everglades agricultural area storage reservoir a-1 30% earthworks design phase
DESCRIPTION
Everglades Agricultural Area Storage Reservoir A-1 30% Earthworks Design Phase. WRAC April 6, 2006 Shawn Waldeck, P.E. Acceler8 Project Manager. Project Purpose. EAA Reservoir A-1 is an important part of the Comprehensive Everglades Restoration Plan (CERP). As part of CERP it will:. - PowerPoint PPT PresentationTRANSCRIPT
Everglades Agricultural AreaStorage Reservoir A-1
30% Earthworks Design Phase
WRACApril 6, 2006
Shawn Waldeck, P.E.Acceler8 Project Manager
Project PurposeEAA Reservoir A-1 is an important part of the Comprehensive Everglades Restoration Plan (CERP). As part of CERP it will:
• Allow SFWMD to better manage water to the environment
• Allow SFWMD to manage water deliveries to agricultural community
A-1
• Capture, store, and make use of EAA Basin runoff and releases from Lake Okeechobee
• Reduce Lake Okeechobee regulatory releases to the estuaries
• Restoration of Everglades’ hydropatterns• Balancing inflow into STA-3/4• Preserve existing agricultural water uses• Ancillary improvement in flood protection in EAA
Project Purpose
Mia
mi C
anal
Mia
mi C
anal
STA-3/4STA-3/4
G-372G-372
G-370G-370
North
New
River C
anal
North
New
River C
anal
FutureFutureA-2A-2
ReservoirReservoir
ProposedProposed
A-1A-1ReservoirReservoir
Holey LandWildlife Management
Area
Holey LandWildlife Management
Area
Pump StationPump Station
Pump StationPump Station
Supply CanalSupply Canal
US H
ighw
ay 27
US H
ighw
ay 27
Overall Plan
STA-3/4 Supply Canal
EAA Reservoir A-1
NortheastPump Station
North NewRiver Canal
From G-372Pump Station
G-370Pump Station
Seepage Canal
Embankment
Internal Borrow Canal
G-383
Gate Structures
Connector Canal
Gate Structure
• 190,000 ac-ft of storage
• Seepage canals • New pump station
from North New River Canal
• Gated discharge structures
• STA-3/4 Supply Canal
Stripping berm
S T R I P P I N G
Borrow canal Seepage canal Cut-off wall
Advantages of Roller Compacted Concrete RCC
• Downstream slope maintenance generally not required if defect free.
• Risk of piping in dam eliminated.• Minor overtopping may be acceptable without damage.• Avoids the need to use moisture sensitive Fort Thompson
Formation material• Occupies less area than an embankment, so EAA Reservoir
A‑1 storage can be maximized.
Disadvantages of Roller Compacted Concrete RCC• Higher cost
• Supply risk because a large volume of cement must be imported.• Special foundation treatment required where caprock thin or absent• Predicting the magnitude of cracking and control of crack location with
certainty is difficult due to the variable foundation conditions. Seepage is expected to occur through cracks.
• Foundation preparation by air/water blasting• Settlement of the cutoff must be compatible with the rigidity of the RCC
structure.• Temperature control of the RCC components difficult in hot temperatures.• Moisture control in stockpiled aggregates difficult during wet season.• An RCC structure does not fit aesthetically with the surroundings. • Vertical upstream face creates a safety hazard; means for escape required
Design Safety
• Dam Design Criteria – DCM (Design Criteria Memorandum) coordination
• Superiority• Stability• Regular Inspections/Monitoring
Potential Recreational Opportunities
Project Assurance Requirements
WRDA (Water Resources Development Act) 2000 and Florida Statute requirements addressed:
• Identify water for the natural system• Identify water for other water-related needs• Confirm quantify water available to existing legal users has not been
diminished• Determine that existing levels of service for flood protection will not be
diminished outside geographic area of the project
Documentation of Project Assurances
• Documentation of Project Assurances for A8 Reservoir will be included in the Preliminary Design Documents (30% Design for both the earthworks and pump station phases)
• Acceler8 system wide benefits, ascribable to the EAA Project, will be identified in the Final Supplemental Environmental Impact Statement (SEIS)
• Corps Project Implementation Report (PIR) documents project assurances for Compartment A in its entirety
Surface Water Flood Protection
• Inherent flood protection due to reservoir• Additional capacity created in the existing canal system• Additional pumping station(s) in system
Seepage Controls
Permitting/Environmental
• 1502 Water Quality Certificate • USACE 404• 1501 Assurances• Environmental Site Assessment and Clean Up• Protected Species
– Manatee– Florida Panther– Wading Birds– Other
• Environmental Enhancements• Construction Permits• Air/Noise
Stakeholder Presentations
• Agricultural• Environmental• 298 Districts• Belle Glade• Pahokee• South Bay• Palm Beach County• Tribes• FPL/FDOT• Recreational• WRAC Issues Workshop• Full WRAC
Stakeholder Comments
• Safety• Flood Protection• Local Economic Development• Recreational Use(s)• Assurances• Consider other “less – engineered” alternatives• Wetland impact and mitigation• Holey Land seepage
S7
Degradation in the EAA
Sheetflow over the sawgrass plains to the EvergladesLake
Okeechobee
EAA
HISTORICAL
LakeOkeechobee
Loss of muck in the EAA through subsidence, compaction, and oxidation
PRESENT
Schedule for EAA Reservoir A-1
2005 2006 2007 2008 2009
Design
Construction
Cost Summary
Project Component
Direct Cost
(millions)
Construction Indirect Costs*
Project Reserve Indirect
Costs
Combined Cost
Embankment and EAA Reservoir A-1
$245.9 $89.0 $14.8 $349.7
Northeast Pump Station
$50.3 $16.8 $3.3 $70.4
Control Structures $10.4 $3.5 $0.7 $14.6
US 27 Bridges $3.8 $1.2 $0.3 $5.3
Totals $310.4 $110.5 $19.1 $440* includes sales tax, general requirements, overhead and profit, bonds, and insurance
Base Cost from Yellow BookEmbankmentPump StationControl StructuresU.S. 27 BridgesSubtotal StructuresTotal Yellow BookProrated to 190,000 AF
$M
437243.3
Costs adjusted to 2006A-1 (acres)Total A (acres)
36416,70030,000
Base Cost from BODR for EAA Reservoir A-1
EmbankmentPump StationControl StructuresU.S. 27 BridgesSubtotal StructuresTotal BODR
Costs adjusted to 2006
310.4 70.4 14.6 5.3
90.3 400.7
412.7
•Added cutoff wall
•Increase water depth to 12 feet
•Modified pump station and added pump station
Preliminary Design Report
Embankment Structures
Total PDR
Costs adjusted to 2006
349.7
90.3
440.0
440.0
•Added concrete to slurry wall
•Added mechanical mixing of slurry wall
•Embankment volume increased
Discussion