equipment labor capabilities 1
DESCRIPTION
Not ImportantTRANSCRIPT
EQUIPMENT CAPABILITIESType of equipment
Average Capabilities1. Bulldozer (108) (a) Clearing
500 sq.m./hr.
(b) Stripping
200 sq.m./hr.
Excavation:
1. Common Soil
45 cu.m./hr.
2. Slightly Hard Materials
25 cu.m./hr.
(d) Quarrying:
107 Common Materials
50 cu.m./hr.
108 Aggregate
40 cu.m./hr.
Boulders
15 cu.m./hr.
200 Needs screening
(e) Pushing
3 cu.m./hr
2. Road Grader (a) Subgrading
300 cu.m./hr
(b) Spreading
50 cu.m./hr.
3. Payloader
(a) Loading
30 cu.m./hr.
4. Crane Shovel
(a) Loading
35 cu.m./hr.
5. Sheep Foot Roller
(a) Static Rolling (12 passes-15 cm./lift)15 cu.m./hr.
(b) Vibratory Rolling ( 4 passes-15 cm.lift)135 cu.m./hr.
6. 3- Wheel Road Roller(a) Static Rolling (6 passes -20 cm. lift )24 cu.m./
7. Tractor Drawn Roller(a) Vibratory Rolling (6 passes-20 cm. lift)24 cu.m./hr.
8. Tandem Roller
(a) Static Rolling (6 passes-20 cm. lift )24 cu.m./hr.
(b) Vibratory Rolling (6 passes-60 cm. lift)72 cu.m.,/hr.
9. 6-T Dump Truck
(a) Hauling Common Borrow Base Course3.5 cu.m./hr.
(b) Hauling Selected Borrow Base Course5.0 cu.m./hr.
Hauling Concrete Batch Class A2 Batch/trip
10. 2 T-Dump Truck(a) Hauling Common Borrow Base Course2.5 cu.m./trip
(b) Hauling Selected Borrow Base Course4.0 cu.m./hr.
Hauling Concrete Batch Class A
1 Batch/trip
11. Buggy
(a) Hauling Concrete Mix
0.17 cu.m./trip
12.Wheel Borrow
(a) Hauling Aggregates
0.17 cu.m./trip
(b) Hauling Concrete Mix
0.05 cu.m./trip
13. Water Truck
(a) Watering
1000sq.m./trip
14. Concrete Mixer
(a) Mixing Concrete
9 cu.m./hr.
15.Rock Crusher
(a) Crushing mixed sand & gravel
30 cu.m./hr.
16. Concrete Vibrator
(a) Vibrating Concrete Mix
40 cu.m./hr.
17. Concrete Floor Finisher(a) Finishing Concrete Floor
140 cu.m./hr.18.Percussioned Drilling(a) Drilling Hard Rock
0.23 m./hr.
(b) Drilling Loose Rock
0.30 m./hr.
Drilling Limestone
0.38 m./hr.
(d) Drilling Sticky Clay
0.49 m./hr.
(e) Drilling Loose Clay
0.70 m./hr.
TASK RATES FOR LABOR-BASED PROJECTS
I. For Item 100- Clearing & Grubbing
Activity :
Productivity
1) Bush Clearing
Sq.m./man-day
Bush Type
a) light bush
200
b) medium bush
100
c) dense bush
50
2) Tree and Stump Removal
One (1) man-day per cm. of trunk diameter a
@ base of tree
3) Grubbing
Sq.m./man-day
Vegetation Type
a) Dense vegetation in firm soil covering80
the whole area
b) Spatse vegetation in loose soil
250
II. For Item 105- Excavation for Roadway & Drainage
Activity
Productivity1) Excavation
Cu.m./man-day (throwing dist. in m.)
Soil Type
0-4m.
4-6m.
6-8m.
a) Loose,rot sticky soil
5.0-6.0
4.5-5.5
3.5-4.5
b) Firm soil
3.5-4.5
3.4-4.0
2.5-3.5
c) Very hard soil, hard soil mixed
2.0-3.0
1.8-2.5
1.7-2.5
with stones
2) Loading
Cu.m./man-day
Type of soil
a) Loose
4.50-5.50
b) Firm
2.50-4.00
c) Hard
1.50-2.50
Excavation combined with loading of soil can be effectively carried out by laborers up to a loading height of about 1.00 e.g. into wheel borrow or head baskets. Above that height, it is preferable to have a separate group of loaders whose output must be matched with that of the excavators.
Necessary output for the Loading ActivitySoil Type
Loading HeightProductivity cu.m./man-daya) Loose
0.1 m.
12-15
b) Loose
1-2 m.
7-10
c) Loose
Over 2 m.
4-5
III. For Item 106- Excavation for StructuresActivity
Productivity
1) Excavation
Depending on the type of soil, there use similar productivity data as those
used for Excavation in Item 105
IV. For Item 110- Foundation Fill
Activity
Productivity1) Backfilling & Tamping
3 cu.m./man-day
V. For Item 108- Aggregate Sub- Base Course
Activity
Productivity
1) Quarrying (Excavation & Gravel)
0.50-2.00 cu.m./man-day2) Loading
7.00-10.00 cu.m./man-day
3) Spreading
8.00-12.00 cu.m./man-day
4) Compacting
8.00-12.00 cu.m./man-day
5) Hauling Activity should be considered in this item, hence, hauling distance has
an important bearing on the cost of the gravelling operation, the maximum acceptable
hauling distance has to be considered from case to case.
VI. For Item 200- Aggregate Base Course
Activity
Productivity
1) Quarrying
0.50-2.00 cu.m./man-day
2) Loading
7.00-10.00 cu.m./man-day
3) Spreading
8.00-12.00 cu.m./mn-day
4) compacting
8.00-12.00 cu.m./man-day
5) Hauling- please refer to activity no.5 of Item 108
6) Screeping
3.00-5.00VII. For Item 413- Reinforced Concrete Pipe Culvert
Activity
Productivity 1) Crushing of stone for aggregate
0.20 cu.m./man-day
2) Casting of culvert rings
2 man-day/ring
3)Laying of standard culvert (24 in. dia.)
Refer culvert laying data belowOr 0.60 m. dia., length 6.00 m., including
Excavation, culvert bad and backfill.
4) Building of headwalls with masonry blocks10 man-day/2 headwalls
If the length of the culvert exceeds 6 meters, the number of man-days has to be increased accordingly.
Culvert laying- this task consist of the excavation of the trench preparing the bed, laying of culvert, backfilling & compaction. Number of man-days required varies with the volume of the excavation and the soil type.
FACTORS TO BE MULTIPLIED TO DETERMINE THE REQUIRED QUANTITY OF EACH MATERIALCONCRETE (BASED) on the 88 lbs. bag of cement
CLASS A CONCRETE ( 3000 psi)
CEMENT 9.1 bags/cu.m of concreteSAND- 0.50 cu.m/cu.m of concrete
GRAVEL 0.84 cu.m/cu.m of concrete
CLASS B CONCRETE ( 2500 psi)
CEMENT 8.38 bags/cu.m of concrete
SAND- 0.45 cu.m/cu.m of concrete
GRAVEL 0.82 cu.m/cu.m of concrete
CLASS C CONCRETE ( 3500 psi)
CEMENT 9.77 bags/cu.m of concrete
SAND- 0.53 cu.m/cu.m of concrete
GRAVEL 0.70 cu.m/cu.m of concrete
CLASS D CONCRETE ( 4000 psi)
CEMENT 11.17 bags/cu.m of concrete
SAND- 0.44 cu.m/cu.m of concrete
GRAVEL 0.68 cu.m/cu.m of concrete
FOR BRIDGE ESTIMATE
LUMBER for false work 60 bd.ft/cu.m of concrete
NAILS
- 2 kilos/cu.m of concrete
TIE WIRES
- 1.1 kilos/cu.m of concrete
Painting structural steel 3 gals/ton
AVERAGE FUEL CONSUMPTION PER DAY
FUEL
ENGINEGEAR
GREASEOIL#10
OIL
OIL
Crane,140 liters (diesel)4 liters
1 liter
2 lbs.
-
Diesel Hammer, 20 liters-
-
-
1 liter
( diesel)
Bulldozer, 200 liters3 liters
1 liter
1 lb.
1 liter
( diesel)
Payloader, 100 liters3 liters
1 liter
1 lb.
1 liter
( diesel )
Grader, 120 liters
3 liters
1 liter
1 lb.
1 liter( diesel 0
Roller, 60 liters ( diesel)2 liters
1 liter/wk.2 lbs./wk.1 liter
Dump Truck, 60 liters1 liter
2 liters/wk.1 lb.
1 liter
( diesel )
Mixer ( 1- bag ), 40 -
-
0.5 lb.
-
Liters ( gasoline )
Vibrator, 15 liters
-
-
-
-
( gasoline )
One Bagger Mixer- 100 bags/day
Crane- minimum of 2 piles/day ( 16m. length including spotting )
VOLUME OF TRENCH CU.M.
Soil Type
7
7-8
10-13
In these cases, the work split over two or more days. First the trench should be excavated and then the preparation of the bed, the laying, backfilling and compaction is done. Only 3 times. Therefore the volume of the excavation has to be limited following rates and then applicable:
Soil Type
Productivitya) hard soil
3.50 cu.m./man-day
b) very hard, stony
2.00 cu.m./man-day
After completion of the trench approximately 4 man-days are needed to lay 6 rings, backfill and compact to finish road level.
I. MECHANIZED ASPECT
A. CLEARING AND GRUBBING
Dozer
Production
Horse
Dense of Vegetation ( No. of Trees/Hectares )
Power
0-50 51-100 101-200 201-250 251&>
120
360
250
190
160
130
140
420
290
220
185
150
160
480
330
255
210
170
180
540
375
285
240
195
200
600
420
310
265
215
B. EXCAVATION ( Common Materials )B.1 CRANE
Tonnages
Capacity ( cu.m./hr.) Bank Volume
Canal
Structure
Creek
15
15
10
10
20
20
15
15
25
25
20
20
30
30
25
25
B.2 DOZER
Horse
Production ( cu.m./hr.) Bank Volume
Power
Canal
Structure
120
30
15
140
35
20
160
40
25
180
45
30
200
50
35
B.3 BACKHOE
Bucket ( cu.m.)
Production ( cu.m./hr.) Bank Volume
Canal
Structure
Creek
0.50
20
15
15
0.75
30
20
20
1.00
40
30
30
1.25
50
40
40
1.50
60
45
45
C. QUARRYING
Dozer ( H.P.)
Production (cu.m./hr.) Bank Volume
Common Aggregate Cobbles/Boulders
140
55
60
27
160
60
65
29
180
65
70
31
200
70
75
33
D. LOADING
Bucket ( cu.m.)
Production ( cu.m./hr.) Bank Volume
Common Aggregate Cobbles/ Boulders
1.0
50
55
35
1.5
75
80
55
2.0
100
110
75
2.5
125
135
90
3.0
150
165
110
E. SPREADING
Grader ( H.P.)
Road ( cu.m./hr.) cmp.
Common Aggregate
80-100
60
70
100-125
70
80
125-150
90
100
150-175
100
110
F. SIDE BORROW ( Common Materials )
Dozer (H.P.)
Production ( cu.m./hr.) Compacted Volume140 35
160 40
180 45
200 50G. STP. BACKFILL WITH SPREADING & COMPACTION
Dozer
Production cu.m./hr. Compacted Volume140 50
160 70
180 80
200 90
H. EMBANKMENT COMPACTION
Capacity ( cu.m./hr.) Compacted Volume
Tons
Self-Propelled
Tamp. Foot drumVib. drum
10
80
60
12
90
70
15
120
90
I. LOADING, SPOT & MANEUVER TIME
Using Loader with 1.00 cu.m. Bucket
Dump Truck Capacity
Compacted Volume ofCobbles/Boulders
CommonRoad Surface
MaterialsMaterials
4.00 cu.m.
7 min.
7 min.
10 min.
6.00 cu.m.
9 min.
9 min.
12 min.
8.00 cu.m.
11 min.11 min. 15 min.
J. AVERAGE SPEED OF DUMP TRUCK
Type of Road
Kilometer per hour
With Load
Without Load
Concrete/Asphalt Road
35
45
Good Maintained Gravel Road30
35
Poorly Maintained Gravel Road20
25
K. DEMOLITION OF CONCRETE
160 CFN Compressor & two (2) Jack Hammer
Capacity- 8.00 cu.m./day for massive concrete
-12.00 cu.m./day for slab & wall
L. DRIVING OF PILES
Steel Pipes: Crane 25 tons with 2-tons drop hammer, Capacity = 8 L.M./Hr.
Concrete Piles : Crane 25 tons with 2500 kgs. Pile hammer, Capacity = 2.00 L.M. per Hr., 4.00 LM/Hr. for thick & thin concrete piles.
N. MANUAL ASPECT
A. Excavation
A.1. Common Materials
Capacity ( cu.m./day) Bank Volume & Depth of Excavation
Type of Work
( meter )
Farmditchs
3.00
2.50
2.00
Canal
2.50
2.00
1.75
Structure
2.00
1.75
1.50
A.2. Slight hard materials ( Ind.)
Type of Work
Capacity ( cu.m./day/man) Bank Volume
Canal
1.00
Sructure
0.75
B. LOADING CAPABILTIES OF FIVE (5) LABORERS
Sand & Common Cobbles Boulders Cement R.S. Bars Lumber Ply
Gravel
cu.m./hr. cu.m./hr. cu.m./hr. cu.m./hr. bags/hr. kgs/hr. bd.ft./hr. pcs./hr.
4
5 3.5 3 300 6,000 4,000 250
C. UNLOADING CAPABILITIES OF FIVE (5) LABORERS
Sand & Common Cobbles Boulders Cement R.S. bars Lumber Ply
Gravelcu.m./hr. cu.m./hr. cu.m./hr. cu.m./hr. bags/hr. kgs./hr. bd.ft./hr. pcs./hr. 6 6 5 4 300 7,000 4,000 250
D. CUT, BEND,& PLACE RSB
Structure
1 Steelman & 1 Helper with Bar Cutter
Canal & Others
80 kgs./day
E. QUARRYING
Capability
cu.m./day/man
Sand & Gravel
Cobbles
Boulder
3.50
2.50
2.00
F. DEMOLITION OF CONCRETE
Slab & Wall
0.50 cu.m./man-day
Massive Concrete
0.20 cu.m./man-day
G. SCREENING OF AGGREGATES
Gravel
4.00 cu.m./day/man
Sand
6.00 cu.m./day/manH. MANUAL BACKFILL
Capacity : 3.00 cu.m./man
I. LAYING OF MATERIALS ( cu.m./day/man)
Cobbles 2.00
Boulders 1.50
J. SPREADING OF AGGREGATE
Capacity : 2.50 cu.m./day/man
K. RUBBLE MASONRY ( Concreting )
Crew : 1- Foreman, 2- Mason, 10- Laborers, & 1- L.E. Operator
Capacity : 6.00 cu.m./day
L. GROUTED RIPRAP
Crew : 1- Foreman, 2- Mason, 10- Laborers, & 1- L.E. Operator
Capacity : 7.50 cu.m./day
M. C.H.B. : Setting Capacity sq.m./day
Crew : 1- Mason, 2- Laborers
Fence
Building
4 CHB
14
10
6 CHB
10
8
N. CONCRETE LINING
Crew : 1- Foreman, 2- Mason, 1- L.E. Operator, 10- Laborers with one (1) bagger mixer
Capacity : 4.50 cu.m./day
O. INSTALLATION OF STEEL GATES
Crew : 1- Mason & 5- Laborers
16 x 16 to 24 x 24
2 assy/day
Above 24 x 24
1 assy/day
P. CONCRETE WORKS
P.1. Fabrication, Placing & Dismantling of Forms
Crew : 2- Carpenters & 4- Laborers; Capacity : 3.50 cu.m./day for 3000 psi
Crew : 1- Carpenter & 1- Laborer; Capacity : 4.50 cu.m./day Canal lining
P.2. Concreting and Curing Capability
P.2.a. With concrete mixer
Crew : 1- Foreman, 2- Mason, 1- L.E. Operator, & 8- Laborers
Class A : 3.50 cu.m./day
Class B : 3.70 cu.m./day
Class C : 3.50 cu.m./day
Lean Concrete : 4.50 cu.m./day
Q. PLASTERING OF CHB WALL
Crew : 2- Mason, & 2- Laborers
Capability : 12 sq.m./day ( one side only )
R. REINFORCED CONCRETE PIPES
Crew
Capability
Diameter
inch
cm.
FabricationInstallation
1- Foreman
12
30
15
16
1- Mason
18
46
11
14
1-Carpenter/Steelman
24
61
9
12
12- Laborers with
30
76
6
10
1- Bagger Mixer
36
91
5
8
48
122
3
6
42
4
7
NOTE : TIME OF MIXER/DAY= BAGS OF CEMENT/DAY X 10 MIN./BAG
60 MINUTES/ HOUR
III. MATERIAL ASPECT
Class Strength Max. Aggre. Cement Sand Gravel Boulder
Size, in. bag,cu.m. cu.m./cu.m. cu.m./cu.m. cu.m./cu.m.A. Concretea. 211 bags 1.50
9.000.45 0.90
-
b. 200 kgs. e 2.00
7.000.50 1.00 -
Canal lining
200 kgs. e 1.00 7.50 0.48 0.96 -
B. Rubble Mason
w/ 211 kgs. e - 4.50 0.225 0.45 0.75
C. Grouted Riprap- 4.20 0.35 0.05 1.00
Plain Riprap - - - 0.10 1.00
D. Lean Concrete - 5.00 0.50 1.00 -
1000 psi
E. Gravel Blanket - - - 1.00 -
F. Filter Drain - - - - -
OTHER MATERIALS
ClassType of Strength F. Lumber pl. wd. Tie wr. Nail
Structure kgs. bd.ft/cu.m. pcs/cu.m. kgs.cu.m kgs/cu.mA
Bridge/Flume 211 40 1.00 1.25%RSB 2.50
A
Siphon/Box Cul. 211 25 1.25 1.205 RSB 2.00A Other Str. @ inc 211 25 1.25 1.10% RSB 2.00
A 211 5 0.10 - 0.50
B 200
5 - - 0.25
A 211 15 0.40 1.00%RSB 1.50
B 200 5 0.10 1.005RSB 0.50
A 211 5 - - 0.25
REINFORCED CONCRETE PIPES
Diameter
Fabrication Materials per pc.
Cement Sand Gravel G.I. F. Lumber Tie Wire CW
Sheet
Nails
Inches Bag Cu.m. Cu.m. Pc. Bd.ft kgs. kgs.
12 0.58 0.02 0.05 0.12 0.34
9.28 0.10
18 1.22 0.05 0.10 0.19 0.36 7.72 0.20
24 1.82 0.08 0.15 0.24 0.48 9.75 0.3030 2.56 0.11 0.21 0.30 0.60 23.22 0.4036 3.33 0.14 0.28 0.34 0.72 50.43 0.5042 4.26 0.18 0.36 0.40 0.84 60.84 0.60INSTALLATION OF R.C. PIPES
DiameterCement SandGravel R.S.B. F. Lumber CWN & TWInches Bags Cu.m. Cu.m. kgs Bd.ft. kgs.
12 0.21 0.01 0.02 - 2.00 0.20
18 0.45 0.02 0.04 3.65 2.00 0.20
24 0.72 0.03 0.06 4.52 3.00 0.30
30 0.93 0.04 0.08 5.26 3.00 0.30
36 1.11 0.05 0.10 6.01 4.00 0.40
42 1.32 0.06 0.12 6.79 4.00 0.40PLASTERING C.H.B. BLOCK
Size
Materials per sq.m. for two (2) sides
Sand
Cement
4 & 6 0.034
0.41
G.I. LAYING OF C.H.B.
Size
Cement
Sand
Bags/aq.m.
Cu.m./sq.m.
4 0.55
0.046
6 1.07 0.089
RECOMMENDED INDIRECT COST
Estimated Direct
Indirect Cost for OCM & Profit Max.Mobilization
Cost ( E.D.C. )
Ranges
O.C.M. % of
C.P. % of E.D.C.
E.D.C.
Up to 1 Million
13%
15% 2% Above 1 M to 5 M 12% 14% 2%Above 5 M to 10 M 12%
14% 2% Above 10 M to 20 M 11% 12% 2%Above 20 M to 50 M 11% 12% 2% Note: The total contract price should be equal to or less than the total COA estimate plus 10% in order to sustain a finding of reasonableness otherwise the contract price will be deemed excessive.
ACEL RATE 1998
Operated Equipment
Description
Rate/DayBulldozer
Komatsu, D80A-12DD
Php 9,160.00
180 Hp
Payloader
75 TCM/Clark, 1.53 cu.m.,
Php 10,010.00
Capacity, 151 Hp
Road Grader
Mitsubishi MG 500 170 Hp
Php 8,808.00
Dump Truck
Japan & Other Make,
Php 9,016.00
10 cu.m. Capacity
Road Roller
Ingersoll Rand SP48 MI Tons Php 8,701.00
Crane
All models, Truck mounted,
Php 11,296.00
standard mechanically operated
31-35 tons
Back Hoe
Komatsu PC 120, Capacity
Php 9,656.00
90 Hp
Transit Mixer
Japan make 3.8 cu.m., 46 cu.m.Php 8,528.00
Capacity 175 Hp
Air Compressor
Gas/Diesel Engine, CFM
Php 1,376.00
20 Hp
Plate Compactor
12 Hp Engine Driven
Php 1,648.00
Asphalt Paver/FinisherWorthington 34 ( basic Php 3,320.00
Equipment only)
Asphalt Distributor
Little Ford Sprasmaster
Php 5,784.00
Bare Equipment
Description
Rate/DayPile Hammer (w/o crane) Domag D8-22
Php 5,067.00
Drop Hammer (w/o crane) Two tons w/ Pile Hammer
Php 100.00
Jack Hammer
Stanley, Hydraulic w/o
Php 294.00
power unit
Welding Machine
Gas/Diesel Driven 250
Php 300.00
Amps., 185 Hp
Concrete Mixer
1-Bagger
Php 298.00
Concrete Vibrator
Gas or Diesel Driven
Php 341.00
Chainsaw
Husquama, 2100 CD w/o BladePhp 180.00
Water Truck
All makes, 500-1000 gals.
Php 1,773.00
Water Pump
All models 3.5 4 size
Php 119.00
Concrete Batch Plant
With Cement Silo Manual
Php 5,113.00
/mo.x Rated Cap. In
Cu.m./hr.
LABOR OUTPUT CAPABILITIESREMOVAL EXISTING STRUCTURES :
Lumpsum
Installations:
Timber:
Girts and Girder
0.10- 0.15 cu.m./man-days
Floor Joist
150 L.M./man-days
Flooring boards
15-18 sq.m./man-days
Post
0.14 cu.m./man-daysWalling/Sliding :
Covering
30 sq.m./man-days
Framing, Studs
12 cu.m./man-days
( Multiply by the no. of days Double walling)
Ceiling Joist and Hangers
16 sq.m./man-days
Ceiling Boards ( 4 x 8 Ply Wood)
30 sq.m./man-days
Windows sashes :
Jambs Fabrication
4 sq.m./man-days
Frames Fabrication
2 sq.m./man-days
Jambs Installation
14 sq.m./man-days
Frames Installation
10 sq.m./man-days
Doors :
Jambs Fabrication/Installation
2.5 sq.m./man-days
Door Fabrication/Installation
1 panel/man-days
Paintings :
Paint Rollers
125 sq.m./man-days
Paint Brush
50 sq.m./man-days
Neutralizer
100 sq.m./man-days
Truss Fabrication
0.25 truss/man-days
Purlins Installaation
60 L.M./man-days
Fascia Boards
0.05 cu.m./man-days
Roof Coverings ( G.I. sheets )
35 pcs./man-days
Concrete Works :
Concrete Pouring
0.30 pcs./man-days
Rebars
20-30 kgs/man-days
Finishing:
Rough Finish
10 sq.m./man-days
Plain/Fine Finish
8 sq.m./man-days
CHB Filling/Laying
6-8 sq.m./man-days
A. CEMENT MORTAR
Table -1 Quantity of Cement and Sand for CHB Mortar per Square Meter Wall
Size of CHB No.per sq.m.
40 Kg. Mixture Cement Bags
A B C D Sand4 x 8 x 16
12.5 0.525 0.394 0.328 0.0438 6 x 8 x 16 12.5 1.013 0.759 0.633 0.0844
8 x 8 x 16 12.5 1.500 1.125 0.938 0.1250
B. MORTAR FOR PLASTERING
Table-2 Quantity of Cement and Sand for Plastering per Square Meter
40 kg. Cement Bags
Mixture Class
16 mm thk.
20 mm. thk.
25 mm. thk.
A
0.288
0.360
0.450
B
0.192
0.240
0.300
C
0.144
0.180
0.225
D
0.120
0.150
0.188
Sand
0.016
0.020
0.0251. Find the area of the wall ( two faces )
Area = 3.00 x 4.00 x 2 faces
A = 24 sq.m.
2. Refer to Table-2 under 16 mm thick plaster class B mixture: Multiply:
Cement = 24 x 0.192 = 4.6 bags
Sand = 24 x 0.016 = 0.384 cu.m.
C. CHB FOOTING
Table-3 Quantity of Cement, Sand, and Gravel for CHB Footing per Meter LengthDimension
Cement in Bags Class Mixture
AggregateCentimeters
40 kg. Cement
Sand
Gravel
t
w
A
B Cu.m.
Cu.m.
10
30
0.270
0.225 0.015
0.030
10
35
0.315
0.263
0.018
0.035
10
40
0.360
0.300
0.020
0.040
10
50
0.450
0.380
0.020
0.050
15
40
0.540
0.450
0.030
0.060
15
45
0.608
0.506
0.034
0.068
15
50
0.675
0.563
0.038
0.075
15
60
0.810
0.675
0.045
0.090
20
40
0.720
0.600
0.040
0.080
20
50
0.900
0.750
0.050
0.100
20
60
1.080 0.900
0.060
0.120
1. Solve for the net length of the CHB wall
Net length = 40 m ( .25 x 11 post )
= 37.25 meters
2. Refer to Table -3 along the 15 x 50 cm footing dimensions 40 kg. Cement class A
Mixture; Multiply :
Cement : 37.25 x 0.675 = 25.14 say 26 bags
Sand : 37.25 x 0.038 = 1.4 say 1.5 cu.m.
Gracel : 37.25 x 0.075 = 2.8 say 3.0 cu.m.
MAINTENANCE BY CONTRACT ( MBC )
METHODS OF CONSTRUCTION1. PATCHING POTHOLES Should be done to the areas specified by the contracts and plans duly approved by the Engineers. Materials to be used must be suitable to acquire best result when compacted.
SCHEDULE OF WORKS :MONTHLY
2. RESHAPING- should also be done to areas required in the plan and contracts. All works should conform to what will be described in the specification.
SCHEDULE OF WORKS :QUARTERLY
3. VEGETATION CONTROL AND CLEANING DITCHES All objects subject for the obstruction of the designed areas should be removed and cleared.
SCHEDULE OF WORKS :TWICE A YEAR
4. REGRAVELLING All materials shall consist of hard, durable particles or fine divided mineral matter that can be compacted reaching for stable sub-base. Using especially equipped vehicles material should be distributed in a continuos uniform layer. The uniform thickness of sub-base material shall be adjusted prior to the compaction by watering or by drying as required in order to obtain the required compaction. Compaction shall continue until a field density of at least 100 (%) per cent of the maximum dry density.
SCHEDULE OF WORKS - ANNUAL
5. BLADING/GRADING- All unstable materials should be removed in areas subject for Blading/Grading. These areas should be brought to a grade required in the plans and contracts. Compaction will follow using heavier compacting units until required density can be attained.