· estimated total cost of project is with reference to the civil, .mep and allied works required...
TRANSCRIPT
Format -1 C ENGINEER'S CERTIFICATE
(FOR THE PURPOSES OF DESIGNATED ACCOUNT)
FOR THE QUARTER/PERIOD ENDING:
PROJECT NAME :- PHASE CRESSIDA I, APOLLO DB CITY,INDORE
ADDRESS :- CRESSIDA I, APOLLO DB CITY,INDORE,GRAM NIPANIA, INDORE.
PROMOTER NAME:- DIVYA DEV DEVELOPERS PVT LTD
.. ADDRESS :- 205, APOLLO ARCADE,1/2 OLD PALASIA,INDORE,-4S2001
This is to certify that I have undertaken assignment of certifying estimated cost and expenses incurred on actual on site construction for the Real Project mentioned above.
1. Following technical professionals were consulted by me for verification /for certification of the cost:
i. M/s /Shri / Smt JITENDRA MEHTA as Architect;
ii. M/s /Shri / Smt ARJAV UPADHYAY as Structural Consultant
iii. M/s /Shri / Smt CHETNA BAM NOTE as MEP Consultant
iv. M/s /Shri / Smt VIJAY DUBEY as Quantity Surveyor
2. We have estimated the cost of the completion of the civil, MEP and allied works, of the Building(s) of the project. Our estimated cost calculations are based on the drawings/plans made available to us for the project under reference by the Promoter, Developer and Consultants and the Schedule of items and quantity for the entire work as calculated by the Quantity Surveyor appointed by the Promoter, and the fair assumption of the cost of material, labor and other inputs made by developer, and the site inspection carried out by us.
3. We estimate Total Estimated Cost for completion of the project under reference as Rs. 2463.72 (Total of S.No. 1 in Tables A and B) including cost of development of common facilities. The estimated Total Cost of project is with reference to the Civil, .MEP and allied works required to be completed for obtaining occupation certificate/ completion certificate for the building(s) from the concerned Competent Authority under whose jurisdiction the previously mentioned project is
being implemented.
4. The estimated actual cost incurred until quarter ending on 31 DEC 2017 is calculated at Rs. 716.48 (Total of S.No. 2 in Tables A and B). The amount of Estimated Cost Incurred is calculated based on
amount of Total Estimated Cost.
5. The Balance cost of Completion of the Civil, MEP and Allied works of the Building(s) of the project to obtain Occupation Certificate/Completion Certificate from the Competent Authority is estimated at Rs. 1747.24 (Total of S.No. 4 in Tables A and B).
6. I certify that the Cost of the Civil, MEP and allied work for the aforesaid Project as completed on the_31 Dec 2017_ date is as given in Tables A and B below:
TABLE A
Building/Wing/Tower bearing Number--or called PHASE CRESSIDA I-
S.No.
1
2
3
4
5
6
Particulars Amounts
Rs 2403.72Total Estimated cost of the building/wing as on date of Registration
Rs 695.84Cost incurred till Dt.(31 Dec 2017) (Based on the actual cost incurred as
per records.)
28.95 %Value of Work done in Percentage (as Percentage of the estimated cost)
(1 *100/2)
Rs 1707.88Balance Cost to be incurred (Based on Estimated Cost) (1:-2)
RsOCost incurred on Additional/ Extra Items not included in the Estimated
Cost (Annexure A)
28.95%Work done in percentage(as Percentage of Estimated Cost plus
additional/Extra items (1 *100)/(2+5)
(Enclose separate sheets for the cost calculations for each unit/bldg. or tower)
TABLE B
Internal & External Development work and common amenities
S.No. Particulars Amounts
1 Total Estimated cost of the Internal and External Development Work~
Rs 60.00 including common amenities and facilities in the layout as on date a
Registration (based on the original/ Estimated cost)
2 Cost incurred until Dt.31 Dec 2017 (Based on the actual cost incurred as per Rs 15.00
records.)
3 Work done in Percentage (as Percentage of the estimated cost) (1 *100/2) 25%
4 Balance Cost to be Incurred (Based on Estimated Cost) (1-2) Rs 45.00
5 Cost incurred on Additional/ Extra Items not included in the Estimated Cost Rs 0
(Annexure A)
6 Work done in percentage(as Percentage of Estimated Cost plus 25%
additional/Extra items (1 *100)/(2+5)
(Encloseseparatesheetforthecostcalculations)
S;gnatureofEngineer ~~
Name :- JITEI\lDRA MEHTA '
n~ENDRA MEHTA Address:- 185 Saket Nagar 1t'tl1o e b R N CN94/17474B. rc. ego o. Aadhar No.:
Pan no.:- ACVPM0069L
(License No -MP09-2012-0166460)
Note:
1. The scope of work is to complete entire Real Estate Project as per drawings approved from time
to time so as to Obtain Occupation Certificate/Completion Certificate.
2. Quantity survey can be done by office of Engineer or can be done by an independence Quantity
Surveyor, whose certificate of quantity calculated can be relied upon by the Engineer. Please
indicate name of the Quantity Surveyor* and for whom he is working.
3. The estimated cost includes all labour, material, equipment and machinery required to carry out
entire work including common facilities, but does not include marketing/advertising costs,
salaries not directly attributable to the project, and loan/interest repayment to financial institutions.
4. Annexures A and B Attach the List of Extra/ additional items executed if any with Cost (which
were not part of the original Estimate of the total Cost) and justification for the same.
5. Refer Guideline for Designated Account document available in DOWNLOAD section of RERA Website.
'.
--
- --
---
----
~, I'~"" ~ · .~ ~f.' '
, Pi 1~SE CRESSIDA I, APOLLO 'Ufj CITY ESTIMATED COST-l ,.
J j ABL ,Ci. _.. -- . ---~ ._< '\1,.... AmountItem
.. ._~-~f---
,- i
- -- '--SlruClural INR 140,645.010
--I- ..
E· ,; veii-IOn II~'! 1l81l,192 ....-- --f---
B~, ;,tilling INfl '.71,449--1-- ..- ---
I~:U, 92,859 .-I- --
Wale; Proofing
A''''-,ermite
INH 392,153
DI<;mantling of RCC INR 900,000
Rf'ilaring INO 5H,800
pee INR 514,691 ... -
MaKing of Cover Block INfl 162,000 '-- - -'
R( (_ INR 64,287,160 ..
INR 62,582,250Stet'; Rebar
INR 120,000RCc.. Periphery Brickwork and Plaster Labour
RCC Labour INR 8,031,456
Steel Structure (Mezzanine Level) INR 152,000
External Road INR 1,890,000
-- INR 56,417,805
Brick Work
2 Architectural
INR 10,352,448
Chicken Mesh INR 360,000
External Plaster INR 4,949,568
Internal Plaster INR 8,310,316
False Ceiling INR 180,000
Water Proofing INR 4,986,240
Dados INR 89,098 '
Flooring INR 362,137
Doors and Windows INR 13,381,424
Railings INR 1,513,920
Miscellaneous Items
Structural Glazing INR 3,600,000
External Wall Finishing INR 4,679,880
Internal Wall and Ceiling Finishing INR 3,652,775
3 MEP !NRil,9SP48
Electrical Expenses as per BOQ INR 8,185,000
Electrical Equiments and Cables INR 912,150
Internal Plumbing INR 8,273,372
External Plumbing INR 2,929,625
Fire Fighting System INR 1,651,000
Lifts and Escalators ~. '0"'
4 INR 6,962,000 '""
5 Electricity Expenses ,
INR 1,000,000
6 Mpiil Entrance iob~ylnteriors INR 1,950,000
Total Amount INR 228,925,963
Contingency Charges (5%) INR 11,446;298
Total (Table A) INR 240,372,261
PHASE CRl :-,~IDA I, APOLLO DB CITY r STIMATED COST TABLE B
.__ . ... 5 No. Itell) J\lllQUnt-_.
I
.. - -r-1 Drainage & Water SUf.!ply , INR 2,800,000
-i.2 .. Outer Plantation - INR 615,000 - _.
3 M05 Developmem I Hard Landscaping INR 1,100,000
--_ .. 3 External lighting INR 1,200,000
Total Amount INR 5,715,000
Contingency Charges (5%) ---~ INR 285,750
Total (Table B) -INR 6,000,750
Cl-=- T_o_ta_I....;.(T_a_b_le_A_+_T_a_b_le_B...;.}.l-1 1 INR 246,373,011
~ . 1.