  • 8/23/2019 Erection Report Lot178 Week 1[1]

    1/10

    Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

    Erection Report Lot 178 Week 1

    Date of Report: August 13, 2012

    Customer: Quadra

    Machine Model: 7495 H

    Serial Number: 141477

    Location: Sierra Gorda, Chile

    Erector Engineer: Walter Villar Prez

    Friday August 3, 2012

    Field assembly day: 1Crew Shift: Day 12 hours

    Work complete:

    Position, clean and prepare truck frame, 50%

    Position, clean and prepare crawler frames, 50%

    Position, clean and prepared revolving frame, 30%

    Inventory material, 15%

    Assemble crawler links, 25%

  • 8/23/2019 Erection Report Lot178 Week 1[1]

    2/10

    Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

    Saturday August 4, 2012

    Field assembly day: 2Crew Shift: Day 12 hours

    Work complete:

    Assembly crawler links first set, 50%

    Clean and prepared truck frame, 75%

    Clean and prepared crawler frames, 100%

    Clean and prepared swing rack, 50%

    Inventory material, 30%

    Clean and prepare special bolts, 100%

  • 8/23/2019 Erection Report Lot178 Week 1[1]

    3/10

    Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

    Sunday August 5, 2012

    Field assembly day: 3Crew Shift: Day 12 hours

    Work complete:

    Installed left hand crawler frame, 100%

    Installed and adjusted the crawler frame bolts LH, 50%

    Assembly crawler links first set, 75%

    Clean components

  • 8/23/2019 Erection Report Lot178 Week 1[1]

    4/10

    Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

    Monday August 6, 2012

    Field assembly day: 4Crew Shift: Day 12 hours

    Work complete:

    Install right side crawler frame, 100%

    Install and adjust the crawler frame bolts RH, 50%

    Install and adjust the crawler frame bolts LH, 100%

    Clean and prepare high voltage collector rings, 100%

    Prepare boom

    Clean and prepare components

  • 8/23/2019 Erection Report Lot178 Week 1[1]

    5/10

    Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

    Tuesday August 7, 2012

    Field assembly day: 5Crew Shift: Day 12 hours

    Work complete:

    Install high voltage collector rings, 30%

    Install and adjust the crawler frame bolts RH, 100%

    Positioning crawler frame over crawler belt

    Check and mark cables, 25%

    Prepare DPT1 and DPT2, 75%

    Install and adjust the crawler frame bolts RH, 100%

  • 8/23/2019 Erection Report Lot178 Week 1[1]

    6/10

    Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

    Wednesday August 8, 2012

    Field assembly day: 6Crew Shift: Day 12 hours

    Work complete:

    Assemble crawler belts second set,

    Positioned truck-crawler frame on crawler link

    Clean and prepare revolving frame, 30%

    Clean and prepare utilitarian room base, 50%

    Clean and prepare lube room base, 50%

  • 8/23/2019 Erection Report Lot178 Week 1[1]

    7/10

    Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

    Thursday August 9, 2012

    Field assembly day: 7Crew Shift: Day 12 hours

    Work complete:

    Install platforms, ladders and handrails on boom, 25%

    Clean and prepare swing rack, 100%

    Clean and prepare boom point sheave, 50%

    Prepare and install DPT1 and DPT2, 50%

  • 8/23/2019 Erection Report Lot178 Week 1[1]

    8/10

    Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

    Friday August 10, 2012

    Field assembly day: 8Crew Shift: Day 12 hours

    Work complete:

    Install and connected crawler belt, 50%

    Install and weld ballast box plates, 10%

    Clean and prepare boom point sheave, 100%

  • 8/23/2019 Erection Report Lot178 Week 1[1]

    9/10

    Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

    Saturday August 11, 2012

    Field assembly day: 9Crew Shift: Day 12 hours

    Work complete:

    Install and connected crawler belt, 100%

    Install and adjust swing rack, 50%

    Install boom point sheave, 100%

    Install and welded ballast box plates, 15%

    Clean components

    Install and connected boom lube system, 30%

  • 8/23/2019 Erection Report Lot178 Week 1[1]

    10/10

    Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

    Sunday August 12, 2012

    Field assembly day: 10Crew Shift: Day 12 hours

    Work complete:

    Install and adjust swing rack on truck frame, 100%

    Install boom platforms, 80%

    Install DPT1 and DPT2, 100

    Install light system on control room roof, 30%

    Install and connected boom lube system, 80%