european carbon dioxide capture and storage laboratory...
TRANSCRIPT
SEVENTH FRAMEWORK PROGRAMME
European Carbon Dioxide
Capture and StoragE Laboratory Infrastructure
1
Enabling low to zero CO2 emissions from
industry and power generation
www.eccsel.org
Project Director Sverre Quale Norwegian University of Science and Technology (NTNU)
SEVENTH FRAMEWORK PROGRAMME
2
Reduce global warming
Reduce CO2 emissions
Close the
knowledge gaps
Nuclear 8% (8%)
Power gen. efficiency and
fuel switching 3% (1%)
Renewables 21% (23%)
End-use fuel switching 12% (12%)
CCS 17%
End-use fuel and electricity
efficiency 42% (39%)
Reduction needed to
keep global warming
within 2 °C
IEA 2 degrees low carbon path
www.eccsel.org
SEVENTH FRAMEWORK PROGRAMME
3
ECCSEL vision:
Enabling low to zero CO2 emissions
from industry and power generation
The main objectives of the ECCSEL
initiative
Establish and operate a world class
Carbon Capture and Storage (CCS)
distributed research infrastructure in
Europe
Integrate and upgrade existing research
facilities and supplement with new ones
Enhance European science, technology
development, innovation and education
in the field of CCS.
Enable spin-off activities and generation
of new business
USTUTT
Operations
Center
SEVENTH FRAMEWORK PROGRAMME
ECCSEL Preparatory Phase Consortium
4
1. Norway (NTNU, SINTEF, RCN)
2. France (IFPEN & BRGM)
3. The Netherlands (TNO)
4. Germany (USTUTT)
5. United Kingdom (BGS)
6. Switzerland (ETHZ)
7. Spain (CIUDEN)
8. Italy (OGS, ENEA)
9. Greece (CERT/ISFTA)
10. Poland (PGI-NRI)
www.eccsel.org
SEVENTH FRAMEWORK PROGRAMME
5
ECCSEL Preparatory Phase – Timeline and Scope
1
www.eccsel.org
SEVENTH FRAMEWORK PROGRAMME
ECCSEL Operations Centre
Lean organization:
4-6 employees
Annual budget ≈ 1 MEUR
6
Location: NTNU/SINTEF Campus
Trondheim, Norway
www.eccsel.org
SEVENTH FRAMEWORK PROGRAMME
Nano scale
Laboratory
scale
0.001
0.01
0.1
1
10
100
1000
0.00 0.20 0.40 0.60 0.80 1.00
CO2 loading / (mol CO2/mol AEEA)
pC
O2 /kP
a
40 C
55 C
70 C
95 C
120 C
Laboratory pilot scale
Industrial
pilot scale
Full industrial scale
Gap analysis
Capture and transport: Need for up-scaling promising solutions and
testing at more severe (diverse) experimental conditions (pressure,
temperature, gas compositions, ...)
Storage: Need for a variety of test/pilot
sites throughout Europe
7
SEVENTH FRAMEWORK PROGRAMME
8
H2020 Infradev3 Consortium (2015 - 2017)
www.eccsel.org
ECCSEL Implementation and Transnational Access
SEVENTH FRAMEWORK PROGRAMME
Initial inventory
Template of Fact sheet for existing facilities
SEVENTH FRAMEWORK PROGRAMME
ECCSEL timeline
10
2008 2020 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
Events
Funding
Operational/Investment phase
Project funding PP1/PP2
• EC FP7: 2.5 MEUR
• RCN/CLIMIT: 1 MEUR
• Other partners: 1 MEUR
FP7 pre project
granted
Horizon 2020 Infradev-
3 funding
• 3 MEUR
Implementation Upgrades and new builds PP1
ECCSEL on
ESFRI roadmap
Infrastructure
investments (until
2030)
• 200+ MEUR
(Funded by EU,
member states,
funds, industry…)
Preparatory phase
PP2
Signed Letter of
Intent (LoI) and
implementation
MoU agreement,
9 European states
ECCSEL
converted into
an ERIC
www.eccsel.org
SEVENTH FRAMEWORK PROGRAMME
Capture facilities Upgrades
Item Description Priority Category Budgeted investment cost in
million €
1
Experimental facility for development and testing of H2-rich fuels in gas turbine
burners and combustor systems, as well as testing of systems with CO2 enrichment,
oxy-combustion, or enriched air combustion.
Candidate locations: DLR Germany, SINTEF Norway and TNO Netherlands
High Upgrade
existing 5-8
2
Oxy-combustion industrial pilot scale; enabled for various solids fuels. Upgrading for
operation periods >1000h.
Candidate location: CIUDEN, Spain
High Upgrade
existing 16-17
3
Modifications of existing pilot plant for testing and verification of conceptual capture
techniques using solvents with flexible combustion system in order to enable a broad
range of fuels, and to also mimic industrial gases in systems using post and pre-
combustion techniques.
Possible location: Tiller, Norway
High Upgrade
existing 4.4
4 RI for emission reducing technologies, solvent technology, Post and Pre-combustion,
Candidate locations: SINTEF Norway and TNO Netherlands High
Upgrade
existing 0,6
5
Reactor set up testing facility for low Temperature adsorption processes at realistic
operating conditions, Post- and Pre- combustion,
Candidate locations: SINTEF, Norway.
High Upgrade
existing 1-3
6
RI for preparation and testing of up-scaled polymeric and hybrid membranes
Candidate locations: NTNU, Norway. High Upgrade
existing 0,8
7
Facilities for testing of lab scale inorganic membranes in realistic gas composition
including H2S
Candidate location: SINTEF, Norway
High Upgrade
existing 0,5
8 Semi pilot scale inorganic membrane fabrication
Candidate location: SINTEF Norway High
Upgrade
existing 0,5
SEVENTH FRAMEWORK PROGRAMME
New Storage Facilities
Item Description Priority Category Budgeted investment
cost in million €
25
A pilot scale research facility for injection into a fracture to study
migration and attenuation processes during migration through the
overburden. Challenges could be site identification and permitting.
Hontomin and Svalbard may be possible candidates.
High
New or
upgrade
existing
3-8
26
A large (i.e. metres-scale) true tri-axial cell to enable cap
rocks. Such a cell will give us the realistic stress testing for
reservoir and opportunity to investigate more realistic stress
distributions. For example, we could run fracture
propagation tests which are not possible in existing
equipment due to boundary effects. A
Medium New 2-3
27
Well scale testing facility at well (with realistic diameter) for
evaluating in-situ a range of in-situ potentially damaging processes
specific to CCS wells (temperature changes, pressure changes, low pH
conditions...). This implies: cement-rock bonding, casing-cement
bonding,
casing boundaries, remediation technologies, borehole monitoring.
Medium New 3-5
28
Engineering facility to develop new low-cost, advanced, drilling
techniques for site characterisation and monitoring.
Svelvik may be a potential candidate
Medium New 2-4
29
Facility to simulate leakage for developing models and integrated
monitoring technologies for offshore storage.
No storage site needed.
High New 3-8
SEVENTH FRAMEWORK PROGRAMME
ECCSEL RI membership development plan
13
Preparatory Phase (2011-2014)
Norway (host)
• NTNU, SINTEF, RCN
France
• IFPEN, BRGM
The Netherlands
• TNO
Germany
• Universität Stuttgart
United Kingdom
• BGS
Switzerland
• ETH Zürich
Spain
• CIUDEN
Italy
• OGS, ENEA
Greece
• CERT, ISFTA
Poland
• PGI-NRI
Implementation (2015-2016)
• Norway
(Operations Centre)
• The Netherlands
• Spain
• United Kingdom
• Poland
• Italy
• Greece
• France
• Switzerland
(Observer)
Expansion
• Germany
• Czech Republic
• Other member states
• Bilateral agreements
with oversea states
www.eccsel.org