evaporative sewer lagoon - us department of energy · 2017-11-01 · treatment plant (wtp))....

2
Electrical Status: Four substations and 200-plus miles of high-voltage transmission and distribution system equipment provides more than 20 megawatts of power from the power utility to the Hanford Site. The Bonneville Power Administration uses Hanford’s system to transmit 100 megawatts of power to surrounding areas. The system is beyond its design life and failures are occurring. Some system upgrades have been initiated. Needs for the Future: Renovated and right-sized electrical system that supports cleanup on Hanford’s Central Plateau. Cleanup of Hanford’s legacy of plutonium production continues, with state-of-the-art waste and groundwater treatment facilities, demolition of hundreds of facilities, and cleanup of hundreds of sites with contaminated soil and waste. Right-sizing and renovating Hanford’s infrastructure for continued safe and effective cleanup operations is ensuring the Department continues to protect workers, the public, and the environment as land is restored for controlled public access and use. INFRASTRUCTURE SUPPORTS HANFORD’S ENVIRONMENTAL MANAGEMENT MISSION: Renovation and modernization of old and antiquated infrastructure to achieve reliable and maintainable infrastructure for Hanford’s cleanup mission supports: Treatment, storage and disposal of Hanford’s Tank Waste Continued treatment of groundwater to remove contaminants Continued cleanup of contaminated facilities and soil sites Continued storage, treatment and disposal of solid waste containing hazardous chemicals and radioactive material Long-term monitoring and stewardship of remaining lands Reliable infrastructure provides: Safe and secure site with emergency response capability Electrical utilities, roads, water, sewer, security, emergency response capability, Information Technology, and other services Ensuring reliable infrastructure requires renovation to: reduce the infrastructure footprint and update existing systems (reliability, maintainability) Supply infrastructure to new facilities (systems designed to service historical missions) Hanford’s infrastructure organization also supports lease agreements with: Columbia Generating Station-400 MW Utility Laser Inferometer Gravitational- Wave Observatory (LIGO) HANFORD Infrastructure Needs for the Future Water (Raw, and Potable) Status: More than 50 miles of distribution piping and a water system that includes 4 pump houses, 4 reservoirs, 2 large potable water storage tanks, and a water treatment facility. Many system components are more than 70 years old, and the system is experiencing line breakages and leaks. Needs for the Future: A renovated and right-sized water system that supports cleanup on Hanford's Central Plateau. Infrastructure Status and Needs Infrastructure Status and Needs Sewer Status: Hanford’s sewer system consists of 37 aging septic tanks and subsurface soil absorption systems of varying size and complexity and a newer, 31-acre evaporative lagoon complex that began operating in 2012. As soil absorption systems fail or approach the end of their useful life, holding tanks are installed and sewage is pumped and trucked to the evaporative lagoon. Needs for the Future: Upgraded sewer system that supports consolidated treatment and cleanup on Hanford’s Central Plateau. 200 West Area Evaporative Sewer Lagoon Roads Status: There are approximately 200 miles of road, with 1 million square yards of paved surfaces up to 45 years old. Primary roads are in need of upgrading and secondary roads have deteriorated. Needs for the Future: Renovated primary roads that support cleanup on Hanford’s Central Plateau.

Upload: dinhque

Post on 05-Jul-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Evaporative Sewer Lagoon - US Department of Energy · 2017-11-01 · Treatment Plant (WTP)). Renovation ... the site’s systems for raw and potable water, electricity, sewer,

Electrical

Status: Four substations and 200-plus miles of high-voltage transmission and distribution system equipment provides more

than 20 megawatts of power from the power utility to the Hanford Site. The Bonneville Power Administration uses Hanford’s system to transmit 100 megawatts of power to surrounding areas.The system is beyond its design life and failures are occurring. Some system upgrades have been initiated.

Needs for the Future: Renovated and right-sized electrical system that supports cleanup on Hanford’s Central Plateau.

Cleanup of Hanford’s legacy of plutonium

production continues, with state-of-the-art

waste and groundwater treatment

facilities, demolition of hundreds of

facilities, and cleanup of hundreds of sites

with contaminated soil and waste.

Right-sizing and renovating Hanford’s

infrastructure for continued safe and

effective cleanup operations is ensuring

the Department continues to protect

workers, the public, and the environment

as land is restored for controlled public

access and use.INFRASTRUCTURE

SUPPORTS HANFORD’S

ENVIRONMENTAL

MANAGEMENT MISSION:

Renovation and modernization of old and antiquated infrastructure to achieve reliable and maintainable infrastructure for Hanford’s cleanup mission supports:

• Treatment, storage and disposal of Hanford’s Tank Waste

• Continued treatment of groundwater to remove contaminants

• Continued cleanup of contaminated facilities and soil sites

• Continued storage, treatment and disposal of solid waste containing

hazardous chemicals and radioactive material

• Long-term monitoring and stewardship of remaining lands

Reliable infrastructure provides:

• Safe and secure site with emergency response capability

• Electrical utilities, roads, water, sewer, security, emergency response

capability, Information Technology, and other services

Ensuring reliable infrastructure requires renovation to:

• reduce the infrastructure footprint

and update existing systems (reliability, maintainability)

• Supply infrastructure to new facilities (systems designed to service

historical missions)

Hanford’s infrastructure organization also supports lease agreements with:

• Columbia Generating Station-400 MW Utility

• Laser Inferometer Gravitational-Wave Observatory (LIGO)

H A N F O R DInfrastructure Needs for the Future

Water (Raw, and Potable) Status: More than 50 miles of distribution piping and a water system that includes 4 pump houses, 4 reservoirs, 2 large potable water storage tanks, and a water treatment facility. Many system components are more than 70 years old, and the

system is experiencing line breakages and leaks.

Needs for the Future: A renovated and right-sized water system that supports cleanup on Hanford's Central Plateau.

Infrastructure Status and NeedsInfrastructure Status and Needs

SewerStatus: Hanford’s sewer system consists of 37 aging septic tanks and subsurface soil absorption systems of varying size and complexity and a newer, 31-acre evaporative lagoon complex that began operating in 2012. As soil absorption systems fail or approach the end of their useful life, holding tanks are installed and sewage is pumped and trucked to the evaporative lagoon.

Needs for the Future: Upgraded sewer system that supports consolidated treatment and cleanup on Hanford’s Central Plateau.

200 West AreaEvaporative

Sewer Lagoon

Roads

Status: There are approximately 200 miles of road, with 1 million square yards of paved surfaces up to 45 years old. Primary roads are in need of

upgrading and secondary roads have deteriorated.

Needs for the Future: Renovated primary roads that support cleanup on Hanford’s Central Plateau.

Page 2: Evaporative Sewer Lagoon - US Department of Energy · 2017-11-01 · Treatment Plant (WTP)). Renovation ... the site’s systems for raw and potable water, electricity, sewer,

I N F R A S T R U C T U R E

A Look Ahead

Hanford’s Infrastructure Story

• 1943-1980’s: Hanford was established during WWII

to support the Manhattan Project. Production and

research was expanded during the Cold War. Nine

production reactors, several test reactors,

hundreds of buildings and structures for chemical

processing and laboratory research were built in

this period, along with accompanying electrical,

water, and sewer systems, as well as transportation

infrastructure (roads, railways).

• 1980’s-2005: The Cold War ends, production of

plutonium at Hanford ceases, and a new era begins

to assess and clean up a legacy of extensive

contamination in facilities, soil, and groundwater. In

1989, a landmark agreement was reached between

the U.S. Department of Energy, the U.S.

Environmental Protection Agency and the State of

Washington, called the Tri-Party Agreement. This

agreement formed a framework for monitoring and

cleanup of Hanford’s legacy contamination, one of

the largest cleanup efforts in the world. Cleanup

work began, some major cleanup projects and

infrastructure upgrades were completed.

Information technology upgrades are installed.

• 2005-2015: Cleanup efforts in areas along the

Columbia River, which runs through the site, near

completion, shrinking the active footprint of

cleanup area to Hanford’s Central Plateau and inner

areas. During this era, DOE maintains Hanford’s

critical infrastructure, and the need for upgrades to

infrastructure is known.

• Beyond 2015: Renovation and right-sizing of

Hanford’s infrastructure is needed as most future

cleanup efforts at the site are concentrated in

Hanford’s Central Plateau (includes Tank Waste

Treatment Plant (WTP)). Renovation needs include

the site’s systems for raw and potable water,

electricity, sewer, information technology and

transportation.

• Continue repair and recondition of the 230 kV and 13.8 kV electrical transmission and distribution systems (including access roads) and begin replacement of selected radio frequency alarm repeaters (RFARs)

• Complete upgrades to Water Filter Plant (controls and flocculater) and continue upgrades for large potable water tank storage replacement and two, 24-inch water mains from the Columbia River to the Central Plateau (approx. 4.5 miles of pipe)

• Initiate installation of a Water Fire Main Loop for new Tank Waste Treatment Facility (WTP/Direct Feed Low Activity Waste (DFLAW))

• Complete selected road repairs in 200E and 100N Areas.

• Continue sewer flow equalization and consolidation in the 200E Area

• Complete selected road refurbishments in the 200E and 100N Areas and continue repair large sections of main Route 4 South

• Complete selected upgrades of the Local Area Network

FY16 Planned ProjectsFY16 Planned Projects $15.07M$15.07M

• Continue repairs and reconditioning of 230 kV electrical transmission and 13.8 kV

distribution system and replacement of selected RFARs, initiate electrical transfer

trip upgrades, and complete electrical access roads

• Complete upgrade of the new 24-inch water main, the large potable water tank

storage system serving the Central Plateau, water filter plant pilot project, and

installation of water fire loop for DFLAW

• Continue sewer flow equalization installation and sewer consolidations

• Rebuild road from Waste Treatment Plant to Hanford’s Integrated Disposal

Facility, and complete repair large sections of main Route 4 South

• Initiate upgrade the 400 Area Fire Station and the emergency siren system

• Replace key pieces of emergency response vehicle equipment and provide

expanded capability for 2 large crane replacements

• Initiate replacement of obsolete fire alarm panels inside selected support facilities

• Continue repairs and reconditioning of 230 kV electrical transmission and 13.8 kV

distribution system and replacement of selected RFARs, initiate electrical transfer

trip upgrades, and complete electrical access roads

• Complete upgrade of the new 24-inch water main, the large potable water tank

storage system serving the Central Plateau, water filter plant pilot project, and

installation of water fire loop for DFLAW

• Continue sewer flow equalization installation and sewer consolidations

• Rebuild road from Waste Treatment Plant to Hanford’s Integrated Disposal

Facility, and complete repair large sections of main Route 4 South

• Initiate upgrade the 400 Area Fire Station and the emergency siren system

• Replace key pieces of emergency response vehicle equipment and provide

expanded capability for 2 large crane replacements

• Initiate replacement of obsolete fire alarm panels inside selected support facilities

FY17 Planned ProjectsFY17 Planned Projects $40M$40M

• Complete repairs and reconditioning of 230 kV electrical transmission and 13.8 kV distribution system, upgrades to electrical transfer trip upgrades and replacement of selected RFARs

• Replace 12-inch potable water main to the 222-S Lab to support DFLAW

• Initiate replacement of 181D Pumping System and 24-inch diameter E-W pipe at 100D (replaces 42-inch diameter pipe)

• Continue sewer consolidations and flow equalization

• Continue upgrades to the 400 Area Fire Station and the emergency siren system

• Complete replacement of obsolete fire alarm panels inside selected support facilities

• Complete repairs and reconditioning of 230 kV electrical transmission and 13.8 kV distribution system, upgrades to electrical transfer trip upgrades and replacement of selected RFARs

• Replace 12-inch potable water main to the 222-S Lab to support DFLAW

• Initiate replacement of 181D Pumping System and 24-inch diameter E-W pipe at 100D (replaces 42-inch diameter pipe)

• Continue sewer consolidations and flow equalization

• Continue upgrades to the 400 Area Fire Station and the emergency siren system

• Complete replacement of obsolete fire alarm panels inside selected support facilities

FY18 Planned ProjectsFY18 Planned Projects $40M$40M

• Complete sewer consolidations and flow equalization

• Complete replacement of 181D water pumping system and 24-inch diameter E-W water pipe at 100D (replaces 42-inch diameter pipe)

• Continue upgrades to the 400 Area Fire Station and the emergency siren system

• Initiate Phase II of Local Area Upgrades (Access Layer)

• Complete sewer consolidations and flow equalization

• Complete replacement of 181D water pumping system and 24-inch diameter E-W water pipe at 100D (replaces 42-inch diameter pipe)

• Continue upgrades to the 400 Area Fire Station and the emergency siren system

• Initiate Phase II of Local Area Upgrades (Access Layer)

FY19 Planned ProjectsFY19 Planned Projects $40M$40M

• Replace/refurbish outdoor lighting

• Initiate replacement of 181B water pumping system and 24-inch diameter E-W water pipe at 100B (replaces 42-inch diameter pipe) and perform 283W Clearwell Tracer Study

• Refurbish route 3 and 3 North

• Complete upgrades to 400 Area Fire station and the emergency siren system

• Upgrade Fire Station 92 including installation of a new equipment storage building

• Complete Phase II Upgrade to Local Area Network (Access Layer)

• Replace/refurbish outdoor lighting

• Initiate replacement of 181B water pumping system and 24-inch diameter E-W water pipe at 100B (replaces 42-inch diameter pipe) and perform 283W Clearwell Tracer Study

• Refurbish route 3 and 3 North

• Complete upgrades to 400 Area Fire station and the emergency siren system

• Upgrade Fire Station 92 including installation of a new equipment storage building

• Complete Phase II Upgrade to Local Area Network (Access Layer)

FY20 Planned ProjectsFY20 Planned Projects $40M$40M

• Complete replacement of 181B water pumping system and 24-inch diameter E-W water pipe at 100B (replaces 42-inch diameter pipe) and modify the 283W Clearwell.

• Install 12-inch potable water loop line to WTP

• Replace 8 major water mains on the Central Plateau

• Initiate replacement of T-Plant fire water supply

• Refurbish 8 sections of road

• Address next generation wireless and HSEAs upgrades

• Renovate 2101M in 200E

• Complete replacement of 181B water pumping system and 24-inch diameter E-W water pipe at 100B (replaces 42-inch diameter pipe) and modify the 283W Clearwell.

• Install 12-inch potable water loop line to WTP

• Replace 8 major water mains on the Central Plateau

• Initiate replacement of T-Plant fire water supply

• Refurbish 8 sections of road

• Address next generation wireless and HSEAs upgrades

• Renovate 2101M in 200E

FY21 Planned ProjectsFY21 Planned Projects $40M$40M

• Renovation of remaining electrical, water, sewer, and road systems, as well as upgrades to facilities and heavy equipment focused on cleanup of Central Plateau

• Renovation of remaining electrical, water, sewer, and road systems, as well as upgrades to facilities and heavy equipment focused on cleanup of Central Plateau

FY22 and Beyond Planned ProjectsFY22 and Beyond Planned Projects $118M$118M