evaluation of generation based incentives scheme for wind...
TRANSCRIPT
F. No. 53/15/2016 -WE
Ministry of New & Renewable Energy
Evaluation of Generation Based Incentives Scheme for Wind Power Projects
The GBI scheme was initially introduced in 11th Plan on 17.12.2009 with the
approval of the Cabinet for taking up 4,000 MW in 11th Plan. Under that scheme a GBI of
Rs. 0.50 per kWh with a ceiling of Rs. 0.62 crore per MW was provided to wind power
project. The incentive was to be availed in not less than 4 years and in maximum of 10 years
with an annual ceiling of Rs. 15.5 lakh per MW in first 4 years. IREDA was designated as
the implementing agency for the Scheme. The scheme was further extended for the 12th
Plan
period with increased ceiling of Rs. 1.0 crore per MW. Under GBI scheme over 7000 MW
capacity has already been registered.
2. IREDA has undertaken an evaluation of the GBI Scheme through CRISIL. CRISIL
has submitted its final report on evaluation of the GBI scheme. The report has been placed on
the website of the Ministry for comments/suggestions/views of the stakeholders.
3. The comments/suggestions/views on the GBI evaluation report may please be sent
through email (preferably in word format) by 15 December 2016 to:
Shri J. K. Jethani
Scientist-D
Ministry of New & Renewable Energy
Blcok-14, CGO Complex, Lodhi Road
New Delhi-110003
Tel/Fax- 24362728
Email: [email protected]
INDIAN RENEWABLE
ENERGY DEVELOPMENT
AGENCY
Evaluation of Generation Based Incentive scheme for wind
power projects
Final report
October 2016
2
Table of content
1. Executive summary ............................................................................................................................................ 5
2. Introduction ....................................................................................................................................................... 11
2.1 Background ................................................................................................................................................. 11
2.2 Objective of study ....................................................................................................................................... 11
2.3 Scope of work ............................................................................................................................................. 11
3. Approach and methodology ............................................................................................................................ 13
3.1 Scope of work ............................................................................................................................................. 13
3.2 Our approach .............................................................................................................................................. 14
4. Key considerations ........................................................................................................................................... 15
4.1 Renewable energy in India ......................................................................................................................... 15
4.2 Wind energy in India ................................................................................................................................... 15
4.3 Incentive schemes for wind sector .............................................................................................................. 16
5. Assessment of GBI scheme ............................................................................................................................. 19
5.1 Progress and performance of GBI scheme ................................................................................................ 19
5.1.1 Achievement of objectives ............................................................................................................. 20
5.1.2 Achievement of targets .................................................................................................................. 22
5.1.3 Key constraints .............................................................................................................................. 22
6. Determination of appropriate GBI benefit ...................................................................................................... 23
6.1 Option 1-GBI to wind investors ................................................................................................................... 23
6.1.1 Based on Revenue Neutrality ........................................................................................................ 25
6.1.2 Based on NPV equal to zero ......................................................................................................... 26
6.1.3 Based on Target Equity IRR .......................................................................................................... 26
6.2 Option 2-GBI benefit to discom ................................................................................................................... 27
6.2.1 Eligibility for availing PBI incentive ................................................................................................ 28
6.2.2 Control period of PBI scheme ....................................................................................................... 28
6.2.3 Impact on exchequer ..................................................................................................................... 28
6.2.4 Sale of wind power under competitive bidding (both intra and inter-state sale to discom) ........... 28
6.3 Methodology for determination of GBI incentive for alternate offtake options ............................................ 29
6.3.1 Sale of wind power under repowering scheme ............................................................................. 29
6.3.2 Sale of wind power under wind solar hybrids ................................................................................ 31
6.3.3 Captive Consumption .................................................................................................................... 32
6.3.4 Third Party Sale ............................................................................................................................. 33
3
6.4 Recommendation on Incentive Level and Cap ........................................................................................... 33
7. Assessment of implementation procedure .................................................................................................... 35
8. Other key aspects ............................................................................................................................................. 37
8.1 Impact of GST and DTC ............................................................................................................................. 37
9. Conclusion and recommendations ................................................................................................................. 38
4
Table of figures
Figure 1: Capacity additions and projects registered (MW) under GBI Phase II .......................................................... 6
Figure 2: Three methodologies used for determination of appropriate level of GBI ..................................................... 7
Figure 3: Proposed approach ..................................................................................................................................... 14
Figure 4: Incentive schemes in wind energy .............................................................................................................. 16
Figure 5: Wind installed capacity trend in India .......................................................................................................... 19
Figure 6: Objectives of GBI scheme ........................................................................................................................... 20
Figure 7: Capacity additions and projects registered under GBI ................................................................................ 21
Figure 8: Share of states in projects availing GBI ...................................................................................................... 21
Figure 9: Three methodologies for determination of required GBI ............................................................................. 23
Figure 10: Repowering potential in India .................................................................................................................... 29
List of tables
Table 1: Treatment of GBI benefits .............................................................................................................................. 6
Table 2: Proposed PBI incentive .................................................................................................................................. 8
Table 3: Estimated financial impact on exchequer from PBI scheme under FIT and bidding route .......................... 10
Table 4: Estimated financial impact on exchequer from GBI scheme-Repowering & wind-solar hybrid projects ...... 10
Table 5: Installed power capacity, as on July 30, 2016 .............................................................................................. 15
Table 6: State-wise installed wind power capacity ..................................................................................................... 15
Table 7: Weighted average SERC parameters .......................................................................................................... 24
Table 8: Various parameters used during the calculation .......................................................................................... 24
Table 9: Appropriate level of GBI based on Revenue Neutrality ................................................................................ 25
Table 10: Appropriate level of GBI based on NPV equal to Zero ............................................................................... 26
Table 11: Appropriate level of GBI based on target Equity IRR ................................................................................. 26
Table 12: Proposed PBI incentive under FIT and competitive bidding route ............................................................. 27
Table 13: Estimated financial impact on exchequer ................................................................................................... 28
Table 14: Assumptions for computation of GBI incentive for repowering projects ..................................................... 30
Table 15: Assumptions for computation of GBI incentive for wind-solar hybrid projects ........................................... 31
Table 16: Proposed PBI incentive .............................................................................................................................. 38
5
1. Executive summary
Wind energy is the fastest growing renewable energy source in India. With an installed capacity of close to 28 GW,
it constitutes about 61% of the country’s installed renewable power capacity.
Commercial wind power projects in India are promoted through fiscal and promotional incentives. The main driving
force for initial development of the wind sector has been the provision of 80% accelerated depreciation (AD). Later,
to broaden the investment base through entry of large independent power producers (IPPs) and attract foreign direct
investment (FDI), the Ministry of New and Renewable Energy (MNRE) introduced the Generation Based Incentive
(GBI) scheme in December 2009. The objective of the scheme was to provide level playing field to IPPs and also
promote increased generation and efficiency in installations.
The GBI scheme, which was withdrawn on March 31, 2012, was reintroduced on September 4, 2013 retrospectively,
with the following terms and conditions:
Under phase II of the scheme, GBI is being provided to wind electricity producers @ Rs 0.50 per unit of
electricity fed into the grid for a period of not less than four years and a maximum period of 10 years, with a
cap of Rs 10 million per MW
The total disbursement in a year cannot exceed one-fourth of the maximum limit of the incentive, i.e. Rs 2.5
million per MW per annum during the first four years
The scheme will be applicable for the entire Twelfth Five-Year Plan period, i.e. up to March 2017
With the GBI scheme nearing its deadline of March 31, 2017, the Indian Renewable Energy Development Agency
(IREDA) and MNRE have facilitated this study to evaluate the performance of the GBI scheme, in terms of meeting
its objectives and targets, its impact on the wind power sector, and identifying and addressing any relevant issues.
To conduct this assessment, financial model was prepared for a typical IPP in various states that includes the impact
of variation in FIT in states on financial viability of the wind power project. Beside, a consultative approach has been
used, which comprises discussions with stakeholders, including MNRE, IREDA, developers of wind power projects,
turbine manufacturers and wind associations. Concern of DISCOMs on account of relatively higher cost of wind
power, compliance of RPO, as well as impact on retail tariffs were also factored in.
The key findings from this study are:
Performance of GBI scheme: Although the performance of GBI phase II, in terms of capacity addition, has been
modest, with a total addition of 5,7621 MW as against the target of 15,000 MW, the GBI scheme has had a positive
impact on the wind power sector, and has been appreciated by wind power developers/ investors and other
stakeholders. It remains one of the key incentive that has driven investments in the sector especially from number of
IPPs who are not availing AD benefit but doing project finance.
1 Source: IREDA; as on March 31, 2016
6
Figure 1: Capacity additions and projects registered (MW) under GBI Phase II
In terms of approach, it has rightly set a transition from investment- or capital-linked incentive to outcome- or
generation-linked objective. The scheme has been successful in improving wind capacity utilization factor
(CUF) levels in the country. The same can be observed from increase in normative CUF levels considered
by Regulatory Commissions over the last 5 years such as Maharashtra (CUF increased from 20% to 22%),
Gujarat (CUF increased from 23% to 24.5%) and Karnataka (CUF increased from 24.5% to 26%)
It has lead on improved technology advancement with better hub-height that has eventually lead to higher
generation or performance.
It has also helped in financial closure by providing comfort to lenders of assured cash flow from the central
government. In fact, investors have cited positive impact the GBI scheme has had, in terms of availing
financial closure for wind projects during times when there have been payment delays by utilities.
Factors affecting GBI offtake: Projects registered under the GBI scheme, as a percentage of total wind projects
commissioned, reduced to less than 40% in 2015-16 from a high of 83% in 2012-13.
In Tamil Nadu and Karnataka, investors preferred alternative offtake options, such as group captive /captive/
third-party models, which offer better returns and financial viability of the project. This lowered the percentage
of projects registered under GBI-sale to distribution companies (discoms).
Also impacting GBI offtake is reluctance by discoms in signing fresh power purchase agreements (PPAs) in
key wind states, such as Rajasthan and Maharashtra. This lowered the share of projects under GBI in 2015-
16.
TREATMENT OF GBI BENEFITS- Considering the ultimate objective of GBI scheme is to benefit the end consumers
and also promote investments in wind sector, there are two approaches for treatment of GBI benefit
Table 1: Treatment of GBI benefits
Options GBI Beneficiary Rationale
1 Investor
1) Provide level playing field with AD benefit
2) Compensate for lesser FIT vis-à-vis submitted
cost of generation as well as to overcome
impact on retail tariffs
1410 17021325 1325
290376 986
2098
2012 -13 2013 -14 2014 -15 2015 -2016
Registered under GBI Other projects not registered under GBI
7
Options GBI Beneficiary Rationale
3) To promote quality investments through
adoption of superior technology as well as
higher generation in the wind sector
4) Unfulfilled target of 15000 MW
2 Discom
1) To incentivize discoms to assure that they
execute PPA and move towards non-solar
RPO compliance, thereby helping in increased
capacity addition in the wind sector
2) To compensate discoms for comparatively
higher cost of wind power over APPC cost,
thereby also helping timely payment to the
investors
3) To help in reducing impact on the retail
consumer tariffs.
DETERMINATION OF APPROPRIATE LEVEL OF GBI: The appropriate level of GBI is arrived at considering both
the options-a) GBI offered to investor b) GBI offered to Discom.
a) Option 1- GBI offered to investor
The analysis of appropriate level of GBI has been done through 3 methodologies as shown below.
Figure 2: Three methodologies used for determination of appropriate level of GBI
Revenue neutrality to AD: Revenue neutral GBI has been calculated considering the levelised value of the
total equity cash flow (post tax), thus taking cognizance of the tax benefit of AD for each year. According to
revenue neutrality, the required GBI level is coming to be in the range of Rs 0.51 per unit.
Based on NPV equal to zero: In this second methodology, the required GBI has been calculated based
upon keeping Net Present Value of equity cash flows (post tax) equal to zero. As per this methodology, the
required GBI level is coming to be Rs 0.48 per unit.
Based on target equity IRR: In this third methodology, the required GBI level has been calculated keeping
equity IRR (post tax) is in the range of 14%-16%. As per this methodology, the required GBI level is coming
to be Rs 1.08/kWh, Rs 1.28/kWh and Rs 1.48/kWh for equity IRR of 14%, 15% and 16% respectively.
Repowering Projects: It is suggested to offer GBI benefit for repowered wind projects. Appropriate GBI has been
calculated considering the difference between levellised cost of generation from repowered project and the weighted
average offtake tariff. Accordingly, GBI benefit to investor is coming to be Rs 0.66 per unit.
Determination of required GBI level
Based on Revenue Neutrality to AD
Based on NPV equal to zero
Based on target Equity IRR
8
Wind-Solar hybrid projects: It is suggested to offer GBI benefit for wind solar hybrid projects. Appropriate GBI has
been calculated considering the difference between levellised cost of generation from wind-solar hybrid project and
weighted average offtake tariff. Accordingly, GBI benefit to investor is coming to be Rs 0.61 per unit.
Incentive Cap: It is suggested that there should not be any further annual or overall cap. This has been explained
in the points below.
In case any cap is imposed to the scheme then it will reduce the availability of GBI for the 10 years period
as assumed in the calculation. This, in turn, would lead an increase in overall GBI requirement.
The removal of cap is also supported from one of the objective of the scheme- to incentivize higher generation
efficiency. Annual or overall cap to the scheme would restrict the efficiency by limiting the amount of
generation that would be eligible for GBI. This would be in conflict to the scheme objective itself.
b) Option 2- GBI offered to discom
One of the key challenge faced by the wind sector is lack of non-Solar RPO compliance (including in states with no
wind potential) as well as recently observed reluctance of discoms to procure wind power due to their weak financial
health or due to its potential impact on the retail level tariffs for consumers. Therefore, suitable mechanisms need to
be developed to use GBI to encourage discoms to procure wind power, make timely payments and also prevent
forced backing down of wind power. This procurement incentive may be provided to the DISCOM till such time utilities’
payout for wind power is greater than the marginal cost of conventional power or average power purchase cost as
well as its likely impact on the retail tariffs & its financial health2.
Further, the GBI scheme was launched with an objective to promote generation efficiency in the wind sector when
the sector was struggling with poor efficiency levels, which the GBI scheme has been successful in addressing and
also promoting investment that are through project finance3.
Therefore, there is a need to shift from generation based incentive to a procurement based incentive by incentivizing
utilities to comply with RPO targets including states with lack of RE resources, Accordingly, a suitable procurement-
based incentive (PBI) is structured to help reduce the purchase cost of wind power for states. Such a change will
enhance transparency, facilitate timely payment to generators and ease out the administration of the incentive with
the central government would only need to deal with the discoms than with investors. It is suggested that apart
from wind repowering and wind solar hybrid power projects, which are still in nascent stage of promotion,
conventional wind power sale to utilities (under both FIT as well as competitive route) should be covered
under the PBI scheme i.e. incentive should be offered to utilities rather that wind investors.
Determination of appropriate level of PBI: With the objective to incentivize utilities to meet RPO targets and ensure
timely payments to investors, the appropriate level of achievement-linked PBI is arrived by computing the difference
between lowest cost of wind generation (lowest wind feed-in-tariff (FIT) of Rs 4.16/kWh) and national average power
procurement cost (Rs 3.40/kWh4). Therefore, an achievement-linked PBI is proposed to be offered to utilities, based
on the following achievement levels:
Table 2: Proposed PBI incentive
S. no. Achievement vis-à-vis state wind targets (MW) specified by MNRE Procurement-based incentive
1 85% and above (till 2017-18) 75 paisa/kWh
2 Below 85% and up to 60% (till 2017-18) 50 paisa/kWh
3 Below 60% (till 2017-18) 25 paisa/kWh
2 Financial health is likely to improve by 2019-20 post implementation of UDAY scheme and its operational targets and benefits 3 The same can be observed from increase in normative CUF levels considered by Regulatory Commissions over the last 5 years such as
Maharashtra (CUF increased from 20% to 22%), Gujarat (CUF increased from 23% to 24.5%), and Karnataka (CUF increased from 24.5% to 26%)
4 http://www.cercind.gov.in/2015/orders/SO15.pdf
9
In order to capture inflation cost under national level average power procurement cost, PBI incentive will be computed
on an annual basis. A multiplier (APPC n-1/APPC n) will be computed, based on Central Electricity Regulatory
Commission (CERC) computation of national level average power procurement cost each year. For e.g., in case
CERC determines average cost of power procurement as Rs 3.60/kWh, the multiplier will be 0.94, i.e. 3.40/3.60.
Accordingly, the PBI incentive will be 0.71 for 2018-19 (0.94 multiplied by 0.75 under the first performance category.
Eligibility criteria: The PBI incentive should be offered under both procurement modes, i.e. procurement under FIT
route, and procurement through competitive bidding route. Further, all new wind projects, including standalone wind
projects, wind-solar hybrids and repowering projects, should be eligible under the scheme.
The payment of PBI incentive to utilities will be built in, with following pre-conditions:
Utilities should clear pending invoices for wind power projects to be eligible
Utilities should submit documentary evidence for timely payment to wind generators, along with the PBI claim
application, monthly
Moreover it is clarified that the PBI incentive should not be monetized by utilities and banks for financing
purpose
Control period for PBI scheme: It is suggested that the PBI scheme will be applicable for a period of 3 years i.e.
till 2019-20, with an incremental wind capacity target of 15 GW. Further, such PBI incentive will be paid for a period
of 5 years for the contracted capacity. It is expected that the utilities financial and operational health will significantly
improve within the next 3 year period with the help various government initiatives including implementation of UDAY
scheme. The scheme will be reviewed after a period of 3 years and re-evaluated depending on RPO targets met,
utilities financial situation etc.
Inclusion of competitive bidding route (both intra and inter-state sale) under the PBI/GBI scheme: With
Ministry notifying guidelines for introduction of competitive bidding for procurement of 1000 MW wind projects by non-
windy states, it is important to evaluate the need for GBI under competitive bidding route. Considering the fact that
under competitive mode, the distribution company is the end procurement party, it is suggested that GBI/PBI scheme
should be applicable under competitive bidding mode also. Therefore, along with offering PBI incentive to utilities
under FIT regime, similar PBI incentive should be offered to procuring utility under competitive bidding route.
Captive consumption and Third party sale: It is suggested to continue third party sale as ineligible for GBI scheme
as the generators would be selling this power at higher/ appropriate tariffs, and thus making considerable/ reasonable
profits.
Summary of Treatment of GBI/PBI scheme
Under FIT and competitive bidding route-PBI incentive to be offered to procuring discoms based on table
2 above (both under FIT as well as competitive bidding route).
Under repowering and wind solar hybrid power projects-GBI payment to be given to wind investor
o For repowering projects-GBI incentive is worked out at Rs 0.66 per unit
o For wind-solar hybrid projects- GBI incentive is worked out at Rs 0.61 per unit
Captive and third party sale-Continue to remain ineligible under GBI/PBI scheme
Impact on exchequer: The financial impact of the PBI scheme on the exchequer will depend on actual performance
of utilities, in terms of compliance with wind targets. Under base case of 100% compliance, the cumulative financial
impact is estimated at Rs 10276 crore.
10
Table 3: Estimated financial impact on exchequer from PBI scheme under FIT and bidding route
2017-18 2018-19 2019-20
Proposed wind capacity targets under PBI scheme (MW) 4000 5000 6000
Expected generation per year (MU)*-(A) 7709 9636 11563
cumulative generation (MU) 7709 17345 28908
PBI incentive (Rs/kWh)**-(B) 0.75 0.71 0.68
Estimated PBI (Rs crore) for a 5 year period (A x B x 5/10) 2891 3445 3940
Cumulative PBI (Rs crore) 10276
(*assuming 22% CUF level and ** considering 100% compliance with estimated increase in APPC cost at 4.91% (based on
historical CAGR for WPI from 2004-05 to 2015-16I)-actual PBI incentive will depend on actual compliance and actual APPC cost
for particular year))
In addition to the above, the financial impact of offering GBI incentive to wind repowering and wind-solar hybrid
projects with a target of 3000 MW (1500 MW each under both wind repowering and wind-solar hybrids) over the next
3 years under both categories and for a period of 10 years is estimated at Rs 3670 crore
Table 4: Estimated financial impact on exchequer from GBI scheme-Repowering & wind-solar hybrid projects
2017-18 2018-19 2019-20
Proposed wind capacity targets under GBI scheme (MW) 1000 1000 1000
Expected generation (MU) per year*-(A) 1927 1927 1927
GBI incentive (Rs/kWh)**-B 0.635 0.635 0.635
Estimated GBI (Rs crore) for a 10 year period (A x B x 10/10) 1224 1224 1224
Cumulative PBI (Rs crore) 3670
(*assuming 22% CUF level and ** considering average GBI benefit of Rs 0.635 for wind repowering and wind-solar hybrid projects)
Implementation procedures:
Separate payment pool for PBI-While IREDA allows monthly claim of GBI benefit, there have been
instances of delay in release of GBI claims to developers, mostly due to non-availability of funds from MNRE.
In order to prevent delay in disbursal of PBI, it is suggested that MNRE should create a separate pool of
amount equivalent to targeted annual PBI payments, and the amount should be monitored and budgeted
annually.
Execution of PPA as a pre-condition for availing GBI payments- The GBI scheme currently makes it
mandatory for wind power projects to register with IREDA within 6 months of commissioning, to be eligible
to avail GBI. To register on GBI web portal, it is desirable that signed PPA is available with the applicant.
However, the applicant will be allowed to register on GBI web portal pending signing of PPA subject to
condition that they shall be eligible to claim GBI only after signing of PPA. Considering the fact there have
been issues related to delays in execution of PPA even after project commissioning in state like Maharashtra,
such projects are not eligible under the present guidelines. It is suggested that such projects where the
project is commissioned but PPA with state utility for sale of power under preferential tariff has not been
signed due to any unforeseen reasons should be allowed to avail GBI benefit from the commissioning date
and not PPA execution date.
Implementation procedure for PBI payments to utilities-It is suggested that existing procedure followed
under the existing GBI scheme for small solar and solar rooftops systems (RPSSGP) should be followed
under the PBI scheme for wind projects as well subject to eligibility criteria discussed above.
11
2. Introduction
Wind energy is one of the fastest growing segments in the renewable energy space. The growth and development
in wind energy has been possible because of the support of the central and state governments, in the form of
promotional and fiscal incentives. Generation Based Incentive (GBI) is one such scheme launched in late 2009 by
the Centre to encourage the participation of IPPs and foreign investors in the wind energy sector. The term for phase
II of the GBI scheme, which was reintroduced in September 2013, will end on March 31, 2017, and a decision is to
be taken on whether it should be continued and any modifications or changes be brought into it. For this purpose,
CRISIL Risk and Infrastructure Solutions Ltd has been appointed to evaluate the GBI scheme for wind power projects.
2.1 Background
Energy is the basic requirement of an economy. For a developing country like India, energy assumes significance as
it is required not just for economic development but also for social development.
Since the past few decades, the country has witnessed rapid industrialization, urbanization, growth in per capita
consumption and increased access to energy, which has increased the demand and consumption of energy.
Currently, India’s energy requirement is largely met through fossil fuels, such as coal, oil and natural gas. But,
considering the issues associated with the use of fossil fuels, such as fuel shortages, rising prices and environmental
impact, the question is being raised as to whether the use of fossil fuels for meeting energy requirements is
sustainable in the long run.
For energy security and long term sustainability it is essential to promote renewable energy sources, such as wind,
solar, biomass and industrial/urban waste.
2.2 Objective of study
The response of phase II of the GBI scheme has been modest. About 5,700 MW has been registered with the IREDA
under the scheme, which is considerably below the target of 15,000 MW set in the Twelfth Five-Year Plan. The major
issues that have been raised by stakeholders with respect to limited offtake under the scheme are:
Need to promote alternate business models: There is a need to promote alternate power sale options,
including repowering, wind-solar hybrid and inter-state sale power
Need to include competitive bidding: With MNRE launching competitive bidding for 1,000 MW wind
projects, it is suggested to also include wind procurement under competitive bidding under the scheme
GBI as a tool to encourage discoms to procure wind power: The biggest challenge facing the sector is
the reluctance of discoms to procure wind power due to their weak financials. Therefore, a suitable
mechanism needs to be put in place to use GBI as a tool encourage discoms to procure wind power and
make timely payments
2.3 Scope of work
Assess the performance of the GBI scheme and its impact on the sector
Interact with stakeholders, including MNRE/IREDA, state nodal agencies/utilities, developers, manufacturers
of wind turbines and their associations, CERC/ state electricity regulatory commissions (SERCs),
government departments and any other organisation, in consultation with MNRE/IREDA, and take
feedback/suggestions on the scheme
Assess implementing procedures of the scheme and guidelines followed, and suggest modifications to the
process
12
Evaluate whether to continue with the scheme or recommend alternatives beyond the Twelfth Five-Year
Plan, taking into consideration factors such as technology development for higher CUF, cost of financing,
cash flow, other fiscal and financial incentives provided by central/state governments, as well as impact of
the likely introduction of goods and services tax (GST) and direct tax code (DTC)
Suggest modalities to continue the scheme beyond the Twelfth Five-Year Plan, considering the different
types of projects, including captive, open access, repowering, hybrid, inter-state sale, projects selling power
at FIT and projects selected through the bidding process
13
3. Approach and methodology
The objective of this study is to assess the performance of the projects registered under GBI, issues pertaining to implementation of the scheme,
and recommend modifications/changes to the scheme..
3.1 Scope of work
The objective of the study is to comprehensively evaluate the performance of projects registered under the GBI
scheme, identify issues with regards to its implementation, recommend any modifications/changes, and study the
impact of the scheme on the wind energy sector.
Therefore, our understanding of each of the components of the scope of work is:
Assess performance of the GBI scheme and recommend whether it should be continued
‒ Assess impact of GBI scheme on wind energy during Twelfth Five-Year Plan
‒ Interact and discuss with MNRE, project developers and associations on the importance of the GBI scheme
for the wind sector, going forward
Assess implementation procedure and guidelines of the scheme and suggest modifications/ changes
‒ Assess barriers and constraints in implementation of the scheme and suggest remedial measures
‒ IREDA is the implementing authority for the GBI scheme. We will hold discussions with IREDA officials as
well as wind developers to understand issues or constraints faced in implementation of the scheme during
the Twelfth Plan
‒ We would also review guidelines/ procedures of the scheme, and based on our understanding from
discussions with IREDA officials as well as beneficiaries of the scheme (wind power developers), we would
suggest necessary modifications/ changes to effectively implement the scheme
Assess adequacy or inadequacy of benefits under scheme
‒ The scheme was introduced as mutually exclusive to the accelerated depreciation (AD) provision. Therefore,
it is essential that the incentive provided under the scheme is equivalent to that under the AD provision
o We would, therefore, compare fiscal benefits available under GBI scheme vis-à-vis AD scheme using a
scenario analysis to arrive at adequacy or inadequacy of the GBI scheme
‒ Evaluate the scheme, with respect to new business models such as group captive/ third party/
repowering/competitive bidding/inter-state sale
‒ The ‘scenario analysis’ would be further distilled to determine whether:
o Current incentive of Rs 0.50 per unit needs to be increased
o Cap of Rs 10 million per MW needs to be raised or removed
Impact assessment of introduction of DTC and GST on wind power sector, and on GBI scheme and
its continuation
‒ We will undertake impact assessment of introduction of GST and DTC on the financials of a typical wind
power project
‒ Findings of the impact assessment will be put forward along with recommendations, in form of an interim
report to stakeholders for comments and/or suggestions
14
3.2 Our approach
Adopt a consultative process
Long term techno-economic viability and reliability of the study to ensure sustainability
Build up scenarios to assess GBI scheme vis-à-vis other fiscal benefits
Suitably incorporate stakeholders’ feedback to provide the most optimal solutions
Figure 3: Proposed approach
Stakeholder interaction
Treatment of GBI scheme
GBI vis-à-vis required tariff
Likely impact of DTC & GST
Review of GBI implementing procedures
Treatment for repowering/hybrid/captive/ third-party/inter-state and
competitive bidding projects
How effective has
been GBI scheme?
Whether GBI scheme
needs to be
continued?
If yes, for what
period?
What should be
adequate level of
GBI?
Whether captive
consumption should
be included?
GBI framework for
new business models
like
hybrid/repowering/
competitive bidding,
etc
What should be
Evaluation of GBI
scheme
15
4. Key considerations
Wind energy is one of the fastest growing segments in the renewable energy space, comprising almost 61% share in the space. This section
captures growth of the renewable energy sector and wind energy in particular; and the facilitators.
4.1 Renewable energy in India
India has huge potential for generating electricity from renewable sources. Development of renewable energy can
become an important catalyst for regional economic development. Also, many states that have rich renewable energy
potential lag in economic development. Developing renewable energy in these states can provide secure power
supply, thereby fostering industrial development, attracting investment and creating employment opportunities.
As per a Central Electricity Authority (CEA) report, as on July 2016, of a total installed power capacity of 304 GW,
the share of grid-connected renewable power capacity was 44 GW, which translates into approximately 14% of total
installed capacity.
Table 5: Installed power capacity, as on July 30, 2016
Sr. no Fuel Capacity (GW) % of total
1. Coal 186.29 61%
2. Gas 24.64 8%
3. Diesel 0.91 0.30%
4. Hydro 42.88 14%
5. Nuclear 5.78 2%
6 Renewable 44.23 15%
Total 304.76 100%
Source: CEA
Further, as per a recent study on renewable energy potential in India, it has emerged that there exists a huge
opportunity to further develop grid interactive renewable energy sources. The wind potential itself is estimated at 302
GW at 100m hub height.
India has projected an ambitious renewable capacity addition target of 175 GW by 2021-22, out of which 60 GW is
from wind power. This translates to annual wind capacity targets of 5 GW. Considering that the highest wind capacity
that has been added in a year is 3.4 GW, the 60 GW target is ambitious.
Meeting the target would require considerable government support, in terms of policies/regulations and fiscal
incentives.
4.2 Wind energy in India
Wind energy is an important source of renewable energy. As on September 30, 2016, the installed wind power
capacity was about 28 GW, accounting for approximately 61% of the installed renewable energy capacity. Globally,
India ranks fourth in terms of the installed wind power capacity, behind China, the US and Germany.
Table 6: State-wise installed wind power capacity
Sr. no State Gross estimated potential (MW) Installed capacity (MW) Potential utilised
1. Andhra Pradesh 44229 1431 3.24%
2. Gujarat 84431 3948 4.68%
3. Karnataka 55857 2869 5.14%
4. Kerala 1700 43 2.53%
16
Sr. no State Gross estimated potential (MW) Installed capacity (MW) Potential utilised
5. Madhya Pradesh 10484 2141 20.42%
6. Maharashtra 45394 4653 10.25%
7. Rajasthan 18770 3993 21.27%
8. Tamil Nadu 33800 7613 22.52%
9. Telangana 4244 77 1.81%
10. Others 3342 4 0.12%
Total 302251 26777 8.86%
Source: MNRE as on March 31, 2016
However, as shown in the above table, all states are yet to realise even half of the estimated wind potential. Tamil
Nadu, Rajasthan, Madhya Pradesh and Maharashtra are the only states that have realised over 10% of their
estimated wind potential.
4.3 Incentive schemes for wind sector
Wind energy dominates the renewable energy sector because of continued support of incentive schemes of state
governments, and regulatory support from CERC and SERCs.
Figure 4: Incentive schemes in wind energy
Central government
schemes
Accelerated depreciation
Income tax holiday
Concessional customs duty
Generation based
incentive
Regulatory interventions
CERC and SERC tariff
policy
Renewable purchase
obligations
Renewable energy
certificates
State government schemes
Sales tax benefit and
capital subsidy
Other state-specific benefits
17
Central government schemes
Accelerated depreciation
The major fiscal incentive offered by the Centre has been the provision of accelerated depreciation (AD) on plant and
machinery. While wind power projects enjoyed 80% AD of gross block (as tax deductible expenditure) in the first year
of installation of a project till 2015, it was reduced to 40% in Union Budget 2015-16.
Tax shelter from AD benefit has been one of the major contributors in improving attractiveness of wind projects. This
is apparent from the fact that this incentive has resulted in attracting sizeable private investment in the sector, and
about 70% of wind energy capacity has been installed through balance sheet financing.
Income tax holiday
Developers of wind power projects are exempt from paying corporate tax for 10 years under Section 80 IA of the
Income Tax Act. However, the income tax holiday has a sunset date of March 31, 2017.
Concessional customs duty
The government provides duty exemption on certain wind-related equipment parts in the form of concessional rates
of duties/taxes, such as customs duty, excise duty, central sales tax and general sales tax.
Generation Based Incentive
In December 2009, the MNRE announced GBI for wind power producers feeding their power into the grid. Under this
scheme, the government earmarked subsidies by way of GBI to the tune of Rs 3.8 billion. During the first phase, GBI
was made applicable to projects of up to 4,000 MW and commissioned till March 31, 2012.
The GBI scheme was reintroduced on September 4, 2013 retrospectively, with the following terms and conditions:
Under phase II of the scheme, GBI is being provided to wind electricity producers @ Rs 0.50 per unit of
electricity fed into the grid for a period of not less than four years and a maximum period of 10 years, with a
cap of Rs 10 million per MW
The total disbursement in a year cannot exceed one-fourth of the maximum limit of the incentive, i.e. Rs 2.5
million per MW per annum during the first four years
The scheme will be applicable for the entire Twelfth Five-Year Plan, with a target of 15,000 MW
‒ As on April 2016, 5,762 MW were registered under the reinstated GBI-Phase II scheme
The scheme is being implemented by IREDA, a financial institution under the administrative control of MNRE
The incentives of AD and GBI are mutually exclusive till the end of the Twelfth Five-Year Plan. All wind power
producers (whether availing AD or GBI) are required to be registered with the IREDA. Upon registration, the
IREDA provides each wind power producer with a unique identification number, which is used to claim GBI
and also for monitoring the performance of projects with respect of quantity of electricity fed into the grid
The existing system followed by state utilities for data collection of electricity generation for the purpose of
disbursal of tariff is being followed as the basis for disbursal of GBI. Investors are required to furnish
documentary proof that no AD has been availed by them
The overall objectives of the GBI scheme are, therefore:
To broaden the investor base and create a level playing field among classes of investors
To incentivise higher efficiencies with the help of generation/outcome-based incentives
To facilitate entry of large independent power producers and foreign direct investors
18
Regulatory interventions
CERC and SERC tariff policy
CERC determines the tariff for generating companies owned or controlled by the central government. The SERC
determines the tariff for generating companies in the respective states, following a cost plus approach. Preferential
tariffs are fixed for renewable energy developers, based on their cost of generation and reasonable investment return
requirement.
Renewable purchase obligation
Renewable purchase obligation (RPO) is set at the state level by the respective SERC. RPO requires that utilities
purchase a certain percentage of their overall power purchase from renewable energy sources. Currently, almost all
states have specified the RPO, which is 1-11%. Various methodologies have been used by the SERCs to determine
the RPO.
There is wide divergence in the way the states have specified RPOs. In most states, on-year RPO targets have been
specified; whereas in some of the states, technology/ renewable energy source-related targets have been specified.
Moreover, there has been limited non-solar RPO compliance by states that have limited wind potential.
Renewable energy certificates
In January 2010, the CERC issued a notification on ‘Terms and Conditions for Recognition and Issuance of
Renewable Energy Certificate for Renewable Energy Generation’. Renewable energy certificate (REC) seeks to
address the mismatch between availability of renewable sources and requirement of the obligated entities to meet
their RPOs. It allows certificate holders to sell renewable energy to states deficient on this front; individual or other
trading entities are expected to stimulate competition and create a market for renewable power across states. The
National Load Dispatch Centre is the central agency for implementation of RECs.
State government schemes
Sales tax benefit and capital subsidy
Capital subsidy and exemption from payment of sales tax are some of the special incentives introduced by state
governments to encourage private investors to set up wind power projects in the states. Developers of wind power
projects were able to recoup the entire capital cost owing to exemption from sales tax along with the tax shelter
through AD. Therefore, the projects were financially viable (with limited generation) and attractive for investors
(especially balance sheet investors).
Other state-specific benefits
Apart from sales tax benefit and capital subsidy, some specific benefits are also provided by state governments to
wind power developers, such as wheeling, open access and electricity duty exemptions.
19
5. Assessment of GBI scheme
This section covers assessment of the GBI scheme, in terms of meeting its objectives, targets and impact on the wind power sector in India.
5.1 Progress and performance of GBI scheme
The driving force until 2009 for development of the wind sector was the provision of accelerated depreciation (AD),
which enabled large profit-making companies, small investor and captive users to participate in the sector. The key
objective for introducing the GBI scheme was to attract investments by IPPs and FDIs who cannot avail AD benefits,
and to improve generation efficiencies. GBI aims to shift the yardstick of incentives from tax-induced capital
investment to productivity-linked revenue enhancement.
The pilot GBI in June 2008 received overwhelming response, with over 300 MW of projects applying for the 49 MW
scheme. Taking this as a positive sign, the government launched the scheme in December 2009, enlarging the size
to 4,000 MW. The target was increased to 15,000 MW when the GBI scheme was re-launched in 2013. This saw
wind power installation rising sharply between 2010 and 2012 and then from 2014 to 2016, compared to wind
installation in period prior to 2010.
Figure 5: Wind installed capacity trend in India
Source: MNRE
The positive impact of GBI on the wind sector was corroborated during stakeholder consultations, including sample
survey of projects/ wind power developers; they unanimously stated that the GBI scheme well achieved its objectives.
20
5.1.1 Achievement of objectives
Figure 6: Objectives of GBI scheme
The main objective of the GBI scheme is to provide a framework for transition from an investment-based incentive to
outcome-based incentive, and accordingly to broaden the investor base by facilitating the entry of large IPPs and
attracting FDI; to provide a level playing field among various classes of investors and to incentivise higher efficiencies.
The overall objective behind the GBI scheme, i.e. providing incentive equivalent to that of AD and thus to provide a
level playing field between various classes of investors, has been appreciated.
This gets reflected in the fact that the GBI scheme has been helpful in securing investments from IPPs and FDIs
to the tune of 7,993 MW5 out of total new installed capacity addition of 14,939 MW6, i.e. close to 54%. This
has resulted in increasing the share of GBI-based projects to about 30%7 of total wind installed capacity in
India.
This is a positive indicator, and accordingly further investment can be expected from this class of investors. It is a
welcome sign and a precursor to transit from tax-induced capital investment to the productivity-linked revenue
enhancement.
5 Source: IREDA; as on March 31, 2016 6 Source: IREDA and MNRE 7 Source: CRIS analysis (7993 MW out to 26883 MW) March 31, 2016
Broaden investor base
Incentivise actual generation with help of
generation/outcome-based incentive
Facilitate entry of large IPP and FDI to wind sector
21
Figure 7: Capacity additions and projects registered under GBI
Source: IREDA
This further gets substantiated by the fact that projects under the GBI scheme are well dispersed among states.
Figure 8: Share of states in projects availing GBI
Source: IREDA
Various wind power developers/ investors, though, have highlighted that the GBI level of Rs 0.50 per unit is
insufficient to promote wind capacity addition in Tamil Nadu, Gujarat and Karnataka due to unviability of FIT plus GBI
model.
Further, with the GBI scheme being limited to sale to discoms and reluctance shown by discoms such as Rajasthan
and Maharashtra (comprise close to 55% of total GBI registration from 2012 to 2016) offtake, investors are concerned
regarding lack of viable business opportunity under FIT plus GBI model post March 2017.
19%
57%
83%82%
57%
39%
0%
25%
50%
75%
100%
0
1000
2000
3000
4000
2010-11 2011-12 2012-13 2013-14 2014-15 2015-16
Registered under GBI (MW) Other projects not registered under GBI (MW)
Percentage of projects under GBI (%)
14%
12%
6%
10%
27%
28%
2%
AP Gujarat Karnataka MP Maharashtra Rajasthan Tamil Nadu
22
5.1.2 Achievement of targets
MNRE had set a target of maximum 15,000 MW capacity of wind projects to be registered under GBI by the end of
the Twelfth Five-Year Plan; but so far, only 5,762 MW have been registered under the scheme. Thus, the GBI scheme
is significantly behind meeting the target.
As per wind power developers/ investors, the key reason for the shortfall is the inadequate GBI level of Rs 0.50 per
unit, which is not attractive to investors looking to set up projects based on the project finance route in Gujarat,
Karnataka, Madhya Pradesh and Tamil Nadu (post March 2017).
However, it is to be highlighted that, in spite of projects availing GBI being well behind the target, its share in overall
wind capacity addition has risen sharply. The percentage of GBI-based projects in overall wind project installed has
increased from 3% in 2010-11 to 30% at end-2015-16. This indicates that the GBI scheme has gained traction with
investors, and it is expected that this number (capacities availing GBI) would increase substantially in the coming
years, subject to continuation of the scheme.
5.1.3 Key constraints
Based on a sample survey of wind power developers/ investors, the key constraints pertaining to the GBI scheme
are:
Need to promote alternate business models: There is a need to promote alternate power sale options,
including repowering, wind solar hybrid and inter-state sale power under GBI scheme
Need to include competitive bidding route under GBI mechanism: With the Ministry launching
competitive bidding for 1,000 MW wind projects, it is suggested to also include wind procurement under
competitive bidding under GBI scheme
Promoting non-solar RPO compliance: With wind potential limited to 7-8 states in India, there has been
limited non-solar RPO compliance and wind procurement by states having limited wind potential. Therefore,
a suitable mechanism is required to promote inter-state sale of wind power and enable non-solar RPO
compliance
GBI as a tool to encourage discoms to procure wind power: The biggest challenge facing the sector is
reluctance on the part of discoms to procure wind power due to their weak financial health. Therefore, suitable
mechanisms need to be developed to use GBI to encourage discoms to procure wind power and make timely
payments
These constraints/ issues, along with those pertaining to implementation procedures of the GBI scheme, have been
analysed in the subsequent chapters.
23
6. Determination of appropriate GBI benefit
This chapter covers the determination of appropriate level of GBI incentive considering the prevailing project parameters of wind power plants
under various options for treatment of GBI incentive. Further it details out GBI benefit across new business areas such as repowering, sale under
competitive bidding route, wind-solar hybrids etc.
The appropriate level of GBI incentive is computed considering both the options of either offering GBI benefit to
investors or to Discoms.
6.1 Option 1-GBI to wind investors
In order to determine appropriate amount of GBI that is required to incentivize investors, three different methodologies
have been adopted as mentioned below.
Figure 9: Three methodologies for determination of required GBI
Further, in each of the methodology mentioned above, the calculations have been done taking 2 sets of assumptions,
CERC Zones and weighted average SERC norms. These are detailed hereunder.
CERC Zones:
In this case, the calculations have been done for each of the five zones specified by CERC on the basis of annual
mean wind power density (W/m2). The calculation has been based upon all parameters, including capital cost, as per
CERC norms used for tariff determination for wind power plants (CERC Tariff Order dated 30th March 2016 regarding
determination of tariff for various renewable energy sources and applicable for FY2016-17).
SERC parameters:
In this case, calculations have been done on weighted average parameters by considering anticipated state wise
capacity addition in the ratio of their wind potential.
Determination of required GBI
Based on Revenue Neutrality to AD
Based on NPV equal to zero
Based on target Equity IRR
24
Table 7: Weighted average SERC parameters
State
Proportionate capacity addition (in terms of wind potential)
Tariff (Rs/kWh)
PLF Capital cost (Rs lakh/MW)
Tamil Nadu 3807 4.16 27.15% 620
Maharashtra 5113 5.56 22% 608.8
Gujarat 9510 4.19 25% 615
Karnataka 6292 4.5 26.60% 600
Rajasthan 2114 4.46 21% 580
Madhya Pradesh 1181 4.78 23% 575
Andhra Pradesh 4982 4.83 24% 600
Weighted Average 33000 4.59 24% 605.81
The table below shows the various parameters used under the two sets of calculations.
Table 8: Various parameters used during the calculation
General Parameters Units Amount
Tariff Rs/unit SERC-4.59, CERC- 6.6, 6, 5.28, 4.4, 4.13
for Zones- 1, 2, 3, 4 & 5 respectively
Total Project Cost Rs Lakh/MW 605.81 (SERC)
619.81 (Zone-1 to 5)
CUF % 24% (SERC), 20% (Zone-1), 22% (Zone-
2), 25% (Zone-3), 30% (Zone-4), 32%
(Zone-5)
Equity % 30%
Loan % 70%
ROE for 1st 10 years % 16.30%
ROE 11th year onwards % 16.06%
Interest on Loan % 12.76%
Repayment Period Years 10
Moratorium Period Years 0
Life of the project (Years) Years 25
Salvage Value % 10%
IT Depreciation rate % 15%
Depreciation rate for 1st 12 years % 5.83%
Depreciation rate for 12th year
onwards
% 1.34%
Operations Parameters
O&M Expenses for FY 2016-17 Rs. Lakhs 11.24
O&M Escalation (%) % 5.72%
Working Capital requirement
Receivables Months 2
25
O&M Expenses Months 1
Spares % of O&M Cost 15%
Interest rate on WC Borrowing % 13.25%
Interest Cost % 12.76%
Income Tax Benefit
Tax Rate (%) % 30%
Surcharge (%) % 7%
Education Cess (%) % 3%
Effective tax (%) % 33.06%
MAT Rate (%) % 18.50%
Effective tax (%) % 20.39%
Acc. Depreciation (%) % 40% (plus additional 20% in first year)
6.1.1 Based on Revenue Neutrality
The revenue neutrality requirement indicates that the total value of GBI is capped at the equivalence of the tax benefit
in case of accelerated depreciation (AD). Thus the government does not spend/gain any additional revenues in case
of GBI as compared to AD. Revenue neutral GBI has been calculated considering the levelised value of the total
equity cash flow (post tax), thus taking cognizance of the tax benefit of AD for each year.
The table below shows the comparison of required GBI levels based on revenue neutrality to AD, as per both- the
survey as well as the CERC Zones. A key assumption in the analysis is that a project opting for AD route is availing
balance sheet financing wherein the other businesses of the company is in position to absorb the tax benefit due to
accelerated depreciation. On the other hand, a project opting for GBI route is assumed to be availing project financing.
Table 9: Appropriate level of GBI based on Revenue Neutrality
Category GBI for AD neutrality
SERC/CERC Rs per unit
SERC 0.51
CERC
Zone-1 0.64
Zone-2 0.58
Zone-3 0.51
Zone-4 0.43
Zone-5 0.40
The key inferences from the above analysis are:
Based on revenue neutrality to AD, the required level of GBI is coming to be in the range of Rs 0.40 per unit
to Rs 0.64 paisa/unit
26
6.1.2 Based on NPV equal to zero
The NPV of equity cash flow without GBI/AD benefit is coming to be negative Rs 40.38 lakhs which is an unwanted
situation from project viability perspective. Accordingly, in this second methodology, the required GBI has been
calculated based upon keeping NPV equal to zero.
The table below shows the comparison of required GBI levels based on NPV equal to zero, as per both- the SERC
as well as the CERC Zones.
Table 10: Appropriate level of GBI based on NPV equal to Zero
Category Project IRR
(Pre Tax)
Project IRR
(Post Tax)
Equity IRR
(Pre Tax)
Equity IRR
(Post Tax)
NPV GBI
SERC/CERC % % % % Rs Lakhs Rs per unit
SERC 13.73% 12.09% 14.13% 11.26% 0.00 0.48
Zone-1 15.08% 13.24% 16.43% 13.23% 43.18 -
Zone-2 15.08% 13.24% 16.43% 13.23% 43.18 -
Zone-3 15.08% 13.24% 16.43% 13.23% 43.18 -
Zone-4 15.08% 13.24% 16.43% 13.23% 43.18 -
Zone-5 15.08% 13.24% 16.43% 13.23% 43.18 -
GBI required for NPV equal to zero 0.48
The key inferences from the above analysis are:
Based on NPV (of equity cash flows- post tax) equal to zero, the required level of GBI is coming to be Rs
0.48 per unit at SERC level
Even at this GBI level of Rs 0.48 per unit, the equity IRR (post tax) is coming to be 11.26%.
It is to be highlighted here that this value of required GBI (Rs 0.48 per unit) is due to inadequate wind tariffs
in States. This gets substantiated by the fact that there is no requirement of GBI benefit considering CERC
specified tariff and parameters.
6.1.3 Based on Target Equity IRR
In this third methodology for calculating the required level of GBI, the approach of target equity IRR has been used.
The target equity IRR gauges the return to the investor on the equity put into a project. It is to be mentioned here that
in present scenario in India, the investors are generally willing to invest only if the equity IRR (post tax) is in the range
of 14%-16% or higher.
The table below shows the comparison of required GBI levels based on target equity IRR (post tax), as per both-
SERC as well as the CERC Zones.
Table 11: Appropriate level of GBI based on target Equity IRR
Category GBI (Rs per unit) corresponding to Equity IRR
(post tax)
SERC/CERC EIRR-14% EIRR-15% EIRR-16%
SERC 1.08 1.28 1.48
Zone-1 0.23 0.50 0.77
27
Category GBI (Rs per unit) corresponding to Equity IRR
(post tax)
SERC/CERC EIRR-14% EIRR-15% EIRR-16%
Zone-2 0.22 0.45 0.68
Zone-3 0.18 0.40 0.60
Zone-4 0.15 0.33 0.50
Zone-5 0.13 0.30 0.47
As evident from the above table, the required GBI level based on target equity IRR is coming to be higher than those
calculated as per the earlier two methodologies. The required GBI level in this case is in the range Rs 1.08 to Rs
1.48 per unit in case of SERC parameters and Rs 0.13 to Rs 0.77 per unit in case of CERC parameters. Similar to
the earlier methodology, the required GBI level in this case too highlights the inadequacy of wind tariffs in States.
6.2 Option 2-GBI benefit to discom
One of the key challenge faced by the wind sector is lack of non-Solar RPO compliance (including in states with no
wind potential) as well as recently observed reluctance of discoms to procure wind power due to their weak financial
health or due to its potential impact on the retail level tariffs for consumers. Therefore, suitable mechanisms need to
be developed to use GBI to encourage discoms to procure wind power, make timely payments and also prevent
forced backing down of wind power. This procurement incentive may be provided to the DISCOM till such time utilities’
payout for wind power is greater than the marginal cost of conventional power or average power purchase cost as
well as its likely impact on the retail tariffs & its financial health8.
Further, the GBI scheme was launched with an objective to promote generation efficiency in the wind sector when
the sector was struggling with poor efficiency levels, which the GBI scheme has been successful in addressing and
also promoting investment that are through project finance9.
Therefore, there is a need to shift from generation based incentive to a procurement based incentive by incentivizing
utilities to comply with RPO targets including states with lack of RE resources, Accordingly, a suitable procurement-
based incentive (PBI) is structured to help reduce the purchase cost of wind power for states. Such a change will
enhance transparency, facilitate timely payment to generators and ease out the administration of the incentive with
the central government would only need to deal with the discoms than with investors. With the objective to
compensate discoms for the comparatively high cost of wind power over average power purchase cost (APPC cost),
the appropriate level of GBI benefit is arrived at by computing the difference between lowest cost of wind generation
(lowest wind FIT of Rs 4.16/kWh) and national level average power procurement cost (Rs 3.40/kWh10). Therefore,
an achievement-linked PBI is proposed to be offered to utilities, based on the following achievement levels:
Table 12: Proposed PBI incentive under FIT and competitive bidding route
S. no. Achievement vis-à-vis state wind targets (MW) specified by MNRE Procurement-based incentive for 2017-18
1 85% and above (till 2017-18) 75 paisa/kWh
2 Below 85% and up to 60% (till 2017-18) 50 paisa/kWh
3 Below 60% (till 2017-18) 25 paisa/kWh
8 Financial health is likely to improve by 2019-20 post implementation of UDAY scheme and its operational targets and benefits 9 The same can be observed from increase in normative CUF levels considered by Regulatory Commissions over the last 5 years such as
Maharashtra (CUF increased from 20% to 22%), Gujarat (CUF increased from 23% to 24.5%), and Karnataka (CUF increased from 24.5% to 26%)
10 http://www.cercind.gov.in/2015/orders/SO15.pdf
28
In order to capture inflation cost under national level average power procurement cost, PBI incentive will be
computed on an annual basis. A multiplier of APPC n-1/APPC n will be computed, based on CERC computation of
national level average power procurement cost each year. For e.g., in case CERC determines average cost of power
procurement as Rs 3.60/kWh, the multiplier will be 0.94, i.e. 3.40/3.60. Accordingly, the PBI incentive will be Rs 0.71
/kWh for 2018-19 (0.94 multiplied by 0.75) under the first performance category.
6.2.1 Eligibility for availing PBI incentive
The PBI will be offered under both procurement modes, i.e. procurement under FIT route, and procurement through
competitive bidding route. Further, all new wind projects, including standalone wind projects, wind-solar hybrids and
repowering projects, should be eligible under the scheme.
The payment of PBI incentive to discoms will be built in with the following pre-conditions:
Utilities should clear pending invoices for wind power projects to be eligible
Utilities should submit documentary evidence of timely payments to wind generators along with the PBI claim
application on a monthly basis
Moreover it is clarified that the PBI incentive should not be monetized by utilities and banks for financing
purpose
6.2.2 Control period of PBI scheme
The PBI scheme will be operational for a period of 3 years i.e. till FY 2019-20. Such PBI incentive will be paid for a
period of 5 years for the contracted capacity during the control period. It is expected that the utilities financial and
operational health will significantly improve within the next 3 year period with the help various government initiatives
including implementation of UDAY scheme. The scheme will be reviewed after a period of 3 years and re-evaluated
depending on RPO targets met, utilities financial situation etc.
6.2.3 Impact on exchequer
The financial impact of the PBI scheme on the exchequer will depend on actual performance of utilities, in terms of
compliance with wind targets. Under base case of 100% compliance, the cumulative financial impact is estimated at
Rs 10276 crore.
Table 13: Estimated financial impact on exchequer
2017-18 2018-19 2019-20
Proposed wind capacity targets under PBI scheme (MW) 4000 5000 6000
Expected generation per year (MU)*-A 7709 9636 11563
cumulative generation (MU) 7709 17345 28908
PBI incentive (Rs/kWh)**-B 0.75 0.71 0.68
Estimated PBI (Rs crore) for a period of 5 years (A x B x 5/10) 2891 3445 3940
Cumulative PBI (Rs crore) for a period of 5 years 10276
(*assuming 22% CUF level and ** considering 100% compliance and estimated increase in APPC cost at 4.91% (based on
historical CAGR for WPI from 2004-05 to 2015-16)-actual PBI incentive will depend on actual compliance and actual APPC cost
for particular year))
6.2.4 Sale of wind power under competitive bidding (both intra and inter-state sale to
discom)
29
With Ministry notifying guidelines for introduction of competitive bidding for procurement of 1000 MW wind projects
by non-windy states, it is important to evaluate the need for GBI under competitive bidding route. Considering the
fact that under competitive mode, the distribution company is the end procurement party, it is suggested that GBI/PBI
scheme should be applicable under competitive bidding mode also. Therefore, along with offering PBI incentive to
utilities under FIT regime, similar PBI incentive should be offered to procuring utility under competitive bidding route.
Further, the Government of India has projected an ambitious target of 175 GW of renewable energy by 2022
comprising of 60 GW from wind power. While potential of wind power is not a challenge for India, there are concerns
in terms of non-uniform spread of the wind energy potential across states and lack of inter-state wind energy sale.
The launch of renewable Energy Certificates was expected to cater to this limitation, but it has failed in its objective
not only because of lack of RPO enforcement but also due to the fact that consumers/utilities have preferred to buy
renewable energy power rather than buy just renewable energy certificates.
Therefore, both intra as well as inter-state sale to discom under competitive bidding route should be covered under
the PBI scheme i.e. offering incentive to utilities for procuring wind power.
6.3 Methodology for determination of GBI incentive for alternate offtake
options
6.3.1 Sale of wind power under repowering scheme
Most of the wind-turbines installed up to the year 2002 are of capacity below 500 kW and are at sites having high
wind energy potential. It is estimated that over 1500 MW capacity installation are from wind turbines of 500 kW or
below and installed prior to 2002. In order to optimally utilise the wind energy resources repowering is required.
Accordingly, MNRE has notified draft repowering policy for promotion of wind repowering.
Figure 10: Repowering potential in India
As observed from the table above, nearly 56% old turbines installed prior to 2002 were in the state of Tamil Nadu.
Hence in order to evaluate a uniform GBI incentive to be offered to repowering projects we have benchmarked it
against GBI requirement in the state of Tamil Nadu. The assumptions used to arrive at the GBI incentive is tabulated
below:
30
Table 14: Assumptions for computation of GBI incentive for repowering projects
Parameter Unit Assumption
Old WTGs
Capacity MW 10
CUF % 14%
Tariff
FIT during 2002/03 Rs/kWh 2.70
Cost Details
Capital Cost Rs Cr/MW 4.00
Residual Value % of Project Cost 10%
Remaining Life of the Asset years 5 (i.e. 15 years completed)
Repowered Asset
Capacity Details
New MW capacity MW 20
CUF % 28%
Tariff
Preferential Tariff Rs/kWh 4.16
Cost Details
Capital Cost Rs Cr/MW 6.00
Capital Structure
Debt % 70%
Equity % 30%
Financing
Interest Rate % 12%
Repayment Period years 12
Moratorium Period months 6
Return of Equity (Pre-Tax) % 20%
Depreciation
IT Rate % 15%
Book % 5.83%
Tax Rate
MAT Rate % 20.96%
Corporate Tax Rate % 33.99%
Operation & Maintenance
O&M Expense Rs Lakh/MW 11.24
Escalation % 5.72%
Interest on Working Capital
O&M Charges
1
Maintenance Spares
15%
Receivables for Debtors
2
Interest Rate % 12.50%
Levellised cost of generation Rs/kWh 4.46
31
Considering the assumption that power generated corresponding to generation prior to repowering would continue
to be procured on the terms of existing PPA and tariff (i.e. Rs 2.70/kWh in case of TN) and remaining additional
generation would be purchased by Discoms at Feed-in-Tariff applicable in the State at the time of commissioning of
the repowering project, i.e. (Rs 4.16/kWh in case of TN), weighted average FIT of Rs 3.80/kWh for repowered project
(considering generation till 14% CUF is sold at Rs 2.70/kWh and generation above 14% is sold at Rs 4.16/kWh)
The GBI incentive for repowered wind projects of Rs 0.66/kWh is arrived by considering the difference between cost
of generation from repowering project (i.e. Rs 4.46/kWh) and the weighted average feed-in-tariff (i.e. Rs 3.80/kWh)
6.3.2 Sale of wind power under wind solar hybrids
Solar and wind power being infirm in nature impose certain challenges on grid security and stability. Studies revealed
that solar and winds are almost complementary to each other and hybridization of two technologies would help in
minimizing the variability apart from optimally utilizing the infrastructure including land and transmission system.
Considering its advantages, MNRE has notified Draft Wind Solar Hybrid Policy. The Policy aims to encourage new
technologies, methods and way-outs involving combined operation of wind and solar PV plants. Therefore it is
suggested that wind power generated from wind solar hybrid project should be made eligible under GBI scheme.
Table 15: Assumptions for computation of GBI incentive for wind-solar hybrid projects
S. No.
Assumption Head
Sub-Head Sub-Head (2) Unit Tariff Parameter
1
Power Generation
Capacity
Wind to solar capacity ratio 1.5
Wind capacity MW 1.50
Solar capacity MW 1.00
Composite capacity (for Dep, ROE & Interest )
MW 1.50
Wind CUF % 24.50%
Solar CUF % 19.00%
Wind Deration Factor % 0.50%
Solar Deration factor 0.50%
Useful Life Years 25
2 Project Cost
Capital Cost/MW
Power Plant Cost (composite cost for 1.5 MW system)
Rs lakh/MW
950
3 Sources of Fund
Debt: Equity
Debt % 70%
Equity % 30%
Total Debt Amount Rs Lacs 1103
Total Equity Amout Rs Lacs 472.5
Debt Component
32
S. No.
Assumption Head
Sub-Head Sub-Head (2) Unit Tariff Parameter
Loan Amount Rs Lacs 1102.5
Repayment Period Years 10
Interest Rate % 12.00%
Equity Component
Equity amount Rs Lacs 472.5
Return on Equity for first 10 years (pre tax)
% p.a 20%
RoE Period Year 10
Return on Equity 11th year onwards (pre tax)
% p.a 24%
Discount Rate 12.00%
4 Financial Assumptions
Depreciation
Depreciation Rate for first 10 years % 7.00%
Depreciation Rate 11th year onwards % 1.33%
5 Working Capital
O&M Charges
1 month O&M expense Months 1.00
Receivables for Debtors
2 months receivables Months 2.00
Maintenance Spares
15% of O&M expense % 15%
Interest On Working Capital
Interest Rate % 13.0%
6 Operation & Maintenance
power plant (First year)
Considering 1% of total project cost Rs Lakh/MW
10.5
Escalation
Annual escalation % 5.72%
Levellised cost of generation (Rs/kWh) 4.91
Based on the assumption above, the cost of generation from the hybrid projects, works out to Rs 4.91/kWh.
Considering composite tariff of Rs 4.30/kWh (i.e. composite tariff worked out based weighted average tariff of wind
FIT of Rs 4.19/kWh and estimated wind generation of 3.22 MU from 1.5 MW wind project and assumed solar bid
tariff of Rs 4.5/kWh and estimated solar generation of 1.66 MU from 1 MW solar project), the GBI incentive works
out to Rs 0.61/kWh.
6.3.3 Captive Consumption
Currently, the captive consumption of energy generated from wind power plants is not eligible to avail GBI benefit. It
is suggested to continue to be ineligible for GBI scheme as the generators would be selling this power at higher/
appropriate tariffs, and thus making considerable/ reasonable profits.
33
6.3.4 Third Party Sale
Currently, the third party sale of energy generated from wind power plants is not eligible to avail GBI benefit. It is
suggested to continue the third party sale as ineligible for GBI scheme as the generators would be selling this power
at higher/ appropriate tariffs, and thus making considerable/ reasonable profits.
6.4 Recommendation on Incentive Level and Cap
Under Option 1-GBI incentive to investor
The three different methodologies used under Section 6.1 provide the different levels of required GBI. However,
considering the primary objective of GBI scheme to maintain a balance between promoting investments in wind space
and also limiting impact on tariff, it is suggested that GBI incentive level should be considered in a worst case
investment scenario wherein NPV equal to zero. The analysis shows that the present level of GBI (i.e. Rs 0.50 per
unit) is adequate and is close to required level of Rs 0.48/kWh needed under NPC equal to zero scenario.
The calculation of required level of GBI assumes availability of incentive for 10 years. It is thus suggested that there
should not be any further annual or overall cap. This has been explained further in the points below.
The calculation methodology equates the levellised cash flows (post tax) required to make NPV equal to
zero; hence there is no requirement/rationale for any further cap.
In case any cap is imposed to the scheme then it will reduce the availability of GBI for the 10 years period
as assumed in the calculation. This, in turn, would lead to reduced levellised benefit in case of GBI and it
would no longer offer NPV equal to zero.
The removal of cap is also supported from one of the objective of the scheme- to incentivize higher generation
efficiency. Annual or overall cap to the scheme would restrict the efficiency by limiting the amount of
generation that would be eligible for GBI. This would be in conflict to the scheme objective itself.
There has been apprehension that with no annual/ overall cap, wind projects may go for higher CUF with
improved technology and thus it would be entitled for higher incentive quantum. It is to be mentioned here
that if wind power investor opts for better technology (such as newer turbines, higher hub height, etc), it
would lead to increase in capital cost too along with the CUF. Considering these, it would be fair to provide
un-capped incentive to power plants that have opted for higher capital investment so as to get better CUF.
Considering the above mentioned points, it is suggested that there should not be annual or overall cap to the GBI
benefit that can be availed by wind power plant.
Special GBI for wind repowering projects and wind-solar hybrid projects.
Wind Repowering-The GBI incentive level for wind repowering projects is arrived at Rs 0.66/kWh. The calculation
of required level of GBI assumes availability of incentive for 10 years. It is thus suggested that there should not be
any further annual or overall cap due to reasons cited above.
Wind-Solar hybrids- The GBI incentive level for wind-solar hybrid projects is arrived at Rs 0.61/kWh. The calculation
of required level of GBI assumes availability of incentive for complete useful life of 25 years. It is thus suggested that
there should not be any further annual or overall cap due to reasons cited above.
Under Option 2-GBI incentive to discom
34
The appropriate level of GBI benefit in case GBI is offered to discoms is arrived by computing the difference between
lowest cost of wind generation (i.e. lowest wind FIT of Rs 4.16/kWh) and national level average power procurement
cost (Rs 3.40/kWh11). Therefore, appropriate GBI/PBI should be offered to discom based on the performance
levels and meeting the eligibility criteria. The scheme suggested to be applicable for a period of 3 years i.e. April
1, 2020 and under both the scenarios of sale under FIT route and procurement through competitive route. Further,
such payment will be made for a period of 5 years for the eligible projects commissioned during the control period of
3 years.
11 http://www.cercind.gov.in/2015/orders/SO15.pdf
35
7. Assessment of implementation procedure
This section covers assessment of the implementation procedure of the PBI incentive and recommendation pertaining to its improvement.
Based on interactions with wind power developers during the primary survey, it was found that the implementation
procedure of the GBI scheme is efficient as well as simple to follow. Besides, the entire process is web-based, making
it effective, time-saving and minimizes the requirement of hard copy of documents.
Some of the concerns observed under the existing implementation procedures and also raised by stakeholders
include the following:
Separate payment pool for PBI-While IREDA allows monthly claim of GBI benefit, there have been
instances of delay in release of GBI claims to developers, mostly due to non-availability of funds from MNRE.
In order to prevent delay in disbursal of PBI, it is suggested that MNRE should create a separate pool of
36
amount equivalent to targeted annual PBI payments, and the amount should be monitored and budgeted
annually.
Execution of PPA as a pre-condition for availing GBI payments- The GBI scheme currently makes it
mandatory for wind power projects to register with IREDA within 6 months of commissioning, to be eligible
to avail GBI. To register on GBI web portal, it is desirable that signed PPA is available with the applicant.
However, the applicant will be allowed to register on GBI web portal pending signing of PPA subject to
condition that they shall be eligible to claim GBI only after signing of PPA. Considering the fact there have
been issues related to delays in execution of PPA even after project commissioning in state like Maharashtra,
such projects are not eligible under the present guidelines. It is suggested that such projects where the
project is commissioned but PPA with state utility for sale of power under preferential tariff has not been
signed due to any unforeseen reasons should be allowed to avail GBI benefit from the commissioning date
and not PPA execution date.
Implementation procedure for PBI payments to utilities-It is suggested that existing procedure followed
under the existing GBI scheme for small solar and solar rooftops systems (RPSSGP) should be followed
under the PBI scheme for wind projects as well subject to eligibility criteria discussed above.
37
8. Other key aspects
This section is related to implementation of GST and DTC and their likely impact on the country’s wind power sector.
8.1 Impact of GST and DTC
Impact of GST
With the implementation of GST, all other taxes, such as central sales tax, value-added tax (VAT), service tax and
excise duty, will be abolished. The GST framework is more tax efficient, and would reduce cascading impact of sales
tax/VAT.
However, it is likely that GST would have an adverse impact on all renewable energy projects:
Presently, all wind projects are exempted from excise levy. In the GST regime, though, all projects (except
for a few) would be under three broad GST duty regimes - 12%, 16% and 20%
All renewable energy-based projects would have an input GST credit of 16% of the sales price.
As electricity, which is the end product of renewable energy projects, is currently not ‘subsumed’, none of
the renewable energy producers would be able to claim output credit of the GST. In other words, the project
cost would increase 16% in form of GST, against the current excise exemption
‒ Accordingly, the capital cost for wind power projects would increase 16% in the proposed GST regime
Impact of DTC
The government, in an effort to simplify the tax regime, has tabled the Direct Tax Code (DTC) Bill in Parliament. The
government, which has reiterated that it wants to reduce the gap between corporate tax structure and minimum
alternate tax, is working on making structural changes to the existing income tax provisions.
It is to be mentioned here that, Section 80 IA of the prevailing Income Tax Act provides an income tax holiday for 10
years. Also, considering that a fair amount of infrastructure projects were commissioned, the central government has
been extending the Section 80 IA from the past two years. However, the same is set to expire on March 31, 2017,
with no decision on its extension yet.
38
9. Conclusion and recommendations
Conclusion
The GBI scheme is having a positive impact on the wind power sector, and has been well- received by wind
power developers/ investors and other stakeholders.
It has rightly set a transition from investment-linked incentive to outcome/ generation-linked objective, and
has resulted in improvement of wind CUF levels.
Projects totaling 5,763 MW have been registered against the target of 15,000 MW by end of the Twelfth Five-
Year Plan. The shortfall is attributable to lower offtake of wind power by discoms, resulting in lower GBI
registration and low GBI preventing large scale wind capacity addition.
‒ At the same time, the share of GBI-based wind projects is increasing as a percentage of total wind installed
capacity, with the percentage of AD-based projects decreasing; highlighting growing participation in the
scheme.
Based on discussion with stakeholders, the biggest challenge facing the wind sector is reluctance of discoms
to procure wind power due to their struggling finances and the difference between cost of wind generation
and average power purchase cost. Therefore, a suitable mechanism needs to be developed to use GBI as
a tool encourage discoms to procure wind power by suitably incentivising them to move towards RPO
compliance and ensure timely payments.
Recommendations
The biggest challenge facing the wind sector is reluctance of discoms to procure wind power due to their
weak financial health. Therefore, suitable mechanisms need to be developed to use GBI to encourage
discoms to procure wind power, make timely payments and also prevent forced backing down of wind power.
Further, the GBI scheme was launched with an objective to promote generation efficiency in the wind sector
when the sector was struggling with poor efficiency levels, which the GBI scheme has been successful in
addressing and also promoting investment that are through project finance.
However, later there has been delay or reluctance on the part of utilities in signing new PPAs as well as
significant delay in payments to developers. Till such time utilities’ payout for wind power is greater than the
marginal cost of conventional power or average power purchase cost as well as its likely impact on the retail
tariffs & its financial health, utilities remain concerned of sourcing wind power.
Therefore, it is imperative that utilities are incentivized to comply with RPO targets, and a suitable
procurement-based incentive (PBI) is structured to help reduce the purchase cost of wind power for states.
Such a change will enhance transparency, facilitate timely payment to generators and ease out the
administration of the incentive with the central government would only need to deal with the discoms.
Therefore the following mechanism is proposed for GBI scheme beyond 12th plan period
o Under FIT and competitive bidding route (for both intra and inter-state sale)-GBI/PBI payment
to be given to procuring discoms as per table below
Table 16: Proposed PBI incentive
S. no. Achievement vis-à-vis state wind targets (MW) specified by MNRE Procurement-based incentive
1 85% and above (till 2017-18) 75 paisa/kWh
2 Below 85% and up to 60% (till 2017-18) 50 paisa/kWh
3 Below 60% (till 2017-18) 25 paisa/kWh
In order to capture inflation cost under national level average power procurement cost, the PBI
incentive will be computed on an annual basis. A multiplier of APPC n-1/APPC n will be computed,
39
based on CERC computation of national level average power procurement cost each year. Further
the payment of PBI incentive to utilities will be built in, with following pre-conditions:
Utilities should clear pending invoices for wind power projects to be eligible
Utilities should submit documentary evidence for timely payment to wind generators, along
with the PBI claim application, monthly. MNRE reserves the right to reduce PBI/GBI
incentive in case of payment delays.
Moreover it is clarified that the PBI incentive should not be monetized by utilities and banks
for financing purpose
It is suggested that the PBI scheme should be applicable till 2019-20, with an incremental wind
capacity target of 15 GW. Further, such PBI incentive will be paid for a period of 5 years for the
contracted capacity
o Under repowering and wind solar hybrid projects-GBI payment to be given to wind investor
For repowering projects-GBI incentive is worked out at Rs 0.66 per unit
For wind-solar hybrid projects- GBI incentive is worked out at Rs 0.61 per unit
It is suggested that there should not be any further annual or overall cap.
Implementation Procedures-
Delays in GBI payment: While IREDA allows monthly claim of GBI benefit, there have been delays in release
of GBI claims to developers, mostly due to non-availability of funds from MNRE. Separate payment pool for PBI
payments: In order to prevent delays in disbursal of PBI incentive to utilities, it is suggested that MNRE should
create a separate pool of amount equivalent to the estimated targeted annual PBI incentives, and the amount
should be monitored and budgeted annually.
Execution of PPA as a pre-condition for availing GBI payments- The GBI scheme currently makes it
mandatory for wind power projects to register with IREDA within 6 months of commissioning, to be eligible to
avail GBI. To register on GBI web portal, it is desirable that signed PPA is available with the applicant. However,
the applicant will be allowed to register on GBI web portal pending signing of PPA subject to condition that they
shall be eligible to claim GBI only after signing of PPA. Considering the fact there have been issues related to
delays in execution of PPA even after project commissioning in state like Maharashtra, such projects are not
eligible under the present guidelines. It is suggested that such projects where the project is commissioned but
PPA with state utility for sale of power under preferential tariff has not been signed due to any unforeseen reasons
should be allowed to avail GBI benefit from the commissioning date and not PPA execution date.
Argentina | China | Hong Kong | India | Poland | Singapore | UK | USA
CRISIL Risk and Infrastructure Solutions Limited (A subsidiary of CRISIL Limited)
CRISIL House, Central Avenue, Hiranandani Business Park, Powai, Mumbai – 400076. India
Phone: + 91 22 3342 3000 | Fax: + 91 22 3342 3001 | www.crisil.com
About CRISIL
CRISIL is a global analytical company providing ratings, research, and risk and policy advisory services. We are India's leading ratings agency. We are also the foremost provider of high-end research to the world's largest banks and leading corporations.
CRISIL is majority owned by S&P Global Inc., a leading provider of transparent and independent ratings, benchmarks, analytics and data to the capital and commodity markets worldwide.
About CRISIL Infrastructure Advisory
CRISIL Infrastructure Advisory is a leading advisor to regulators and governments, multilateral agencies, investors, and large public and private sector firms. We help shape public policy and enable infrastructure development. Our services span a wide array of infrastructure development activities. Our work in the areas of policy formulation, regulation, design and implementation of public-private partnership (PPP) frameworks and infrastructure financing mechanisms helps create a vibrant ecosystem for infrastructure development. Our services at the project level include bid process management, valuations and due diligence to enable investment decisions. We are known for our core values of independence and analytical rigour combined with deep domain expertise. Our teams have expertise across the complete range of infrastructure sectors - urban development, energy, transport and logistics, natural resources, education, and healthcare. We have a rich understanding of PPP and financing related issues. We operate in India and 22 other emerging economies in Asia, Africa, and the Middle East. CRISIL Infrastructure Advisory is a division of CRISIL Risk and Infrastructure Solutions Limited, a wholly owned subsidiary of CRISIL Limited.
CRISIL Privacy Notice
CRISIL respects your privacy. We use your contact information, such as your name, address, and email id, to fulfil your request and service your account and to provide you with additional information from CRISIL and other parts of S&P Global Inc. and its subsidiaries (collectively, the “Company”) you may find of interest.
For further information, or to let us know your preferences with respect to receiving marketing materials, please visit www.crisil.com/privacy. You can view the Company’s Customer Privacy at https://www.spglobal.com/privacy
Last updated: April 2016
Disclaimer
This report is prepared by CRISIL Risk and Infrastructure Solutions Limited (CRIS). This report may have been prepared by CRIS at the request of a client of CRIS (client). This report may include or refer to information and materials provided by the client and/or obtained by CRIS from sources that CRIS considers reliable (together, “materials”). In preparing this report, CRIS does not independently validate any such materials and assumes those materials are accurate. CRIS does not guarantee the accuracy, adequacy or completeness of any material contained in or referred to in the report. While CRIS takes reasonable care in preparing the report, CRIS shall not be responsible for any errors or omissions in or for the results obtained from the use of or the decisions made based on, the report. The user takes full responsibility for the use of and the decisions made based on the report. While portions of materials are included in the report, CRIS makes all reasonable attempts to attribute credits to the source of the materials; however, even if a particular source of a material is not so attributed, CRIS stakes no claim to any such material in the form as provided to or made accessible to CRIS. No third party whose material is included or referenced in this report under credit to it, assumes any liability towards the user with respect to such material. Neither CRIS nor its directors, employees and representatives accept any liability with regard to any access, use of or reliance on, the report and that CRIS expressly disclaim all such liability. Any third party brands, names or trademarks contained in the report belong to the relevant third parties. The report contains CRIS’ view as at the date of the report based on available material. CRIS does not assume an obligation to update the report where updated materials are available or to notify anyone that an updated report is available. This report may not be reproduced or redistributed or communicated directly or indirectly in any form or published or copied in whole or in part except as authorized by CRIS. Unless CRIS has expressly agreed in writing, this report is not intended for use outside India. By accessing and/or using any part of the report, the user accepts the foregoing disclaimers and exclusion of liability which operates to the benefit