37: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

34

ENVIRONMEN

TAL – SOCIAL

ISSUES

MITIGATION MEASURE VIETNAM

CODE/REGULATION

water-ways and roads where necessary.

12. Interruptio

n of utility

services

Planned and unplanned interruptions to water, gas, power, internet services: the Contractor must

undertake prior consultation and contingency planning with local authorities about the consequences

of a particular service failure or disconnection.

Coordinate with relevant utility providers to establish appropriate construction schedules.

Provide information to affected households on working schedules as well as planned disruptions (at

least 5 days in advance).

Interruptions of water supply to agricultural areas must also be avoided.

The contractor should ensure alternative water supply to affected residents in the event of disruptions

lasting more than one day.

Any damages to existing utility systems of cable shall be reported to authorities and repaired as soon as

possible.

Decree No. 73/2010/ND-

CP on administrative

penalization security and

society issues

13. Restoration

of affected

areas

Cleared areas such as borrow pits which are no longer in use, disposal areas, site facilities, workers‟

camps, stockpiles areas, working platforms and any areas temporarily occupied during construction of

the project works shall be restored using landscaping, adequate drainage and revegetation.

Start revegetation at the earliest opportunity. Appropriate local native species of vegetation shall be

selected for the planting and restoration of the natural landforms.

Spoil heaps and excavated slopes shall be re-profiled to stable batters, and grassed to prevent erosion.

All affected areas shall be landscaped and any necessary remedial works shall be undertaken without

delay, including green-spacing, roads, bridges and other existing works.

Trees shall be planted at exposed land and on slopes to prevent or reduce land collapse and keep

stability of slopes.

Soil contaminated with chemicals or hazardous substances shall be removed and transported and

buried in waste disposal areas.

Restore all damaged road and bridges caused by project activities.

Law on Environment

protection No.

52/2005/QH11

14. Worker and

public

Safety

Contractor shall comply with all Vietnamese regulations regarding worker safety.

Prepare and implement action plan to cope with risk and emergency.

Preparation of emergency aid service at construction site.

Decree No.

22/2010/TT-BXD on

regulation of

construction safety

Page 38: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

35

ENVIRONMEN

TAL – SOCIAL

ISSUES

MITIGATION MEASURE VIETNAM

CODE/REGULATION

Training workers on occupational safety regulations.

If blasting is to be used, additional mitigation measures and safety precautions must be outlined in the

EMP.

Ensure that ear pieces are provided to and used by workers who must use noisy machines such as

piling, explosion, mixing, etc., for noise control and workers protection.

During demolition of existing infrastructure, workers and the general public must be protected from

falling debris by measures such as chutes, traffic control, and use of restricted access zones.

Install fences, barriers, dangerous warning/prohibition site around the construction area which

showing potential danger to public people (such as unfinished power pole foundation, high risk

electrical shock areas, etc.).

The contractor shall provide safety measures as installation of fences, barriers warning signs, lighting

system against traffic accidents as well as other risk to people and sensitive areas.

If previous assessments indicate there could be unexploded ordnance (UXO), clearance must be done

by qualified personnel and as per detailed plans approved by the Construction Engineer.

Instruction No. 02

/2008/CT-BXD on

safety and sanitation

issues in construction

agencies

TCVN 5308-91:

Technical regulation

on safety in

construction

Decision No.

96/2008/QD-TTg on

clearance of UXO.

15. Communica

tion with

local

communitie

s

Maintain open communications with the local government and concerned communities; the contractor

shall coordinate with local authorities (leaders of local wards or communes, leader of villages) for

agreed schedules of construction activities at areas nearby sensitive places or at sensitive times (e.g.,

religious festival days).

Copies in Vietnamese of these ECOPs and of other relevant environmental safeguard documents shall

be made available to local communities and to workers at the site.

Reduced playground space, loss of playing fields and car parking: The loss of amenities during the

construction process is often an unavoidable source of inconvenience to users in sensitive areas.

However, early consultation with those affected, provides the opportunity to investigate and

implement alternatives.

Disseminate project information to affected parties (for example local authority, enterprises and

affected households, etc) through community meetings before construction commencement.

Provide a community relations contact from whom interested parties can receive information on site

activities, project status and project implementation results.

Provide all information, especially technical findings, in a language that is understandable to the

Decree No.

73/2010/ND-CP on

administrative

penalization security

and society issues

Page 39: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

36

ENVIRONMEN

TAL – SOCIAL

ISSUES

MITIGATION MEASURE VIETNAM

CODE/REGULATION

general public and in a form of useful to interested citizens and elected officials through the

preparation of fact sheets and news release, when major findings become available during project

phase.

Monitor community concerns and information requirements as the project progresses;

Respond to telephone inquiries and written correspondence in a timely and accurate manner.

Inform local residents about construction and work schedules, interruption of services, traffic detour

routes and provisional bus routes, blasting and demolition, as appropriate.

Provide technical documents and drawings to PC‟s community, especially a sketch of the construction

area and the EMP of the construction site.

Notification boards shall be erected at all construction sites providing information about the project, as

well as contact information about the site managers, environmental staff, health and safety staff,

telephone numbers and other contact information so that any affected people can have the channel to

voice their concerns and suggestions.

16. Chance find

procedures If the Contractor discovers archeological sites, historical sites, remains and objects, including graveyards

and/or individual graves during excavation or construction, the Contractor shall:

Stop the construction activities in the area of the chance find.

Delineate the discovered site or area.

Secure the site to prevent any damage or loss of removable objects. In cases of removable antiquities

or sensitive remains, a night guard shall be arranged until the responsible local authorities or the

Department of Culture and Information takes over.

Notify the Construction Supervision Consultant who in turn will notify responsible local or national

authorities in charge of the Cultural Property of Viet Nam (within 24 hours or less).

Relevant local or national authorities would be in charge of protecting and preserving the site before

deciding on subsequent appropriate procedures. This would require a preliminary evaluation of the

findings to be performed. The significance and importance of the findings should be assessed

according to the various criteria relevant to cultural heritage; those include the aesthetic, historic,

scientific or research, social and economic values.

Decisions on how to handle the finding shall be taken by the responsible authorities. This could

include changes in the layout (such as when finding an irremovable remain of cultural or

Law on Cultural

Heritage (2002)

Law on Cultural

Heritage (2009) for

supplementary and

reformation

Decree No.

98/2010/ND-CP for

supplementary and

reformation

Page 40: ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam ... · PDF fileSOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK For Vietnam Distribution Efficiency

37

ENVIRONMEN

TAL – SOCIAL

ISSUES

MITIGATION MEASURE VIETNAM

CODE/REGULATION

archeological importance) conservation, preservation, restoration and salvage.

If the cultural sites and/or relics are of high value and site preservation is recommended by the

professionals and required by the cultural relics authority, the Project‟s Owner will need to make

necessary design changes to accommodate the request and preserve the site.

Decisions concerning the management of the finding shall be communicated in writing by relevant

authorities.

Construction works could resume only after permission is granted from the responsible local

authorities concerning safeguard of the heritage.