Erection Report Lot 178 Week 1
Date of Report: August 13, 2012
Customer: Quadra
Machine Model: 7495 H
Serial Number: 141477
Location: Sierra Gorda, Chile
Erector Engineer: Walter Villar Prez
Friday August 3, 2012
Field assembly day: 1Crew Shift: Day 12 hours
Work complete:
Position, clean and prepare truck frame, 50%
Position, clean and prepare crawler frames, 50%
Position, clean and prepared revolving frame, 30%
Inventory material, 15%
Assemble crawler links, 25%
-
8/23/2019 Erection Report Lot178 Week 1[1]
2/10
Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900
Saturday August 4, 2012
Field assembly day: 2Crew Shift: Day 12 hours
Work complete:
Assembly crawler links first set, 50%
Clean and prepared truck frame, 75%
Clean and prepared crawler frames, 100%
Clean and prepared swing rack, 50%
Inventory material, 30%
Clean and prepare special bolts, 100%
-
8/23/2019 Erection Report Lot178 Week 1[1]
3/10
Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900
Sunday August 5, 2012
Field assembly day: 3Crew Shift: Day 12 hours
Work complete:
Installed left hand crawler frame, 100%
Installed and adjusted the crawler frame bolts LH, 50%
Assembly crawler links first set, 75%
Clean components
-
8/23/2019 Erection Report Lot178 Week 1[1]
4/10
Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900
Monday August 6, 2012
Field assembly day: 4Crew Shift: Day 12 hours
Work complete:
Install right side crawler frame, 100%
Install and adjust the crawler frame bolts RH, 50%
Install and adjust the crawler frame bolts LH, 100%
Clean and prepare high voltage collector rings, 100%
Prepare boom
Clean and prepare components
-
8/23/2019 Erection Report Lot178 Week 1[1]
5/10
Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900
Tuesday August 7, 2012
Field assembly day: 5Crew Shift: Day 12 hours
Work complete:
Install high voltage collector rings, 30%
Install and adjust the crawler frame bolts RH, 100%
Positioning crawler frame over crawler belt
Check and mark cables, 25%
Prepare DPT1 and DPT2, 75%
Install and adjust the crawler frame bolts RH, 100%
-
8/23/2019 Erection Report Lot178 Week 1[1]
6/10
Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900
Wednesday August 8, 2012
Field assembly day: 6Crew Shift: Day 12 hours
Work complete:
Assemble crawler belts second set,
Positioned truck-crawler frame on crawler link
Clean and prepare revolving frame, 30%
Clean and prepare utilitarian room base, 50%
Clean and prepare lube room base, 50%
-
8/23/2019 Erection Report Lot178 Week 1[1]
7/10
Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900
Thursday August 9, 2012
Field assembly day: 7Crew Shift: Day 12 hours
Work complete:
Install platforms, ladders and handrails on boom, 25%
Clean and prepare swing rack, 100%
Clean and prepare boom point sheave, 50%
Prepare and install DPT1 and DPT2, 50%
-
8/23/2019 Erection Report Lot178 Week 1[1]
8/10
Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900
Friday August 10, 2012
Field assembly day: 8Crew Shift: Day 12 hours
Work complete:
Install and connected crawler belt, 50%
Install and weld ballast box plates, 10%
Clean and prepare boom point sheave, 100%
-
8/23/2019 Erection Report Lot178 Week 1[1]
9/10
Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900
Saturday August 11, 2012
Field assembly day: 9Crew Shift: Day 12 hours
Work complete:
Install and connected crawler belt, 100%
Install and adjust swing rack, 50%
Install boom point sheave, 100%
Install and welded ballast box plates, 15%
Clean components
Install and connected boom lube system, 30%
-
8/23/2019 Erection Report Lot178 Week 1[1]
10/10
Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900
Sunday August 12, 2012
Field assembly day: 10Crew Shift: Day 12 hours
Work complete:
Install and adjust swing rack on truck frame, 100%
Install boom platforms, 80%
Install DPT1 and DPT2, 100
Install light system on control room roof, 30%
Install and connected boom lube system, 80%