e&s bmp design - westmoreland conservation...
TRANSCRIPT
Are Compost Socks Enough?
• Compost socks are excellent BMPs when properly used and maintained
• However, they do have limitations
Compost Socks
• The right sized mesh must be used
• The flat dimension must be at least 1.5 times the specified diameter of the sock
Compost Socks
• Cannot be used in areas of concentrated flow
• Best case: Undercut or overtopped
• Worst case: Failure
Haul Roads• Haul roads can become major sources of
sediment pollution if not properly designed, constructed, and maintained
Haul Roads• Runoff should be directed off the roadway as
efficiently as possible• One method: crowning
Haul Roads• A suitable top dressing not only reduces
sediment discharge but reduced wear & tear on equipment
Haul Roads• Where insloping is used, a roadside ditch is
needed
• Protective liners are required for roadside ditches discharging to special protection waters (HQ or EV), where discharging directly to surface waters, or where necessary to prevent the erosion of ditch itself
Haul Roads• Properly spaced cross drains can help by
keeping flow in the ditch to a minimum
• Make use of existing flow paths• Provide suitable outlet protection
Haul Roads• Outlet protection typically takes the form of
riprap aprons
• Can also include transition mats, stilling basins, and drop structures
Haul Roads• Broad-based dips are recommended for active
haul roads
Broad-based Dip
Low Gradient (<5%) Roadways
Haul Roads• Broad-based dips for steeper gradients
Broad-based Dip
High Gradient (5% - 10%) Roadways
Haul Roads• Stream Crossings - 105 Permits!!!
• It is not true that one crossing is allowed without a stabilized crossing!
Residential Lot BMPs• Chapter 10 in the E & S Manual addresses
typical BMPs used during construction on residential lots
• Three basic scenarios shown in the standard details:
Lot Above Roadway Lot Below Roadway Lot Along Ascending or
Descending Roadway
Residential Lot BMPs• BMPs for residential lots are very simple:– Upslope diversion
• Channel• Compost sock with
modified filler
Residential Lot BMPs• BMPs for residential lots are very simple:– Upslope diversion– Downslope sediment barrier
• Silt fence
Residential Lot BMPs• BMPs for residential lots are very simple:– Upslope diversion– Downslope sediment barrier
• Silt fence• Fiber log
Residential Lot BMPs• BMPs for residential lots are very simple:– Upslope diversion– Downslope sediment barrier
• Silt fence• Fiber log• Compost Sock
Residential Lot BMPs• BMPs for residential lots are very simple:– Upslope diversion– Downslope sediment barrier– Stabilized Entrance
Residential Lot BMPs• BMPs for residential lots are very simple:– Upslope diversion– Downslope sediment barrier– Stabilized Entrance– Downspouts attached to roof leaders extended to
curb
Commercial Lot BMPs• Stormwater facilities can often be used as
temporary E&S BMPs
Perforated Metal box attached toconcrete riser
Commercial Lot BMPs• Stormwater facilities can often be used as
temporary E&S BMPs
• Embankment sediment trap with slope pipes & plywood baffles
Design of Compost Sock Traps• Same maximum drainage area, required
storage capacity, and freeboard as for other traps
• Sump area above socks often helpful
• No spillway required
• Minimum trap height = one 12” dia. Sock
• Socks may be stacked
Construction Sequencing
• Keep it simple!
• Must be site specific
• Must be complete – from initial disturbance to final stabilization
• Address all proposed E&S BMPs
• Do not include maintenance
• Stabilize as you go
• Remove temporary BMPs when no longer needed
• Conditions of stabilization
Utilities• Avoid conflicts with E&S BMPs – show them
on the E&S plan maps
• Installing a stormwater manhole in a sediment trap
Utilities• Avoid conflicts with E&S BMPs – show them
on the E&S plan maps
• Avoid crossing surface waters wherever possible – otherwise bypass normal flows
Flumed Stream Crossing Pump Bypass Cofferdam
Utilities• Avoid conflicts with E&S BMPs – show them
on the E&S plan maps
• Avoid crossing surface waters wherever possible – bypass normal flows
• Use stabilized crossings
Culverted Crossing
Temporary Bridge
Utilities• Avoid conflicts with E&S BMPs – show them
on the E&S plan maps
• Avoid crossing surface waters wherever possible – bypass normal flows
• Use stabilized crossings
• Get 105 permits where needed
• Minimize open trenches (50’ max at end of day)
• Follow OSHA requirements
• Keep current with backfilling & stabilization
• Blanket within 50’ of surface water (100’ of HQ or EV water)
Transmission Lines
• Time period for open trench operations at any station should be minimized– 30 days for most locations
– Longer periods can be approved on case-by-case basis if sufficient justification provided
Transmission Lines
• Time period for open trench operations at any station should be minimized– 30 days for most locations
– Longer periods can be approved on case-by-case basis if sufficient justification provided
• Trench plugs used at all stream & wetland crossings as well as on steep slopes
Transmission Lines
• Time period for open trench operations at any station should be minimized– 30 days for most locations
– Longer periods can be approved on case-by-case basis if sufficient justification provided
• Trench plugs used at all stream & wetland crossings as well as on steep slopes
• Open cut stream crossings– Bypass flows for minor streams (10’ wide or less
at normal flow depth)
– Completed within 24 (minor stream) to 48 hours (major stream up to 100’ wide)
Transmission Lines– Facilities for removing sediment from pumped
water should be provided at all crossings
Pumped water filter bag
Portable Sediment Tank
w/Inclined Planes
Transmission Lines– Facilities for removing sediment from pumped
water provided at all crossings
– Pipe should be ready for placement before trenching begins
Transmission Lines
• Horizontal Directional Drilling (HDD) installation– Suitable BMPs in place (sediment barriers) &
operating properly
– Readiness for any inadvertent return
– Suitable method for collecting & treating drilling fluid
Darl Rosenquest|P.E., P.G.
Senior Civil Engineer
DEP California Mining Office
25 Technology Drive
Coal Center, PA 15423