eu procurement a presentation by graeme palmer, associate, burness llp 24 march 2009 click here to...

32
EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP ebsite

Upload: james-mcgrath

Post on 26-Mar-2015

218 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

EU Procurement

A presentation by Graeme Palmer, Associate, Burness LLP24 March 2009

Click here to visit Burness LLP website

Page 2: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

EU Procurement

• What is EU Procurement?

• Why and when is it relevant in the context of construction contracts?

• What are the possible consequences when it goes wrong?

Page 3: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

What is EU Procurement?

• Rationale for regulating the procurement practices of public bodies and utilities across EU member states

• EU Procurement rules comprise:

- EU Directives

- Implementing regulations in member states

- Case law of the European Court of Justice

- Principles derived from the EU Treaty

Page 4: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

What is EU Procurement?

• Principles of the EU Treaty

- Non-discrimination

- Equal treatment

- Transparency

- Proportionality

Page 5: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

What is EU Procurement?

• Directive and Regulations set out detailed rules and procedures to be followed by public bodies and utilities in procuring works, goods and services

• The Directive has been ‘clarified’ in a number of areas by decisions of the European Court of Justice

• Even where the Directive or Regulations do not apply in full to a proposed contract, the procurement of that contract must comply with the principles derived from the EU Treaty

Page 6: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

When is EU Procurement relevant?

• When a ‘contracting authority’ seeks to procure works, goods or services

• Joint ventures involving public sector bodies

• When a utility seeks to procure works, goods or services which are to be used in relation to the utility activities

• When a private or third sector body receives public funding a condition of which obliges that body to comply with EU Procurement rules

Page 7: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

When is EU Procurement relevant?

• Above threshold and below threshold procurement

• Threshold for works - £3,497,313

• Threshold for services - £90,319 (central government) and £139,893 (for other public bodies)

• Procedures under EU procurement rules

- open - competitive dialogue

- restricted - negotiated

• Specification of selection and award criteria and weighting

Page 8: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

When is EU Procurement relevant?

• When a private sector body is bidding for a contract from a public sector organisation or utility

• When a private sector body has won a works concession contract and has to advertise sub-contracts in OJEU

• Contracts with a value below the threshold or which are not subject to the full requirements of the directives

- contracts which may have a cross-border interest must be subject to a degree of advertising which enables them to be opened up to competition (C-324/98 Telaustria)

Page 9: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

When is EU Procurement relevant?

• Material amendments to an existing contract during the term of the contract can constitute the award of a new contract (Case C-454/06 pressetext)

• A material amendment is one which:- Introduces conditions which, if they had been part of the

initial award procedure, would have allowed for the admission of bidders other than those initially admitted or allowed for the acceptance of another bid

- Extends the scope of the contract as originally tendered by encompassing services not originally covered

- Changes the economic balance of the contract in favour of the contractor in a manner not provided for in the terms of the initial contract

Page 10: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

When is EU Procurement relevant?

• When a contracting authority enters into a Development Agreement?

• Case C-220/05 - Jean Auroux and Others v Commune de Roanne

• The public procurement rules apply where one contracting authority entrusts another contracting authority with executing works, regardless of whether or not the first contracting authority is, or will become, the owner of all or part of the works, and irrespective of the fact that sub-contracts will be tendered

Page 11: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Why is EU Procurement relevant?

• Regulation 47(1) of The Public Contracts (Scotland) Regulations 2006

- “The obligation on a contracting authority to comply with the provisions of these Regulations…. and with any enforceable Community obligation in respect of a public contract…. is a duty owed to an economic operator.”

Page 12: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Why is EU Procurement relevant?

• Regulation 47(6)

- “A breach of duty owed in accordance with paragraph (1)… shall be actionable by any economic operator which, in consequence, suffers, or risks suffering, loss or damage and those proceedings shall be brought in the Sheriff Court, the Court of Session, or, in England and Wales and Northern Ireland, the High Court.”

Page 13: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Why is EU Procurement relevant?

• Remedies Directive (Directive 2007/66/EC)

- Final date for implementation in national legislation – 19 December 2009

- To address the issue of the direct award of contracts where these contracts have not been advertised as required in terms of the procurement directive.

Page 14: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Why is EU Procurement relevant?

• Remedies Directive (cont’d)

• Ineffectiveness: national courts to make a contract “ineffective” where

- a contracting authority has awarded a contract directly to a provider which ought to have been advertised in OJEU

- the contracting authority has:

• not complied with the requirements of the standstill period, which has deprived the tenderer of the opportunity to pursue pre-contractual remedies; and,

• has acted in breach of the procurement directive where that breach has affected the chance of the tenderer applying for a review to obtain the contract.

Page 15: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Why is EU Procurement relevant?

• Remedies Directive (cont’d)

• An organisation which wishes to avail itself of the new remedies must make an application within 30 days of the publication of a contract award notice or, if no such contract award notice is published in OJEU, within six months of the date of the contract being concluded.

 

Page 16: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Possible consequences when things go wrong

• Where the contracting authority fails to adequately specify

minimum requirements and award criteria in the contract

notice and contract documents.

• Excluded bidder was awarded £109,555.20 for loss of profits over three years – due to lack of clarity in contract notice and specifications, changes in personnel and lack of relevant experience of personnel assessing the bids

Aquatron Marine v Strathclyde Fire Board ([2007] ScotCS CSOH_185)

Page 17: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Possible consequences when things go wrong

• Where the contracting authority uses ‘qualification criteria’

as ‘award criteria’, where there is undue discretion given

to panel members in scoring bids and where there is

inadequate de-briefing.

• The case (which was an action for interim interdict) also raised the issue of equality of treatment when bidding against an incumbent when issues of TUPE would apply.

Lightways (Contractors) Ltd v North Ayrshire Council [2008] CSOH 91

Page 18: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Possible consequences when things go wrong

• McLaughlin & Harvey Limited v Department of Finance & Personnel, judgment on remedies, 30 October 2008 ([2008] NIQB 122)

• High Court of Justice in Northern Ireland set aside a framework agreement which had been entered into between the Department and five construction companies

• The court ruled that the Department had breached the procurement rules by failing to disclose in advance certain elements of the award criteria applied in assessing tenders

Page 19: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

EU Procurement

A presentation by Graeme Palmer, Associate, Burness [email protected] (Direct Dial: 0141 273 6738)24 March 2009

Page 20: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Procurement and Community Benefits

A presentation by Colin Clelland, Director, Burness LLP24 March 2009

Page 21: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Introductory Comments

• Challenges of EU Procurement Rules

• Focus on practical solutions

Page 22: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

EU Procurement Law

• Relevant Cases

- EU Commission v Ireland (1988)

- Gebroeders Beentjes v The State (Netherlands) (C3187)

- Nord-Pas-de-Calais Region (C22J98) – Commission v The French Republic

- Insalud (C-23403 – Contse SA v Insalud (2005))

- EU Commission v Italy [1991]

Page 23: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

EU Procurement Law (Contd)

• All very confusing but broad themes are

- the need for procedural fairness

- application of equal treatment principle

- prohibition of conditions which have a discriminatory effect

Page 24: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Use of Contract Conditions

• Not to be discriminatory

• Effectiveness of Contract Conditions

- Is there a loss to recover?

- Do you really want to terminate?

• Alternative strategies

Page 25: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

The role of community benefits in EU Procurement

• The EU Social Communication

• The Consolidated Directive

• Social Issues in Purchasing – OGC

• Scottish Government Consultation Paper – Community Benefits in Public Procurement

Page 26: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Social Communication

“… any contracting authority is free, when defining the goods or services it intends to buy, to choose goods, services or works which correspond to its concerns as regards social policy… provided that such choice does not result in restricted access to the contract…to the detriment of tenderers from other Member States”

Page 27: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

OGC’s Social Note

“A core requirement can be defined as an essential part of the contract and this should be reflected in the specifications and the conditions of contract… It is possible for social issues to be a core requirement provided that it is central to the subject of a procurement.”

Page 28: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Scottish Government Consultation Paper

“The inclusion of Targeted Recruitment and Training (TR + T) or other community benefit requirements in the award process introduces the need for a new skill evaluating bidders’ tenders in response to these requirements.”

Page 29: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

• Core requirement – part of the subject of the contract

• Core requirement cannot be discriminatory

• Secondary requirements

- Relate to social issues not part of the core requirements but which the procurer wants to see delivered

• Ability to meet core requirements but not secondary requirements can influence the award of the contract

Core and Secondary Requirements

Page 30: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

• Payment for success

- Incentivisation

- Abatement from payment otherwise due

- Termination as a last resort

Using Community Benefits as Core Requirement

Page 31: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Framework Agreements

• Framework agreements with performance measured against key performance indicators

• How to use KPIs

- the carrot or the stick

• Use of Work Allocation System to reward success

Page 32: EU Procurement A presentation by Graeme Palmer, Associate, Burness LLP 24 March 2009 Click here to visit Burness LLP website

Procurement and Community Benefits

A presentation by Colin Clelland, Director, Burness [email protected] (Direct Dial: 0141 273 6738)24 March 2009