Environmental Monitoring Report - No. 1
Project Number: 39153 August 2009
PRC: Chongqing-Lichuan Railway Development Project
Prepared by: Beijing AOSIS Environmental Protection Technology Co., Ltd.
For: Ministry of Railways (MOR)
This report has been submitted to ADB by the Ministry of Railways and is made publicly available in accordance with ADB’s public communications policy (2005). It does not necessarily reflect the views of ADB.
New Project Developed with Loan from
Asian Development Bank
Chongqing-Lichuan Railway
Environment Monitoring Report
Beijing OASIS Environmental Protection Technology Co., Ltd.
August 2009
Table of Contents
1. FOREWORD ...................................................................................................................................... 1
1.1 PROJECT INTRODUCTION ................................................................................................................. 1
1.2 OBJECTIVES ..................................................................................................................................... 3
1.3 MONITORING CONTENTS ................................................................................................................. 4
2. PROJECT PROGRESS ..................................................................................................................... 4
2.1 PROJECT IMPLEMENTATION UNITS, CONTRACTORS AND CONSTRUCTION SUPERVISION
COMPANIES OF CHONGQING-LICHUAN RAILWAY .................................................................................. 4
2.2 PROJECT PROGRESS ...................................................................................................................... 5
3. ENVIRONMENTAL CONTROL ..................................................................................................... 7
3.1 ENVIRONMENTAL CONTROL SYSTEM .............................................................................................. 7
3.2 DAILY ENVIRONMENTAL MONITORING SYSTEM .............................................................................. 9
4. PRE-JOB TRAINING ON ENVIRONMENTAL PROTECTION ............................................... 10
5. SUPERVISION AND INSPECTION OF AFFECTED POINTS.................................................. 12
5.1 IMPLEMENTATION STATUS OF ENVIRONMENTAL PROTECTION FOR EACH BID SECTION ................. 13
5.2 RESULTS AND ANALYSIS ................................................................................................................ 32
6. POPULARIZATION-WORTHY MEASURES AS WELL AS PROBLEMS AND SUGGESTIONS ................................................................................................................................... 33
6.1 POPULARIZATION-WORTHY MEASURES ......................................................................................... 33
6.2 EXISTING PROBLEMS AND IMPROVEMENT SUGGESTIONS .............................................................. 33
List of Photos Photo 1: Training on environmental monitoring Photo 2: Construction roads for Paihuadong tunnel under China Railway 12th Bureau Group
Co., Ltd. Photo 3: Construction site of Paihuadong tunnel under China Railway 12th Bureau Group Co.,
Ltd. Photo 4: Slope of construction site of Paihuadong tunnel under China Railway 12th Bureau
Group Co., Ltd. (absence of protection) Photo 5: Guarantee system diagram of environmental protection and water & soil reservation
by China Railway 12th Bureau Group Co., Ltd. Photo 6: Construction site of mixing station under China Railway 12th Bureau Group Co., Ltd. Photo 7: Watering cart of China Railway 11th Bureau Group Co., Ltd. Photo 8: Sedimentation tank for sewage from mixing station at Changshou North under China
Railway 11th Bureau Group Co., Ltd.(messy) Photo 9: Construction site of mixing station at Changshou North under China Railway 11th
Bureau Group Co., Ltd.(messy) Photo 10: Construction site of Huangcaoshan tunnel under China Railway 11th Bureau Group
Co., Ltd. Photo 11: Spoil from Huangcaoshan tunnel under China Railway 11th Bureau Group Co., Ltd.
(absence of protection) Photo 12: Garbage tanks at the construction site of Huangcaoshan tunnel under China Railway
11th Bureau Group Co., Ltd. Photo 13: Protection measures on oil penetration from air compressor at the construction site of
China Railway 11th Bureau Group Co., Ltd. Photo 14: Sedimentation tank for slurry from drilling pile construction under China Railway
11th Bureau Group Co., Ltd. Photo 15: Construction of 9# pier foundation of Hanjiatuo major bridge under China Zhongtie
Major Bridge Engineering Group Co., Ltd. Photo 16: Spoil protection for 22# pier of Caijiagou Super-major bridge under China Zhongtie
Major Bridge Engineering Group Co., Ltd. Photo 17: Construction site of Jianfengding tunnel under China Zhongtie Major Bridge
Engineering Group Co., Ltd. Photo 18: Sedimentation tank for sewage from Shijiapo tunnel under China Zhongtie Major
Bridge Engineering Group Co., Ltd. Photo 19: Garbage tanks at the construction site of Jianfengding tunnel under China Zhongtie
Major Bridge Engineering Group Co., Ltd. Photo 20: Construction roads for Shijiapo tunnel under China Zhongtie Major Bridge
Engineering Group Co., Ltd. Photo 21: Spoil from Fangdoushan tunnel under China Railway Tunnel Group Co., Ltd.
(absence of protection) Photo 22: Temporary protection for spoil from Fangdoushan tunnel under China Railway Tunnel
Group Co., Ltd.
2
Photo 23: Sedimentation tank for sewage from Fangdoushan tunnel under China Railway Tunnel Group Co., Ltd.
Photo 24: Construction roads of China Railway Tunnel Group Co., Ltd. Photo 25: Billboard for environmental protection of China Railway Tunnel Group Co., Ltd. Photo 26: Sedimentation tank for sewage from Guanyinyan tunnel under China Railway Tunnel
Group Co., Ltd. Photo 27: Construction site of Wanshoushan tunnel under China Railway 18th Bureau Group
Co., Ltd. Photo 28: Garbage tanks at the construction site of China Railway 18th Bureau Group Co., Ltd. Photo 29: Sedimentation tank for sewage from Wanshoushan tunnel under China Railway 18th
Bureau Group Co., Ltd. Photo 30: Billboard for environmental protection of China Railway 18th Bureau Group Co., Ltd. Photo 31: Side slope protection along the entrance to 1# transverse gallery of Wanshoushan
under China Railway 18th Bureau Group Co., Ltd. Photo 32: Office at the construction camp of China Railway 18th Bureau Group Co., Ltd. Photo 33: Living quarter at the construction camp of China Railway 18th Bureau Group Co.,
Ltd. Photo 34: Billboard for environmental control system of China Railway No. 5 Engineering
Group Co., Ltd. Photo 35: Billboard for environmental initiatives of pollution prevention and discharge control
by China Railway No. 5 Engineering Group Co., Ltd. Photo 36: Afforestation of construction camp of China Railway No. 5 Engineering Group Co.,
Ltd. Photo 37: Sedimentation tank for sewage from Dutingshan tunnel under China Railway No. 5
Engineering Group Co., Ltd. Photo 38: Side slope protection at the construction site of Dutingshan tunnel under China
Railway No. 5 Engineering Group Co., Ltd. Photo 39: Spoil ground for Dutingshan tunnel under China Railway No. 5 Engineering Group
Co., Ltd. (retaining wall under construction) Photo 40: Categorized collection of garbage at the construction camp of China Railway No. 5
Engineering Group Co., Ltd. Photo 41 Construction camp of China Railway 12th Bureau Group Co., Ltd. Photo 42 Water sprinkling at the construction site of China Railway 12th Bureau Group Co.,
Ltd.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 1
1. Foreword
1.1 Project Introduction
1.1.1 Basis of Preparation
1. Invitation for bid for implementation of monitoring project for environmental impact assessment of the new project of Chongqing-Lichuan Railway developed with the loan from Asian Development Bank (September 2008);
2. Tender document for Implementation of monitoring project for environmental management program of the new project of Chongqing-Lichuan Railway developed with the loan from Asian Development Bank (Beijing OASIS Environmental Protection Technology Co., Ltd. , September 2008);
3. Letter of Acceptance for the environmental monitoring project of Chongqing-Lichuan Railway from Foreign Capital Utilization and Technology Import Center of Ministry of Railways (December 22, 2008);
4. Environmental impact assessment report (EIA report) on the new project of Chongqing-Lichuan railway (China Railway Eryuan Engineering Group Co., Ltd., December, 2007);
5. Reply to EIA report on the New Project of Chongqing-Lichuan Railway from Ministry of Environmental Protection (No. 21 document for environmental review in 2008);
6. Opinions from Preliminary Review of EIA Report on the New Project of Chongqing-Lichuan Railway from Ministry of Railways (No. 1 for letter from railway plan in 2008).
1.1.2 Direction of Railway and Main Technical Standards
Situated in Chongqing Municipality and Enshi Autonomous Prefecture of Hubei province, newly-built Chongqing-Lichuan Railway starts in the west from Chongqing North Station in Yubei District, Chongqing, goes eastward through such administration areas in Chongqing municipality as Jiangbei District, Changshou District, Fuling District, Fengdu County and Shizhu County and ends at Lichuan city, Enshi, Hubei. The 259.5 km-long railway line and Yichang-Wanzhou railway under way link up at Liangwu Station. The line is the west section of Shanghai-Wuhan-Chengdu Railway Express Passageway in the Long and Medium-Term Planning for China's Highway Construction, the most important transverse railway passageway connecting China’s East, Middle and West, starting from Shanghai, through Nanjing, Hefei, Wuhan, Yichuan, Chongqing to Chengdu, crossing 4 provinces (Jiangsu, Anhui, Hubei and Sishuan) and 2 municipalities (Shanghai and Chongqing).
The construction period of this project is 5 years (initiated from 2008, and completed in 2013), with the total investment for this project is RMB 26.183 billion yuan, and design short-term stage shall be in 2020, and 2030 for long-term stage.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 2
The main technical standards for the main line of Chongqing-Lichuan railway:
Grade of railway: State railway, grade one; Number of main lines: double-line railway Target speed of passenger train: 200km/h The minimum radius of curve: 3500m Traction mode: Electric Traction mass: 4000t Track type With ballasted bed; the jointed track is adopted for truck road
diversion, with jointless track for the rest in the hub of Chongqing.
1.1.3 Main Engineering Contents
Along the whole Chongqing-Lichuan line, there are 118 new-built bridges totaling 48386.4 linear meters; 222 culverts with 8108 linear meters in length and 60 tunnels with total length of 166,360 m. Therefore, the overall length of bridges and tunnels is calculated as 214.7 km, accounting for 82.7% of the whole line.
The total volume of earth and stone for the whole line is 5901.1×104 m3 cubic meters, among which, 5425.2 ×104 m3 cubic meters for excavation, 475.7×104 m3 cubic meters for filling and 4967.4×104 m3 for spoil. 93 spoil grounds have been arranged.
7 new railway stations will be built including Miaoxian North Station, Changshou North Station, Fuling North Station, Fengdu Station, Shizhu Station, Shaziguan Station and Liangwu Station; and Chongqing North Station will be expanded along the whole line.
Permanent/temporary occupation of land is 623.7 hm2 and 579.0 hm2 respectively along the line.
New storage and departure yard for MU train will be built in North Chongqing. 16 storage and departure sidings, production and living facilities like train’s finish cleaning, vacuum drainage, signal, comprehensive operation and apartments of train crew will be provided in the near future.
Passenger Train Technology Preparation Facility at Chongqing North Station will be reconstructed.
7 new traction substations will be built including Miaoxian North Station, Changshou North Station, Fuling North Station, Fengdu Station, Shizhu Station, Shaziguan Station and Daxikou Station; and the existing traction substation at Chongqing North Station will be rebuilt along the whole line.
The floor area of the buildings along the line is 127, 920 m2, of which that of houses for living is 2550 m2, and supporting facilities for production and living including water supply and drainage, heating system and air conditioner.
Newly-built roads for vehicle transport is 139 km, and reconstructed local road is 255 km. There are 1 Beam Fabricated Factory, 4 Concrete Mixing Plants, 4 Material Plants and 4 temporary wharves.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 3
1.1.3 Characteristics of This Project
Chongqing-Lichuan railway line is situated in the parallel mountain ridges and valleys of the transition zone from the northeastern foot of Yungui Plateau to the eastern edge of Sichuan Basin, with a sharply undulating terrain, crossing hill area, low mountain area, middle mountain area and middle mountain haystack area along the whole line. Land along the line is predominantly used as cropland and forestland, with high forest coverage rate and abundant rainfall. Trees will be cut down during the construction, disturbing the native vegetation. The newly-built and reconstructed roads for transportation is 494 km, particularly paying more attention to water and soil loss caused by temporary works in the mountainous area like new construction roads and camps. There are new 60 tunnels along the whole line, totaling 166,360 m in length. The construction of some tunnels in the karst development region is likely to lead to water-leaking and loss of surface water which could exert influence over farmland irrigation, vegetation growth and domestic water of local residents. Therefore, the monitoring on the top of lava tunnel and surface water level fluctuation nearby shall be strengthened throughout the entire construction period and actions shall be taken to prevent the loss of surface water from affecting production and daily life if necessary . The total spoil is 4967.4 × 104m3, of which spoil from tunnel is massive, up to 3318.7× 104m3, accounting for 67% of the total. The establishment and protection of spoil grounds is the key to reduce water and soil loss and protect the ecological environment; in particular, ones in the deep slopes and clough are important; otherwise fragments of stones would slide down due to improper setting and protection in the storm seasons causing river blockage, farmland flood or other natural disasters. There are 118 newly-built bridges along the line with the total length of 48386.4 linear meters. Thereinto Qingxi Yangtze River Major Bridge (Renamed as “Hanjiatuo Yangtze River Major Bridge”) is in the passage for fish migration in Yangtze river basin; nursery ground and spawning ground for fish are in the upstream and downstream of the bridge site. Longxihe Super-major Bridge is located in the upstream of Level II Natural Preservation Zone at the Water intake of Miaoshan Water Plant, Changshou County. Effect on the water quality of the river and fish spawning by the construction of in-water piers and measures shall be focused on during the bridge construction along the whole line. Through Yunfengshan Forest Park in Chongqing in the form of tunnels, bridges and cuttings, and through City-level Forest Park in Nanmuyuan in the form of tunnels, near Xingdoushan Natural-level Natural Preservations Zone and Baiyan Scenic Spot, Zhangguan, Chongqing municipality, the construction of Chongqing-Lichuan railway will have an effect over local ecological environment in these natural preservation zones. Ancient trees thrive at both sides of the line; therefore actions should be taken to protect them. Note: Data of engineering volume referred in the section is the data in feasibility study.
1.2 Objectives
Based on design and EIA of project, this monitoring report is to check the implementation status of environmental protection measures during the construction period of the project, find the existing problems and provide the solutions. Actually, it is a supplement to the environmental impact assessment of the project and the monitoring of implementation of environmental protection measures. It reflects the implementation status of environmental protection work on the construction site during the construction activities to confirm whether the relevant rules and regulations on environmental protection have been satisfied and the requirements of Ministry of Railways and Asian Development Bank have been met. Speaking more accurately, this report is to:
confirm whether the environmental impacts caused in the construction period conforms to those environmental problems in the EIA report;
check the implementation status of environmental protection measures in the EIA report; identify and find out the unanticipated environmental problems and put forward the
solutions;
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 4
Report the environmental protection work on this project to Ministry of Railways, Asian Development Bank and the competent authorities.
1.3 Monitoring Contents The environmental protection work on Chongqing-Lichuan railway shall be undertaken by Beijing OASIS Environmental Protection Technology Co., Ltd. (hereinafter referred simply to as “Beijing OASIS”). The service range shall cover the whole Chongqing-Lichuan railway line. On the basis of the environmental monitoring in the whole construction period for the whole line and in two years after the completion and operation of this project as well as the on-site survey and various monitoring data collected biannually in the construction period and annually within two years after completion of this project, the environmental monitoring report (both Chinese and English versions) shall be submitted to Foreign Capital Utilization and Technology Import Center of Ministry of Railways, Chongqing-Lichuan Railway Construction Co., Ltd., Department of Development Plan of Ministry of Railways and Asian Development Bank. The monitoring report shall include the following contents:
Impacts on the ecological environment from the construction of stations, tunnels, bridges and roadbeds inside the key ecological environmental protection zones such as the natural preservation zones, the scenic spots etc. as well as the recovery and treatment measures;
Arrangement, protection, reclamation and afforestation measures for the spoil ground, impacts on the water and soil conservation facilities, and construction’s disturbance of vegetation as well as the recovery and treatment measures;
Impacts on the ambient environment from the tunnel construction and the implementation status of preventive measures;
Impacts on the surface water body from the bridge construction and the implementation status of preventive measures;
Implementation of preventive measures on roadbed slope and the effects;
Prevention and treatment of noise, sewage water, air environment and solid waste resulting from the construction camps, construction roads, at the temporary engineering sites and in beam construction and storage yards and rail construction bases;
Implementation status of various environmental protection measures adopted by the project (including the noise prevention engineering, sewage water treatment and electromagnetism).
Propaganda for sanitation at the construction camps and health of construction personnel.
2. Project Progress
2.1 Project Implementation Units, Contractors and Construction Supervision Companies of Chongqing-Lichuan Railway
The project implementation unit of Chongqing-Lichuan is Chongqing-Lichuan Railway Construction Co., Ltd., totaling 6 bid sections in the whole railway line. Table 2-1 shows the construction and supervision units for each bid section.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 5
Table 2-1: Construction and Supervision Units for each section of Chongqing-Lichuan Railway
S.N. Bid
section Construction unit Supervision unit
Construction mileage
Length of bid
section (km)
1 I China Railway 12th Bureau
Group Co., Ltd. Chengdu Southwest
Supervision Company DKO+000~
DK36+111.31 36.118
2 II China Railway 11th Bureau
Group Co., Ltd.
Sichuan Tieke Construction Supervision
Company
DK36+111.31~DK86+051.787 49.911
3 III China Zhongtie Major Bridge Engineering Group Co., Ltd.
Sichuan Tieke Construction Supervision
Company
DK86+051.787~DK124+716.25 25.231
4 IV China Railway Tunnel Group
Co., Ltd. China Railway Eryuan Supervision Company
DK124+716.25~D1K199+026.8 77.188
5 V China Railway 18th Bureau
Group Co., Ltd. Changsha Zhongda
Supervision Company D1K199+026.8~
DK233+370.3 34.344
6 VI China Railway No. 5
Engineering Group Co., Ltd. Changsha Zhongda
Supervision Company D1K233+370.3~
DK274+983 41.626
2.2 Project Progress The project of Chongqing-Lichuan railway was kicked off on December 29, 2008. Presently, constructions including tunnel excavation, roadbeds and bridge foundation had been under way. By June 30, 2009, the completed engineering works and the completion status of key engineering are summarized in Tables 2-2 and 2-3.
Table 2-2: Summary of Completed Engineering Works Name Unit Total accumulative
volume completed annually
Total accumulative volume completed ever since kickoff
Completed ratio of design (%)
Investment 104 yuan 142517.8 144529.2 9.6 Incl: Construction and
installation 104 yuan 133257.8 135269.2 9.3
Roadbed cubic meter of earth and stone
104 m3 52470.8 52470.8 3.9
In which: sectional cubic meter of earth and stone
104 m3 1864.1 1864.1 2.3
Cubic meter of earth and stone of station and yard
104 m3 50606.7 50606.7 4.1
Super-major, major and medium bridges
Linear meter 4152.2 4152.2 11.1
Incl: Super-major bridges Linear meter 2063.9 2063.9 15.8 Major bridges Linear meter 1931.6 1931.6 18.5
Medium bridges Linear meter 156.7 156.7 21.4 Culverts Horizontal linear
meter 506.8 506.8 27.1
Tunnels Linear meter 9732.5 9732.5 7.1
By June 30, 2009
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 6
Table 2-3: Summary of Completed Key Engineering
S. N. Name Scale (m)
Total accumulative
volume completed annually
(m)
Total accumulative
volume completed ever since
kickoff (m)
Completed ratio of total
accumulative volume
completed ever since kickoff
Contractor
1 Paihuadong Tunnel 4955 380 380 7.7 China Railway
12th Bureau Group Co., Ltd.
2 Huangcaoshan Tunnel 6663 549.13 549.13 8.24
China Railway 11th Bureau
Group Co., Ltd.
3 Caijiagou Super-major Bridge 2057.4 17.7 17.7 0.86%
China Zhongtie Major Bridge Engineering
Group Co., Ltd.
4 Xinqiao Super-major Bridge 1712.3 17.86 17.86 1.04%
China Zhongtie Major Bridge Engineering
Group Co., Ltd.
5 Hanjiatuo Super-major Bridge 1078.8 130.39 130.39 12.08%
China Zhongtie Major Bridge Engineering
Group Co., Ltd.
6 Jianfengding 1# Tunnel 870 135.29 135.29 15.92%
China Zhongtie Major Bridge Engineering
Group Co., Ltd.
7 Jianfengding 2# Tunnel 1050 225.74 225.74 21.5%
China Zhongtie Major Bridge Engineering
Group Co., Ltd.
8 Daliang Tunnel 10942 337.8 337.8 3.1 China Railway Tunnel Group
Co., Ltd.
9 Hujiapo Tunnel 5475 180.8 180.8 3.3 China Railway Tunnel Group
Co., Ltd.
10 Fangdoushan Tunnel 4870 157.6 157.6 3.2
China Railway Tunnel Group
Co., Ltd.
11 Nanbaidong Tunnel 6935 183.5 183.5 2.6 China Railway Tunnel Group
Co., Ltd.
12 Changhongling Tunnel 13287 372.2 372.2 2.8
China Railway Tunnel Group
Co., Ltd.
13 Jinzhutan Longhe Major Bridge 478.07 92 92 19.2
China Railway Tunnel Group
Co., Ltd.
14 Fangjiaya
Super-major Double-track Bridge
681.98 99 99 14.5 China Railway Tunnel Group
Co., Ltd.
15 Wanshoushan Tunnel 13474 596 596 4.4%
China Railway 18th Bureau
Group Co., Ltd.
16 Shaziguan Tunnel 9252 478 478 5.2% China Railway
18th Bureau Group Co., Ltd.
17 Xiangjiaba Tunnel 6510 257 257 3.9% China Railway
18th Bureau Group Co., Ltd.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 7
S. N. Name Scale (m)
Total accumulative
volume completed annually
(m)
Total accumulative
volume completed ever since
kickoff (m)
Completed ratio of total
accumulative volume
completed ever since kickoff
Contractor
18 Xinwu Tunnel 793 109 109 13.7% China Railway
18th Bureau Group Co., Ltd.
19 Qingshiyan Major Bridge 415.67 54 54 13%
China Railway 18th Bureau
Group Co., Ltd.
20 Tuntianba Major Bridge 191.1 18 18 9.4%
China Railway 18th Bureau
Group Co., Ltd.
21 Xiangjiaba Major Bridge 292 0 0 0%
China Railway 18th Bureau
Group Co., Ltd.
22 Dutingshan
Double-track Tunnel
9739 420 420 4.31
China Railway No. 5
Engineering Group Co., Ltd.
23 Yujia Double-track Tunnel 3491 201 201 5.76
China Railway No. 5
Engineering Group Co., Ltd.
24 Fubaoshan Tunnel 6223 280 280 4.5
China Railway No. 5
Engineering Group Co., Ltd.
25 Qingjiang Overline
Double-track Super-major Bridge
2614.05 47.9 47.9 1.84
China Railway No. 5
Engineering Group Co., Ltd.
26 Longdong
Super-major Double-track Bridge
780.64 46.95 46.95 6.01
China Railway No. 5
Engineering Group Co., Ltd.
By June 30, 2009
3. Environmental Control 3.1 Environmental Control System Chongqing-Lichuan Railway Construction Co., Ltd., the implementation unit for this railway line, is held responsible for the environmental protection of this section and the Environmental Protection Adiministrations of Chongqing municipality (Including Jiangbei District, Yubei District, Fuling District, Fengdu County and Shizhu County) and Lichuan City, Hubei Province are responsible for supervision and management of environmental protection in their respective jurisdiction regions. Environmental monitoring for Chongqing-Lichuan Railway shall be undertaken by Beijing OASIS. The construction and supervision units take responsibility for daily monitoring and supervision during construction period. The implementation unit and OASIS are to collect monitoring data, and then OASIS shall prepare the environmental monitoring report and submit it to the MOR and Asian Development Bank. The environmental monitoring procedures for this railway line are shown in block diagram 3-1.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 8
Diagram 3-1: Block diagram for environmental monitoring procedures
Notes: Chongqing-Lichuan Railway Construction Co., Ltd.: as the project implementation unit, it entrusts and assists the monitoring units to complete the monitoring work, and when the contract is awarded, it signs the contract containing environmental protection requirements with the construction and supervision units. Construction Units: it executes the project and completes the environmental protection work according to the contractual requirements. Supervision Units: it supervises the engineering quality and environmental protection processing according to contractual requirements. Environmental monitoring units: as an external monitor units, it supervises the implementation of environmental engineering and submits the monitoring reports to Chongqing-Lichuan Railway Construction Co., Ltd. , the MOR and Asia Development Bank. Based on the characteristics of this project and the environmental problems with high-frequent occurrence during the construction, the monitoring units shall require the relevant units to build up an environmental protection system in the following aspects:
Each unit concerned is required to have the professional environmental protection staff who shall receive the special pre-job training on environmental protection, be responsible for supervision and control of environmental problems that occur during its own construction and assist the environment control department with environmental control work;
Each construction unit is required to fulfill the correspondent environmental protection promises in the construction contract, make the relevant environmental protection measures in accordance with requirements for environmental protection work in the design documents to protect the environment of construction site and avoid and reduce the pollution and damage to the environment due to improper construction. Once the environment-affecting events occur, they should take active countermeasures. If they can not solve it, it is necessary to ask the relevant experts and units for help as soon as possible;
It is required to be responsible for daily environmental monitor work in accordance with the environmental protection requirements in the construction contract. Once an environmental
Consultation services
Entrustment and assistance
Environment Monitor Units
Contract awarding
Contracting
Construction units Engineering supervision units
Implement Supervise
Construction of Chongqing-Lichuan Railway Project
Supervise the implementation of
project
Chongqing-Lichuan Railway Co., Ltd.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 9
problem occurs during the construction, it should supervise and urge its timely solution and include the environmental protection into the engineering quality supervision system.
3.2 Daily Environmental Monitoring System The daily monitoring of water, gas and noise in the construction period shall be conducted by the construction and supervision units and the periodical monitoring of water, gas and noise can be entrusted to the railway bureaus or the environmental monitoring stations of cities along the line in accordance with the actual needs. Beijing OASIS shall assist the completion of entrustment of environmental monitoring work in accordance with the requirements from Chongqing-Lichuan Railway Construction Co., Ltd.. The monitoring data shall be collected by Chongqing-Lichuan Railway Construction Co., Ltd. and Beijing OASIS, included in the environmental monitoring report and submitted to the MOR and Asian Development Bank. Chongqing-Lichuan Railway Construction Co., Ltd. has professional environmental protection engineers set up inside its engineering management division to be in charge of the daily management and supervision of environmental protection in the construction period and professional full-time (part-time) environmental protection engineers are arranged for each bid section to supervise and check the environmental protection work in its bid section. Compilation of Management System of Standardization of Chongqing-Lichuan Railway (Tentative) (CLTC [2009] No. 4 Document) was issued by Chongqing-Lichuan Railway Construction Co., Ltd. on January 8, 2009, including Measures for Administration of Environmental Protection and Measures for Administration of Water and Soil Conservation. A leading group for management of environmental protection composed of general manager of the company (group leader), other leaders (deputy leaders) as well as directors in charge of each department, project managers of construction units, the chief supervision engineers and the general designers (members) and Engineering Management Division of the company (responsible for daily work) has been built. It has defined the duties and responsibilities of the company, design units, construction units and consultation units in the aspects of environmental protection and water and soil conservation in Measures for Management of Environmental Protection and Management of Water and Soil Conservation and put forward the key points for environmental protection and water and soil conservation as well as the inspection and acceptance system. In this survey, we found that ‘Measures on Management of Environmental Protection, Water and Soil Conservation during the Construction of I Bid Section of Chongqing-Lichuan Railway’ was made by China Railway 12th Bureau Group Co., Ltd.; a leading group composed of project manager, the chief engineer, head of Division of Security and Quality, head of Division of Engineering Technology and the engineers for water, environmental protection was established; the block diagram for environmental and water protection system for construction was provided, each branch division and construction unit had been required to arrange its own specialized environmental protection engineers and the detailed measures for water, environmental protection were made. Besides, ‘Measures on Environmental Protection during the Construction of the Tunnel’ was made by China Railway 11th Bureau Group Co., Ltd. and Diagram for Environmental Protection and Water and Soil Conversation and Assurance System was established. China Zhongtie Major Bridges Engineering Group Co., Ltd. found a leading group for environmental protection led by the project manager and signed Responsibilities for Environmental Protection Objectives with its subordinated branches, and ‘Leading group for environmental protection’, ‘Environmental protection system’, ‘Organizational chart of SHEQ’ and ‘Objectives of environmental management’ are available; Project Department of China Railway Tunnel Group Co., Ltd. had established the ‘System Diagram of Responsibilities for Environmental and Water Protection’, clarifying the responsibilities of leading group and relevant departments like Engineering, Safety and Quality, with ‘Objectives of Environmental Protection’ available; Wanshoushan Tunnel Bid Section under China Railway 18th Bureau Group Co., Ltd. had established ‘Leading Group for Environmental Protection’, ‘System Block Diagram of Environmental Protection and Water and Soil Preservation’, defining measures organizationally, systematically, technically and economically, specifying the responsibilities of Environmental Protection and Water and Soil Preservation Department and PE Department; China Railway No. 5 Engineering Group Co., Ltd. had made ‘Scheme on Implementing Environmental Protection for
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 10
VI Bid Section of New Chongqing-Lichuan Railway’ and ‘Scheme on Implementing Water and Soil Preservation for VI Bid Section of New Chongqing-Lichuan Railway’, defining leading group for environmental protection led by project manager, with project secretary, general manager and deputy manager as deputy chief of the group, and Safety and Quality Department is charge of implementation.
4. Pre-job Training on Environmental Protection In accordance with the regulations in the bidding/tendering documents for this project, Beijing OASIS assisted Chongqing-Lichuan Railway Construction Co., Ltd. with the training class opened on March 26, 2009 for environmental monitoring. The teaching materials are Training Material for Railway Environmental Management compiled by Environmental Protection Committee, China Railway Association and Supplementary Training Material for Environmental Protection during the Construction Period of Chongqing-Lichuan Railway Project Developed with the Loan from Asian Development Bank self-compiled by Beijing OASIS. The trainees are those people in charge of construction units and supervision units as well as the professional and part-time environmental protection personnel. Mr. Jia Guoquan, researcher from Beijing OASIS made detailed explanations. The main contents for training include: Laws, rules and regulations for management of environmental protection. He emphatically introduced the contents relevant to laws on environmental protection, rules and regulations for management of environmental protection of construction projects and measures for management of environmental protection of completed construction projects etc. as well as the contents relevant to laws and regulations for environmental protection made by Chongqing municipality and Hubei province; Environmental impacts from the railway construction projects and the environmental protection measures in the construction period. Explanations were made in phases of preparation for construction, construction and completion; Main environmental monitoring contents and key environmental monitoring points of this project, a project developed the loan from Asian Development Bank; Opinions made by the MOR after its pre-examination of EIA report for this project and water and soil conservation programs as well as the replies from Ministry of Environmental Protection and Ministry of Water Resources to the EIA report and the water and soil conservation programs. He introduced and explained the above-mentioned documents approved and delivered these documents as the attachments to the supplementary teaching materials so that the construction and supervision units could grasp the requirements from the approved documents. The participants for the training are listed in Table 4-1.
Table 4-1: Participants for the training on environmental monitoring of Chongqing-Lichuan Railway
S.N. Name Unit Post 1 Yuan Bude Chongqing-Lichuan Railway Construction Co., Ltd. Head of Division 2 Xiao Bin Chongqing-Lichuan Railway Construction Co., Ltd. Deputy Head of Division 3 Fu Chao Chongqing-Lichuan Railway Construction Co., Ltd. Senior Engineer 4 Fu Xinping Chongqing-Lichuan Railway Construction Co., Ltd. Engineer 5 Wang Jun Chongqing-Lichuan Railway Construction Co., Ltd. Engineer 6 Li Tao Chongqing-Lichuan Railway Construction Co., Ltd. Engineer 7 Zhang Guodi Chongqing-Lichuan Railway Construction Co., Ltd. Engineer
8 Yang Chunhua
Chongqing-Lichuan Railway Construction Co., Ltd. Engineer
9 Xu Zeyi China Railway 12th Bureau Group Co., Ltd. Deputy Manager of Construction Site of the Project
10 Li
Shousheng China Railway 12th Bureau Group Co., Ltd. Deputy Manager of Construction
Site of the Project
11 Zhao
Haishan China Railway 12th Bureau Group Co., Ltd. Deputy Head of Safety and
Quality Division
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 11
S.N. Name Unit Post
12 Tang Xiaoqi China Railway 12th Bureau Group Co., Ltd. Deputy Head of Safety and Quality Division
13 Kong Biao China Railway 12th Bureau Group Co., Ltd. Director-General of Safety 14 He Lin China Railway 12th Bureau Group Co., Ltd. Director-General of Safety
15 Ming Jianlong
China Railway 12th Bureau Group Co., Ltd. Safety and Quality Department
16 Song Yongling
China Railway 12th Bureau Group Co., Ltd. Safety and Quality Department
17 Qi Wansheng
China Railway 12th Bureau Group Co., Ltd. Technician
18 Chen Weishi China Railway 12th Bureau Group Co., Ltd. Quality Inspector 19 Li Dahai China Railway 12th Bureau Group Co., Ltd. Technician 20 Yu Xiaoqi Chengdu Southwest Supervision Company Deputy Director-General
21 Yang Huihong
Chengdu Southwest Supervision Company Deputy Director-General
22 Ni Zhijun Chengdu Southwest Supervision Company Leader of Supervision Team
23 Yang Yaxiong
Chengdu Southwest Supervision Company Engineer
24 Li Yinglai Chengdu Southwest Supervision Company Engineer 25 Xiang Yang Chengdu Southwest Supervision Company Engineer
26 Gong Jianyong
China Railway 11th Bureau Group Co., Ltd. Head of Safety and Quality Division
27 Guan Ye China Railway 11th Bureau Group Co., Ltd. Director-General of Safety
28 Wu Jianxing China Zhongtie Major Bridge Engineering Group Co., Ltd.
Manager of Construction Site of the Project
29 Li Guohui China Zhongtie Major Bridge Engineering Group Co., Ltd.
Deputy Manager of Construction Site of the Project
30 Zheng Fayuan
China Zhongtie Major Bridge Engineering Group Co., Ltd.
Deputy Manager of Construction Site of the Project
31 Ai Minguo China Zhongtie Major Bridge Engineering Group Co., Ltd.
Assistant Chief Engineer
32 Zhang Xiaoping
China Zhongtie Major Bridge Engineering Group Co., Ltd.
Head of Safety and Quality Division
33 Xiong Yunbo
China Zhongtie Major Bridge Engineering Group Co., Ltd.
Head of Safety and Quality Division
34 Zhou Min China Zhongtie Major Bridge Engineering Group Co., Ltd.
Head of Safety and Quality Division
35 He Jie China Zhongtie Major Bridge Engineering Group Co., Ltd.
Head of Safety and Quality Division
36 Hao Jieqing China Zhongtie Major Bridge Engineering Group Co., Ltd.
Engineer
37 Jiang Peixian
China Zhongtie Major Bridge Engineering Group Co., Ltd.
Engineer
38 Huang Yuzhe
Sichuan Tieke Construction Supervision Company Deputy Director-General
39 Xian Wei Sichuan Tieke Construction Supervision Company Deputy Director-General
40 Luo Zhongjun
Sichuan Tieke Construction Supervision Company Leader of Supervision Team
41 Zhang Weihua
Sichuan Tieke Construction Supervision Company Engineer
42 Chen Wu Sichuan Tieke Construction Supervision Company Supervisory Engineer 43 Yu Hua Sichuan Tieke Construction Supervision Company Supervisory Engineer 44 Qin Shaoyun Sichuan Tieke Construction Supervision Company Supervisory Engineer
45 Sun Baoquan
China Railway Tunnel Group Co., Ltd. Manager
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 12
S.N. Name Unit Post
46 Chen Hongyu
China Railway Tunnel Group Co., Ltd. Manager
47 Geng Wei China Railway Tunnel Group Co., Ltd. Deputy Manager
48 Zou Yangli China Railway Tunnel Group Co., Ltd. Head of Safety and Quality Division
49 Yan Ruiguang
China Railway Tunnel Group Co., Ltd. Director
50 Fu Qingzhou China Railway Tunnel Group Co., Ltd. Head of Safety and Quality Division
51 Li Jun China Railway Tunnel Group Co., Ltd. Head of Safety and Quality Division
52 Zheng Zijie China Railway Tunnel Group Co., Ltd. Director-General of Safety
53 Zhou Qiangbo
China Railway Tunnel Group Co., Ltd. Safety Supervisor
54 Ni Qing China Railway Tunnel Group Co., Ltd. Assistant Engineer 55 Li Delin China Railway Eryuan Supervision Company Deputy Director-General
56 Wang Daxian
China Railway 18th Bureau Group Co., Ltd. Manager
57 Liu Wenyou China Railway 18th Bureau Group Co., Ltd. Deputy Manager 58 Yang Hanfu China Railway 18th Bureau Group Co., Ltd. Deputy Manager 59 Liu Xiaoyou China Railway 18th Bureau Group Co., Ltd. Deputy Manager
60 Hu Wei China Railway 18th Bureau Group Co., Ltd. Head of Environmental Protection Department
61 Jia Baojun China Railway 18th Bureau Group Co., Ltd. Leader of Project Department
62 Wang Chansgjun
China Railway 18th Bureau Group Co., Ltd. Head of Safety and Quality Division
63 Zhou Heping China Railway 18th Bureau Group Co., Ltd. Safety and Quality Division 64 Bai Huajun China Railway 18th Bureau Group Co., Ltd. Leader of Project Team
65 Sun Yingchun
China Railway No. 5 Engineering Group Co., Ltd. Deputy Manager
66 Wang Man China Railway No. 5 Engineering Group Co., Ltd. General Engineer
67 Tang Taowen
China Railway No. 5 Engineering Group Co., Ltd. General Engineer
68 Deng Minggao
China Railway No. 5 Engineering Group Co., Ltd. Head of Safety and Quality Division
69 Zhong Qicun China Railway No. 5 Engineering Group Co., Ltd. Director-General of Safety 70 Wu Jianfen China Railway No. 5 Engineering Group Co., Ltd. Safety and Quality Division 71 Hu Lianhua China Railway No. 5 Engineering Group Co., Ltd. Safety Supervisor 72 Lu Zhanhai Changsha Zhongda Supervision Company Deputy Director-General
73 Geng Yourong
Changsha Zhongda Supervision Company Special supervisor of Environmental Protection
74 Zhang Jingbo
Changsha Zhongda Supervision Company Director of Lab
5. Supervision and Inspection of Affected Points
In August 2009, project team members of our company are accompanied by the personnel for management of environmental protection from Chongqing-Lichuan Railway Construction Co., Ltd., made a sample check of construction sites for each section of this railway line. The on-site investigation made this time is to check the work contents of construction unit in the following several aspects: 1. To know about the internal management of environmental protection and water conservancy
work from the construction units;
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 13
2. To understand the implementation of environmental protection measures in the tunnel construction;
3. To find out the implementation of environmental protection measures at construction sites; 4. To make out the implementation of environmental protection measures during the bridge
construction; 5. To know about the preventive measures for construction roads.
5.1 Implementation Status of Environmental Protection for Each Bid Section The implementation status of environmental protection for each bid section is shown in Tables 5-1 ~ 5-6.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 14
Table 5-1: Implementation Status of Environmental Protection for I Bid Section
Construction unit: China Railway 12th Bureau Group Co., Ltd.
Supervision unit: Chengdu Southwest Supervision Company
Major C
onstruction camps
Location Garbage Treatment Measures Sewage
Treatment Measures
Billboard of Environmental
Protection Remarks
Dazhulin Town in New Zone of the north of
Chongqing
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 100 staff members.
Camp self-built
Paihua Village, Longxing Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 140 staff members.
Camp self-built
Taihongchang, Luoqi Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 108 staff members.
Camp self-built
Tiangongdian Road in New Zone of the north
of Chongqing
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available
150 staff members.
Camp self-built
Tunnel more than 1000m in
length
Name Mileage Construction progress Remarks
Paihuadong Tunnel
DK30+320~DK35+285 Cavitation completed: 315
m
Spoil grounds for the entrance and exit to Paihuadong Tunnel
Yufengshan Tunnel
DK15+924~DK19+146 Cavitation completed: 75
m Official drawing not
available yet
Huofengshan Tunnel
HLZDK12+880~HLZDK22+295 HLYDK13+165~HLYDK22+295
No progress made, because the construction roads for the exit to tunnel and 2#
inclined shaft being under way
Official drawing not available yet
Yanwo Tunnel
DK8+251~DK10+673 Cavitation completed: 260
m /
Dashiba Tunnel
DK23+485~DK25+120 / Official drawing not
available yet Moyubao Left Line
(Single-track) HLZDK25+526~HLZDK27+830
Cavitation completed: 80 m
/
Moyubao Right Line
HLYDK25+815~HLYDK28+410 Cavitation completed: 75
m /
Super-major and major
bridges
Name Mileage Construction progress Remarks Julong Super-major Double-track Bridge
LTSK33+991.19~ LTSK35+455.43
8 piers and 1 bearing platform completed
/
Liangchanghe Left Line Super-major Bridge
LTSDK31+404.5 Construction roads under way Drawing not
available now Liangchanghe Right Line
Super-major Bridge LTXDK31+416 Construction roads under way
Drawing not available now
Cuntan Super-major Bridge
HLZDK23+161 Construction not started yet Drawing not
available now Wangjiahe Super-major
Bridge HLYDK11+033 Construction not started yet
Drawing not available now
Jinzhou Dadao Overline HLYDK12+311.1 Construction not started yet Drawing not
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 15
Super-major Bridge available now Cuntan Super-major Double-track Bridge
DK6+592 Construction roads under way Drawing not
available now Longjingou Super-major
Double-track Bridge D1K27+888 Construction not started yet /
Yulinhe Super-major Double-track Bridge
D1K28+836 4 piers, 2 bearing platforms and
435-linear meter excavation pile completed
/
Main borrow pits /spoil grounds
Location mileage Designed soil-borrowing and spoiling quantity and measures
Progress Implementation
status Remarks
Spoil ground of Yanwo Tunnel
Total discarded waste slag of 35×104m3, occupying dry land
of 60 mu (1 mu=0.0667 hectares) and less-occupied
forest land restored to vegetation after completion
2.5×104m3 Retaining wall
under construction
At 100 m to the right
side of Moyubao
Tunnel entrance
Entrance of Yufengshan Tunnel
Total discarded waste slag of 22.2×104m3, occupying land of
35.1 mu 0.06×104m3
Retaining wall under
construction
Exit of Yufengshan
Tunnel
Spoil ground of Yanwo Tunnel
Total discarded waste slag of 16.9×104m3, occupying dry
land of 40 mu and less-occupied forest land and
cropland restored to vegetation after completion
2×104m3 Retaining wall
under construction
Exit of Yanwo Tunnel
Spoil ground of Yufengshan Tunnel
Total discarded waste slag of 22×104m3, occupying dry land
of 45 mu and less-occupied forest land and cropland
restored to vegetation after completion
1.2×104m3 Retaining wall
under construction
Entrance of Yufengshan
Tunnel
Spoil ground of entrance and exit of Paihuadong Tunnel
Total discarded waste slag of 43.5×104m3 for both entrance
and exit, and the area of entrance and exit is 100 mu
respectively.
4.6×104m3 Retaining wall
under construction
Spoils from Paihuadong
Tunnel
Renhe Dashi Spoil ground
Owner designated spoil ground with discarded waste slag of
300×104m3 20×104m3 Under use
Renhe Dashi Spoil
ground
Yuanyang D61 Spoil ground
Owner designated spoil ground with discarded waste slag of
300×104m3 /
No delivery for use yet
Yuanyang D61 Spoil
ground
Noise-sensitive points
Name Mileage Design
measures Implementation
status Remarks
Remarks
1. Fugitive dust from construction site and roads has been resolved by sprinkling water at construction site and if more dust at construction site, conduct the sealing treatment (e.g. Mixing station) with more-frequently watering to keep ground surface wet. Another way to reduce dust adopted is the hardening treatment of site roads and construction site.
2. Leaking water of tunnels shall be flowed into sedimentation tank and then discharged up to the standard. 3. Spoil of tunnel shall be discarded at spoil grounds along which retaining walls are being constructed. 4. No cultural relics have so far been found at the whole zone of piping construction. 5. Color-bar cloth shall be used to cover materials entering the site.
On-site investigation results of
The on-site investigation results of monitoring are: Paihuadong tunnel: the construction roads appear tidy, convenient and clear; billboard of environmental protection erected; air compressor stored inside air compressor room; no protection and water interception and
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 16
monitoring drainage facility is available at the border of spoil ground, which is prone to cause water and soil loss; only Level I sewage sedimentation tank not cleaned immediately shall be cleared without delay. Liangchanghe Mixing station: sedimentation tank for sewage from production is available; garbage bin and waste collection pool have been set up for centralized collection and uniform disposal by local environmental sanitation department; there are watering cart; and rinsing water from mixing plant after settling in sedimentation tank which is suggested to be established shall be recycled for dust removal at the construction site and roads. Engineering at the natural reservation zone and scenic spot has not been started yet.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 17
Table 5-2: Implementation Status of Environmental Protection for II Bid Section
Construction unit: China Railway 11th Bureau Group Co., Ltd.
Supervision unit: Sichuan Tieke Supervision Company
Construction cam
ps
Location Garbage Treatment Measures Sewage Treatment Measures
Billboard of Environmental
Protection Remarks
Duzhou Village, Duzhou Town, Changshou District
Set up garbage bin for centralized collection and uniform disposal by local environmental sanitation
department
Sedimentation tank, septic tank and
drainage facility established
Available at station
135 staff members. Camp
self-built
Fengsheng Village, Duzhou Town,
Changshou District
Set up garbage bin for centralized collection and uniform disposal by local environmental sanitation
department
Sedimentation tank, septic tank and
drainage facility established
Available at station
158 staff members. Camp
self-built
Lidu Town, Fuling District
Set up garbage bin for centralized collection and uniform disposal by local environmental sanitation
department
Sedimentation tank, septic tank and
drainage facility established
Available at station
189 staff members. Camp
self-built and rent local
houses
Baohua Village, Luoqi Town, Yubei District
Set up garbage bin for centralized collection and uniform disposal by local environmental sanitation
department
Sedimentation tank, septic tank and
drainage facility established
Available at station
129 staff members.
Camp self-built and rent local
houses
Tunnel more than 1000m in
length
Name Mileage Construction progress Remarks
Gaoshipan Tunnel
DK58+105~DK60+834.67
Entrance not started yet due to removal of houses; At exit, excavation of top heading
completed 16 m.
Spoil ground planned to be set up both at entrance and
exit respectively
Shaping Tunnel DK70+837`DK73+653 Cavitation completed 46.8 m at entrance; and 149.2 m at exit.
Spoil ground planned to be set up both at entrance and
exit respectively
Huangcaoshan Tunnel
DK79+290~DK85+953 Cavitation completed 376.93 m at entrance; and 172.2 m at exit.
Spoil ground planned to be set up both at entrance and
exit respectively
Super-major and major
bridges
Name Mileage Progress Remarks
Fangjiawan Super-major Bridge
DK36+629~DK37+363 106 piles of pile foundation have been formed, 5 bearing platforms and spread
foundation /
Yaojiaju Super-major Bridge
DK38+268.8~DK39+040.8 38 piles of pile foundation have been
formed, 3 bearing platforms and 2 pier shafts completed
/
Wujiagou Super-major Bridge
DK50+448.7~DK51+540.2 33 piles of pile foundation have been
formed, 3 bearing platforms and 2 pier shafts completed
/
Zhouxinhe Super-major Bridge
DK56+765~DK57+550 56 piles of pile foundation have been formed, 9 bearing platforms, spread
foundation and 1 pier shaft completed /
Longxihe Super-major Bridge
DK75+194~DK76+360 Excavation of pile foundation for pore-creating 308 m
/
Mengziwan Super-major Bridge
DK77+369~DK77+833 67 piles of pile foundation have been
formed, 7 bearing platforms and spread foundation
/
Zhangjiawan DK77+955~DK78+998 58 piles of pile foundation have been /
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 18
Super-major Bridge formed, 3 bearing platforms and spread foundation
Main borrow pits /spoil grounds
Location mileage Designed soil-borrowing and spoiling quantity and measures
Progress Implementation
status Remarks
Spoil ground of the exit to Gaoshipan
Tunnel
Total discarded waste slag of 18×104m3, occupying dry land of 23 mu, reclamation of 10 mu and
vegetation of 13 mu.
5×103m3 Retaining wall
under construction /
Spoil ground of the entrance to Shaping
Tunnel
Total discarded waste slag of 23×104m3, occupying dry land of 25 mu, reclamation of 10 mu and
vegetation of 14 mu.
1.6×104m3 Retaining wall
under construction /
Spoil ground of the exit to Shaping
Tunnel
Total discarded waste slag of 18×104m3, occupying dry land of 15.3 mu, reclamation of 2 mu and vegetation of 2 mu; retaining wall
set up and spoil ground leveled mechanically
2.5×104m3 Retaining wall
under construction /
Spoil ground of the entrance to Mayiling
Tunnel
Total discarded waste slag of 15×104m3, occupying dry land of 57.5 mu, reclamation of 22.9 mu
and vegetation of 34.6 mu.
2.1×104m3 Retaining wall
under construction /
Spoil ground of Dashanpo Tunnel
Total discarded waste slag of 8×104m3, occupying dry land of 20
mu, reclamation of 4 mu and vegetation of 16 mu.
3×104m3 Retaining wall
under construction /
Spoil ground of the entrance and exit to
Huangcaoshan Tunnel
Total discarded waste slag of 83×104m3, occupying land of 135 mu totaled by both spoil grounds of which 73 mu of forest land and
60 mu dry land and plan to implement protection and
vegetation measures.
7.5×104m3 Retaining wall
under construction /
Spoil ground of inclined shaft of
Huangcaoshan Tunnel
Total discarded waste slag of 4×104m3, occupying dry land of 35
mu, reclamation of 10 mu and vegetation of 25 mu.
2.1×104m3 Retaining wall
under construction /
Remarks
1. Fugitive dust from construction site and roads has been resolved by sprinkling water at construction site and if more dust at construction site, conduct the sealing treatment (e.g. Mixing station) with more-frequently watering to keep ground surface wet. Another way to reduce dust adopted is the hardening treatment of site roads and construction site.
2. Leaking water of tunnels shall be flowed into sedimentation tank and then discharged up to the standard. 3. There is no roadbed construction for this bid section; spoil of tunnel shall be discarded at spoil grounds along
which retaining walls are being constructed. 4. No cultural relics have so far been found at the whole zone of piping construction. 5. Color-bar cloth shall be used to cover materials entering the site.
On-site investigation results of monitoring
The on-site investigation results of monitoring are: Huangcaoshan tunnel: the construction site appears tidy and orderly; Guarantee system diagram of environmental protection and water & soil reservation and billboard of environmental protection are available; garbage bins have been set up; no sedimentation tank for sewage; no protection and water interception and drainage facility is available at spoil ground, which is prone to cause water and soil loss and immediate correction is necessary. Changshou North Mixing station: the construction site is messy; sedimentation tank for sewage from production is available and being cleaned; garbage bin and waste collection pool have been set up for centralized collection and uniform disposal by local environmental sanitation department; there are watering cart. Construction of the piers in the water has not yet started for Longxihe Super-major bridge.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 19
Table 5-3: Implementation Status of Environmental Protection For III Bid Section
Construction unit: China Zhongtie Major Bridge Engineering Group Co., Ltd.
Supervision unit: Sichuan Tieke Supervision Company
Construction cam
ps
Location Garbage Treatment Measures Sewage Treatment Measures
Billboard of Environmen
tal Protection
Remarks
Nitrogenous Fertilizer Plant of Hanjia Village, Jiangbei Office, Fuling
District
Set up garbage bin for centralized collection and uniform disposal by local environmental sanitation
department
Sedimentation tank, septic tank and
drainage facility established
Available /
Ma’an Zhaohua Science Park, Lidu Town, Fuling
District
Set up garbage bin for centralized collection and uniform disposal by local environmental sanitation
department
Sedimentation tank, septic tank and
drainage facility established
Available /
Chuandong Shipyard, Fuling District
Set up garbage bin for centralized collection and uniform disposal by local environmental sanitation
department
Sedimentation tank, septic tank and
drainage facility established
Available /
Lailong Village, Huangqi Town, Fuling District
Set up garbage bin for centralized collection and uniform disposal by local environmental sanitation
department
Sedimentation tank, septic tank and
drainage facility established
Available /
Nitrogenous Fertilizer Plant of Hanjia Village, Jiangbei Office, Fuling
District
Set up garbage bin for centralized collection and uniform disposal by local environmental sanitation
department
Sedimentation tank, septic tank and
drainage facility established
Available /
Tunnel more than 1000m in
length
Name Mileage Construction progress Remarks
Banpo Tunnel DK87+315.5 Top heading tunneling 180 m, bottom heading tunneling 52 m and inverted arch completed is
42 m /
Bajiaoshu Tunnel
DK106+322.5
Top heading tunneling 45 m, bottom heading tunneling 130 m and left and right sides of
timbering in the open excavation completed are 12 m respectively
/
Jianfengding Tunnel
D3K110+543 Upper bench excavation completed is 32 m /
Shijiapo Tunnel D3K115+960 Top heading tunneling 171 m, bottom heading
tunneling 133 m and inverted arch completed is 104 m
/
Ma’anshan Tunnel
DK121+557.5 Upper bench is excavated 130 m, lower bench 81 m and inverted arch completed is 7m
/
Super-major and major
bridges
Name Mileage Progress Remarks
Daqinggou Major Bridge
DK88+694.00 3 piers and 1 bearing platform have been completed, and pile foundation
has excavated 282 linear meter. /
Xiaranfang Major Four-track Bridge
DK103+506.18 / Construction drawing is
unavailable. Caijiagou D3K108+416 24 pile foundations and bearing /
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 20
Super-major Bridge platform are under construction. Youcaowan Major
Bridge D3K111+820 2 file foundations have been
completed. /
Xinqiao Super-major Bridge
D3K113+192.00 10 file foundations have been completed.
/
Shiyuanzi Major Bridge
D3K114+090.00 7 file foundations have been
completed and bearing platform is under construction.
/
Hanjiatuo Yangtze River Super-major
Bridge D3K118+161.00 5 file foundations and 2 bearing
platforms have been completed /
Lishizi Super-major Double-track Bridge
DK124+628.00 Construction drawing is
unavailable.
Main borrow pits /spoil grounds
Location mileage Designed soil-borrowing and spoiling quantity and measures
Progress Implementati
on status Remarks
Spoil ground of the entrance to Banpo
Tunnel DK85+700
Total discarded waste slag of 18×104m3, occupying land of 50 mu, and carrying out reclamation
and vegetation.
1.8×104m3 Retaining wall under
construction /
Spoil ground of the exit to Banpo Tunnel
DK88+456
Total discarded waste slag of 18×104m3, occupying land of 60 mu, and carrying out reclamation
and vegetation.
/ / No
construction started
Spoil ground of the entrance to Bajiaoshu
Tunnel DK105+200
Total discarded waste slag of 18.5×104m3, occupying land of
60 mu, and carrying out reclamation and vegetation.
0.45×104m3 Retaining wall under
construction /
Spoil ground of 1# exit to Jianfengding
Tunnel D3K110+500
Total discarded waste slag of 20×104m3, occupying land of 36 mu, and carrying out reclamation
and vegetation.
0.55×104m3 Retaining wall under
construction /
Spoil ground of 2# exit to Jianfengding
Tunnel D3K111+550
Total discarded waste slag of 20×104m3, occupying land of 40 mu, and carrying out reclamation
and vegetation.
0.06×104m3 Retaining wall under
construction /
Entrance to Shijiapo Tunnel
D3K114+200
Total discarded waste slag of 26×104m3, occupying land of 70 mu, and carrying out reclamation
and vegetation.
1.15×104m3 Retaining wall under
construction /
Exit to Shijiapo Tunnel
Total discarded waste slag of 26×104m3, occupying land of 50 mu, and carrying out reclamation
and vegetation.
1.55×104m3 Retaining wall under
construction /
Exit to Ma’anshan
Total discarded waste slag of 13×104m3, occupying land of 23 mu, and carrying out reclamation
and vegetation.
1.25×104m3 Retaining wall under
construction
Remarks
1. Fugitive dust from construction site and roads has been resolved by sprinkling water at construction site and if more dust at construction site, conduct the sealing treatment (e.g. Mixing station) with more-frequently watering to keep ground surface wet. Another way to reduce dust adopted is the hardening treatment of site roads and construction site.
2. Leaking water of tunnels shall be flowed into sedimentation tank and then discharged up to the standard.
3. Retaining wall shall be built prior to discarding spoil from tunnel at spoil grounds 4. At present, there is no cultural relics found and no sensitive point such as Natural Preservation Zone
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 21
in the whole zone of piping construction. 5. Color-bar cloth shall be used to cover materials entering the site.
On-site investigation results of monitoring
The on-site investigation results of monitoring are: Jianfengding tunnel: the construction site appears tidy and orderly with entrance to the tunnel cave harmonized with natural landscape; construction roads are arranged neatly with distinct border; leading group of environmental protection has been established with billboard of environmental protection erected; garbage bins have been set up; sedimentation tank for sewage from production is available; no protection and water interception and drainage facility is available at spoil ground, which is prone to cause water and soil loss. Hanjiatuo Yangtze River Super-major Bridge: construction roads are arranged neatly with distinct border; watering carts are available; and construction of excavation pile fulfill the relevant requirements. Sedimentation tank for slurry is setup in the construction of excavation piles, and pier construction in the water has not started yet.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 22
Table 5-4: Implementation Status of Environmental Protection for IV Bid Section
Construction unit: China Railway Tunnel Group Co., Ltd.
Supervision unit: China Railway Eryuan Supervision Company
Construction cam
ps
Location Garbage Treatment Measures Sewage
Treatment Measures
Billboard of Environmental Protection
Remarks
Baimuyuan Village, Longhe Town, Fengdu County
Set up garbage bin for centralized collection and uniform disposal at
regular intervals
Sedimentation tank, septic tank
and drainage facility
established
Available 250 staff
members. Camp self-built
Jiangchi Town, Fengdu County
Set up garbage bin for centralized collection and uniform disposal at
regular intervals
Sedimentation tank, septic tank
and drainage facility
established
Available 290 staff
members. Camp rent
Wusong Village, Wulong Township, Jiangchi Town,
Fengdu County
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 160 staff
members. Camp self-built
Lvcunba Village, Sanjian Township, Fengdu County
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 114 staff members.
Camp self-built
Xiaojing Village, Anning Township, Fengdu County
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 172 staff members.
Camp self-built
Liaojiaba Village, Sanjian Township, Fengdu County
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 152 staff members.
Camp self-built
Shiban Hydropower Station, Fengdu County
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 149 staff members.
Camp self-built
Wanshoufang, Chengnanyizidong, Nanbin
Town, Shizhu County, Chongqing
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Municipal sewage piping
network Available
123 staff members. Camp rent
Chengdong Village, Nanbin Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 164 staff members.
Camp self-built
Jintian Village, Nanbin Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 172 staff members.
Camp self-built
Youhao Village, Xialu Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 102 staff members.
Camp self-built
Fangjiaya Village, Xialu Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
Available 151 staff members. Camp rent
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 23
established
Shiba Village, Qingxi Town, Fuling District, Chongqing
Set up garbage bin for centralized collection and uniform disposal at
regular intervals
Sedimentation tank for sewage and toilet with
septic tank established
Available 126 staff members.
Camp self-built
Qinglong Village, Qingxi Town, Fuling District,
Chongqing
Set up garbage bin for centralized collection and uniform disposal at
regular intervals
Sedimentation tank for sewage and toilet with
septic tank established
Available 132 staff members.
Camp self-built
Longju Village, Nantuo Town, Fuling District, Chongqing
Set up garbage bin for centralized collection and uniform disposal at
regular intervals
Sedimentation tank for sewage and toilet with
septic tank established
Available 325 staff members.
Camp self-built
Niulankou, Xialu Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 130 staff members.
Camp self-built
Major Bridges Group of Shangjin Village, Xialu Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available 160 staff members.
Camp self-built
Tunnel more than 1000m in
length
Name Mileage Construction progress Remarks
Dingzishan Tunnel D1K196+994~D1K198+440 Upper bench completed 42.8 m
Spoil ground of Entrance to Dingzishan Tunnel
Anzishan Tunnel D1K193+870~D1K194+978
Excavation of open slot completed 189 m
Spoil ground of Entrance to Anzishan Tunnel
Zhaiziling Tunnel D1K189+355~D1K 190+725 Upper bench completed 65.2 m
Spoil ground of Exit to Zhaiziling Tunnel
Changhongling Tunnel
DK170+300~DK175+000
Tunnel excavation at the Entrance completed 280 m
Spoil ground of Entrance to Changhongling Tunnel and Exit
to Nanbaidong Transverse Gallery of Changhongling
Tunnel
HDK1+720~ HDK0+0
Timbering excavation completed 400 m
Spoil ground of Transverse Gallery of Changhongling
Tunnel Exit to
Changhongling Tunnel
DK170+300~ DK183+594
Tunnel excavation completed 190 m
Spoil ground of Exit to Changhongling Tunnel
2# Inclined Shaft of Changhongling
Tunnel
XD2K0+000~XD2K0+370
Tunnel excavation completed 370 m
Spoil ground of Exit to Changhongling Tunnel
1# Inclined Shaft of Changhongling
Tunnel
XD1K0+000~XD1K1+300
Tunnel excavation completed 460 m
Spoil ground of 1# Inclined Shaft of Changhongling Tunnel
Exit to Fangdoushan
Tunnel
D8K163+430~ D8K160+976
Tunnel excavation completed 80 m
Gravel Plant at Exit to Fangdoushan Tunnel
Huayuan Tunnel in Fengdu County
D5K154+237
Excavation progress of 381 m, inverted arch completed 308 m and secondary lining completed
130 m
Spoil ground of Huayuan Tunnel
Xiongjialing Tunnel D5K148+026~D5K1
48+455 Tunnel excavation completed
170 m Temporary spoil ground of
Xiongjialing Tunnel
Entrance to D5K149+796~D5K153+260 Tunnel excavation completed Temporary spoil ground of
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 24
Shigangpo Tunnel 16 m Shigangpo Tunnel Exit to Shigangpo
Tunnel D5K153+250 0 m
Construction of main cave not started
Liziping Tunnel D5K156+904~D5K 158+360 D5K156+904~D5K157+292
Excavation of tunnel (1456 m in length) completed 368 m
Entrance to Fanddoushan
Tunnel
D8K158+512~ D8K160+971
Full-section primary support completed 125 m
Spoil ground of Xiaojin Village
Entrance to Nanbaidong Tunnel
D8K165+965~D8K 169+435
Full-section primary support completed 152 m
Spoil ground of Liaojiaba
Exit to Nanbaidong Tunnel
D8K172+960~D8K 169+465
Full-section primary support completed 186 m
Spoil ground of Exit to Nanbaidong Tunnel
Hujiapo Tunnel DK135+725~DK141+196
Transverse gallery completed 255 m, main cave at transverse gallery 50 m, and main cave at
the Exit 273 m
Transverse gallery spoil ground set for Entrance and Transverse
Gallery; one common spoil ground used for Exit and
Guanyinyan
Guanyinyan Tunnel DK141+330~DK145+720
Tunnel excavation at the Entrance completed 306 m,
main cave at the Exit not started construction
Entrance and Hujiapo using one spoil ground together, but spoil
ground of Exit not available.
Entrance to Daliang Tunnel DK124﹢720
Tunnel excavation completed 71.5 m
Spoil ground of Entrance
Inclined Shaft of Daliang Tunnel DK128﹢300 Timbering excavated 664 m Spoil ground of Inclined Shaft
Main Cave at the Exit to Daliang
Tunnel DK135﹢665
Tunnel excavation completed 269 m
Spoil ground of Exit
Parallel Heading at the Exit to Daliang
Tunnel DK135﹢662 Timbering excavated 559 m Spoil ground of Exit
Entrance to Zhoujiaping Tunnel DK183+865
Full-section excavated 90 m /
Exit to Zhoujiaping Tunnel DK187+705
Full-section excavated 280 m Beside Fangjiaya Super-major
Bridge
Super-major and major
bridges
Name Mileage Progress Remarks Fangjiaya 1# Major Double-track Bridge
DK188+548 3 bearing platforms completed and piling 620 m
/
Chenjiabao Longhe Major Double-track Bridge
D1K189+202 Construction not started Entering construction site
shortly Songziba Nanbinhe Major
Double-track Bridge D1K190+855 Construction not started Drawing unavailable
Huafeng Major Double-track Bridge
D1K195+576 Construction not started Drawing unavailable
Jiangchi Longhe Major Double-track Bridge
DK183+725 Construction not started Entering construction site
shortly
Shizhu Station 1# Major Four-track Bridge
D1K191+955 Construction not started Drawing unavailable
Shizhu Station Arrival and Departure 1# Major Four-track Bridge
Dd191+939 Construction not started Drawing unavailable
Shizhu Station 3# Major Four-track Bridge
D1K192+804 Construction not started Drawing unavailable
Shizhu Station 4# Major Four-track Bridge
D1K193+768 Construction not started Drawing unavailable
Tuzhuyan Major D1K196+915 Piling of manual-excavation /
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 25
Double-track Bridge piles 60 m Double-track Bridge at Fengdu Station, Fengdu
County
DK147+137.5~ DK147+837.95
4 bearing platforms completed and piling 350 m
/
Jinzhutan Major Bridge of Fengdu County
D5K153+262.60~D5K153+740.6
7 bearing platforms completed and piling 560 m
/
Longhe Major Bridge, Daqiaoshiban, Sanjian
Township, Fengdu County
D8K172+915.7~D8K173+136.85
Bearing platforms for 1# and 3# piers completed
/
Major Bridge of Sanjian Township, Fengdu County
D8K164+832.4~D8K165+086.79 Construction not started /
Lvchunba Major Bridge of Sanjian Township, Fengdu
County
D9K182+147.4~D9K183+037.42 Construction not started Drawing unavailable
Main borrow pits /spoil grounds
Location mileage Designed soil-borrowing and spoiling quantity and measures
Progress Implementation
status Remarks
Spoil grounds of various tunnel caves and inclined
shaft / 12×104m3
Protection engineering has not been started due to absence
of design drawing.
Tunnel spoil
Noise-sensitive points
Name Mileage Design
measures Implementation
status Remarks
Remarks
Acceptance inspection of expropriation of land has been completed for all construction sites. It is required to strengthen cleaning and water sprinkling to reduce fugitive dust emission from construction roads. Water leaking from tunnel shall be discharged after three-stage sedimentation in sedimentation tank. Environmental protection measures like vegetation protection at spoil ground have been implemented well. Up to now, no cultural relics have been found during the construction.
On-site investigation results of monitoring
The on-site investigation results of monitoring are: Fangdoushan tunnel: the construction site appears tidy and orderly; construction roads are arranged neatly with distinct border; billboards of environmental protection are available; garbage bins have been set up; three-stage sedimentation tank for sewage from production is available; there is only temporary protection, but on the whole no protection and water interception and drainage facility is available at spoil ground, which is prone to cause water and soil loss. Guanyinyan Tunnel: the common spoil ground is used for both Entrance to Guanyinyan Tunnel and Hujiapo Tunnel; absence of protection and water interception and drainage facility; sedimentation tank for sewage is available; there is guarantee system diagram of environmental protection and water & soil reservation; garbage bins and pools available for collection of garbage; and billboard of environmental protection has been erected.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 26
Table 5-5: Implementation Status of Environmental Protection for V Bid Section
Construction unit: China Railway 18th Bureau Group Co., Ltd.
Supervision unit: Changsha Zhongda Supervision Company
Construction cam
ps
Location Garbage Treatment Measures Sewage
Treatment Measures
Billboard of Environmental
Protection Remarks
Shuangqing Village, Nanbin Town, Shizhu
County
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department at regular intervals
Sedimentation tank, septic tank
and drainage facility
established
Available 150 staff
members. Camp self-built
Shiping Group, Shazi Village, Shazi Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department at regular intervals
Sedimentation tank, septic tank
and drainage facility
established
Available 210 staff
members. Camp self-built
Malanba Group, Xinglong Village, Shazi
Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department at regular intervals
Sedimentation tank, septic tank
and drainage facility
established
Available 130 staff
members. Camp self-built
Xiangshixi, Xinglong Village, Shazi Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department at regular intervals
Sedimentation tank, septic tank
and drainage facility
established
Available 160 staff
members. Camp self-built
Taoyuan Village, Shazi Town, Shizhu County
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department at regular intervals
Sedimentation tank, septic tank
and drainage facility
established
Available 280 staff
members. Camp self-built
Longyuan Village, Shazi Town, Shizhu County
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank
and drainage facility
established
Available
180 staff members.
Camp self-built
Tunnel more than 1000m in
length
Name Mileage Construction progress Remarks Wanshoushan
Tunnel DK199+480~DK212+954 Excavation of tunnel
completed: 539 m 4 spoil grounds are available for spoil disposal respectively
Shaziguan Tunnel
DK213+160~DK219+128 Excavation of tunnel completed: 210 m
2 spoil grounds are available for spoil disposal respectively
Exit to Shaziguan
Tunnel DK222+412~DK219+128 Excavation of tunnel
completed: 280 m Xiangshixi, Xinglong Village, Shazi Town
Xinwu Tunnel
DK222+459~DK223+253 Excavation of tunnel completed: 172 m
Malanba, Xinglong Village, Shazi Town
Entrance to Xiangjiaba
Tunnel
DK223+545~DK2226+800 Excavation of tunnel
completed: 100 m Shiping Group, Xinglong
Village, Shazi Town
Exit to Xiangjiaba
Tunnel
DK226+800~D1K233+370 Full-section timbering tunneling 220 m, and lining 12
m
Spoil ground of Taoyuan Village, Shazi Town, Shizhu
County Dazhaiping
Tunnel D1K230+163~D1K232+660 Construction not started Drawing not available now
Super-major and major
bridges
Name Mileage Construction progress Remarks Qingshiyan Major
Double-track Bridge DK199+026.83~DK199
+442.5 8 pile foundations poured /
Tuntianba Major Double-track Bridge
DK212+959.55~DK213+150.55 3 pile foundations poured /
Xiangjiaba Major Bridge DK223+253~DK223 +545 Construction not started Drawing not
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 27
available now
Xiaohekou Major Bridge D1K232+849~ D1K233+214
4 dig piles completed without pouring
/
Main borrow pits /spoil grounds
Location mileage Designed soil-borrowing and
spoiling quantity and measures
Progress Implementation
status Remarks
DK199+500
Total discarded waste slag of 52×104m3, occupying land of
55 mu and retaining wall available
3×104m3 Waiting for the
drawing of retaining wall
Spoil from Entrance to
Wanshoushan Tunnel
DK212+150
Total discarded waste slag of 60×104m3, occupying land of 129.2 mu and retaining wall
available
To be expropriated
Construction not started yet
Spoil from 1# Transverse Gallery of
Wanshoushan Tunnel
DK208+400
Total discarded waste slag of 50×104m3, occupying land of 56.5 mu and retaining wall and drainage ditch available
0×104m3 Waiting for the
drawing of retaining wall
Spoil from 2# Transverse Gallery of
Wanshoushan Tunnel
DK213+300
Total discarded waste slag of 26.3×104m3, occupying land of 45.8 mu and retaining wall
available
3.5×104m3 Waiting for the
drawing of retaining wall
Spoil from Exit to Wanshoushan
Tunnel
DK213+350DK212+940
Total discarded waste slag of 41.7×104m3, occupying land of 60 mu and retaining wall
available
To be expropriated
Construction not started yet
Spoil from Exit to Wanshoushan
Tunnel
DK213+900
Total discarded waste slag of 45×104m3, occupying land of 70 mu and retaining wall and
drainage ditch available
To be expropriated
Construction not started yet
Spoil from Entrance to Shaziguan
Tunnel
DK216+500
Total discarded waste slag of 42.5×104m3, occupying land of 80 mu and retaining wall and drainage ditch available
3.0×104m3 Waiting for the
drawing of retaining wall
Spoil from Inclined Shaft of
Shaziguan Tunnel
Spoil ground of Exit to Shaziguan Tunnel
Total discarded waste slag of 42.6×104m3, occupying land of 73.708 mu and retaining
wall available to be removed after completion
3.6×104m3 Retaining wall
under construction
Spoil ground of Shaziguan Exit
Spoil ground of Xinwu Tunnel
Total discarded waste slag of 11×104m3, occupying land of 26.095 mu and retaining wall available to be removed after
completion
2.2×104m3 Retaining wall
under construction
Spoil ground of Xiwu Tunnel
Slag yard of Exit to Xiangjiaba Tunnel
Total discarded waste slag of 44×104m3, occupying land of 77.791 mu and retaining wall available to be removed after
completion
3.1×104m3 Retaining wall
under construction
Spoil ground of Xiangjiaba Entrance
Spoil ground of Exit to Xiangjiaba Tunnel
Total discarded waste slag of 58.5×104m3, occupying land of 59.8 mu, reclamation of 21.8 mu, vegetation of 38.0
mu
Excavation of foundation
started at spoil ground
Retaining wall under
construction
Spoil from Exit to Xiangjiaba
Tunnel
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 28
Dazhaiping Tunnel
Total discarded waste slag of 44×104m3, of which
15×104m3 at Entrance shall be discarded at Taoziyuan spoil ground, and spoil ground for Exit not to be determined yet.
The spoil ground shall be restored after completion.
Spoil ground not put into use
yet /
Construction drawing
unavailable
Slag yard of 1# and 2# Taoziyuan Tunnel
Total discarded waste slag of 5×104m3, occupying land of 13 mu and shall be restored
after completion
Excavation of foundation
started at spoil ground
/
Noise-sensitive points
Name Mileage Design
measures Implementation
status Remarks
Remarks
Acceptance inspection of expropriation of land has been completed for all construction sites. It is required to strengthen cleaning and water sprinkling to reduce fugitive dust emission from construction roads. Water leaking from tunnel shall be discharged after three-stage sedimentation in sedimentation tank. Environmental protection measures like vegetation protection at spoil ground have been implemented well. Up to now, no cultural relics have been found during the construction.
On-site
investigation results of
monitoring
The on-site investigation results of monitoring are: Wanshoushan tunnel: the construction site appears tidy and orderly; construction roads are arranged neatly with distinct border; watering carts are provided; air compressor stored inside air compressor room; billboards of environmental protection are available; garbage bins have been set up at construction site; three-stage sedimentation tank for sewage from production is available; no protection and water interception and drainage facility is available at spoil ground, which is prone to cause water and soil loss. Construction camp of Wanshoushan tunnel: standardization construction of construction camp goes well; there is billboard of environmental control system; garbage bins and pools available for collection of garbage; and septic tank available for treatment of sewage.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 29
Table 5-6: Implementation Status of Environmental Protection for VI Bid Section
Construction unit: China Railway No. 5 Engineering Group Co., Ltd.
Supervision unit: Changsha Zhongda Supervision Company
Construction cam
ps
Location Garbage Treatment Measures Sewage Treatment Measures
Billboard of
Environmental
Protection
Remarks
Longyuan Village, Shazi Town, Shizhu County
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, and drainage facility
established Available
422 staff members.
Camp self-built
Tuanbazi, Tianhe Village, Lengshui Township, Shizhu
County
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank and
drainage facility established
Available
144 staff members.
Camp self-built
Balong Village, Lengshui Township,
Shizhu County
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank and
drainage facility established
Available
161 staff members.
Camp self-built
Shiyu Village, Fengmu Township, Chongqing
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank and
drainage facility established
Available
240 staff members.
Camp self-built
Eighth Group, Baiyang Tang Village, Wangying
Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank and
drainage facility established
Available
260 staff members.
Camp self-built
Liaojiacao Village, Wangying Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank and
drainage facility established
Available
185 staff members.
Camp self-built
Qingjiangyuan Village, Wangying Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank and
drainage facility established
Available
420 staff members.
Camp self-built
Jiaoyitai Village, Wangying Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank and
drainage facility established
Available
150 staff members.
Camp self-built
Hujiaba Village, Wangying Town
Set up garbage bin for centralized collection and uniform disposal by
local environmental sanitation department
Sedimentation tank, septic tank and
drainage facility established
Available
120 staff members.
Camp self-built
Working crew from Xiushui Village, Wangying Town,
Lichuan City
Set up garbage bin for centralized collection and uniform disposal by
logistic personnel
Sedimentation tank, septic tank and
drainage facility established
Available 125 staff members. Camp rent
Working crew from Xiangshu Village, Wangying Town,
Lichuan City
Set up garbage bin for centralized collection and uniform disposal by
logistic personnel
Sedimentation tank, septic tank and
drainage facility established
Available 136 staff members. Camp rent
No. 3 working crew from Liangwu Township,
Lichuan City
Set up garbage bin for centralized collection and uniform disposal by
logistic personnel
Sedimentation tank, septic tank and
drainage facility established
Available 128 staff members. Camp rent
Tunnel more than 1000m in
length
Name Mileage Construction progress Remarks
Dutingshan Tunnel
DK236+211- DK244+100
Excavation of tunnel completed for Entrance 219.4 m, 39.9 m for 1# inclined shaft and
47.31 m for 2# inclined shaft.
Spoil ground of Dutingshan Tunnel Entrance, 1# and 2#
Inclined Shafts Dutingshan DK244+100- Excavation of tunnel completed at Exit 100.9 Spoil ground of Exit to
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 30
Tunnel DK245+950 m Dutingshan Tunnel
Liziba Tunnel DK246+040- DK248+249
Excavation of tunnel completed at Entrance 68.1 m
Excavation of tunnel completed at Exit 41.7 m
Spoil ground of Exit to Yujia Tunnel
Entrance to Yujia Tunnel
DK248+874- DK252+365
Excavation of tunnel completed at Entrance 105.3 m
Excavation of tunnel completed at Exit 88.3 m
Spoil ground of Entrance to Fubaoshan
Tunnel
Fubaoshan Tunnel
DK254+983- DK261+207
Excavation of tunnel completed at Entrance 167 m
Excavation of tunnel completed at Exit 87 m
Spoil ground of Exit to Fubaoshan Tunnel
Super-major and major
bridges
Name Mileage Construction progress Remarks Tongguping Major
Double-track Bridge D1K233+377.97- D1K233+610.50
40 pile foundations and 3 bearing platforms completed
/
Shaziguan 1# Major Double-track Bridge
D1K233+707.95- D1K233+910.95
48 pile foundations, 5 bearing platforms and 2 piers completed
/
Shaziguan 2# Super-major
Four-track Bridge
DK234+218.20- DK234+785.8 Construction not started
Drawing not available now
Longdong Super-major Bridge
DK252+745.96- DK253+526.73
54 bored piles and 2 bearing platforms completed
/
Tangjiayuanzi Major Bridge
DK254+540.65- DK254+867.3
14 bored piles and 1 bearing platform completed
/
Huodiping Super-major
Double-track Bridge
DK261+962.77- DK263+598.18
380 bored piles and 1 bearing platform completed
/
Cunjiayuanzi 1# Major Double-track
Bridge
DK264+383- DK265+042-
44 pile foundations and 2 bearing platforms completed
/
Cunjiayuanzi 2# Major Double-track
Bridge
DK264+801- DK265+247
62 pile foundations and 2 bearing platforms completed
/
Huangshangou Major Double-track Bridge
DK265+250- DK265+820 8 pile foundations completed /
Jiangjiadayuanzi Super-major
Double-track Bridge
DK265+827- DK266+145 43 pile foundations completed /
Lijiagou Major Double-track Bridge
DK266+617- DK267+302 Hole forming 200 m /
Daping Major Double-track Bridge
DK267+164 DK267+951 Hole forming 360 m /
Main borrow pits /spoil grounds
Location mileage Designed soil-borrowing and spoiling quantity and measures
Progress Implementation
status Remarks
Spoil ground of DK233+8001
Roadbed
Total discarded waste slag of 30×104m3, and restoring native
vegetation after completion 3.15×104m3
Construction not started
No construction drawing
Spoil ground of DK234+2002
Roadbed
Total discarded waste slag of 20×104m3, and restoring native
vegetation after completion 1.67×104m3
Construction not started
No construction drawing
Spoil ground of Entrance to
Dutingshan Tunnel DK236+100
Total discarded waste slag of 45×104m3, and restoring native
vegetation after completion 2.95×104m3
Temporary retaining wall
built
No construction drawing
Spoil ground of 1# Inclined Shaft of
Total discarded waste slag of 34×104m3, and restoring native
2.34×104m3 Construction not started
No construction drawing
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 31
Dutignshan Tunnel vegetation after completion Spoil ground of 2# Inclined Shaft of
Dutignshan Tunnel
Total discarded waste slag of 47×104m3, and restoring native
vegetation after completion 4.51×104m3
Construction not started
No construction drawing
Spoil ground of Exit to Dutignshan Tunnel
Total discarded waste slag of 40×104m3, with filling 8 m. Less farmland is occupied, building retaining wall and restoring native vegetation
after completion
3.5×104m3 Retaining wall
under construction
Spoil from Exit to Dutingshan
Tunnel and Entrance to
Liziba Tunnel
Spoil ground of Entrance to Yujia
Tunnel
Total discarded waste slag of 30×104m3, with filling 7 m. Less farmland is occupied, building retaining wall and restoring native vegetation
after completion
3.2×104m3 Retaining wall
under construction
Spoil from Entrance to
Yujia Tunnel and Exit to
Liziba Tunnel
Spoil ground of Exit to Yujia Tunnel
Total discarded waste slag of 25×104m3, with filling 8 m. Less farmland is occupied, building retaining wall and restoring native vegetation
after completion
3.0×104m3 Retaining wall
under construction
Spoil from Exit to Yujia Tunnel and Zhoujiawan
Tunnel
Spoil ground of Entrance to
Fubaoshan Tunnel
Total discarded waste slag of 35×104m3
2.65×104m3 Retaining wall
under construction
Spoil from Entrance to Fubaoshan
Tunnel
Spoil ground of Exit to Fubaoshan Tunnel
Total discarded waste slag of 26×104m3
1.7×104m3 Retaining wall
completed
Spoil from Exit to Fubaoshan
Tunnel
Spoil ground of Inclined Shaft of
Fubaoshan Tunnel
Total discarded waste slag of 19.8×104m3
0.32×104m3 Retaining wall
under construction
Spoil from Inclined Shaft of Fubaoshan
Tunnel
Spoil ground of Yaojia Tunnel
Total discarded waste slag of 12.6×104m3
0.18×104m3 Retaining wall
under construction
Spoil from Exit to Yaojia Tunnel
Exit to Yejiangou Tunnel
DK264+280
Total discarded waste slag of 2.5×104m3, occupying land of 10 mu with filling 8 m. Less forestland and farmland is
occupied, and restoring native vegetation after completion
0.3×104m3 Retaining wall
under construction
Spoil from Entrance to Yejiangou Tunnel and
Major Bridge
DK272+850 Spoil Ground
Total discarded waste slag of 12×104m3, occupying dry land of 8.3 mu. Building retaining
wall and restoring native vegetation after completion
7.5×104m3
Retaining wall under
construction and drainage
ditch completed
Spoil from clearing roadbed
DK270+400 Spoil Ground
Total discarded waste slag of 8×104m3, occupying dry land of 12 mu. Building retaining
wall and restoring native vegetation after completion
1.9×104m3
Retaining wall under
construction and drainage
ditch completed
Spoil from Pengjiapo
Tunnel
Noise-sensitive points
Name Mileage Design
measures Implementation
status Remarks
Remarks 1. Fugitive dust from construction site and roads has been resolved by sprinkling water at construction site
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 32
and if more dust at construction site, conduct the sealing treatment (e.g. Mixing station) with more-frequently watering to keep ground surface wet. Another way to reduce dust adopted is the hardening treatment of site roads and construction site.
2. Leaking water of tunnels shall be flowed into sedimentation tank and then discharged up to the standard. 3. Spoil of tunnel shall be discarded at spoil grounds along which retaining walls are being constructed. 4. No cultural relics have so far been found at the whole zone of piping construction. 5. Color-bar cloth shall be used to cover materials entering the site or placed in storehouse.
On-site investigation results of monitoring
The on-site investigation results of monitoring are: Dutingshan tunnel: the construction site appears tidy and orderly; construction roads are arranged neatly with distinct border; watering carts are provided; air compressor stored inside air compressor room; billboards of environmental protection are available; garbage bins have been set up at construction site; three-stage sedimentation tank for sewage from production with billboards is available; temporary retaining wall is being built at spoil ground. Living areas and offices of 1# Inclined Shaft Team of Dutingshan Tunnel: standardization construction of construction camp goes well; there is billboard of environmental control system; carrying out greening; garbage bins and pools available for categorized collection of garbage; and septic tank available for treatment of sewage.
5.2 Results and Analysis (1) Internal management Each construction unit has established the internal management system in accordance with the requirements, set up the organizational structure and measures for environmental protection, arranged the full-time/part-time environmental protection management personnel and defined the duties and responsibilities of each department. (2) Construction of tunnel Of the construction of tunnel, the main issues are the disposal of dreg from the tunnel and the protection of construction platform. (3) Construction of bridge Most of the bridges have not started their construction and are still in preparation stage. Each unit has arranged the slurry sedimentation tank for the bored piles. (4) Protection of construction pavements The construction pavements set up by each construction unit are normal and are maintained by specially-assigned people. Water spraying vehicles are equipped by the construction units to prevent the dust pollution. (5) Construction camp site Garbage bins and tanks are arranged for each construction camp site. The domestic garbage is collected and sent to the local environment sanitation administrative department for treatment. The railway line is situated in the mountainous regions with many bridge-tunnel connection sections. Pay attention to the protection of side slope at construction camp sites and the construction sites. (6) Bulletin board All construction units have set up Bulletin boards at the construction camp sites and the construction sites, but they limit themselves to the propaganda of measures for environmental protection and administrative system of environmental protection and have not arranged the signs that can let the public around know about the person in charge of the environment protection for this construction section and the telephone number for complaint of environmental protection.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 33
6. Popularization-worthy Measures as well as Problems and Suggestions
6.1 Popularization-worthy Measures (1) The setup of roads and construction sites is standard and the boundary is clear for Paihuadong
Tunnel and Liangchanghe Mixing Station under China Railway 12th Bureau Group Co., Ltd.. (2) Side slope had been protected by hydroseeding at the construction site of Huangcaoshan
Tunnel under China Railway 11th Bureau Group Co., Ltd., combining slope setup with planting.
(3) The setup of the construction site of Jianfengding Tunnel under China Zhongtie Major Bridge Engineering Group Co., Ltd. is standard, harmonizing with natural landscape; Retaining wall was under construction for Caijiagou Super-major Bridge to prevent water and soil loss effectively.
(4) Categorized collection of garbage is adopted by China Railway Tunnel Group Co., Ltd. for the construction site of Fangdoushan tunnel.
(5) The setup of the construction site of Wanshoushan Tunnel under China Railway 18th Bureau Group Co., Ltd. is standard, and posters of environmental protection are put up at the construction camp.
(6) Retaining wall and water interception and drainage facility were under construction for spoil ground of Dutingshan Tunnel under China Railway No. 5 Engineering Group Co., Ltd., and slope was protected by combing the slope setup with planting; large coverage area of forestation is available.
6.2 Existing Problems and Improvement suggestions (1) Each unit has not defined the person in charge of the environmental protection and the
supervision telephone number on the billboards on the construction site. It is suggested that they should be publicized on billboards as soon as possible so that the public can make supervisions.
(2) It is found during this on-site inspection that no retaining walls or water interception and drainage facilities have been arranged for the spoil of each tunnel. Each unit is required to make retaining walls before the disposal of spoil from each tunnel and enhance the retaining walls and water interception and drainage facilities of spoil grounds.
(3) It is suggested that oil tanks out of use be removed from the construction sites; harden the ground surface on which oil tanks are placed and set cofferdam and devices for collecting used oil; oil tanks be placed together on the hardened surface with cofferdam, and oil groove provided for temporary use of oil tanks; shelters are available for these places so as to prevent pollution caused by loss of used oil in the rain.
(4) Chongqing-Lichuan Railway Construction Co., Ltd. is suggested to require the construction units to setup billboards of environmental protection at the construction boundary prior to the construction at key ecological environmental protection zones including water resource protection zones, natural preservation zones and scenic spots, with the purpose to remind the construction staff of entering the environment-sensitive regions, and put forward precautions on environmental protection.
(5) It is suggested that Chongqing-Lichuan Railway Construction Co., Ltd. push forward the supervision units and construction units for the project to carry out the self-checks of side slope protection for the spoils of tunnel, construction sites and camps so as to reduce water and soil loss.
(6) In accordance with the requirements from Ministry of Environmental Protection, it is suggested that Chongqing-Lichuan Railway Construction Co., Ltd. request the supervision units of this project to report the environmental protection supervision work periodically and submit the summary report of environmental protection supervision after completion of this project.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 34
Photo 1: Training on environmental monitoring Photo 3: Construction site of Paihuadong tunnel under China Railway 12th Bureau Group Co., Ltd. Photo 5: Guarantee system diagram of environmental protection and water & soil reservation by China Railway 12th Bureau Group Co., Ltd
Photo 2: Construction roads for Paihuadong tunnel under China Railway 12th Bureau Group Co., Ltd. Photo 4: Slope of construction site of Paihuadong tunnel under China Railway 12th Bureau Group Co., Ltd. (absence of protection) Photo 6: Construction site of mixing station under China Railway 12th Bureau Group Co., Ltd
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 35
Photo 7: Watering cart of China Railway 11th Bureau Group Co., Ltd Photo 9: Construction site of mixing station at Changshou North under China Railway 11th Bureau Group Co., Ltd.(messy)
Photo 11: Spoil from Huangcaoshan tunnel under China Railway 11th Bureau Group Co., Ltd. (absence of protection)
Photo 8: Sedimentation tank for sewage from mixing station at Changshou North under China Railway 11th Bureau Group Co., Ltd.(messy) Photo 10: Construction site of Huangcaoshan tunnel under China Railway 11th Bureau Group Co., Ltd Photo 12: Garbage tanks at the construction site of Huangcaoshan tunnel under China Railway 11th Bureau Group Co., Ltd.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 36
Photo 13: Protection measures on oil penetration from air compressor at the construction site of China Railway 11th Bureau Group Co., Ltd
Photo 15: Construction of 9# pier foundation of Hanjiatuo major bridge under China Zhongtie Major Bridge Engineering Group Co., Ltd. Photo 17: Construction site of Jianfengding tunnel under China Zhongtie Major Bridge Engineering Group Co., Ltd
Photo 14: Sedimentation tank for slurry from drilling pile construction under China Railway 11th Bureau Group Co., Ltd Photo 16: Spoil protection for 22# pier of Caijiagou Super-major bridge under China Zhongtie Major Bridge Engineering Group Co., Ltd Photo 18: Sedimentation tank for sewage from Shijiapo tunnel under China Zhongtie Major Bridge Engineering Group Co., Ltd
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 37
Photo 19: Garbage tanks at the construction site of Jianfengding tunnel under China Zhongtie Major Bridge Engineering Group Co., Ltd. Photo 21: Spoil from Fangdoushan tunnel under China Railway Tunnel Group Co., Ltd. (absence of protection) Photo 23: Sedimentation tank for sewage from Fangdoushan tunnel under China Railway Tunnel Group Co., Ltd.
Photo 20: Construction roads for Shijiapo tunnel under China Zhongtie Major Bridge Engineering Group Co., Ltd. Photo 22: Temporary protection for spoil from Fangdoushan tunnel under China Railway Tunnel Group Co., Ltd Photo 24: Construction roads of China Railway Tunnel Group Co., Ltd.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 38
Photo 25: Billboard for environmental protection of China Railway Tunnel Group Co., Ltd Photo 27: Construction site of Wanshoushan tunnel under China Railway 18th Bureau Group Co., Ltd Photo 29: Sedimentation tank for sewage from Wanshoushan tunnel under China Railway 18th Bureau Group Co., Ltd
Photo 26: Sedimentation tank for sewage from Guanyinyan tunnel under China Railway Tunnel Group Co., Ltd. Photo 28: Garbage tanks at the construction site of China Railway 18th Bureau Group Co., Ltd. Photo 30: Billboard for environmental protection of China Railway 18th Bureau Group Co., Ltd.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 39
Photo 31: Side slope protection along the entrance to 1# transverse gallery of Wanshoushan under China Railway 18th Bureau Group Co., Ltd Photo 33: Living quarter at the construction camp of China Railway 18th Bureau Group Co., Ltd. Photo 35: Billboard for environmental initiatives of pollution prevention and discharge control by China Railway No. 5 Engineering Group Co., Ltd
Photo 32: Office at the construction camp of China Railway 18th Bureau Group Co., Ltd Photo 34: Billboard for environmental control system of China Railway No. 5 Engineering Group Co., Ltd. Photo 36: Afforestation of construction camp of China Railway No. 5 Engineering Group Co., Ltd.
Environmental Monitoring Report on the New Chongqing-Lichuan Railway Development Project (2009.8)
Beijing OASIS Environmental Protection Technology Co., Ltd. 40
Photo 37: Sedimentation tank for sewage from Dutingshan tunnel under China Railway No. 5 Engineering Group Co., Ltd. Photo 39: Spoil ground for Dutingshan tunnel under China Railway No. 5 Engineering Group Co., Ltd. (retaining wall under construction) Photo 41 Construction camp of China Railway 12th Bureau Group Co., Ltd
Photo 38: Side slope protection at the construction site of Dutingshan tunnel under China Railway No. 5 Engineering Group Co., Ltd. Photo 40: Categorized collection of garbage at the construction camp of China Railway No. 5 Engineering Group Co., Ltd Photo 42 Water sprinkling at the construction site of China Railway 12th Bureau Group Co., Ltd.