epc in leisure centres - dublin city council's exemplar project

18
EPC in Leisure Centres- DCC Exemplar Project Cormac Healy, Project Manager, Dublin City Council Declan Mc Cormac, Project Manager, Codema

Upload: codema

Post on 09-Feb-2017

151 views

Category:

Engineering


1 download

TRANSCRIPT

EPC in Leisure Centres- DCC Exemplar Project

Cormac Healy, Project Manager, Dublin City CouncilDeclan Mc Cormac, Project Manager, Codema

Energy Use for DCCSummaryDCC 120 GWh (TFC) in 2014,

Public Lighting and Transport highest consumers highest cost

Register of Opportunities

Office

Sports

Secti

on

Dublin

Fire B

rigad

e

Travel

ling C

ommun

ity

Housin

g Main

tenan

ce

Communi

ty Dev

elopm

ent S

ection

Dublin

Fire B

rigad

eOffice

Office

Sports

Secti

on

Parkin

g Enfo

rcemen

t & Po

licy Se

ction

Dublin

Fire B

rigad

e

Parkin

g Enfo

rcemen

t & Po

licy Se

ction

Road

Mainten

ance

Servi

ces Office€0

€200,000€400,000€600,000€800,000 € Electricity € Gas

DCC Exemplar project

Ballymun Leisure Centre

Built in 2005 3,279m2

Energy Spend € 229,463/yr

Finglas Leisure Centre

Built 2003 1,915m2

Energy Spend € 158,219/yr

Markievicz

Built 2002 1,182m2

Energy Spend € 116,613/yr

What are the Issues? Legislation - 20 20 20

Staff non-technical

Limited by operating parameters

Multiple traditional maintenance contracts

Budgetary restrictions

Is EPC the Solution?It Should:

One stop shop for maintenance

Provide energy reduction guarantee

Allow future budget forecasting

Outside capital finance

Is there a Business Case?Conducted Investment Grade Audits (IGAs), general findings:

Upgrade of existing CHP and installation of new CHPs

New BMS

Heat Pumps

Increased controls of AHUs

General upgrade of plant – pumps, improved schedules etc

The Numbers Annual Spend € 504,295

Total Investment Required €661,000+

Total Expected Annual Savings € 203,300

Simple Payback 3.2 Years

On paper there is a business case for an EPC

How Do We Get From Here to There?

Identify champions

Approval from senior management to proceed

Engage with the SEAI Exemplar program

Start a well structured project management process

Project Management Structure

Create the plan or Work Breakdown Structure

DCC EPC

Tender

Publish Contract

NoticePre-Qualification

Competitive

Dialogue

Write Tender

NoticeEvaluate Tenders Signed Contract

Shortlist Report on CD Invitation to

Tender

Re-Evaluate Financial Appraisal

Appoint Facilitator and Contract

Manager

Select Preferred

Tender

Inform Unsuccessful

tenderers

Schedule

Management Approval to proceed to procurement (Milestone)

Week 3 October

Publish contract notice (Milestone) Week 1 Febuary

Issue Invitation to tender (Milestone) Week 1 November

Select preferred tender (if applicable if not reject all) (Milestone)

Week 1 December

Contract Signing (Milestone)Week 3 December

Close out Week 4 January

Summary of the PM Process for EPC1. Establish the Business Case – IGA’s2. Get Senior Management Approval3. Identify champions at all levels4. Assemble the ‘core’ project team – Finance, Legal, technical, Procurement5. Start the procurement process – PIN notice, start to design your PQQ6. Assemble the technical file7. Issue PQQ8. Select tenderers9. Conduct competitive dialogue10. Issue ITT 11. Select winning tender12. Start contract

Why Competitive Dialogue? Advantages Possible Disadvantages

• 2 stage process Lack of experience

Face to Face Principles of public procurement!

Minimises the need to design the works Need Tenderers buy in

Range of solutions

‘Free’ expert consultancy

Compare ‘In-house IGAs to the Market opinion

Lessons Learnt So Far…. It will take longer than you think!!

Competitive Dialogue is very informative

Don’t underestimate the need for legal, financial, technical and procurement advice

There is an appetite in the market for EPC in Ireland

The need for champions

The need to explain EPC

Thank You

[email protected]@codema.ie