Ethylene Production From Tennessee Fracked Natural Gas
University of Tennessee at ChattanoogaENGR 5910/ENCH 4300
4/26/2012
Brandon Dodd Valentine Mbamalu
![Page 2: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/2.jpg)
Outline
• Introduction• Design Basis• Cracking Reaction• Process Flow Diagram• Equipment Design• Project Economics• Conclusion
![Page 3: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/3.jpg)
Introduction
www.timesonline.com
![Page 4: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/4.jpg)
Design Basis
• Analyze 500,000 metric tons Ethane feedstock per year
• Feedstock will be considered as 100% Ethane
• Negligible reaction byproducts not to be considered for this level of design
![Page 5: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/5.jpg)
Ethane Cracking Reaction
Byproducts
Methane Propane
Hydrogen Gas
![Page 6: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/6.jpg)
Generalized Process Flow Diagram
![Page 7: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/7.jpg)
Steam Cracker• 170 MW heat duty
• Modeled as 2 100MW separate pyrolysis
furnaces
• Each furnace 100 MW capacity
• Operates at 80% capacity.
![Page 8: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/8.jpg)
Transfer Line Exchanger
• Shell and Tube Model
• 73 MW Heat Removed from Product Stream
• 820 m2 Total Exchange Area
• 2 Units in Series
![Page 9: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/9.jpg)
Distillation Columns
• 3 Total Columns• 8 stage de-methanizer– 10m high– 3m diameter
• 20 stage de-ethylenizer– 15m high– 3m diameter
• 40 stage de-ethanizer– 27m high– 3m diameter
![Page 10: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/10.jpg)
Other Equipment Estimated
• Quench Tower
• Compressors
• Refrigeration
• Pumps
• Fans
![Page 11: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/11.jpg)
![Page 12: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/12.jpg)
![Page 13: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/13.jpg)
Unit Cost SummaryUnit Description # Units Cost (Millions)C-101 Compressor 1 2C-102 Compressor 1 12.7K-101 Drier 1 1.2E-101 Transfer Line Heat Exchanger 1 0.5E-102 Refrigeration Train 1 0.4E-103 Regrigeration Train 1 0.6F-101 Fans 20 0.3H-101 Pyrolysis Furnace/Cracker 1 21.5H-102 Pyrolysis Furnace/Cracker 1 12.6P-101 Pump 10 2.9R-101 Acetylene Converter 1 0.2T-101 De-methanizer - tower 1 3.7T-102 De-ethylenizer - tower 1 5.4T-103 De-ethanizer - tower 1 9.3V-101 Product Holding Tank 1 2.7Z-101 Quench Tower 1 2
Unit Cost Estimation Summary
![Page 14: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/14.jpg)
Costs – In Millions
• Capital Costs - $121– Includes land cost
• Total Annual Operating Costs - $617– Utility Cost - $142– Raw Material Cost - $475– Labor Cost – estimated $1
![Page 15: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/15.jpg)
![Page 16: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/16.jpg)
Revenue – In Millions
Total Yearly Revenue - $960
•Ethylene – 560,000 metric tons– $955
•Methane – 3000 metric tons– $0.7
•Propane – 3000 metric tons– $0.7
![Page 17: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/17.jpg)
Revenue Vs. Cost
![Page 18: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/18.jpg)
Payback Period
![Page 19: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/19.jpg)
ENVIRONMENTAL IMPACT
• Air pollution• Primary – Nitrogen dioxide, Particulate Matters, Volatile Organic Component
. Secondary – Ozone
. Incinerators
![Page 20: Ethylene Production From Tennessee Fracked Natural Gas University of Tennessee at Chattanooga ENGR 5910/ENCH 4300 4/26/2012 Brandon Dodd Valentine Mbamalu](https://reader036.vdocument.in/reader036/viewer/2022062517/56649e795503460f94b790f8/html5/thumbnails/20.jpg)
Conclusions
• Costing based on key component• Project is profitable• Economic activities will receive boost• Jobs and revenue to state and local gov.