european bank for reconstruction and development (ebrd)in order to support the borrower with the...
TRANSCRIPT
82530 TOR published
UB Solid Waste Modernisation Page | 1 of 14
TERMS OF REFERENCE
Mongolia: Implementation of Livelihood Restoration Plan for UB Solid Waste Modernisation
CONTENTS
1 | Background 2
2 | Objectives of the Assignment 2
3 | Scope of Work 7
3.1 | Task 1: Desktop Review and Implementation Planning 7
3.2 | Task 2: LRP Implementation 8
3.3 | Task 3: Monitoring 9
4 | Implementation Arrangements 10
5 | Deliverables 10
82530 TOR published
UB Solid Waste Modernisation Page | 2 of 14
1 | BACKGROUND
The European Bank for Reconstruction and Development (the “EBRD” or the “Bank”) approved
funding to the Government of Mongolia to finance priority solid waste investments in the
Municipality of Ulaanbaatar (the “Borrower”), including the expansion of landfill capacity and
building a Construction and Demolition Waste (“CDW”) plant. The EBRD has signed a loan
agreement with the Municipality of Ulaanbaatar and a Project Support Agreement with the
Ministry of Finance in May 2018.
The Project has been categorised B in accordance with the EBRD Environmental and Social Policy
2014. The Project will provide significant environmental and social benefits to the Municipality
of Ulaanbaatar and surrounding communities through the provision of a landfill designed to EU
standards, and the construction of a new Construction and Demolition Waste (CDW) plant.
During the environmental and social due diligence (ESDD) for the Project, it was determined that
a number of people were collecting waste at the waste dump for livelihood generation. When the
Project is implemented, access to the dump by waste pickers will be restricted, affecting the source
of their livelihoods and requiring waste pickers to move to a new location or find other sources of
livelihoods. In accordance with EBRD’s Environmental and Social Policy of 2008, in cases of
economic and physical displacement generated by the Project, appropriate standard of living and
livelihood restoration measures have to be developed and implemented.
During 2017 and 2019, a consultant developed first a Livelihood Restoration Framework (LRF)
and then a full Livelihood Restoration Plan (LRP), as per the agreed Environmental and Social
Action Plan (ESAP), in advance of Project construction, which is scheduled to start in 2020. The
LRP provides (i) a socio-economic baseline, (ii) the applicable principles of livelihood restoration
as per EBRD’s Performance Requirement 5 (PR5) on Land Acquisition, Involuntary Resettlement
and Economic Displacement, (iii) eligibility criteria and entitlements to compensation measures,
and (iv) a budget, timeline and other implementation arrangements (the “LRP” or the “Plan”). The
Plan is included in Annex 2.
In order to support the Borrower with the timely and expertly implementation of the LRP, the
Bank wishes to engage an experienced consultant (the “Consultant”) to carry out the provisions
laid out in the LRP in line with the EBRD’s 2014 Environment and Social Policy (“ESP”)2,
specifically PR5 and PR10. The objective of this assignment is to ensure that those affected by the
Project’s implementation are well-informed and involved in the LRP implementation and that no
one is left worse-off than before the Project was put into place.
1.1| PROJECT DESCRIPTION
The UB Waste Modernization Project (46581) has been designed to provide finance for the
Government of Mongolia to finance priority solid waste investments in the Municipality of
Ulaanbaatar. These improvements include both the expansion of landfill capacity and the creation
of a Construction and Demolition Waste (CDW) plant. The planned location for this project is
2 Available at http://www.ebrd.com/downloads/research/policies/esp-final.pdf
82530 TOR published
UB Solid Waste Modernisation Page | 3 of 14
adjacent to the Moringiin Davaa Dump Site (MDDS), located approximately 18km southwest of
Ulaanbaatar city.
Three landfills serve Ulaanbaatar: Narangiin Enger (NEDS), Tsagaan Davaa (TDDS) and
Moringiin Davaa, located in the northwest, northeast and southwest of Ulaanbaatar respectively
(Figure 1). MDDS is the smallest of three landfills, receiving approximately 400 tonnes of waste
daily in 2015, compared to 1,700 tonnes at Narangiin Enger, and 1,200 tonnes at Tsagaan Davaa.
Figure 1 Landfill Sites in Ulaanbaatar
In addition to the population increase, the level of solid waste being generating is also increasing
due to an increased volume of construction waste as older buildings in the city centre are replaced
with modern constructions. The combination of these factors is shortening the lifespan of the three
landfill facilities.
The three landfills are managed by the Landscaping and Cleaning Service Department (LCSD) of
the City of Ulaanbaatar. Waste pickers work on all three landfill sites. The total number of waste
pickers across the three sites is estimated by LCSD in 2019 to be around 370 people (150 each at
NEDS and TDDS and 70 at MDDS).
The MDDS is located in Khoroo 12 of the Khan-Uul District of Ulaanbaatar, and the nearest Ger
area of Khan-Uul Khoroo 12 is approximately 1.2 km north and 1.4km west, with the nearest
household 700m to the northwest of the site (
Figure 2 and
82530 TOR published
UB Solid Waste Modernisation Page | 4 of 14
Figure 3).
Figure 2 Location of the Project
Figure 3 Nearest Household to the Project Site
82530 TOR published
UB Solid Waste Modernisation Page | 5 of 14
The MDDS was established in 1970, and formalised into a municipal waste facility in 2009, with
an improvement programme in 2011. The Waste Modernization project will entail the
development of a new landfill area and the establishment of a CDW Recycling plant, as seen in
Figure 4.
Figure 4 Conceptual Design of the Project
*Purple line shows the allocated land for the project.
1.2| DISPLACEMENT IMPACTS
The development of the two project components (CDW recycling plant, and the new landfill) are
expected to primarily generate economic displacement impacts for waste pickers at MDDS, TDDS
and NEDS, with potential physical displacement impacts for a small number of MDDS waste
pickers. Waste buyers from MDDS are also expected to experience some level of economic
displacement. The types of potential displacement and eligibility conditions are summarised in
Table 1-1.
Table 1-1 Potential Categories of Impact Displacement
Category Type of displacement /
impact of loss
Impact source and category
A Physical displacement –
permanent loss of informal
shelter at MDDS
Prohibition of access to MDDS will
make it necessary for any waste
pickers resident on the dump site at
the time of the census to find an
alternate residential location.
82530 TOR published
UB Solid Waste Modernisation Page | 6 of 14
B Physical displacement –
permanent loss of
residential ger or house
Land acquisition required to
develop the footprint of the new
landfill cell.
C Economic Displacement –
loss of waste picker access
to MDDS leading to loss
of income
Prohibition of access to MDDS will
require all waste pickers to find an
alternative livelihood activity.
D Economic displacement –
loss of construction and
demolition waste from
NEDS and TDDS
reducing income levels for
waste pickers at those sites
Redirection of all CDW to the new
CDW recycling plant at MDDS will
reduce the potential income of waste
pickers working at NEDS and
TDDS as they will no longer be able
to collect and sell scrap metal.
E Economic displacement –
loss of business
opportunity to purchase
waste from waste pickers
at MDDS and potential
default of waste pickers on
loans taken from waste
buyers
The cessation of waste picking
activities at MDDS will reduce and /
or result in the cessation of business
activities by waste buyers
purchasing waste from MDDS. In
addition, waste buyers may
experience significant loan default
from waste pickers.
These potential categories of impact were investigated during the course of fieldwork conducted
on site in August 2017 and again in August 2019. Findings from the fieldwork informed the
definition of anticipated impacts provided in Error! Reference source not found.. The number
of affected individuals / households is clearly fluid and will need to be validated through additional
and repeat baseline data collection exercises immediately prior to the implementation of the
project.
Detailed information is available in the LRP in Annex 2.
2 | OBJECTIVES OF THE ASSIGNMENT
The objective of the Assignment is therefore to:
Implement the LRP in a timely and effective manner broadly in line with the
implementation timeline presented in the LRP;
Work with LCSD to start immediate daily registration of waste pickers at MDDS, update
baseline data, and start period of eligibility;
Complement LCSD census (daily registration) with additional baseline surveys, as
necessary, to generate a final list of eligible waste pickers as defined in the LRP;
Engage and consult with informal waste pickers on the proposed mitigation and
compensation measures;
82530 TOR published
UB Solid Waste Modernisation Page | 7 of 14
Engage and consult with relevant NGOs/CSOs working with informal waste pickers and
on other social development and welfare issues in Ulaanbaatar (e.g. women’s support);
Develop a detailed implementation plan and updated timeline following baseline survey
and engagement activities;
Work closely with the waste pickers of MDDS in an intensive format for a period of no
less than six months (3 months prior to cessation of waste picker access to MDDS and 3
months afterwards) to ensure all the implementation activities described in the LRP are
carried out.
Coordinate the implementation process with all the project proponent’s relevant staff, in
particular the City’s Project Implementation Unit (PIU), the Waste Management
Department and the Landscaping and Cleaning Service Department (LCSD);
Work with Social/Welfare department and other relevant social/medical professionals to
facilitate access to social benefits and undertake training, psychological, medical support,
etc. to waste pickers;
Adapt mitigation and compensation measures (including additional measures for
particularly vulnerable individuals) in response to any changes on the ground and
consultation with affected and interested stakeholders;
Ensure delivery of communal facilities at NEDS and TDDS as per the LRP;
Monitor the outcomes of the LRP implementation.
3 | SCOPE OF WORK
The overall scope of work will cover but not be limited to the following tasks.
3.1 | TASK 1: IMPLEMENTATION PLANNING
The Consultant will:
Review the LRP and any other relevant materials related to the Project, including the
Project’s Environmental and Social Impact Assessment when it becomes available
(ESIA), as well as Project design and construction timeline;
Consult with the authors of the LRP (Shared Resources) to gain a better understanding of
the setting and past engagement and clarify any outstanding issues;
Check with the PIU for any updates in the Project implementation timeline and designs to
determine the LRP implementation timeline; the timeline will be built around the point in
time when waste pickers will be impacted, i.e. either (a) cessation of access to MDDS by
waste pickers, or (b) cessation of delivery of any new wastes to MDDS, whichever
occurs sooner;
82530 TOR published
UB Solid Waste Modernisation Page | 8 of 14
Develop a detailed work plan for the LRP implementation activities, including engagement
schedule;
Develop a plan for ongoing monitoring to be carried out during and following LRP
implementation;
Prepare an initial list of implementation partners to include the Client, local authorities,
relevant government agencies (welfare officer, pensions, etc.), and civil society
organisations (CSOs), where appropriate, so as to coordinate the LRP implementation
activities.
3.2 | TASK 2: LRP IMPLEMENTATION
The Consultant will carry out multiple site visits to Ulaanbaatar and the Moringiin Davaa Dump
Site and conduct meetings with implementation partners, specifically to:
Work with LCSD to start immediate daily registration of waste pickers at MDDS, update
baseline data, and start period of eligibility;
Complement LCSD census (daily registration) with additional baseline surveys (using the
questionnaire from work conducted to inform the LRP), as necessary, to generate a final
list of eligible waste pickers as defined in the LRP;
Finalise the list of and coordination arrangements with the different implementation
partners;
Engage and consult with informal waste pickers on the proposed mitigation and
compensation measures;
Engage with service delivery consultants and organisations responsible for delivery of
aspects of the LRP entitlement to ensure a consistent understanding of the commitments
made in the LRP and the objectives of the specific measures;
Develop a detailed implementation plan and updated timeline following baseline survey
and engagement activities;
Create individual files for each affected waste picker household and document their
circumstances, eligibility, potential vulnerability factors and tailored measures, etc.
Work closely with the waste pickers of MDDS in an intensive format for a period of no
less than six months (3 months prior to cessation of waste picker access to MDDS and 3
months afterwards) to ensure all the implementation activities described in the LRP are
carried out. This includes:
o Organisation of “event days” to inform waste pickers, provide medical services,
meetings with social welfare officers, and develop individualised livelihood
plans;
82530 TOR published
UB Solid Waste Modernisation Page | 9 of 14
o Provide psychologist support;
o Provide support for registration for welfare benefits;
o Registration for livelihood restoration support options;
o Delivery system for payments of transition allowances;
o Provision of training and support for alternative employment.
Coordinate the implementation process with all the project proponent’s relevant staff, in
particular the City’s Project Implementation Unit (PIU), the Waste Management
Department and the Landscaping and Cleaning Service Department (LCSD);
Work with Social/Welfare department and other relevant social/medical professionals to
facilitate access to social benefits and undertake training, psychological, medical support,
etc. to waste pickers;
Adapt mitigation and compensation measures (including additional measures for
particularly vulnerable individuals) in response to any changes on the ground and
consultation with affected and interested stakeholders;
Ensure delivery of communal facilities at NEDS and TDDS as per the LRP;
3.3 | TASK 3: MONITORING
Monitoring is a critical component of this assignment. The Consultant will monitor the indicators
collected during the baseline studies carried out for the LRP and complemented by additional
surveys carried out at the outset of this assignment in order to measures livelihood impacts and
both quantitative and qualitative outcomes of the livelihood restoration measures provided for
under the LRP (see section 10 of the LRP).
The consultant will:
Monitor waste pickers on a regular basis immediately after displacement, with frequency
decreasing over time. In the event that indicator trends are less than positive, additional
measures will need to be developed to support waste pickers. Data will need to be analysed
to consider results at an aggregate level and also broken down by sub-groups (e.g. elderly
waste pickers, waste pickers with no formal education; vulnerable households etc).
Monitor at the time of Project construction to ensure Project inputs are delivered and to
collect a summary of the intentions of each waste picker household (their livelihood
option).
Monitor on a 3 monthly basis after the cessation of access to MDDS. The first round of
monitoring (beginning of month 3) will have provided time for waste pickers to participate
in the training and other forms of support outlined in the LRP, and to, hopefully, have
secured another form of employment. The beginning of Month 3 will also mark the end
82530 TOR published
UB Solid Waste Modernisation Page | 10 of 14
of the value of the “second transition allowance” payment and as such will provide a good
status update on the prospects for the waste picker household.
Monitor on a six monthly basis after the first year, with waste pickers who have
successfully transitioned to formal secure employment “graduating” from the group and
no longer requiring monitoring.
Monitoring activities would be expected to conclude when the Modernization Project is complete
(assumed to be 3 years time).
4 | IMPLEMENTATION ARRANGEMENTS
The Consultant will report on all aspects of the Assignment to the EBRD in consultation with the
Client’s representative, and liaise with the Resident Office and the Environmental and
Sustainability Department lead, based at EBRD headquarters in London.
The Client and the Bank will provide the Consultant with access to, or copies of all, relevant
information in English or Mongolian. The Consultant will make a detailed review of this
information and provide all documentation expected as deliverables in both English and
Mongolian. The Consultant will bear the cost of any necessary translations.
The Consultant will be expected to work with a variety of relevant implementation partners and
stakeholders including officials of the Municipality of Ulaanbaatar, the Project’s PIU,
management of the City’s waste disposal services and of the MDDS site in particular (LCSD),
local authorities and other government representatives, PAPs, as well as possible partner NGOs
or CSOs where appropriate.
5 | DELIVERABLES
The Consultant will submit the below deliverables. All documents shall be prepared in English
and Mongolian and provide for one round of reviews by the Bank and the Client/PIU. Any
information identifying individual waste picker households and containing any names or other
information allowing the identification of individuals will be presented in Annexes that can be
readily removed from documents prior to public disclosure. Final versions will be provided in
word and pdf formats.
Deliverable 1: Detailed work plan for the LRP implementation activities, including a
detailed Monitoring Plan and a list of implementation partners to include the Client, local
authorities, relevant government agencies (welfare officer, pensions, etc.), and civil
society organisations (CSOs), where appropriate, so as to coordinate the LRP
implementation activities (2 weeks from assignment start)
Deliverable 2: Monthly Implementation Progress Reports for a period of 6 months
(starting 4 weeks after assignment starts)
Deliverable 3: Implementation Completion Report (2 weeks following delivery of all the
key LRP compensation and mitigation activities)
82530 TOR published
UB Solid Waste Modernisation Page | 11 of 14
Deliverable 4: Four 3-monthly Monitoring Reports (starting 6 weeks following after all
the key LRP compensation and mitigation activities have been delivered over the
duration of 12 months)
Deliverable 5: Four 6-monthly Monitoring Reports (starting after the first year of
monitoring)
Deliverable 6: LRP Implementation Evaluation Report (3 years following start of
monitoring).
All final documents and reports prepared for this contract delivered in Word and PDF versions in
English and Mongolian.
82530 TOR published
UB Solid Waste Modernisation Page | 12 of 14
ANNEX 1
BREAKDOWN OF COSTS (EXCLUSIVE OF VAT)
DIRECT EXPENSES
1. Fees (Remuneration):
Name of Experts Job Titles Working
Period
In the
Field (Days)
In Home
Office (Days)
Total
No of Days
Expert
Daily Rate
Total
Days
Total Fees
2. Per Diem Allowance:
Place Number Rate
Period Per Diem Total
Total Per Diem
REIMBURSABLE EXPENSES
(may include indirect taxes, such as VAT which are not otherwise recoverable by the Consultant)
3. Air Travel: (Full Economy Class or Equivalent)
Routing Air Fare No. of Flights
Total
Total Air Travel
4. Local Travel: (Travel from home to departure airport & return, and reasonable local travel abroad)
Journey Cost No. of
Journeys Total
Total Local Travel
5. Miscellaneous
Item Description Number Total
Visas
Interpretation and Translation
82530 TOR published
UB Solid Waste Modernisation Page | 13 of 14
Reports
Communications
Equipment Purchase
Accommodation for long term experts (not listed in Per Diem)
Other Miscellaneous Expenses (to be specified)
Total Miscellaneous
6. Contingencies: (utilisation only after prior approval in writing by the Bank)
Item Amount
Total Contingencies
Total Financial Proposal
82530 TOR published
UB Solid Waste Modernisation Page | 14 of 14
ANNEX 2 – LIVELIHOOD RESTORATION PLAN
(To be send as a separate file)