Environmental Monitoring Report Semi-Annual Report No. 3 July 2013 VIE: Yen Vien-Lao Cai Railway Upgrading Project Prepared by CDM Smith-DBI JV Associates, Inc. for Viet Nam Railway under the Ministry of Transport of Vietnam, and the Asian Development Bank.

Upload: hakiet

Post on 31-Aug-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Environmental Monitoring Report Semi-Annual Report No. 3 July 2013

VIE: Yen Vien-Lao Cai Railway Upgrading Project

Prepared by CDM Smith-DBI JV Associates, Inc. for Viet Nam Railway under the Ministry of Transport of Vietnam, and the Asian Development Bank.

CURRENCY EQUIVALENTS

(as of 1 July 2013)

Currency unit –

dong (D)

D1.00 = $0.0000472 $1.00 = VND21,170

ABBREVIATIONS ADB – Asian Development Bank AFD – Agency Francoise de Development DONRE – Department of Natural Resources and Environment EMP – environmental management plan IEE – initial environmental examination

NOTE In this report, "$" refers to US dollars unless otherwise stated.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

VIETNAM RAILWAY (VNR)

Under MINISTRY OF TRANSPORT

SUPERVISION CONSULTANTS’ SERVICES

FOR

YEN VIEN - LAO CAI UPGRADING PROJECT

SEMI-ANNUAL ENVIRONMENTAL MONITORING

PROGRESS REPORT NO. 03

JULY 2013

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

2

Contents

1.  Introduction ........................................................................................................ 3 

2.  Incorporation of Environmental Requirements into Project Contractual Arrangements................................................................................................................. 3 

3.  Scope and Reporting period .............................................................................. 5 

4.  Methodology ........................................................................................................ 5 

5.  Project Status ...................................................................................................... 5 

6.  Compliance with EMP ..................................................................................... 12 

6.1 Environmental Performance ............................................................................. 12 

6.2. Environmental Effects Monitoring .................................................................. 19 

7.  Environmental Permits/Clearances ................................................................ 20 

8.  Complaints ........................................................................................................ 20 

9.  Environmental Training/Orientation ............................................................. 20 

10.  Issues for Further Action .................................................................................. 20 

11.  Conclusion .......................................................................................................... 23 

12.  Annex .................................................................................................................. 23 

 

   

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

3

THE SECOND SEMI‐ANNUAL ENVIRONMENTAL MONITORING REPORT 

(FROM JANUARY TO JUNE 2013) 

1. Introduction 

The railway from Yen Vien station (Hanoi) to Lao Cai province ‐ the border with China 

and one branch from Pho Lu to Xuan Giao is an important transportation system for 

mountainous northwest. The current railway contains sharp curves and weak bridges 

which causes train speed reduction. Besides, the track is lack of maintenance for a long 

time; many bridges should be upgraded and replaced as soon as possible. 

Asian  Development  Bank  (ADB),  Agency  Françoise  de  Development  (AFD)  and 

Direction Generable du Tresor et de la Politique Economique (DGPTE) have assessed 

and agreed to provide a loan for upgrading railway Yen Vien ‐ Lao Cai project.  

The project objective  is upgrading Yen Vien  ‐ Lao Cai  railway  (estimation of 285km 

length) in order to improve the transportation capacity and commercial development 

in the northern mountainous area. The Project will  increase trading profits between 

Vietnam and China, especially within the Kunming area.  

Beside  the  positive  impacts  the  project  also  has  negative  impacts  on  the  local 

environment. Therefore the project environmental management plan is implemented 

during the project, in order to: 

- Apply appropriate measurement  to minimize  the negative  impacts on environment 

complying  with  the  current  Vietnam  environmental  regulations  and  laws  and 

environmental policies of international organizations, if necessary; 

- Use an appropriate organizational structure in environmental protection throughout 

construction period of the Project to ensure that the mitigation measures proposed in 

the  Environmental  Impact  Assessment  Report  or  IEE  and  EMP  are  effectively 

implemented; 

- Planning to deal with the environmental emergencies and accidents that may occur 

during the implementation of the Project; 

- The Environmental Management Plan shall be implemented by the Contractors during 

the work execution and shall be monitored by the Engineer and the Employer on daily 

basis. 

2. Incorporation  of  Environmental  Requirements  into  Project  Contractual 

Arrangements 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

4

To  implement  the  requirements  of  the  project  environmental  plan  effectively,  the 

tasks/work are arranged as follows: 

- Supervision consultant and Independent contractors environmental monitoring: 

i) Carry out baseline environmental monitoring and monitor implementation 

of the environmental management plans, including any required sampling 

and  testing  to ascertain baseline and  in‐construction noise pollution, air 

quality, water quality and solid waste disposal requirements. 

ii) Report on any difficulties in the monthly and quarterly progress reports and 

recommend the implementation of amelioration measures to be taken to 

reduce adverse impacts. 

iii) To monitor the baseline environment in the project area the construction 

phase. 

iv) Reporting  the  status of  the environment and propose  the application of 

measures to minimize the impact on the surrounding environment.  

- Contractors (including subcontractors):  

i) Implementation of environmental monitoring of air, water, solid waste at 

the construction site and areas affected: 

a. Monitoring number, status, changes in negative impacts’ origin arising 

from construction site to environment quality; 

b. Subscribe flow/ volume/ frequency and period measurement, sampling 

and analysis of pollution parameters, characteristic of the waste arising 

from  the  facility operation  (waste water, waste gas and  solid waste, 

hazardous waste, noise, vibration, and other criteria); 

c. Periodic measurement, sampling and analysis of the parameters related 

to the negative environmental impacts origin in the area (surface water, 

groundwater, air, soil); 

d. Monitoring  of  changes  and  measure  the  current  status  factors  (if 

relevant):  erosion,  sliding,  falling,  landslides,  land  subsidence;  river 

bank erosion, stream, lake; sedimentation of rivers, streams, reservoir; 

changing the water surface and underground water; and other impacts. 

ii) To monitor and inspect food, and sanitary conditions at construction site. 

iii) Report on construction activities at  the site and  the current state of  the 

environment during the construction process, the comments complained 

of the surrounding community. 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

5

iv) Adjust  the  construction  activities;  apply  measures  to  minimize 

environmental impact. 

3. Scope and Reporting period 

Environmental monitoring report for the first six months of year (from January to June 

2013) will aggregate  the environmental performance of Yen Vien  ‐  Lao Cai  railway 

upgrading projects in general and environmental control activities, the environmental 

mitigation measures are applied to the construction bid package. The report reviews 

the compliance of environmental activities with EMP and proposes activities  in  the 

future environment in order to control and minimize negative environmental impacts. 

4. Methodology 

The project environmental monitoring report bases on the following methods: 

- Methods listing: Specify the full impacts caused by the project's activities. 

- Methods  of  synthesis  compare:  Synthesis  of  data  collected,  comparing  with 

environmental standards then assess the current state of environmental quality in 

the studied area, forecast evaluate and propose solutions to minimize the project 

works environmental impact. 

- Field survey method: field sampling, laboratory analysis of samples in accordance 

with  the  provisions  of  VN  standards  to  determine  the  environmental  quality 

parameters  (including:  air  quality  survey,  noise,  water  quality,  wastewater 

composition,  ecosystem  project  area).  Field  visits  and  compare  with  the 

regulations on sanitary conditions, labor safety, fire protection, electrical safety... 

- Method  of  assessment:  the  calculation  load  of  pollutants  from  the  production 

activities of the project. 

5. Project Status 

The project status as in table 1.  

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

6

Table 1. The status of project 

No  Name of works Construction activities

Ongoing site works During the previous 

months For the subsequent months 

  Construction of Bridges     

 Ngoi Sen Bridge (Km 145+950) 

Finished scaffolding installation; Installed bundle beam rail; Constructed wing walls. 

Receive rubble stone Install steel girder, Casting concrete for girder Construct retaining wall completed 7/2013 

 Van Phu Bridge (Km 148+920) 

Finished bored piles; Finished 2 abutments; Transport materials for scaffolding installation

Casting concrete ditch, embankment sand 

Transport and install steel girder onsite. Casting concrete for abutments cap to place the girder, Casting for girder, Completed 6/2013 

 Dao Thinh Bridge (Km 171+414) 

Finished 1 trial pile driving for Lao Cai abutment 

Replaced girder, abutment repaired in Yenvien side 

Casting and massive driving at Lao Cai abutment Improve the Hanoi abutment due to the crack Completed 8/2013 

 Thac Thu bridge (Km 173+287) 

Finished Construction Casting concrete seg. 2 body wall and top slab 

Land acquisition and excavate ditches at upstream 

 Con Tran Bridge (Km 173+960) 

Finished concrete casting for U‐shaped beam; Finished Lao Cai abutment; Improved Yen Vien abutment 

The new bridge and new abutment 

New construction for Yen Vien abutment Laugh main upstream 

 Mau A Bridge (Km 188+050) 

Reinforce 2 bridge approaches; steel girder transportation; install steel girder. 

Replaced girder, abutment repaired. Repaired abutment covering and wall. 

Repair the scaffolding according to approved method statement, Labor safety must  be improved  Install  steel girder Casting concrete for composite girder Upgrade and repair the abutment. 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

7

No  Name of works Construction activities 

Ongoing site works During the previous 

months For the subsequent months 

 Khe Hoi bridge (Km 189+000) 

Casting trial pile. Trial pile driving 1st time. 

Replaced girder, renew two abutment. 

2nd trial pile driving is expected on 2nd June. Need strict supervision.  Massive pile driving will be proceeded. 

 Khai Bridge (Km 195+394) 

Gather materials on site Install scaffolding; Make access road 

Install scaffolding;  Assemble steel girder. 

 Tro Bridge (Km 204+825) 

Install scaffolding Make access road 

Replaced girder, abutment repaired. Repaired abutment covering and wall. 

Install steel girder and scaffolding. Casting concrete for composite girder. Upgrade and repair the abutment. 

 Phuc Minh bridge (Km 214+742) 

Assemble steel girder; transport steel girder 

Install scaffolding Install steel girder. Casting concrete for steel girder.  

 Bau bridge (Km 221+953) 

Assemble steel girder 

Replaced girder, abutment repaired. Repaired abutment covering and wall. 

Assemble and transport steel girder to site. 

  Ly bridge (Km 225+170) Transport scaffolding materials 

‐  Install scaffolding and transport steel girder to site 

 Construction of embankment 

     

 

Section 6. Slope Protection (Km178+632 ‐ 179+193) 561m, 349m 

Under construction. 

Treat weak embankment, mud raising and water stagnancy. Excavate and replace soil, place geotextile woven fabric, construct 

Continue the work. Mobilize more materials.  

 Section 7. Slope Protection (Km179+905 ‐ 

Casting concrete border for gabion and lay out gabion for the slope. 

Finish the 2 remaining segments and finalize the item on 10th June. 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

8

No  Name of works Construction activities 

Ongoing site works During the previous 

months For the subsequent months 

180+275) 370m, 90m  underground drainage ditches, top and longitudinal ditches. Treat erosion, settlement and slide of slope: construction of retaining wall and reinforcement of slope. 

 Section 8: from Km182+158 to Km 182+566 

Completed 95% and is finalizing 

Continue the work. Mobilize more materials. 

 Section 9. Slope Protection (Km 182+158 – 182+560) 

Under construction  Continue the work. Mobilize more materials. 

 

Section 14. Slope Protection (Km188+196 ‐ 188+297) 101m, 63m 

Under construction Continue the work. Mobilize more materials. Revise the differences between shop drawing and actual site condition. 

 

Section 17. Slope Protection (Km195+783 ‐ 196+155) 372m, 62m+163 

Under construction  Continue the work. Mobilize more materials. 

 

Section 19. Slope Protection (Km199+978 ‐ 200+471) 493m, 145m 

Under construction  Continue the work. Mobilize more materials. 

 Section 21. Slope Protection (km 225+000 – 225+323). 

Under construction  Continue the work. Mobilize more materials. 

  Construction of the culverts       

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

9

No  Name of works Construction activities 

Ongoing site works During the previous 

months For the subsequent months 

 

- Pipe Culvert, D=1.0m (Km194+654.95) 

- Pipe Culvert D=1.0m (Km197+040) 

- Pipe Culvert D=1.0m (Km197+195) 

- Pipe Culvert D=1.0m (Km197+390) 

- Pipe Culvert D=1.0m (Km202+988) 

- Pipe Culvert D=1.0m (Km226+000,225+652.65) 

Submit method statement.  Make temporary girder Demolish old culvert Install framework.  Casting concrete the foundation and install the culvert.  Backfilling after construction.  Demolish old culvert 

Clearance, excavation, installation of culverts 

Completion of the work content in the approved construction plans 

  Construction of Station     

 1. Van Phu Station‐Km148+350: 

  

   

  ‐ Track work  

Soil filling K95 and K98, and excavate the foundation for precast ditches R50, R60 along the track. 

Adjustment of general layout terminal, hold the opening of the station and way operational. Adding one road tail track and the road into the station. 

Soil backfilling is striving to finish on 15th June. Soil filling for Van Phu station must wait for the completion of track no. 4, 5, 6. 

  ‐ Architecture part Finished incurred construction: 

   

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

10

No  Name of works Construction activities 

Ongoing site works During the previous 

months For the subsequent months 

- Temporary generator house and sanitary unit. 

- Transfer the existing generator to the new generator house, and the sanitary unit is operating. 

 ‐ Signaling and communication 

Completed the capacity profiles 

 

Make inspection procedures and inspection minutes for quantity assessment of completed items. To finish the connection procedures for signaling and telecommunication. 

  ‐ Power supply Review capacity profiles for materials and suppliers 

 

Complete capacity profiles. Complete inspection procedures and connection procedures. Inspect the transformer station. 

 2. Mau Dong Station (Km 194+895) 

Casting concrete for retaining wall segment 1 to 12 

Carry out excavation and embankment 

Continue and finish the remaining segments. Need land acquisition for Mau Dong station (1 household). Commence backfilling for the foundation of Mau Dong Station. 

 3. Lam Giang Station (Km 210+000) 

Constructing the retaining wall at the South of the Station. Casting concrete for the platform between 1‐II, II‐3. Backfilling for the foundation at the North of the Station.

Carry out excavation and embankment 

Complete backfilling for the foundation at the North of the Station. Handle the soil filling for extension of track no.1. Construct new turnout guard house before commencing track work for extension track. Prepare materials for track work.

  Track Work        

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

11

No  Name of works Construction activities 

Ongoing site works During the previous 

months For the subsequent months 

 Realignment section km 169+700 – Km 173+700 

Excavate the foundation  Soil and sand backfilling. Construct slope protection 5A, 6A, 7A, 8 

 

Continue the construction of slope protection 5A, 6A, 7A, 8. Track work Km 171+410 – Km 172+410: replace rail P50/PC sleepers. Culvert must be constructed in sync with track work. Supervise the safety issues 

 Upgrading section Km 148+250 – Km 155+250 

Replace rail P50/PC sleepers from Km 149+900 – Km 150+500: add more ballast. 

 Continue the track work Km 150+500 – Km 155+250.Supervise the safety issues 

 Upgrading section Km 155+250 – Km 165+000 

Track work Km 163+451‐Km 164+051 

 Continue the track work Km 164+051 – Km 165+000.Supervise the safety issues 

 Upgrading section Km 194+750 – Km 201+750 

Km 198+300‐Km 198+900: Replace rail P50/PC sleepers

 Continue the track work Km 198+900 – Km 201+750.Supervise the safety issues

 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

12

6. Compliance with EMP 

6.1 Environmental Performance 

6.1.1. Compliance with environmental mitigation measures 

Evaluation of the implementation of environmental mitigation measures are summarized in Table 2.  

Table 2 ‐ Table summarizing compliance with ALL environmental mitigation measures specified in the EMP   

Environmental Impact/Issue of works 

item EMP requirement on  Mitigation Measures 

Compliance Attained 

(Yes, No, Partial) 

Comment on Reasons for Partial or Non ‐Compliance 

Issues for Further action and Target 

Dates 

A. Construction Phase        

I. Soil        

Disposal of excess excavated earthworks 

Earthworks cut will be used in embankments where possible. Residual will be placed in storage areas with containment walls. Residual spoil will be disposed of according to the erosion prevention plan (ErPP). 

Partial  

Contractor has not applied strictly to the mitigation measures. 

Implemental EMP requirement on Mitigation Measure; Target time: before finish 

Loss of topsoil 

The topsoil from all areas to be permanently covered will be stripped and stored in stockpiles. Topsoil will be used for vegetation works. Construction vehicles, machinery, and equipment will move or be stationed in designated areas. Access to adjacent agricultural land will be minimized. 

Yes     

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

13

Environmental Impact/Issue of works 

item EMP requirement on  Mitigation Measures 

Compliance Attained 

(Yes, No, Partial) 

Comment on Reasons for Partial or Non ‐Compliance 

Issues for Further action and Target 

Dates 

Impact to temporarily acquired agricultural land 

All temporarily acquired land will be rehabilitated after completion. 

Yes     

Failure to rehabilitate borrow pits 

All borrow pits will be rehabilitated after use.  Yes   Comply with the EMP before finish construction

Soil erosion and siltation 

On road embankment slopes, slopes of cuts, etc., soil erosion mitigation and siltation prevention measures will include, on a case‐by‐case basis, planting shrubs and grass, sediment basins, fiber mats, mulch, grasses, and slope drains. 

Partial Current projects under construction 

Comply with the EMP before finish construction 

Contaminated by  hazardous waste and materials, including hydrocarbons 

(i) Oil separators will be installed at wash down and refueling areas. 

(ii) Fuel storage and hazardous waste and materials storage sites will have adequate secondary containment to contain spills. All spilled materials and contaminated earth will be collected and disposed of according to EFB guidelines. 

 

Partial 

Some contractors may not archive properly stored fuel demand. 

Comply with the EMP 

Seismic activity 

Mitigation measure include extending slopes, widening subgrade surfaces, and adding dual‐direction geotechnical grating in the crushed stone layer.   

Yes     

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

14

Environmental Impact/Issue of works 

item EMP requirement on  Mitigation Measures 

Compliance Attained 

(Yes, No, Partial) 

Comment on Reasons for Partial or Non ‐Compliance 

Issues for Further action and Target 

Dates 

II. Water Resources        

Siltation into water bodies 

Erosion prevention measures will be conducted in accordance with the ErPP including construction setting ponds. 

Partial 

Contractor has not applied strictly to the mitigation measures 

Comply with the EMP 

Disposal of septic waste and maintenance workshop  wastewater into waterways 

(i) Maintenance workshop wastewater will be treated to discharge standards. Where possible, wastewater will be discharged to municipal treatment systems. 

(ii) The sewage system for the construction camps will be properly designed, built, and operated to prevent pollution to ground or adjacent watercourses. 

(iii) The wastewater from the battery room will undergo electro dialysis.

Partial 

The sewage system for the construction camps haven’t built (very little by the number of workers) 

Use portable toilets or rent of locals 

Contaminated runoff from inappropriately stored hazardous material and solid waste. 

Solid hazardous and no hazardous waste will be appropriately stored to prevent contaminated runoff to adjacent waterways. 

Partial 

Contractor has not applied strictly to the mitigation measures 

Comply with the EMP 

III. Air Quality    

Generation of dust (i) All earthworks vehicles will be covered to 

avoid spillage. Partial 

Some case material storage site not enough far away 

Comply with the EMP 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

15

Environmental Impact/Issue of works 

item EMP requirement on  Mitigation Measures 

Compliance Attained 

(Yes, No, Partial) 

Comment on Reasons for Partial or Non ‐Compliance 

Issues for Further action and Target 

Dates 

(ii) Material storage site should be 300 m away from residential areas. 

(iii) Water will be sprayed on the construction sites and major feeder roads twice daily during dry season. 

(iv) The concrete batching plants and crushing plants will be sited at least 500m from the nearest habitation and fitted with dust extraction units in compliance with the PRC and local standards. 

from residential areas  

Emissions from Construction Vehicles, Equipment, and Machinery 

Discharge emission standards. All vehicles, equipment, and machinery used for construction will be regularly maintained and operated (including the use of dust filters or hoods). 

Yes   

 

IV. Noises and Vibration        

Noise from vehicles, plant and earthmoving  equipment  

(i) Plant and equipment used in construction will strictly conform to the PRC and local noise standards. 

(ii) Within 200 m of the nearest habitation, construction work such as crushing, concrete mixing and batching, mechanical compaction, etc., will be stopped between 2200 and 0600 hours.    

Yes     

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

16

Environmental Impact/Issue of works 

item EMP requirement on  Mitigation Measures 

Compliance Attained 

(Yes, No, Partial) 

Comment on Reasons for Partial or Non ‐Compliance 

Issues for Further action and Target 

Dates 

V. Solid Waste and Hazardous Materials 

Storage and disposal of hazardous and no hazardous waste, and hazardous materials 

(i) Disposal of domestic waste (hazardous and no hazardous) and construction waste will occur regularly in approved municipal disposal sites. 

(ii) There will be no on‐site development of landfills. 

(iii) Hazardous waste and hazardous materials will be stored on‐site in approved facilities according to relevant standards, including secondary containment. 

(iv) Licensed contractors will remove hazardous waste from site to approved hazardous waste disposal facilities. 

Partial  No standard storage Comply with the EMP 

VI. Impact on Flora        

Loss of or damage to vegetation   

(i) Disposal of domestic waste (hazardous and no hazardous) and construction waste will occur regularly in approved municipal disposal sites. 

(ii) There will be no on‐site development of landfills. 

(iii) Hazardous waste and hazardous materials will be stored on‐site in approved facilities 

Partial 

Contractor not yet determined the location and permit disposal sites 

Comply with the EMP 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

17

Environmental Impact/Issue of works 

item EMP requirement on  Mitigation Measures 

Compliance Attained 

(Yes, No, Partial) 

Comment on Reasons for Partial or Non ‐Compliance 

Issues for Further action and Target 

Dates 

according to relevant standards, including secondary containment. 

(iv) Licensed contractors will remove hazardous waste from site to approved hazardous waste disposal facilities. 

VII. Impact on Fauna        

Impact to ridge aquatic biology at bridge Construction 

Mitigation measure will include appropriate engineering design to minimize increases in Suspended solids. 

Yes     

Loss of habitat  

Minimize habitat clearance during construction operations. Rehabilitation of temporarily occupied site

Yes     

VIII. Historical, Cultural, and Archaeological  

Encounter sites during construction 

Should a historical, cultural, or archaeological sites be encountered during construction, all activities will halt and an established action plan will be enacted. 

Yes     

IX. Social Impact     

Accidents due to unfamiliarity with railways 

Along the majority of the alignment and the public is unfamiliar with safety issues associated with railways crossings. A public education campaign will be undertaken to minimize 

No 

Contractor has not applied strictly to the mitigation measures 

Comply with the EMP 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

18

Environmental Impact/Issue of works 

item EMP requirement on  Mitigation Measures 

Compliance Attained 

(Yes, No, Partial) 

Comment on Reasons for Partial or Non ‐Compliance 

Issues for Further action and Target 

Dates 

accidents at grade crossings and other locations. Furthermore, all road crossings will be grade‐separated to increase public safety. 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

19

6.1.2. The workers health and safety provisions 

Through inspection, field supervisor can evaluate: 

- The sanitation facilities are available or inappropriate; 

- Have water supply for drinking and washing.  

- In some sub‐contractors the first aid provisions not enough, safety equipment in the 

construction site as provisions. 

- For spoils disposal site: some only have obtain agreements with land owners 

- Well done the specified on safety in the construction process to ensure the safety of 

the community 

- The required mitigation measures are sufficient or still appropriate considering current 

site conditions and on‐going site works. 

- A some difficulties in the implementation of measures to minimize the impact on the 

environment:  (1) due  to  the construction of most of  the small streams, slope, high 

water  flow  rate  should be made  to  reduce  the  suspended  solids difficulty;  (2)  the 

gathering  of  excess  solid waste  for  disposal  is  limited  by  the  volume  is  not  large, 

transport distances are too far away and difficult; (3) the time to mobilize engineering 

supervision is not sufficient to ensure task requirements. 

 

6.2. Environmental Effects Monitoring  

6.2.1. Monitoring baseline environmental 

Environment monitoring construction stage wasn’t carry out in this 6 months (January 

to June 2013).  

6.2.2. Monitoring internal environment of Contractor 

According to the Environmental Management Program of Construction Package CP2, 

Namkwang contractors will  carry out  internal environmental monitoring  indicators, 

frequency  and  location  in  the  table  3. Currently packages CP2 has not  carried out 

environmental  monitoring.  Recommend  contractors  conduct  environmental 

monitoring in the future as summary in Table 3. 

Table 3. Environmental Monitoring Program of CP2  

No  Item  Parameters Monitoring Location 

Monitoring Frequency 

1  Air Quality 

(TSP), CO, NO2, SO2, Temperature, Humility, wind direction and velocity 

Van Phu Station; Lam Giang Station; Tuan Quan Bridge; … 

Monthly 

2  Noise level  Lep, Lamax, L50 

Van Phu Station; Lam Giang Station; Tuan Quan Bridge; … 

Monthly 

3 Surface Water Quality 

     

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

20

No  Item  Parameters Monitoring Location 

Monitoring Frequency 

   pH, Turbidity,  Suspended Solids; DO, BOD5; Oil, Coliform 

Van Phu Station; Lam Giang Station; Tuan Quan Bridge; … 

Monthly 

4 Solid Waste Disposal 

Quantity and component  To be identified  Six months 

 

7.  Environmental Permits/Clearances 

- The final report of the IEE and EMP was approved by ADB in year 2006 

- Environmental  License  of  the Ministry  of Natural  Resources  and  Environment was 

approved in 2007. 

- The construction materials supply from mines have been granted permission from the 

authorities. 

- License/Permits for solid waste disposal at the expected burial location have not 

registered  with DONRE 

- In the construction field are no reports of environmental quality monitoring. 

8. Complaints 

There are no complaints on effect environmental.  

9.  Environmental Training/Orientation 

There are no environmental  training or orientation carried out during  the previous 

month and the coming month.  

10.  Issues for Further Action 

The action plan for further in the table 4.   

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

21

Table 4. The action plan further 

Issue  Cause Required Action

Responsibility Timing  (Target dates) 

Resolution and Timing (Actual) 

Old Issues from Previous Reports 

           

           

New Issues from this Reports 

Implementation of the request does not comply, not achieved in EMP (table 2). 

Ensure environmental minimize impacts  +  Contractors  Immediately   

Increased safety monitoring, field sanitation 

To guide contractors, workers apply, implement safety measures and hygiene in the field of construction works

+ Contractors & Supervision Consultant

Whole time of the project

 

Monitor of mitigation measures in the sites 

Ensure contractor applies the mitigation measures in the EMP 

+ Contractors and Supervision Consultant 

Whole time of the project 

 

Contractor implementation environmental monitoring as the EMP require and submit monthly reports 

To ensure that the construction activities shall not exceed the standards allow, cause environmental pollution. 

+  Contractor Whole time of the project 

 

Supervision consultants continue to monitor the environment by EMP 

Monitoring of project activities affect the environment around the project area. 

Supervision Consultant (independent environmental monitoring) 

As schedule   

Monthly reports and quarterly 

For donors, the project very clearly state the project's impact on the environment and make required adjustments of the project activities 

+ Supervision consultant and constructor 

As schedule   

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

22

Issue  Cause Required Action

Responsibility Timing  (Target dates) 

Resolution and Timing (Actual) 

Monitor of mitigation measures in the sites 

To ensure Contractor the application of safety measures to minimize adverse impacts of the project 

+ Supervision consultant 

Whole time of the project 

 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

23

11. Conclusion 

a. Environmental Management/Mitigation Measures Implementation Overall Progress 

- Consultant supervision (CS2) planned the environmental monitoring program for the 

project (include: CP1, CP2 and CP3) and submitted RPMU to ADB. 

- CS2  have  conducted  baseline  environmental  monitoring  for  prior  stage  and 

contraction of  the project as  requirements, but  in  the  first  semiannual of  this year 

(2013) haven’t carry out. 

- Namkwang Contractor has planning environmental management program (EMP) for 

CP2 and approved by RPMU in June 2012. Lotte –Sampyo Joint Venture haven’t EMP 

submit. 

- The  environmental  impact mitigation measures  of  project  have  been  applied,  but 

incompletely and properly designed requirement. 

- Up to June 2013 Namkwang contractor (CP2) has not yet implemented internal 

environmental monitoring as stated in the EMP. 

b. Summary of Problems Identified and Actions Recommended 

- The contractor is requested to follow the requirements in EMP.  

- Consultant supervision and contractor will improve safety monitoring and sanitation 

in field. 

- Consultant supervision and contractor will improve monitoring of mitigation measures 

on sites. 

- Contractor will have to implement environmental monitoring as required in the EMP 

and submit monthly reports. 

- Consultant supervision carry out environmental monthly and quarterly reports. 

- Rock and sand quarries, crushers, batching plants, borrow areas not have copies of 

licenses and need ready in site. 

12. Annex 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

24

Annex 1. Summary Environmental Management Plan (for whole project) 

Environmental Impact/Issue 

Mitigation Measures  Location  Time Frame Responsibility

Implementation 

Supervision 

A. Construction Phase X. Soil   

Disposal of excess excavated earthworks 

Earthworks cut will be used in embankments where possible. Residual will be placed in storage areas with containment walls. Residual spoil will be disposed of according to the erosion prevention plan (ErPP). 

Throughout the Project corridor at all construction sites 

During Construction

Contractor 

EPMD and Soil Conservation Department (SCD)  

Loss of topsoil 

The topsoil from all areas to be permanently covered will be stripped and stored in stockpiles. Topsoil will be used for vegetation works. Construction vehicles, machinery, and equipment will move or be stationed in designated areas. Access to adjacent agricultural land will be minimized. 

Throughout the project corridor, all borrow and spoil areas 

During Construction

Contractor  EPMD and SCD 

Impact to temporarily acquired agricultural land 

All temporarily acquired land will be rehabilitated after completion. 

Throughout the project corridor 

During Construction

Contractor  EPMD and SCD 

Failure to rehabilitate borrow pits 

All borrow pits will be rehabilitated after use.  All borrow areas During Construction

Contractor  EPMD and SCD 

Soil erosion and siltation 

On road embankment slopes, slopes of cuts, etc., soil erosion mitigation and siltation prevention measures will include, on a case‐by‐case basis, planting shrubs and 

Within construction corridor and all 

During Construction

Contractor  EPMD and SCD 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

25

Environmental Impact/Issue 

Mitigation Measures  Location  Time Frame Responsibility 

Implementation 

Supervision 

grass, sediment basins, fiber mats, mulches, grasses, and slope drains. 

construction and work sites 

Contamination by hazardous waste and materials, including hydrocarbons 

(i) Oil separators will be installed at wash down and refueling areas. 

(ii) Fuel storage and hazardous waste and materials storage sites will have adequate secondary containment to contain spills. All spilled materials and contaminated earth will be collected and disposed of according to EFB guidelines. 

Throughout project corridor 

During Construction and Operation 

Contractor 

EPMD with assistance from local EPBs 

Seismic activity Mitigation measure include extending slopes, widening subgrade surfaces, and adding dual‐direction geotechnical grating in the crushed stone layer.  

 Construction and Operation 

Engineering designers and contractors 

EPMD and RPMU 

XI. Water Resources 

Siltation into water bodies 

Erosion prevention measures will be conducted in accordance with the ErPP including construction setting ponds. 

Throughout project corridor 

During Construction

contractor EPMD and local WRB 

Disposal of septic waste and maintenance workshop wastewater into waterways 

(iii) Maintenance workshop wastewater will be treated to discharge standards. Where possible, wastewater will be discharged to municipal treatment systems. 

(iv) The sewage system for the construction camps will be properly designed, built, and operated to prevent pollution to ground or adjacent watercourses. 

(v) The wastewater from the battery room will undergo electro dialysis. 

Maintenance workshops and Construction Camps 

During Construction and Operation 

Contractor EPMD and local WRB 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

25

Environmental Impact/Issue 

Mitigation Measures  Location  Time Frame Responsibility 

Implementation 

Supervision 

grass, sediment basins, fiber mats, mulches, grasses, and slope drains. 

construction and work sites 

Contamination by hazardous waste and materials, including hydrocarbons 

(i) Oil separators will be installed at wash down and refueling areas. 

(ii) Fuel storage and hazardous waste and materials storage sites will have adequate secondary containment to contain spills. All spilled materials and contaminated earth will be collected and disposed of according to EFB guidelines. 

Throughout project corridor 

During Construction and Operation 

Contractor 

EPMD with assistance from local EPBs 

Seismic activity Mitigation measure include extending slopes, widening subgrade surfaces, and adding dual‐direction geotechnical grating in the crushed stone layer.  

 Construction and Operation 

Engineering designers and contractors 

EPMD and RPMU 

XI. Water Resources 

Siltation into water bodies 

Erosion prevention measures will be conducted in accordance with the ErPP including construction setting ponds. 

Throughout project corridor 

During Construction

contractor EPMD and local WRB 

Disposal of septic waste and maintenance workshop wastewater into waterways 

(iii) Maintenance workshop wastewater will be treated to discharge standards. Where possible, wastewater will be discharged to municipal treatment systems. 

(iv) The sewage system for the construction camps will be properly designed, built, and operated to prevent pollution to ground or adjacent watercourses. 

(v) The wastewater from the battery room will undergo electro dialysis. 

Maintenance workshops and Construction Camps 

During Construction and Operation 

Contractor EPMD and local WRB 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

26

Environmental Impact/Issue 

Mitigation Measures  Location  Time Frame Responsibility 

Implementation 

Supervision 

Contaminated runoff from inappropriately stored hazardous material and solid waste. 

Solid hazardous and no hazardous waste will be appropriately stored to prevent contaminated runoff to adjacent waterways. 

Storage areas for Hazardous Material and solid wastes (hazardous and non‐Hazardous) 

During Establishment, Operation and Dismantling Storage areas 

Contractor EPMD and Local EPBs 

XII. Air Quality          

Generation of dust 

(v) All earthworks vehicles will be coved to avoid spillage. 

(vi) Material storage site should be 300 m away from residential areas. 

(vii) Water will be sprayed on the construction sites and major feeder roads twice daily during dry season. 

(viii) The concrete batching plants and crushing plants will be sited at least 500m from the nearest habitation and fitted with dust extraction units in compliance with the PRC and local standards. 

Throughout project corridors, all access roads, sites temporarily acquired and all borrow areas 

Construction Contractor EPMD and EPBs 

Emissions from Construction Vehicles, Equipment, and Machinery 

Discharge emission standards. All vehicles, equipment, and machinery used for construction will be regularly maintained and operated (including the use of dust filters or hoods). 

Throughout project corridor 

Construction contractor EPMD and EPBs 

XIII. Noises and Vibration          

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

27

Environmental Impact/Issue 

Mitigation Measures  Location  Time Frame Responsibility 

Implementation 

Supervision 

Noise from vehicles, plant and earthmoving equipment 

(i) Plant and equipment used in construction will strictly conform to the PRC and local noise standards. 

(ii) Within 200 m of the nearest habitation, construction work such as crushing, concrete mixing and batching, mechanical compaction, etc., will be stopped between 2200 and 0600 hours.    

Throughout project corridor, all access roads, sites temporarily acquired and all Borrow areas 

Construction Contractor EPMD and EPBs 

XIV. Solid Waste and Hazardous Materials 

Storage and disposal of hazardous and no hazardous waste, and hazardous materials 

(v) Disposal of domestic waste (hazardous and no hazardous) and construction waste will occur regularly in approved municipal disposal sites. 

(vi) There will be no on‐site development of landfills. (vii) Hazardous waste and hazardous materials will be 

stored on‐site in approved facilities according to relevant standards, including secondary containment. 

(viii) Licensed contractors will remove hazardous waste from site to approved hazardous waste disposal facilities. 

Construction sites, construction camps, stations and maintenance workshops. 

Construction and operation 

Contractor (construction period) and EA (operation period) 

EPMD and Soil cultivation department 

XV. Impact on Flora        

Loss of or damage to vegetation         

(v) Disposal of domestic waste (hazardous and no hazardous) and construction waste will occur regularly in approved municipal disposal sites. 

(vi) There will be no on‐site development of landfills. (vii) Hazardous waste and hazardous materials will be 

stored on‐site in approved facilities according to 

Entire project site 

Construction Contractor EPMD and Forest Department 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

28

Environmental Impact/Issue 

Mitigation Measures  Location  Time Frame Responsibility 

Implementation 

Supervision 

relevant standards, including secondary containment. 

(viii) Licensed contractors will remove hazardous waste from site to approved hazardous waste disposal facilities. 

XVI. Impact on Fauna        

Impact to ridge aquatic biology at bridge Construction 

Mitigation measure will include appropriate engineering design to minimize increases in Suspended solids. 

Bridge sites  construction  contractor 

EPMD, Forestry and Agricultural Departments. 

Loss of habitat Minimize habitat clearance during construction operations. Rehabilitation of temporarily occupied site 

Throughout the corridor, in particular the mountainous areas.

Construction Contractor 

EPMD, Forestry and Agricultural Departments. 

XVII. Historical, Cultural, and Archaeological  

Encounter sites during construction 

Should a historical, cultural, or archaeological sites be encountered during construction, all activities will halt and an established action plan will be enacted. 

Throughout project corridor 

Construction Contractor EPMD, Conservation Departments. 

XVIII. Social Impact 

Accidents due to unfamiliarity with railways 

Along the majority of the alignment and the public is unfamiliar with safety issues associated with railways crossings. A public education campaign will be undertaken to minimize accidents at grade crossings and other 

Throughout project corridor 

Construction Contractor EPMD and RPMU 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

29

Environmental Impact/Issue 

Mitigation Measures  Location  Time Frame Responsibility 

Implementation 

Supervision 

locations. Furthermore, all road crossings will be grade‐separated to increase public safety. 

B. Operation Phase 

Contamination by hazardous waste and materials, including hydrocarbons 

(i) Oil separators will be installed at wash down and refueling areas. 

(ii) Fuel storage and hazardous waste and materials storage sites will have adequate secondary containment to contain spills. All spilled materials and contaminated earth will be collected and disposed off according to guidelines. 

Throughout project corridor 

Construction and Operation periods 

Contractor and EA 

EPMD Assistance from Local EPBs 

Wastewater disposal from maintenance facilities and stations 

(i) Wastewater will be treated to appropriate discharge standards. 

(ii) All wastewater will be directed to municipal treatment where possible. 

(iii) The wastewater from the battery room will undergo electro dialysis. 

Maintenance workshops and stations 

Operation  EA  EPMD&EPBs 

Air emissions from boilers at stations and maintenance workshops  

(i) All boilers will conform to GB 13271‐2001. Boilers with capacities equal to or greater than 1 ton/hour will be equipped with multipurpose dust traps. Boilers of 1.4 megawatts or greater will be equipped with wet desulfurization dust traps. 

(ii) Boilers will be regularly inspected to ensure that they are operating efficiently and emission standards are met.  

Maintenance Workshops and stations 

Operation  IA  EPMD&EPBs 

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

30

Environmental Impact/Issue 

Mitigation Measures  Location  Time Frame Responsibility 

Implementation 

Supervision 

Noise from maintenance workshops 

Noise from maintenance workshops will strictly conformto the local noise standards. 

Maintenance Workshops 

Operation IA EPMD&EPBs

Noise from operation of the railway 

(i) Noise control measures will be installed for noise‐sensitive points within 60 m on either side of the tracks. 

(ii) Sound barriers, 3 m in eight with high absorbing capacity, will be installed in noise‐sensitive communities with over 50 households. 

(iii) Sound‐insulating windows will be installed in noise sensitive communities with less than 50 households. 

(iv) Monitoring will be conducted during the operational phase to conform modeling results. 

Along entire Alignment 

Operation IA EPMD&EPBs

   

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

31

 

Summary Environmental Management Plan (from EMP of CP2) 

EMP Requirement Compliance Attained1 

Comment on Reasons for 

Partial or Non‐Compliance 

Issues for Further action and Target 

Dates Type of impact  Impacted area  Mitigation Methods 

Waste disposal Whole project area 

- Arrange wastebaskets in construction site, office and worker’s camp to collect waste. 

- All waste, soil and remain material will be daily collected and treated. The contractor will contact with a local organization for collecting and treating solid waste according to regulations at Decision No. 59/ 2007/ NĐ‐ CP 

- An unit with functions and responsibilities in handling hazardous waste will be hired to collect and treat hazardous materials according to the Circular  12/ 2006/ TT‐ BTNMT 

   

Traffic and work accident 

In the project and surrounding areas   

- Arrange traffic routes to avoid traffic jam in rush hours. 

- Set up traffic light and signs    

 

Disputes between workers and local people and increase social evils 

Project area 

- Train on workers’ awareness in prevention of social evils for the workers. 

- The recruitment of workers will give priority to local people. 

- Train workers on suitable behaviors in contacting to local communities.

   

 

1 Yes, No, Partial

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

32

EMP Requirement Compliance Attained1 

Comment on Reasons for 

Partial or Non‐Compliance 

Issues for Further action and Target 

Dates Type of impact  Impacted area  Mitigation Methods 

Erosion  causing turbidity  in  the water 

Filling  and digging area 

- Protect the exposed  land as much as possible and replant the destroyed area. 

- Build French drain  to  intercept  rain  runoff. Direct rain  runoff  manhole  to  collect  sediment  before joining to the natural water flow.

 

Effect  of  Bridge construction  on the Irrigation 

Bridge construction  

- Mud solution from drilling area will be collected and disposed of in the appropriate place. 

- Oil  and  grease  generated  from  construction vehicles will be strictly control  in accordance with Circular No 12/ 2006 BTNMT dated on 26/12/2006. 

- Carefully practice and manage in construction. 

     

Air pollution  In  the  project area 

- Only construction equipment and machines which have been registered with quality of exhausted gas according to TCVN 6438:2001 are applied. 

- Regularly maintenance of machines. - Cover trucks transporting materials transport with 

canvas. - Cover the stockpiles such as sand and gravel in the 

dry season to decrease dust caused by wind. 

 

Water pollution  In  the  project area 

- Management  of  charge  sources  to  maintain  the sanitation for river and other water source 

- Washing of machines at water sources and places that  discharge  to  water  sources  will  be  strictly prohibited. 

- Materials  and  equipment  of  waste  water treatment, bridge construction‐ betonies slurry and 

     

`

YEN VIEN – LAO CAO RAILWAY UPGRADING PROJECT ADB LOAN No.2302-VIE and AFD LOAN No. CVN 6006 01

CONTRACT No. 17HDYVLC-CS2

33

EMP Requirement Compliance Attained1 

Comment on Reasons for 

Partial or Non‐Compliance 

Issues for Further action and Target 

Dates Type of impact  Impacted area  Mitigation Methods 

washed  concrete  will  be  kept  away  from  water discharge systems in order to prevent their spillage or seepage into the systems,

Water pollution  In  the  project area 

- Public toilets in the construction site will have septic tanks  and  standardized  in  conformity  with regulations on hygiene of the Ministry of Health and Ministry  of  Construction  and  will  be  away  from accommodation  and  residential  areas,  away  from water  sources.  Ensure  that  wastewater  will  be treated to meet the standards stipulated  in QCVN 14:2008/  BTNMT  before  discharge  in  to  water bodies. 

- The  toilets when  being  removed will  be  dredged and  then  ground will  be  dumped with  backfilling materials. 

     

Noise  and vibration 

in  the  project area 

- Using technical methods to reduce vibration such as applying isolation of shake by special structures 

- Stipulate  time  of  heavy  vehicle  operation,  pile driving  to  ensure  that  those  activities  are  not carried out at the same time

     

Impair  on ecosystem  

In  rivers  and aquaculture farm nearby 

- Management  of  charge  sources  to  maintain  the sanitation for the rivers, aquaculture fields around the Site and other ecosystems.