estimating tender presentation
TRANSCRIPT
![Page 1: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/1.jpg)
DK CONSTRUCTION SDN.BHD.BUILDING THE FUTURE
![Page 2: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/2.jpg)
AgendaBUILDING THE FUTURE.
01 02 03 04Company Profile &
Project Team
Strengths of the company
tender
Weaknesses of the company
tender
Errors in the tender
![Page 3: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/3.jpg)
Company ProfileBUILDING THE FUTURE.
Headquater10, Jalan Setia Prima G, U13/G, Setia Alam, Seksyen U13,40170 Shah Alam, Selangor.
DK Construction Sdn. Bhd.
Company No. : 215203ACIDB Registration : Grade 4 B04Registration No : 0120160303- WP171579Authorized Capital RM1,000,000
www.dkconstruction.com.my
+6 03 3291 0503+6 03 3291 0706
![Page 4: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/4.jpg)
About UsBUILDING THE FUTURE.
Teamwork
Integrity
Commitment
CORE
VAL
UES
Founder : Tee Dee Kei
![Page 5: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/5.jpg)
Our VisionBUILDING THE FUTURE.
01
0203
Build partnerships in the community.Provide
valuable services to clients. Deliver important
resources.
![Page 6: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/6.jpg)
Why Choose DKBUILDING THE FUTURE.
01We reduce wastage.DK finds ways to minimize waste and maximize use of time, labor, and materials.
02Professional in BIM.DK has become the leading industry exponent of the transformational construction tool and process Building Information Modeling (BIM), with more than $50 billion in BIM project experience.
![Page 7: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/7.jpg)
DK TodayBUILDING THE FUTURE.
DK Construction Sdn. Bhd. is a fully integrated civil engineering and building construction firm based in the Penisular Malaysia state of Selangor. DK has
transformed vast acres of uninhabitable swampland into modern housing and industrial estates, tourist resorts, commercial centres, airports and highways.
![Page 8: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/8.jpg)
DK TodayBUILDING THE FUTURE.
We offer:
01 02 03 04General contracting Construction
managementDesign-build Preconstruction
planning services
![Page 9: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/9.jpg)
DK TodayBUILDING THE FUTURE.
Our people bring their technical knowledge, experience, and resourcefulness to the delivery of our construction services.
Driven by a commitment to continuous improvement, DK embraces Building Information Modeling to improve efficiency and enhance client's value.
![Page 10: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/10.jpg)
Project TeamBUILDING THE FUTURE.
![Page 11: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/11.jpg)
AgendaBUILDING THE FUTURE.
01 02 03 04Company Profile &
Project Team
Strengths of the company
tender
Weaknesses of the company
tender
Errors in the tender
![Page 12: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/12.jpg)
1) Registered Contractor Company
BUILDING THE FUTURE.
01
02
Registered contractor company under CIDB.
Grade 4 with RM1000,000 capacity.
![Page 13: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/13.jpg)
2) ExpertiseBUILDING THE FUTURE.
• We’ve spent decades constructing impressive buildings of every shape, size and purpose, from bridge to modern housing, road to industrial estates, airport to highways.
• Hence, we’ve developed a highly efficient approach to construction: a powerful combination of people, process, and technology.
![Page 14: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/14.jpg)
2) ExpertiseBUILDING THE FUTURE.
People We retain our employees significantly longer than the industry average.
Process Project managers handle estimating, procurement, operations and client relations. For you, as an owner, this means flexibility, consistency across multiple projects and a single point of contact who’s empowered to do whatever is needed to ensure you’re satisfied.
Technology That ensures efficient, cost-effective construction and better quality of work
01
02
03
![Page 15: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/15.jpg)
3) Good ReputationBUILDING THE FUTURE.
TROPICANA KL DEVELOPMENT SDN.
BHD.
SP SETIA BERHAD GROUP
IJM LAND BERHAD
GSD LANDSDN. BHD.
SELANGOR PROPERTIES BHD. WCT CONSTRUCTION
“Good quality of workmanship.”
“Experienced and well-known
company.”
“Great working performance.
Satisfaction met.”
“No delay of work, on-time completion.”
“Excellent management
on site.”
“Good implemention
of BIM in achieving
efficiency.”
![Page 16: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/16.jpg)
4) Good Management SkillBUILDING THE FUTURE.
PROJECT MANAGEMENTBIM provides a visible view of constructability, interconnectivity of building systems and aesthetic elements during preconstruction stage.
LABOURS & MACHINERIES MANAGEMENTEnsure maximise the use of resources
Reason: Reduce waste of resources, time and cost.
![Page 17: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/17.jpg)
5) Experienced on Relevant ProjectBUILDING THE FUTURE.
![Page 18: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/18.jpg)
6) Risk ManagementBUILDING THE FUTURE.
- DK Construction takes a multi-faceted approach to risk management: examining potential risks to ensure clients are satisfied with their project and our partnership.
- Safety and quality are at the top of our list, and we can handle all matters related to insurance coverage, claims and loss control, with competence born of experience. We are prepared for the risks associated with delivering the highest quality building.
- We believe it’s nothing more than you should expect from a professional construction firm.
![Page 19: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/19.jpg)
AgendaBUILDING THE FUTURE.
01 02 03 04Company Profile &
Project Team
Strengths of the company
tender
Weaknesses of the company
tender
Errors in the tender
![Page 20: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/20.jpg)
1) Newly hired unskilled labourBUILDING THE FUTURE.
We value our worker’s learning experience.
We are hiring a gang of new workers and plan to give them hands on experience in this project.
We are charging low prices, but hoping of giving them another learning opportunity in this project
![Page 21: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/21.jpg)
2) Restricted design variationsBUILDING THE FUTURE.
1. We are imposing a very slim profit margin.
2. Therefore, we don't encourage too much variations and changes occur in the design.
3. Otherwise, cost plus situation may happen.
4. Cost plus will increase the overall cost of the project.
![Page 22: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/22.jpg)
AgendaBUILDING THE FUTURE.
01 02 03 04Company Profile &
Project Team
Strengths of the company
tender
Weaknesses of the company
tender
Errors in the tender
![Page 23: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/23.jpg)
Error made by Client in the Tender Document
Error 1
Error 2
Error 1The client does not specify the amount of the Tender Deposit.
Error 2The form of tender bond should be shown in Appendix “D” as stated in the content.
BUILDING THE FUTURE.
![Page 24: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/24.jpg)
Error 3
Error 3The client does not provide the Letter of Tender Invitation which must be included the date of collecting tender document and the date of closing tender.
Error made by Client in the Tender DocumentBUILDING THE FUTURE.
![Page 25: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/25.jpg)
Error 4 Error 5Error 6
Error 4, 5 and 6
The unit should be in M3 for the concrete binding screed according to SMM clause F3.1
Error made by Client in the Tender DocumentBUILDING THE FUTURE.
![Page 26: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/26.jpg)
Error 7The submission date of tender document should be not later than 10am on 7th June 2016.
Error made by Client in the Tender DocumentBUILDING THE FUTURE.
![Page 27: Estimating tender presentation](https://reader034.vdocument.in/reader034/viewer/2022051705/58834baa1a28abbe6b8b6d65/html5/thumbnails/27.jpg)
Error of company tenderBUILDING THE FUTURE.
General Scaffolding including Staging
Wall height below 3.5 meter can reach by ladder.
RM800.00 for scaffolding will be used to replace taxation.
PRELIMINARIES