Environmental Monitoring Report Semi-Annual Report No. 3 July 2013
VIE: Yen Vien-Lao Cai Railway Upgrading Project
Prepared by CDM Smith-DBI JV Associates, Inc. for Viet Nam Railway under the Ministry of Transport of Vietnam, and the Asian Development Bank.
CURRENCY EQUIVALENTS
(as of 1 July 2013)
Currency unit –
dong (D)
D1.00 = $0.0000472 $1.00 = VND21,170
ABBREVIATIONS ADB – Asian Development Bank AFD – Agency Francoise de Development DONRE – Department of Natural Resources and Environment EMP – environmental management plan IEE – initial environmental examination
NOTE In this report, "$" refers to US dollars unless otherwise stated.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
VIETNAM RAILWAY (VNR)
Under MINISTRY OF TRANSPORT
SUPERVISION CONSULTANTS’ SERVICES
FOR
YEN VIEN - LAO CAI UPGRADING PROJECT
SEMI-ANNUAL ENVIRONMENTAL MONITORING
PROGRESS REPORT NO. 03
JULY 2013
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
2
Contents
1. Introduction ........................................................................................................ 3
2. Incorporation of Environmental Requirements into Project Contractual Arrangements................................................................................................................. 3
3. Scope and Reporting period .............................................................................. 5
4. Methodology ........................................................................................................ 5
5. Project Status ...................................................................................................... 5
6. Compliance with EMP ..................................................................................... 12
6.1 Environmental Performance ............................................................................. 12
6.2. Environmental Effects Monitoring .................................................................. 19
7. Environmental Permits/Clearances ................................................................ 20
8. Complaints ........................................................................................................ 20
9. Environmental Training/Orientation ............................................................. 20
10. Issues for Further Action .................................................................................. 20
11. Conclusion .......................................................................................................... 23
12. Annex .................................................................................................................. 23
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
3
THE SECOND SEMI‐ANNUAL ENVIRONMENTAL MONITORING REPORT
(FROM JANUARY TO JUNE 2013)
1. Introduction
The railway from Yen Vien station (Hanoi) to Lao Cai province ‐ the border with China
and one branch from Pho Lu to Xuan Giao is an important transportation system for
mountainous northwest. The current railway contains sharp curves and weak bridges
which causes train speed reduction. Besides, the track is lack of maintenance for a long
time; many bridges should be upgraded and replaced as soon as possible.
Asian Development Bank (ADB), Agency Françoise de Development (AFD) and
Direction Generable du Tresor et de la Politique Economique (DGPTE) have assessed
and agreed to provide a loan for upgrading railway Yen Vien ‐ Lao Cai project.
The project objective is upgrading Yen Vien ‐ Lao Cai railway (estimation of 285km
length) in order to improve the transportation capacity and commercial development
in the northern mountainous area. The Project will increase trading profits between
Vietnam and China, especially within the Kunming area.
Beside the positive impacts the project also has negative impacts on the local
environment. Therefore the project environmental management plan is implemented
during the project, in order to:
- Apply appropriate measurement to minimize the negative impacts on environment
complying with the current Vietnam environmental regulations and laws and
environmental policies of international organizations, if necessary;
- Use an appropriate organizational structure in environmental protection throughout
construction period of the Project to ensure that the mitigation measures proposed in
the Environmental Impact Assessment Report or IEE and EMP are effectively
implemented;
- Planning to deal with the environmental emergencies and accidents that may occur
during the implementation of the Project;
- The Environmental Management Plan shall be implemented by the Contractors during
the work execution and shall be monitored by the Engineer and the Employer on daily
basis.
2. Incorporation of Environmental Requirements into Project Contractual
Arrangements
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
4
To implement the requirements of the project environmental plan effectively, the
tasks/work are arranged as follows:
- Supervision consultant and Independent contractors environmental monitoring:
i) Carry out baseline environmental monitoring and monitor implementation
of the environmental management plans, including any required sampling
and testing to ascertain baseline and in‐construction noise pollution, air
quality, water quality and solid waste disposal requirements.
ii) Report on any difficulties in the monthly and quarterly progress reports and
recommend the implementation of amelioration measures to be taken to
reduce adverse impacts.
iii) To monitor the baseline environment in the project area the construction
phase.
iv) Reporting the status of the environment and propose the application of
measures to minimize the impact on the surrounding environment.
- Contractors (including subcontractors):
i) Implementation of environmental monitoring of air, water, solid waste at
the construction site and areas affected:
a. Monitoring number, status, changes in negative impacts’ origin arising
from construction site to environment quality;
b. Subscribe flow/ volume/ frequency and period measurement, sampling
and analysis of pollution parameters, characteristic of the waste arising
from the facility operation (waste water, waste gas and solid waste,
hazardous waste, noise, vibration, and other criteria);
c. Periodic measurement, sampling and analysis of the parameters related
to the negative environmental impacts origin in the area (surface water,
groundwater, air, soil);
d. Monitoring of changes and measure the current status factors (if
relevant): erosion, sliding, falling, landslides, land subsidence; river
bank erosion, stream, lake; sedimentation of rivers, streams, reservoir;
changing the water surface and underground water; and other impacts.
ii) To monitor and inspect food, and sanitary conditions at construction site.
iii) Report on construction activities at the site and the current state of the
environment during the construction process, the comments complained
of the surrounding community.
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
5
iv) Adjust the construction activities; apply measures to minimize
environmental impact.
3. Scope and Reporting period
Environmental monitoring report for the first six months of year (from January to June
2013) will aggregate the environmental performance of Yen Vien ‐ Lao Cai railway
upgrading projects in general and environmental control activities, the environmental
mitigation measures are applied to the construction bid package. The report reviews
the compliance of environmental activities with EMP and proposes activities in the
future environment in order to control and minimize negative environmental impacts.
4. Methodology
The project environmental monitoring report bases on the following methods:
- Methods listing: Specify the full impacts caused by the project's activities.
- Methods of synthesis compare: Synthesis of data collected, comparing with
environmental standards then assess the current state of environmental quality in
the studied area, forecast evaluate and propose solutions to minimize the project
works environmental impact.
- Field survey method: field sampling, laboratory analysis of samples in accordance
with the provisions of VN standards to determine the environmental quality
parameters (including: air quality survey, noise, water quality, wastewater
composition, ecosystem project area). Field visits and compare with the
regulations on sanitary conditions, labor safety, fire protection, electrical safety...
- Method of assessment: the calculation load of pollutants from the production
activities of the project.
5. Project Status
The project status as in table 1.
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
6
Table 1. The status of project
No Name of works Construction activities
Ongoing site works During the previous
months For the subsequent months
Construction of Bridges
Ngoi Sen Bridge (Km 145+950)
Finished scaffolding installation; Installed bundle beam rail; Constructed wing walls.
Receive rubble stone Install steel girder, Casting concrete for girder Construct retaining wall completed 7/2013
Van Phu Bridge (Km 148+920)
Finished bored piles; Finished 2 abutments; Transport materials for scaffolding installation
Casting concrete ditch, embankment sand
Transport and install steel girder onsite. Casting concrete for abutments cap to place the girder, Casting for girder, Completed 6/2013
Dao Thinh Bridge (Km 171+414)
Finished 1 trial pile driving for Lao Cai abutment
Replaced girder, abutment repaired in Yenvien side
Casting and massive driving at Lao Cai abutment Improve the Hanoi abutment due to the crack Completed 8/2013
Thac Thu bridge (Km 173+287)
Finished Construction Casting concrete seg. 2 body wall and top slab
Land acquisition and excavate ditches at upstream
Con Tran Bridge (Km 173+960)
Finished concrete casting for U‐shaped beam; Finished Lao Cai abutment; Improved Yen Vien abutment
The new bridge and new abutment
New construction for Yen Vien abutment Laugh main upstream
Mau A Bridge (Km 188+050)
Reinforce 2 bridge approaches; steel girder transportation; install steel girder.
Replaced girder, abutment repaired. Repaired abutment covering and wall.
Repair the scaffolding according to approved method statement, Labor safety must be improved Install steel girder Casting concrete for composite girder Upgrade and repair the abutment.
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
7
No Name of works Construction activities
Ongoing site works During the previous
months For the subsequent months
Khe Hoi bridge (Km 189+000)
Casting trial pile. Trial pile driving 1st time.
Replaced girder, renew two abutment.
2nd trial pile driving is expected on 2nd June. Need strict supervision. Massive pile driving will be proceeded.
Khai Bridge (Km 195+394)
Gather materials on site Install scaffolding; Make access road
Install scaffolding; Assemble steel girder.
Tro Bridge (Km 204+825)
Install scaffolding Make access road
Replaced girder, abutment repaired. Repaired abutment covering and wall.
Install steel girder and scaffolding. Casting concrete for composite girder. Upgrade and repair the abutment.
Phuc Minh bridge (Km 214+742)
Assemble steel girder; transport steel girder
Install scaffolding Install steel girder. Casting concrete for steel girder.
Bau bridge (Km 221+953)
Assemble steel girder
Replaced girder, abutment repaired. Repaired abutment covering and wall.
Assemble and transport steel girder to site.
Ly bridge (Km 225+170) Transport scaffolding materials
‐ Install scaffolding and transport steel girder to site
Construction of embankment
Section 6. Slope Protection (Km178+632 ‐ 179+193) 561m, 349m
Under construction.
Treat weak embankment, mud raising and water stagnancy. Excavate and replace soil, place geotextile woven fabric, construct
Continue the work. Mobilize more materials.
Section 7. Slope Protection (Km179+905 ‐
Casting concrete border for gabion and lay out gabion for the slope.
Finish the 2 remaining segments and finalize the item on 10th June.
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
8
No Name of works Construction activities
Ongoing site works During the previous
months For the subsequent months
180+275) 370m, 90m underground drainage ditches, top and longitudinal ditches. Treat erosion, settlement and slide of slope: construction of retaining wall and reinforcement of slope.
Section 8: from Km182+158 to Km 182+566
Completed 95% and is finalizing
Continue the work. Mobilize more materials.
Section 9. Slope Protection (Km 182+158 – 182+560)
Under construction Continue the work. Mobilize more materials.
Section 14. Slope Protection (Km188+196 ‐ 188+297) 101m, 63m
Under construction Continue the work. Mobilize more materials. Revise the differences between shop drawing and actual site condition.
Section 17. Slope Protection (Km195+783 ‐ 196+155) 372m, 62m+163
Under construction Continue the work. Mobilize more materials.
Section 19. Slope Protection (Km199+978 ‐ 200+471) 493m, 145m
Under construction Continue the work. Mobilize more materials.
Section 21. Slope Protection (km 225+000 – 225+323).
Under construction Continue the work. Mobilize more materials.
Construction of the culverts
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
9
No Name of works Construction activities
Ongoing site works During the previous
months For the subsequent months
- Pipe Culvert, D=1.0m (Km194+654.95)
- Pipe Culvert D=1.0m (Km197+040)
- Pipe Culvert D=1.0m (Km197+195)
- Pipe Culvert D=1.0m (Km197+390)
- Pipe Culvert D=1.0m (Km202+988)
- Pipe Culvert D=1.0m (Km226+000,225+652.65)
Submit method statement. Make temporary girder Demolish old culvert Install framework. Casting concrete the foundation and install the culvert. Backfilling after construction. Demolish old culvert
Clearance, excavation, installation of culverts
Completion of the work content in the approved construction plans
Construction of Station
1. Van Phu Station‐Km148+350:
‐ Track work
Soil filling K95 and K98, and excavate the foundation for precast ditches R50, R60 along the track.
Adjustment of general layout terminal, hold the opening of the station and way operational. Adding one road tail track and the road into the station.
Soil backfilling is striving to finish on 15th June. Soil filling for Van Phu station must wait for the completion of track no. 4, 5, 6.
‐ Architecture part Finished incurred construction:
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
10
No Name of works Construction activities
Ongoing site works During the previous
months For the subsequent months
- Temporary generator house and sanitary unit.
- Transfer the existing generator to the new generator house, and the sanitary unit is operating.
‐ Signaling and communication
Completed the capacity profiles
Make inspection procedures and inspection minutes for quantity assessment of completed items. To finish the connection procedures for signaling and telecommunication.
‐ Power supply Review capacity profiles for materials and suppliers
Complete capacity profiles. Complete inspection procedures and connection procedures. Inspect the transformer station.
2. Mau Dong Station (Km 194+895)
Casting concrete for retaining wall segment 1 to 12
Carry out excavation and embankment
Continue and finish the remaining segments. Need land acquisition for Mau Dong station (1 household). Commence backfilling for the foundation of Mau Dong Station.
3. Lam Giang Station (Km 210+000)
Constructing the retaining wall at the South of the Station. Casting concrete for the platform between 1‐II, II‐3. Backfilling for the foundation at the North of the Station.
Carry out excavation and embankment
Complete backfilling for the foundation at the North of the Station. Handle the soil filling for extension of track no.1. Construct new turnout guard house before commencing track work for extension track. Prepare materials for track work.
Track Work
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
11
No Name of works Construction activities
Ongoing site works During the previous
months For the subsequent months
Realignment section km 169+700 – Km 173+700
Excavate the foundation Soil and sand backfilling. Construct slope protection 5A, 6A, 7A, 8
Continue the construction of slope protection 5A, 6A, 7A, 8. Track work Km 171+410 – Km 172+410: replace rail P50/PC sleepers. Culvert must be constructed in sync with track work. Supervise the safety issues
Upgrading section Km 148+250 – Km 155+250
Replace rail P50/PC sleepers from Km 149+900 – Km 150+500: add more ballast.
Continue the track work Km 150+500 – Km 155+250.Supervise the safety issues
Upgrading section Km 155+250 – Km 165+000
Track work Km 163+451‐Km 164+051
Continue the track work Km 164+051 – Km 165+000.Supervise the safety issues
Upgrading section Km 194+750 – Km 201+750
Km 198+300‐Km 198+900: Replace rail P50/PC sleepers
Continue the track work Km 198+900 – Km 201+750.Supervise the safety issues
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
12
6. Compliance with EMP
6.1 Environmental Performance
6.1.1. Compliance with environmental mitigation measures
Evaluation of the implementation of environmental mitigation measures are summarized in Table 2.
Table 2 ‐ Table summarizing compliance with ALL environmental mitigation measures specified in the EMP
Environmental Impact/Issue of works
item EMP requirement on Mitigation Measures
Compliance Attained
(Yes, No, Partial)
Comment on Reasons for Partial or Non ‐Compliance
Issues for Further action and Target
Dates
A. Construction Phase
I. Soil
Disposal of excess excavated earthworks
Earthworks cut will be used in embankments where possible. Residual will be placed in storage areas with containment walls. Residual spoil will be disposed of according to the erosion prevention plan (ErPP).
Partial
Contractor has not applied strictly to the mitigation measures.
Implemental EMP requirement on Mitigation Measure; Target time: before finish
Loss of topsoil
The topsoil from all areas to be permanently covered will be stripped and stored in stockpiles. Topsoil will be used for vegetation works. Construction vehicles, machinery, and equipment will move or be stationed in designated areas. Access to adjacent agricultural land will be minimized.
Yes
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
13
Environmental Impact/Issue of works
item EMP requirement on Mitigation Measures
Compliance Attained
(Yes, No, Partial)
Comment on Reasons for Partial or Non ‐Compliance
Issues for Further action and Target
Dates
Impact to temporarily acquired agricultural land
All temporarily acquired land will be rehabilitated after completion.
Yes
Failure to rehabilitate borrow pits
All borrow pits will be rehabilitated after use. Yes Comply with the EMP before finish construction
Soil erosion and siltation
On road embankment slopes, slopes of cuts, etc., soil erosion mitigation and siltation prevention measures will include, on a case‐by‐case basis, planting shrubs and grass, sediment basins, fiber mats, mulch, grasses, and slope drains.
Partial Current projects under construction
Comply with the EMP before finish construction
Contaminated by hazardous waste and materials, including hydrocarbons
(i) Oil separators will be installed at wash down and refueling areas.
(ii) Fuel storage and hazardous waste and materials storage sites will have adequate secondary containment to contain spills. All spilled materials and contaminated earth will be collected and disposed of according to EFB guidelines.
Partial
Some contractors may not archive properly stored fuel demand.
Comply with the EMP
Seismic activity
Mitigation measure include extending slopes, widening subgrade surfaces, and adding dual‐direction geotechnical grating in the crushed stone layer.
Yes
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
14
Environmental Impact/Issue of works
item EMP requirement on Mitigation Measures
Compliance Attained
(Yes, No, Partial)
Comment on Reasons for Partial or Non ‐Compliance
Issues for Further action and Target
Dates
II. Water Resources
Siltation into water bodies
Erosion prevention measures will be conducted in accordance with the ErPP including construction setting ponds.
Partial
Contractor has not applied strictly to the mitigation measures
Comply with the EMP
Disposal of septic waste and maintenance workshop wastewater into waterways
(i) Maintenance workshop wastewater will be treated to discharge standards. Where possible, wastewater will be discharged to municipal treatment systems.
(ii) The sewage system for the construction camps will be properly designed, built, and operated to prevent pollution to ground or adjacent watercourses.
(iii) The wastewater from the battery room will undergo electro dialysis.
Partial
The sewage system for the construction camps haven’t built (very little by the number of workers)
Use portable toilets or rent of locals
Contaminated runoff from inappropriately stored hazardous material and solid waste.
Solid hazardous and no hazardous waste will be appropriately stored to prevent contaminated runoff to adjacent waterways.
Partial
Contractor has not applied strictly to the mitigation measures
Comply with the EMP
III. Air Quality
Generation of dust (i) All earthworks vehicles will be covered to
avoid spillage. Partial
Some case material storage site not enough far away
Comply with the EMP
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
15
Environmental Impact/Issue of works
item EMP requirement on Mitigation Measures
Compliance Attained
(Yes, No, Partial)
Comment on Reasons for Partial or Non ‐Compliance
Issues for Further action and Target
Dates
(ii) Material storage site should be 300 m away from residential areas.
(iii) Water will be sprayed on the construction sites and major feeder roads twice daily during dry season.
(iv) The concrete batching plants and crushing plants will be sited at least 500m from the nearest habitation and fitted with dust extraction units in compliance with the PRC and local standards.
from residential areas
Emissions from Construction Vehicles, Equipment, and Machinery
Discharge emission standards. All vehicles, equipment, and machinery used for construction will be regularly maintained and operated (including the use of dust filters or hoods).
Yes
IV. Noises and Vibration
Noise from vehicles, plant and earthmoving equipment
(i) Plant and equipment used in construction will strictly conform to the PRC and local noise standards.
(ii) Within 200 m of the nearest habitation, construction work such as crushing, concrete mixing and batching, mechanical compaction, etc., will be stopped between 2200 and 0600 hours.
Yes
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
16
Environmental Impact/Issue of works
item EMP requirement on Mitigation Measures
Compliance Attained
(Yes, No, Partial)
Comment on Reasons for Partial or Non ‐Compliance
Issues for Further action and Target
Dates
V. Solid Waste and Hazardous Materials
Storage and disposal of hazardous and no hazardous waste, and hazardous materials
(i) Disposal of domestic waste (hazardous and no hazardous) and construction waste will occur regularly in approved municipal disposal sites.
(ii) There will be no on‐site development of landfills.
(iii) Hazardous waste and hazardous materials will be stored on‐site in approved facilities according to relevant standards, including secondary containment.
(iv) Licensed contractors will remove hazardous waste from site to approved hazardous waste disposal facilities.
Partial No standard storage Comply with the EMP
VI. Impact on Flora
Loss of or damage to vegetation
(i) Disposal of domestic waste (hazardous and no hazardous) and construction waste will occur regularly in approved municipal disposal sites.
(ii) There will be no on‐site development of landfills.
(iii) Hazardous waste and hazardous materials will be stored on‐site in approved facilities
Partial
Contractor not yet determined the location and permit disposal sites
Comply with the EMP
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
17
Environmental Impact/Issue of works
item EMP requirement on Mitigation Measures
Compliance Attained
(Yes, No, Partial)
Comment on Reasons for Partial or Non ‐Compliance
Issues for Further action and Target
Dates
according to relevant standards, including secondary containment.
(iv) Licensed contractors will remove hazardous waste from site to approved hazardous waste disposal facilities.
VII. Impact on Fauna
Impact to ridge aquatic biology at bridge Construction
Mitigation measure will include appropriate engineering design to minimize increases in Suspended solids.
Yes
Loss of habitat
Minimize habitat clearance during construction operations. Rehabilitation of temporarily occupied site
Yes
VIII. Historical, Cultural, and Archaeological
Encounter sites during construction
Should a historical, cultural, or archaeological sites be encountered during construction, all activities will halt and an established action plan will be enacted.
Yes
IX. Social Impact
Accidents due to unfamiliarity with railways
Along the majority of the alignment and the public is unfamiliar with safety issues associated with railways crossings. A public education campaign will be undertaken to minimize
No
Contractor has not applied strictly to the mitigation measures
Comply with the EMP
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
18
Environmental Impact/Issue of works
item EMP requirement on Mitigation Measures
Compliance Attained
(Yes, No, Partial)
Comment on Reasons for Partial or Non ‐Compliance
Issues for Further action and Target
Dates
accidents at grade crossings and other locations. Furthermore, all road crossings will be grade‐separated to increase public safety.
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
19
6.1.2. The workers health and safety provisions
Through inspection, field supervisor can evaluate:
- The sanitation facilities are available or inappropriate;
- Have water supply for drinking and washing.
- In some sub‐contractors the first aid provisions not enough, safety equipment in the
construction site as provisions.
- For spoils disposal site: some only have obtain agreements with land owners
- Well done the specified on safety in the construction process to ensure the safety of
the community
- The required mitigation measures are sufficient or still appropriate considering current
site conditions and on‐going site works.
- A some difficulties in the implementation of measures to minimize the impact on the
environment: (1) due to the construction of most of the small streams, slope, high
water flow rate should be made to reduce the suspended solids difficulty; (2) the
gathering of excess solid waste for disposal is limited by the volume is not large,
transport distances are too far away and difficult; (3) the time to mobilize engineering
supervision is not sufficient to ensure task requirements.
6.2. Environmental Effects Monitoring
6.2.1. Monitoring baseline environmental
Environment monitoring construction stage wasn’t carry out in this 6 months (January
to June 2013).
6.2.2. Monitoring internal environment of Contractor
According to the Environmental Management Program of Construction Package CP2,
Namkwang contractors will carry out internal environmental monitoring indicators,
frequency and location in the table 3. Currently packages CP2 has not carried out
environmental monitoring. Recommend contractors conduct environmental
monitoring in the future as summary in Table 3.
Table 3. Environmental Monitoring Program of CP2
No Item Parameters Monitoring Location
Monitoring Frequency
1 Air Quality
(TSP), CO, NO2, SO2, Temperature, Humility, wind direction and velocity
Van Phu Station; Lam Giang Station; Tuan Quan Bridge; …
Monthly
2 Noise level Lep, Lamax, L50
Van Phu Station; Lam Giang Station; Tuan Quan Bridge; …
Monthly
3 Surface Water Quality
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
20
No Item Parameters Monitoring Location
Monitoring Frequency
pH, Turbidity, Suspended Solids; DO, BOD5; Oil, Coliform
Van Phu Station; Lam Giang Station; Tuan Quan Bridge; …
Monthly
4 Solid Waste Disposal
Quantity and component To be identified Six months
7. Environmental Permits/Clearances
- The final report of the IEE and EMP was approved by ADB in year 2006
- Environmental License of the Ministry of Natural Resources and Environment was
approved in 2007.
- The construction materials supply from mines have been granted permission from the
authorities.
- License/Permits for solid waste disposal at the expected burial location have not
registered with DONRE
- In the construction field are no reports of environmental quality monitoring.
8. Complaints
There are no complaints on effect environmental.
9. Environmental Training/Orientation
There are no environmental training or orientation carried out during the previous
month and the coming month.
10. Issues for Further Action
The action plan for further in the table 4.
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
21
Table 4. The action plan further
Issue Cause Required Action
Responsibility Timing (Target dates)
Resolution and Timing (Actual)
Old Issues from Previous Reports
New Issues from this Reports
Implementation of the request does not comply, not achieved in EMP (table 2).
Ensure environmental minimize impacts + Contractors Immediately
Increased safety monitoring, field sanitation
To guide contractors, workers apply, implement safety measures and hygiene in the field of construction works
+ Contractors & Supervision Consultant
Whole time of the project
Monitor of mitigation measures in the sites
Ensure contractor applies the mitigation measures in the EMP
+ Contractors and Supervision Consultant
Whole time of the project
Contractor implementation environmental monitoring as the EMP require and submit monthly reports
To ensure that the construction activities shall not exceed the standards allow, cause environmental pollution.
+ Contractor Whole time of the project
Supervision consultants continue to monitor the environment by EMP
Monitoring of project activities affect the environment around the project area.
+
Supervision Consultant (independent environmental monitoring)
As schedule
Monthly reports and quarterly
For donors, the project very clearly state the project's impact on the environment and make required adjustments of the project activities
+ Supervision consultant and constructor
As schedule
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
22
Issue Cause Required Action
Responsibility Timing (Target dates)
Resolution and Timing (Actual)
Monitor of mitigation measures in the sites
To ensure Contractor the application of safety measures to minimize adverse impacts of the project
+ Supervision consultant
Whole time of the project
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
23
11. Conclusion
a. Environmental Management/Mitigation Measures Implementation Overall Progress
- Consultant supervision (CS2) planned the environmental monitoring program for the
project (include: CP1, CP2 and CP3) and submitted RPMU to ADB.
- CS2 have conducted baseline environmental monitoring for prior stage and
contraction of the project as requirements, but in the first semiannual of this year
(2013) haven’t carry out.
- Namkwang Contractor has planning environmental management program (EMP) for
CP2 and approved by RPMU in June 2012. Lotte –Sampyo Joint Venture haven’t EMP
submit.
- The environmental impact mitigation measures of project have been applied, but
incompletely and properly designed requirement.
- Up to June 2013 Namkwang contractor (CP2) has not yet implemented internal
environmental monitoring as stated in the EMP.
b. Summary of Problems Identified and Actions Recommended
- The contractor is requested to follow the requirements in EMP.
- Consultant supervision and contractor will improve safety monitoring and sanitation
in field.
- Consultant supervision and contractor will improve monitoring of mitigation measures
on sites.
- Contractor will have to implement environmental monitoring as required in the EMP
and submit monthly reports.
- Consultant supervision carry out environmental monthly and quarterly reports.
- Rock and sand quarries, crushers, batching plants, borrow areas not have copies of
licenses and need ready in site.
12. Annex
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
24
Annex 1. Summary Environmental Management Plan (for whole project)
Environmental Impact/Issue
Mitigation Measures Location Time Frame Responsibility
Implementation
Supervision
A. Construction Phase X. Soil
Disposal of excess excavated earthworks
Earthworks cut will be used in embankments where possible. Residual will be placed in storage areas with containment walls. Residual spoil will be disposed of according to the erosion prevention plan (ErPP).
Throughout the Project corridor at all construction sites
During Construction
Contractor
EPMD and Soil Conservation Department (SCD)
Loss of topsoil
The topsoil from all areas to be permanently covered will be stripped and stored in stockpiles. Topsoil will be used for vegetation works. Construction vehicles, machinery, and equipment will move or be stationed in designated areas. Access to adjacent agricultural land will be minimized.
Throughout the project corridor, all borrow and spoil areas
During Construction
Contractor EPMD and SCD
Impact to temporarily acquired agricultural land
All temporarily acquired land will be rehabilitated after completion.
Throughout the project corridor
During Construction
Contractor EPMD and SCD
Failure to rehabilitate borrow pits
All borrow pits will be rehabilitated after use. All borrow areas During Construction
Contractor EPMD and SCD
Soil erosion and siltation
On road embankment slopes, slopes of cuts, etc., soil erosion mitigation and siltation prevention measures will include, on a case‐by‐case basis, planting shrubs and
Within construction corridor and all
During Construction
Contractor EPMD and SCD
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
25
Environmental Impact/Issue
Mitigation Measures Location Time Frame Responsibility
Implementation
Supervision
grass, sediment basins, fiber mats, mulches, grasses, and slope drains.
construction and work sites
Contamination by hazardous waste and materials, including hydrocarbons
(i) Oil separators will be installed at wash down and refueling areas.
(ii) Fuel storage and hazardous waste and materials storage sites will have adequate secondary containment to contain spills. All spilled materials and contaminated earth will be collected and disposed of according to EFB guidelines.
Throughout project corridor
During Construction and Operation
Contractor
EPMD with assistance from local EPBs
Seismic activity Mitigation measure include extending slopes, widening subgrade surfaces, and adding dual‐direction geotechnical grating in the crushed stone layer.
Construction and Operation
Engineering designers and contractors
EPMD and RPMU
XI. Water Resources
Siltation into water bodies
Erosion prevention measures will be conducted in accordance with the ErPP including construction setting ponds.
Throughout project corridor
During Construction
contractor EPMD and local WRB
Disposal of septic waste and maintenance workshop wastewater into waterways
(iii) Maintenance workshop wastewater will be treated to discharge standards. Where possible, wastewater will be discharged to municipal treatment systems.
(iv) The sewage system for the construction camps will be properly designed, built, and operated to prevent pollution to ground or adjacent watercourses.
(v) The wastewater from the battery room will undergo electro dialysis.
Maintenance workshops and Construction Camps
During Construction and Operation
Contractor EPMD and local WRB
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
25
Environmental Impact/Issue
Mitigation Measures Location Time Frame Responsibility
Implementation
Supervision
grass, sediment basins, fiber mats, mulches, grasses, and slope drains.
construction and work sites
Contamination by hazardous waste and materials, including hydrocarbons
(i) Oil separators will be installed at wash down and refueling areas.
(ii) Fuel storage and hazardous waste and materials storage sites will have adequate secondary containment to contain spills. All spilled materials and contaminated earth will be collected and disposed of according to EFB guidelines.
Throughout project corridor
During Construction and Operation
Contractor
EPMD with assistance from local EPBs
Seismic activity Mitigation measure include extending slopes, widening subgrade surfaces, and adding dual‐direction geotechnical grating in the crushed stone layer.
Construction and Operation
Engineering designers and contractors
EPMD and RPMU
XI. Water Resources
Siltation into water bodies
Erosion prevention measures will be conducted in accordance with the ErPP including construction setting ponds.
Throughout project corridor
During Construction
contractor EPMD and local WRB
Disposal of septic waste and maintenance workshop wastewater into waterways
(iii) Maintenance workshop wastewater will be treated to discharge standards. Where possible, wastewater will be discharged to municipal treatment systems.
(iv) The sewage system for the construction camps will be properly designed, built, and operated to prevent pollution to ground or adjacent watercourses.
(v) The wastewater from the battery room will undergo electro dialysis.
Maintenance workshops and Construction Camps
During Construction and Operation
Contractor EPMD and local WRB
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
26
Environmental Impact/Issue
Mitigation Measures Location Time Frame Responsibility
Implementation
Supervision
Contaminated runoff from inappropriately stored hazardous material and solid waste.
Solid hazardous and no hazardous waste will be appropriately stored to prevent contaminated runoff to adjacent waterways.
Storage areas for Hazardous Material and solid wastes (hazardous and non‐Hazardous)
During Establishment, Operation and Dismantling Storage areas
Contractor EPMD and Local EPBs
XII. Air Quality
Generation of dust
(v) All earthworks vehicles will be coved to avoid spillage.
(vi) Material storage site should be 300 m away from residential areas.
(vii) Water will be sprayed on the construction sites and major feeder roads twice daily during dry season.
(viii) The concrete batching plants and crushing plants will be sited at least 500m from the nearest habitation and fitted with dust extraction units in compliance with the PRC and local standards.
Throughout project corridors, all access roads, sites temporarily acquired and all borrow areas
Construction Contractor EPMD and EPBs
Emissions from Construction Vehicles, Equipment, and Machinery
Discharge emission standards. All vehicles, equipment, and machinery used for construction will be regularly maintained and operated (including the use of dust filters or hoods).
Throughout project corridor
Construction contractor EPMD and EPBs
XIII. Noises and Vibration
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
27
Environmental Impact/Issue
Mitigation Measures Location Time Frame Responsibility
Implementation
Supervision
Noise from vehicles, plant and earthmoving equipment
(i) Plant and equipment used in construction will strictly conform to the PRC and local noise standards.
(ii) Within 200 m of the nearest habitation, construction work such as crushing, concrete mixing and batching, mechanical compaction, etc., will be stopped between 2200 and 0600 hours.
Throughout project corridor, all access roads, sites temporarily acquired and all Borrow areas
Construction Contractor EPMD and EPBs
XIV. Solid Waste and Hazardous Materials
Storage and disposal of hazardous and no hazardous waste, and hazardous materials
(v) Disposal of domestic waste (hazardous and no hazardous) and construction waste will occur regularly in approved municipal disposal sites.
(vi) There will be no on‐site development of landfills. (vii) Hazardous waste and hazardous materials will be
stored on‐site in approved facilities according to relevant standards, including secondary containment.
(viii) Licensed contractors will remove hazardous waste from site to approved hazardous waste disposal facilities.
Construction sites, construction camps, stations and maintenance workshops.
Construction and operation
Contractor (construction period) and EA (operation period)
EPMD and Soil cultivation department
XV. Impact on Flora
Loss of or damage to vegetation
(v) Disposal of domestic waste (hazardous and no hazardous) and construction waste will occur regularly in approved municipal disposal sites.
(vi) There will be no on‐site development of landfills. (vii) Hazardous waste and hazardous materials will be
stored on‐site in approved facilities according to
Entire project site
Construction Contractor EPMD and Forest Department
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
28
Environmental Impact/Issue
Mitigation Measures Location Time Frame Responsibility
Implementation
Supervision
relevant standards, including secondary containment.
(viii) Licensed contractors will remove hazardous waste from site to approved hazardous waste disposal facilities.
XVI. Impact on Fauna
Impact to ridge aquatic biology at bridge Construction
Mitigation measure will include appropriate engineering design to minimize increases in Suspended solids.
Bridge sites construction contractor
EPMD, Forestry and Agricultural Departments.
Loss of habitat Minimize habitat clearance during construction operations. Rehabilitation of temporarily occupied site
Throughout the corridor, in particular the mountainous areas.
Construction Contractor
EPMD, Forestry and Agricultural Departments.
XVII. Historical, Cultural, and Archaeological
Encounter sites during construction
Should a historical, cultural, or archaeological sites be encountered during construction, all activities will halt and an established action plan will be enacted.
Throughout project corridor
Construction Contractor EPMD, Conservation Departments.
XVIII. Social Impact
Accidents due to unfamiliarity with railways
Along the majority of the alignment and the public is unfamiliar with safety issues associated with railways crossings. A public education campaign will be undertaken to minimize accidents at grade crossings and other
Throughout project corridor
Construction Contractor EPMD and RPMU
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
29
Environmental Impact/Issue
Mitigation Measures Location Time Frame Responsibility
Implementation
Supervision
locations. Furthermore, all road crossings will be grade‐separated to increase public safety.
B. Operation Phase
Contamination by hazardous waste and materials, including hydrocarbons
(i) Oil separators will be installed at wash down and refueling areas.
(ii) Fuel storage and hazardous waste and materials storage sites will have adequate secondary containment to contain spills. All spilled materials and contaminated earth will be collected and disposed off according to guidelines.
Throughout project corridor
Construction and Operation periods
Contractor and EA
EPMD Assistance from Local EPBs
Wastewater disposal from maintenance facilities and stations
(i) Wastewater will be treated to appropriate discharge standards.
(ii) All wastewater will be directed to municipal treatment where possible.
(iii) The wastewater from the battery room will undergo electro dialysis.
Maintenance workshops and stations
Operation EA EPMD&EPBs
Air emissions from boilers at stations and maintenance workshops
(i) All boilers will conform to GB 13271‐2001. Boilers with capacities equal to or greater than 1 ton/hour will be equipped with multipurpose dust traps. Boilers of 1.4 megawatts or greater will be equipped with wet desulfurization dust traps.
(ii) Boilers will be regularly inspected to ensure that they are operating efficiently and emission standards are met.
Maintenance Workshops and stations
Operation IA EPMD&EPBs
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
30
Environmental Impact/Issue
Mitigation Measures Location Time Frame Responsibility
Implementation
Supervision
Noise from maintenance workshops
Noise from maintenance workshops will strictly conformto the local noise standards.
Maintenance Workshops
Operation IA EPMD&EPBs
Noise from operation of the railway
(i) Noise control measures will be installed for noise‐sensitive points within 60 m on either side of the tracks.
(ii) Sound barriers, 3 m in eight with high absorbing capacity, will be installed in noise‐sensitive communities with over 50 households.
(iii) Sound‐insulating windows will be installed in noise sensitive communities with less than 50 households.
(iv) Monitoring will be conducted during the operational phase to conform modeling results.
Along entire Alignment
Operation IA EPMD&EPBs
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
31
Summary Environmental Management Plan (from EMP of CP2)
EMP Requirement Compliance Attained1
Comment on Reasons for
Partial or Non‐Compliance
Issues for Further action and Target
Dates Type of impact Impacted area Mitigation Methods
Waste disposal Whole project area
- Arrange wastebaskets in construction site, office and worker’s camp to collect waste.
- All waste, soil and remain material will be daily collected and treated. The contractor will contact with a local organization for collecting and treating solid waste according to regulations at Decision No. 59/ 2007/ NĐ‐ CP
- An unit with functions and responsibilities in handling hazardous waste will be hired to collect and treat hazardous materials according to the Circular 12/ 2006/ TT‐ BTNMT
Traffic and work accident
In the project and surrounding areas
- Arrange traffic routes to avoid traffic jam in rush hours.
- Set up traffic light and signs
Disputes between workers and local people and increase social evils
Project area
- Train on workers’ awareness in prevention of social evils for the workers.
- The recruitment of workers will give priority to local people.
- Train workers on suitable behaviors in contacting to local communities.
1 Yes, No, Partial
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
32
EMP Requirement Compliance Attained1
Comment on Reasons for
Partial or Non‐Compliance
Issues for Further action and Target
Dates Type of impact Impacted area Mitigation Methods
Erosion causing turbidity in the water
Filling and digging area
- Protect the exposed land as much as possible and replant the destroyed area.
- Build French drain to intercept rain runoff. Direct rain runoff manhole to collect sediment before joining to the natural water flow.
Effect of Bridge construction on the Irrigation
Bridge construction
- Mud solution from drilling area will be collected and disposed of in the appropriate place.
- Oil and grease generated from construction vehicles will be strictly control in accordance with Circular No 12/ 2006 BTNMT dated on 26/12/2006.
- Carefully practice and manage in construction.
Air pollution In the project area
- Only construction equipment and machines which have been registered with quality of exhausted gas according to TCVN 6438:2001 are applied.
- Regularly maintenance of machines. - Cover trucks transporting materials transport with
canvas. - Cover the stockpiles such as sand and gravel in the
dry season to decrease dust caused by wind.
Water pollution In the project area
- Management of charge sources to maintain the sanitation for river and other water source
- Washing of machines at water sources and places that discharge to water sources will be strictly prohibited.
- Materials and equipment of waste water treatment, bridge construction‐ betonies slurry and
`
YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01
CONTRACT No. 17HDYVLC-CS2
33
EMP Requirement Compliance Attained1
Comment on Reasons for
Partial or Non‐Compliance
Issues for Further action and Target
Dates Type of impact Impacted area Mitigation Methods
washed concrete will be kept away from water discharge systems in order to prevent their spillage or seepage into the systems,
Water pollution In the project area
- Public toilets in the construction site will have septic tanks and standardized in conformity with regulations on hygiene of the Ministry of Health and Ministry of Construction and will be away from accommodation and residential areas, away from water sources. Ensure that wastewater will be treated to meet the standards stipulated in QCVN 14:2008/ BTNMT before discharge in to water bodies.
- The toilets when being removed will be dredged and then ground will be dumped with backfilling materials.
Noise and vibration
in the project area
- Using technical methods to reduce vibration such as applying isolation of shake by special structures
- Stipulate time of heavy vehicle operation, pile driving to ensure that those activities are not carried out at the same time
Impair on ecosystem
In rivers and aquaculture farm nearby
- Management of charge sources to maintain the sanitation for the rivers, aquaculture fields around the Site and other ecosystems.