everyday solutions: abc designs from shrp2 solutions: abc designs from shrp2 bala sivakumar hntb...
TRANSCRIPT
SHRP2 Project R04
Everyday Solutions: ABC Designs from SHRP2
Bala Sivakumar
HNTB Corp.
Introduction
Many deficient bridges in the US are in need of replacement
Minimizing traffic disruption is a
priority
Most of these are routine structures
Need for standardized solutions to deploy successful ABC technologies
Systems that are easy to construct and
adaptable to many sites
SHRP2 Project R04 PROJECT GOAL
To develop standardized approaches to designing, constructing, and reusing complete
bridge systems that address rapid renewal needs
Phase I – Define ABC Challenges
Phase II – Identify & Refine the Best ABC Technologies
Phases III & IV – Standardize & Deploy ABC
SHRP2 Project R04
INNOVATIVE BRIDGE DESIGNS FOR RAPID RENEWAL
2008 -- 2013
HNTB (Prime) Iowa State University
Structural Engineering Assoc.
Genesis Structures
Dr Monica Starnes, Senior Program Officer SHRP2
Accelerated Bridge Construction (ABC)
Prefabricated Elements
Modular Construction
Structure Placement Methods
Accelerated Geo-tech Work
ABC ELEMENTS & METHODS
SHRP2 R04 -- Phases I, II, III (2008 – 2011)
Phase IV (2011-2013)
This presentation is on first 3 Phases
ABC elements and modular systems
SHRP2 R04 ABC Toolkit
Expected Outcome: The designer, guided by the standard plans, details and the set of ABC design examples will be able to easily complete an ABC design for a routine bridge replacement project.
1 ABC STANDARD PLANS
2
3
4
ABC DESIGN EXAMPLES
ABC ERECTION CONCEPTS
5 ABC CONSTRUCTION SPECIFICATIONS
ABC DESIGN SPECIFICATIONS (LRFD)
First Demonstration Project Demonstrate Use of ABC Standards Developed
in SHRP2 R04 Keg Creek Bridge, Iowa
– Total prefabricated bridge (PBES)
– ABC standard plans & details developed in SHRP2 R04 Project were used with minimal customization for the site
14 day ABC period
Opened Nov 1, 2011
Feb 16 ABC Webinar
ABC Standard Plans
• Focus on “workhorse’ bridges
• Complete bridges using prefabricated elements and modular systems
• Contractor could self-perform a lot of the work
• Simple to fabricate on site or in a plant and easy to erect using conventional cranes
• Fast assembly in the field in 1 to 2 weeks
• Durable connections / durable bridges
GOALS:
Outline of ABC Standard Plans
Standard Sheet Sets Contents
G1 – G3 General Information Sheets
A1 – A12 Precast Abutments, Wingwalls, & Approach Slabs
P1 – P9 Precast Complete Pier Systems
S1 – S8 Decked Steel Girder Superstructures
C1 – C12 Decked Concrete Girder Superstructures
CC1 – CC32 ABC Erection Concepts
Span Ranges for Superstructures • Simple / continuous spans from 40 ft to 130 ft.
• Simple for DL ; Continuous for LL ; No Open Joints
• Plans are grouped in the following span ranges:
– 40 ft to 70 ft
– 70 ft to 100 ft
– 100 ft to 130 ft.
• Spans to 130 ft can usually be transported and erected in one piece at many sites.
• Weight < 200 Kips for erection using conventional cranes commonly used by contractors
• Some ABC standards can be adapted to spans < 40 ft
Modular Superstructure Systems
Deck Bulb
Tees
Double
Tees
Composite
Steel
System
2 Lane bridge with shoulders shown – customize width for site
Typical Decked Steel Girder Module Interior
• Not proprietary
• Contractor can self-perform precasting of deck onsite
• Lightweight system for ABC
Decked Steel Girder Module Exterior
• Barrier can be precast
• Barrier load on exterior module
Prestressed Decked Girders
Based on the PCI NEXT
beam
Spans to 90 ft
Low depth alternative
Deck Bulb Tee
Span lengths from 40 ft to 130 ft
UT, WA, ID among states with DBT
standards
ABC Standards for Substructures
ABUTMENTS & WINGWALLS
– Semi Integral Abutments
– Integral Abutments
– Inline or U type Wingwalls
– Pile Foundation and Spread Footing Options
COMPLETE PIERS
– Precast Conventional Pier
– Precast Straddle Bent
– Drilled Shaft and Spread Footing Options
Integral and Semi-Integral Bridges for
Rapid Renewal
• Well suited for ABC
• They allow the joints to be moved beyond the bridge
• Close tolerances required when utilizing expansion bearings and joints are eliminated
• The backwall is precast with the deck.
• Fast erection in 1 to 2 days, economical
Semi-Integral Abutment Suspended Backwall
• H piles or spread footings • Fill pile pockets with SCC • Easy fit-up in the field
Integral Abutment
• Only one row of vertical piles • Precast backwall - dowelled • Fast construction
Precast Approach Slab Precast Sleeper
Slab
• Flooded backfill
• Flowable fill under slab
• Exp joint can be moved to
sleeper slab
Complete Precast Piers
Conventional Pier
Straddle Bent
• Deep foundation may be outside existing footprint
• Non-prestressed so contractor can self-perform precasting
• Fast erection using grouted splice couplers
ABC Connections • Connections affect field assembly time.
• Goal is rapid field assembly and long-term durability of joints
• Also, flexural continuity between modules to emulate CIP construction
• Connections affect seismic performance
• REFERENCE: FHWA Connections Manual
Connections for ABC
– Ultra High Performance Concrete (UHPC) longitudinal & transverse joints between superstructure modules
– Grouted splice couplers in piers replace the typical lap splice
– Self Consolidating Concrete (SCC) pile connections and abutment to wingwall connections
……………………………………………………………………………………
– Grouted cap pockets / grouted ducts for substructure connections (seismic)
– Other rapid set concrete options may be used
Grouted Splice Coupler
• Allows rapid construction. No post tensioning required • UHPC joints are typically 6 in wide. Good durability • Can be reinforced with hairpin bars or straight bars
UHPC Joints in Bridge Deck
(Longitudinal Joint.
Longitudinal steel not shown)
Transverse UHPC Joint in Deck Iowa Project: First use in the US for UHPC Trans. Joints
• Simple for DL -- Continuous for LL
• UHPC joint carries the full LL tension
• Tie plates transfer compression
Lab Tested at Iowa
State University
Erection Concept Drawings • Erection using conventional cranes.
• Erection using ABC construction technologies adapted from long span construction
Organization of drawings for erection using cranes
ABC ERECTION CONCEPTS
Select Cranes - Module Weight /
Pick Radius
Use Single Crane
Use Two Cranes
Bridges over Waterway
Bridges over Roadway
Bridges over Waterway
Bridges over Roadway
Erection Concepts for Bridge Replacement Using Cranes
Fact
ors
to
Co
nsi
der
Weight of Module
Pick Radius
Crane Set Up Locations
Ground Access / Barge / Causeway / Work Trestle
Truck Access for Delivery
Erection Concepts for Bridge Replacement Using Cranes
Short Single Span over Stream
Cranes selected for 90 Kip pick
Longer Span over Roadway
Weight up to 200 kips
Erection with ABC Construction Technologies
• Use ABC construction technologies where ground access for cranes below the bridge may be limited.
• ABC technologies that allow construction from above:
– Above Deck Driven Carriers
– Launched Temporary Bridge
– Transverse Gantry Frames
– Longitudinal Gantry Frames
Above Deck Driven Carriers
Allows fast rate of erection
Rides on existing bridge, new
bridge (check capacity to support)
Ideal for bridges with many spans.
long viaducts
Launched Temporary Bridge • Sites with limited ground access or long spans
• Launched across or lifted over a span to act as a “temporary bridge”
• Used to deliver the heavier modules without inducing large erection stresses.
• Temp bridge can also support transverse gantry frames
Gantry Frames
Longitudinal Gantry Frame
Transverse Gantry Frame
• The LRFD Design Specifications do not explicitly deal with the unique aspects of large scale prefabrication
• In some cases, the most extreme load case may occur during shipping and handling.
• The work in SHRP2 R04 entailed the identification of any shortcomings in the current LRFD Bridge Design Specifications
• Recommendations are provided for addressing these limitations.
ABC Design Specifications for LRFD
ABC Specific Construction Loads
• Dynamic Dead Load Allowance—An increase in the self-weight of components to account for inertial effects during handling and transportation
• Camber Leveling Force—A vertically applied force used to equalize differential camber prior to establishing connectivity between the elements.
RECOMMENDED PROVISIONS FOR LRFD DESIGN OF PREFABRICATED SYSTEMS FOR ABC
(NEW SECTION)
XX.1 General XX.2 Design Objectives XX.3 Loads and Load Factors XX.4 Analysis XX.5 Control of Cracking XX.6 Lifting and Handling Stresses XX.7 Prestressed Components XX.8 Design of the Grouted Splice Coupler XX.9 Provisions for Joints XX.10 Provisions for Steel Composite Systems
Economical ABC Design • In ABC design the careful determination of span arrangement,
girder spacings and module dimensions for shipping and erection can add significant savings.
• Consider ABC as an option during preliminary design
• Not all sites are suited for ABC -- Reference: FHWA Decision-Making Framework for ABC
ABC Design Examples
ABC Design Examples
• Three ABC design examples for prefabricated systems in the toolkit:
– Decked Steel Girder
– Decked Precast Prestressed Girder
– Precast Pier
• Design Criteria:
• AASHTO LRFD (5th Edition)
• Supplemental ABC criteria
The design examples provide step by step guidance on the overall
structural design of bridge components for ABC
LRFD for ABC Design
• The design of most ABC elements and systems follows traditional LRFD design specifications.
• Design the ABC elements and the completed structure using all applicable LRFD Limit States
• Additional requirements apply for ABC connections, lifting and moving of prefabricated elements and modules.
Decked Steel Girder Design for ABC
• Three Stages for Design
Prefabrication Stage (many support options)
– Load Case 1 = Dead load on module steel section only
– Load Case 2 = Dead load on module composite section
Erection Stage (many lift options)
– Load Case 3 = Modules are lifted into place
Final Stage
– Load Case 4 = Modules are assembled and made continuous » DL
» FWS
» LL + IM
» Utilities
Decked Steel Girder Design for ABC Erection Stage
• Erection Loads
– Analysis for pick points / supports shown on plans
– Contractor may select other erection method and do own erection analysis
• Erection Limit State
– Load Factor for erection dead Loads
– IM for dead loads
• Erection Stresses
– Flexural stresses < Allowable
Decked Prestressed Concrete Girder Design Camber Leveling Forces
• Control of differential camber at erection is key to
proper fit up
• If the prescribed tolerance cannot be attained use an approved leveling system to equalize cambers
• Camber leveling forces cause additional concrete tension – need to be factored into the girder design
• Reduce allowable tension
• ABC aspects Illustrated in design example
• Recommended Special Requirements for ABC
• Focus heavily on means and methods requirements for rapid construction.
New Section in LRFD Construction Specifications
XX.1 GENERAL
XX.2 RESPONSIBILITIES
XX.3 MATERIALS
XX.4 FABRICATION
XX.5 SUBMITTALS
XX.6 QUALITY ASSURANCE
XX.7 HANDLING, STORING, AND TRANSPORTATION
XX.8 GEOMETRY CONTROL
XX.9 CONNECTIONS
XX.10 ERECTION METHODS
XX.11 ERECTION PROCEDURES
ABC Construction Specifications
• Review the ABC Standard Plans and Design Examples
• General Information Sheets Introduce the intent and scope of the ABC standard plans and details -- includes instructions to designers so that all the key ABC issues are addressed
• Engineer of Record (EOR) should perform own ABC design calculations for the site using the examples as a guide
• EOR to customize the standard plans for the site --- span lengths / bridge width / module size / skew / foundations / etc
• Adapt ABC Special Requirements for construction
• EOR to add any aesthetic enhancements as needed or use lightweight concrete to reduce erection weights
Using the ABC Toolkit
ABC Design Example
Organization of Deck Bulb Tee Design Example General: Design Philosophy Design Criteria Girder Design: Permanent Loads Precast Lifting Weight Live Loads Prestress Losses -- Erection Prestress Losses -- Final
Concrete Stresses at Release Concrete Stresses at Erection Concrete Stresses at Final Flexural Strength Shear Strength Negative Moment Design Camber and Deflections at Release / Erection / Final
*** Engineer of Record should perform own ABC design
Closing
• New generation of ABC systems are economical to construct and designed for durability
• SHRP2 R04 ABC toolkit and training materials will be available to provide guidance to those new to ABC
• ABC costs are coming down with repeated use
• The time for ABC is now
Join us for the February 16 webinar on the Iowa and NY ABC projects