eucard-wp7-hfm collaboration meeting 15/11/2011
DESCRIPTION
EuCARD-WP7-HFM Collaboration Meeting 15/11/2011. Task 3 : High Field Magnet. - PowerPoint PPT PresentationTRANSCRIPT
EuCARD-WP7-HFM Collaboration Meeting
15/11/2011
Task 3 : High Field Magnet
Thomas Dalla Foglia, Melanie Devaux, Maria Durante, Philippe Fazilleau, Jean-Jacques Goc, Pierre Manil, Attilio Milanese, Jean-Francois Millot, Juan Carlos Perez, Alain Przybylski, Jean-Michel Rifflet, Gijs de Rijk,
Francoise Rondeaux
Outline
•Task 3 status report–Recall of the objectives of the Task–Recent activities
•Specification•Conductor•Design•Tests•Winding tooling•Dipole – Insert Interaction & Interface
–Work for the next 6 months–Global planning–Conclusions
15/11/2011 2CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
15/11/2011 3
Recall of the objectives of the Task•Design, build and test a dipole model to upgrade the
superconducting cable test facility FRESCA at CERN –1.5 m long,–100 mm aperture –13 T magnetic field (with the possibility to go to 15 T for Fresca2)–Nb3Sn high current Rutherford cables.
•Dipole model as a test bed for large high field accelerator magnets.
What WhoMagnet design CEA and CERN
Conductor characterization CERN
Thermal design and thermal component tests CEA, CERN and PWR
Coils fabrication CEA
Magnet assembly CERN
Cryogenic tests CERN
CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
Specification
• The specification was slightly modified (minor adjustments and addition of missing data) and approved recently (10/10/2011)
• It is accessible athttps://espace.cern.ch/EuCARD/WP7/SWGroup/Shared Documents/FRESCA2_magnet_specification-v3.1.pdf
415/11/2011 CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
Conductor• Conductor design working group acts mainly by mail exchanges
and telephone calls (not formal WG meeting) but it works• Part of the work is done in the framework of the French Special
Contribution to LHC• 10 km CERN order to Brucker
– 1st billet : delivered in march 2011– 2nd billet : drawn, delivered at CERN ?– 3rd billet : drawing being done
• 10 km CERN order to OST– Breakage delays delivery 12/2011
• 15 km CEA order to Brucker– Kick off : 04/08/2011– Delivery: 02/2012
• 15 km CEA order to OST + 10 km option– Kick off : 18/08/2011– Delivery: 04/2012
• 20 km CEA order + options (+10,+15 km)– Call for tender under preparation
515/11/2011
Qualification lengths
Pilot lengths
Production lengths
CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
6
Design : Magnet• Preliminary Magnet design Working Group closed after the
ESAC dipole review (14 meetings)• Magnet Design Working Group created in January. Already 14
meetings have taken place• The magnet design is considered as fixed :
15/11/2011
Some recent changes done, e.g. insulation thickness between coil 2 and 3 : 0.5 1.5 mm
CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
7
Design : Cold mass
15/11/2011
Mechanical structure is fixed, however some points are still pending (see next pages):
CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
8
Design : Thermal studiesThermal studies (WP 7.2)• Study at 4.2 K OK
– Modeling of cool-down process – 2 D transient model» From 300 k to 20 K : indirect
col-down through cooling tubes» From 20 K to 4.2 K : direct
filling with helium
• Modeling of thermal process in the magnet during ramping process – 2 D steady state model
• New study : Two fluids model at 1.8 K
15/11/2011 CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
9
Design : Protection– Protection: 2 or 3 quench heaters per
quadrant ?• At tdet = 100 ms (50 ms for
detection and 50 ms for heaters activation),
– 2 heaters : T max = 244 K– 3 heaters : T max = 224 k
• 3 heaters reduce the thermal gradient
15/11/2011 CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
2 heaters
3 heaters
P. Fazilleau: report within a few days
2 heaters
2 heaters3 heaters
3 heaters
10
• Simpler tooling• Is the winding easier ? Yes• Is the conductor stable and in
good position ? Yes
Chosen configuration
Tests : Upside down winding
15/11/2011
But
Dishing
CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
11
Tests : Dishing measurement- Measure dishing effect in order
to take it into account for the tooling design
- Choose the winding parameters minimizing dishing effect
• It exists on cable before winding• It is enhanced during coil
winding
Could it be corrected by adjusting the cabling parameters ? Studies ongoing at CERN
15/11/2011 CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
12
Tests : Jump layer test- Check jump layer design- Choose between single or
double bending
• Test done with annealed copper, non annealed copper, PIT Nb3Sn cable with 120-mm and 140-mm twist pitch Not annealed Cu and the two PIT cables exhibit a similar behaviour
• Dishing is the same in the two winding directions
The double bending is chosenSome minor improvements
(gaps in the grooves, plate fixation, …) on the real tooling
15/11/2011
single bending double bending
CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
13
Tests : Cable behavior during heat treatment1) PIT cable without "end mandrel"• The dishing is significantly
increased after heat treatment• No significant change in overall
dimensions
2) PIT cable with "end mandrel"• The cable is unstable in straight
parts• The end mandrel has moved
(~0.6 mm) and 1.4 mm gap between cable and mandrel has been measured
• Dishing in the end part has disappeared
15/11/2011 CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
14
Tests : Cable behavior during heat treatment
3) Cu cable with "end mandrel“ (short thermal cycle)• The dishing is increased in the end part and
has disappeared in the straight sections• No move of the end mandrel• Some Cu traces on shims
Following tests:• New support allowing 1-10 complete turns• Additional cycles with titanium, stainless and
magnetic steel
15/11/2011 CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
15
Tests : Mechanical structure
An assembly test of the structure with a dummy magnet is in preparation
• Parts fabrication will be launched soon this year, after small drawing updates
15/11/2011 CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
Structure mock-up
16
Winding Tooling
15/11/2011
• Drawing appoval : 13/10• Call for tender end of
November• Fabrication end of January
Winding of a Cu double pancake in March 2012
CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
Dipole – Insert Interaction & Interface• Mechanics:
– Inner free dipole diameter = 100 mm– The insert is mechanically independent of the
dipole (gap)
• Protection:– Coupling of magnets and effects on protection
should start soon
15/11/2011 17CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
Activities for the next 6 months
1815/11/2011
• Splices and connection configuration needed for end 11/2011
• Dipole protection design 15/11/2011
• Reaction and impregnation tooling design end 12/2011
• Coil reaction studies end 02/2012
• Coil 3-4 Winding tooling procurement mid 01/2012
• Copper coil 3-4 winding end 02/2012
• Coil 3-4 Reaction tooling procurement mid 03/2012
• Coil 3-4 Impregnation tooling procurement end 03/2012
• Mechanical structure assembly procurement end 03/2012
• Detailed coil fabrication procedures end 03/2012
• Coil components procurement & characterization 31/03/2012
CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
15/11/2011 19
Global Planning
CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet
EuCARD 7.3Specifications, magnet preliminary design Fresca 2 Nb3Sn Dipole designCoils component and tooling detailed studiesCoil component and tooling procurementAssembly structure procurement and testConducteur procurement QUALIFICATION PILOT PRODUCTION
Cabling and characterizationCu dummy coil manufacturingCoil manufacturingCoil testsDipole assembly M1
Dipole tests M1
Design studies, CAO (CEA and CERN)
CEA and CERN realisation
Procurements
at CERN
EuCARD Milestone or Deliverable
CEF Milestone or Deliverable
39 42 4524 27 30 33 36 48
2009 2010 2011 2012 2013
T2
M0 3 6
T2 T3 T4 T1 T2T1 T2 T3 T4 T1 T4
9 12 15 18 21
T3 T4 T1 T2 T3T3 T4 T1
ble
15/11/2011 20
Conclusions•Fresca2 magnet design (2D and 3D) is now well advanced.
Some point still to be fixed soon•Winding tooling is defined and will be tested beginning of
2012•Validation tests have started. More tests have to be done to
understand the behaviour of the cable during winding and during the heat treatment. This is necessary to fix the winding and curing process.
•Tests made with PIT cable must be repeated wit RRP cable•A structure assembly test is planned early 2012
•A lot of work has been done but …
a lot of work is still to be done
CEA/DSM/Irfu/SACM – J.M. Rifflet - EuCARD HFM - Task 3 : High Field Magnet