evaluation of how o&m costs vary for alternative flood control strategies€¦ ·  ·...

35
Evaluation of How O&M Costs Vary for Alternative Flood Control Strategies Fargo-Moorhead Diversion Channel ASFPM Conference June 13, 2013 Matt Redington, PE Jeremy Cook HDR Engineering

Upload: nguyenthuy

Post on 21-Apr-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

Evaluation of How O&M Costs Vary for Alternative Flood Control Strategies

Fargo-Moorhead Diversion Channel

ASFPM Conference June 13, 2013

Matt Redington, PE

Jeremy Cook HDR Engineering

Red River of the North Watershed

• Insert map showing Red River Watershed and various states • Get this map from Ted Shannon HMS project

Flood Fighting

• Flood Stage = 18 feet (19 of the past 20 years) • 29 of 90 previous years reached flood

stage • 1997, 2009, 2011, 2013

Fargo and Moorhead

Moorhead, Minnesota Fargo,

North Dakota

Red River

Red River Valley Flooding

Regular Flood Fighting

The Fargo Arena

Diversion Project Features

Channel

Storage

In-Town Improvements • Buyouts • Levees • Interior drainage • Pump stations

Fargo-Moorhead Diversion Channel Is a Monumental Effort

Total Cost: $2 Billion USACE O&M Estimate: $3,559,000

Fargo-Moorhead Diversion Channel O&M Considered in Design

Two Ways O&M Costs Entered Planning: • What are the O&M cost impacts of varying

flood control strategies?

• What are the cost savings for Alternate Flood Protection Measures?

Operations Defined

• Inventory • Administration • Inspections and Monitoring • Public Communications • Heavy Equipment and Generators • Supply and HR Management • Temporary Levees • Sandbagging

Operations Defined

• Revenue Losses – Campgrounds Admission – Golf Courses Greens Fees – Athletic Facility Fees

Maintenance Defined

• Clean up: – Streets – Open spaces

• Repair: – Levee Embankments – Roadway Embankments – Topsoil and Turf Repair – Ditch cleanout – Debris Removal

Maintenance

Clean up Paved Surfaces • Linear Feet of Street • RS Means

Maintenance

Clean up Open Space • Assumed crew • Estimated wages • Assumed acres/hr

Maintenance

Roadway Embankment Repair Ditch Cleanout and Debris Removal

Calculating Operations Costs

Existing Conditions Proposed Alternatives

FEMA Cost Data

Cost Curves Economist

Constructing Cost Curves

Insert Figures 2 and 3

Calculating New O&M Costs

• Calculated Expected Annual O&M Costs – Similar approach that HEC-FDA uses to

estimate flood damages

• How its calculated: – Variable O&M is estimated for each

exceedance – O&M Costs are weighted by the exceedance

probability – Sum the probability weighted O&M Costs

$’s O

&M

Exceedance

0.5 0.2 0.1

Exceedance and O&M Cost Curve

Expected Annual O&M is the sum of the O&M Costs weighted by the exceedance probability across the curve

Baseline Costs to Compare The Flood Control Strategy of the System

$70,000,000

$75,000,000

$80,000,000

$85,000,000

$90,000,000

$95,000,000

$3,400,000

$3,600,000

$3,800,000

$4,000,000

$4,200,000

$4,400,000

$4,600,000

$4,800,000

30 31 32 33 34 35 36 37

Pres

ent V

alue

Expe

cted

Ann

ual

100 Year Operational Stage

Pre Mitigation - Total O&M

EA PV

Determining Costs Savings for Alternate Flood Protection Measures

Determining Costs Savings for Alternate Flood Protection Measures

Determining Costs Savings for Alternate Flood Protection Measures

Stage

Before Mitigation

With Mitigation Option 1

PV O&M Cost ($ Millions)

PV O&M Cost ($ Millions)

% Reduction

30 78.53 78.40 -0.2% 31 84.19 83.34 -1.0% 32 85.91 84.27 -1.9% 33 86.85 83.77 -3.6% 34 88.87 84.25 -5.2% 35 91.25 84.96 -6.9% 36 91.68 84.90 -7.4% 37 91.86 84.84 -7.6%

Summary

• O&M costs should be a design consideration

• Alternate flood control strategies can result in varying O&M costs

• Historical flood fighting data can be a useful tool for proposed conditions

Questions?

Extra photos for incorporation into presentation

Base Condition Results

100 Year Event Operational Stage

Total Operations and Maintenance

Cost of 100 Year Event

Expected Annual Cost

Present Value*

30 4,194,000 3,893,000 78,525,000 31 4,660,000 4,174,000 84,191,000 32 4,802,000 4,259,000 85,906,000 33 5,010,000 4,306,000 86,854,000 34 5,417,000 4,406,000 88,871,000 35 6,159,000 4,524,000 91,252,000 36 6,858,000 4,545,000 91,677,000 37 7,497,000 4,554,000 91,857,000

Costs Not Included

• Lost Business Revenue • Road Closures • Private Property

– In-Town Cleanup – Golf Courses – Farmland

Operations Defined

Calculating Operations Costs

• Costs removed for stages<30 feet • Daily average cost per foot of inundation • Estimated that 80% of costs were for

temporary measures and 20% for permanent measures

• Divided costs by linear feet of protection impacted by flooding

Discount Factor for Smaller Events

River Stage

In Town Flood 100-year Flood Protection Level

30 31 32 33 34 35 36 37

30 1.0 - - - - - - - 31 1.0 1.0 - - - - - - 32 1.0 1.0 1.0 - - - - - 33 0.8 1.0 1.0 1.0 - - - - 34 0.6 0.8 1.0 1.0 1.0 - - - 35 0.4 0.6 0.8 1.0 1.0 1.0 - - 36 0.2 0.4 0.6 0.8 1.0 1.0 1.0 - 37 0.2 0.2 0.4 0.6 0.8 1.0 1.0 1.0

Valuing Change in O&M Costs

Expected Annual O&M is the sum of the O&M Costs weighted by the exceedance probability across the curve

Exceedance Relationships

Exceedance 100 Year Event Operational Stage

30 31 32 33 34 35 36 37

5 30 30 30 30 30 30 30 30

6 30 31 32 32 32 32 32 32

7 30 31 32 33 33 33 33 33

8 30 31 32 33 34 34 34 34

10 30 31 32 33 34 35 34 34

25 30 31 32 33 34 35 36 37

50 30 31 32 33 34 35 36 37

100 30 31 32 33 34 35 36 37