evaluation of barriers to value management …

19
Bruno Lot Tanko, Noor Azeyah Khiyon and Roger Flanagan (2019) Evaluation of barriers to value management application in construction projects In: Laryea, S. and Essah, E. (Eds) Procs West Africa Built Environment Research (WABER) Conference, 5-7 August 2019, Accra, Ghana, 551-569 551 West Africa Built Environment Research (WABER) Conference 10 th Anniversary Conference, 5-7 August 2019, Accra, Ghana Proceedings Edited by Laryea, S. and Essah, E. ISBN: 978 – 9988 – 2– 6010 – 1 DOI: https://doi.org/10.33796/waberconference2019.38 EVALUATION OF BARRIERS TO VALUE MANAGEMENT APPLICATION IN CONSTRUCTION PROJECTS Bruno Lot Tanko 1 , Noor Azeyah Khiyon 2 and Roger Flanagan 3 1,2 School of the Built Environment, University of Reading Malaysia, Malaysia 3 School of Construction Management and Engineering, University of Reading, UK Value Management (VM) initiatives have been recognized as beneficial to the construction industry of most developed and developing countries. The Society of American Value Engineers (SAVE) has reiterated that the application of VM methodology would enhance the quality and performance of construction projects. Though a number of countries apply the VM technique, a developing country like Nigeria seems to have a limited application. This study therefore evaluates the critical barriers to VM application in the Nigerian construction industry. Data collection was based on self-administered questionnaires from construction professionals, while data analysis techniques employed include: descriptive analysis, normality test; reliability test; validity test using Kaiser-Meyer-Olkin (KMO) and Barlett’s test of sphericity; factor analysis; and structural equation modelling (SEM). Lack of VM experts, lack of awareness on VM among clients, poor working relationship among stakeholders, inadequate facilitation skills/training, and absence of local VM guidelines are the major barriers to VM practice. Fifteen (15) barriers were validated under four major classifications (People, Government, Environment, and Methodology). The implication of this study is to assist construction practitioners, researchers, and academics to focus on the important concerns that are necessary to support the application of VM in developing countries in order to enhance the value of construction projects. Keywords: barriers, construction industry, construction professionals, Nigeria, structural equation modelling, value management INTRODUCTION The construction industry is one and only sector that is saddled with the commitment of transforming various resources into constructed physical structure. As a viable sector in the economy of any country (Abdullah et al., 2004; Ogunsemi et al., 2008), the industry is largely concerned with the development of roads, railways, bridges, residential, institutional and commercial buildings. Construction activity in Nigeria is handled by construction professionals, and indigenous/foreign construction contractors who offer their services to both private and public clients. Nevertheless, Nigerian Bureau of Statistics (2010) submitted that government is 1 [email protected] 2 [email protected] 3 [email protected]

Upload: others

Post on 01-Dec-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Bruno Lot Tanko, Noor Azeyah Khiyon and Roger Flanagan (2019) Evaluation of barriers to value management application in construction projects In: Laryea, S. and Essah, E. (Eds) Procs West Africa Built Environment Research (WABER) Conference, 5-7 August 2019, Accra, Ghana, 551-569 551

West Africa Built Environment Research (WABER) Conference 10th Anniversary Conference, 5-7 August 2019, Accra, Ghana

Proceedings Edited by Laryea, S. and Essah, E. ISBN: 978 – 9988 – 2– 6010 – 1

DOI: https://doi.org/10.33796/waberconference2019.38

EVALUATION OF BARRIERS TO VALUE MANAGEMENT APPLICATION IN CONSTRUCTION PROJECTS

Bruno Lot Tanko1, Noor Azeyah Khiyon2 and Roger Flanagan3 1,2School of the Built Environment, University of Reading Malaysia, Malaysia 3School of Construction Management and Engineering, University of Reading, UK

Value Management (VM) initiatives have been recognized as beneficial to the construction industry of most developed and developing countries. The Society of American Value Engineers (SAVE) has reiterated that the application of VM methodology would enhance the quality and performance of construction projects. Though a number of countries apply the VM technique, a developing country like Nigeria seems to have a limited application. This study therefore evaluates the critical barriers to VM application in the Nigerian construction industry. Data collection was based on self-administered questionnaires from construction professionals, while data analysis techniques employed include: descriptive analysis, normality test; reliability test; validity test using Kaiser-Meyer-Olkin (KMO) and Barlett’s test of sphericity; factor analysis; and structural equation modelling (SEM). Lack of VM experts, lack of awareness on VM among clients, poor working relationship among stakeholders, inadequate facilitation skills/training, and absence of local VM guidelines are the major barriers to VM practice. Fifteen (15) barriers were validated under four major classifications (People, Government, Environment, and Methodology). The implication of this study is to assist construction practitioners, researchers, and academics to focus on the important concerns that are necessary to support the application of VM in developing countries in order to enhance the value of construction projects.

Keywords: barriers, construction industry, construction professionals, Nigeria, structural equation modelling, value management

INTRODUCTION

The construction industry is one and only sector that is saddled with the commitment of transforming various resources into constructed physical structure. As a viable sector in the economy of any country (Abdullah et al., 2004; Ogunsemi et al., 2008), the industry is largely concerned with the development of roads, railways, bridges, residential, institutional and commercial buildings. Construction activity in Nigeria is handled by construction professionals, and indigenous/foreign construction contractors who offer their services to both private and public clients. Nevertheless, Nigerian Bureau of Statistics (2010) submitted that government is

1 [email protected] 2 [email protected] 3 [email protected]

Tanko, Khiyon and Flanagan

552

the biggest investor of the industry as a large amount of capital formation goes into investments in real estate and infrastructure development. This submission is maintained by Dim and Ezeabasili (2015) who stated that the Government of Nigeria procure 70% of the construction projects while 30% are procured by the private sector. Since construction projects are sponsored by the Federal, State and Local Governments, it means that the Nigerian construction industry is directly influenced by the public sector as a major client of the industry. According to Kolo and Ibrahim (2010), the federal government of Nigeria has realised the need to improve service delivery by stipulating that procurement of public assets and services must go through the application of value-added practices. Value-added actions and activities assume an indispensable part in the delivery of projects in the construction industry. These actions feature all techniques and methods that would ensure that projects are executed at the least possible cost while maintaining value and quality. However, there are several construction projects that are on hold or abandoned in Nigeria as a result of several factors including the lack of sustainable value ventures.

A study by Tanko et al. (2017a) revealed a considerable number of value-added activities and methods in the Nigerian construction industry. Kolo and Ibrahim (2010) articulated that value management (VM) is a universally accepted methodology that can realise value-added initiatives. Consequently, most clients and stakeholders are now getting involved with value thinking to achieve the best from their ventures (Ramly and Shen, 2012). Kissi et al. (2015) put forward that a good number of countries (USA, UK, Australia, Hong Kong, China, Saudi Arabia and Malaysia) with new value-added needs have embraced value-added innovations through VM. In the same vein, Thiry (1997) advanced that other countries like Italy, Germany, France, South Korea, Kuwait, Denmark, Taiwan, South Africa, Hungary, and Canada have also embraced VM. Consequently, Ramly and Shen (2012) capitulated that VM has been brought into the construction industry to achieve the best value-for-money. Mohd Rahim et al. (2016) described Value-for-money as the ideal combination of quality and whole life cost with the primary drive to satisfy the requirements of users. Although, according to Ong (2004), VM has extended the traditional emphasis on value-for-money to value for stakeholders, environment, systems, quality, social, ethics, etc. Following the introduction of VM in the construction industry, the technique has gained popularity among industrial scholars and academics (Ramly et al., 2013), and its demand has generally been on the increase (Oke and Ogunsemi, 2011). Various terms such as value assessment, value review, value analysis, value methodology, value engineering, value planning and value control have been associated with VM. Thus, Kissi et al. (2015) and Ong (2004) put forward that VM is synonymous with value engineering (Fan et al. 2013), and value analysis. Thiry (1997) also advanced that VM encompasses value engineering, value analysis, value control, and other value techniques. The agreement to use the term ‘VM’ is basically to describe the combined extensive application of value techniques. Although many terms have been used, what is very important is the improvement of value without sacrificing the intended function.

Tanko et al. (2018a) defined VM as a systematic, team oriented and multi-disciplinary value-added methodology (job plan) aimed at optimizing functions of systems or facilities at the lowest overall life cycle cost and a value system determined by the client. It is a well-thought-out framework that aids successful

Tanko, Khiyon and Flanagan

553

decision making relating to the ‘best value’. In addition, VM is a process by which the project is assessed and analysed to have the best value-for-money by adhering to a certain methodology, the process being led by a trained facilitator (Rangelova and Traykova, 2014). The concept of VM targets to optimise the value of construction projects by providing vital functions or elements at the lowest cost without giving up performance criteria. Therefore, Hwang et al. (2014) and Tanko et al. (2018b) acknowledged VM as a potent technique for attaining best value for construction clients. VM has a propensity to obviously define responsibilities of participants, resolve uncertainties and misperceptions in construction projects, and enhance relationships among stakeholders. A study by Tanko et al. (2018b) inferred that “VM creates innovative and systematic ideas, reduces unnecessary costs, optimises quality and develops teamwork as a means to improve productivity”. Nonetheless, Thiry (1997) stated that VM can only exist when a goal needs to be accomplished or a problem needs to be resolved, when there is no goal or problem, there is no need to improve value. Thus, within the context of this paper, VM is a team-oriented, analytical, and multi-disciplinary methodology directed at enhancing the value of projects. The attainment of better value, removal of unnecessary costs, savings in project cost, understanding and evaluating project’s objectives, improving team work among construction stakeholders, and enhancing the function of projects are some of the benefits of VM.

However, VM has not been formally practiced in Nigeria (Akinpelu, 2016; Sabiu and Agarwal, 2016) as a result of many barriers hindering its implementation (Li and Ma, 2012). Hence, this study seeks to identify the barriers to VM application; evaluate the identified barriers; develop measurement and structural models of barriers to VM application, and to answer the big question, “What are the critical barriers to VM application in the Nigerian construction industry?”

LITERATURE REVIEW

Historical development of VM The origin of VM is traced to the United States General Electric Company, which during the Second World War, searched for way out to address the major shortages of existing resources, raw materials and skilled labour (Whyte and Cammarano, 2012). VM was first introduced in the US by a purchase engineer called Lawrence Miles. The engineer works with the General Electric Company (GEC) in the 1940s during World War II. The company (GEC) was compelled to use substitute materials due to the shortages caused by the war. Thus, the engineer proposed the value analysis method to provide the needed functions at a lower cost. Mr Lawrence Miles found out that a good number of substitutes give equal or better performance without incurring much cost. Therefore, a formal procedure known as value analysis was later developed by him and applied in GEC (Shen and Yu, 2012). Value analysis was widely adopted by other industries after the war due to the noteworthy effect on products performance and cost reduction. In 1954, a more proactive value program was used at the design and engineering stage by the United States Department of Defense’s Navy Bureau of ships, thus, value analysis was changed to value engineering (Thiry, 1997) and was used in North America. Thereafter, the Society of American Value Engineers was established in 1959 (Thiry, 1997), and value engineering was practiced by many engineering firms, government formations and the construction industry. It is a tool which seeks to meet the basic

Tanko, Khiyon and Flanagan

554

functions of a product, service or project at the lowest cost (Zhang et al., 2009). Therefore, the justification of value engineering in the construction industry is to come up with innovative ideas and proffer solutions for increased value of construction projects. Value engineering began in the United Kingdom in the early to mid-1960s and to Australia in mid to late 1960s. Whyte and Cammarano (2012) put forward that the construction industry in the UK adapted Lawrence Mile’s value analysis and advanced it under the name VM which is synonymous with value engineering. Also, Thiry (1997) advanced that in 1965, VM was introduced in Japan. Since it was recognised that the orientation of value engineering activity was more of management than engineering, the UK Institute of Value Management (IVM) was formed in 1966 (Shen and Yu, 2012). VM afterwards was introduced in Germany, France (1978), South Korea, Kuwait, Denmark, Hungary (Thiry, 1997), China (1978), Saudi Arabia (1981), Malaysia (1986) and Hong Kong (1988). According to Thiry (1997), VM was introduced in South Africa and Taiwan in the eighties, while in 1993, it was introduced in Canada.

Definitions of VM Shen (1993) defined VM as “an organised function-oriented and systematic team approach, directed at examining the functions and costs of a service, system, equipment, supply, or facility for the aim of improving its value through attaining the required functions indicated by the clients at the least cost, consistent with the requirements for performance”. It is a creative and a system approach to validate a certain proposal; and has to undergo a structured and systematic job plan which emphasises on the analysis of functions (Che Mat, 1999). Jaapar et al. (2009) upheld that VM is a “multi-disciplinary, team oriented, structured, analytical process and systematic analysis function, which specifically seeks best value through the design and construction process to meet client’s perceived needs”. In addition, it is a technique for improving the overall life cycle of projects, products and systems. Odeyinka (2006) defined VM as “a service, which maximise the functional value of a project by managing its development from concept to completion and commissioning through the audit (examination) of all decisions against a value system determined by the client”. It is a systematic and multi-disciplinary effort focused on analysing the functions of projects for the sole aim of achieving the best value at the lowest overall life cycle cost (SAVE, 2008). The Institute of Value Management UK (2008) distinct VM as a style of management particularly committed to motivate people, improve skills, and stimulate synergies and innovation, with the goal of maximising the general performance of an organisation. On the other hand, Oke and Ogunsemi (2011) likened VM to “a systematic and multi-disciplinary process which is aimed towards analysing the functions of projects from its inception to completion and commissioning (through auditing or examination) for the goal of achieving best value and return on investment at lowest possible overall Life Cycle Cost”.

Therefore, VM has been described as an organised framework that aids effective decision making regarding the best value. Essentially, it is a process where a project is examined and studied to achieve maximum value-for-money by adhering to a particular methodology, and led by a knowledgeable and experienced facilitator (Rangelova and Traykova, 2014) while minimising or keeping the overall life cycle cost (Saifulnizam, et al., 2011). Olawumi et al. (2016) simply attributed VM as a well-established methodology meant to define and maximise the value-for-money,

Tanko, Khiyon and Flanagan

555

while Luvara and Mwemezi (2017) recognised VM as a function-oriented method which has been established and verified as an operationally effective management technique for achieving better-quality design, construction, and cost effectiveness in many construction projects.

The VM methodology The practice of VM in any setting necessitates facilitation. Facilitation is an activity that assist a specific task and makes it realizable. A person who takes on such responsibility is called a facilitator. Consequently, a VM facilitator is one who knowledgeably designs, manages, controls, and leads a VM study team throughout the value management process (Leung and Kong, 2008). However, the VM facilitator is expected to making sure that VM workshops are completed according to an established schedule. Japaar et al. (2012) inferred that an effective VM facilitator requires sufficient knowledge on VM methodology, experience and skills.

The VM process is usually carried out by a multi-disciplinary group of construction professionals, the client (owner), the end-user, and other relevant stakeholders. Generally, the process is separated into pre-workshop, workshop, and post-workshop stages. The pre-workshop is dedicated to gathering of relevant background details of proposed projects. Ramly and Shen (2012) put forward that at the pre-workshop stage, roles and responsibilities are assigned to stakeholders. Subsequently, the definite workshop stage has six (6) phases which include: Information; function analysis, creativity, evaluation, development, and presentation phases (Kelly et al., 2004; SAVE International, 2007; Japaar et al., 2012; Hwang et al., 2014). At the information phase, sharing of project information related to scope, timing, cost, location, and function is imperative. At the function analysis phase, functions are generated and classified into basic and secondary functions (SAVE International, 2007; Ramly and Shen, 2012;) and high cost areas are also identified. The ideas are being brainstormed and assessed to meet the desired functions of projects at the creativity phase (Kelly et al., 2004). At the evaluation phase, Ramly and Shen (2012) advanced that brainstorming should go through further screening to convincingly determine how they could be applied to meet the desired function, and should be classified into: realistically possible to be implemented; remotely possible; and impossible to be implemented. At the development phase, the short-listed ideas are then developed into a feasible solution and presented as an action plan at the presentation phase.

Barriers to VM application in the construction industry Many academics and researchers have investigated the barriers to applying VM in the construction industry. In Saudi Arabia, AI-Yami (2008) identified the following barriers to VM application in the construction industry: lack of information (specifications, standards, historical data, etc.), lack of leadership, lack of time to implement VM, lack of awareness on VM, and client commitment. A study in Southeast Asia by Cheah and Ting (2005) revealed that lack of knowledge on VM, and lack of time for implementation are the main factors that hinder the application of VM. In the Hong Kong’s construction industry, Shen (1997) identified three most significant reasons (lack of knowledge to implement VM, no confidence to introduce VM to clients, and lack of time to implement VM) for not using VM. However, in China, Li and Ma (2012) found out that lack of time to implement VM is not a severe challenge but lack of knowledge on VM, lack of technical norms and

Tanko, Khiyon and Flanagan

556

standards, and lack of VM experts. In Malaysia, Lai (2006) identified lack of knowledge about VM, lack of government support, and lack of local VM implementation guideline as main barriers to VM application in the construction industry. Similarly, Jaapar et al. (2009) confirmed that lack of VM knowledge and practice, the resistance to change by the involved parties, and the conflicting objectives of the project among parties are the main difficulties faced during the VM workshop. Jaapar et al. (2012) also found out that one of the challenges of VM application is the VM workshop which could not efficiently be implemented due to insufficient information provided. Also the difficulty of handling different character, background, and values of people was a key barrier faced by VM facilitators. In addition, a study by Ramly et al. (2015) revealed some factors that would promote VM application in the Malaysian construction industry. This include: VM knowledge and experience of participants, multidisciplinary team mix of participants, competency of the facilitator, attitude and discipline of participants, and client support/active participation. Finally, inadequate regulatory frameworks, and poor stakeholder management are also some of the challenges facing the application of VM in the construction industry (Kissi et al., 2015).

RESEARCH DESIGN AND METHODS

The study utilized data obtained from construction professionals based in Abuja, Kaduna, and Jos. Abuja is the federal capital of Nigeria located at the middle of the country. In 2015, Abuja experienced an annual growth rate of 35% (United Nations Report, 2015) with a significant level of construction output. Kaduna and Jos were chosen because of the proximity to Abuja, high construction activities, and population. According to Rowley (2014), “questionnaire is one of the most extensively used means of collecting data, and is typically used in surveys to profile a population”. This study adopts the 5-point Likert scale closed-ended questions for the structured questionnaire based on the methodology, objectives of the research, and the outcome of a pilot survey. The questionnaire was structured into four (4) sections. The third section was made up of questions aimed at identifying the barriers to VM application in the construction industry, and these barriers were identified from literature and pilot survey. The quantitative approach was adopted for this study. This is because sampling, measurement and the use of questionnaires are utilized due to the complexity and fragmentation of the construction industry. The study began with identifying the research challenges and establishing the gap that exists in the application of VM. The research question was developed and the review of past and present studies was conducted to get an in-depth knowledge of the research problem.

The study had 93 variables, 5 responses per variable (i.e. 465) as recommended by most researchers for factor analysis (Pallant, 2005). Self-administered questionnaires were distributed to 465 construction professionals who were chosen from contracting, project management, consulting engineering, quantity surveying, consulting architects, and client organisations. A total of 344 (73.98%) questionnaires were appropriately filled and returned. Normality test was first conducted using skewness and kurtosis to confirm the normality of the data collected. Similarly, Tabish and Jha (2012) pointed out that in order to establish the stability and comprehension of respondents, instrument reliability should be used to adequately measure the variables of a study. Hence, reliability test was

Tanko, Khiyon and Flanagan

557

conducted using the Cronbach’s alpha coefficient to confirm the reliability of the data collected. The Kaiser-Meyer-Olkin (KMO) and Barlett’s test of sphericity were also used to establish the instrument validity by assessing the sample adequacy and multivariate normality of the study variables. Structural Equation Modelling (SEM), using Confirmatory Factor Analysis (CFA) in AMOS software further validates the measurement models by indicating satisfactory goodness of fit among acknowledged determinants of the study. In addition, cross-tabulation using SPSS version 25 was used to record the frequency of respondents that have specific characteristics. Subsequently, mean scores were used to determine the frequency of occurrence, the degree of severity of the respondents’ responses, as well as the ranking of different research variables. The research design was followed, and the summary of research findings were extracted from the results of the analysis.

ANALYSIS AND DISCUSSION OF RESULTS

This section presents demographic analysis, reliability test, factor analysis, perception of construction professionals on VM barriers, and the overall ranking of barriers to VM application. The barriers are the main obstacles to applying VM by the respective construction professionals, and were derived from literature and pilot survey. The pilot survey was conducted in Nigeria and consisted of consultations and discussions. A thorough literature review was initially carried out to identify the factors that constitute the practice of VM with their associated barriers. A list of factors were derived and developed from literature review. At the commencement of the conversations, the participants were given the list of the factors identified from literature, and were asked to indicate their opinions on whether they considered the factors relevant or advise whether existing factors are irrelevant, or suggest other factors that they considered relevant but were not stated in the list. As a consequence, some variables were deleted while a few were added to the list. The modified and added factors were used to design the main questionnaire. A total of 45 pilot questionnaire survey were administered to the five (5) different professionals in the construction industry, while 32 (71%) questionnaires were returned and completed.

Demographic analysis Table 1 provides an understanding of the respondents’ demography. These consist of the respondent’s working experience, specialisations, and the role of their respective organisations.

Most of the respondents worked for a good number of years in the construction industry. From the analysis, it was revealed that the respondents had the necessary experience to carry out this research survey as 83% (285) of the respondents had at least 6 years working experience, while only 17% (59) had less than 5 years’ experience in the construction industry. The results of the demographic analysis indicated the specialisations of the respondents. From Table 1, 31% (108) of the total respondents are Quantity Surveyors, 26% (90) Architects, 20% (68) Builders, 17% (59) Civil Engineers, while 6% (19) are Services Engineers. The role played by the different organisations in the Nigerian construction industry was also revealed. The respondents from the quantity surveying firms constitute 31% (108), 23% (78) from consulting/designing engineering firms, 16% (54) from contracting firms, while 13% (46), 11% (38), and 6% (20) were from consulting architects, project

Tanko, Khiyon and Flanagan

558

management, and client organisations respectively. This indicates that the respondents are from the core area of study under investigation, and gives credibility to the data used.

Table 1. Demographic characteristics

Demographic Characteristics

(N= 344)

f %

Profession Architects

Quantity Surveyors

Builders

Civil Engineers

Services Engineers

90

108

68

59

19

26

31

20

17

6

Working Experience > 20 years

16 – 20 years

11 – 15 years

6 – 10 years

≤ 5 years

25

38

117

105

59

7

11

34

31

17

Role of Respondents’ Organisations

Contractor

Project Manager

Consulting Engineer

Cost Consultant

Consulting Architect

Client

54

38

78

108

46

20

16

11

23

31 13

6

Instrument reliability test and factor analysis The reliability test was conducted using the Cronbach’s alpha coefficient to confirm the reliability and validity of the data collected. The least Cronbach’s alpha coefficient was 0.80 while the highest value was 0.91. The KMO test, which is a measure of sampling adequacy that compares the magnitudes of the partial correlation coefficients of measuring variables, is 0.711, while Barlett’s test of sphericity, which tests the correlation matrix is significant since the p-value is less than 0.05 (Table 2).

Table 2. KMO and Bartlett's Test

Kaiser-Meyer-Olkin Measure of Sampling Adequacy .711

Bartlett's Test of Sphericity Approx. Chi-Square 8431.239

Barriers Df 210

Sig. .000 The extraction of the components of VM barriers was based on the total variance explained which indicated eigenvalues of 1 and above. Thus, the four components explain a total variance of 73.21%, while the loading of each of the variables is

Tanko, Khiyon and Flanagan

559

presented in Table 3. Instrument reliability was used to satisfactorily measure the variables of this research. The Cronbach’s Alpha values were used to examine the internal consistency of the interrelated multiple scale items. The results of reliability and validity test through the Cronbach’s Alpha in Table 4 show that the barrier attributes are within the range of 0.87 to 0.91. This indicates that the results are highly significant since according to Enegbuma et al. (2015), the values obtained must be higher than the recommended minimum value of 0.60. The barriers are categorised into four groups: Environment (BP), People (BG), Government (BE), and Methodology (BM) based on factor analysis and presented in Table 4.

Table 3. Rotated component matrixa

Component 1 2 3 4

BP1 .894 BP2 .747 BP3 .541 BP4 .690 BP5 .672 BP6 .852 BP7 .705 BG1 .832 BG2 .800 BG3 .754 BG4 .909 BG5 .771 BE1 .819 BE2 .906 BE3 .911 BE4 .847 BM1 .886 BM2 .720 BM3 .897 BM4 .784 Extraction Method: Principal Component Analysis. Rotation Method: Varimax with Kaiser Normalisation. a. Rotation converged in 5 iterations.

Table 4. Reliability of barriers to VM Application

Variable Label Items Cronbach Alpha

BP Environment 7 0.875

BG People 5 0.907

BE Government 4 0.904

BM Methodology 4 0.883

Perception of construction professionals on barriers to VM application The results of cross-tabulation of the data provided an understanding on the frequencies of the respondents’ perception on barriers to VM application. Consequently, the Mean Score (Equation 1) was used to analyse the weight of the respondent’s responses.

Mean Score = ∑ (0≤index≤5) 1

Tanko, Khiyon and Flanagan

560

Where, ni = number of respondents that chose pi.

pi = 1 to 5 on a Likert scale.

N = total number of questionnaire returned.

The 20 barriers to VM application among construction professionals were identified, selected, and accepted by the respondents at the pilot survey phase of this study. While Tables 5 shows the mean scores of barriers to VM application among construction professionals, Table 6 depicts the ranking of these barriers by the respective respondents within the construction industry. Consequently, Majid and McCaffer (1997) posited that factors can be rated as “very hinder” (3.5 ≤ mean < 4.5), or “averagely hinder” (2.5 ≤ mean < 3.5) depending on their mean values. Hence, the criticality of the barriers was established.

Table 5. Mean scores of barriers to VM application

Var.

Architects Q/Survey Builders Civil Engr Serv. Engr Overall MS Rk MS Rk MS Rk MS Rk MS Rk MS Rk

BP 1 4.023 11 4.204 2 4.015 6 4.034 3 4.339 3 4.100 4 2 3.739 15 3.648 16 3.794 13 3.831 13 4.111 7 3.757 15 3 4.091 9 3.935 11 3.838 11 3.881 12 4.056 8 3.953 11 4 4.148 6 4.056 5 3.985 9 3.983 7 4.333 4 4.067 7 5 3.614 16 3.722 15 3.691 16 3.678 15 4.167 6 3.704 16 6 3.761 14 3.944 10 3.794 13 3.814 14 4.000 9 3.848 12 7 3.818 13 3.843 13 3.824 12 3.678 15 3.833 13 3.804 14 BG 1 4.534 1 4.278 1 4.235 1 4.102 2 3.833 13 4.282 1 2 4.102 8 3.870 12 4.015 6 3.949 8 3.889 11 3.974 10 3 4.420 2 4.056 5 4.074 4 4.034 3 3.889 11 4.141 3 4 4.364 3 3.963 8 4.088 3 4.000 5 3.944 10 4.097 5 5 4.273 4 4.093 4 4.029 5 4.000 5 3.833 13 4.097 5 BE 1 3.966 12 3.796 14 3.750 15 3.949 8 3.556 16 3.845 13 2 4.216 5 4.148 3 4.176 2 4.136 1 4.556 1 4.191 2 3 4.136 7 4.037 7 4.015 6 3.949 8 4.278 5 4.056 8 4 4.034 10 3.963 8 3.941 10 3.932 11 4.389 2 3.994 9 BM 1 2.330 18 2.111 19 2.250 18 2.203 20 2.667 17 2.240 19 2 2.000 20 2.278 18 2.238 19 2.525 17 2.667 17 2.282 18 3 2.023 19 1.991 20 2.147 20 2.254 19 2.556 20 2.106 20 4 2.568 17 2.528 17 2.456 17 2.424 18 2.611 19 2.510 17

From Table 5, the Architect perceives the following five (5) factors as “very hinder” or of major hindrance to VM application in the construction industry. These are: lack of VM experts [BG1]; poor collaboration and working relationship among stakeholders [BG3]; inadequate facilitation skills and training [BG4]; lack of willingness to accept changes and new innovations [BG5], and Lack of awareness among clients [BE2].

In addition, other barriers that are of major hindrance to the application of VM by the Architects include: lack of active involvement of clients and stakeholders [BP4]; absence of local VM guidelines [BE3]; lack of VM knowledge [BG2]; difficulty in the involvement of decision makers/other key partners in VM workshop [BP3]; and lack of encouragement on the part of government [BE4]. However, barriers that are

Tanko, Khiyon and Flanagan

561

considered “averagely hinder” or of moderate hindrance to the Architects are: incurring additional cost as a result of VM workshop; lack of time to conduct VM studies; difficulty in conducting analysis/evaluation of functions, and inappropriateness of procurement strategies to implement VM.

Secondly, the research revealed that the Quantity Surveyors distinguishes lack of VM experts [BG1], stakeholders resistance to accept new innovations [BP1], lack of awareness among clients [BE2], lack of willingness to accept changes and new innovations [BG5], and lack of active involvement of clients and stakeholders [BP4] as major hindrances to VM application in the construction industry. Other barriers that are of major hindrance to the Quantity Surveyors are: poor collaboration and working relationship among stakeholders [BG3], absence of local VM guidelines [BE3], inadequate facilitation skills and training [BG4], lack of encouragement on the part of government [BE4] and self-justifying attitude of the original design team [BP6]. Conversely, lack of time to conduct VM studies, difficulty in conducting analysis/evaluation of functions, VM workshop incurs additional cost, and inappropriateness of procurement strategies to implement VM were considered to be of moderate hindrance to VM application by the Quantity Surveyors.

Table 6. Ranking of barriers among construction professionals

Ranking Architects QS Builder Civil Engineer Services Engineer

1 BG1 BG1 BG1 BE2 BE2

2 BG3 BP1 BE2 BG1 BE4

3 BG4 BE2 BG4 BP1 BP1

4 BG5 BG5 BG3 BG3 BP4

5 BE2 BP4 BG5 BG4 BE3

6 BP4 BG3 BP1 BG5 BP5

7 BE3 BE3 BG2 BP4 BP2

8 BG2 BG4 BE3 BG2 BP3

9 BP3 BE4 BP4 BE1 BP6

10 BE4 BP6 BE4 BE3 BG4

11 BP1 BP3 BP3 BE4 BG2

12 BE1 BG2 BP7 BP3 BG3

13 BP7 BP7 BP2 BP2 BG1

14 BP6 BE1 BP6 BP6 BG2

15 BP2 BP5 BE1 BP5 BG5

16 BP5 BP2 BP5 BP7 BE1

17 BM4 BM4 BM4 BM2 BM1

18 BM1 BM2 BM1 BM4 BM2

19 BM3 BM1 BM2 BM3 BM4

20 BM2 BM3 BM3 BM1 BM3

Thirdly, the study revealed that the Builders also identify lack of VM experts [BG1], lack of awareness among clients [BE2], inadequate facilitation skills and training

Tanko, Khiyon and Flanagan

562

[BG4], poor collaboration and working relationship among stakeholders [BG3], and lack of willingness to accept changes and new innovations [BG5] as major hindrances to VM application in the construction industry. Afterward, stakeholder’s resistance to accept new innovations [BP1], lack of VM knowledge [BG2], absence of local VM guidelines [BE3], lack of active involvement of clients and stakeholders [BP4], and lack of encouragement on the part of government [BE4] are some of the major hindrances to VM application as perceived by the Builders. However, the following barriers were considered to moderately hinder VM application. These are: lack of time to conduct VM studies; incurring additional cost as a result of VM workshop; difficulty in conducting analysis/evaluation of functions; and inappropriateness of procurement strategies to implement VM.

The civil engineer recognises the following five (5) factors as “very hinder” or of major hindrance to VM application in the construction industry. These are: lack of awareness among clients [BE2]; lack of VM experts [BG1]; stakeholder’s resistance to accept new innovations [BP1]; poor collaboration and working relationship among stakeholders [BG3]; and inadequate facilitation skills and training [BG4].

In addition, other barriers that are of major hindrance to VM application by the Civil Engineer include: lack of willingness to accept changes and new innovations [BG5]; lack of active involvement of clients and stakeholders [BP4]; lack of VM knowledge [BG2]; lack of legislation which provides VM application in the construction industry [BE1]; and absence of local VM guidelines [BE3]. On the other hand, barriers that are considered “averagely hinder” or of moderate hindrance to the Engineers are: lack of time to conduct VM studies; inappropriateness of procurement strategies to implement VM; difficulty in conducting analysis/evaluation of functions; and incurring additional cost as a result of VM workshop.

And last but not least, the Services Engineer distinguishes lack of awareness among clients [BE2], lack of active involvement of clients and stakeholders [BP4], stakeholder’s resistance to accept new innovations [BP1], Lack of active involvement of clients and stakeholders [BP4], and absence of local VM guidelines [BE3] as the major obstacles to VM application in the construction industry. The Services Engineer also sees other barriers as major obstacles to VM application in the construction industry. These take account of: difficulty to establish mutual project objectives by stakeholders [BP5]; lack of commitment to implement VM [BP2]; difficulty in the involvement of decision makers and other key partners in VM workshop [BP3]; self-justifying attitude of the original design team [BP6]; and inadequate facilitation skills and training [BG4]. On the contrary, lack of time to conduct VM studies, difficulty in conducting analysis/evaluation of functions, VM workshop incurs additional cost, and inappropriateness of procurement strategies to implement VM were measured to be of moderate hindrance to VM application in the Nigerian construction industry.

It is essential to note here that the barriers that moderately hinder the application of VM are common to all the construction professionals in this study.

Ranking of barriers to VM application in the construction industry From Table 5, the people-related factor (lack of VM experts-BG1) ranked top (Av.MS=4.282) by the construction professionals, inferring that VM experts are essential for the implementation of VM in the Nigerian construction industry. This

Tanko, Khiyon and Flanagan

563

finding is supported by Li and Ma (2012), therefore VM experts can be forerunners who would aid the application of VM in the domestic construction projects. A government-related factor (lack of VM awareness among clients-BE2) was 2nd with MS of 4.191. This implies that there is need to orientate public clients on the potential and benefits of applying VM in construction projects. Similarly, AI-Yami (2008) found out that lack of awareness about VM is a major hindrance to VM application in the Saudi construction projects. Another people-related factor (poor collaboration and working relationship among stakeholders-BG3) ranked 3rd (Av.MS=4.141). This finding is supported by Ojoko et al. (2016) and Tanko et al. (2017b) who identified poor communication and teamwork as one of the challenges facing the Nigerian construction environment. That is to say effective communication and collaboration would assist to drive home the actualisation of VM implementation.

The 4th (Av.MS=4.100) barrier is an environment-related factor (stakeholder’s resistance to accept new innovations-BP1). Jaapar et al. (2009) maintained that resistance to changes is a major hindrance to VM application. Therefore, stakeholders should endeavour to welcome new innovations and ideas in order to promote the VM technique and add value to construction projects. Inadequate facilitation skills/training-BG4 and lack of willingness to accept changes-BG5, which are people-related factors ranked 5th (Av.MS=4.097) and 6th (Av.MS=4.097) respectively. Based on these findings, insufficient VM facilitation skills/knowledge and unwilling acceptance to changes would inevitably affect the existence and application of VM. Hence, construction professionals should be trained in the aspect of VM because it is implausible for professionals who have inadequate facilitation skills to request their clients to apply VM in their projects. Next, a local environment-related factor (lack of active involvement of clients and stakeholders-BP4) ranked 7th (Av.MS=4.067), while government-related factors (absence of local VM guidelines-BE3 and lack of encouragement on the part of government-BE4) ranked 8th (Av.MS=4.056) and 9th (Av.MS=3.994) respectively. The 10th (Av.MS=3.974) barrier to VM application is the lack of VM knowledge-BG2 among construction professionals which is classified under people-related factor.

The study also revealed other barriers (11th-16th) that were rated as “very hinder” which include: difficulty in the involvement of decision makers and other key partners in VM workshop (Av.MS=3.953); self-justifying attitude of the original design team (Av.MS=3.848); lack of legislation which provides VM application in the construction industry (Av.MS=3.845); client’s inability to communicate requirements and needs to the design team (Av.MS=3.804); lack of commitment to implement VM (Av.MS=3.757); and difficulty to establish mutual project objectives by stakeholders (Av.MS=3.974).

On the other hand, only one factor (inappropriateness of procurement strategies to implement VM) which is methodology-related obeys the decision rule of “averagely hinder” (2.5 ≤ mean < 3.5), ranked as the 17th (Av.MS=2.510) barrier. Other barriers (VM workshop incurs additional cost, difficulty in conducting analysis/evaluation of functions, and lack of time to conduct VM studies) were neither high nor moderate and fall under the methodology-related factors. These barriers ranked 18th, 19th, and 20th respectively.

Tanko, Khiyon and Flanagan

564

The four (4) identified groups of barriers to VM application were ranked to reveal the criticality of the groupings. The people-related group ranked 1st with an average MS of 4.12 followed by the government-related group with Av.MS of 4.02. The environment-related and methodology-related groups ranked 3rd (Av.MS= 3.89) and 4th (Av.MS= 2.29) respectively. Figure 1 shows the ranking of the VM barrier components in the Nigerian construction industry.

Figure 1. Barriers to VM Implementation

Measurement and structural models for VM Application The barriers to VM application were validated using measurement and structural models to determine the leading authenticated barriers hindering the successful application of VM. The first-order measurement model establishes the strength of relationship of the items or variables of each construct. According to Musa et al. (2015), the first order measurement analysis is often initially carried out to test the validity of measurement models. The base limits of indices used as a part of measuring the goodness-of-fit of the measurement model are specified by Awang et al. (2015), Enegbuma et al. (2015) and Hair et al. (2008) as p < 0.05, Comparative Fit Index (CFI) ≥ 0.90, Goodness of Fit Index (GFI) ≥ 0.90, Chi-square/df (X2/df) < 5, and Root Mean Square Error of Approximation (RMSEA) ≤ 0.05-0.08. Musa et al. (2015) also established that the values of X2 /df should be less than 3, GFI > 0.9, CFI > 0.9, and RAMSEA < 0.08.

Therefore, the measurement model in Figure 2 mainly measures the relationship of the variables or items to each first-order construct (BP, BG, BE, and BM). The fit statistics discovered a p-value of 0.000, CFI value of 0.942, GFI, 0.90, χ2/df value of 2.98, and RMSEA value of 0.08. These values are adequate and within the acceptable thresholds to establish the convergence validity of the measurement model for the barriers to VM application in the Nigerian construction industry. The results from the structural model for barriers to VM application in Figure 3 are also

RANK 1

PEOPLE

Lack of VM experts

Poor collaborationand workingrelationship amongstakeholders

Inadequatefacilitation skills andtraining

Lack of willingness toaccept changes andnew innovations

Lack of VMknowledge

RANK 2

GOVERNMENT

Lack of VMawareness amongclients

Absence of local VMguidelines

Lack ofencouragement on thepart of government

Lack of legislationwhich provides VMapplication in theconstruction industry

RANK 3

ENVIRONMENT

Stakeholders resistanceto accept new innovations

Lack of activeinvolvement of clients andstakeholders

Difficulty in theinvolvement of decisionmakers and other keypartners in VM workshop

Self-justifying attitude ofthe original design team

Client’s inability to communicate requirementsand needs to the designteam

Lack of commitment toimplement VM

Difficulty to establishmutual project objectivesby stakeholders

RANK 4METHODOLOGY

The procurementstrategies areinappropriate forimplementing VM

VM workshop incursadditional cost

Difficulty inconducting analysis andevaluation of functions

Lack of time toconduct VM studies

Tanko, Khiyon and Flanagan

565

found to have met satisfactory thresholds on all of the statistical parameters for a model fit. The statistics revealed a p-value of 0.000, CFI value of 0.93, GFI, 0.89, χ2/df value of 3.65, and RMSEA value of 0.088. Hence, the tested latent factors of the barriers have been verified by the analysis of results.

Figure 2. Measurement model for barriers to VM application

Figure 3. Structural model for barriers to VM application

CONCLUSION AND RECOMMENDATIONS

The study revealed the barriers to VM application in order to establish the impediments to VM practice in the construction industry. The critical barriers are: lack of VM experts; lack of awareness on VM among clients; poor collaboration and

Tanko, Khiyon and Flanagan

566

working relationship among stakeholders; stakeholder’s resistance to accept new innovations; lack of willingness to accept new changes in the construction industry; inadequate facilitation skills and training; lack of active involvement of clients and stakeholders in a VM workshop; absence of local VM guidelines; lack of encouragement on the part of government; difficulty in the involvement of decision makers and other key partners in VM workshop. It was discovered that the people-related factor (lack of VM experts, poor collaboration, lack of awareness/knowledge on VM, inadequate facilitation skills) which ranked top by the Nigerian construction professionals is supported by the findings of Li and Ma (2012), AI-Yami (2008), Ojoko et al. (2016), and Kissi et al. (2015); inferring that trained VM experts are essential for the implementation of VM in the Nigerian construction industry in order to optimize the value of construction projects.

Based on the findings of this study, the following recommendations are made:

I. VM experts are needed for the successful implementation of VM in the Nigerian construction industry.

II. There is a dare need to familiarise both public and private clients on the potential and benefits of applying VM in construction projects.

III. Effective communication and co-operation among construction professionals, clients, contractors, government agencies, and other stakeholders would support the actualisation of VM implementation in Nigerian construction projects.

IV. Stakeholders must be ready and willing to welcome and adopt new value-added innovations and ideas so as to promote VM.

V. Construction professionals should be adequately trained in VM. VI. Active participation of clients and other participants will stimulate successful

implementation of VM in the construction industry. VII. Government and top management play the leading role in terms of policy

initiation, strategy development, and the implementation of strategies and policies. Therefore, the implementation of VM guidelines as well as government support are central to VM application.

VIII. The participation and decision making ability of government and other associates in the realm of VM would uphold the implementation of the technique in Nigerian construction projects.

In general, it is vital to note that the “people” and “government” related factors posed a major hindrance to VM application in the Nigerian construction environment. Therefore, the need to remedy the identified barriers should be given high priority so as to improve the value of Nigerian construction projects without sacrificing any performance standard.

REFERENCES

Abdullah, F., Chiet, C. V., Anuar, K., and Shen, T.T. (2004). An Overview on the Growth and Development of the Malaysian Construction Industry Workshop on Construction Contract Management 2004, Universiti Teknologi Malaysia.

Tanko, Khiyon and Flanagan

567

Akinpelu, A. (2016). Value Engineering/Management in Construction Project Implementation, Monitoring and Evaluation in Nigeria. NIQS Workshop: Budgeting & Capital Project Monitoring and Evaluation in an Era of Change, 1-17. Retrieved from niqs.org.ng/wp.../NIQS-WKSHOp-budgeting-capital-project-monitoring-evaluat.pdf August 30, 2017.

AI-Yami, A. (2008). An Integrated Approach to Value Management and Sustainable Construction during Strategic Briefing in Saudi Construction Projects. PhD Thesis, Loughborough University.

Awang, Z., Afthanorhan, A. and Asri, M.A.M. (2015). Parametric and Non Parametric Approach in Structural Equation Modeling (SEM): The Application of Bootstrapping. Modern Applied Science, 9(9), 58-67.

Cheah, C.Y.J. and Ting, S.K. (2005). Appraisal of Value Engineering in Construction in Southeast Asia. International Journal of Project Management, 23(2), 151-158.

Dim, N.U. and Ezeabasili, A.C.C. (2015). Strategic Supply Chain Framework as an Effective Approach to Procurement of Public Construction Projects in Nigeria. International Journal of Management and Sustainability, 4(7), 163-172.

Enegbuma, W.I., Aliagha, G.U. and Ali, K.N. (2015). Effects of Perceptions on BIM Adoption in Malaysian Construction Industry. Jurnal Teknologi, 77(15), 69–75.

Fan, S., Shen, Q., Luo, X., and Xue, X. (2013). Comparative Study of Traditional and Group Decision Support-Supported Value Management Workshops. J. Manage. Eng., 10.1061/(ASCE) ME.1943-5479 .0000151, 345–354.

Hair, J.F., Anderson, R.E., Tatham, R.L. and Black, W.C. (2008). Multivariate Data Analysis, 7th edition. Upper Saddle River, New Jersey: Prentice Hall Publisher.

Hwang, B. G., Zhao, X., and Toh, L. P. (2014). Risk Management in Small Construction Projects in Singapore: Status, Barriers and Impact. Int. J. Project Manage., 32(1), 116–124.

Jaapar, A., Endut, I. R., and Bari, N.A.A. (2009). The Impact of Value Management Implementation in Malaysia. Journal of Sustainable Development, 2(2), 210-219.

Jaapar, A., Maznan, N.A., and Zawawi, M. (2012). Implementation of Value Management in Public Projects. Procedia-Social and Behavioral Sciences, 68, odeyinka77-86.

Kelly, J., Male, S. and Graham, D. (2004). Value Management of Construction Projects. Malden, USA: Blackwell Science Ltd.

Kissi, E., Boateng, E. B. and Adjei-Kumi, T. (2015). Strategies for Implementing Value Management in the Construction Industry of Ghana. Proceedings of the DII-2015 Conference on Infrastructure Development and Investment Strategies for Africa, pp. 255–267.

Kolo, B.A. and Ibrahim, A.D. (2010). Value Management: How Adoptable is it in the Nigerian Construction Industry? In: Laryea, S., Leiringer, R. And Hughes, W. (Eds) Conference Proceedings of West Africa Built Environment, 653-663.

Lai, N.K. (2006). Value Management in Construction Industry. MSc dissertation, Technology University Malaysia.

Leung, M.Y and Kong, S.S. (2008). Identifying Key Competencies of VM Facilitators based on International Standards. International Value Management Conference. Hong Kong.

Tanko, Khiyon and Flanagan

568

Li, X. and Ma, W. (2012). Appraisal of Value Engineering Application to Construction Industry in China. Y.Zang (Ed.): Future Wireless Networks and Information Systems, LNEE 144: 303-311.

Luvara, V.G.M. and Mwemezi, B. (2017). Obstacles Against Value Management Practice in Building Projects of DuresSalaam Tanzania. International Journal of Construction Engineering and Management, 6(1), 13-21.

Majid, M. and McCaffer, R. (1997). Assessment of Work Performance of Maintenance Contractors in Saudi Arabia. Journal of Management in Engineering, 13(5), 91–91.

Mohd Rahim, F.A., Muzafar, S.A., Zakaria, N., Zainon, N., and Johari, P.A. (2016). Implementation of Life Cycle Costing in Enhancing Value-for-money of Projects. International Journal of Property Science, 6(1), 39- 48.

Odeyinka, H. A. (2006). The Role of Quantity Surveyor in Value Management. 22nd Biennial Conference on Quantity Surveying in the 21st Century Agenda for the Future. Nigerian Institute of Quantity Surveyors.

Ojoko, E.O., Tanko, B.L., Jibrin, M., Ojoko, O. and Enegbuma, W.L. (2016). Project Delay Causes and Effects in the Construction Industry. In IGCESH. Proceedings of the 6th International Graduate Conference on Engineering, Science and Humanities, 15th-17th August, 2016, p.221-223.

Oke, A. E. and Ogunsemi, D. R. (2011). Value Management in the Nigerian Construction Industry: Militating Factors and the Perceived Benefits. Second International Conference on Advances in Engineering and Technology, 353-359.

Olawumi, T.O., Akinrata, E.B. and Arijeloye, B.T. (2016). Value Management-Creating Functional Value for Construction Project: An Exploratory Study, World Science News, 54, 40-59.

Ong. H. T. (2004). Quality and Value Management in Construction. In International Conference on Managing Excellence in Construction, China.

Pallant, J. (2005). SPSS Survival Manual: A Step by Step Guide to Data Analysis for Windows (version 12), 2nd edition. Australia: Allen & Unwin.

Ramly, Z.M. and Shen, G. Q. (2012). Value Management in Malaysia: Past, Present and Future. Proceedings of the International Conference on Value Engineering and Management ‘Innovation in value methodology’ 6th-7th December, 2012.The Hong Kong Polytechnic University Hong Kong, 105-110.

Ramly, Z.M., Shen, G.Q. and Yu, A.T.W. (2015). Critical Success Factors for Value Management Workshops in Malaysia. Journal of Management in Engineering, 31, 1-9.

Rangelova, F. and Traykova, M. (2014). Value Management in Construction Industry. First Scientific- Applied conference With International Participation ‘Project Management in Construction’. University of Architecture, Civil Engineering and Geodesy, Sofia, Bulgaria, Europe. 4-5 December, 2014.

Rowley, J. (2014). Designing and Using Research Questionnaires. Management Research Review, 37(3), 308-330.

Sabiu, B.Y. and Agarwal, V.C. (2016). Minimizing the Factors Hindering the Practice of Value Management in the Nigerian Construction Industry. International Journal of Science, Engineering and Technology Research, 5(10), 2974-2978.

Tanko, Khiyon and Flanagan

569

Saifulnizam, M., Coffey, V. and Preece, C.N. (2011). Value Management: An Extension of Quantity Surveying Services in Malaysia. In Christopher, Preece & Syazli, fathi (Eds) International construction Business and Management Symposium. Queensland University of Technology, Brisbane Australia, 2011. Available: http://eprints.qut.edu.au/47073/ Accessed: [2016-01-11].

SAVE International (2007). Value Methodology Standard

SAVE International (2008). Value Management.

Shen, Q. P. (1993). A Knowledge-Based Structure for Implementing Value Management in the Design of Office Buildings. PhD Thesis, Univ. of Salford, Published by the British Library, Document Supply Centre, U.K.

Shen, G.Q. and Yu, A.T. W. (2012). Value Management: Recent Developments and Way Forward. Construction Innovation, 12(3), 264-271.

Tanko, B. L., Abdullah, F., Ramly, Z. M. and Enegbuma, W.I. (2017a). Confirmatory Factor Analysis of Value Management Current Practice in the Nigerian Construction Industry. Journal of Advanced Research in Applied Sciences and Engineering Technology, 9(10), 32-41.

Tanko, B. L., Abdullah, F. and Ramly, Z. M. (2017b). Stakeholders Assessment of Constraints to Project Delivery in the Nigerian Construction Industry. International Journal of Built Environment and Sustainability, 4(1), 56-62.

Tanko, B. L., Abdullah, F. and Ramly, Z. M. (2018a). Benefits of Adopting Value Management to Mitigate the Problems in the Nigerian Construction Industry. Advanced Science Letters, 24, 3818-3822.

Tanko, B. L., Abdullah, F., Ramly, Z. M. and Enegbuma, W.I. (2018b). An Implementation Framework of Value Management in the Nigerian construction industry. Built Environment Project and Asset Management, 8(3), 305-319.

The Institute of Value Management. What is value management? (2008). Available: http://www.ivm.org.uk/what_vm.htm Accessed: [2015-09-13].

Thiry, M. (1997). Value Management Practice. Philadelphia: PMI Publication.

United Nations Report (2015). UN Habitat Report. Available: https://sustainabledevelopment.un.org/ Accessed: [2016-01-12].

Whyte, A. and Cammarano, C. (2012). Value Management in Infrastructure Projects in Western Australia: Techniques and Staging In: Smith, S.D (Ed) Procs 28th Annual ARCOM Conference, 3-5 September 2012, Edinburgh, UK, Association of Researchers in Construction Management, 797-806.

Zhang, X., Mao, X., and AbouRizk, S.M. (2009). Developing a Knowledge Management System for Improved Value Engineering Practices in the Construction Industry. Automation in Construction, 18, 777–789.