european region project planning processplanning process · – drawing up of tender documents by...

29
1 Conventional Facilities and Siting GG Conventional Facilities and Siting GG Global Design Effort Global Design Effort 1 European Region Project Planning Process Planning Process J.L.Baldy & J.Osborne (CERN)

Upload: hadung

Post on 07-Jul-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

1Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort1

European Region Project Planning ProcessPlanning Process

J.L.Baldy & J.Osborne (CERN)

Page 2: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

2Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort2

Overview1. Typical planning for a large scale Project2. Site investigation3 F liti ith H t C t A th iti3. Formalities with Host Country Authorities4. LHC Schedule for civil engineering5. Methodology & follow-up for Time Schedules plus Examplesgy p p p6. Selection Procedures7. Work Packages8 Insourcing/Outsourcing8. Insourcing/Outsourcing9. Mandate to CE Consultants10. Experience gained at LHC with FIDIC Contracts for the Works11 M i Ri k f d l11. Main Risks for delays12. Conclusion

Page 3: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

3Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort3

1. Typical planning for a large scale Project (1)

1 Initiation of the Project / Baseline Configuration Document1. Initiation of the Project / Baseline Configuration Document– Reception of project request– Appointment of Project Leader with mandate– Project Launch meeting

Identification of the requestor’s needs– Identification of the requestor s needs

2. Feasibility Study / Reference Design Report– Analysis of needs and translation into technical needs

P j t h d li d di t ib ti f t k– Project scheduling and distribution of tasks– Feasibility study : technical solution, cost and time estimates– Green light from requestor and funding in place

3 D i St / E i i D i R t3. Design Stage / Engineering Design Report

– Studies carried out within each group under supervision of Project Leader (with or without outside consultants)V lid ti f d i b R t– Validation of design by Requestor

– Drawing up of Tender documents by each group– Contractors/Suppliers selection procedures established– Preparation of execution drawings

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 4: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

4Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort4

1. Typical planning for a large scale Project (2)

4 E ti St4. Execution Stage– Issue a ‘Start of Works’ Notice– Kick-Off meeting organised by PL and all participants– Performance and Supervision of the Works managed by technical groups with

the help of Global groups (and possible outside consultants)– Testing & Acceptance by technical groups– Hand over to Requestor of completed works– Lifting of reservations– Acceptance by operating services– Supply of a full set of operation & maintenance documents

5. Assessment Stage– Establishment of finished Project File– Internal and External assessment– Modification of procedures for future projects

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

j

Page 5: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

5Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort5

1. Typical planning for a large scale Project (3)- LHC Civil Engineering Pre-Contract Award Phaseg g

April 1996 Consultants Contract Start Date

PRELIMINARY DESIGN (3 Months)

July 1996 Freeze Design for Tender Purposes

TENDER DESIGN (7 Months)

February 1997 Completion of Contract Documents

April 1997 Launch Call for Tender

BID PREPARATION (4 Months)

August 1997 Return of Offers

ANALYSIS OF BIDS

PREPARATION OF FC PAPERS

November 1997 Finance Committee

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 6: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

6Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort6

2. Site Investigation• For LHC studies, all LEP geotechnical investigative reports were

collated and new specific borings executed 3-4 years before the start of the worksitestart of the worksite.

• As an example, for the CMS worksite, 11 new boreholes were drilled and tested Information collated included :and tested. Information collated included :– Detailed cross sections of ground geology– Any known faults in the underlying rock identified– Ground permeabilityGround permeability– Existence of underground water tables– Rock strengths etc etc

• Separate contracts were awarded for these site investigations prior to Tender design studies starting.

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 7: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

7Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort7

3. Formalities with Outside World (1)- Environmental Impact Study

Main Contents :

Scientific Basis of the ProjectScientific Basis of the Project

Project Description (Machine & Detectors)

Civil EngineeringCivil Engineering

Works Management

I t th E i tImpact on the Environment

Measures in place to mitigate Impact

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 8: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

8Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort8

3. Formalities with Outside World (2) - Building Permit Procedures

• In order to prepare the Building PermitsIn order to prepare the Building Permits specialist consultants must be appointed :– Building Architectsg– Land Surveyors– Landscape Architects

• This process can take several months.

• The submissions must include layout drawings, safety d t il l d i fil d t l d idetails, landscaping profiles, cadastral drawings,standard administrative forms etc..

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 9: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

9Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort94. LHC Civil Engineering As-Built Schedule (1)

March 2005

Planning Approval granted by French

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Planning Approval granted by French Prime Minister L.Jospin (following CERN Impact Study)

End of LEP operation

Page 10: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

10Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort10

4. LHC Civil Engineering As-Built Schedule (2)- LHC civil engineering cash flow MCHF

120,000,000

80,000,000

100,000,000

40 000 000

60,000,000

20,000,000

40,000,000

01996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 11: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

11Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort5 M th d l & f ll f Ti S h d l (1) 115. Methodology & follow-up for Time Schedules (1)

• Planning Methodology for LHC :– Master Schedule :Master Schedule :

• strategic goals and major milestones– General co-ordination schedule :

• implement most effective sequence of installation ( with resources & time)Detailed Installation schedule :– Detailed Installation schedule :

• ensure resources are available / work feasible within allocated time slot• Installation Sequence :

– Phase 1 general services– Phase 2 cryogenic line– Phase 3 Machine components– Phase 4 Hardware commissioning

• Technical Dept follow up :• Technical Dept. follow up :– Day to Day progress monitoring– Early warning on delays– Short term planning methodologyp g gy– Continuous feedback to allow dynamic modifications

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 12: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

12Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort12

5. Methodology & follow-up for Time Schedules (2) - Example of ILC Civil Engineering planning methodology

Extract of ‘typical’ ILC planning produced by M Gastal

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

produced by M.Gastal

Page 13: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

13Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort13

Sector5. Methodology & follow-up for Time Schedules (3) - Example of Full LHC Installation Schedule

Cabling

Interconnections

Powering tests

Tim

e

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 14: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

14Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort146.Selection Procedures (1)

- LHC Civil Engineering Selection Procedure for Contractors using the ‘Two Envelope Technique’

Technical Envelope :p•Administration information

•Planning

•Sub-contracting

•Execution methods

•Plant

•Labour resources

•Alternatives

JURY

Commercial Envelope :T t l P i•Total Price

•Financial conditions

•Price breakdown

•Payment cashflow

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 15: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

15Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort156.Selection Procedures (2) - LHC Civil Engineering Selection Procedure

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 16: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

16Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort16

Package 02

7. Work Packages (1) - Geographical layout of surface works for LHC

Package 03

Package 01

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 17: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

17Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort17

Package 02

7. Work Packages (2) - Geographical layout of underground works for LHC

Package 03

Package 01

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 18: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

18Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort187. Work Packages (3)

Package PLACE PROJECT CONSULTANT CONTRACTOR

1 POINT 1 ATLAS- EDF (F)- KNIGHT & PIESOLD (GB)

- TEERAG-ASDAG (A)- BARESEL (D)- LOCHER (CH)

- GIBB (GB)2 POINT 5 CMS

- GIBB (GB)- GEOCONSULT (A)- SIG (CH)

- DRAGADOS (E)- SELI (I)

3A AUTRES ALL OTHER WORKSEXCEPT TI 8

- BROWN & ROOT (GB)INTECSA (E)

- TAYLOR-WOODROW (GB)AMEC (GB)3A POINTS EXCEPT TI 8 - INTECSA (E)

- HYDROTECHNICA (P)- AMEC (GB)- SPIE-BATIGNOLLES (F)

3B TI 8 TI8 TRANSFER TUNNEL DITO - LOSINGER (CH)

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 19: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

19Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort19

8. Insourcing / Outsourcing (1)•At a very early stage it was decided to outsource as many result-oriented activities for LHC as possible.

•For example the Civil Engineering design & supervision.

•Key responsibilities were managed in-house For example :•Key responsibilities were managed in-house. For example :

Planning approval processesPreliminary designPreliminary designFeasibility studiesFinancial Control including claim managementSite co-ordination with other CERN groupsg p

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 20: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

20Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort20

8. Insourcing/Outsourcing (2)- Civil engineering outsourcing structureg g g

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 21: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

21Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort21

9.Mandate to CE Consultants•For LHC, consultancy contracts were awarded for the design & supervision of the Works. The services were phased, with penalties in case of late delivery :

•Phase 1 : Prepare all preliminary layout drawings, designs and cost estimates

•Phase 2 : Prepare the ‘Tender Design’ including drawings, bill of quantities, specification etc. assuming 50 year lifespan

•Phase 3 : Prepare Execution Documents & Assist in tender analysis

•Phase 4 : Site Supervision

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

•Phase 5 Maintain staff on site until Final Payment Certificate agreed.

Page 22: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

22Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort10. Experience gained at LHC with FIDIC Contracts (1)- Why FIDIC form of Contract ?

22

•FIDIC – the International Federation of Consulting Engineers.g g

•CERN used a modified version of FIDIC “Conditions of Contract for Works of Civil Engineering Construction” 4th Edition, or “The Red Book” Re measurement type of contractBook . Re-measurement type of contract.

•This type of contract is well suited to the ILC type of construction forThis type of contract is well suited to the ILC type of construction for the following reasons :

•Well recognised contract documents for International Projects

•Suitable for projects where main responsibility for the design lies with the Client (or his Engineer).

•Work done is measured payment via Bill of Quantities•Work done is measured, payment via Bill of Quantities

•Scope to modify the works via Variation Orders

•Adjudication Process for Claims & Disputes•Adjudication Process for Claims & Disputes

Page 23: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

23Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort23

P f th E i T h i l d i i i d ith th

10. Experience gained at LHC with FIDIC Contracts (2)

- Major Modifications made by CERN to the standard Contract• Powers of the Engineer : Technical decisions remained with the

Engineer, whereas financial ones remained with CERN (with advice from the Engineer).

• Sufficiency of Contract : The contractors were obliged to satisfy themselves on the sufficiency of all tender documents to carry out the works described.

• In case of disputes : Panel of Adjudicators, then if required,In case of disputes : Panel of Adjudicators, then if required, Arbitration in Geneva after completion of the Works

• Penalties for late delivery rather than liquidated damages• Penalties for late delivery rather than liquidated damages.

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 24: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

24Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort24

• Adjudication procedure was deemed a great success

10. Experience gained at LHC with FIDIC Contracts (3)

- CERN’s experience for LHC with FIDIC• Adjudication procedure was deemed a great success.

• A panel of 5 “experts” agreed with the Contractors.

• 3 disputes were referred to the panel (2 with the Contractors and 1 with the Consultants).

• Several disputes settled without need for Adjudication because one party “fearedSeveral disputes settled without need for Adjudication because one party feared losing control”.

• Decisions made very quickly (within 2 months) in accordance with Contract.

• Each adjudication cost less than 1.5% of the adjudicated amount.

• All disputes during LHC construction have been resolved.p g

• No Arbitrations.

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 25: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

25Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort25

• Value Engineering was developed for one of the LHC Packages during the

10. Experience gained at LHC with FIDIC Contracts (4) - Value Engineering

• Value Engineering was developed for one of the LHC Packages during the course of the Works.

• Due to delays on CERN’s side (LEP running longer than expected) and dueDue to delays on CERN s side (LEP running longer than expected) and due to the introduction of the new 35hour law in France, it became apparent that the tender planning was not realistic.

A T t C t f th j t d ith C t t hi h ld• A Target Cost for the project was agreed with Contractor which could fluctuate depending on CERN’s requirements.

• Partnering Agreement established with Profit/Loss sharing conceptPartnering Agreement established with Profit/Loss sharing concept.

• The contractor had to be transparent with his ‘real’ costs under this new agreement.g

• The Works were completed to the satisfaction of both parties under this agreement.

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 26: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

26Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort26

11. Main Risks for delay for CE Works (1)

A full risk assessment must be carried out for both the pre-construction phase and execution phase of the works.

The Pre-construction phase must assess risks such as :

•Delay during the planning permission approval process

•Objections raised from the public on environmental groundsj p g

•Problems with the project management team

•Project financing uncertainties

•Tenders submissions not reaching minimum bidding standards

Page 27: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

27Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort27

11. Main Risks for delays for CE Works (2)

Th i h f h k i k hThe execution phase of the works must assess risks such as :

• Uncertainties with geological, hydrological and climate conditions, including:Uncertainties with geological, hydrological and climate conditions, including:– Unstable tunnel excavation face– Fault zones– Large amounts of water inflow– Large amounts of water inflow– Unexpected ground movements (especially in large caverns)

• Anomalies in contract documents (e g large quantity inaccuracies)Anomalies in contract documents (e.g. large quantity inaccuracies)• Interference from outside sources• Delayed submission of approved execution drawings• Design changes from the consultants and/or ownerDesign changes from the consultants and/or owner• Lack of thorough safety and/or environmental control• Labour relations• etc

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 28: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

28Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort28

12. ConclusionsI i /O t i li t b d id d• Insourcing/Outsourcing policy must be decided at an early stage

• Establishing a competent time scheduling team f i iti l h d l d it ifor initial schedule and monitoring

• Detailed Site Investigation essential

• The form of Contract must be carefully chosen e.g. FIDIC for LHC proved successful

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)

Page 29: European Region Project Planning ProcessPlanning Process · – Drawing up of Tender documents by each group ... April 1997 Launch Call for Tender BID PREPARATION (4 Months) ... or

29Conventional Facilities and Siting GGConventional Facilities and Siting GG

Global Design EffortGlobal Design Effort29

Savings……………..

31 May 2007European Region Project Planning Process

J.L.Baldy (& J.Osborne)