ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS LTC. Antonino MIDOLO Chief of FPE Doctrine & Studies Section [email protected] ITALIAN ENGINEERS COMMAND

Upload: others

Post on 28-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ESMRM

RISK ANALYSIS

ON DEPLOYED

OPERATIONS

LTC. Antonino MIDOLOChief of FPE Doctrine & Studies [email protected]

ITALIAN ENGINEERS COMMAND

Page 2: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

FP ENGINEERING SUPPORT CENTRE

MAIN TASKS

• Support FP Doctrine development• Develop FPE technical manuals• Conduct FP/FPE courses• Advising on FP/FPE matters• Develop research, experimentation and

test on FP/FPE materiel and equipment• Joint Analysis and Lessons learned

process

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

01 FEB 2016

Page 3: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

AGENDA

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

1. BACKGROUND ON FORCE PROTECTION (FP)

2. THE AMMUNITION DEPOTS DESIGN

3. CASE STUDY

4. CONCLUSIONS

Page 4: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

1

BACKGROUND ON FP

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

1. FP connections to ESMRM

2. Importance of ESMRM for FP

3. FP-ESMRM relationship

Page 5: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

MINIMIZE VULNERABILITY FROM THREATS AND

HAZARDS ON OPERATIONS

• Contrast all form of threats• Preserve survivability• Prevent risks & hazards• Minimize uncertainty• Avoid fratricide fire

FORCE PROTECTION (FP)

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

ESMRMInvolvement

Page 6: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

MINIMISE VULNERABILITIES FROM

THREATs & HAZARDS

FP ENGINEERING (FPE)

� Physical Protection� Field Fortification� Fire Protection� Environmental Protection� Military Search

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

ESMRMTechnical Support

Ammo DepotsDesign

Page 7: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

2

THE AMMUNITION

DEPOTS DESIGN

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

1. Reference

2. Criteria

3. Model

4. Process

Page 8: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

MAIN DOCTRINAL & LAW REFERENCES

• AJP-04 “Allied Joint Logistic Doctrine”• AJP 3.14 (A) “Allied Joint Doctrine for Force Protection”• AD 80-25 “ACO Force Protection Directive”• Bi-SC 85-1 “Capability Package Directive”• ATP 3.12.1 “Allied tactical Doctrine for Military Engineering”• ALP 16 “Explosives Safety and Munitions Risk Management (ESMRM) in

NATO Planning, Training, and Execution”• National publication PSE 3.14.1 “Military Base Protection in Operations”• National Law n. 131/2016 (adoption of AASTP 1-5 in NATO operations)

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

FP/FPE Documents ESMRM Documents

Page 9: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

MAIN TECHNICAL REFERENCES• STANAG 2280 “Test procedures and classification of the effects of weapon on

structures” - ATP 3.12.1.8• STANAG 2953 “The identification of ammunitions” - AOP-2• STANAG 4123 “Determination of the classification of military ammunition and

explosives” - AASTP-3• STANAG 4440 “Manual of NATO safety principles for the storage of military

ammunition and explosives” - AASTP-1• STANAG 4442 “Application of risk analysis to the storage and transport of

military ammunition and explosives” - AASTP-4• STANAG 4657 “NATO “Guidelines for the storage, maintenance and transport

of ammunition on deployed missions or operations” - AASTP-5• STANAG 7141 “Joint NATO doctrine for environmental protection during NATO

led military activities”• National SOP FPE (Engineering Techniques and Procedures)• National SOP FE (Field Engineering Techniques and Procedures)

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

Page 10: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

RestrictionsLimitations

Tempo

Standard & Design Criteria

OperationalRequirements

Site Information Requirements

Analysis

DrawingStatement of Works

Orders &Tasks

1 2 3

4

5

8

67

1- FEASIBILITY STUDY

2 - ON SITE RECCE3 - DESIGN PROCESS

BiddingProcess

AmmodepotDesigningProcess

FPE PROJECT MANAGEMENT

Mis

sion

Ana

lysi

sR

ealiz

atio

n

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

Page 11: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

PHASE 1 - FEASIBILITY STUDY

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

PES LAY OUT (ESMRM)• Net Explosive Quantity (NEQ)• Hazard divisions – Compatibility Groups• Storage requirements• Hazardous areas• Field Distances - External Safety Distances• Barricades

PROTECTION MEASURES (FPE)• Physical & structural protections• Surveillance systems• Fire protection• Stand-off• Security procedures

TOOLS:• Technical manuals• AASTP 1-5• FP Model• FPE Standard• Technical Legislation

ESMRM RESTRICTIONS• Storage limitations• Initial Exposed Sites (ES)• Natural & mutual hazards

FPE RESTRICTIONS• Active security organization• Antiterrorism measures• FPE Materiel

Page 12: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

PHASE 2 - ON SITE RECONNAISSANCE

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

VERIFY APPLICABILITY OF THE FEASIBILITY

STUDY

OBJECTIVES OF ANALYSIS• Size of storage area• Terrain• Weather conditions• Viability• Switching stations• Electrical supply lines• General security conditions

RESTRICTIONS• Site selection (free or imposed) • Operational & national caveats• Severe weather conditions • Host Nation regulations• Environment hazards

Page 13: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

PHASE 3 – DESIGNING PROCESS

1 Analysis ofAmmunition

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

• ES characteristics• FP Model and ESMRM

comparison• Residual risk

evaluation• Final FD & ESD• Fire evaluations

4 AMMODEPOTphysical

protection measures (FPE)

6 Induced risks from

environment to PES-ES and vice versa

• Fire protectionequipment &firefighting procedures

• Precautions guidelines• Signs• Support plants• Access control

2 Identification of necessary

PES

3 AMMODEPOTDesigning

FP MODEL• Threat Assessment• Vulnerability

Assessment• Risk Assessment• Risk Management• FPE Designing

5 Analysis ofSafety Distances

(ESMRM)

Page 14: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

3

CASE STUDY

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

“A FPE Officers training with real

implications”

Task : design a munition depot in order to storage thecombat munitions day of supply and integrate itssafety measures into a FPE masterplan

Page 15: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

FPE ASSUMPTIONS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

FSB Site assigned

Host Nation (HN) Barracks

Site assessment:• Part of a HN military barracks• Civilian houses and a main traffic road close

to the external site’s perimeter• Military accommodations and facilities close

to the internal site’s perimeter• Outer access control provided by HN• Perimeter fence only in the northern side

Page 16: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

HYPOTHESIZED FSB ZONING

Main gate

Secondary gate

Page 17: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

STANDARD AND CONSTRAINS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

STANDARD:• STANAG 4657 “NATO “Guidelines for the storage, maintenance and

transport of ammunition on deployed missions or operations” - AASTP-5• National SOP FPE (FP Engineering Techniques and Procedures)

CONSTRAINS:• Site imposed by HN• High temperatures• Possible sand storms• Torrential rains AND…:

• Lessons Learned• Other similar projects realized in

operations

Page 18: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

AMMO DEPOT DESIGNING

2 AMMO DEPOTS EACH WITH 10 CONTAINERS

(1 available for future storages)

AMMO DEPOT ONE

AMMO DEPOT TWO

MAX QUANTITY IN CONTAINER: 180 KG

REFERENCE NEQ:

250(table 2-3 of the AASTP-5)

Page 19: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ES ANALYSIS (OUTSIDE FSB)

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

Ammunition Depot Area

Exposed Sites

MilitaryAccommodation

Building

MilitaryStorages

Civilian Houses

HN HQ

Farmhouses

BarracksTraining Compounds

Fuel Installation

HighTrafficRoad

Distances (meters)50

50

100110

180

200

45

200

220

35

Page 20: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

ES ANALYSIS (INSIDE FSB)

Ammunition Depot Area

Distances (meters)

Page 21: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

AMMO DEPOT PROTECTIONS

Page 22: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

FIELD DISTANCES CRITERIA

REFERENCES:FD1-FD4-FD8

(table 2-2 of theAASTP-5)

Page 23: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

FIELD DISTANCES EVALUATION

REFERENCES FD1-FD4-FD8 (table 2-3 of the

AASTP-5)

REFERENCE NEQ:

250(table 2-3 of the AASTP-5)

Page 24: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

50 M 100 M

Ammunition Depot Area

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

ES ANALYSIS (SAFETY ARCS OUTSIDE FSB)

150 M

NORTHERN AREA

Page 25: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

50 M 100 M

Ammunition Depot Area

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

150 M

SOUTHERN AREA

ES ANALYSIS (SAFETY ARCS OUTSIDE FSB)

Page 26: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

Ammunition Depot Area

50 M 100 M 150 M

ES ANALYSIS (SAFETY ARC INSIDE FSB)

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

INNER AREA

Page 27: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

Forbidden

building/area

Additional

Barriers

X

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

FSB ESMRM RISKS MITIGATIONS (SOLUTION 1)

Page 28: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

New Semi

Hardened

Additional

Barriers

FSB ESMRM RISKS MITIGATION IMPROVEMENT (SOLUTION 2)

Page 29: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

OUTER FSB ESMRM RISKS MITIGATION IMPROVEMENT

1) Interdict using of houses and road insideyellow arc (accommodations in ALPHA &BRAVO areas)

2) Realize a road bypass for civilian localpopulation in area ALPHA

3) Support HN to relocate homeless in new houses

• High costs• Difficult to carry

out within locals• HN acceptance• Command level

residual riskacceptance

Page 30: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

4

CONCLUSIONS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

1. Gaps and implications in the operational

evaluations

2. Improvement and integration within

staff procedures in operations

Page 31: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

AASTP-5

• field distances doesn’t consider assets protection andfatalities/injuries from flying glass/materiel

• risk management:� suggests to evaluate risk mitigations with earth barriers or

natural barricades�doesn’t give indications about it (standard, tools, methods of

calculation, …)

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

1. What are the gaps into ESMRM?

ESO

• needs knowledge, experience and properly training on explosivesto prepare the explosive safety case

• employment not only during operational phase

Page 32: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

• Gammy Risk Management• Different knowledge – different evaluations• Engineer/EOD SMEs constant support to ESO (if

available on site)

1. What consequences?

• What kind of explosive training is needed?• Is ESO to be an Engineer task (i.e. like EOD)?

Page 33: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ESMRMRisk Analysis

FP MODEL

ESMRM Explosive Safety

Site Plan

FP Officer(FP Woking

Group)

ExplosiveSafety Officer

(ExplosiveSafety Board)

Develop and Implement FP Controls and

Measures(FP PLANNING)

2. What implications in the operational evaluations?

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

ESMRM IS NOT A STAND ALONE PROCESS

Page 34: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

FPO

ESO

EPO

Environmental Baseline Studies

ESMRM Explosive Safety

Site Plan

FP Plans

ES

OPERATIONAL ENVIRONMENT

THREATS

PES

NATURAL ENVIRONMENT

HAZARDS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

2. What implications in the operational evaluations?

Page 35: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

FPO

ESO

EPO

Environmental Baseline Studies

ESMRM Explosive Safety

Site Plan

FP Plans

ES

OPERATIONAL ENVIRONMENT

THREATS

PES

NATURAL ENVIRONMENT

HAZARDS

FPWG

FPWG

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre

3. How we could improve and integrate the ESMRM

process within staff procedures in operations?

Page 36: ESMRM RISK ANALYSIS ON DEPLOYED OPERATIONS...• Joint Analysis and Lessons learned process ITALIAN ENGINEERS COMMAND FP Engineering Support Centre 01 FEB 2016. AGENDA ITALIAN ENGINEERS

ITALIAN ENGINEERS COMMANDFP Engineering Support Centre