ethics-vinakeen beers
TRANSCRIPT
PLANT CONSTRUCTION IS NOT PERMITTED:
THE VINAKEN BEER COMPANY, A BREWERY
FACTORY HAS BEEN BUILT WITHOUT A LICENSE IN A
LAND PLOT ZONED FOR AGRICULTURAL
PRODUCTION IN HO CHI MINH CITY’S HOC MON
DISTRICT
DISCHARGING UNTREATED WASTE WATER INTO THE ENVIRONMENT:
ACCORDING TO BUILDING DESIGN, PLANT WITH A CAPACITY OF 15
MILLION LITERS OF BEER PER YEAR. BUT, THE SYSTEM DOES NOT
MEET THE STANDARD NORMS. THEY BUILT UNDERGROUND PIPES TO
DISCHARGE UNTREATED WASTEWATER INTO PUBLIC DRAINS AND THEN
FLOWS DIRECTLY INTO RACH SA CANAL, CAUSING ENVIRONMENTAL
POLLUTION
BUSINESS WRONG SECTOR: THE VINAKEN
COMPANY MADE A CONTRACT WITH TAN CHAU BINH
CO. TO IMPORT 54,670 BARRELS OF BUDWEISER
BEER THAT WERE EXPIRED THEN TREATED THEM BY
THEIR TECHNOLOGY
VINAKEN.CO.LTD
VIOLATIONS
Plant construction is not permitted
Discharging untreated waste water into the
environment
Business wrong sector
CONSEQUENCES
Farmer has no land to grow
Damage to environmental
More damage to environment and state
budget
Plant construction is not permitted
Total costs for damage is 45 billions for the
goverment and cause damage to all the people who live in the plant when Vinaken including the cost
of enforcement organization 90 the
equivalent of 1.8 billion.
Discharging untreated waste
water into the environment
Vinaken built the drains to discharge untreated waste water straight out Rach Sa cannal.The violation has
helped Vinaken save a lot of money but also damage
environment and cause a lot of consequences to the people living around the
Rach Sa canals .
Business wrong sector
Vinaken receive 54,670 barrels of Budweiser of Tan Chau Binh
company and the factory directly dumped 1,950 barrels
of beer. This has caused a serious impact on the Rach Sa
canal particular and environmental issues in general. The receipt of
Budweiser beer barrel without a processing license is the
biggest mistakes in the wrong business sector, this means that continue to pollute the
environment.
Solutions:
Stop the activity of Vinaken company to
check out and list the problem to solve
Following the government’ s lead to: register
license for the construction of the plant,
solve untreated waste water by upgrading
technology, stop the business wrong sector