EVANSTON SLOW ZONE REMEDIATION
CTA Track Maintenance
April 22, 2013
![Page 2: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/2.jpg)
DRAFT Presentation: For Internal Use Only
TODAY’S PRESENTATION
• Background
• Project Scope and Benefits
• What to Expect
• Tentative Project Schedule
• Track Renewal Process
• Efforts to Lessen Community Impact
![Page 3: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/3.jpg)
DRAFT Presentation: For Internal Use Only
BACKGROUND
• Originally constructed in
1908-12
• Track last renewed in 1976
• Typical useful life of 25 years
• Currently over 6,700 feet
(16%) of track-related slow
zones
![Page 4: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/4.jpg)
DRAFT Presentation: For Internal Use Only
PROJECT SCOPE & BENEFITS
• Goal to mitigate slow zones until
a major renewal is funded
• Selective track & spot tie renewal
• Project Duration: 7 Months
• Work will occur under single
tracks on nights and weekends
• Over 6000 ties replaced
• Customers will experience a
smoother, faster ride
![Page 5: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/5.jpg)
DRAFT Presentation: For Internal Use Only
PROJECT SCOPE & BENEFITS
![Page 6: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/6.jpg)
DRAFT Presentation: For Internal Use Only
WHAT TO EXPECT
• Sunday through Thursday night work
occurring between 9PM and 4:30AM
• Weekend daytime work between 7AM and
7PM
• Noise as work occurs
• Work zone lighting
• Minor delays to service and boarding
changes during single track operation
• Regular track maintenance will continue
weekdays 9AM – 2:30PM
![Page 7: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/7.jpg)
DRAFT Presentation: For Internal Use Only
TENTATIVE PROJECT SCHEDULE
Phase
Affected
Wards
Track
Footage
Track
Slow
Zone May Jun Jul Aug Sep Oct Nov
Mulford St. to South Blvd. 3, 8, 9 700 ft
South Blvd. to Lee St. 3, 4, 9 3700 ft 2875 ft
Lee St. to Church St. 2, 3, 4 5200 ft 2732 ft
Church St. to Milburn St. 1, 2, 5, 7 4100 ft 821 ft
Milburn St. to Isabella St. 7 3300 ft 1454 ft
Isabella St. to Linden 7 500 ft
Construction Notices will be distributed to adjacent properties before work
begins in each area.
![Page 8: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/8.jpg)
DRAFT Presentation: For Internal Use Only
TRACK RENEWAL PROCESS
Tie handler
• distributes new ties
• cleans up old ties
![Page 9: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/9.jpg)
DRAFT Presentation: For Internal Use Only
TRACK RENEWAL PROCESS
Tie inserter
• Removes old ties
• Inserts new ties
![Page 10: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/10.jpg)
DRAFT Presentation: For Internal Use Only
TRACK RENEWAL PROCESS
Production Spiker
• Drives spikes into ties
![Page 11: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/11.jpg)
DRAFT Presentation: For Internal Use Only
TRACK RENEWAL PROCESS
Ballast cars
• Drops new stone ballast to fill in the track
![Page 12: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/12.jpg)
DRAFT Presentation: For Internal Use Only
TRACK RENEWAL PROCESS
Ballast Regulator
• Distributes and shapes new stone ballast
![Page 13: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/13.jpg)
DRAFT Presentation: For Internal Use Only
TRACK RENEWAL PROCESS
Production Tamper
• Sets track alignment
• Tamps (compacts) stone ballast
• Creates a solid, smooth ride
![Page 14: Evanston project briefing 4 22 13](https://reader033.vdocument.in/reader033/viewer/2022052912/55a1b43b1a28abc4538b4801/html5/thumbnails/14.jpg)
DRAFT Presentation: For Internal Use Only
EFFORTS TO LESSEN COMMUNITY IMPACT
• Pre-construction coordination meetings with
Evanston city officials
• Biggest, most disruptive work will occur in spring
and fall
• Structured work shift so that loudest work occurs
before midnight
• Biggest production will occur on weekends during
the day
• Presentation to City Council members outlining
project scope and schedule
• Distribution of construction activity notices prior to
beginning work in a given area
• CTA Contact: Ryan Mouw, [email protected]