environmentalmanagementplan.pdf
TRANSCRIPT
-
7/25/2019 EnvironmentalManagementPlan.pdf
1/76
CORRIBFIELDDEVELOPMENT
LANDFALL&PULL-INSERVICES
ENVIRONMENTALMANAGEMENT
PLANDocument No: GEN-3761-010-TW
Controlled Copy Distribution
No. 1 TW (site) - Project ManagerNo. 2 TW (site) - Project Management TeamNo. 3 TW officeNo. 4 ACC (Project Manager & Site)
D1 Issue for Construction 03-06-2005 SFU DRA JGO HAB
C1 Issue for Approval 27-05-2005 SFU DRA JGO HABB1 Issue Comments 30-04-2005 SFU DRA JGO HAB
A1 Issue Internal Review 14-04-2005 SFU DRA JGO HAB
Rev Reason for change Date Prepared by QA/QC Check HSE Check Approved by Company
Contractor:Tideway BV Marine andOffshore Contractors
Project No: 368821/LF/001
Company:
Al lseas Construction Contractors S.A.
-
7/25/2019 EnvironmentalManagementPlan.pdf
2/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 2
TABLE OF CONTENTS
Page No.:
1
Introduction............................................................................................................4
1.1 General ................................................................................................................41.2 Scope...................................................................................................................4
2 Reference Documents ...........................................................................................62.1 Legislation ............................................................................................................62.2 Company & Client Documents/Specifications ...........................................................62.3 Contractor Documents/Procedures .........................................................................6
3 Defini tions and Abbreviations ..............................................................................63.1 Definitions ............................................................................................................63.2 Abbreviations........................................................................................................6
4 Environmental Policy ............................................................................................7
5 Responsibil li ties and organisation ......................................................................85.1 Environmental Responsibilities Project Manager: ...................................................105.2 Environmental Responsibilities Works Manager: ....................................................105.3 Environmental Advisor (Engineer): ........................................................................10
6 Project Communications ....................................................................................116.1 Internal Communications......................................................................................116.2 External Communications.....................................................................................116.3 Documentation....................................................................................................11
7
Environmental Management ...............................................................................12
7.1 Legal and Other Constraints .................................................................................127.2 Aspects and Impacts of Construction Activity .........................................................127.3 Traffic Management ..........................................................................................127.4 Training ..............................................................................................................137.5 Waste Management.............................................................................................147.6 Monitoring...........................................................................................................157.7 Internal Audits and Inspections .............................................................................157.8 Environmental Operational Control Procedures ......................................................15
-
7/25/2019 EnvironmentalManagementPlan.pdf
3/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 3
FIGURES
Figure 1 Emergency Procedure Onshore
Figure 2 Emergency Procedure Offshore
APPENDICES
Appendix 1 Legislation Register
Appendix 2 Impacts Register Onshore
Appendix 3 Impacts Register Offshore
Appendix 4 Environmental Output
Appendix 5 Environmental operational control Procedures: EP101 Training EP102 Reporting EP103 Inspections and Audits EP104 Monitoring and Measuring EP105 Consents and Authorisations EP108 Plant Maintenance EP201 Pollution Prevention and Control - Onshore EP202 Pollution Prevention and Control Air EP203 Pollution Prevention and Control - Offshore EP209 Storage and Bunding EP213 Noise EP301 Waste Management EP404 Soil EP405 Grasslands EP408 Birds EP416 Archaeology EP418 General Reinstatement EP420 Marine Mammals
-
7/25/2019 EnvironmentalManagementPlan.pdf
4/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 4
1 INTRODUCTION
1.1 General
The Corrib Field Development Project, being developed by Shell E&P Ireland Ltd, is a gas fieldlocated in 350 m of water some 60 to 65 km off the County Mayo coastline. The field will bedeveloped as a long-range sub sea tieback to an onshore facility. The gas will then be treated tomeet the defined gas specification before onward transportation to the Bord Gais Eireann (BGE)grid via a new cross-country pipeline.
The sub sea facilities will consist of a manifold with cluster wells, together with a number of satellitewells. The pipeline system comprises flexible flow lines from the satellite wells to the manifold, andan export line to shore. This 83km 20-inch sub sea pipeline from the manifold makes a landfall atBroadhaven Bay in County Mayo, and thence a further 9km onshore pipeline leads to the terminal.An electro-hydraulic umbilical system will parallel the pipeline system, and a water outfall pipeline
will also run from the terminal to a diffuser offshore.
The Work covered by this document includes the installation of a nominal 20-inch diameter pipelineand multicore umbilical system from the landfall at Glengad Headland to the new Terminal.Additionally, a nominal 8 inch diameter polyethylene outfall pipeline runs from the Terminal to apoint approximately 12km offshore.
Tideway (TW) has been awarded the subcontract for trench dredging, pipeline pull-in and trenchbackfilling 2005. The trench will have a depth of 3m below seabed and will have a width of 3 m.The nearshore trench, from 200m offshore until 1400m offshore, will be dredged by a backhoedredger and a splithopper barge. The backhoe dredger, a spudlegged pontoon mounted excavator,will excavated the material and deposit in the splithopper barge. The splithopper barge will sail to
an underwater stockpile within the wayleave and deploy the material, using GPS positioning, untilre-dredging for backfill purposes. A section of approximately 180 m rock will be fractured usingmechanical rock breakers. Two long reach excavators, mounted on a spudlegged self-elevatingplatform, equipped with hydraulic rock hammers will fracture the rock layer by layer. After fracturingthe backhoe dredger will dredge the material. Upon pipeline installation the materials will be re-dredged and backfilled at their originate position.The intertidal section, 200m offshore to cliff face, will be excavated by land-based excavators. Atemporary causeway will be constructed at the north side of the proposed trench and the excavatorwill excavate the trench. During the 2002 works the rock material was fractured so the requirementfor mechanical rock fracturing does not exist. The cliff will be excavated and separate soil layersencountered will be stockpiled separately and netted to prevent birds nesting. Upon pipelineinstallation the temporary causeway will be removed, the trench will be backfilled and the cliff will
be reinstated.Upon trench completion a steel wire will be laid and connected to the offshore pipelay vessel. Thepipeline will be pulled ashore using a linear winch. Upon pipeline position acceptance the completetrench will be backfilled and reinstatement will be completed.
1.2 Scope
This Environmental Management Plan details all the environmental aspects and impactsassociated with this contract such as waste management, pollution prevention and protection offlora and fauna, with an emphasis on the sensitivity of the Glenamoy Bog Complex SAC and theBroadhaven Bay SAC. The Impacts register (Appendices 3 and 4) provides the framework foridentifying the potential environmental impacts generated by construction and the associated
works. The Environmental Operational Control Procedures and activity specific method statements(ref: TW-MS-001 -007) detail the working methods necessary for managing and mitigating theseimpacts, whether it is by prevention or amelioration. Prior to construction activities taking place the
-
7/25/2019 EnvironmentalManagementPlan.pdf
5/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 5
Environmental Operational Control Procedures will be updated to conform to precise site-specificrequirements at the Glengad Headland. They are intended to be stand-alone documents
Two Environmental method statements are in place in relation to works within the two SACs withinthe working area; Glenamoy Bog Complex and Broadhaven Bay. These documents describe theoffshore and landfall construction activities for the shore approach of the pipe line (ref: TW-EMS-001, TW-EMS-002).
This Environmental Management Plan has been based on the principles of the ISO 14,001standard. As the project progresses the Environmental Management Plan will be reviewed andrevised to include any changes and improvements made during the Works.
-
7/25/2019 EnvironmentalManagementPlan.pdf
6/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 6
2 REFERENCE DOCUMENTS
2.1 Legislation
1. Foreshore Acts 1933 to 1988 (administered by the Department of Communications Marine& Natural Resources) Regulations and Guidance Notes2. Local Government (Planning and Development) Acts and Regulations3. The Safety, Health and Welfare at Work (Construction) Regulations 2001: SI 4814. Foreshore Licence with Conditions5. Pipeline Consent (Sect 40) with Conditions
2.2 Company & Client Documents/Specifications
1. Contract 368821/LF/001 Landfall and Pull-In Services2. Environmental Impact Statement Corrib Field to Terminal (October 2001)3. Terminal Planning Permission with Conditions
2.3 Contractor Documents/Procedures
1. GEN-3761-001-TW; Master Document Register2. GEN-3761-002-TW; Construction Drawing Register3. GEN-3761-008-TW; Emergency Response Procedure4. GEN-3761-009-TW; Overall H&S Plan5. OC-3761-000-TW; Overall Organisation Scheme TW6. TW-EMS-001; EMS Glengad Headland_Glennamoy Bog Complex SAC 5007. TW-EMS-002; EMS Broadhaven Bay_Broadhaven Bay SAC 4728. TW-MS-001; Dredging and Backfilling9. TW-MS-002; Mechanical Rock Removal10. TW-MS-003; Temporary Causeway Construction
11. TW-MS-004; Welfare Facility12. TW-MS-005; Onshore Trench Excavation & Backfilling13. TW-MS-006; Pipeline Pull-In14. TW-MS-007; Cliff Reinstatement
3 DEFINITIONS AND ABBREVIATIONS
3.1 Definitions
Client Shell E&P Ireland Ltd.Company Allseas Construction Contractors SAContractor Tideway BV, Marine and Offshore ContractorsWork All activities in accordance with the
Contract
3.2 Abbreviations
ACC Allseas Construction Contractors SACOSHH Control of Substances Hazardous to HealthEIS Environmental Impact StatementEP Environmental Operation Control ProcedureEMS Environmental Method StatementEPA Environmental Protection AgencyMSDS Material Safety Data Sheet
TW Tideway BV, Marine and Offshore Contractors
-
7/25/2019 EnvironmentalManagementPlan.pdf
7/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 7
4 ENVIRONMENTAL POLICY
TW recognise that their operations have a direct impact on the natural and built environment andhave made environmental management an integral part of their projects. All employees areaccountable for the success of TWs environmental performance.
TW will manage, monitor and improve its environmental performance through the implementationof its Environmental Management Plan and associated Operational Control Procedures. Thesefollow the internationally recognised ISO 14001 standard.
TW is committed to the following environmental objectives in relation to its activities:
TW will ensure that the production of waste is minimised and that all such waste ismanaged effectively and disposed of safely.
TW will ensure that the impact on watercourses, the aquatic environment, terrestrialhabitats and all species therein is minimised.
TW will ensure that the condition of all associated land will be returned to its pre-workscondition.
TW will ensure that its emissions to the atmosphere will be minimised.
TW will ensure that all environmental legislation is complied with and contractualobligations met.
TW will monitor its performance and review its procedures to ensure continualimprovement.
-
7/25/2019 EnvironmentalManagementPlan.pdf
8/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 8
5 RRESPONSIBILLITIES AND ORGANISATION
The overall responsibility for the activities rests with the Project Manager. It will be theresponsibility of the Project Manager to approve key personnel required for employment on the
project. He will liase with the Company Site Representatives on- and offshore.
The Project Manager will lead the works on site. He will be responsible for the management andcontrol of the activities and will be responsible for the implementation of all aspects of theEnvironmental Management Plan. He will be assisted by the Works Manager who will act as hisdeputy.
A project team consisting of the following persons will be of assistance:
Project Engineer; the Project Engineer will assist the Project & Works Manager in all facetsoff the work.
Environmental Advisor; the environmental advisor will prepare and implement all aspects ofthe Environmental Management Plan.
QA/HS Engineer; the QA/HS Engineer will monitor the operations with respect to theobservation, implementation and adherence of QA and HS rules and procedures.
Survey; the Chief Surveyor and his assistant will be responsible for the management andcontrol of the survey activities and liaise with Company Survey Representatives on- andoffshore. The Surveyor will report to the Works Manager
Superintendents; the Superintendent will lead the specific operations onboard off the
vessels or on the onshore construction site. The superintendent will be responsible for thedirect supervision of the works and construction crew. He will report to the Works Manager.
The management structure is shown overleaf
-
7/25/2019 EnvironmentalManagementPlan.pdf
9/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 9
-
7/25/2019 EnvironmentalManagementPlan.pdf
10/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 10
5.1 Environmental Responsibilit ies Project Manager:
Will have ultimate responsibility for the site environmental issues.
Will ensure that there are sufficient resources to manage and monitor the environmentalaspects and impacts of the project.
Will ensure that the environmental management plan reflects any changes during theconstruction process that may have a significant environmental impact and manage themaccordingly.
Will keep the Company and the Client fully informed on any site environmental issues. Willensure that environmental records are returned to head office for review.
5.2 Environmental Responsibilit ies Works Manager:
Will be responsible for ensuring that all crews work to the TW Environmental ManagementPlan. This includes communicating the relevant environmental operational control and
emergency procedures. Will be responsible for managing and monitoring environmental issues onshore and
offshore.
Will ensure that all environmental incidents are reported and dealt with effectively.
Will adhere to the procedures written by the environmental advisor.
5.3 Environmental Advisor (Engineer):
Will be site based during the project and will have responsibility for the identification andmanagement of site environmental issues
Will ensure that the Company and the Client are kept informed about all environmentalissues as the project progresses.
Will ensure that all consents/licences are in place prior to carrying out the associatedworks.
Will ensure that the Project Manager and Works Manager are fully informed on anyenvironmental issues.
Will be responsible for the induction and training of all staff working on the project in relationto all environmental issues.
Will keep records of all staff inductions.
Will be responsible for producing and carrying out tool box talk as part of on-site learning.
Will keep the communications register up to date in order to facilitate effectiveenvironmental management with the Company and the Client.
Will carry out or supervise all environmental monitoring on the project ensuring that all
records are fully completed and stored correctly. Will develop the Environmental Operational Control Procedures.
Will provide environmental input into the Method Statements.
Will, in conjunction with the Works Manager, write procedures for site-specific issues.
Will carry out internal daily and weekly audits in line with the programme of audits specifiedby the Client.
Will ensure that all remedial action identified by inspections are closed out.
Will supervise reinstatement of the site.
Will supervise works to ensure minimal disturbance of wildlife such as sand martins nestingat Glengad Headland and cetaceans offshore
Will carry out regular noise monitoring onsite and at sensitive receptors such as local
residences prior to and during the work. Will initiate measures to mitigate light disturbance caused by work at night.
Will ensure waste management procedures are implemented (EP301, Appendix 5)
-
7/25/2019 EnvironmentalManagementPlan.pdf
11/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 11
6 PROJECT COMMUNICATIONS
6.1 Internal Communications
The TW Environmental Policy will be displayed on the office notice board. All staff and Sub contractors working on behalf of TW undergo an Environmental Induction
prior to working on site. A Green Card, Enviro-Tips, will be issued to all personnel oncompletion of the Induction.
Daily environmental audits will be carried out on both the onshore and offshore activities.These issues are discussed with the Works Manager prior to the delegating of correctiveaction.
Weekly Construction Progress meetings include environmental issues on the agenda anddiscuss areas of the operational procedures that could be enhanced or improved.
Toolbox talks will be given to all staff and sub contractors by the environmental advisor.These will be based on the specific activities being carried out.
Records are maintained detailing content and attendance.
6.2 External Communications
Communications between Tideway and third parties and landowners are recorded andmanaged by the Environmental Advisor.
Any complaints received from third parties and landowners are recorded in the complaintlog and communicated to the Company and the Client.
Adherence to the project traffic Management Plan (ref: 2044 Shell E&P Ltd. TransportManagement Plan) will be communicated to all users of the roads that are involved in theconstruction works.
6.3 Documentation
Plans and Procedures in place prior to construction:Pre-Construction Flora/Fauna SurveysProject Environmental Management Plan; (GEN-3761-010-TW)Environmental Input to Works Procedures (Various)Method Statements for each activity MS-TW-001 - 007Environmental Method Statements EMS-TW-001 & 002
Registers and Records developed throughout the project:Induction registerToolbox talk registerForemans Daily Log Sheet
Total Incident DatabaseStatistics generated from the databaseComplaints logThird Party Communications RegisterWeekly Environmental checklistInternal Audit checklist and reportPhotographic ArchiveReinstatement Details
-
7/25/2019 EnvironmentalManagementPlan.pdf
12/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 12
7 ENVIRONMENTAL MANAGEMENT
7.1 Legal and Other Constraints
TW are bound to comply with existing legislation and any other constraints that are a condition ofthe consents granted for the Works. A comprehensive Legislation Register can be found asAppendix 1, which lists National and European Legislation, Regulations and Guidelines. In additionTW work to the established Best Environmental Practice. An Environmental Impact Statement isa legal requirement for consent for the Project as a whole, and this has anticipated many of theeffects on the environment caused by the development. Consent is forthcoming only whenassurance has been given by the developers that environmental impacts have been identified andwill be controlled, minimised and made good.
The Environmental Operational Control Procedures, which describe the control and managementof environmental impacts, have been written using Best Practice and Legal obligation.
TWs environmental procedures are an integrated package of: Training programmes involving all the workforce
On-site environmental presence
Detailed procedures to put in place physical controls
Detailed Emergency procedures
A good internal communication and reporting procedure
7.2 Aspects and Impacts of Construct ion Activity
An Aspects and Impacts Register specific to the Glenamoy Bog Complex SAC and theBroadhaven Bay SAC has been compiled by an experienced and qualified person to identify theenvironmental risks associated with this project. This forms Appendix 2 and 3 of this document.
The relevant components of this register will be included in the Works Method Statements asImpact Assessments. Aspects of the work which have associated environmental impacts will bethe subject of an Environmental Operational Control Procedure stating the mitigation measuresrequired to prevent, or ameliorate, the environmental impact, and this will be cross referenced inthe relevant Works Method Statement.
7.3 Traffic Management
All construction traffic activities will adhere to the Shell E&P Ireland Ltd Transport ManagementPlan, (ref. 2044 Shell E&P Irl. Ltd Transport Management Plan). Below the anticipated trafficmovements for landfall construction activities are given.
ESTIMATE OF TRAFFIC MOVEMENTS DURING CONSTRUCTION ACTIVITIES
Load WeightFrom
(Location)Route (to be
agreed) To (Location)No ofMove-ments
Period
1 Onshore Equipment
Portocabins 2T Ballina R314 or 313 Landfall 401/06 15/10
Hydraulic Excavator 45T BallinaN5/N59 - R314 or
313 Landfall 401/07 01/10
Hydraulic Excavator 14T Pullathomas R313
Rock Material 20 T Bellmullet R 314 Landfall 5001/07 01/10
2 Pull Act ivities
300 T linear winch 30T DublinN5/N59 - R314 or
313 Landfall 201/05 01/09
-
7/25/2019 EnvironmentalManagementPlan.pdf
13/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 13
Pull wires (2 pcs) 40T DublinN5/N59 - R314 or
313 Landfall 401/05 01/09
Containers (20') 10T DublinN5/N59 - R314 or
313Landfall / Along
route 1001/04 01/06
Reelwinders incl
Powerpack 8T Dublin
N5/N59 - R314 or
313 Landfall 4
01/04
01/06
Holdback Anchors 12 T DublinN5/N59 - R314 or
313 Landfall 401/08 01/09
7.4 Training
All employees and subcontractors will be given a comprehensive induction before they start work.This environmental training will take place in conjunction with H&S training and will involve a slideshow explained and narrated by both the H&S Adviser and Environmental Adviser.The environmental aspects will include:
An overview of the Environmental Management Plan, goals and objectives.
Awareness in relation to the risk, consequences and methods of avoiding noisepollution, oil/diesel spills, silt run-off, loss of topsoil, disturbance to wildlife anddisturbance to local residents.
Awareness of individual environmental responsibilities and environmental constraintsto specific jobs.
Location and sensitivity of The Glenamoy Bog Complex SAC and the Broadhaven BaySAC, how activities may effect them, methods necessary to protect them and activitiesto be avoided.
All personnel who have attended the Environmental Induction will sign a Register which will bekept on the Project Files.
In addition toolbox talks will be given to all staff and sub contractors by the environmental advisoras invaluable onsite training. These will be based on the specific activities being carried out suchas:
Dredging and backfilling
Mechanical rock breaking
Temporary causeway construction and reinstatement
Landfall and trench excavation.
Pipeline pull-in
Landfall and trench reinstatement
These talks will take place close to the time of work and will concentrate on environmental issues
particular to the Glenamoy Bog Complex SAC and the Broadhaven Bay SAC, namely; Oil/Diesel spill prevention onshore and offshore including safe refuelling practice.
Emergency response procedures used to deal with an oil/diesel spill.
Minimising disturbance to wildlife such as the sand martins nesting at Glengadheadland and cetaceans offshore.
Prevention of loss of topsoil and silt run-off.
Waste management procedures and correct segregation of waste.
Minimising noise pollution and disturbances to local residents.
See Appendix 5 (EP 101 Training).
-
7/25/2019 EnvironmentalManagementPlan.pdf
14/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 14
7.5 Waste Management
Waste will be managed through the following measures:
Covered lockable skips, bins and barrels will be position on site at Glengad Headland and atBallyglass to contain all waste (described below) generated during the works.
All staff will be made aware of their responsibility to dispose of all waste as described in thisprocedure.
ONSHORE
General waste
All reasonable steps will be undertaken to minimise the volume of wastes generatedthroughout the works.
All waste will be stored within the Yard until such time that is taken away by the projectappointed authorised Waste Contractor.
Separate skips will be used for the storage of timber, metal and general waste.
All skips will be covered.
All waste will be transported and disposed of by McGrath Waste Disposal (Castlebar)to an Authorised waste disposal facility.
Contaminated waste
Contaminated waste such as used spill kits and oily rags etc will be stored in clearlylabelled UN approved steel drums sealable metal barrels, as provided by Atlas IrelandLimited, who are also responsible for the disposal of the contaminated wastes to theirlicenced facility.
Hazardous waste
Hazardous wastes, such as aerosol cans, will also be stored in clearly labelled UNapproved steel drums as provided by Cara Waste Management who are responsible
for the disposal of these hazardous wastes to a suitably licenced facility.
Sewage waste
Sewage and wastewater will be stored in a fully contained steel holding tank which willbe located behind the welfare facilities at the Glengad Headland site. This tank will beemptied as necessary by Walsh Waste Disposal (Galway) who are responsible for thedisposal of the effluent to Bangor Erris Wastewater Treatment Plant.
OFFSHORE
All waste will be segregated and stored in specific covered containers on the vessels
in the same manner as all onshore wastes. Offshore wastes will be brought off vesselsat the pier and stored in covered lockable skips and barrels, awaiting collection fordisposal by the Waste Contractors mentioned above.
-
7/25/2019 EnvironmentalManagementPlan.pdf
15/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Page 15
Sewage and wastewater will be stored in temporary holding tanks.
Recording
Every movement of waste will be accompanied by a Controlled Waste Transfer Note and/or
C1 Document.
See Appendix 5 (EP 301 Waste Management).
7.6 Monitoring
The environmental concerns identified in the Aspects and Impacts Register will be controlledthrough the adherence to the Environmental operational control Procedures, Method Statementsand COSHH/MSDS recommendations.
The project will be monitored by daily and weekly site inspections of work activities and internalaudit reports.
The Environmental Advisor will also carry out regular noise monitoring onsite and at sensitivereceptors such as local residences prior to and during the work.
Water monitoring of a nearby stream will be carried out when flow is detected as this only occurs intime of heavy rainfall.
A long term and continual ecological survey has been put in place by the Client, part of whichincludes cetaceans, habitats, birds and other fauna.
The Environmental Advisor will assess the need for further monitoring.
See Appendix 5 (EP 104 Monitoring and measuring).
7.7 Internal Audits and Inspections
In line with the Quality Assurance System procedure and the audit programme, the site will beaudited to ensure compliance with the Environmental Management Plan and Procedures. TheEnvironment Advisor will carry out daily and weekly audits, the findings of which will be recordedon daily and weekly checklist.
Information collected in these audits will form the basis of decision on any corrective or preventiveaction which will be carried out by the Works Manager.
See Appendix 5 (EP103 Inspections and Audits).
7.8 Environmental Operational Control Procedures
All the Environmental Operational Control Procedures are found in Appendix 5
-
7/25/2019 EnvironmentalManagementPlan.pdf
16/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project
Figure 1 Emergency Procedure Onshore
-
7/25/2019 EnvironmentalManagementPlan.pdf
17/76
Page 1 of 1
FIG 1. EMERGENCY PROCEDURE ONSHORE
IN THE EVENT OF A POLLUTANT RELEASE
IN WATER ON LAND
ASSESSMAGNITUDE
LARGE SPILL
24 HR CALL OUT
LINKS WITH ALLSEAS
EMERGENCYPROCEEDURES
ON SITE SPILL
OILHYDRAULIC FLUID
DIESEL
COMPANY AND CLIENTTO BEINFORMED IMMEDIATELYBYTHE PROJECT MANAGER OR
DESIGNATED PERSON
MAYO COUNTY COUNCIL ANDTHE FISHERIES BOARD TO BE
INFORMED IMMEDIATELYBY
THE CLIENT
ALL INCIDENTS TO BE REPORTED ON INCIDENT FORMS
AND/OR ON DAILY CHECKLISTS (BOTH SUBMITTED TO THE
COMPNY AND THE CLIENT)
ALL INCIDENTS, EXCEPT SMALL SPILLS/LEAKS ON LAND, TO
BE SUBJECT OF SAME DAY REVIEW AND ANALYSIS BY
PROJECT MANAGEMENT TEAM
INFORMWORKS MANAGER
IMMEDIATELY
STOP DISCHARGE
CONTROL SPREAD
WITH BOOMS, SPILLKITS, SAND BAGS,
STRAW BALES
STOP DISCHARGE
CONTROL SPREAD
WITH SAND BAGS, EARTHBUNDS, GRANULES
DISPOSAL
CONTAMINATED CLEAN UP
MATERIAL TO SEALABLE
METAL BARRELS KEPTON SITE
MEDIUM SPILL
CLEAN UP USINGGRANULES, SPILL
KITS OR DIGGING UPCONTAMINATED
GROUND
SMALL SPILL/LEAK
CLEAN UP USING
SPILL KIT, GRANULES
INFORM WORKSMANAGER IMMEDIATELY
CLEAN UP
GENTLY TAKINGOIL OFF SURFACE
MAYO COUNTY
COUNCIL AND THEFISHERIES BOARD TO
BE FOLLOWED
EXACTLY
PROJECT EMERGENCY NUMBERS
24 HR CALL OUT +353 999CLIENT 1800201525
CLIENT ENV ADVISOR +353 87 0516871
EPA +353 5 60600PROJECT MANAGER +353 87 6918592
ENV ADVISOR +353 86 8123660
H&S ADVISOR +353 87 2887395
MAYO COUNTYCOUNCIL AND NPWS
TO BE INFORMEDIMMEDIATELYBY
THE CLIENT
COMPANY AND CLIENTTO BEINFORMED IMMEDIATELYBY
THE PROJECT MANAGER ORDESIGNATED PERSON
-
7/25/2019 EnvironmentalManagementPlan.pdf
18/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project
Figure 2 Emergency Procedure Offshore
-
7/25/2019 EnvironmentalManagementPlan.pdf
19/76
fig 2 rev d1_emergency proceedure offshore.doc Page 1 of 1
FIG 2. EMERGENCY PROCEEDURE
IN THE EVENT OF A POLLUTANT RELEASE OFFSHORE
IN THE SEA ON BOARD
IDENTIFY SOURCEASSESSMAGNITUDE
SPILLOIL
HYDRAULIC FLUIDDIESEL
CEMENT
CHEMICAL
INFORM MASTER IMMEDIATELY
ALL INCIDENTS TO BE RECORDED IN LOG
ALL OIL DISCHARGES INTO THE SEA TO BE REPORTED IMMEDIATELY TO:
-TH ENVIRONMENTAL ADVISOR
-THE PROJECT MANAGER
-THE COASTGUARD
AND THE CLIENT WHO WILL INFORM ALL RELEVENT 3RD
PARTIES
REPORTS TO BE WRITTEN UP ACCORDING TO PROCEDURE
INFORMMASTER
STOP DISCHARGE
CONTROL SPREADWITH SAND, SORBENTS,
GRANULES
DISPOSAL
CONTAMINATED CLEAN UPMATERIAL TO SPECIAL
WASTE CONTAINERSTOP DISCHARGE/MINIMISE ESCAPECONTROL SPREADWITH BOOMS,SORBENTS AND WHATEVERSEAMANSHIP AND NAVIGATIONAL
MEASURES ARE NECESSARY
ALERT
CREW MEMEBERS
-
7/25/2019 EnvironmentalManagementPlan.pdf
20/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project
Appendix 1 Legis lat ion Register
-
7/25/2019 EnvironmentalManagementPlan.pdf
21/76
Allseas Construction Contractors S.A. Title: Landfall and Pull-In Services Document NoCorrib Field Development Project Appendix 1: L
Category Legislation Regulations Other Requirem
Planning Pre
Construction
Local Government (Planning andDevelopment )Acts, Regs 1994 -1999Local Government Planning &
Development Regulations 2001Foreshore Acts 1933-1998Gas Acts 1976-2000Continental Shelf Act 1968Petroleum and Other MineralsDevelopment Act 1960 (Section13A) Regulations 1990Building Control Act 1990Acquisition of Land (Assessment ofCompensation) Act 1919
PD 8010:2004 Part I & IIof Practice for Design anInstallation of Gas Trans
Pipelines
Annex III EU Directive (8
EC (EIA) Amendment Re1999 (SI No. 419 0f 1994
Transport
Roads Act 1993
Public Safety Act 1927-1928
Ai r Emissions(includingdust andodouremissions)
Air Pollution Act No.6 1987
Air Pollution Act 1987 (Air QualityStandards) Regs
Air Pollution Act 1987 (SulphurContent of Gas Oil) Regs. 1994
EPA Act 1992 (Ambient Air QualityAssessment and Management)Regs. 1999Air Quality Standards RegulationsSI 271 of 2002Protection of the Environment Act2004
IPC Licensing by EPA
EU Regulation 3093/9Substances that deplOzone Layer
EU Directive 96/62/EAmbient Air Quality Aand Management 199
Geneva Protocol
Montreal Protocol
PollutionPrevention -General
EPA Act 1992Sea Pollution Act1991Dumping at Sea Act 1981-1996
Environmental Protection Agency(Licensing) Regs. 1994
IPC Licensing by EPA
-
7/25/2019 EnvironmentalManagementPlan.pdf
22/76
Allseas Construction Contractors S.A. Title: Landfall and Pull-In Services Document NoCorrib Field Development Project Appendix 1: L
GeneralWaste
HazardousWaste
Public Health Ireland Act 1878
Waste Management Act 1996
Waste Management (Planning)Regs1997
Waste Management (Register)Regs1997
Waste Management (Amendment ofWaste Management Act) Regs 1998
Waste Management (MiscellaneousProvisions) Regs 1998
Waste Management (Permits) Regs1998
Waste Management (HazardousWaste) Regs 1998
EU (Amendment of WasManagement Act) Regs.
EO Directive on Waste. 75/442
-
7/25/2019 EnvironmentalManagementPlan.pdf
23/76
Allseas Construction Contractors S.A. Title: Landfall and Pull-In Services Document NoCorrib Field Development Project Appendix 1: L
Category Legislation Regulations Other Requirem
Noise &Statutory
Nuisance
Air Pollution Act 1987 (Air QualityStandards) Regs
Environmental Protection AgencyAct 1992 (Noise) Regs
EC (Construction Plant aEquipment)(PermissableLevels) Regs 1988-1996
EC (Protection ofWorkers)(Exposure to N1990
EPA Guidance Notes forrelation to Scheduled Ac
The Montreal Protocol
The Geneva Protocol
The Kyoto Protocol 1997
-
7/25/2019 EnvironmentalManagementPlan.pdf
24/76
Allseas Construction Contractors S.A. Title: Landfall and Pull-In Services Document NoCorrib Field Development Project Appendix 1: L
Category Legislation Regulations Other Requirem
NatureConservation,
LandscapeandArchaeology
Wildlife and Amendment Acts (1976and 2000) which includes:
a. Natural habitats regulations: European Communities
(Natural Habitats)Regulation 1997 (SI No 94of 1997); and
European Communities(Natural Habitats)Regulation 1998 (SI No 233of 1998).
b. Flora Protection Order 1999 (SINo 94 of 1999)
Council Directive 92/EEC (Habitats
Directive)EU Directive No. 79/409 EEC (BirdsDirective)Wildlife Act 1976 and 2000
Heritage Act 1976
National Monuments Act 1930 andAmendment 1954, 87, 94
Bern Convention 1979 oconservation of Europeaand Natural Habitats.
Annex I EU Habitats Dire(habitat)
Annex II EU Habitats Dir(species)
Birds Directive
Site Designations:Ramsar Site (wetlands)SACs (habitats and specSPAs (Birds)
-
7/25/2019 EnvironmentalManagementPlan.pdf
25/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project
Appendix 2 Impacts Register Onshore
-
7/25/2019 EnvironmentalManagementPlan.pdf
26/76
-
7/25/2019 EnvironmentalManagementPlan.pdf
27/76
Allseas Construction Contractors S.A. Title: Landfall and Pull-In Services Document No: GENCorrib Field Development Project Appendix 2: Env. Im
ACTIVITY ASPECTUNAVOIDABLE
CONSEQUENCE
ASPECTDUE TO MISHANDLING,
NON-COMPLIANCE
POTENTIAL ADVERSEIMPACT
PREVENTION, MLEGAL REQUIRE
vehicle tracks conditions.Excessive compaction.Contamination
layer.Potential for spread of disease ifsoil is transportedArchaeological damageDamage to quality of farmlandand lasting visual impact.
Archaeological waSoil Procedure anfollowed. Also notefor disease, and fo
Any work inSACs
All activities generatenoise, fumes, groundvibration, compactionand disturbance
Failure to work toprocedures exacerbatesthe disturbance
Damage and disturbance toflora and fauna.Exclusion from their habitat.Permanent damage to siteintegrity.Landscape/Visual Impact
Avoidance where Strict adherence tothe constraints in tWildlife Act 1976Annex II and V of Directive
Welding Waste produced Failure to segregate and
dispose of wasteappropriately.
Uncontrolled waste on site,
detrimental to animals, possiblytoxic to plants and soil.Failure of Duty of Care
All waste to be bro
disposed of in appEPA Guidelines, EDuty of Care
Refuelling Use of fossil fuels Spills and leaks Ground and Watercontamination from toxicsubstances
Refuel as much asyard.Spill trays placed All fuel bowsers wand carry adequatand funnels.Refuelling only to designated personRefuelling not to taof a watercourse.
EPA Act 1992
PlantMaintenance
Use of, and drainingoff, diesel and oils onsite.
Spills and Leaks Ground and Watercontamination from toxicsubstances
Designated peoplePlant Maintenancechecks (rather thaCarry out Plant manecessary) in yardExtreme care.EPA Act 1992
-
7/25/2019 EnvironmentalManagementPlan.pdf
28/76
Allseas Construction Contractors S.A. Title: Landfall and Pull-In Services Document No: GENCorrib Field Development Project Appendix 2: Env. Im
ACTIVITY ASPECTUNAVOIDABLE
CONSEQUENCE
ASPECTDUE TO MISHANDLING,
NON-COMPLIANCE
POTENTIAL ADVERSEIMPACT
PREVENTION, MLEGAL REQUIRE
Fuel and OilStorage
Hazardous materialson site
Spills and leaks Ground and Watercontamination from toxicsubstances
Oil drums will be sdesignated bundefrom watercoursesTanks bunded (11Adequate supply ogranules.Locks on fuel tankDesignated persoEPA Guidelines, E
WasteCollection
Waste generation Waste material left on site Uncontrolled waste on site,detrimental to animals, possiblytoxic to plants and soil.Failure of Duty of Care
All waste to be segseparate polythentemporarily in seathe yard.
Waste ManagemeAmendment 1998
Waste Storageand Disposal
Storage of possiblyhazardoussubstances.Use of finite landfillspace
Failure to classify andsegregate waste. Norecycling policy
Uncontrolled waste on site,detrimental to animals, possiblytoxic to plants and soil.Failure of Duty of CareExtra costs
Separate covered metal drums.Special Waste cleRecycle where poWaste collected reDocumentation in Waste ManagemeAmendment 1998
Vehicle andplant
operations
Emission of noxiousgases. Production of
substances with GWP
Excessive air pollution andeffect on local and global
climate
Environmental degradation Implement Plant Mwhich involves fre
plant checks/mainAir Pollution Act19Standards) RegulaIPC Local Authorit
-
7/25/2019 EnvironmentalManagementPlan.pdf
29/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project
Appendix 3 Impacts Register Offshore
-
7/25/2019 EnvironmentalManagementPlan.pdf
30/76
-
7/25/2019 EnvironmentalManagementPlan.pdf
31/76
Allseas Construction Contractors S.A. Title: Landfall and Pull-In Services Document No: GENCorrib Field Development Project Appendix 3: Env. Im
OFFSHOREACTIVITY
ASPECTUNAVOIDABLE
CONSEQUENCE
ASPECTDUE TO MISHANDLING,
NON-COMPLIANCE
POTENTIAL ADVERSEIMPACT
PREVENTION, MLEGAL REQUIR
Causewayconstruction
Habitatdisturbance andvisual impact.Noise andincreased traffic
Undue disturbance, leadingto inadequate reinstatement.
Permanent visual impact andhabitat destruction.
No imported rockspeedy reinstateFollow procedure
Backfilling Disturbance tosea bedsediments
Lasting damage Permanent visual impact andhabitat destruction.
Adherence to Re
-
7/25/2019 EnvironmentalManagementPlan.pdf
32/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project
Appendix 4 Environmental Output
-
7/25/2019 EnvironmentalManagementPlan.pdf
33/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project Appendix 4: Environmental Output
Revision: D1 Page 1 of 1
Action Person Responsible Output
Pre-Construction
Sub Contractor Questionnaire QA/HS Engineer Questionnaire
Environmental Management Plan,including Waste Management and
Pollution Prevention procedures,internally reviewed and approved by theClientEnvironmental Method Statements SAC(Broadhaven Bay) and SAC (GlenamoyBog Complex).
Environmental Engineer Project EnvironmentalManagement Plan,
including comprehensiveOperational ControlProcedures
Environmental input into activity specificMethod Statements
Environmental Engineer Works Method Statements
Training
Environmental Induction and issue ofgreen card, EnviroTips
Environmental Engineer Register of names
Environmental Tool box Talks Environmental Engineer Register of names
Site presence and informal talks Environmental EngineerWork procedures
Waste management, Duty of Care,recycling schemes in place.
Yard Foreman andEnvironmental Engineer
Waste Documentation,Transfer/ConsignmentNotes
Foremans Log Foreman Daily return with WorkSheet
Action List, generated from checks andForemans Log
Works Manager andEnvironmental Engineer
Ongoing, working list
Environmental Incident/Concern form Environmental Engineer Incident forms andsummary
Weekly Project meetings Works Manager
Third Party Liaison Environmental Engineer Contacts RegisterPhotographic Record Environmental Engineer et al Photograph Archive
Monitoring
Specific Environmental monitoring. Environmental Engineer Sound monitoring reportsand daily and weeklychecklists
Ecological monitoring Survey put in place by theClient.
Ecological survey ofcetaceans, habitats andbirds.
Checks
Spot checks on site Environmental Engineer
Spill kit check at each refuelling Foreman Column in Refuelling
notebookWeekly Checklist Environmental Engineer Weekly Checklist
Monthly Audit on Documentation andWorking Procedures
Environmental Auditor Monthly Audit Report
Signs and Notices
On site on Roads, at Watercourses,Footpaths, on Waste skips/drums
Works Manager andEnvironmental Engineer
Offices and Canteen Information andupdates.
Environmental Engineer
Post Construction
Reinstatement Plan Environmental Engineer Reinstatement Plan
Monitoring reinstatement TW Monitoring report
End of project review and assessment TW Programme forimprovement
-
7/25/2019 EnvironmentalManagementPlan.pdf
34/76
Allseas Construction Contractors S.A. Title: Environmental Management PlanLandfall and Pull-In Services Document No: GEN-3761-010-TWCorrib Field Development Project
Appendix 5 Environmental Operational Control Procedures
-
7/25/2019 EnvironmentalManagementPlan.pdf
35/76
Environmental Procedure EP 101
ENVIRONMENTAL TRAINING
Rev D1
ep 101_rev d1_environmental training Page 1 of 2
1.0 SCOPE AND APPLICATION
These procedures apply prior to, and throughout, the construction period of this project.
2.0 PURPOSE
The objective of this Procedure is to outline the type of environmental training which will bereceived by all project personnel, whether they are TW staff or sub-contractors. All sitemanagement will have received relevant training on both general and site specificenvironmental matters prior to the commencement of any pre-construction and constructionactivities.
3.0 RESPONSIBILITIES
All personnel must be aware of the significance of the environmental issues addressed in the
EMP.Environmental Inductions will be given to all staff by the Environmental AdviserEnvironmental Toolbox Talks will also be given by the Environmental Adviser to supplementlearning as the project progresses.The works Manager is responsible for ensuring that all personnel attend the InductionsThe Environmental Adviser is responsible for advising on the need for any further training.
4.0 PROCEDURE
Employees will be given a comprehensive induction before they start work. No persons,including Subcontractors, will be permitted to commence employment on site without priorattendance at an induction training course. The environmental training will take place inconjunction with H&S training and will involve a slide show explained and narrated by both the
H&S Adivisor and Environmental Adviser.The environmental aspects will include:
An overview of the Environmental Management Plan, goals and objectives.
Rationale for environmental responsibility, including legislative requirements, clientenvironmental policy objectives, corporate environmental liability.
Awareness in relation to the risk, consequences and methods of avoiding noisepollution, oil/diesel spills, silt run-off, loss of topsoil, disturbance to wildlife anddisturbance to local residents.
Awareness of individual environmental responsibilities and environmental constraints tospecific jobs.
Location and sensitivity of The Glenamoy Bog Complex SAC and the Broadhaven BaySAC, how activities may effect them, methods necessary to protect them and activities
to be avoided. Avoidance of damage to habitats by prevention of encroachment into the adjacent dune
grassland, sand dunes and foreshore
All personnel who have attended the Environmental Induction will sign a Register which willbe kept on the Project Files.
In additiontoolbox talks will be given to all staff and sub contractors by theenvironmental advisor as invaluable onsite training. These will be based on thespecific activities being carried out such as:
Dredging and backfilling
Mechanical rockbreaking
Temporary causeway construction and reinstatement Landfall and trench excavation.
Pipeline pull-in
Landfall and trench reinstatement
-
7/25/2019 EnvironmentalManagementPlan.pdf
36/76
Environmental Procedure EP 101
ENVIRONMENTAL TRAINING
Rev D1
ep 101_rev d1_environmental training Page 2 of 2
These talks will take place close to the time of work and will concentrate on
environmental issues particular to the Glenamoy Bog Complex SAC and theBroadhaven Bay SAC, namely;
Oil/Diesel spill prevention onshore and offshore including correct refuellingprocedure.
Emergency response procedures used to deal with an oil/deisel spill.
Minimising disturbance to wildlife such as the sand martins at GlengadHeadland.
Prevention of loss of topsoil and silt run-off.
Waste management procedures and correct segregation of waste.
Minimising noise pollution and disturbances to local residents.
5.0 TERMINOLOGY
EMP - Environmental Management PlanSAC Special Area of ConservationH&S Health & Safety
6.0 FORMS/ASSOCIATED DOCUMENTATION
The following forms will be used:
Induction Register
Toolbox Talk Register
-
7/25/2019 EnvironmentalManagementPlan.pdf
37/76
Environmental Procedure EP 102
ENVIRONMENTAL REPORTING
Rev D1
ep 102_rev d1_reporting Page 1 of 2
1.0 SCOPE AND APPLICATION
These procedures apply throughout the construction period of this project.
2.0 PURPOSE
The objective of this Procedure is to outline the reporting of environmental concerns andincidents. TW is committed to a policy of continual improvement. A programme will bedeveloped to review and implement beneficial change, incorporating both short and long-termperspectives. This has to be based on quantifiable and objective data collected from the sites;which is why the reporting procedure is a fundamental prerequisite to measuredimprovement. For the reporting procedure to be used effectively a change in traditionalattitude is necessary. Reporting is not to be viewed as a negative activity to be avoided, butas a positive and crucial contribution to the continual improvement of our industry. This
viewpoint will be transmitted to the whole workforce during training sessions.
3.0 RESPONSIBILITIES
All personnel working out on the pipeline will be made aware of the significance of theReporting procedures and will assist their Foremen with relevant observations.The Foremen are responsible for completing the Foremans Log on a daily basis and giving itto the Works Manager at the end of each day.The Works Manager is responsible for checking or implementing the corrective action.The Project Manager is responsible for all liaison with the ClientThe Environmental Adviser is responsible for completing Incident and Complaint Forms,closing out corrective actions and communicating with the Company and the Client.
4.0 PROCEDURE
All Foremen will keep Logs. These will be used for the daily recording of ALL environmentalincidents, occurrences and observations. They will include:
All spillages and leaks, however minor,
Silt run-off and pollution
Wildlife and Stock presence on site
Landowner and Public complaints
Maintenance work required
Road Condition
Unsafe conditions
Near misses
The date, location, description and any cleaning up action taken will be recorded. Thisinformation/sheet will be passed to the Works Manager and Environmental Advisor. TheEnvironmental Advisor will assess the magnitude and seriousness of the incident.In the case of a serious incident such as a large oil/diesel spill on land or at sea; the Companyand the Client will be informed immediately who will in turn liase with all third partiesconcerned. Incident forms will also be completed and forwarded to the Company and theClient.In the case of minor incidents the Environmental advisor will record the information on daily andsubsequent weekly checklists which will be duplicated filed and passed on to the Company andthe Client.
The Logs from all the Foremen and the Environmental Incident Forms will be summarised forthe monthly Progress meeting.
-
7/25/2019 EnvironmentalManagementPlan.pdf
38/76
Environmental Procedure EP 102
ENVIRONMENTAL REPORTING
Rev D1
ep 102_rev d1_reporting Page 2 of 2
The Environmental Advisor will complete an Environmental Incident record.
All corrective actions will be completed satisfactorily and closed out. Liaison with the Companyand the Client will take place when necessary. All Complaints from Landowners or the Publicwill be recorded on the Complaints Form.
5.0 TERMINOLOGY
Incident: An event or near miss which could lead, to adverse effects on livingorganisms, habitats or any other environmental resource.
All Incidents are classified as Non-Conformances. Events can include:
Excessive Pollution of the air
Pollution of the ground
Any Pollutants entering watercourses
Pollution of topsoil
Excessive noise pollution
Harmful emissions to the atmosphere
Events involving chemical wastes
Mishandling, or illegal disposal of, general wastes
Damage to environmentally sensitive areas
Damage to Flora and Fauna
6.0 FORMS/ASSOCIATED DOCUMENTATION
The following forms may be used during these procedures: Foremans Log
Environmental Incident Record
Incident Report
Action List
Third Party Contact List
Complaints Form
-
7/25/2019 EnvironmentalManagementPlan.pdf
39/76
Environmental Procedure EP 103
INSPECTIONS AND AUDITSRev D1
ep 103_rev d1_inspections and audits Page 1 of 7
1.0 SCOPE AND APPLICATION
These procedures apply throughout the construction period of this project.
2.0 PURPOSE
The objective of this Procedure is to outline the inspection and auditing of all construction activities and theassociated works and installations. Sub-Contractors will be included in all inspections and audits and aresubject to the same constraints as TW staff.
3.0 RESPONSIBILITIES
All personnel working on the pipeline will be made aware of Inspections and Audits and the standards that arerequired.
The Environmental Adviser is responsible for completing daily and weekly inspections and discussingcorrective and preventive actions with the Works Manager.The Works Manager is responsible for implementing corrective action.The Environmental Adviser is qualified to perform Internal Audits.
4.0 PROCEDURE
Subcontractors such as diving and plant hire companies will be issued with a Subcontractor Questionnaireand their Method Statements will be inspected prior to employment. They will conform to the same stringentenvironmental constraints as the TW procedures. Subcontractors will be expected to follow TWsEnvironmental Procedures and will be subject to the regular inspections and monitoring on the basis of this.Deviation from the accepted practice will not be tolerated. Subcontractor documentation and site performancewill be audited under the same rules as those for TW.
Daily and weekly Environmental Inspectionswill be completed by the Environmental Adviser. A samplecopy of the Checklist used is appended to this Procedure (Form D2). The checklist includes:
Checks on the security of storage, adequate segregation and handling of waste produced on site.
Checks that waste transfer and consignment notes have been adequately filled in and filed.
Check the site for any potential for pollution and instigate preventive measures
Check soil piles remain segregated.
Checks to ensure compliance with other commitments in EMP.
Check the Environmental Incident Record daily and ensure that the causes of any incident have beeninvestigated and measures taken to minimise the chance of a recurrence.
Provide recommendations on how waste management and recycling, or any other aspect of
environmental performance could be practically improved.The results of the checklist will form the basis of an Action List that will be discussed between theEnvironmental Adviser and Works Manager who will delegate the appropriate corrective action to be taken.
An internal Environmental Audi twill take place on a monthly basis and include the following tasks:
Check that all records for Environmental Inspections and Monitoring are in place.
Provide an Audit Report
Review the Environmental Management System and provide a review
Time permitting, interview a cross section of the workforce to ensure quality of the training system
5.0 TERMINOLOGY
Audit: Formal, systematic and objective activity undertaken to verify whether a requirement is beingfulfilled, performed by one or more persons who are independent of that which is audited
-
7/25/2019 EnvironmentalManagementPlan.pdf
40/76
Environmental Procedure EP 103
INSPECTIONS AND AUDITSRev D1
ep 103_rev d1_inspections and audits Page 2 of 7
Inspection: Conformity evaluation by observation and judgement accompanied as appropriate bymeasurement, testing or gauging
EMP Environmental Management Plan
6.0 FORMS/ASSOCIATED DOCUMENTATION
The following forms may be used during these procedures:
Daily Inspection Checklist
Weekly Inspection Checklist
Action List
Audit Checklist and Report
Audit Method Statement
-
7/25/2019 EnvironmentalManagementPlan.pdf
41/76
Form D.2 Site Environmental Audit Protocols
Daily Environmental Inspection Checklist
This form is to be completed by the Site Scientist dailyfrom the start of main construction work on site. Completed forms are to
be kept readily available (preferably on site) for the duration of construction works, after which time shall form part of the Project
Environment file.
Any Environmental actions identified are to be brought to the urgent attention of the appropriate personnel as soon as possible.
Contractor/Project Manager to be notified of actions required/taken.
Audit Items for Construction Phase Comment Action Required
Protection of Watercourses
Visual Inspection of watercourses and drains forsigns of silt and other pollutants
Ensure flumes are installed in drains PRIOR tocrossing
Inspect topsoil stripping
Dust
Inspect all road crossings and access points forsigns of mud and/or dust
Inspect haul routes and running tracks for dust.
Waste
Inspect Skips & Containers are clearly andappropriately labelled, and not over full
Check for evidence of litter or waste on the
working widthSegregation of wood, metal, cardboard, paper,plastic
General and special waste segregated correctly
Check that all stored fuels and chemicals are inthe correct containers and location
Habitat and Species Protection
Check the fencing is intact and in place toprotect the San Martin Colony
Ensure that method statements are being
followed to protect key habitats (sand martincolony, Broadhaven Bay)
Bird or cetaceans in work area
Archaeology
Dredging/excavation, items encountered
-
7/25/2019 EnvironmentalManagementPlan.pdf
42/76
ENVIRONMENT INSPECTION - COMMENTS
If required, provide supporting comments relating to the specified environmental checks or on any site environmental matter
worthy of note
Audit Items for Construction Phase Comment Action Required
Protection of Land
Machinery in good condition with no leaks orspills evident
Use of designated refuelling areas and specialmeasures as required.
Spill kits available, on machines and at key
locationsAre all environmental signs and warnings inplace?
Check the fencing is intact and in place toprotect the foreshore
Check the fencing is intact and in place toprotect the dune grassland not subject to works
Check the fencing is intact and in place toprotect the sand dunes
Nuisance
Traffic management system in operation
Machines switched off when not used
No excessive noise, all appropriate plantsilenced
-
7/25/2019 EnvironmentalManagementPlan.pdf
43/76
Weekly Environment Inspection Checklist
This form is to be completed by the Site Scientist weeklyfrom the start of main construction work on site. Completed forms are
to be kept readily available (preferably on site) for the duration of construction works, after which time shall form part of the
Project Environment file.
Any Environmental actions identified (NCRs) are to be brought to the urgent attention of the appropriate personnel as soon as
possible. Contractor/Project Manager to be notified of actions required/taken.
Audit Items for Construction Phase Comment Action RequiredProtection of Watercourses
No of recorded incidents?
Monitoring results this week
Number of permits to pump issued
Dust
No of NCRs raised?
No of complaints received ?
Noise
Random check of equipment for NCTcertification if required
Have extended working hours been approved ?
Have any complaints relating to noise beenreceived?, have they all been logged andactions taken?.
Noise monitoring results from dwellings within100m proximity to main pipeline activities, orany other activity monitored.
Waste
Amount of waste taken offsite this week, haveall relevant forms been completed?
Amounts of recycling taken this week, have allrelevant forms been completed
Condition of waste facilities
Public Relations
No of events occurred this week?
Habitat and Species Protection
Is all vegetation kept short to deter groundnesting birds
Are all demarcation signs and fences in placeto protect the San Martin Colony
Have all persons working in each area beenfully briefed on requirements? Are recordsavailable?
Have all method statemnets and reinstatementplans been approved by NPWS etc? are copiesavailable?
Archaeology
Dredging/excavation, items encountered
-
7/25/2019 EnvironmentalManagementPlan.pdf
44/76
ENVIRONMENT INSPECTION - COMMENTS
If required, provide supporting comments relating to the specified environmental checks or on any site environmental matter
worthy of note
Continutation sheet No Pages:
Protection of Land
Check the fencing is intact and in place toprotect the foreshore
Check the fencing is intact and in place toprotect the dune grassland not subject to works
Check the fencing is intact and in place toprotect the sand dunes
Are fuel and chemical storage areas inaccordance with project and legislationrequirements?
Refueling and spill kits
Soil: excavation, reinstatement, silt control
No. of site environmental inductions carried outthis week
No. of tool box talks undertaken this week
Competance of suppliers
Have all assessments been undertaken for all
new suppliers and subcontractors? Are recordsup to date?
Other
Environmental incidents/near misses/hazardsreported this week
Has Incident (TW and SEPIL) register beenupdated
-
7/25/2019 EnvironmentalManagementPlan.pdf
45/76
Environmental Procedure EP 103
INSPECTIONS AND AUDITS
Rev 0
ep 103_rev d1_inspections and audits Page 7 of 7
Monthly Environmental Report
A monthly report will be prepared which will be issued to SEPIL and will be suitable for the EnvironmentalMonitoring Group: It will include amongst other aspects the following issues:
Review of Construction Activities
Suppliers
i.e. Check suppliers/contractors accreditations/qualifications?
i.e. Archaeologists, waste carriers, etc
Environmental Method Statements
Waste Management
Identify all waste carriers and disposal routesReview of waste taken offsite.
Calculation of % recycled for:Wood, metal, carboard, paper, plastic
Ecological Monitoring results
Other Monitoring results
Noise
Water
Environmental Incidents
Complaints
-
7/25/2019 EnvironmentalManagementPlan.pdf
46/76
Environmental Procedure EP 104
MONITORING AND MEASURING
Rev D1
ep 104_rev d1_monitoring and measuring Page 1 of 1
1.0 SCOPE AND APPLICATION
These procedures apply throughout the construction period of this project.
2.0 PURPOSE
The objective of this Procedure is to outline the type of environmental monitoring which will takeplace during the works. Key characteristics of the operations and activities that can have asignificant impact on the environment have been tabulated in the Aspects and ImpactsRegister.
3.0 RESPONSIBILITIES
The Environmental Advisor will advise on the monitoring requirements.The Environmental Advisor will record and assess the data and discuss any corrective and
preventive action with the Works Manager.The Construction Manager is responsible for implementing the corrective action.
4.0 PROCEDURE
Environmental monitoring will be carried out off shore, on site and near sensitive receptors suchas local residences. This information will be documented, as necessary by the EnvironmentalAdvisor.Monitoring will be specific and may entail the collection of baseline data prior to anyconstruction activity.
Noise monitoring will take place on site and near local residences. Regular noisemonitoring will take place during the course of the work..
There is a watercourse directly south of the site which flows only in times of very high
rainfall. Water sampling will be carried out when flow is detected and analysed forgeneral water quality at an accredited laboratory. Sample bottles will be kept on siteshould water sampling prove necessary.
All staff will be required to notify their foreman of the presence of wildlife in the workarea such as, cetaceans (offshore) and nesting birds (onsite, Glengad Headland). Theforeman will in turn notify the Environmental Advisor. A long term and continualecological survey has been put in place by the Client, part of which involves a cetaceanand bird watch.
Any reinstatement will be monitored for a period of six months as part of the aftercareprogramme
The Environmental Advisor will assess the need for any further monitoring.
Monitoring equipment shall be calibrated and maintained and records of this process shall beretained by the QA Department.
5.0 TERMINOLOGY
Monitoring: The regular and systematic collection of data in a manner that can bereplicated.
6.0 FORMS/ASSOCIATED DOCUMENTATION
The following forms may be used during these procedures:
Specific Data Collection Record
-
7/25/2019 EnvironmentalManagementPlan.pdf
47/76
Environmental Procedure EP 105
CONSENTS AND AUTHORISATIONS
Rev D1
EP 105_Rev D1_Consents and Authorisations Page 1 of 2
1.0 SCOPE AND APPLICATION
These procedures apply as soon as the tender is awarded and throughout the constructionperiod of this project.
2.0 PURPOSE
The objective of this Procedure is to provide specific instruction and guidelines for gaining thenecessary consents and authorisations for the project. As a rule, construction activities arelegally constrained from starting without the necessary consents in place.
3.0 RESPONSIBILITIES
The Environmental Advisor is responsible for applying for the necessary consents.The Environmental Advisor will have responsibility for liaison with the Company and the
Client. The Client will then liase with all relevant Third Parties.The statutory authority responsible for wildlife and nature conservation is the National Parksand Wildlife Service (NPWS) of the Dept. of the Environment, Heritage and LocalGovernment (DoEHLG).The Works Manager is responsible for implementing requirements of the Company and theClient.
4.0 PROCEDURE
All necessary consents and authorisations will be in place before the relevant workproceeds. These are summarised in the appended table.
Mayo County Council will be notified and consulted on relevant pipeline activities.
The Emergency Services will be notified and hold a copy of the Traffic ManagementPlan.
Close liaison will take place with NPWS on ecological issues, especially where wildlifehandling requires a special licence.
Mayo County Council and the North Western Regional Fisheries Board (NWRFB)will bekept fully informed of construction activities at all times. Consultation will take placewith the Fisheries Board prior to any abstraction or discharge of A good workingrelationship will be developed between these bodies and the contractor and workingprocedures will follow the approved guidelines.
A record of all Third Party meetings, telephone calls and correspondence will be kept ina chronologically organised Third Party Communications Register. This will besubmitted with the monthly progress report.
5.0 TERMINOLOGY
Third Parties: Statutory Bodies, whether Government organisations or NGOs, who have avested interest in the construction activities.
6.0 FORMS/ASSOCIATED DOCUMENTATION
The following forms may be used during these procedures:
Consent Application Forms
-
7/25/2019 EnvironmentalManagementPlan.pdf
48/76
Environmental Procedure EP 105
CONSENTS AND AUTHORISATIONS
Rev D1
EP 105_Rev D1_Consents and Authorisations
ENVIRONMENTAL CONSENT AND AUTHORISATION CHECKL
ACTIVITY LEGISLATION CONSULTATION/APPROVAL SUPPORTING PAPERWOR
Water Discharge EnvironmentalProtection Act 1992
Mayo County CouncilNW Fisheries Board
Detailed and site specific MethStatements, including environmmitigation measures
Alter Flow ofwatercourse
EnvironmentalProtection Act 1992
Mayo County CouncilNW Fisheries BoardNPWS
Noise Environment ProtectionAct 1992
Mayo County Council Statement detailing noise, mitigmeasures and possible monito
Working Hours Mayo County Council Statement detailing preferred wand asking permission to work those approved by the Council
Waste Waste Management Act
1996Transport Amendment1998
Mayo County Council
Environment Protection Agency
Copy of Waste Carriers Licenc
on site. Waste segregated andC1 documents
Hazardous substances Waste Management(Hazardous Material)Regs 1998
Mayo County CouncilEnvironment Protection Agency
Hazardous Waste segregated of appropriately
Nesting Birds Wildlife Acts, 1976 and2000
NPWS Any vegetation removal (brambscrub etc.) to take place before
Archaeological Site Heritage Act 1976 DoEHLG Survey required to identify sitesArchaeologist on site with watc
-
7/25/2019 EnvironmentalManagementPlan.pdf
49/76
Environmental Procedure EP 108
Plant Maintenance Programme
Rev D1
ep 108_rev d1_plant maintenance Page 1 of 1
1.0 SCOPE AND APPLICATION
This procedure applies to ALL plant brought onto the site, irrespective of ownership.
2.0 PURPOSE
The objective of this Procedure is to provide specific instruction and guidelines for theacceptance, inspection and maintenance of all plant and equipment that is brought onto thesite. The same programme is to be used for TW, Sub-Contractor and Hired Plant. Thisprocedure is designed to enable TW to meet the required standards it has set itself forpollution prevention and control.
3.0 RESPONSIBILITIES
The Procurement Officer is responsible for ordering plant for the project.
The Safety Advisor is responsible for auditing this programme.The Environmental Advisor is responsible for auditing this programme.The Lifting Gear and Plant Co-ordinator is responsible for implementing this programme andmaintaining the appropriate records.
4.0 PROCEDURE
The Procurement Officer orders the Plant required for the project. The Assistant Procurement Officer records the Plant as it enters the Yard and
immediately passes a copy of the record to the Lifting Gear and Plant Co-ordinator. The Lifting Gear and Plant Co-ordinator makes a check of the Plant, including any
associated paperwork/calibration certificates, and completes the Plant, Machinery andEquipment Checklist.
The Checklist is a unique record for one piece of Plant only, and is treated as aclearance Permit for that piece of Plant to be used on site. They are held in the SiteDocument Control room.
The Lifting Gear and Plant Co-ordinator puts a visible mark on the piece of Plant toindicate that it has been passed for use. This is useful as a quick check on site to ensurethat all Plant has been included in this procedure.
The Lifting Gear and Plant Co-ordinator transfers the unique Plant number to a list whichis the basis of the regular Plant Maintenance Checklist.
When machinery is off-hired or removed from site the Assistant Procurement Officerinforms the Lifting Gear and Plant Co-ordinator who deletes it from the PlantMaintenance Checklist
The Environmental Adviser and the Safety Advisor audit this procedure monthly. Repair to equipment and machinery carried out on site will be done in accordance with
best practice. This will involve; qualified personnel, the use of spill trays and spill kits,work at designated workshop area (if possible). Strict adherence to the pollution controlprocedures will be enforced.
5.0 FORMS/ASSOCIATED DOCUMENTATIONPlant, Machinery and Equipment ChecklistPlant Maintenance Checklist
-
7/25/2019 EnvironmentalManagementPlan.pdf
50/76
Environmental Procedure EP 201
POLLUTION PREVENTION AND CONTROL - ONSHORE
Rev D1
ep 201_rev d1_pollution prevention and control - onshore f1 Page 1 of 2
1.0 SCOPE AND APPLICATION
These procedures apply to all activities that could result in a pollution incident on land with particularattention being paid to a nearby minor watercourses at Glengad Headland due south of the trenchexcavation, These procedures are effective from the first presence on site and throughout theconstruction period of this project. All activities will be conducted in such a manner as to
Prevent adverse environmental impacts to the Glenamoy Bog Complex SAC and the nearbyBroadhaven Bay SAC
Ensure mitigation measures are implemented for non-preventable environmental impacts
Reinstate/restore, as far as is practicable, the environment to its pre-project state
2.0 PURPOSE
The objective of this Procedure is to fully describe the actions necessary to prevent a pollution incidentonshore including watercourses. It also describes the mitigation measures that will be implemented
should there be such an occurrence.
3.0 RESPONSIBIL ITIES
Al lpersonnel have a legal responsibility to ensure that ground and water will not be contaminated.Pollution is a prosecutable offence, for an individual as well as a company.All personnel are responsible for following the clean up procedures should contaminants spill or leakonto the ground or into a watercourse.The Foremen are responsible for assessing the magnitude of the spill and acting according to theEmergency Procedures described in the Flow Chart (See Fig1).The Foremen are responsible for ensuring any spill or leak is reported in the Foremans Log and copiedto the Works Manager and the environmental advisor.The Environmental Advisor is responsible for advising on any subsequent action and completing theReporting Procedures.
The Works Manager is responsible for implementing any corrective action.
4.0 PROCEDURE
Pollution prevention is dependent on the strict adherence to waste managemnt and storage andbunding procedures. The most likely pollutants on site are diesel, oil, hydraulic fluid, cement and alimited range of job specific chemicals. The potential for small spills and leaks is high on a constructionsite. To limit their environmental impact the following precautions will be in place:
All staff will be given a comprehensive environmental induction prior to commencing work. Thiswill place an emphasis on the nature of the Glenamoy Bog Complex SAC and the BroadhavenBay SAC; and the sensitive ecosystems therein.
Regular toolbox talks will also be given based on specific tasks and the related environmentalhazards.
A high priority will be given to using equipment such as pumps and generators with integral DripTrays. Small leaks and spills of oil and diesel will then be contained without their mixing withlarge amounts of rainwater. (All of which is then a Hazardous Waste and expensive in time andmoney terms to dispose of)
There will be sufficient clean up material (spill kits) on site to cope with all forseeable small andmedium size spills.
An Emergency 24 hour call out number for oil spill clean up specialists is held on site tofacilitate a rapid response in the event of a major incident, where additional pollution controlequipment may be required.
All site vehicles will carry a Spill Kit.
Extra spill kits and bags of granules will be stored at areas of high risk, such as refuelling points.
Refuelling will be carried out by designated persons only.
Fuel Bowsers will be double hulled (to prevent leaks) and lockable. Storage tanks will not be located near any watercourse.
Refuelling will not take place within 10m of a minor watercourse, or near top soil storage piles..
-
7/25/2019 EnvironmentalManagementPlan.pdf
51/76
Environmental Procedure EP 201
POLLUTION PREVENTION AND CONTROL - ONSHORE
Rev D1
ep 201_rev d1_pollution prevention and control - onshore f1 Page 2 of 2
Plant maintenance will only be carried out with a drip tray under the work area and with
adequate spill kit material to hand. All Foremen will hold a copy of the Emergency Procedure (Onshore) on site.
All inert, contaminated and hazardous waste must be segregated to a designated labelled skip(covered) or sealable metal barrel for subsequent disposal.
All oils and job specific chemical will be stored in a covered, lockable, steel bund.
In the case of excavation work particular attention will be paid to the prevention of silt run-offinto watercourses and the nearby Broadhaven Bay SAC with the use of straw bales andgeotextiles.
If a spill or leak should occurs the Emergency Procedures (See Fig 1) will be implemented immediately.These are summarised as follows:
STOP-
By turning off machinery and valves, blocking leaks and placing a containerbeneath leaks
CONTAIN - by using granules and spill kits, or inert material such as sand or earth, diggingtrenches and using absorbent pads, booms or skimmers.
NOTIFY- The foreman and the Environmental Advisor will be informed of all spills. TheEnvironmental Advisor will then assess the incident and either inform the Company and theClient immediately (large spill) or record the incident as part of a weekly report. The Client willthen notify the appropriate third parties.
DIPOSE - Bag all contaminated materials and dispose of it in the yard in the appropriatecontainer.
REPORT - all pollution incidents will be assessed by the environmental advisor who will theninitiate corrective action to prevent a repeat occurrence.
5.0 TERMINOLOGYPollution of the Environment : The release into air, water or ground of substances which arecapable of causing harm to any living organism.
6.0 FORMS/ASSOCIATED DOCUMENTATION
The following forms may be used during these procedures:Foremans LogEnvironmental Incident Record
7.0 LEGISLATION AND REFERENCES
The recent EU Water Framework Directive is a comprehensive piece of legislation aimed to protect thewater quality of inland surface waters, groundwater and transitional water. It seeks to prevent furtherdeterioration and restore the aquatic ecosystem on the basis of environmental criteria. This Directive
has yet to be transposed to Irish legislation, however, this Project will operate in accordance with thestated aims.Pollution control shall be carried out in accordance with the following:
EPA Act 1992
Environmental Protection Agency (Licensing) Regs. 1994
EU Water Framework Directive
Local Government (Water Pollution) Regs 1987, and Amendment 1999
Fisheries Act 1959, consolidated 1999
COSHH/MSDS (Material Data Sheets)
Environment Agencys Pollution Prevention Guidelines(These are standard guidelines held in common between the Environment Agency England and
Wales and the Scottish Environment Protection Agency. There are 22 of these Guidelines,about half directly relating to pipeline construction works. However, they are guidelines onlyand cannot be used directly as procedures.)
-
7/25/2019 EnvironmentalManagementPlan.pdf
52/76
Environmental Procedure EP 202
POLLUTION PREVENTION AND CONTROL - AIR
Rev D1
ep 202_rev d1_pollution prevention and control - air Page 1 of 2
1.0 SCOPE AND APPLICATION
These procedures apply to all activities that could result in air pollution, from the first presence onsite and throughout the construction period of this project. All activities will be conducted in such amanner as to:
Prevent adverse environmental impacts to the Glenamoy Bog Complex SAC and the nearbyBroadhaven Bay SAC
Ensure mitigation measures are implemented for non-preventable environmental impacts
Reinstate/restore, as far as is practicable, the environment to its pre-project state
2.0 PURPOSE
The objective of this Procedure is to fully describe the actions necessary to prevent air pollution.
3.0 RESPONSIBILITIES
Al lpersonnel have a legal responsibility to ensure that the air is not contaminated. Pollution is aprosecutable offence, for an individual as well as a company.The Foremen are responsible for ensuring plant is maintained.The Environmental Advisor, or his designate, is responsible for advising on any subsequent actionand completing the Reporting ProceduresThe Works Manager is responsible for implementing any corrective action.
4.0 PROCEDURE
Emissions that can pollute the air can be exhaust fumes from plant and machinery, fumes fromchemicals, coatings and solvents or mechanical processes, dust and grit generated by siteoperations. The following procedures will be put in place to reduce the impact of such emissions:
All staff will be given a comprehensive environmental induction prior to commencing work. Thiswill place an emphasis on the nature of the Glenamoy Bog Complex SAC and the BroadhavenBay SAC; and the sensitive ecosystems therein.
Regular toolbox talks will also be given based on specific tasks and the related environmentalhazards.
All plant used on site will be in good operative condition. Exhaust emissions from all plant will bereduced as much as possible by effective and regular maintenance.
Plant and generators will be switched off when not in use.
Care will be taken to ensure that no emissions can percolate into excavations by removing thesource from the immediate area. Where such risks occur, adequate ventilation or forced air flowswill be installed.
During prolonged periods of dry weather, dust may cause a nuisance to local residents and
damage vegetation and animal habitats. For major dust control on the working width, a watersprinkling system will be used as necessary. Adequate P.P.E. will be provided for personnelworking in these environments.
A 10 m.p.h. speed limit will operate on the working width to reduce excessive airborne dust duringdry spells.
Haul lorries carrying dusty loads will be covered.
Road cleaning services will be provided by the Client to remove potential dust sources fromtransport routes.
-
7/25/2019 EnvironmentalManagementPlan.pdf
53/76
Environmental Procedure EP 202
POLLUTION PREVENTION AND CONTROL - AIR
Rev D1
ep 202_rev d1_pollution prevention and control - air Page 2 of 2
TYPICAL AIR EMISSIONS FOR PLANT AND EQUIPMENT TO BE USED
5.0 TERMINOLOGY
Pollution of the Environment: The release into air, water or ground of substances which are capableof causing harm to any living organism.
6.0 FORMS/ASSOCIATED DOCUMENTATION
The following forms may be used during these procedures:Foremans LogEnvironm