euston approach update · • phase four: 6 april to 3 may –northbound lane between the junctions...

19
EUSTON APPROACH UPDATE HS2 Enabling works January 2020

Upload: others

Post on 24-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

EUSTON APPROACH UPDATE

HS2 Enabling works

January 2020

Page 2: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

Regents Park Estate utility diversions and demolition works

Stanhope Street

• The junction with Varndell Street is closed late January to late February

• Southbound lane closure opposite Augustus House for 3 weeks in February

• 10 metre lane closure in front of Langdale from 27 to 31 January

Hampstead Road

• Short southbound lane closure on Hampstead Road opposite Robert Street from 13 to 31 January

• Northbound footpath closed from 20 January to 21 February, bus stop relocated south towards Cartmel

Page 3: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

Regents Park Estate demolition activities and sequence

Indicative demolition dates and durations

1. Ainsdale - completed to ground level

2. Eskdale – completed to ground level

3. Silverdale – due to complete to ground level by end

February 2020

4. Granby House – due to complete to ground level by end

February 2020

5. Stalbridge – due to complete to ground level by end

February 2020

6. Old Tenant’s Hall – due to start during March 2020

Page 4: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

Silverdale demolition sequence• Hampstead road footpath and bus lane closure from 20

January to 21 February, bus stop relocated towards Cartmel

• East/west wing demolition –Top down method

• Scaffold encapsulation• Cranes lift small excavators on to the

roof and then each floor as it comes down

encapsulation

install ladder beams to support the scaffold and spread load out away from the building

Page 5: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

Combined and applied systems for Regent’s Park Estate for dust suppression

For Regent's Park Estate

a combination of the above systems to be usedAlso, spray nozzles on curtain screen will be

designed for this project specifically

Dust nozzle

Demolition curtain

suspended by crane

Moto Fog

Dust Boss

Water supply

Rubber strips

Steel beam

Page 6: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

Dust suppression2. Trolley mounted unit (MotoFOG)• Concentrated water vein

• Range 15 to 55m

• Suitable for high floors

1. Dust cannon (Dust Boss)• Fine mist cloud

• Range up to 80m

• Covers large areas

3. Spray nozzles on the long reach arm

Page 7: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

Euston South demolition works

Wolfson House – due to be completed in April Walkden House – forecast completion in late April

Demolition has re-started in Wolfson House this month, main demolition is due to be completed in April.

Demolition is ongoing, next phase to include the removal of the first and ground floor slabs, with the above ground structure due to be completed by late April.

Page 8: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

Euston South demolition works Euston Towers demolition works

• Grant Thornton Works, 11 floors have been

demolished and currently down to ground

floor level. The remaining walls will be fully

demolished by February

• 1 Euston Tower, 14 floors have been

demolished and currently down to the larger

1st floor level slab. The demolition of this

slab will start following scaffold

modifications and continue until late

summer.

Page 9: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

North Gower Street and Gower Street utility works North Gower Street between Drummond Street and

Stephenson Way

• Phase one: 7 January to 2 February – Southbound lane,

between the junctions of Drummond St and Euston St.

• Phase two: 3 February to 1 March – Northbound lane,

between the junctions of Drummond St and Euston St.

• Phase three: 2 March to 5 April – Southbound lane

between the junctions of Euston St and Stephenson Way.

• Phase four: 6 April to 3 May – Northbound lane between

the junctions of Euston St and Stephenson Way.

Gower Street and Gower Place

• Phase one: 7 January to 23 February – West side lane in the

junction with Euston Road.

• Phase two: 23 February to 22 March – East side lane in the

junction with Euston Road.

• Phase three: 23 March to 28 June – Gower Place between

Gower Street and Gower Court.

Page 10: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

2020 Community drop-in events, venues to be confirmed

Date Time

Tuesday, 21 January 5-7pm

Wednesday, 4 March 12–2pm

Thursday, 16 April 3-5pm

Tuesday, 2 June 5-7pm

Wednesday, 15 July 12–2pm

Tuesday, 8 September 5-7pm

Wednesday, 21 October 4-6pm

Thursday, 3 December 5-7pm

Page 11: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

CSJV Community investment

Page 12: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

CSJV’s achievements

School engagement

80 STEM/STEAM Ambassadors

11,027 Number of students engaged with

209 Events

Supporting students from mainstream education and SEND

Page 13: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

CSJV’s Achievements

73 Apprentices

208 Previously

unemployed

5 Homeless through

supply chain

Care leaver support

2,232 work

experience

hours

£29,868

money raised

in 3 years

Page 14: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

November 2019, essay competition with Maria Fidelis

School, Euston. Over 26 submissions from students,

topics ranging from gender equality, knife crime and

their family heritage.

Maria Fidelis essay competition

Page 15: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

Maria Fidelis essay competition WINNER!!

Page 16: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

We have been supporting the ZAD café on Ampthill

Square Estate, by refurbishing their site. This month,

they will be reopening to the public. ZAD Café

Page 17: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

Delivery made to the Trussell Trust at St Pancras

Church house in December. The staff at HS2 & CSJV

donated over £600 worth of food and toiletries for

people in need in Camden.

Trussell Trust Donation

Page 18: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

In September 2019, seven CSJV staff visited C4WS ‘Friday food

club’ and cooked up a storm with their meat/vegetarian chilli

con carne. They fed 65 people in Camden who are currently

homeless and rely on the support the charity provides.

C4WS FRIDAY FOOD CLUB

Page 19: EUSTON APPROACH UPDATE · • Phase four: 6 April to 3 May –Northbound lane between the junctions of Euston St and Stephenson Way. Gower Street and Gower Place • Phase one: 7

HS2’s Camden fundOver £2.4m has been awarded to

projects from

the Camden Fund

The Brandon Centre -bespoke training and support to strengthen the mental-health capacity and skills of various organisations working with young people.

Phoenix Youth Community Project -a programme of youth activities including homework club, workshops and more

Clime-it Brothers Academy – a service that provides employment and apprenticeship placements for ex-offenders and young people at risk, teaching participants to design and manufacture merchandise to be sold at Camden Market.

The Story Garden – a new community space located behind the British Library - a space to listen, share and act on ideas.

The Third Age Project – to help older people access various activities in a new community hub