evidence issues in forensic use of cpm scheduling
DESCRIPTION
Evidence Issues in Forensic Use of CPM Scheduling. prepared by Fredric L. Plotnick, Ph.D., Esq., P.E. Author Biography. Fredric L. Plotnick, Ph.D., Esq., P.E. Degree: Ph.D. – Civil Engineering – Drexel University – Relationship Diagramming Method - PowerPoint PPT PresentationTRANSCRIPT
Evidence Issues inForensic Use of CPM Scheduling
prepared by
Fredric L. Plotnick, Ph.D., Esq., P.E.
Author BiographyFredric L. Plotnick, Ph.D., Esq., P.E.• Degree:
– Ph.D. – Civil Engineering – Drexel University – Relationship Diagramming Method– J.D. – Law – Widener University – Member of Bars of PA, NJ, FL– M.S. – Civil Engineering – Drexel University – Construction Management– B.S. – Civil Engineering – Drexel University – Geotechnical – Professional Engineer – PA, NJ, FL, MD – President NSPE/PSPE Philadelphia PA
• University:– Professor of Engineering – Drexel U – Temple U – U of Pennsylvania – since 1979– Author – CPM in Construction Management – Author – Contracts and the Legal Environment for Engineers & Architects
• Years of Experience:– Engineering & Property Management Consultants (“EnProMaC”) since 1983– a variety of assignments 1975-1983
• Professional Field:– "Choreographers for the Construction Industry"™
• Something you do not know about me:– Enjoys fishing
®
• How reliable is CPM to establish a claim of delay or disruption?
• Claims before CPM• Claims after CPM• Frye v Daubert• Current State-of-the-Art• Intrinsic Unreliability of CPM• Daubert II • Robinson Factor Analysis• Analytical Gap Test• Specific Flaws of this CPM• All leading to …
RDM Relationship Diagramming Method
• Old Knowledge – New Software Technology
• New Knowledge – Software Implementation
• RDM – in a nutshell
RD CPM®
Compliance Certified
RD CPM®
Compliance Certified
More Accurate Model / Calculations
• Events – Description – Coding – Maths • Durations – P/C/K – C/I/S – M/R/P – Calendar
• Restraints – FS/SS/PS/FF/FR/SF CT/CC/DD
• Reason/Why – Just-In-Time – Description • Relationship Coding – Automated Reason/Why
Pre-CPM Claims of Delay
• Generally, if two parties claim concurrent delays, the court will not try to unravel the factors involved and will disallow the claims by both parties. In United States vs. Citizens and Southern National Bank, 367 F. 2d 473 (1966), a subcontractor was able to show delay damages caused by the general contractor. However, the general contractor, in turn, was able to demonstrate that portions of the damages were caused by factors for which he was not responsible. In the absence of clear evidence separating the two claims, the court rejected both claims, stating:
• “As the evidence does not provide any reasonable basis for allocating the additional costs among those contributing factors, we conclude that the entire claim should have been rejected.”
CPM in Construction Management, 7th Edition, page 609
Post-CPM Claims of Delay• The courts gave early recognition to the validity of CPM. In 1972 (Appeal of
Minmar Builders, Inc. GSBCANo. 3430, 72-2 BOA), the court rejected a claim based on bar graph schedules, stating:
“The schedules were not prepared by the Critical Path Method (CPM) and, hence, are not probative as to whether any particular activity or group of activities was on the critical path or constituted the pacing element for the project.”
• Also in 1972, a Missouri Court (Natkin & Co. v. Fuller. 347 F Supp 17) stated that bar charts did not “afford an overall coordinated schedule of the total work covered by the contract.”
• An Illinois court (Pathman Construction Co. v. Hi-Way Electric Co. 65 Ill. App. ad 480, 382 N.E. 2d 453,460) in 1978 noted that
“technological advances and the use of computers to devise work schedules and chart progress on a particular project have facilitated the court’s ability to allocate damages.”
CPM in Construction Management, 7th Edition, page 26
Frye v Daubert
• Frye v. United States, 293 F. 1013 (D.C. Cir. 1923)• “Just when a scientific principle or discovery crosses the line between the experimental and
demonstrable stages is difficult to define. Somewhere in this twilight zone the evidential force of the principle must be recognized, and while the courts will go a long way in admitting experimental testimony deduced from a well-recognized scientific principle or discovery, the thing from which the deduction is made must be sufficiently established to have gained general acceptance in the particular field in which it belongs”
• Daubert v. Merrell Dow Pharmaceuticals, Inc., 43 F.3d 1311 (9th Cir. 1995)• 1.The theory or technique must be falsifiable, refutable, and testable by empirical testing
2.Judicial review of the extent to which the technique relies upon the subjective interpretation of the expert 3.Degree to which theory has been subjected to peer review and publication (noting date and subsequent history) 4.Existance and explanation of a known or potential error rate5.The existence and maintenance of standards and controls concerning its operation (reducing subjectivity)6.Degree to which the theory and technique is generally accepted by a relevant scientific community7.Non-judicial uses which have been made of the theory or technique8.”Any other factor which is helpful in determining the reliability of scientific evidence”
• Additional Factors and Analytical Gap Test issues• 1. Is the testimony is based upon sufficient facts or data?
2. Is the testimony is the product of reliable principles and methods?3. Has the witness has applied the principles and methods reliably to the facts of the case?
• Analysis of Delay• As-Planned• As-Built• As-Impacted• Zeroing-Out• Windows• Zeroing-Out Windows
State of the Art Analysis & Presentation
ACTIVITY IDACTIVITY
DESCRIPTIONORIGDUR
ActualDuration START FINISH
1991 1992 1993 1994 1995MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB
1000 NOTICE TO PROCEED 1 1 10MAY91A 10MAY91A 0
1005 MOBILIZATION 10 10 10MAY91A 23MAY91A 0
1020 SED BASIN EXCAV to 236.15 5 24 24MAY91A 27JUN91A 005 1 0
1070 SED BASIN SOG @ 236.40 15 38 12JUL91A 4SEP91A 005 1 0
3000 SED BASIN SOG @ 240.40/242.75 44 50 15JUL91A 23SEP91A 0
3015 SED BASIN (N,S,E) WALL to 264 64 84 5SEP91A 3JAN92A 009 1 0
1075 FLOC BASIN FOOTING @ 240.25 5 5 14NOV91A 20NOV91A 0
1080 FLOC BASIN FOOTING WALL to 247 5 5 21NOV91A 27NOV91A 0
1150 FLOC BASIN CONC FILL to 247 1 1 29NOV91A 29NOV91A 0
3150 FLOC BASIN SOG @~249 INCL GRADE BEAM 40 25 2DEC91A 7JAN92A 022 1 0
3155 FLOC BASIN (N,S,W) WALL to 261.58/264 50 48 2JAN92A 9MAR92A 022 2 0
3415 PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33 40 73 21APR92A 2OCT92A 053 1 0
3305 CHEM BLDG EAST SOG STEP FTGS @ 230//240.50 6 8 18JUN92A 29JUN92A 029 1 58
3310 CHEM BLDG EAST WALL to 243//250 22 22 1JUL92A 31JUL92A 008 1 58
4050 CHEM WEST SOG @ 246/246.67 30 16 26OCT92A 16NOV92A 0
3315 CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250 16 22 5AUG92A 3SEP92A 058 1 58
4055 CHEM WEST WALLS to 263 30 230 13JUL92A 27AUG93A 045 1 0
3360 CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67 25 28 17DEC92A 27JAN93A 093 2 58
4310 CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS 4 120 10AUG92A 28JAN93A 0
4320 CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG 10 158 27AUG92A 9APR93A 0
4060 CHEM WEST BEAMS & SLABS to 264 50 52 16SEP92A 8MAR93A 084 3 0
3370 CHEM BLDG EAST MASONRY TO 265 10 26 22MAR93A 26APR93A 097 2 58
R1760 CHEM EAST GLAZED STRUCTURAL TILE 10 6 19APR93A 26APR93A 58
3371 CHEM BLDG EAST MONORAIL SUPPORT STEEL 2 4 21APR93A 27APR93A 131 2 66
R1795 CHEM EAST CAST STONE/BRICK 10 67 20APR93A 25JUL93A 330
R1740 CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266 2 8 28APR93A 7MAY93A 58
3375 CHEM BLDG EAST MASONRY TO 280 10 16 8MAY93A 1JUN93A 58
R1741 CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67 2 3 2JUN93A 4JUN93A 58
3385 CHEM BLDG EAST MASONRY TO PARAPET 5 36 5JUN93A 27JUL93A 63
4100 CHEM WEST STR STL COLS/BEAMS to 275.33/288.33 6 12 19MAR93A 5APR93A 0
4120 CHEM WEST ELEV SLAB @ 276 24 30 29MAR93A 7MAY93A 121 5 0
4125 CHEM WEST MASONRY TO 280 10 176 19OCT92A 27JUN93A 187 1 0
R1415 CHEM WEST 3rd FLOOR C.M.U. 8 36 16JUN93A 5AUG93A 29
3525 PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67 5 3 2JUN93A 4JUN93A 0
R4804 ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B. 10 30 4JUN93A 16JUL93A 117 1 0
4126 CHEM WEST MASONRY TO 288 15 15 5JUN93A 27JUN93A 1
3530 PRE-OZONE CONTACT BASIN MASONRY to PARAPET 3 10 17MAY93A 28MAY93A 7
2525 PIPE GALLERY/FILTER 12" DECK PANELS 5 20 21APR93A 18MAY93A 47
3390 CHEM BLDG EAST ROOFING 8 25 28JUL93A 31AUG93A 079 2 0
3535 PRE-OZONE CONTACT BASIN ROOFING 8 9 19AUG93A 31AUG93A 63
4160 CHEM WEST R/S LIME STO SILOS 1 1 23DEC92A 23DEC92A 1
4135 CHEM WEST STR STL BEAMS @ 288.33 10 13 28JUN93A 15JUL93A 150 1 7
4165 CHEM WEST R/S LIME FEEDER HOPPERS 1 4 17MAY93A 20MAY93A 1
4170 CHEM WEST R/S LIME DUST COLLECTORS 2 2 13MAY93A 14MAY93A 1
R6155 ELECTRICAL ROOM MISCELLANEOUS WORK 88 84 16APR93A 13AUG93A 0
4172 CHEM WEST - LIME STO R/S LIME CONV BLOWERS 2 3 10MAY93A 12MAY93A 1
4195 CHEM WEST - LIME STO R/S 6" 8" 10" PPG 10 36 20MAY93A 12JUL93A 1
4200 CHEM WEST 8" DECK PANELS @ 289 20 19 21JUL93A 16AUG93A 1
4127 CHEM WEST MASONRY TO PARAPET 10 11 17AUG93A 31AUG93A 1
R4805 ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR 10 6 24AUG93A 31AUG93A 117 1 21
R1495 CHEM WEST CAST STONE 20 98 1MAR93A 8SEP93A 141 2 1
4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT 8 7 31AUG93A 9SEP93A 21
1300 2ND FL ARCH INTERNAL MASONRY 25 200 19OCT92A 30JUL93A 148 2 1
1200 1ST FL ARCH INTERNAL MASONRY 20 195 26OCT92A 30JUL93A 145 2 17
R6090 2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING 30 33 15JUL93A 30AUG93A 9
4205 CHEM WEST ROOFING @ 280.67/289 8 9 2SEP93A 15SEP93A 1
4505 CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG 5 123 28DEC92A 18JUN93A 10
R1410 CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE 7 42 16JUN93A 13AUG93A 28
R2675 FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS 1 1 30APR93A 30APR93A 65
1320 2ND FL ARCH ELEC R/I 10 214 16NOV92A 17SEP93A 9
R6000 1st FLOOR CHEM WEST PIPING & PANELS 15 15 1AUG93A 21AUG93A 6
R6095 2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS 10 10 1SEP93A 15SEP93A 0
R6115 S.B./FILTERS/FLOCC. PULL FEEDERS 15 17 22AUG93A 15SEP93A 5
R6040 CHEM EAST/PUMP STATION PULL FEEDERS 15 15 1OCT93A 21OCT93A 10
R6140 3rd FLOOR CHEM WEST PULL FEEDERS 10 11 22OCT93A 5NOV93A 15
R1320 CHEM WEST COMPUTER ROOM EQUIPMENT 5 6 25MAR94A 1APR94A 14
R6005 1st FLOOR CHEM WEST PULL FEEDER WIRE 10 10 21AUG93A 5SEP93A 6
R6100 2nd FLOOR CHEM WEST/C.B. BRANCH WIRING 30 54 15SEP93A 30NOV93A 0
R6120 S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS 25 25 16SEP93A 20OCT93A 5
R6045 CHEM EAST/PUMP STATION PULL BRANCH WIRING 20 22 22OCT93A 22NOV93A 10
R1315 CHEM WEST LAB PIPING 2 5 23MAY94A 30MAY94A 4
R6010 1st FLOOR CHEM WEST PULL BRANCH WIRING 15 18 6SEP93A 30SEP93A 6
R1310 CHEM WEST LAB INSTRUMENTATION 5 5 23MAY94A 30MAY94A 4
R6050 CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT 20 21 1APR94A 30APR94A 10
R1305 CHEM WEST LAB EQUIPMENT/FURNITURE 5 6 15FEB94A 22FEB94A 4
R6015 1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT 10 11 1OCT93A 15OCT93A 6
R6125 S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT 15 19 5APR94A 30APR94A 5
R6105 2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE 20 21 1DEC93A 30DEC93A 0
R6165 ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS 30 35 1MAR94A 18APR94A 191 1 0
1500 OPERATIONAL PUNCHLIST 25 36 1MAY94A 21JUN94A 161 2 15
R1321 INSTALL SOFTWARE & DEBUG SYSTEM 20 42 18APR94A 15JUN94A 165 4 0
1510 PROCESS PAINTING 20 21 15APR94A 15MAY94A 15
1505 INITIAL MECH PERF TEST OPER TESTING & TRAINING 20 65 1MAR94A 31MAY94A 156 3 0
1515 INITIAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 201 7 0
1520 INITIAL MECH PERF TEST PUNCHLIST 5 5 20JUN94A 24JUN94A 0
1525 FINAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 0
5205 GARAGE EXCAV to 243 2 0 17AUG94A 22AUG94A 204 1 0
END1 880 DAY PART A COMPLETION 1 0 24JUN94A 24JUN94A END 33
5215 GARAGE SOG @ 243.83 4 0 1SEP94A 8SEP94A 0
5210 GARAGE FTG FDN @ 244 3 108 29AUG94A 31AUG94A 1
5220 GARAGE FTG WALLS to 247.27 +/- 4 0 9SEP94A 16SEP94A 0
5225 GARAGE BFILL 1 0 16SEP94A 19SEP94A 0
5230 GARAGE SOG @ 248 5 0 21SEP94A 29SEP94A 0
5235 GARAGE MASONRY 5 20 3OCT94A 28OCT94A 214 1 0
5240 GARAGE STR STL @ 260 +/- 2 0 18OCT94A 20OCT94A 0
5250 GARAGE 8" DECK PANELS @ 262.67 5 6 21OCT94A 28OCT94A 214 1 0
5255 GARAGE ROOFING 8 31 31OCT94A 13DEC94A 0
5260 GARAGE ARCH DETAILS 2 14 3JAN95A 20JAN95A 204 1 0
5290 GARAGE BUILDING PUNCHLIST 10 5 15JAN95A 20JAN95A 0
1390 ARCHITECTURAL & FINAL PUNCHLIST 20 63 1NOV94A 31JAN95A 190 3 0
1395 OWNER ACCEPTANCE 1 63 1NOV94A 31JAN95A 0
END2 1065 DAY PART B COMPLETION 1 0 31JAN95A 31JAN95A 0
NOTICE TO PROCEED
MOBILIZATION
SED BASIN EXCAV to 236.15
SED BASIN SOG @ 236.40
SED BASIN SOG @ 240.40/242.75
SED BASIN (N,S,E) WALL to 264
FLOC BASIN FOOTING @ 240.25
FLOC BASIN FOOTING WALL to 247
FLOC BASIN CONC FILL to 247
FLOC BASIN SOG @~249 INCL GRADE BEAM
FLOC BASIN (N,S,W) WALL to 261.58/264
PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33
CHEM BLDG EAST SOG STEP FTGS @ 230//240.50
CHEM BLDG EAST WALL to 243//250
CHEM WEST SOG @ 246/246.67
CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250
CHEM WEST WALLS to 263
CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67
CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS
CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG
CHEM WEST BEAMS & SLABS to 264
CHEM BLDG EAST MASONRY TO 265
CHEM EAST GLAZED STRUCTURAL TILE
CHEM BLDG EAST MONORAIL SUPPORT STEEL
CHEM EAST CAST STONE/BRICK
CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266
CHEM BLDG EAST MASONRY TO 280
CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67
CHEM BLDG EAST MASONRY TO PARAPET
CHEM WEST STR STL COLS/BEAMS to 275.33/288.33
CHEM WEST ELEV SLAB @ 276
CHEM WEST MASONRY TO 280
CHEM WEST 3rd FLOOR C.M.U.
PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67
ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B.
CHEM WEST MASONRY TO 288
PRE-OZONE CONTACT BASIN MASONRY to PARAPET
PIPE GALLERY/FILTER 12" DECK PANELS
CHEM BLDG EAST ROOFING
PRE-OZONE CONTACT BASIN ROOFING
CHEM WEST R/S LIME STO SILOS
CHEM WEST STR STL BEAMS @ 288.33
CHEM WEST R/S LIME FEEDER HOPPERS
CHEM WEST R/S LIME DUST COLLECTORS
ELECTRICAL ROOM MISCELLANEOUS WORK
CHEM WEST - LIME STO R/S LIME CONV BLOWERS
CHEM WEST - LIME STO R/S 6" 8" 10" PPG
CHEM WEST 8" DECK PANELS @ 289
CHEM WEST MASONRY TO PARAPET
ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR
CHEM WEST CAST STONE
CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT
2ND FL ARCH INTERNAL MASONRY
1ST FL ARCH INTERNAL MASONRY
2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING
CHEM WEST ROOFING @ 280.67/289
CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG
CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE
FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS
2ND FL ARCH ELEC R/I
1st FLOOR CHEM WEST PIPING & PANELS
2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS
S.B./FILTERS/FLOCC. PULL FEEDERS
CHEM EAST/PUMP STATION PULL FEEDERS
3rd FLOOR CHEM WEST PULL FEEDERS
CHEM WEST COMPUTER ROOM EQUIPMENT
1st FLOOR CHEM WEST PULL FEEDER WIRE
2nd FLOOR CHEM WEST/C.B. BRANCH WIRING
S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS
CHEM EAST/PUMP STATION PULL BRANCH WIRING
CHEM WEST LAB PIPING
1st FLOOR CHEM WEST PULL BRANCH WIRING
CHEM WEST LAB INSTRUMENTATION
CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT
CHEM WEST LAB EQUIPMENT/FURNITURE
1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT
S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT
2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE
ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS
OPERATIONAL PUNCHLIST
INSTALL SOFTWARE & DEBUG SYSTEM
PROCESS PAINTING
INITIAL MECH PERF TEST OPER TESTING & TRAINING
INITIAL MECH PERF TEST 48 HR PLANT OPERATION
INITIAL MECH PERF TEST PUNCHLIST
FINAL MECH PERF TEST 48 HR PLANT OPERATION
GARAGE EXCAV to 243
880 DAY PART A COMPLETION
GARAGE SOG @ 243.83
GARAGE FTG FDN @ 244
GARAGE FTG WALLS to 247.27 +/-
GARAGE BFILL
GARAGE SOG @ 248
GARAGE MASONRY
GARAGE STR STL @ 260 +/-
GARAGE 8" DECK PANELS @ 262.67
GARAGE ROOFING
GARAGE ARCH DETAILS
GARAGE BUILDING PUNCHLIST
ARCHITECTURAL & FINAL PUNCHLIST
OWNER ACCEPTANCE
1065 DAY PART B COMPLETION
Target Date 10MAY91Plot Date 15FEB95Data Date 1FEB95Project Start10MAY91Project Finish31JAN95
(c) Primavera Systems, Inc.
inactive Sheet 1 of 1
As-BuiltAs-PlannedAs-Impacted
nProMaC, Inc
As-PlanSTART
As-PlanFINISH
EARLYSTART
EARLYFINISH
1991 1992 1993 1994M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
24JUN91 29JUL91 25JUL91A 22FEB93A
10JUL91 2AUG91 13SEP91A 9DEC92A
4JUN91 24JUN91 12JUL91A 11JUN92A
6AUG91 19AUG91 22OCT91A 18JUN93A
7FEB92 14FEB92 18JUN92A 27JAN93A
4DEC91 17DEC91 27JAN92A 15JAN93A
9JUL91 10JUL91 8JUN92A 27AUG93A
23AUG91 6SEP91 14SEP92A 22DEC92A
12JUN92 12JUN92 2SEP92A 16AUG93A
16OCT91 19NOV91 25JUN92A 31AUG93A
12SEP91 20SEP91 26JUN92A 15JUL93A
24DEC91 15JAN92 18JUN93A 20DEC93A
9APR92 9APR92 24JUN92A 30SEP93A
4FEB92 6FEB92 16OCT92A 15NOV94A
21JAN93 27JAN93 1MAR94A 15SEP94A
P.S. CONCRETE
C.W./OZONE/GAC CONCRETE
S.B./FLOCC CONCRETE
FLUME/FILTER/P.G. CONCRETE
CHEM EAST CONCRETE
CONTACT BASIN CONCRETE
CHEM WEST CONCRETE
L/C CONCRETE
ROOF DECK
MASONRY
STRUCTURAL STEEL
ROOFING
MECH EQUIPMENT
OZONE SYSTEM
INSTRUMENTATION
Target Date 10MAY91Plot Date 20FEB95Data Date 1FEB95Project Start 10MAY91Project Finish 31JAN95
Primavera Systems, Inc.
Summary Bar/Early Dates
inactive
Critical DesignatorTarget Dates
R8U1 Page 1 of 1
A CT TI TLE O D E S- EC ON D AC T T ITL E OD ES -E CO ND
P CO 00 50 1 PC O00 5 NT P A DDL R OC K EX CA V & R EI NF C ONC 1 0 6/ 21 /9 1 PC O1 16 01 P CO1 16 N TP ADD L WA LL S LE EVE S CH EM W EST S LA B@ 27 6 1 05 /0 5/ 93
P CO 00 70 1 PC O00 7 NT P R EBA R RE VI SI ON S @ F LU ME S 1 0 7/ 26 /9 1 PC O1 17 01 P CO1 17 N TP WOO D BL OC KI NG @ RO OF O PE NIN GS 1 05 /2 1/ 93
P CO 00 80 1 PC O00 8 NT P G F L ET TE R 6/ 21 /91 1 0 7/ 26 /9 1 PC O1 20 01 P CO1 20 N TP ADD L NE LS ON S TUD S @ L/ C 1 05 /0 1/ 93
P CO 00 90 1 PC O00 9a NT P B RIC K LE DG ES & CL OU MN Q UA NTI TI ES 1 0 8/ 16 /9 1 PC O1 21 01 P CO1 21 N TP CHE M WE ST 3 RD SL AB /M AS ON RY IN TE RF AC E 1 04 /2 6/ 93
P CO 01 00 1 PC O01 0 NT P C ONS TR UC TI ON /C ONT RA CT IO N JOI NT S 1 0 9/ 06 /9 1 PC O1 24 01 P CO1 24 N TP ADD L RO OF H AT CHE S @ OZ ON E A IR P RE P 1 12 /2 1/ 92
P CO 01 20 1 PC O01 2 NT P R EVI SE D EL EC S UBS TA TI ON 1 0 9/ 26 /9 1 PC O1 26 01 P CO1 26 N TP MAS ON RY C HA NG ES CH LO R, L/ C B AT H, OZ ON E 1 03 /2 3/ 93
P CO 01 30 1 PC O01 3 NT P R EBA R CH AN GE S 1 1 0/ 10 /9 1 PC O1 28 01 P CO1 28 N TP ARC H MO DS F OR HV AC & P LU MBI NG 1 05 /2 0/ 93
P CO 01 40 1 PC O01 4 NT P W ATE RS TO P CH AN GES @ C LE AR WEL L & C. B 1 1 0/ 01 /9 1 PC O1 31 01 P CO1 31 N TP STR S TL B EA M REP AI RS @ C HLO R & GA C 1 02 /1 6/ 93
P CO 01 60 1 PC O01 6 NT P G F M EM O 10 /2 2/ 91 1 1 0/ 22 /9 1 PC O1 36 01 P CO1 36 N TP MOD IF Y 12 " S. S. AI R WA SH PI PE 1 06 /2 1/ 93
P CO 01 70 1 PC O01 7 NT P A DDL R EB AR @ C .W. S UM PS 1 0 9/ 25 /9 1 PC O1 41 01 P CO1 41 N TP MAS ON RY C HA NG E @ C HI MN EY AR EA 1 09 /0 3/ 93
P CO 01 80 1 PC O01 8 NT P G F M EM O 10 -2 9- 91 1 1 0/ 29 /9 1 PC O1 45 01 P CO1 45 N TP MOD S @ EL EV AT OR MA CH IN E ROO M 1 07 /2 6/ 93
P CO 02 00 1 PC O02 0 NT P G F L ET TE R 11 /1 1/9 1 1 1 1/ 11 /9 1 PC O1 48 01 P CO1 48 N TP CHA NG E DO OR S IZE @ C OR R 122 & L IN TE L 1 08 /2 7/ 93
P CO 02 10 1 PC O02 1 NT P F LOC C WL AK WA Y CHA NG ES 1 1 1/ 18 /9 1 PC O1 49 01 P CO1 49 N TP STR F RA MI NG C HAN GE S @ P. S. LO UV ER 1 10 /2 5/ 93
P CO 02 20 1 PC O02 2 NT P F LOC C DR AI N SL OT RE LO CA TI ON 1 1 1/ 21 /9 1 PC O1 50 01 P CO1 50 N TP A DDL N EL SO N ST UDS C HE M WE ST 3R D FL 1 07 /0 2/ 93
P CO 02 60 1 PC O02 6 NT P F LOC C IN TE RM ED BA FF LE W AL L D RA IN 1 1 1/ 25 /9 1 PC O1 51 01 P CO1 51 N TP L &N CH LO RI NE S YST EM M OD IF ICA TI ON S 1 03 /1 5/ 94
P CO 02 70 1 PC O02 7 NT P S .S. W AL KW AY C HAN GE S 1 1 2/ 03 /9 1 PC O1 52 01 P CO1 52 N TP A DDL M ET AL S TU D F RA MI NG @ L/ C 1 10 /1 3/ 93
P CO 02 80 1 PC O02 8 NT P R ELO CA TE S .B . DOO RS 1 1 2/ 05 /9 1 PC O1 54 01 P CO1 54 N TP N EW CA RP ET S TY LE 1 09 /0 2/ 93
P CO 02 90 1 PC O02 9 NT P C HEM E AS T RE BA R M OD IF IC AT ION 1 1 2/ 12 /9 1 PC O1 55 01 P CO1 55 N TP A DDL S UB CO NT RA CT WO RK @ L /C RO OF 1 08 /1 4/ 93
P CO 03 00 1 PC O03 0 NT P H ATC H & AN CH OR BO LT C HA NG ES 1 0 1/ 01 /9 2 PC O1 55 03 P CO1 55 S UBC ON TR AC T WO RK @ L/ C RO OF OP EN IN GS 1 no ne
P CO 03 10 1 PC O03 1 NT P A DDS W AL L PI PE S & B LI ND F LAN GE S 1 1 0/ 11 /9 1 PC O1 56 01 P CO1 56 N TP I NST AL L 30 " NJ BF V @ NO RT H B RA NC H 1 05 /0 6/ 94
P CO 03 20 1 PC O03 2 NT P E NVI RE X S. B. S LUD GE C OL L FIL L CO NC 1 0 1/ 02 /9 2 PC O1 56 03 P CO1 56 I NST L 30 " NJ B FV @ NO RT H BRA NC H RW PS 3 no ne
P CO 03 30 1 PC O03 3 NT P G F L ET TE R 12 /1 9/9 1 1 1 2/ 12 /9 1 PC O1 57 01 P CO1 57 N TP R EPL AC EM EN T LO UVE R @ L/ C 1 12 /1 0/ 93
P CO 03 40 1 PC O03 4 NT P G F M EM O 12 /2 0/ 91 DI ME NS IO NAL C HA NG ES 1 1 2/ 20 /9 1 PC O1 57 03 P CO1 57 I NST AL L RE PL AC EME NT L OU VE R @ L /C 1 no ne
P CO 03 50 1 PC O03 5 NT P G F L ET TE R 12 /1 9/9 5 DR WG C LAR IF IC AT N 1 1 2/ 19 /9 1 PC O1 60 01 P CO1 60 N TP A DD 2 TU RB ID IM ETE R IN DI CA TOR S TO G AC 1 01 /2 0/ 94
P CO 03 90 1 PC O03 9 NT P C HAN GE S P. S. D RAI N PI PI NG 1 0 1/ 29 /9 2 PC O1 61 01 P CO1 61 N TP A DD PR ES SU RE S WIT CH & A LA RM CO NT AC TS 1 03 /0 2/ 94
P CO 04 10 1 PC O04 1 NT P S PIL L CO NT AI NM ENT T AN K RE VIS IO NS 1 0 1/ 28 /9 2 PC O1 61 03 P CO1 61 P RES SU RE S WI TC H & A LA RM C ONT AC T HS PS 1 no ne
P CO 04 20 1 PC O04 2 NT P A DDL D RA IN C HA NNE L 1 0 1/ 28 /9 2 PC O1 62 01 P CO1 62 N TP A DD 4 SL OT D IF FUS ER S IN L /C 1 01 /1 0/ 94
P CO 04 50 1 PC O04 5 NT P G F M EM O 1/ 28 /9 2 R EF R FI #3 0 1 0 1/ 28 /9 2 PC O1 62 03 P CO1 62 A DD 4 SL OT D IF FUS ER S IN L /C 10 no ne
P CO 04 60 1 PC O04 6 NT P G F M EM O 2/ 18 /9 2 R EF R FI #4 7 1 0 2/ 18 /9 2 PC O1 63 01 P CO1 63 N TP A DD FI RE WA LL I N L /C 1 01 /1 4/ 94
P CO 04 70 1 PC O04 7 NT P C HEM B LD G CO L & J OI NT C HA NGE S 1 0 2/ 26 /9 2 PC O1 63 03 P CO1 63 A DD FI RE WA LL I N L /C T &M 13 no ne
P CO 04 90 1 PC O04 9 NT P F LUM E OV ER FL OW BO X EL EV R EV& R EL AT ED 1 0 7/ 09 /9 2 PC O1 65 01 P CO1 65 N TP C ONT RO L MO NI TO R F RA ME WO RK RE VI SI ON S 1 02 /2 4/ 94
P CO 05 10 1 PC O05 1 NT P P .S. T &M W OR K PER A AM #2 09 1 0 4/ 23 /9 2 PC O1 68 01 P CO1 68 N TP 8 " B YP AS S AR OU ND 10 " PL AN T S ER VI CE 1 04 /2 8/ 94
P CO 05 20 1 PC O05 2 NT P P .S. E LE CT RI C OPE NI NG S RE VIS IO N 1 0 4/ 23 /9 2 PC O1 68 03 P CO1 68 8 " B YP AS S AR OU ND 10 " PL AN T S ER VI CE 30 no ne
P CO 05 30 1 PC O05 3 NT P C .B. W AL L PO UR DE LA Y 1 0 5/ 06 /9 2 PC O1 71 01 P CO1 71 N TP M ODI FY L /C T OI LET P AR TI TI ONS 1 03 /2 5/ 94
P CO 05 40 1 PC O05 4 NT P H AND RA IL C HA NG ES 1 0 4/ 16 /9 2 PC O1 71 03 P CO1 71 P ROC UR EM EN T RE L/ C TO IL ET PA RT IT IO NS 52 no ne
P CO 05 70 1 PC O05 7 NT P C HEM B LD G SL AB TH IC KN ES S 1 0 5/ 22 /9 2 PC O1 77 01 P CO1 77 N TP C HLO RI NA TI ON S YST EM M OD IF ICA TI ON S 1 04 /0 7/ 94
P CO 05 80 1 PC O05 8 NT P A DDI TI ON AL W AT ERS TO P 1 0 5/ 29 /9 2 PC O1 77 03 P CO1 77 C HLO RI NA TI ON S YST EM M OD IF ICA TI ON S 20 no ne
P CO 05 90 1 PC O05 9 NT P C ERA MI C TI LE C HAN GE S 1 0 6/ 01 /9 2 PC O1 80 01 P CO1 80 N TP ADD L PR OJ EC T MIL LW OR K 1 01 /0 7/ 94
P CO 06 20 1 PC O06 2 NT P P .S. R AI N PI PI NG RE VI SI ON S 1 0 6/ 12 /9 2 PC O1 81 01 P CO1 81 N TP CEI LI NG C HA NG ES 1 02 /2 1/ 94
P CO 06 30 1 PC O06 3 NT P C HEM W ES T SU MP CH AN GE S 1 0 6/ 15 /9 2 PC O1 81 03 P CO1 81 ADD L ME TA L SO FFI T EN VI R LAB 2 no ne
P CO 06 40 1 PC O06 4 NT P D ELE TE C OM PU TE R A CC ES S FL OOR 1 0 4/ 16 /9 2 PC O1 81 04 P CO1 81 REM OV E IN SU L FRO M ME TA L CEI LI NG 3 no ne
P CO 06 50 1 PC O06 5 NT P D ELE TE F LO CC T ERR AZ ZO 1 0 4/ 10 /9 2 PC O1 82 01 P CO1 82 N TP E XPA NS IO N JO IN T B OO T RE TR OFI T 1 03 /1 7/ 94
P CO 06 60 1 PC O06 6 NT P A DD 1 LO UV ER 1 0 5/ 29 /9 2 PC O1 82 03 P CO1 82 P ROC UR EM T F/ E XPA NS N JO IN T B OO T RE TR O 20 no ne
P CO 06 70 1 PC O06 7 NT P S UBS TI TU TE G AT E F OR B FV 'S & BA CK FL OW 1 0 2/ 28 /9 2 PC O1 82 05 P CO1 82 T &M IN ST L EX PA NSN J OI NT B OOT R ET RO FI T 5 no ne
P CO 06 80 1 PC O06 8 NT P S .B. R OO F BE AM CO NS TR UC TI ON JO IN T 1 0 2/ 25 /9 2 PC O1 83 01 P CO1 83 N TP R AW WA TE R SA MP LE LI NE E XT ENS IO N 1 03 /3 0/ 94
P CO 07 00 1 PC O07 0 NT P C HAN GE P VC M AS ONR Y FL AS HI NG 1 0 6/ 25 /9 2 PC O1 84 01 P CO1 84 N TP O ZON E PI PI NG M ODI FI CA TI ON S 1 04 /1 8/ 94
P CO 07 10 1 PC O07 1 NT P M ODI FY P IP E SU PPO RT S 1 0 7/ 30 /9 2 PC O1 84 03 P CO1 84 P ROC UR ME NT F / OZO NE P IP IN G M OD S 15 no ne
P CO 07 20 1 PC O07 2 NT P A DD CA RP ET T O COM PU TE R RO OM 1 0 4/ 16 /9 2 PC O1 85 01 P CO1 85 N TP I NST AL L LA RG ER AN GL E CL IP S @ R OO F 1 07 /0 2/ 93
P CO 07 30 1 PC O07 3 NT P 7 /1/ 92 M OD IF IC ATI ON S PE R RFI #8 2 1 0 7/ 13 /9 2 PC O1 86 01 P CO1 86 N TP INC OR RE CT P IP E P AI NT IN G 1 11 /0 1/ 93
P CO 07 50 1 PC O07 5 NT P A DDL C AS T ST ON E 1 0 7/ 23 /9 3 PC O1 86 03 P CO1 86 F IX IN CO RR EC T PIP E PA IN TI NG 3 no ne
P CO 07 60 1 PC O07 6 NT P A AM FW O# 08 69 W ALL P OU R DE LAY 1 0 7/ 16 /9 2 PC O1 87 01 P CO1 87 N TP VAR IO US C ON TR ACT D WG C HA NGE S 1 03 /0 2/ 93
P CO 07 90 1 PC O07 9 NT P P .S. T AP ER ED R OOF M OD IF IC ATI ON S 1 0 6/ 16 /9 3 PC O1 88 01 P CO1 88 N TP LEV EL P RO BE S UPP OR T BR AC KET 1 03 /2 5/ 94
P CO 08 10 1 PC O08 1 NT P C ORE D RI LL O PE NIN GS @ C .B . 1 0 7/ 22 /9 2 PC O1 90 01 P CO1 90 N TP APP LY S EA LE R TO EX PO SE D INT B RI CK 1 05 /2 0/ 94
P CO 08 20 1 PC O08 2 NT P A DDL F LO OR O PE NIN GS @ P IL OT TE ST E Q 1 0 9/ 15 /9 2 PC O1 90 03 P CO1 90 INT M AS ON RY C LEA NI NG & S EAL ER 10 no ne
P CO 08 40 1 PC O08 4 NT P C HEM B LD G 2N D FL CO NS TR J OIN T DE LA Y 1 0 9/ 16 /9 2 PC O1 91 01 P C01 91 N TP L&N C ON TR AC T EXT EN SI ON R EQU ES T 1 02 /0 1/ 94
P CO 08 50 1 PC O08 5 NT P P .S. R OO F PL AN K C HA NG ES 1 0 6/ 24 /9 2 PC O1 92 01 P CO1 92 N TP POS T CL 2/ GA C EFF L SA MP LE PT C HA NG ES 1 05 /2 0/ 94
P CO 08 90 1 PC O08 9 NT P P IPE B LA NK -O FF PL AT E @ 42 " F UT P PG 1 0 3/ 24 /9 2 PC O1 92 03 P CO1 92 A DDL W OR K 1 no ne
P CO 09 00 1 PC O09 0 NT P A LUM IN UM S UP PO RT FR AM IN G & C UR B @ PS 1 0 9/ 04 /9 2 PC O1 94 01 P CO1 94 N TP HAN DI CA PP ED P ARK IN G RE VI SIO NS 1 06 /0 8/ 94
P CO 09 00 3 PC O09 0 F ABR & I NS TA LL MC C SU PP OR T 3 3 n on e PC O1 94 03 P CO1 94 HAN DI CA PP ED P ARK IN G RE VI SIO NS 10 no ne
P CO 09 10 1 PC O09 1 NT P R E M AS ON RY , RO OFI NG , TE RR AZZ O 1 0 9/ 04 /9 2 PC O1 95 01 P CO1 95 N TP ADD R EG UL AT OR S - A IR P UR GE ME TE R CO N 1 06 /0 8/ 94
P CO 09 3B 1 PC O09 3b NT P S TRU CT UR AL S TE EL CH AN GE S 1 0 5/ 20 /9 2 PC O1 95 03 P CO1 95 ADD R EG UL AT OR S 1 no ne
P CO 09 3C 1 PC O09 3c NT P S TRU CT UR AL S TE EL CH AN GE S 1 0 6/ 16 /9 2 PC O1 96 01 P CO1 96 N TP INS TA LL V AL VE @ 48 " RA W WAT ER L IN E 1 06 /1 4/ 94
P CO 09 3F 1 PC O09 3f NT P S TRU CT UR AL S TE EL CH AN GE S 1 0 9/ 25 /9 2 PC O1 96 03 P CO1 96 A DDL W OR K 2 no ne
P CO 09 3H 1 PC O09 3h NT P S TRU CT UR AL S TE EL CH AN GE S 1 1 2/ 16 /9 2 PC O1 97 01 P CO1 97 N TP COR E DR IL L VE NT HO LE S IN P. S. S UM P 1 06 /0 1/ 94
P CO 09 40 1 PC O09 4 NT P M ASO NR Y CH AN GE S 1 0 1/ 04 /9 3 PC O1 97 03 P CO1 97 A DDL W OR K 3 no ne
P CO 09 7A 1 PC O09 7a NT P M ASO NR Y CH AN GE S C HL OR ,L /C BA TH ,O ZO NE 1 1 1/ 10 /9 2 PC O1 98 01 P CO1 98 N TP CHA NG E HD WE D OOR S 20 2 & 203 1 06 /1 6/ 94
P CO 09 7C 1 PC O09 7c NT P M ASO NR Y CH AN GE S C HL OR ,L /C BA TH ,O ZO NE 1 0 2/ 10 /9 3 PC O1 99 01 P CO1 99 N TP LOW ER G AC S AM PLE L IN E FO OT VA LV E 1 06 /1 6/ 94
P CO 10 00 1 PC O10 0 NT P B EAM 3 0A 1 1 0/ 13 /9 2 PC O2 01 01 P CO2 01 N TP FUT F LO RI DE C HEM F D CA RR IER C ON DU IT 1 06 /1 6/ 94
P CO 10 10 1 PC O10 1 NT P A DD PI PE S UP PO RT CH AN NE LS @ GA C P. G. 1 1 1/ 16 /9 2 PC O2 01 03 P CO2 01 A DDL W OR K 2 no ne
P CO 10 20 1 PC O10 2 NT P L ATE RA L BR AC IN G R EQ MT S 1 1 2/ 01 /9 2 PC O2 03 01 P CO2 03 N TP PIT OT T UB E FL OW ME TE R XM TR RE LO C 1 06 /1 6/ 94
P CO 10 5B 1 PC O10 5b NT P M ODI FI ED R OO F PLA NK 1 0 3/ 20 /9 3 PC O2 03 03 P CO2 03 ADD L WO RK 2 no ne
P CO 10 5C 1 PC O10 5c NT P M ODI FI ED R OO F PLA NK 1 0 3/ 25 /9 3 PC O2 04 01 P CO2 04 N TP GAR AG E RE VI SI ONS 1 07 /1 2/ 94
P CO 10 5C 3 PC O10 5 F ABR M OD IF IE D ROO F PL AN K 2 0 n on e PC O2 04 03 P CO2 04 A DDL P RO CU RE ME NT 25 no ne
P CO 10 70 1 PC O10 7 NT P E XTR A NE LS ON S TUD S @ L/ C 1 0 2/ 04 /9 3 PC O2 04 05 P CO2 04 A DDL W OR K U /S PP G 2 no ne
P CO 10 80 1 PC O10 8 NT P S OFF IT & L IN TE L T O CO NC EA L D UC TW OR K 1 0 1/ 20 /9 3 PC O2 11 01 P CO2 11 N TP 48" R AW W AT ER MA IN T IE -I N T O IN TE RI M 1 08 /2 9/ 94
P CO 10 90 1 PC O10 9 NT P R EV BA SE P LA TE , L IN TE L, M ASO NR Y 1 0 3/ 25 /9 3 PC O2 11 03 P CO2 11 PRO CU RE A DD L 48" P IP E 55 no ne
P CO 11 00 1 PC O11 0 NT P S TRU CT UR AL S TE EL MO DI FI CA TIO NS 1 0 4/ 19 /9 3 PC O2 11 05 P CO2 11 INS TA LL T IE -I N P IP E 14 no ne
P CO 11 00 3 PC O11 0a R EPA IR S TO L IM E S IL O ST R STL 6 n on e PC O2 12 01 P CO2 12 N TP ADD L FI LT ER B ACK WA SH T UR BID OM ET ER S 1 06 /1 4/ 94
P CO 11 00 4 PC O11 0b R EPA IR S TO E LE VAT OR S HA FT ST R ST L 5 n on e PC O2 14 01 P CO2 14 N TP GAR AG E RO OF P LAN K CH AN GE S 1 08 /1 7/ 94
P CO 11 10 1 PC O11 1 NT P P IPE M OD S @ WA TER M ET ER C HAM BE R 1 0 4/ 12 /9 3
P CO 11 20 1 PC O11 2 NT P A DDL L IN TE L @ COR RI DO R 11 6 1 0 2/ 03 /9 3
ACT SUC LAG REL ADD ADD ACT SUC LAG REL ADD ADD ACT SUC LAG REL ADD ADD
DUR DAYS DUR DAYS DUR DAYS
PCO00501 1020 0 FS 2 0 PCO097A1 3370 0 FS 3 0 PCO18403 2250 0 FS 15 0
PCO00501 1070 0 FS 2 0 PCO097C1 R3115 0 FS 1 0 PCO18501 3065 0 FS 10 0
PCO00701 2315 0 FS 3 0 PCO10001 2065 0 FS 2 0 PCO18601 PCO18603 0 FS 0 0
PCO00801 3310 0 FS 3 0 PCO10101 2060 1 FF 1 0 PCO18603 3031 0 FS 0 0
PCO00901 3015 0 FS 2 0 PCO10201 2160 0 FS 2 0 PCO18603 R2799 0 FS 0 0
PCO00901 3025 0 FS 9 0 PCO10201 2455 0 FS 2 0 PCO18701 3360 0 FS 1 0
PCO01001 1100 0 FS 6 0 PCO10201 4120 0 FS 2 0 PCO18701 4125 0 FS 2 0
PCO01001 1105 0 FS 12 0 PCO105B1 2225 5 FF 2 0 PCO18801 6015 0 FS 1 0
PCO01201 2335 0 FS 0 10 PCO105C1 PCO105C3 0 FS 0 0 PCO19001 PCO19003 0 FS 0 0
PCO01301 1110 0 FS 1 0 PCO105C3 2185 0 FS 0 0 PCO19003 1390 0 FS 0 0
PCO01401 1055 0 FS 0 0 PCO10701 5030 0 FS 2 0 PCO19101 R1321 0 FS 0 0
PCO01401 1100 0 FS 4 0 PCO10801 4129 2 FF 2 0 PCO19101 R6165 20 FF 0 0
PCO01601 2325 0 FS 0 0 PCO10901 5030 0 FF 0 15 PCO19101 136106 15 FF 0 0
PCO01701 1100 0 FS 2 2 PCO11001 PCO11003 0 FS 0 0 PCO19201 PCO19203 0 FS 0 0
PCO01801 2425 0 FS 0 0 PCO11001 PCO11004 0 FS 0 0 PCO19203 1515 0 FS 0 0
PCO02001 2455 0 FS 1 0 PCO11003 4120 0 FS 0 0 PCO19401 PCO19403 0 FS 0 0
PCO02101 3185 0 FS 0 0 PCO11004 4120 0 FS 0 0 PCO19403 R4515 0 FS 0 0
PCO02201 3150 0 FS 0 0 PCO11101 6335 4 FF 0 0 PCO19501 PCO19503 0 FS 0 0
PCO02201 3155 0 FS 0 0 PCO11201 2450 3 FF 3 0 PCO19503 1500 5 FF 0 0
PCO02601 3155 0 FS 0 0 PCO11601 4120 1 FF 2 0 PCO19601 PCO19603 0 FS 0 0
PCO02701 3030 0 FS 1 0 PCO11701 R4800 0 FS 10 0 PCO19603 1515 0 FS 0 0
PCO02801 3060 0 FS 0 0 PCO11701 R4801 0 FS 2 0 PCO19701 PCO19703 0 FS 0 0
PCO02901 3305 0 FS 0 0 PCO11701 R4802 0 FS 5 0 PCO19703 1515 0 FS 0 0
PCO03001 1140 0 FS 2 0 PCO11701 R4803 0 FS 2 0 PCO19801 1390 5 FF 0 0
PCO03001 2425 0 FS 1 0 PCO11701 R4804 0 FS 2 0 PCO19901 1515 0 FS 0 0
PCO03101 2020 0 FS 3 0 PCO11701 R4805 0 FS 3 0 PCO20101 PCO20103 0 FS 0 0
PCO03201 3030 0 FS 12 0 PCO12001 5050 2 FF 2 0 PCO20103 1515 0 FS 0 0
PCO03301 3085 0 FS 0 0 PCO12101 4120 10 FF 1 0 PCO20301 PCO20303 0 FS 0 0
PCO03401 2330 0 FS 0 0 PCO12401 2230 0 FS 3 0 PCO20303 1515 0 FS 0 0
PCO03501 3410 0 FS 0 0 PCO12401 R4800 0 FS 2 0 PCO20401 PCO20403 0 FS 0 0
PCO03901 2415 0 FS 0 0 PCO12601 5030 0 FS 1 0 PCO20403 PCO20405 0 FS 0 0
PCO03901 2425 0 FS 5 0 PCO12801 1300 1 FF 1 0 PCO20405 5205 0 FS 0 0
PCO04101 5315 0 FS 1 0 PCO12801 4540 0 FS 1 0 PCO20405 5260 30 FS 0 0
PCO04201 1140 0 FS 1 0 PCO13101 2170 1 FF 0 0 PCO21101 PCO21103 0 FS 0 0
PCO04201 3080 0 FS 0 0 PCO13101 3371 1 FF 0 0 PCO21103 PCO21105 3 FS 0 0
PCO04501 4055 0 FS 0 0 PCO13601 R1140 0 FS 2 0 PCO21105 1390 0 FS 0 0
PCO04601 1140 0 FS 0 0 PCO14101 R1495 0 FS 1 0 PCO21105 R4515 0 FS 0 0
PCO04701 4040 0 FS 0 0 PCO14501 1200 0 FS 2 0 PCO21201 R2627 3 FF 3 0
PCO04701 4045 0 FS 1 0 PCO14501 4405 0 FS 1 0
PCO04901 3085 0 FS 4 20 PCO14801 1300 0 FS 2 0
PCO05101 2425 0 FS 6 12 PCO14901 R3665 0 FS 2 0
PCO05201 2425 0 FS 0 0 PCO15001 4135 0 FS 1 0
PCO05301 3415 0 FS 1 0 PCO15101 R1321 1 FF 1 0
PCO05401 2615 0 FS 0 0 PCO15201 R4030 0 FS 2 0
PCO05701 4030 0 FS 0 0 PCO15401 1225 0 FS 0 0
PCO05801 3315 0 FS 1 0 PCO15401 1325 0 FS 0 0
PCO05901 1260 0 FS 0 0 PCO15401 5190 0 FS 0 0
PCO05901 1360 0 FS 0 0 PCO15501 PCO15503 0 FS 0 0
PCO05901 5155 0 FS 0 0 PCO15503 5090 0 FS 0 0
PCO06201 2450 0 FS 1 0 PCO15601 PCO15603 0 FS 0 0
PCO06301 4060 0 FS 2 0 PCO15603 1505 0 FS 0 0
PCO06401 1325 0 FS 0 0 PCO15701 PCO15703 0 FS 0 0
PCO06501 1325 0 FS 0 0 PCO15703 R4115 0 FS 0 0
PCO06601 1260 0 FS 0 0 PCO16001 R1321 1 FF 1 0
PCO06701 2000 0 FS 0 0 PCO16001 136106 15 FF 1 0
PCO06801 3040 0 FS 12 0 PCO16101 PCO16103 0 FS 0 0
PCO07001 3060 0 FS 0 0 PCO16103 1500 0 FS 0 0
PCO07101 2050 0 FS 1 0 PCO16201 PCO16203 0 FS 0 0
PCO07201 1325 0 FS 0 0 PCO16203 R4115 0 FS 0 0
PCO07301 4615 0 FS 2 5 PCO16301 PCO16303 0 FS 0 0
PCO07501 R1495 0 FS 2 0 PCO16303 R4115 0 FS 0 0
PCO07601 4615 2 FS 2 0 PCO16501 R1321 5 FF 0 0
PCO07901 3390 0 FS 2 0 PCO16801 PCO16803 0 FS 0 0
PCO08101 3505 0 FS 2 0 PCO16803 1515 0 FS 0 0
PCO08201 4060 0 FS 2 0 PCO17101 PCO17103 0 FS 0 0
PCO08401 4060 0 FS 2 0 PCO17103 5155 0 FS 3 0
PCO08501 2465 0 FS 1 22 PCO17701 PCO17703 0 FS 0 0
PCO08901 4005 0 FS 1 0 PCO17703 1505 0 FS 0 0
PCO09001 PCO09003 0 FS 0 0 PCO18001 5155 1 FF 0 0
PCO09003 2610 0 FS 0 0 PCO18101 PCO18103 0 FS 0 0
PCO09101 2180 0 FS 1 0 PCO18101 PCO18104 0 FS 0 0
PCO09101 3390 0 FS 1 0 PCO18103 5155 1 FF 0 0
PCO09101 R3395 0 FS 2 0 PCO18104 5155 1 FF 0 0
PCO093B1 2435 0 FS 1 0 PCO18201 PCO18203 0 FS 0 0
PCO093C1 5045 0 FS 2 0 PCO18203 PCO18205 0 FS 0 0
PCO093F1 5045 0 FS 1 0 PCO18205 2041 0 FS 2 0
PCO093H1 3360 0 FS 0 0 PCO18205 3031 0 FS 0 0
PCO093H1 3371 0 FS 1 0 PCO18301 1505 0 FS 1 0
PCO09401 1200 2 FF 2 0 PCO18301 5320 0 FF 2 0
PCO09401 3370 0 FS 1 0 PCO18401 PCO18403 0 FS 0 0
1 9 9 1 1 9 9 2 1 9 9 3 1 9 9 4 1 9 9 5M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N
1 0 0 5
M O B I L I Z A T I O N
3 0 0 0
S E D B A S I N S O G@ 2 4 0 . 4 0 / 2 4 2 . 7 5
3 0 1 5
S E D B A S I N ( N , S , E ) W A L L t o 2 6 4
3 4 0 0
P R E - O Z O N E C O N T A C TB A S I N E X C A V t o 2 4 0 . 2 5
4 0 8 0
C H E M W E S T I N S T LC O N T A I N M E N T L I N E R
4 1 9 0
C H E M W E S T R / SS P A R E B A T C H T A N K
4 1 7 2
C H E M W E S T - L I M E S T OR / S L I M E C O N V B L O W E R S
1 3 0 0
2 N D F L A R C HI N T E R N A L M A S O N R Y
R 1 3 5 5
C H E M W E S T 2 n dF L O O R C A R P E T
1 3 0 5
2 N D F L A R C HC A R P E N T R Y / D R Y W A L L
2 2 3 0
O Z O N E / T R A N S F O R M E R R O O F I N G
4 1 2 5
C H E M W E S TM A S O N R Y T O 2 8 0
3 0 9 0
P I P E G A L L E R Y I N S T L L G P P G
3 3 2 0
C H E M B L D G E A S T S T OA R E A W A L L S t o 2 4 9
3 4 0 5
C H E M B L D G W E S T ( N O R T H ) 2 4 " 3 6 " 4 2 " 6 " U / S P P G
1 0 2 0
S E D B A S I NE X C A V t o 2 3 6 . 1 5
1 0 7 0
S E D B A S I NS O G @ 2 3 6 . 4 0
2 3 2 5
F L U M E F I L T 1 - 2 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5
3 4 1 0
P R E - O Z O N E C O N T A C TB A S I N S O G @ 2 4 2 . 5 0
3 3 1 0
C H E M B L D G E A S TW A L L t o 2 4 3 / / 2 5 0
2 3 9 0
F L U M E U - S H A P Et o 2 5 4 . 8 3 / 2 5 8 . 3 3
3 1 0 0
P I P E G A L L E R YE L E V S L A B @ 2 5 6
3 1 0 5
P I P E G A L L E R Y A R E A W A L L S t o 2 6 3 . 8 4
2 5 1 0
F I L T E R # 1 - 6 W A L K W A Y @2 6 5 . 3 3 [ P R E C A S T = 1 5 d a y s ]
2 2 5 0
O Z O N E R / S 6 "8 " O Z O N E P P G
R 1 3 2 0
C H E M W E S T C O M P U T E RR O O M E Q U I P M E N T
R 1 3 4 5
C H E M W E S T 2 n d F L O O RR U B B E R T I L E F L O O R
R 3 3 1 0
G A C C O N T A C T O R -P . G . S A M P L E P U M P S
2 5 2 0
P I P E G A L L E R Y / F I L T E R S T R S T L t o 2 7 7
3 1 1 5
P I P E G A L L E R Y A R E AE L E V S L A B @ 2 6 4 . 6 7
2 3 5 5
F L U M E F I L T 1 - 2 W A L L t o 2 6 4 . 6 7
2 4 2 5
P U M P S T A E L E VS L A B @ 2 5 0
2 3 7 0
F L U M E F I L T 3 - 6 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5
3 0 8 0
P I P E G A L L E R Y S O G @ 2 4 2 . 5 0
1 0 1 0
C L E A R W E L L / O Z O N E E X C A Vt o 2 2 4 . 7 5 / 2 1 8 . 7 5
2 3 0 0
F L U M E S E X C A Vt o 2 2 4 . 7 5
3 0 7 5
P I P E G A L L E R Y 2 4 "3 6 " 6 " 8 " U / S P P G
2 3 4 0
F L U M E F I L T 1 - 2 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5
2 3 5 0
F L U M E F I L T 1 - 2 W A L Lt o H A U N C H t o 2 4 8 . 6 7
4 3 2 0
C H E M W E S T / S E T T L E D / M I X E DB Y P A S S 4 8 " 5 4 " 6 6 " P P G
2 5 0 0
F I L T E R # 1 - 6 I N S T LF I L T E R U / D R A I N
2 5 2 5
P I P E G A L L E R Y / F I L T E R 1 2 " D E C K P A N E L S
R 3 3 2 0
G A C C O N T A C T O R -P L A N T S E R V I C E L I N E S
R 1 0 6 0
C H E M W E S T 2 n d F L O O RI N S T R U M E N T A T I O N R E V I E W
R 5 0 6 0
G A R A G E -P A I N T I N G
R 5 0 5 0
G A R A G E - H O L L O WM E T A L D O O R S
4 4 6 0
C H E M W E S T R / SC H E M F E E D L I N E S
4 1 4 5
C H E M W E S T / S K Y L I G H T F R A M I N G R O O F I N G i n c S K Y L I G H T
R 4 8 0 0
A S S O R T E D R O O F T O P W O R KF L O C C . / S . B . / F I L T E R / O Z O N E
4 1 7 5
C H E M W E S T R / SK M n O 4 F E E D E R
2 3 9 5
F L U M E W A L Lt o 2 6 3 . 8 3
4 3 1 0
C H E M W E S T / R A W W A T E R 4 8 "P P G w / P R E C O N T A C T B Y P A S S
4 0 5 5
C H E M W E S TW A L L S t o 2 6 3
2 3 8 0
F L U M E W A L L &S L A B t o 2 5 0 . 1 6
2 3 7 5
F L U M E F I L T 3 - 6E L E V S L A B @ 2 4 6 . 4 2
1 1 5 0
F L O C B A S I NC O N C F I L L t o 2 4 7
3 0 2 0
P I P E G A L L E R Y S T R U C B F I L L
1 0 1 5
P U M P S T A T I O NE X C A V t o 2 1 9 . 5 0
2 3 1 5
F L U M E S / P U M PS T A S O G @ 2 2 7
2 3 3 0
F L U M E F I L T 3 - 6 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5
1 0 8 0
F L O C B A S I N F O O T I N GW A L L t o 2 4 7
2 3 4 5
F L U M E F I L T 1 - 2E L E V S L A B @ 2 4 6 . 4 2
3 3 1 5
C H E M B L D G E A S T B E A M4 4 , 4 5 , S L A B @ 2 4 7 . 5 0 , P I L A S @ 2 5 0
4 0 6 0
C H E M W E S T B E A M S& S L A B S t o 2 6 4
4 1 0 0
C H E M W E S T S T R S T LC O L S / B E A M S t o 2 7 5 . 3 3 / 2 8 8 . 3 3
2 5 3 0
P I P E G A L L E R Y / F I L T E R R O O F I N G
R 1 2 7 0
C H E M W E S TP O L Y M E R L I N E S
R 1 3 4 0
C H E M W E S T 2 n dF L O O R V C T F L O O R
R 5 0 3 5
G A R A G E -M I S C . M E T A L S
R 4 5 3 5
S I T E W O R K - C H A I NL I N K F E N C E
R 1 3 5 0
C H E M W E S T 2 n d F L O O RQ U A R R Y T I L E F L O O R
6 1 8 0
C H E M W E S T F I L T E R A I D M I S C P P G & E Q U I P
3 5 2 5
P R E - O Z O N E C O N T A C T B A S I N 8 " D E C K P A N E L S @ 2 8 0 . 6 7
4 1 2 0
C H E M W E S TE L E V S L A B @ 2 7 6
3 3 2 5
C H E M B L D G E A S T C O L S t o 2 6 4 . 6 7
3 3 0 0
C H E M B L D G E A S T I N T L5 4 " U / S P P G @ 2 2 5 . 2 5
1 0 7 5
F L O C B A S I NF O O T I N G @ 2 4 0 . 2 5
1 0 5 0
C L E A R W E L L / O Z O N EI N S T L R O C K A N C H O R S
1 0 6 0
P U M P S T A I N S T LR O C K A N C H O R S
3 1 5 0
F L O C B A S I N S O G @ ~ 2 4 9I N C L G R A D E B E A M
3 3 0 5
C H E M B L D G E A S T S O GS T E P F T G S @ 2 3 0 / / 2 4 0 . 5 0
3 3 6 0
C H E M B L D G E A S T B E A M S4 3 , 4 6 , 4 7 & S L A B @ 2 6 4 . 6 7
3 3 7 5
C H E M B L D G E A S T M A S O N R Y T O 2 8 0
R 1 2 1 5
C H E M W E S TL I M E F E E D E R S
3 3 9 0
C H E M B L D GE A S T R O O F I N G
R 1 2 4 5
C H E M W E S TF I L T E R A I D L I N E S
R 1 3 0 5
C H E M W E S T L A BE Q U I P M E N T / F U R N I T U R E
R 4 6 6 5
Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( W E S T )
R 4 6 6 0
Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( S . E . )
R 1 3 1 0
C H E M W E S T L A BI N S T R U M E N T A T I O N
R 1 2 6 5
C H E M W E S T P O L Y M E RM I X I N G S Y S T E M
R 4 8 0 4
A S S O R T E D R O O F T O P W O R KE L E C T R I C A L R O O M / C . B .
R 1 7 4 1
C H E M B L D G E A S T E L E C A R E A 8 " D E C K P A N E L S @ 2 8 0 . 6 7
2 4 5 5
P U M P S T A M E Z Z P O U RW A L K W A Y @ 2 6 4 . 6 7
1 1 2 0
O Z O N E I N L E T O R I F I C ET R O U G H W A L L S & S U P P W O R K
1 0 6 5
P U M P S T AS O G @ 2 2 2
3 0 0 5
S E D B A S I N S U M P S W A L L t o 2 4 1 . 1 7
1 1 2 5
O Z O N E W A L L S &C A S C A D E t o 2 4 3 . 2 5
1 1 3 5
C L E A R W E L L / O Z O N E I N S T L7 2 x 4 8 S L U I C E G A T E S
2 4 5 0
P U M P S T AM A S O N R Y t o 2 8 3
R 1 7 4 0
C H E M B L D G E A S T C L 2 A R E A 8 " D E C K P A N E L S @ 2 6 6
R 1 0 3 5
C H E M W E S T C O N C R E T E P A D S& C U R B S - 3 R D F L O O R
6 1 3 5
C H E M W E S T 3 R D F L I N S T A L LB A T C H T A N K M I X E R S
R 1 3 1 5
C H E M W E S TL A B P I P I N G
R 4 5 9 0
Y A R D P I P E - 6 " T I E - I NT O H Y D R A N T ( N O R T H W E S T )
5 3 6 0
S I T E S E E D I N G& L A N D S C A P I N G
4 4 1 0
C H E M W E S T A L U M S T O R / SM I S C P P G & E Q : S E A L W A T E R
6 1 3 0
C H E M W E S T 3 R D F L R / SF E E D P U M P S & T A N K S
3 5 3 0
P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o P A R A P E T
3 5 2 0
P R E - O Z O N E C O N T A C TB A S I N M A S O N R Y t o 2 8 0
3 3 7 0
C H E M B L D G E A S T M A S O N R Y T O 2 6 5
4 0 5 0
C H E M W E S T S O G@ 2 4 6 / 2 4 6 . 6 7
1 1 4 0
C L E A R W E L L / O Z O N EE L E V S L A B @ 2 5 0 + / -
1 1 1 5
O Z O N E B A F F L E W A L L St o 2 4 2 . 2 5 / 2 4 7 . 5 0
1 1 1 0
O Z O N E W A L L S t o 2 4 8 . 5 0
1 1 0 0
C L E A R W E L L / O Z O N E S O G @ 2 2 7
3 1 5 5
F L O C B A S I N ( N , S , W ) W A L L t o 2 6 1 . 5 8 / 2 6 4
3 4 1 5
P R E - O Z O N E C . B . E X T W A L Lt o 2 6 1 . 8 3 / 2 6 8 . 3 3 / 2 6 9 . 3 3
3 3 4 5
C H E M B L D G E A S T S T OA R E A E L E V S L A B @ 2 5 0
R 1 7 6 0
C H E M E A S T G L A Z E DS T R U C T U R A L T I L E
2 5 0 5
F I L T E R # 1 - 6 B E A M S @2 6 4 . 6 7 [ P R E C A S T = 1 5 d a y s ]
6 3 1 0
S E D B A S I N M I S CP P G & E Q U I P
R 2 6 2 7
F I L T E R O P E R A T I N GR O O M I N S T R U M E N T A T I O N
4 4 5 5
C H E M W E S T R / S 1 5 "P V C & S A M P L E L I N E S
5 3 5 0
S I T E F I N EG R A D I N G
R 4 5 1 0
S I T E W O R K - D E M O@ P R O P A N E T A N K S
4 4 2 0
C H E M W E S T A L U M S T OR / S I N S T R U M E N T A T I O N
R 2 6 3 5
F I L T E R S - P . G .S A M P L E P U M P S
2 6 0 0
P U M P S T A M I S CP P G & E Q U I P
4 1 8 0
C H E M W E S T R / SP O L Y P H O S P H A T E B A T C H T A N K
4 3 0 0
C H E M W E S T R / SP O L Y P H O S P H A T E T A N K
4 3 0 5
C H E M W E S T I N S T LA L U M S T O T A N K S
4 1 8 5
C H E M W E S T R / SF I L T E R A I D B A T C H T A N K
2 2 0 0
G A C A R E A M I S CP P G & E Q U I P
4 5 0 5
C H E M W E S T B L O W E R R O O M R / S 6 " 8 " 1 2 " A I R P P G
R 5 4 2 5
N O R T H B R A N C HI N T A K E - P A I N T I N G
R 5 4 2 0
N O R T H B R A N C H I N T A K E- I N S T R U M E N T A T I O N
4 5 1 5
C H E M W E S T B L O W E R R O O M R / S M I S C P P G & E Q U I P
6 3 0 5
S E D B A S I N R / S S E D I M E N T A T I O NC O L L E C T O R E Q U I P
R 1 4 1 5
C H E M W E S T 3 r dF L O O R C . M . U .
3 0 6 5
S E D B A S I N / F L O CB A S I N R O O F I N G
3 1 1 0
P I P E G A L L E R Y I N S T LS M P P G & V A L V E S
R 1 4 5 0
C H E M W E S T 2 n d F L O O RD O O R S & W I N D O W S
6 4 2 5
N O R T H B R A N C H R E P L A C EP U M P S # 1 & # 2 & P P G
5 2 1 0
G A R A G E F T GF D N @ 2 4 4
1 5 0 0
O P E R A T I O N A LP U N C H L I S T
R 1 3 3 0
C H E M W E S T 2 n d F L O O RE P O X Y T E R R A Z Z O
R 2 6 2 5
F I L T E R S - P . G .I N S T R U M E N T A T I O N R E V I E W
6 3 0 0
S E D B A S I NR / S 6 " 8 " P P G
4 1 2 6
C H E M W E S TM A S O N R Y T O 2 8 8
4 2 0 0
C H E M W E S T 8 "D E C K P A N E L S @ 2 8 9
1 2 0 0
1 S T F L A R C HI N T E R N A L M A S O N R Y
1 3 3 5
2 N D F L A R C H M I L L W O R K
R 1 1 2 5
C H E M W E S T D I PP L A N T S E R V I C E
1 5 1 0
P R O C E S SP A I N T I N G
5 2 0 5
G A R A G EE X C A V t o 2 4 3
1 5 1 5
I N I T I A L M E C H P E R F T E S T 4 8 H R P L A N T O P E R A T I O N
R 1 3 2 1
I N S T A L L S O F T W A R E& D E B U G S Y S T E M
4 4 6 5
C H E M W E S T R / SM I S C P P G & E Q U I P
R 1 4 4 5
C H E M W E S T 1 s tF L O O R D O O R S
4 1 2 7
C H E M W E S T M A S O N R YT O P A R A P E T
4 1 6 0
C H E M W E S T R / SL I M E S T O S I L O S
4 1 6 5
C H E M W E S T R / SL I M E F E E D E R H O P P E R S
R 1 4 9 5
C H E M W E S TC A S T S T O N E
4 2 0 5
C H E M W E S T R O O F I N G@ 2 8 0 . 6 7 / 2 8 9
R 1 1 1 5
C H E M W E S T C O P P E RW A T E R L I N E S
1 5 2 0
I N I T I A L M E C H P E R FT E S T P U N C H L I S T
1 5 2 5
F I N A L M E C H P E R F T E S T4 8 H R P L A N T O P E R A T I O N
6 1 9 0
C H E M W E S T 3 R D F I L T E RA I D M I S C P P G & E Q U I P
4 1 7 0
C H E M W E S T R / S L I M ED U S T C O L L E C T O R S
4 1 9 5
C H E M W E S T - L I M E S T O R / S 6 " 8 " 1 0 " P P G
R 2 6 0 5
F I L T E R S - P . G .M I S C . P I P E
R 1 3 2 2
C H E M W E S T 3 r d F L O O RI N S T R U M E N T A T I O N R E V I E W
5 2 0 0
G A R A G E D E M O E X G1 6 " W A T E R M A I N
5 2 1 5
G A R A G E S O G@ 2 4 3 . 8 3
R 1 3 3 5
C H E M W E S T 2 n d F L O O RC E R A M I C T I L E F L O O R S / W A L L S
R 3 3 0 5
G A C C O N T A C T O R -I N S T R U M E N T A T I O N R E V I E W
4 1 3 5
C H E M W E S T S T R S T LB E A M S @ 2 8 8 . 3 3
R 4 8 0 5
A S S O R T E D R O O F T O P W O R KC H E M W E S T 3 r d F L O O R
R 1 3 2 5
C H E M W E S T 1 s t F L O O RR U B B E R T I L E F L O O R
5 2 2 0
G A R A G E F T G W A L L St o 2 4 7 . 2 7 + / -
5 2 2 5
G A R A G E B F I L L
R 1 3 7 5
C H E M W E S T 2 n d F L O O RA C O U S T I C A L W A L L T R E A T M E N T
1 2 0 5
1 S T F L A R C HC A R P E N T R Y / D R Y W A L L
4 2 1 0
C H E M W E S TR / S E L E V A T O R
1 3 5 5
2 N D F L A R C H P A I N T I N G
5 2 3 0
G A R A G ES O G @ 2 4 8
5 2 3 5
G A R A G EM A S O N R Y
4 3 4 5
C H E M W E S T R E C I R C M I S CP P G & E Q : S E A L W A T E R S Y S
4 4 0 0
C H E M W E S T A L U M S T O R / SA L U M T R A N S F E R P U M P
5 2 4 0
G A R A G E S T RS T L @ 2 6 0 + / -
5 2 5 0
G A R A G E 8 " D E C KP A N E L S @ 2 6 2 . 6 7
4 4 0 5
C H E M W E S T R / SA i r , A . F . , A . V . P P G
4 4 3 0
C H E M W E S T R / S R A WW A T E R S A M P L E P U M P
5 2 5 5
G A R A G ER O O F I N G
5 2 6 0
G A R A G EA R C H D E T A I L S
4 5 4 0
C H E M W E S T L I M E S T O M I S C P P G & E Q U I P
6 1 1 5
C H E M W E S T F E E D ( L I M E ) M I S C P P G & E Q U I P
R 5 0 2 5
G A R A G E - F / R / PS E T T L I N G B A S I N S
5 2 9 0
G A R A G E B U I L D I N GP U N C H L I S T
1 3 9 0
A R C H I T E C T U R A L &F I N A L P U N C H L I S T
R 5 0 2 0
G A R A G E - F / R / PC O N C R E T E P A D S
R 1 4 1 0
C H E M W E S T 3 r d F L O O RG L A Z E D S T R U C T U R A L T I L E
R 1 3 8 5
C H E M W E S T 2 n d F L O O RA C O U S T I C A L T I L E C E I L I N G
R 5 0 5 5
G A R A G E -C O I L I N G D O O R S
R 1 3 9 5
C H E M W E S T 2 n d F L O O RG Y P S U M B O A R D C E I L I N G
R 1 3 9 0
C H E M W E S T 2 n d F L O O RM E T A L C E I L I N G
R 1 0 5 5
C H E M W E S T 1 s t F L O O RI N S T R U M E N T A T I O N R E V I E W
1 3 2 5
2 N D F L A R C H F L O O R I N G
Pl ot D at e 15 FE B9 5Da ta D at e 10 MA Y9 1Pr oj ec t St ar t10 MA Y9 1Pr oj ec t Fi ni sh26 NO V9 3
(c ) Pr im av er a S ys te ms , Inc .
A c t i v i t y B a r / E a r l y D a t e sa c t i d S U M M A R Y R O L L - U P
P . S . C O N C R E T E C . W . / O Z O N E / G A C C O N C R E T ES . B . / F L O C C C O N C R E T E F L U M E / F I L T E R / P . G . C O N C R E T EC H E M E A S T C O N C R E T E C O N T A C T B A S I N C O N C R E T EC H E M W E S T C O N C R E T E L / C C O N C R E T ES T R U C T U R A L S T E E L M A S O N R YR O O F D E C K M E C H E Q U I P M E N T
W 0 0 X P a g e 1 o f 1
1 9 9 1 1 9 9 2 1 9 9 3 1 9 9 4 1 9 9 5M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N
1 0 1 0
C L E A R W E L L / O Z O N E E X C A Vt o 2 2 4 . 7 5 / 2 1 8 . 7 5
1 1 0 5
C L E A R W E L L W A L L S t o 2 5 0
1 1 3 5
C L E A R W E L L / O Z O N E I N S T L 7 2 x 4 8 S L U I C E G A T E S
2 0 6 5
G A C P P G G A L L E R YE L E V S L A B @ 2 6 9 . 6 7
R 3 3 9 5
G A C C O N T A C T O RP A R A P E T M A S O N R Y
4 1 3 5
C H E M W E S T S T R S T LB E A M S @ 2 8 8 . 3 3
4 1 2 5
C H E M W E S T M A S O N R Y T O 2 8 0
3 4 0 0
P R E - O Z O N E C O N T A C T B A S I N E X C A V t o 2 4 0 . 2 5
1 0 7 5
F L O C B A S I NF O O T I N G @ 2 4 0 . 2 5
1 0 5 5
C L E A R W E L L / O Z O N E 2 S O G @ 2 2 1
1 0 5 0
C L E A R W E L L / O Z O N EI N S T L R O C K A N C H O R S
1 0 1 5
P U M P S T A T I O NE X C A V t o 2 1 9 . 5 0
1 0 6 5
P U M P S T AS O G @ 2 2 2
2 3 3 5
P U M P S T A T I O N W A L L S t o 2 4 8 . 6 7
1 1 2 5
O Z O N E W A L L S &C A S C A D E t o 2 4 3 . 2 5
3 3 1 5
C H E M B L D G E A S T B E A M4 4 , 4 5 , S L A B @ 2 4 7 . 5 0 , P I L A S @ 2 5 0
4 0 3 0
C H E M W E S T W A S T E W A T E RS U M P G R A D E B E A M # 1 7 & 1 8
2 1 8 5
G A C A R E A 8 "D E C K P A N E L @ 2 8 4
R 4 8 0 3
A S S O R T E D R O O F T O PW O R K C H L O R I N E B U I L D I N G
6 0 4 5
C H E M E A S T C L 2 S T O R / S M O N O R A I L
3 3 7 1
C H E M B L D G E A S TM O N O R A I L S U P P O R T S T E E L
2 1 6 0
O Z O N E / T R A N S F O R M E RE L E V S L A B # 1 @ 2 6 4 . 6 7
3 3 4 5
C H E M B L D G E A S T S T OA R E A E L E V S L A B @ 2 5 0
3 4 1 0
P R E - O Z O N E C O N T A C T B A S I N S O G @ 2 4 2 . 5 0
3 0 1 5
S E D B A S I N ( N , S , E ) W A L L t o 2 6 4
1 0 6 0
P U M P S T A I N S T LR O C K A N C H O R S
1 0 2 0
S E D B A S I NE X C A V t o 2 3 6 . 1 5
1 0 7 0
S E D B A S I NS O G @ 2 3 6 . 4 0
1 1 0 0
C L E A R W E L L / O Z O N E S O G @ 2 2 7
1 1 1 0
O Z O N E W A L L S t o 2 4 8 . 5 0
3 1 8 5
F L O C B A S I NW A L K W A Y S @ 2 6 4 . 6 7
2 5 0 0
F I L T E R # 1 - 6 I N S T LF I L T E R U / D R A I N
2 5 0 5
F I L T E R # 1 - 6 B E A M S @2 6 4 . 6 7 [ P R E C A S T = 1 5 d a y s ]
4 5 0 5
C H E M W E S T B L O W E R R O O M R / S 6 " 8 " 1 2 " A I R P P G
2 4 5 0
P U M P S T A M A S O N R Y t o 2 8 3
3 0 8 0
P I P E G A L L E R Y S O G @ 2 4 2 . 5 0
2 3 2 5
F L U M E F I L T 1 - 2 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5
2 3 1 5
F L U M E S / P U M PS T A S O G @ 2 2 7
2 3 0 0
F L U M E S E X C A Vt o 2 2 4 . 7 5
3 0 0 0
S E D B A S I N S O G@ 2 4 0 . 4 0 / 2 4 2 . 7 5
2 3 5 0
F L U M E F I L T 1 - 2 W A L L t o H A U N C H t o 2 4 8 . 6 7
2 4 2 5
P U M P S T A E L E V S L A B @ 2 5 0
4 3 2 0
C H E M W E S T / S E T T L E D / M I X E D B Y P A S S 4 8 " 5 4 " 6 6 " P P G
5 0 5 0
L O B B Y / C O N F E R E N C EC A S T S T O N E & G R A N I T E
R 1 1 2 5
C H E M W E S T D I PP L A N T S E R V I C E
5 0 9 0
L O B B Y / C O N F R O O F I N G
R 4 1 1 5
L O B B Y / C O N F E R E N C EM E T A L C E I L I N G S Y S T E M
6 1 1 5
C H E M W E S T F E E D ( L I M E ) M I S C P P G & E Q U I P
R 1 2 1 5
C H E M W E S TL I M E F E E D E R S
R 3 1 1 5
O Z O N E E Q U I P M E N T B L D G .C A S T S T O N E / B R I C K
2 4 5 5
P U M P S T A M E Z Z P O U RW A L K W A Y @ 2 6 4 . 6 7
3 3 2 0
C H E M B L D G E A S T S T OA R E A W A L L S t o 2 4 9
2 4 3 5
P U M P S T A M E Z Z E R E C TS T R U C S T E E L t o 2 8 3
1 1 2 0
O Z O N E I N L E T O R I F I C ET R O U G H W A L L S & S U P P W O R K
3 0 2 0
P I P E G A L L E R Y S T R U C B F I L L
1 0 8 0
F L O C B A S I N F O O T I N GW A L L t o 2 4 7
3 0 0 5
S E D B A S I N S U M P S W A L L t o 2 4 1 . 1 7
2 0 0 0
C L E A R W E L L @ G A C P P G G A L L E R Y W A L L & S L A B @ 2 3 9 . 9 2
3 0 8 5
P I P E G A L L E R Y W A L L t o 2 5 4 . 8 3
4 0 4 5
C H E M W E S T F T GW A L L b e l o w 2 4 6
1 2 0 0
1 S T F L A R C H I N T E R N A L M A S O N R Y
R 1 4 4 5
C H E M W E S T 1 s tF L O O R D O O R S
3 0 3 1
S E D B A S I N W A T E R T E S T
2 1 8 0
G A C A R E A M A S O N R Y
3 1 0 5
P I P E G A L L E R Y A R E A W A L L S t o 2 6 3 . 8 4
2 0 5 0
G A C A R E A W A L L S & E L E V S L A B t o 2 6 8 . 6 7
3 0 3 0
S E D B A S I N E L E VS L A B @ 2 6 4 . 6 7
3 0 2 5
S E D B A S I N L A U N D E R C O L S W A L L S B E A M S
1 1 5 0
F L O C B A S I NC O N C F I L L t o 2 4 7
2 4 1 5
P U M P S T A P I P E A R E AW A L L S 2 3 6 t o 2 4 8 . 6 7
2 3 5 5
F L U M E F I L T 1 - 2 W A L L t o 2 6 4 . 6 7
4 0 0 5
C H E M W E S T R / S4 2 " U / S F U T P P G
2 3 9 5
F L U M E W A L Lt o 2 6 3 . 8 3
3 1 1 5
P I P E G A L L E R Y A R E A E L E V S L A B @ 2 6 4 . 6 7
4 1 7 2
C H E M W E S T - L I M E S T OR / S L I M E C O N V B L O W E R S
4 4 3 0
C H E M W E S T R / S R A WW A T E R S A M P L E P U M P
4 2 0 5
C H E M W E S T R O O F I N G@ 2 8 0 . 6 7 / 2 8 9
4 1 9 5
C H E M W E S T - L I M E S T O R / S 6 " 8 " 1 0 " P P G
4 1 2 0
C H E M W E S TE L E V S L A B @ 2 7 6
2 0 6 0
G A C P P G G A L L E R Y I N S T L P P G & S U P P @ 2 5 0
2 0 2 0
C L E A R W E L L @ G A C P P GG A L L E R Y W A L L S t o 2 4 8 . 5 0
3 1 5 0
F L O C B A S I N S O G @ ~ 2 4 9I N C L G R A D E B E A M
2 3 3 0
F L U M E F I L T 3 - 6 W A L L S t o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5
6 3 0 5
S E D B A S I N R / S S E D I M E N T A T I O NC O L L E C T O R E Q U I P
3 1 0 0
P I P E G A L L E R YE L E V S L A B @ 2 5 6
6 3 1 0
S E D B A S I N M I S CP P G & E Q U I P
4 1 0 0
C H E M W E S T S T R S T LC O L S / B E A M S t o 2 7 5 . 3 3 / 2 8 8 . 3 3
R 1 4 1 5
C H E M W E S T 3 r dF L O O R C . M . U .
4 1 2 7
C H E M W E S T M A S O N R YT O P A R A P E T
5 2 0 5
G A R A G EE X C A V t o 2 4 3
4 2 0 0
C H E M W E S T 8 "D E C K P A N E L S @ 2 8 9
4 1 6 5
C H E M W E S T R / SL I M E F E E D E R H O P P E R S
2 2 2 5
O Z O N E / T R A N S F O R M E R8 " D E C K P A N E L S @ 2 7 8
4 1 6 0
C H E M W E S T R / SL I M E S T O S I L O S
4 0 5 0
C H E M W E S T S O G@ 2 4 6 / 2 4 6 . 6 7
3 4 1 5
P R E - O Z O N E C . B . E X T W A L L t o 2 6 1 . 8 3 / 2 6 8 . 3 3 / 2 6 9 . 3 3
3 1 5 5
F L O C B A S I N ( N , S , W ) W A L L t o 2 6 1 . 5 8 / 2 6 4
1 1 4 0
C L E A R W E L L / O Z O N E E L E V S L A B @ 2 5 0 + / -
4 3 1 0
C H E M W E S T / R A W W A T E R 4 8 " P P G w / P R E C O N T A C T B Y P A S S
6 3 3 5
Y A R D P P G T R E A T E D W A T E RM E T E R P I T I N T P P G
R 1 1 4 0
C H E M W E S TS . S . A I R L I N E S
4 1 9 0
C H E M W E S T R / SS P A R E B A T C H T A N K
1 5 2 5
F I N A L M E C H P E R F T E S T4 8 H R P L A N T O P E R A T I O N
5 2 1 0
G A R A G E F T GF D N @ 2 4 4
5 2 2 0
G A R A G E F T G W A L L St o 2 4 7 . 2 7 + / -
1 5 1 5
I N I T I A L M E C H P E R F T E S T 4 8 H R P L A N T O P E R A T I O N
1 5 1 0
P R O C E S SP A I N T I N G
4 1 8 5
C H E M W E S T R / SF I L T E R A I D B A T C H T A N K
1 3 0 0
2 N D F L A R C H I N T E R N A L M A S O N R Y
3 4 0 5
C H E M B L D G W E S T ( N O R T H ) 2 4 " 3 6 " 4 2 " 6 " U / S P P G
2 3 8 0
F L U M E W A L L &S L A B t o 2 5 0 . 1 6
3 0 7 5
P I P E G A L L E R Y 2 4 "3 6 " 6 " 8 " U / S P P G
3 0 4 0
S E D B A S I N C O L S & B E A M S t o 2 7 7 . 3 3
3 0 6 0
S E D B A S I N M A S O N R Y t o 2 8 0 . 5 0
4 1 7 5
C H E M W E S T R / SK M n O 4 F E E D E R
6 1 3 5
C H E M W E S T 3 R D F L I N S T A L LB A T C H T A N K M I X E R S
5 1 5 5
L O B B Y / C O N F F I N I S H E S ,F U R N I S H I N G S & S P E C I A L T I E S
R 1 3 2 0
C H E M W E S T C O M P U T E RR O O M E Q U I P M E N T
R 1 3 1 0
C H E M W E S T L A BI N S T R U M E N T A T I O N
R 4 6 6 0
Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( S . E . )
R 4 6 6 5
5 2 9 0R 4 5 1 5
S I T E W O R K -D R I V E " A "
5 2 4 0
G A R A G E S T RS T L @ 2 6 0 + / -
5 2 1 5
G A R A G E S O G@ 2 4 3 . 8 3
R 1 3 2 1
I N S T A L L S O F T W A R E& D E B U G S Y S T E M
R 1 3 0 5
C H E M W E S T L A BE Q U I P M E N T / F U R N I T U R E
5 3 1 5
Y A R D P P G I N S T A L LC O N T A I N M E N T T A N K & P P G
2 2 3 0
O Z O N E / T R A N S F O R M E R R O O F I N G
2 5 3 0
P I P E G A L L E R Y / F I L T E R R O O F I N G
2 5 2 5
P I P E G A L L E R Y / F I L T E R 1 2 " D E C K P A N E L S
2 5 2 0
P I P E G A L L E R Y / F I L T E R S T R S T L t o 2 7 7
2 5 1 0
F I L T E R # 1 - 6 W A L K W A Y @ 2 6 5 . 3 3 [ P R E C A S T = 1 5 d a y s ]
3 3 1 0
C H E M B L D G E A S TW A L L t o 2 4 3 / / 2 5 0
1 1 1 5
O Z O N E B A F F L E W A L L St o 2 4 2 . 2 5 / 2 4 7 . 5 0
3 3 0 0
C H E M B L D G E A S T I N T L5 4 " U / S P P G @ 2 2 5 . 2 5
3 3 0 5
C H E M B L D G E A S T S O GS T E P F T G S @ 2 3 0 / / 2 4 0 . 5 0
3 3 2 5
C H E M B L D G E A S T C O L S t o 2 6 4 . 6 7
3 3 6 0
C H E M B L D G E A S T B E A M S4 3 , 4 6 , 4 7 & S L A B @ 2 6 4 . 6 7
3 3 7 0
C H E M B L D G E A S T M A S O N R Y T O 2 6 5
R 3 3 2 0
G A C C O N T A C T O R -P L A N T S E R V I C E L I N E S
R 3 3 1 0
G A C C O N T A C T O R -P . G . S A M P L E P U M P S
R 2 6 2 7
F I L T E R O P E R A T I N GR O O M I N S T R U M E N T A T I O N
R 1 3 1 5
C H E M W E S TL A B P I P I N G
R 5 4 2 0
N O R T H B R A N C H I N T A K E- I N S T R U M E N T A T I O N
5 2 5 0
G A R A G E 8 " D E C KP A N E L S @ 2 6 2 . 6 7
5 2 2 5
G A R A G E B F I L L
1 5 2 0
I N I T I A L M E C H P E R FT E S T P U N C H L I S T
R 1 0 3 5
C H E M W E S T C O N C R E T E P A D S& C U R B S - 3 R D F L O O R
R 1 7 4 0
C H E M B L D G E A S T C L 2 A R E A 8 " D E C K P A N E L S @ 2 6 6
5 0 3 0
L O B B Y / C O N F M A S O N R Y
2 6 0 0
P U M P S T A M I S C P P G & E Q U I P
2 3 9 0
F L U M E U - S H A P Et o 2 5 4 . 8 3 / 2 5 8 . 3 3
2 3 4 0
F L U M E F I L T 1 - 2 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5
2 3 4 5
F L U M E F I L T 1 - 2E L E V S L A B @ 2 4 6 . 4 2
4 0 4 0
C H E M W E S T C O L S
4 0 6 0
C H E M W E S T B E A M S & S L A B S t o 2 6 4
3 3 7 5
C H E M B L D G E A S T M A S O N R Y T O 2 8 0
6 1 8 0
C H E M W E S T F I L T E R A I D M I S C P P G & E Q U I P
5 2 3 0
G A R A G ES O G @ 2 4 8
5 2 5 5
G A R A G E R O O F I N G
5 2 6 0
G A R A G EA R C H D E T A I L S
5 2 3 5
G A R A G EM A S O N R Y
R 4 8 0 5
A S S O R T E D R O O F T O P W O R KC H E M W E S T 3 r d F L O O R
R 1 7 4 1
C H E M B L D G E A S T E L E C A R E A 8 " D E C K P A N E L S @ 2 8 0 . 6 7
3 0 9 0
P I P E G A L L E R Y I N S T L L G P P G
2 3 7 0
F L U M E F I L T 3 - 6 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5
2 3 7 5
F L U M E F I L T 3 - 6E L E V S L A B @ 2 4 6 . 4 2
4 0 5 5
C H E M W E S T W A L L S t o 2 6 3
4 0 8 0
C H E M W E S T I N S T LC O N T A I N M E N T L I N E R
4 1 4 5
C H E M W E S T / S K Y L I G H T F R A M I N G R O O F I N G i n c S K Y L I G H T
4 1 2 9
C H E M W E S T M A S O N R Y T O 2 7 7
4 6 1 5
C H E M W E S T W E S T O FC L # 3 W A L L S T O 2 6 3
6 3 0 0
S E D B A S I N R / S 6 " 8 " P P G
R 1 4 9 5
C H E M W E S T C A S T S T O N E
1 5 0 0
O P E R A T I O N A LP U N C H L I S T
R 1 2 4 5
C H E M W E S TF I L T E R A I D L I N E S
3 0 6 5
S E D B A S I N / F L O CB A S I N R O O F I N G
R 1 7 6 0
C H E M E A S T G L A Z E DS T R U C T U R A L T I L E
3 5 0 5
P R E - O Z O N E C O N T A C T B A S I N E L E V S L A B @ 2 6 9 . 3 3
4 3 0 5
C H E M W E S T I N S T LA L U M S T O T A N K S
2 1 7 0
G A C A R E A R O O FF R A M I N G S T E E L
4 1 2 6
C H E M W E S TM A S O N R Y T O 2 8 8
4 4 0 0
C H E M W E S T A L U M S T O R / SA L U M T R A N S F E R P U M P
R 2 6 3 5
F I L T E R S - P . G .S A M P L E P U M P S
3 5 2 5
P R E - O Z O N E C O N T A C T B A S I N 8 " D E C K P A N E L S @ 2 8 0 . 6 7
3 5 2 0
P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o 2 8 0
5 0 4 5
L O B B Y / C O N F S T R S T Lt o 2 8 6 . 6 5 - P A R T I A L
R 4 8 0 0
A S S O R T E D R O O F T O P W O R KF L O C C . / S . B . / F I L T E R / O Z O N E
4 1 8 0
C H E M W E S T R / SP O L Y P H O S P H A T E B A T C H T A N K
4 1 7 0
C H E M W E S T R / S L I M ED U S T C O L L E C T O R S
4 3 0 0
C H E M W E S T R / SP O L Y P H O S P H A T E T A N K
2 4 6 5
P U M P S T A 8 "D E C K P A N E L S @ 2 8 4
R 4 8 0 1
A S S O R T E D R O O F T O PW O R K H . S . P . S .
3 5 3 0
P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o P A R A P E T
4 5 4 0
C H E M W E S T L I M E S T O M I S C P P G & E Q U I P
3 3 9 0
C H E M B L D GE A S T R O O F I N G
R 4 8 0 4
A S S O R T E D R O O F T O P W O R KE L E C T R I C A L R O O M / C . B .
R 4 8 0 2
A S S O R T E D R O O F T O PW O R K G A C C O N T A C T O R
R 1 4 1 0
C H E M W E S T 3 r d F L O O RG L A Z E D S T R U C T U R A L T I L E
Pl ot D at e 15 FE B9 5Da ta D at e 1 FE B9 5Pr oj ec t St ar t10 MA Y9 1Pr oj ec t Fi ni sh31 JA N9 5
(c ) Pr im av er a S ys te ms , Inc .
A c t i v i t y B a r / E a r l y D a t e sa c t i d S U M M A R Y R O L L - U P
P . S . C O N C R E T E C . W . / O Z O N E / G A C C O N C R E T ES . B . / F L O C C C O N C R E T E F L U M E / F I L T E R / P . G . C O N C R E T EC H E M E A S T C O N C R E T E C O N T A C T B A S I N C O N C R E T EC H E M W E S T C O N C R E T E L / C C O N C R E T ES T R U C T U R A L S T E E L M A S O N R YR O O F D E C K M E C H E Q U I P M E N T
R 8 U 1 P a g e 1 o f 1
As-Planned v. As-Built Summary
As-Planned v As-Impacted v As-Built
As-Plan of Significant Acitivities
As-Built of Significant Activities
CHANGE ORDERS IMPACTING CRITICAL WORK & IMPACT TO WORK DURATIONS
Actual Actual Crit. # of BasePCO'sPCO TF
Relief From L/D’sExtended Overhead
Add Probability and Risk
• Pertmaster – Monte Carlo -15%/+20%
• Calculate probability of finish by set date
• Track alternate critical paths by frequency
• What was natural risk of project delay?
State of the Art Analysis & PresentationACTIVITY ID
ACTIVITYDESCRIPTION
ORIGDUR
ActualDuration START FINISH
1991 1992 1993 1994 1995MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB
1000 NOTICE TO PROCEED 1 1 10MAY91A 10MAY91A 0
1005 MOBILIZATION 10 10 10MAY91A 23MAY91A 0
1020 SED BASIN EXCAV to 236.15 5 24 24MAY91A 27JUN91A 005 1 0
1070 SED BASIN SOG @ 236.40 15 38 12JUL91A 4SEP91A 005 1 0
3000 SED BASIN SOG @ 240.40/242.75 44 50 15JUL91A 23SEP91A 0
3015 SED BASIN (N,S,E) WALL to 264 64 84 5SEP91A 3JAN92A 009 1 0
1075 FLOC BASIN FOOTING @ 240.25 5 5 14NOV91A 20NOV91A 0
1080 FLOC BASIN FOOTING WALL to 247 5 5 21NOV91A 27NOV91A 0
1150 FLOC BASIN CONC FILL to 247 1 1 29NOV91A 29NOV91A 0
3150 FLOC BASIN SOG @~249 INCL GRADE BEAM 40 25 2DEC91A 7JAN92A 022 1 0
3155 FLOC BASIN (N,S,W) WALL to 261.58/264 50 48 2JAN92A 9MAR92A 022 2 0
3415 PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33 40 73 21APR92A 2OCT92A 053 1 0
3305 CHEM BLDG EAST SOG STEP FTGS @ 230//240.50 6 8 18JUN92A 29JUN92A 029 1 58
3310 CHEM BLDG EAST WALL to 243//250 22 22 1JUL92A 31JUL92A 008 1 58
4050 CHEM WEST SOG @ 246/246.67 30 16 26OCT92A 16NOV92A 0
3315 CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250 16 22 5AUG92A 3SEP92A 058 1 58
4055 CHEM WEST WALLS to 263 30 230 13JUL92A 27AUG93A 045 1 0
3360 CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67 25 28 17DEC92A 27JAN93A 093 2 58
4310 CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS 4 120 10AUG92A 28JAN93A 0
4320 CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG 10 158 27AUG92A 9APR93A 0
4060 CHEM WEST BEAMS & SLABS to 264 50 52 16SEP92A 8MAR93A 084 3 0
3370 CHEM BLDG EAST MASONRY TO 265 10 26 22MAR93A 26APR93A 097 2 58
R1760 CHEM EAST GLAZED STRUCTURAL TILE 10 6 19APR93A 26APR93A 58
3371 CHEM BLDG EAST MONORAIL SUPPORT STEEL 2 4 21APR93A 27APR93A 131 2 66
R1795 CHEM EAST CAST STONE/BRICK 10 67 20APR93A 25JUL93A 330
R1740 CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266 2 8 28APR93A 7MAY93A 58
3375 CHEM BLDG EAST MASONRY TO 280 10 16 8MAY93A 1JUN93A 58
R1741 CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67 2 3 2JUN93A 4JUN93A 58
3385 CHEM BLDG EAST MASONRY TO PARAPET 5 36 5JUN93A 27JUL93A 63
4100 CHEM WEST STR STL COLS/BEAMS to 275.33/288.33 6 12 19MAR93A 5APR93A 0
4120 CHEM WEST ELEV SLAB @ 276 24 30 29MAR93A 7MAY93A 121 5 0
4125 CHEM WEST MASONRY TO 280 10 176 19OCT92A 27JUN93A 187 1 0
R1415 CHEM WEST 3rd FLOOR C.M.U. 8 36 16JUN93A 5AUG93A 29
3525 PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67 5 3 2JUN93A 4JUN93A 0
R4804 ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B. 10 30 4JUN93A 16JUL93A 117 1 0
4126 CHEM WEST MASONRY TO 288 15 15 5JUN93A 27JUN93A 1
3530 PRE-OZONE CONTACT BASIN MASONRY to PARAPET 3 10 17MAY93A 28MAY93A 7
2525 PIPE GALLERY/FILTER 12" DECK PANELS 5 20 21APR93A 18MAY93A 47
3390 CHEM BLDG EAST ROOFING 8 25 28JUL93A 31AUG93A 079 2 0
3535 PRE-OZONE CONTACT BASIN ROOFING 8 9 19AUG93A 31AUG93A 63
4160 CHEM WEST R/S LIME STO SILOS 1 1 23DEC92A 23DEC92A 1
4135 CHEM WEST STR STL BEAMS @ 288.33 10 13 28JUN93A 15JUL93A 150 1 7
4165 CHEM WEST R/S LIME FEEDER HOPPERS 1 4 17MAY93A 20MAY93A 1
4170 CHEM WEST R/S LIME DUST COLLECTORS 2 2 13MAY93A 14MAY93A 1
R6155 ELECTRICAL ROOM MISCELLANEOUS WORK 88 84 16APR93A 13AUG93A 0
4172 CHEM WEST - LIME STO R/S LIME CONV BLOWERS 2 3 10MAY93A 12MAY93A 1
4195 CHEM WEST - LIME STO R/S 6" 8" 10" PPG 10 36 20MAY93A 12JUL93A 1
4200 CHEM WEST 8" DECK PANELS @ 289 20 19 21JUL93A 16AUG93A 1
4127 CHEM WEST MASONRY TO PARAPET 10 11 17AUG93A 31AUG93A 1
R4805 ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR 10 6 24AUG93A 31AUG93A 117 1 21
R1495 CHEM WEST CAST STONE 20 98 1MAR93A 8SEP93A 141 2 1
4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT 8 7 31AUG93A 9SEP93A 21
1300 2ND FL ARCH INTERNAL MASONRY 25 200 19OCT92A 30JUL93A 148 2 1
1200 1ST FL ARCH INTERNAL MASONRY 20 195 26OCT92A 30JUL93A 145 2 17
R6090 2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING 30 33 15JUL93A 30AUG93A 9
4205 CHEM WEST ROOFING @ 280.67/289 8 9 2SEP93A 15SEP93A 1
4505 CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG 5 123 28DEC92A 18JUN93A 10
R1410 CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE 7 42 16JUN93A 13AUG93A 28
R2675 FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS 1 1 30APR93A 30APR93A 65
1320 2ND FL ARCH ELEC R/I 10 214 16NOV92A 17SEP93A 9
R6000 1st FLOOR CHEM WEST PIPING & PANELS 15 15 1AUG93A 21AUG93A 6
R6095 2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS 10 10 1SEP93A 15SEP93A 0
R6115 S.B./FILTERS/FLOCC. PULL FEEDERS 15 17 22AUG93A 15SEP93A 5
R6040 CHEM EAST/PUMP STATION PULL FEEDERS 15 15 1OCT93A 21OCT93A 10
R6140 3rd FLOOR CHEM WEST PULL FEEDERS 10 11 22OCT93A 5NOV93A 15
R1320 CHEM WEST COMPUTER ROOM EQUIPMENT 5 6 25MAR94A 1APR94A 14
R6005 1st FLOOR CHEM WEST PULL FEEDER WIRE 10 10 21AUG93A 5SEP93A 6
R6100 2nd FLOOR CHEM WEST/C.B. BRANCH WIRING 30 54 15SEP93A 30NOV93A 0
R6120 S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS 25 25 16SEP93A 20OCT93A 5
R6045 CHEM EAST/PUMP STATION PULL BRANCH WIRING 20 22 22OCT93A 22NOV93A 10
R1315 CHEM WEST LAB PIPING 2 5 23MAY94A 30MAY94A 4
R6010 1st FLOOR CHEM WEST PULL BRANCH WIRING 15 18 6SEP93A 30SEP93A 6
R1310 CHEM WEST LAB INSTRUMENTATION 5 5 23MAY94A 30MAY94A 4
R6050 CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT 20 21 1APR94A 30APR94A 10
R1305 CHEM WEST LAB EQUIPMENT/FURNITURE 5 6 15FEB94A 22FEB94A 4
R6015 1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT 10 11 1OCT93A 15OCT93A 6
R6125 S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT 15 19 5APR94A 30APR94A 5
R6105 2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE 20 21 1DEC93A 30DEC93A 0
R6165 ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS 30 35 1MAR94A 18APR94A 191 1 0
1500 OPERATIONAL PUNCHLIST 25 36 1MAY94A 21JUN94A 161 2 15
R1321 INSTALL SOFTWARE & DEBUG SYSTEM 20 42 18APR94A 15JUN94A 165 4 0
1510 PROCESS PAINTING 20 21 15APR94A 15MAY94A 15
1505 INITIAL MECH PERF TEST OPER TESTING & TRAINING 20 65 1MAR94A 31MAY94A 156 3 0
1515 INITIAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 201 7 0
1520 INITIAL MECH PERF TEST PUNCHLIST 5 5 20JUN94A 24JUN94A 0
1525 FINAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 0
5205 GARAGE EXCAV to 243 2 0 17AUG94A 22AUG94A 204 1 0
END1 880 DAY PART A COMPLETION 1 0 24JUN94A 24JUN94A END 33
5215 GARAGE SOG @ 243.83 4 0 1SEP94A 8SEP94A 0
5210 GARAGE FTG FDN @ 244 3 108 29AUG94A 31AUG94A 1
5220 GARAGE FTG WALLS to 247.27 +/- 4 0 9SEP94A 16SEP94A 0
5225 GARAGE BFILL 1 0 16SEP94A 19SEP94A 0
5230 GARAGE SOG @ 248 5 0 21SEP94A 29SEP94A 0
5235 GARAGE MASONRY 5 20 3OCT94A 28OCT94A 214 1 0
5240 GARAGE STR STL @ 260 +/- 2 0 18OCT94A 20OCT94A 0
5250 GARAGE 8" DECK PANELS @ 262.67 5 6 21OCT94A 28OCT94A 214 1 0
5255 GARAGE ROOFING 8 31 31OCT94A 13DEC94A 0
5260 GARAGE ARCH DETAILS 2 14 3JAN95A 20JAN95A 204 1 0
5290 GARAGE BUILDING PUNCHLIST 10 5 15JAN95A 20JAN95A 0
1390 ARCHITECTURAL & FINAL PUNCHLIST 20 63 1NOV94A 31JAN95A 190 3 0
1395 OWNER ACCEPTANCE 1 63 1NOV94A 31JAN95A 0
END2 1065 DAY PART B COMPLETION 1 0 31JAN95A 31JAN95A 0
NOTICE TO PROCEED
MOBILIZATION
SED BASIN EXCAV to 236.15
SED BASIN SOG @ 236.40
SED BASIN SOG @ 240.40/242.75
SED BASIN (N,S,E) WALL to 264
FLOC BASIN FOOTING @ 240.25
FLOC BASIN FOOTING WALL to 247
FLOC BASIN CONC FILL to 247
FLOC BASIN SOG @~249 INCL GRADE BEAM
FLOC BASIN (N,S,W) WALL to 261.58/264
PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33
CHEM BLDG EAST SOG STEP FTGS @ 230//240.50
CHEM BLDG EAST WALL to 243//250
CHEM WEST SOG @ 246/246.67
CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250
CHEM WEST WALLS to 263
CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67
CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS
CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG
CHEM WEST BEAMS & SLABS to 264
CHEM BLDG EAST MASONRY TO 265
CHEM EAST GLAZED STRUCTURAL TILE
CHEM BLDG EAST MONORAIL SUPPORT STEEL
CHEM EAST CAST STONE/BRICK
CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266
CHEM BLDG EAST MASONRY TO 280
CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67
CHEM BLDG EAST MASONRY TO PARAPET
CHEM WEST STR STL COLS/BEAMS to 275.33/288.33
CHEM WEST ELEV SLAB @ 276
CHEM WEST MASONRY TO 280
CHEM WEST 3rd FLOOR C.M.U.
PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67
ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B.
CHEM WEST MASONRY TO 288
PRE-OZONE CONTACT BASIN MASONRY to PARAPET
PIPE GALLERY/FILTER 12" DECK PANELS
CHEM BLDG EAST ROOFING
PRE-OZONE CONTACT BASIN ROOFING
CHEM WEST R/S LIME STO SILOS
CHEM WEST STR STL BEAMS @ 288.33
CHEM WEST R/S LIME FEEDER HOPPERS
CHEM WEST R/S LIME DUST COLLECTORS
ELECTRICAL ROOM MISCELLANEOUS WORK
CHEM WEST - LIME STO R/S LIME CONV BLOWERS
CHEM WEST - LIME STO R/S 6" 8" 10" PPG
CHEM WEST 8" DECK PANELS @ 289
CHEM WEST MASONRY TO PARAPET
ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR
CHEM WEST CAST STONE
CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT
2ND FL ARCH INTERNAL MASONRY
1ST FL ARCH INTERNAL MASONRY
2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING
CHEM WEST ROOFING @ 280.67/289
CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG
CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE
FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS
2ND FL ARCH ELEC R/I
1st FLOOR CHEM WEST PIPING & PANELS
2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS
S.B./FILTERS/FLOCC. PULL FEEDERS
CHEM EAST/PUMP STATION PULL FEEDERS
3rd FLOOR CHEM WEST PULL FEEDERS
CHEM WEST COMPUTER ROOM EQUIPMENT
1st FLOOR CHEM WEST PULL FEEDER WIRE
2nd FLOOR CHEM WEST/C.B. BRANCH WIRING
S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS
CHEM EAST/PUMP STATION PULL BRANCH WIRING
CHEM WEST LAB PIPING
1st FLOOR CHEM WEST PULL BRANCH WIRING
CHEM WEST LAB INSTRUMENTATION
CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT
CHEM WEST LAB EQUIPMENT/FURNITURE
1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT
S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT
2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE
ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS
OPERATIONAL PUNCHLIST
INSTALL SOFTWARE & DEBUG SYSTEM
PROCESS PAINTING
INITIAL MECH PERF TEST OPER TESTING & TRAINING
INITIAL MECH PERF TEST 48 HR PLANT OPERATION
INITIAL MECH PERF TEST PUNCHLIST
FINAL MECH PERF TEST 48 HR PLANT OPERATION
GARAGE EXCAV to 243
880 DAY PART A COMPLETION
GARAGE SOG @ 243.83
GARAGE FTG FDN @ 244
GARAGE FTG WALLS to 247.27 +/-
GARAGE BFILL
GARAGE SOG @ 248
GARAGE MASONRY
GARAGE STR STL @ 260 +/-
GARAGE 8" DECK PANELS @ 262.67
GARAGE ROOFING
GARAGE ARCH DETAILS
GARAGE BUILDING PUNCHLIST
ARCHITECTURAL & FINAL PUNCHLIST
OWNER ACCEPTANCE
1065 DAY PART B COMPLETION
Target Date 10MAY91Plot Date 15FEB95Data Date 1FEB95Project Start10MAY91Project Finish31JAN95
(c) Primavera Systems, Inc.
inactive Sheet 1 of 1
As-BuiltAs-PlannedAs-Impacted
nProMaC, Inc
As-PlanSTART
As-PlanFINISH
EARLYSTART
EARLYFINISH
1991 1992 1993 1994M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
24JUN91 29JUL91 25JUL91A 22FEB93A
10JUL91 2AUG91 13SEP91A 9DEC92A
4JUN91 24JUN91 12JUL91A 11JUN92A
6AUG91 19AUG91 22OCT91A 18JUN93A
7FEB92 14FEB92 18JUN92A 27JAN93A
4DEC91 17DEC91 27JAN92A 15JAN93A
9JUL91 10JUL91 8JUN92A 27AUG93A
23AUG91 6SEP91 14SEP92A 22DEC92A
12JUN92 12JUN92 2SEP92A 16AUG93A
16OCT91 19NOV91 25JUN92A 31AUG93A
12SEP91 20SEP91 26JUN92A 15JUL93A
24DEC91 15JAN92 18JUN93A 20DEC93A
9APR92 9APR92 24JUN92A 30SEP93A
4FEB92 6FEB92 16OCT92A 15NOV94A
21JAN93 27JAN93 1MAR94A 15SEP94A
P.S. CONCRETE
C.W./OZONE/GAC CONCRETE
S.B./FLOCC CONCRETE
FLUME/FILTER/P.G. CONCRETE
CHEM EAST CONCRETE
CONTACT BASIN CONCRETE
CHEM WEST CONCRETE
L/C CONCRETE
ROOF DECK
MASONRY
STRUCTURAL STEEL
ROOFING
MECH EQUIPMENT
OZONE SYSTEM
INSTRUMENTATION
Target Date 10MAY91Plot Date 20FEB95Data Date 1FEB95Project Start 10MAY91Project Finish 31JAN95
Primavera Systems, Inc.
Summary Bar/Early Dates
inactive
Critical DesignatorTarget Dates
R8U1 Page 1 of 1
A C T T I T L E O D E S - E C O N D A C T T I T L E O D E S - E C O N D
P C O 0 0 5 0 1 P C O 0 0 5 N T P A D D L R O C K E X C A V & R E I N F C O N C 1 0 6 / 2 1 / 9 1 P C O 1 1 6 0 1 P C O 1 1 6 N T P A D D L W A L L S L E E V E S C H E M W E S T S L A B @ 2 7 6 1 0 5 / 0 5 / 9 3
P C O 0 0 7 0 1 P C O 0 0 7 N T P R E B A R R E V I S I O N S @ F L U M E S 1 0 7 / 2 6 / 9 1 P C O 1 1 7 0 1 P C O 1 1 7 N T P W O O D B L O C K I N G @ R O O F O P E N I N G S 1 0 5 / 2 1 / 9 3
P C O 0 0 8 0 1 P C O 0 0 8 N T P G F L E T T E R 6 / 2 1 / 9 1 1 0 7 / 2 6 / 9 1 P C O 1 2 0 0 1 P C O 1 2 0 N T P A D D L N E L S O N S T U D S @ L / C 1 0 5 / 0 1 / 9 3
P C O 0 0 9 0 1 P C O 0 0 9 a N T P B R I C K L E D G E S & C L O U M N Q U A N T I T I E S 1 0 8 / 1 6 / 9 1 P C O 1 2 1 0 1 P C O 1 2 1 N T P C H E M W E S T 3 R D S L A B / M A S O N R Y I N T E R F A C E 1 0 4 / 2 6 / 9 3
P C O 0 1 0 0 1 P C O 0 1 0 N T P C O N S T R U C T I O N / C O N T R A C T I O N J O I N T S 1 0 9 / 0 6 / 9 1 P C O 1 2 4 0 1 P C O 1 2 4 N T P A D D L R O O F H A T C H E S @ O Z O N E A I R P R E P 1 1 2 / 2 1 / 9 2
P C O 0 1 2 0 1 P C O 0 1 2 N T P R E V I S E D E L E C S U B S T A T I O N 1 0 9 / 2 6 / 9 1 P C O 1 2 6 0 1 P C O 1 2 6 N T P M A S O N R Y C H A N G E S C H L O R , L / C B A T H , O Z O N E 1 0 3 / 2 3 / 9 3
P C O 0 1 3 0 1 P C O 0 1 3 N T P R E B A R C H A N G E S 1 1 0 / 1 0 / 9 1 P C O 1 2 8 0 1 P C O 1 2 8 N T P A R C H M O D S F O R H V A C & P L U M B I N G 1 0 5 / 2 0 / 9 3
P C O 0 1 4 0 1 P C O 0 1 4 N T P W A T E R S T O P C H A N G E S @ C L E A R W E L L & C . B 1 1 0 / 0 1 / 9 1 P C O 1 3 1 0 1 P C O 1 3 1 N T P S T R S T L B E A M R E P A I R S @ C H L O R & G A C 1 0 2 / 1 6 / 9 3
P C O 0 1 6 0 1 P C O 0 1 6 N T P G F M E M O 1 0 / 2 2 / 9 1 1 1 0 / 2 2 / 9 1 P C O 1 3 6 0 1 P C O 1 3 6 N T P M O D I F Y 1 2 " S . S . A I R W A S H P I P E 1 0 6 / 2 1 / 9 3
P C O 0 1 7 0 1 P C O 0 1 7 N T P A D D L R E B A R @ C . W . S U M P S 1 0 9 / 2 5 / 9 1 P C O 1 4 1 0 1 P C O 1 4 1 N T P M A S O N R Y C H A N G E @ C H I M N E Y A R E A 1 0 9 / 0 3 / 9 3
P C O 0 1 8 0 1 P C O 0 1 8 N T P G F M E M O 1 0 - 2 9 - 9 1 1 1 0 / 2 9 / 9 1 P C O 1 4 5 0 1 P C O 1 4 5 N T P M O D S @ E L E V A T O R M A C H I N E R O O M 1 0 7 / 2 6 / 9 3
P C O 0 2 0 0 1 P C O 0 2 0 N T P G F L E T T E R 1 1 / 1 1 / 9 1 1 1 1 / 1 1 / 9 1 P C O 1 4 8 0 1 P C O 1 4 8 N T P C H A N G E D O O R S I Z E @ C O R R 1 2 2 & L I N T E L 1 0 8 / 2 7 / 9 3
P C O 0 2 1 0 1 P C O 0 2 1 N T P F L O C C W L A K W A Y C H A N G E S 1 1 1 / 1 8 / 9 1 P C O 1 4 9 0 1 P C O 1 4 9 N T P S T R F R A M I N G C H A N G E S @ P . S . L O U V E R 1 1 0 / 2 5 / 9 3
P C O 0 2 2 0 1 P C O 0 2 2 N T P F L O C C D R A I N S L O T R E L O C A T I O N 1 1 1 / 2 1 / 9 1 P C O 1 5 0 0 1 P C O 1 5 0 N T P A D D L N E L S O N S T U D S C H E M W E S T 3 R D F L 1 0 7 / 0 2 / 9 3
P C O 0 2 6 0 1 P C O 0 2 6 N T P F L O C C I N T E R M E D B A F F L E W A L L D R A I N 1 1 1 / 2 5 / 9 1 P C O 1 5 1 0 1 P C O 1 5 1 N T P L & N C H L O R I N E S Y S T E M M O D I F I C A T I O N S 1 0 3 / 1 5 / 9 4
P C O 0 2 7 0 1 P C O 0 2 7 N T P S . S . W A L K W A Y C H A N G E S 1 1 2 / 0 3 / 9 1 P C O 1 5 2 0 1 P C O 1 5 2 N T P A D D L M E T A L S T U D F R A M I N G @ L / C 1 1 0 / 1 3 / 9 3
P C O 0 2 8 0 1 P C O 0 2 8 N T P R E L O C A T E S . B . D O O R S 1 1 2 / 0 5 / 9 1 P C O 1 5 4 0 1 P C O 1 5 4 N T P N E W C A R P E T S T Y L E 1 0 9 / 0 2 / 9 3
P C O 0 2 9 0 1 P C O 0 2 9 N T P C H E M E A S T R E B A R M O D I F I C A T I O N 1 1 2 / 1 2 / 9 1 P C O 1 5 5 0 1 P C O 1 5 5 N T P A D D L S U B C O N T R A C T W O R K @ L / C R O O F 1 0 8 / 1 4 / 9 3
P C O 0 3 0 0 1 P C O 0 3 0 N T P H A T C H & A N C H O R B O L T C H A N G E S 1 0 1 / 0 1 / 9 2 P C O 1 5 5 0 3 P C O 1 5 5 S U B C O N T R A C T W O R K @ L / C R O O F O P E N I N G S 1 n o n e
P C O 0 3 1 0 1 P C O 0 3 1 N T P A D D S W A L L P I P E S & B L I N D F L A N G E S 1 1 0 / 1 1 / 9 1 P C O 1 5 6 0 1 P C O 1 5 6 N T P I N S T A L L 3 0 " N J B F V @ N O R T H B R A N C H 1 0 5 / 0 6 / 9 4
P C O 0 3 2 0 1 P C O 0 3 2 N T P E N V I R E X S . B . S L U D G E C O L L F I L L C O N C 1 0 1 / 0 2 / 9 2 P C O 1 5 6 0 3 P C O 1 5 6 I N S T L 3 0 " N J B F V @ N O R T H B R A N C H R W P S 3 n o n e
P C O 0 3 3 0 1 P C O 0 3 3 N T P G F L E T T E R 1 2 / 1 9 / 9 1 1 1 2 / 1 2 / 9 1 P C O 1 5 7 0 1 P C O 1 5 7 N T P R E P L A C E M E N T L O U V E R @ L / C 1 1 2 / 1 0 / 9 3
P C O 0 3 4 0 1 P C O 0 3 4 N T P G F M E M O 1 2 / 2 0 / 9 1 D I M E N S I O N A L C H A N G E S 1 1 2 / 2 0 / 9 1 P C O 1 5 7 0 3 P C O 1 5 7 I N S T A L L R E P L A C E M E N T L O U V E R @ L / C 1 n o n e
P C O 0 3 5 0 1 P C O 0 3 5 N T P G F L E T T E R 1 2 / 1 9 / 9 5 D R W G C L A R I F I C A T N 1 1 2 / 1 9 / 9 1 P C O 1 6 0 0 1 P C O 1 6 0 N T P A D D 2 T U R B I D I M E T E R I N D I C A T O R S T O G A C 1 0 1 / 2 0 / 9 4
P C O 0 3 9 0 1 P C O 0 3 9 N T P C H A N G E S P . S . D R A I N P I P I N G 1 0 1 / 2 9 / 9 2 P C O 1 6 1 0 1 P C O 1 6 1 N T P A D D P R E S S U R E S W I T C H & A L A R M C O N T A C T S 1 0 3 / 0 2 / 9 4
P C O 0 4 1 0 1 P C O 0 4 1 N T P S P I L L C O N T A I N M E N T T A N K R E V I S I O N S 1 0 1 / 2 8 / 9 2 P C O 1 6 1 0 3 P C O 1 6 1 P R E S S U R E S W I T C H & A L A R M C O N T A C T H S P S 1 n o n e
P C O 0 4 2 0 1 P C O 0 4 2 N T P A D D L D R A I N C H A N N E L 1 0 1 / 2 8 / 9 2 P C O 1 6 2 0 1 P C O 1 6 2 N T P A D D 4 S L O T D I F F U S E R S I N L / C 1 0 1 / 1 0 / 9 4
P C O 0 4 5 0 1 P C O 0 4 5 N T P G F M E M O 1 / 2 8 / 9 2 R E F R F I # 3 0 1 0 1 / 2 8 / 9 2 P C O 1 6 2 0 3 P C O 1 6 2 A D D 4 S L O T D I F F U S E R S I N L / C 1 0 n o n e
P C O 0 4 6 0 1 P C O 0 4 6 N T P G F M E M O 2 / 1 8 / 9 2 R E F R F I # 4 7 1 0 2 / 1 8 / 9 2 P C O 1 6 3 0 1 P C O 1 6 3 N T P A D D F I R E W A L L I N L / C 1 0 1 / 1 4 / 9 4
P C O 0 4 7 0 1 P C O 0 4 7 N T P C H E M B L D G C O L & J O I N T C H A N G E S 1 0 2 / 2 6 / 9 2 P C O 1 6 3 0 3 P C O 1 6 3 A D D F I R E W A L L I N L / C T & M 1 3 n o n e
P C O 0 4 9 0 1 P C O 0 4 9 N T P F L U M E O V E R F L O W B O X E L E V R E V & R E L A T E D 1 0 7 / 0 9 / 9 2 P C O 1 6 5 0 1 P C O 1 6 5 N T P C O N T R O L M O N I T O R F R A M E W O R K R E V I S I O N S 1 0 2 / 2 4 / 9 4
P C O 0 5 1 0 1 P C O 0 5 1 N T P P . S . T & M W O R K P E R A A M # 2 0 9 1 0 4 / 2 3 / 9 2 P C O 1 6 8 0 1 P C O 1 6 8 N T P 8 " B Y P A S S A R O U N D 1 0 " P L A N T S E R V I C E 1 0 4 / 2 8 / 9 4
P C O 0 5 2 0 1 P C O 0 5 2 N T P P . S . E L E C T R I C O P E N I N G S R E V I S I O N 1 0 4 / 2 3 / 9 2 P C O 1 6 8 0 3 P C O 1 6 8 8 " B Y P A S S A R O U N D 1 0 " P L A N T S E R V I C E 3 0 n o n e
P C O 0 5 3 0 1 P C O 0 5 3 N T P C . B . W A L L P O U R D E L A Y 1 0 5 / 0 6 / 9 2 P C O 1 7 1 0 1 P C O 1 7 1 N T P M O D I F Y L / C T O I L E T P A R T I T I O N S 1 0 3 / 2 5 / 9 4
P C O 0 5 4 0 1 P C O 0 5 4 N T P H A N D R A I L C H A N G E S 1 0 4 / 1 6 / 9 2 P C O 1 7 1 0 3 P C O 1 7 1 P R O C U R E M E N T R E L / C T O I L E T P A R T I T I O N S 5 2 n o n e
P C O 0 5 7 0 1 P C O 0 5 7 N T P C H E M B L D G S L A B T H I C K N E S S 1 0 5 / 2 2 / 9 2 P C O 1 7 7 0 1 P C O 1 7 7 N T P C H L O R I N A T I O N S Y S T E M M O D I F I C A T I O N S 1 0 4 / 0 7 / 9 4
P C O 0 5 8 0 1 P C O 0 5 8 N T P A D D I T I O N A L W A T E R S T O P 1 0 5 / 2 9 / 9 2 P C O 1 7 7 0 3 P C O 1 7 7 C H L O R I N A T I O N S Y S T E M M O D I F I C A T I O N S 2 0 n o n e
P C O 0 5 9 0 1 P C O 0 5 9 N T P C E R A M I C T I L E C H A N G E S 1 0 6 / 0 1 / 9 2 P C O 1 8 0 0 1 P C O 1 8 0 N T P A D D L P R O J E C T M I L L W O R K 1 0 1 / 0 7 / 9 4
P C O 0 6 2 0 1 P C O 0 6 2 N T P P . S . R A I N P I P I N G R E V I S I O N S 1 0 6 / 1 2 / 9 2 P C O 1 8 1 0 1 P C O 1 8 1 N T P C E I L I N G C H A N G E S 1 0 2 / 2 1 / 9 4
P C O 0 6 3 0 1 P C O 0 6 3 N T P C H E M W E S T S U M P C H A N G E S 1 0 6 / 1 5 / 9 2 P C O 1 8 1 0 3 P C O 1 8 1 A D D L M E T A L S O F F I T E N V I R L A B 2 n o n e
P C O 0 6 4 0 1 P C O 0 6 4 N T P D E L E T E C O M P U T E R A C C E S S F L O O R 1 0 4 / 1 6 / 9 2 P C O 1 8 1 0 4 P C O 1 8 1 R E M O V E I N S U L F R O M M E T A L C E I L I N G 3 n o n e
P C O 0 6 5 0 1 P C O 0 6 5 N T P D E L E T E F L O C C T E R R A Z Z O 1 0 4 / 1 0 / 9 2 P C O 1 8 2 0 1 P C O 1 8 2 N T P E X P A N S I O N J O I N T B O O T R E T R O F I T 1 0 3 / 1 7 / 9 4
P C O 0 6 6 0 1 P C O 0 6 6 N T P A D D 1 L O U V E R 1 0 5 / 2 9 / 9 2 P C O 1 8 2 0 3 P C O 1 8 2 P R O C U R E M T F / E X P A N S N J O I N T B O O T R E T R O 2 0 n o n e
P C O 0 6 7 0 1 P C O 0 6 7 N T P S U B S T I T U T E G A T E F O R B F V ' S & B A C K F L O W 1 0 2 / 2 8 / 9 2 P C O 1 8 2 0 5 P C O 1 8 2 T & M I N S T L E X P A N S N J O I N T B O O T R E T R O F I T 5 n o n e
P C O 0 6 8 0 1 P C O 0 6 8 N T P S . B . R O O F B E A M C O N S T R U C T I O N J O I N T 1 0 2 / 2 5 / 9 2 P C O 1 8 3 0 1 P C O 1 8 3 N T P R A W W A T E R S A M P L E L I N E E X T E N S I O N 1 0 3 / 3 0 / 9 4
P C O 0 7 0 0 1 P C O 0 7 0 N T P C H A N G E P V C M A S O N R Y F L A S H I N G 1 0 6 / 2 5 / 9 2 P C O 1 8 4 0 1 P C O 1 8 4 N T P O Z O N E P I P I N G M O D I F I C A T I O N S 1 0 4 / 1 8 / 9 4
P C O 0 7 1 0 1 P C O 0 7 1 N T P M O D I F Y P I P E S U P P O R T S 1 0 7 / 3 0 / 9 2 P C O 1 8 4 0 3 P C O 1 8 4 P R O C U R M E N T F / O Z O N E P I P I N G M O D S 1 5 n o n e
P C O 0 7 2 0 1 P C O 0 7 2 N T P A D D C A R P E T T O C O M P U T E R R O O M 1 0 4 / 1 6 / 9 2 P C O 1 8 5 0 1 P C O 1 8 5 N T P I N S T A L L L A R G E R A N G L E C L I P S @ R O O F 1 0 7 / 0 2 / 9 3
P C O 0 7 3 0 1 P C O 0 7 3 N T P 7 / 1 / 9 2 M O D I F I C A T I O N S P E R R F I # 8 2 1 0 7 / 1 3 / 9 2 P C O 1 8 6 0 1 P C O 1 8 6 N T P I N C O R R E C T P I P E P A I N T I N G 1 1 1 / 0 1 / 9 3
P C O 0 7 5 0 1 P C O 0 7 5 N T P A D D L C A S T S T O N E 1 0 7 / 2 3 / 9 3 P C O 1 8 6 0 3 P C O 1 8 6 F I X I N C O R R E C T P I P E P A I N T I N G 3 n o n e
P C O 0 7 6 0 1 P C O 0 7 6 N T P A A M F W O # 0 8 6 9 W A L L P O U R D E L A Y 1 0 7 / 1 6 / 9 2 P C O 1 8 7 0 1 P C O 1 8 7 N T P V A R I O U S C O N T R A C T D W G C H A N G E S 1 0 3 / 0 2 / 9 3
P C O 0 7 9 0 1 P C O 0 7 9 N T P P . S . T A P E R E D R O O F M O D I F I C A T I O N S 1 0 6 / 1 6 / 9 3 P C O 1 8 8 0 1 P C O 1 8 8 N T P L E V E L P R O B E S U P P O R T B R A C K E T 1 0 3 / 2 5 / 9 4
P C O 0 8 1 0 1 P C O 0 8 1 N T P C O R E D R I L L O P E N I N G S @ C . B . 1 0 7 / 2 2 / 9 2 P C O 1 9 0 0 1 P C O 1 9 0 N T P A P P L Y S E A L E R T O E X P O S E D I N T B R I C K 1 0 5 / 2 0 / 9 4
P C O 0 8 2 0 1 P C O 0 8 2 N T P A D D L F L O O R O P E N I N G S @ P I L O T T E S T E Q 1 0 9 / 1 5 / 9 2 P C O 1 9 0 0 3 P C O 1 9 0 I N T M A S O N R Y C L E A N I N G & S E A L E R 1 0 n o n e
P C O 0 8 4 0 1 P C O 0 8 4 N T P C H E M B L D G 2 N D F L C O N S T R J O I N T D E L A Y 1 0 9 / 1 6 / 9 2 P C O 1 9 1 0 1 P C 0 1 9 1 N T P L & N C O N T R A C T E X T E N S I O N R E Q U E S T 1 0 2 / 0 1 / 9 4
P C O 0 8 5 0 1 P C O 0 8 5 N T P P . S . R O O F P L A N K C H A N G E S 1 0 6 / 2 4 / 9 2 P C O 1 9 2 0 1 P C O 1 9 2 N T P P O S T C L 2 / G A C E F F L S A M P L E P T C H A N G E S 1 0 5 / 2 0 / 9 4
P C O 0 8 9 0 1 P C O 0 8 9 N T P P I P E B L A N K - O F F P L A T E @ 4 2 " F U T P P G 1 0 3 / 2 4 / 9 2 P C O 1 9 2 0 3 P C O 1 9 2 A D D L W O R K 1 n o n e
P C O 0 9 0 0 1 P C O 0 9 0 N T P A L U M I N U M S U P P O R T F R A M I N G & C U R B @ P S 1 0 9 / 0 4 / 9 2 P C O 1 9 4 0 1 P C O 1 9 4 N T P H A N D I C A P P E D P A R K I N G R E V I S I O N S 1 0 6 / 0 8 / 9 4
P C O 0 9 0 0 3 P C O 0 9 0 F A B R & I N S T A L L M C C S U P P O R T 3 3 n o n e P C O 1 9 4 0 3 P C O 1 9 4 H A N D I C A P P E D P A R K I N G R E V I S I O N S 1 0 n o n e
P C O 0 9 1 0 1 P C O 0 9 1 N T P R E M A S O N R Y , R O O F I N G , T E R R A Z Z O 1 0 9 / 0 4 / 9 2 P C O 1 9 5 0 1 P C O 1 9 5 N T P A D D R E G U L A T O R S - A I R P U R G E M E T E R C O N 1 0 6 / 0 8 / 9 4
P C O 0 9 3 B 1 P C O 0 9 3 b N T P S T R U C T U R A L S T E E L C H A N G E S 1 0 5 / 2 0 / 9 2 P C O 1 9 5 0 3 P C O 1 9 5 A D D R E G U L A T O R S 1 n o n e
P C O 0 9 3 C 1 P C O 0 9 3 c N T P S T R U C T U R A L S T E E L C H A N G E S 1 0 6 / 1 6 / 9 2 P C O 1 9 6 0 1 P C O 1 9 6 N T P I N S T A L L V A L V E @ 4 8 " R A W W A T E R L I N E 1 0 6 / 1 4 / 9 4
P C O 0 9 3 F 1 P C O 0 9 3 f N T P S T R U C T U R A L S T E E L C H A N G E S 1 0 9 / 2 5 / 9 2 P C O 1 9 6 0 3 P C O 1 9 6 A D D L W O R K 2 n o n e
P C O 0 9 3 H 1 P C O 0 9 3 h N T P S T R U C T U R A L S T E E L C H A N G E S 1 1 2 / 1 6 / 9 2 P C O 1 9 7 0 1 P C O 1 9 7 N T P C O R E D R I L L V E N T H O L E S I N P . S . S U M P 1 0 6 / 0 1 / 9 4
P C O 0 9 4 0 1 P C O 0 9 4 N T P M A S O N R Y C H A N G E S 1 0 1 / 0 4 / 9 3 P C O 1 9 7 0 3 P C O 1 9 7 A D D L W O R K 3 n o n e
P C O 0 9 7 A 1 P C O 0 9 7 a N T P M A S O N R Y C H A N G E S C H L O R , L / C B A T H , O Z O N E 1 1 1 / 1 0 / 9 2 P C O 1 9 8 0 1 P C O 1 9 8 N T P C H A N G E H D W E D O O R S 2 0 2 & 2 0 3 1 0 6 / 1 6 / 9 4
P C O 0 9 7 C 1 P C O 0 9 7 c N T P M A S O N R Y C H A N G E S C H L O R , L / C B A T H , O Z O N E 1 0 2 / 1 0 / 9 3 P C O 1 9 9 0 1 P C O 1 9 9 N T P L O W E R G A C S A M P L E L I N E F O O T V A L V E 1 0 6 / 1 6 / 9 4
P C O 1 0 0 0 1 P C O 1 0 0 N T P B E A M 3 0 A 1 1 0 / 1 3 / 9 2 P C O 2 0 1 0 1 P C O 2 0 1 N T P F U T F L O R I D E C H E M F D C A R R I E R C O N D U I T 1 0 6 / 1 6 / 9 4
P C O 1 0 1 0 1 P C O 1 0 1 N T P A D D P I P E S U P P O R T C H A N N E L S @ G A C P . G . 1 1 1 / 1 6 / 9 2 P C O 2 0 1 0 3 P C O 2 0 1 A D D L W O R K 2 n o n e
P C O 1 0 2 0 1 P C O 1 0 2 N T P L A T E R A L B R A C I N G R E Q M T S 1 1 2 / 0 1 / 9 2 P C O 2 0 3 0 1 P C O 2 0 3 N T P P I T O T T U B E F L O W M E T E R X M T R R E L O C 1 0 6 / 1 6 / 9 4
P C O 1 0 5 B 1 P C O 1 0 5 b N T P M O D I F I E D R O O F P L A N K 1 0 3 / 2 0 / 9 3 P C O 2 0 3 0 3 P C O 2 0 3 A D D L W O R K 2 n o n e
P C O 1 0 5 C 1 P C O 1 0 5 c N T P M O D I F I E D R O O F P L A N K 1 0 3 / 2 5 / 9 3 P C O 2 0 4 0 1 P C O 2 0 4 N T P G A R A G E R E V I S I O N S 1 0 7 / 1 2 / 9 4
P C O 1 0 5 C 3 P C O 1 0 5 F A B R M O D I F I E D R O O F P L A N K 2 0 n o n e P C O 2 0 4 0 3 P C O 2 0 4 A D D L P R O C U R E M E N T 2 5 n o n e
P C O 1 0 7 0 1 P C O 1 0 7 N T P E X T R A N E L S O N S T U D S @ L / C 1 0 2 / 0 4 / 9 3 P C O 2 0 4 0 5 P C O 2 0 4 A D D L W O R K U / S P P G 2 n o n e
P C O 1 0 8 0 1 P C O 1 0 8 N T P S O F F I T & L I N T E L T O C O N C E A L D U C T W O R K 1 0 1 / 2 0 / 9 3 P C O 2 1 1 0 1 P C O 2 1 1 N T P 4 8 " R A W W A T E R M A I N T I E - I N T O I N T E R I M 1 0 8 / 2 9 / 9 4
P C O 1 0 9 0 1 P C O 1 0 9 N T P R E V B A S E P L A T E , L I N T E L , M A S O N R Y 1 0 3 / 2 5 / 9 3 P C O 2 1 1 0 3 P C O 2 1 1 P R O C U R E A D D L 4 8 " P I P E 5 5 n o n e
P C O 1 1 0 0 1 P C O 1 1 0 N T P S T R U C T U R A L S T E E L M O D I F I C A T I O N S 1 0 4 / 1 9 / 9 3 P C O 2 1 1 0 5 P C O 2 1 1 I N S T A L L T I E - I N P I P E 1 4 n o n e
P C O 1 1 0 0 3 P C O 1 1 0 a R E P A I R S T O L I M E S I L O S T R S T L 6 n o n e P C O 2 1 2 0 1 P C O 2 1 2 N T P A D D L F I L T E R B A C K W A S H T U R B I D O M E T E R S 1 0 6 / 1 4 / 9 4
P C O 1 1 0 0 4 P C O 1 1 0 b R E P A I R S T O E L E V A T O R S H A F T S T R S T L 5 n o n e P C O 2 1 4 0 1 P C O 2 1 4 N T P G A R A G E R O O F P L A N K C H A N G E S 1 0 8 / 1 7 / 9 4
P C O 1 1 1 0 1 P C O 1 1 1 N T P P I P E M O D S @ W A T E R M E T E R C H A M B E R 1 0 4 / 1 2 / 9 3
P C O 1 1 2 0 1 P C O 1 1 2 N T P A D D L L I N T E L @ C O R R I D O R 1 1 6 1 0 2 / 0 3 / 9 3
ACT SUC LAG REL ADD ADD ACT SUC LAG REL ADD ADD ACT SUC LAG REL ADD ADD
DUR DAYS DUR DAYS DUR DAYS
PCO00501 1020 0 FS 2 0 PCO097A1 3370 0 FS 3 0 PCO18403 2250 0 FS 15 0
PCO00501 1070 0 FS 2 0 PCO097C1 R3115 0 FS 1 0 PCO18501 3065 0 FS 10 0
PCO00701 2315 0 FS 3 0 PCO10001 2065 0 FS 2 0 PCO18601 PCO18603 0 FS 0 0
PCO00801 3310 0 FS 3 0 PCO10101 2060 1 FF 1 0 PCO18603 3031 0 FS 0 0
PCO00901 3015 0 FS 2 0 PCO10201 2160 0 FS 2 0 PCO18603 R2799 0 FS 0 0
PCO00901 3025 0 FS 9 0 PCO10201 2455 0 FS 2 0 PCO18701 3360 0 FS 1 0
PCO01001 1100 0 FS 6 0 PCO10201 4120 0 FS 2 0 PCO18701 4125 0 FS 2 0
PCO01001 1105 0 FS 12 0 PCO105B1 2225 5 FF 2 0 PCO18801 6015 0 FS 1 0
PCO01201 2335 0 FS 0 10 PCO105C1 PCO105C3 0 FS 0 0 PCO19001 PCO19003 0 FS 0 0
PCO01301 1110 0 FS 1 0 PCO105C3 2185 0 FS 0 0 PCO19003 1390 0 FS 0 0
PCO01401 1055 0 FS 0 0 PCO10701 5030 0 FS 2 0 PCO19101 R1321 0 FS 0 0
PCO01401 1100 0 FS 4 0 PCO10801 4129 2 FF 2 0 PCO19101 R6165 20 FF 0 0
PCO01601 2325 0 FS 0 0 PCO10901 5030 0 FF 0 15 PCO19101 136106 15 FF 0 0
PCO01701 1100 0 FS 2 2 PCO11001 PCO11003 0 FS 0 0 PCO19201 PCO19203 0 FS 0 0
PCO01801 2425 0 FS 0 0 PCO11001 PCO11004 0 FS 0 0 PCO19203 1515 0 FS 0 0
PCO02001 2455 0 FS 1 0 PCO11003 4120 0 FS 0 0 PCO19401 PCO19403 0 FS 0 0
PCO02101 3185 0 FS 0 0 PCO11004 4120 0 FS 0 0 PCO19403 R4515 0 FS 0 0
PCO02201 3150 0 FS 0 0 PCO11101 6335 4 FF 0 0 PCO19501 PCO19503 0 FS 0 0
PCO02201 3155 0 FS 0 0 PCO11201 2450 3 FF 3 0 PCO19503 1500 5 FF 0 0
PCO02601 3155 0 FS 0 0 PCO11601 4120 1 FF 2 0 PCO19601 PCO19603 0 FS 0 0
PCO02701 3030 0 FS 1 0 PCO11701 R4800 0 FS 10 0 PCO19603 1515 0 FS 0 0
PCO02801 3060 0 FS 0 0 PCO11701 R4801 0 FS 2 0 PCO19701 PCO19703 0 FS 0 0
PCO02901 3305 0 FS 0 0 PCO11701 R4802 0 FS 5 0 PCO19703 1515 0 FS 0 0
PCO03001 1140 0 FS 2 0 PCO11701 R4803 0 FS 2 0 PCO19801 1390 5 FF 0 0
PCO03001 2425 0 FS 1 0 PCO11701 R4804 0 FS 2 0 PCO19901 1515 0 FS 0 0
PCO03101 2020 0 FS 3 0 PCO11701 R4805 0 FS 3 0 PCO20101 PCO20103 0 FS 0 0
PCO03201 3030 0 FS 12 0 PCO12001 5050 2 FF 2 0 PCO20103 1515 0 FS 0 0
PCO03301 3085 0 FS 0 0 PCO12101 4120 10 FF 1 0 PCO20301 PCO20303 0 FS 0 0
PCO03401 2330 0 FS 0 0 PCO12401 2230 0 FS 3 0 PCO20303 1515 0 FS 0 0
PCO03501 3410 0 FS 0 0 PCO12401 R4800 0 FS 2 0 PCO20401 PCO20403 0 FS 0 0
PCO03901 2415 0 FS 0 0 PCO12601 5030 0 FS 1 0 PCO20403 PCO20405 0 FS 0 0
PCO03901 2425 0 FS 5 0 PCO12801 1300 1 FF 1 0 PCO20405 5205 0 FS 0 0
PCO04101 5315 0 FS 1 0 PCO12801 4540 0 FS 1 0 PCO20405 5260 30 FS 0 0
PCO04201 1140 0 FS 1 0 PCO13101 2170 1 FF 0 0 PCO21101 PCO21103 0 FS 0 0
PCO04201 3080 0 FS 0 0 PCO13101 3371 1 FF 0 0 PCO21103 PCO21105 3 FS 0 0
PCO04501 4055 0 FS 0 0 PCO13601 R1140 0 FS 2 0 PCO21105 1390 0 FS 0 0
PCO04601 1140 0 FS 0 0 PCO14101 R1495 0 FS 1 0 PCO21105 R4515 0 FS 0 0
PCO04701 4040 0 FS 0 0 PCO14501 1200 0 FS 2 0 PCO21201 R2627 3 FF 3 0
PCO04701 4045 0 FS 1 0 PCO14501 4405 0 FS 1 0
PCO04901 3085 0 FS 4 20 PCO14801 1300 0 FS 2 0
PCO05101 2425 0 FS 6 12 PCO14901 R3665 0 FS 2 0
PCO05201 2425 0 FS 0 0 PCO15001 4135 0 FS 1 0
PCO05301 3415 0 FS 1 0 PCO15101 R1321 1 FF 1 0
PCO05401 2615 0 FS 0 0 PCO15201 R4030 0 FS 2 0
PCO05701 4030 0 FS 0 0 PCO15401 1225 0 FS 0 0
PCO05801 3315 0 FS 1 0 PCO15401 1325 0 FS 0 0
PCO05901 1260 0 FS 0 0 PCO15401 5190 0 FS 0 0
PCO05901 1360 0 FS 0 0 PCO15501 PCO15503 0 FS 0 0
PCO05901 5155 0 FS 0 0 PCO15503 5090 0 FS 0 0
PCO06201 2450 0 FS 1 0 PCO15601 PCO15603 0 FS 0 0
PCO06301 4060 0 FS 2 0 PCO15603 1505 0 FS 0 0
PCO06401 1325 0 FS 0 0 PCO15701 PCO15703 0 FS 0 0
PCO06501 1325 0 FS 0 0 PCO15703 R4115 0 FS 0 0
PCO06601 1260 0 FS 0 0 PCO16001 R1321 1 FF 1 0
PCO06701 2000 0 FS 0 0 PCO16001 136106 15 FF 1 0
PCO06801 3040 0 FS 12 0 PCO16101 PCO16103 0 FS 0 0
PCO07001 3060 0 FS 0 0 PCO16103 1500 0 FS 0 0
PCO07101 2050 0 FS 1 0 PCO16201 PCO16203 0 FS 0 0
PCO07201 1325 0 FS 0 0 PCO16203 R4115 0 FS 0 0
PCO07301 4615 0 FS 2 5 PCO16301 PCO16303 0 FS 0 0
PCO07501 R1495 0 FS 2 0 PCO16303 R4115 0 FS 0 0
PCO07601 4615 2 FS 2 0 PCO16501 R1321 5 FF 0 0
PCO07901 3390 0 FS 2 0 PCO16801 PCO16803 0 FS 0 0
PCO08101 3505 0 FS 2 0 PCO16803 1515 0 FS 0 0
PCO08201 4060 0 FS 2 0 PCO17101 PCO17103 0 FS 0 0
PCO08401 4060 0 FS 2 0 PCO17103 5155 0 FS 3 0
PCO08501 2465 0 FS 1 22 PCO17701 PCO17703 0 FS 0 0
PCO08901 4005 0 FS 1 0 PCO17703 1505 0 FS 0 0
PCO09001 PCO09003 0 FS 0 0 PCO18001 5155 1 FF 0 0
PCO09003 2610 0 FS 0 0 PCO18101 PCO18103 0 FS 0 0
PCO09101 2180 0 FS 1 0 PCO18101 PCO18104 0 FS 0 0
PCO09101 3390 0 FS 1 0 PCO18103 5155 1 FF 0 0
PCO09101 R3395 0 FS 2 0 PCO18104 5155 1 FF 0 0
PCO093B1 2435 0 FS 1 0 PCO18201 PCO18203 0 FS 0 0
PCO093C1 5045 0 FS 2 0 PCO18203 PCO18205 0 FS 0 0
PCO093F1 5045 0 FS 1 0 PCO18205 2041 0 FS 2 0
PCO093H1 3360 0 FS 0 0 PCO18205 3031 0 FS 0 0
PCO093H1 3371 0 FS 1 0 PCO18301 1505 0 FS 1 0
PCO09401 1200 2 FF 2 0 PCO18301 5320 0 FF 2 0
PCO09401 3370 0 FS 1 0 PCO18401 PCO18403 0 FS 0 0
1 9 9 1 1 9 9 2 1 9 9 3 1 9 9 4 1 9 9 5M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N
1 0 0 5
M O B I L I Z A T I O N
3 0 0 0
S E D B A S I N S O G@ 2 4 0 . 4 0 / 2 4 2 . 7 5
3 0 1 5
S E D B A S I N ( N , S , E ) W A L L t o 2 6 4
3 4 0 0
P R E - O Z O N E C O N T A C TB A S I N E X C A V t o 2 4 0 . 2 5
4 0 8 0
C H E M W E S T I N S T LC O N T A I N M E N T L I N E R
4 1 9 0
C H E M W E S T R / SS P A R E B A T C H T A N K
4 1 7 2
C H E M W E S T - L I M E S T OR / S L I M E C O N V B L O W E R S
1 3 0 0
2 N D F L A R C HI N T E R N A L M A S O N R Y
R 1 3 5 5
C H E M W E S T 2 n dF L O O R C A R P E T
1 3 0 5
2 N D F L A R C HC A R P E N T R Y / D R Y W A L L
2 2 3 0
O Z O N E / T R A N S F O R M E R R O O F I N G
4 1 2 5
C H E M W E S TM A S O N R Y T O 2 8 0
3 0 9 0
P I P E G A L L E R Y I N S T L L G P P G
3 3 2 0
C H E M B L D G E A S T S T OA R E A W A L L S t o 2 4 9
3 4 0 5
C H E M B L D G W E S T ( N O R T H ) 2 4 " 3 6 " 4 2 " 6 " U / S P P G
1 0 2 0
S E D B A S I NE X C A V t o 2 3 6 . 1 5
1 0 7 0
S E D B A S I NS O G @ 2 3 6 . 4 0
2 3 2 5
F L U M E F I L T 1 - 2 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5
3 4 1 0
P R E - O Z O N E C O N T A C TB A S I N S O G @ 2 4 2 . 5 0
3 3 1 0
C H E M B L D G E A S TW A L L t o 2 4 3 / / 2 5 0
2 3 9 0
F L U M E U - S H A P Et o 2 5 4 . 8 3 / 2 5 8 . 3 3
3 1 0 0
P I P E G A L L E R YE L E V S L A B @ 2 5 6
3 1 0 5
P I P E G A L L E R Y A R E A W A L L S t o 2 6 3 . 8 4
2 5 1 0
F I L T E R # 1 - 6 W A L K W A Y @2 6 5 . 3 3 [ P R E C A S T = 1 5 d a y s ]
2 2 5 0
O Z O N E R / S 6 "8 " O Z O N E P P G
R 1 3 2 0
C H E M W E S T C O M P U T E RR O O M E Q U I P M E N T
R 1 3 4 5
C H E M W E S T 2 n d F L O O RR U B B E R T I L E F L O O R
R 3 3 1 0
G A C C O N T A C T O R -P . G . S A M P L E P U M P S
2 5 2 0
P I P E G A L L E R Y / F I L T E R S T R S T L t o 2 7 7
3 1 1 5
P I P E G A L L E R Y A R E AE L E V S L A B @ 2 6 4 . 6 7
2 3 5 5
F L U M E F I L T 1 - 2 W A L L t o 2 6 4 . 6 7
2 4 2 5
P U M P S T A E L E VS L A B @ 2 5 0
2 3 7 0
F L U M E F I L T 3 - 6 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5
3 0 8 0
P I P E G A L L E R Y S O G @ 2 4 2 . 5 0
1 0 1 0
C L E A R W E L L / O Z O N E E X C A Vt o 2 2 4 . 7 5 / 2 1 8 . 7 5
2 3 0 0
F L U M E S E X C A Vt o 2 2 4 . 7 5
3 0 7 5
P I P E G A L L E R Y 2 4 "3 6 " 6 " 8 " U / S P P G
2 3 4 0
F L U M E F I L T 1 - 2 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5
2 3 5 0
F L U M E F I L T 1 - 2 W A L Lt o H A U N C H t o 2 4 8 . 6 7
4 3 2 0
C H E M W E S T / S E T T L E D / M I X E DB Y P A S S 4 8 " 5 4 " 6 6 " P P G
2 5 0 0
F I L T E R # 1 - 6 I N S T LF I L T E R U / D R A I N
2 5 2 5
P I P E G A L L E R Y / F I L T E R 1 2 " D E C K P A N E L S
R 3 3 2 0
G A C C O N T A C T O R -P L A N T S E R V I C E L I N E S
R 1 0 6 0
C H E M W E S T 2 n d F L O O RI N S T R U M E N T A T I O N R E V I E W
R 5 0 6 0
G A R A G E -P A I N T I N G
R 5 0 5 0
G A R A G E - H O L L O WM E T A L D O O R S
4 4 6 0
C H E M W E S T R / SC H E M F E E D L I N E S
4 1 4 5
C H E M W E S T / S K Y L I G H T F R A M I N G R O O F I N G i n c S K Y L I G H T
R 4 8 0 0
A S S O R T E D R O O F T O P W O R KF L O C C . / S . B . / F I L T E R / O Z O N E
4 1 7 5
C H E M W E S T R / SK M n O 4 F E E D E R
2 3 9 5
F L U M E W A L Lt o 2 6 3 . 8 3
4 3 1 0
C H E M W E S T / R A W W A T E R 4 8 "P P G w / P R E C O N T A C T B Y P A S S
4 0 5 5
C H E M W E S TW A L L S t o 2 6 3
2 3 8 0
F L U M E W A L L &S L A B t o 2 5 0 . 1 6
2 3 7 5
F L U M E F I L T 3 - 6E L E V S L A B @ 2 4 6 . 4 2
1 1 5 0
F L O C B A S I NC O N C F I L L t o 2 4 7
3 0 2 0
P I P E G A L L E R Y S T R U C B F I L L
1 0 1 5
P U M P S T A T I O NE X C A V t o 2 1 9 . 5 0
2 3 1 5
F L U M E S / P U M PS T A S O G @ 2 2 7
2 3 3 0
F L U M E F I L T 3 - 6 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5
1 0 8 0
F L O C B A S I N F O O T I N GW A L L t o 2 4 7
2 3 4 5
F L U M E F I L T 1 - 2E L E V S L A B @ 2 4 6 . 4 2
3 3 1 5
C H E M B L D G E A S T B E A M4 4 , 4 5 , S L A B @ 2 4 7 . 5 0 , P I L A S @ 2 5 0
4 0 6 0
C H E M W E S T B E A M S& S L A B S t o 2 6 4
4 1 0 0
C H E M W E S T S T R S T LC O L S / B E A M S t o 2 7 5 . 3 3 / 2 8 8 . 3 3
2 5 3 0
P I P E G A L L E R Y / F I L T E R R O O F I N G
R 1 2 7 0
C H E M W E S TP O L Y M E R L I N E S
R 1 3 4 0
C H E M W E S T 2 n dF L O O R V C T F L O O R
R 5 0 3 5
G A R A G E -M I S C . M E T A L S
R 4 5 3 5
S I T E W O R K - C H A I NL I N K F E N C E
R 1 3 5 0
C H E M W E S T 2 n d F L O O RQ U A R R Y T I L E F L O O R
6 1 8 0
C H E M W E S T F I L T E R A I D M I S C P P G & E Q U I P
3 5 2 5
P R E - O Z O N E C O N T A C T B A S I N 8 " D E C K P A N E L S @ 2 8 0 . 6 7
4 1 2 0
C H E M W E S TE L E V S L A B @ 2 7 6
3 3 2 5
C H E M B L D G E A S T C O L S t o 2 6 4 . 6 7
3 3 0 0
C H E M B L D G E A S T I N T L5 4 " U / S P P G @ 2 2 5 . 2 5
1 0 7 5
F L O C B A S I NF O O T I N G @ 2 4 0 . 2 5
1 0 5 0
C L E A R W E L L / O Z O N EI N S T L R O C K A N C H O R S
1 0 6 0
P U M P S T A I N S T LR O C K A N C H O R S
3 1 5 0
F L O C B A S I N S O G @ ~ 2 4 9I N C L G R A D E B E A M
3 3 0 5
C H E M B L D G E A S T S O GS T E P F T G S @ 2 3 0 / / 2 4 0 . 5 0
3 3 6 0
C H E M B L D G E A S T B E A M S4 3 , 4 6 , 4 7 & S L A B @ 2 6 4 . 6 7
3 3 7 5
C H E M B L D G E A S T M A S O N R Y T O 2 8 0
R 1 2 1 5
C H E M W E S TL I M E F E E D E R S
3 3 9 0
C H E M B L D GE A S T R O O F I N G
R 1 2 4 5
C H E M W E S TF I L T E R A I D L I N E S
R 1 3 0 5
C H E M W E S T L A BE Q U I P M E N T / F U R N I T U R E
R 4 6 6 5
Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( W E S T )
R 4 6 6 0
Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( S . E . )
R 1 3 1 0
C H E M W E S T L A BI N S T R U M E N T A T I O N
R 1 2 6 5
C H E M W E S T P O L Y M E RM I X I N G S Y S T E M
R 4 8 0 4
A S S O R T E D R O O F T O P W O R KE L E C T R I C A L R O O M / C . B .
R 1 7 4 1
C H E M B L D G E A S T E L E C A R E A 8 " D E C K P A N E L S @ 2 8 0 . 6 7
2 4 5 5
P U M P S T A M E Z Z P O U RW A L K W A Y @ 2 6 4 . 6 7
1 1 2 0
O Z O N E I N L E T O R I F I C ET R O U G H W A L L S & S U P P W O R K
1 0 6 5
P U M P S T AS O G @ 2 2 2
3 0 0 5
S E D B A S I N S U M P S W A L L t o 2 4 1 . 1 7
1 1 2 5
O Z O N E W A L L S &C A S C A D E t o 2 4 3 . 2 5
1 1 3 5
C L E A R W E L L / O Z O N E I N S T L7 2 x 4 8 S L U I C E G A T E S
2 4 5 0
P U M P S T AM A S O N R Y t o 2 8 3
R 1 7 4 0
C H E M B L D G E A S T C L 2 A R E A 8 " D E C K P A N E L S @ 2 6 6
R 1 0 3 5
C H E M W E S T C O N C R E T E P A D S& C U R B S - 3 R D F L O O R
6 1 3 5
C H E M W E S T 3 R D F L I N S T A L LB A T C H T A N K M I X E R S
R 1 3 1 5
C H E M W E S TL A B P I P I N G
R 4 5 9 0
Y A R D P I P E - 6 " T I E - I NT O H Y D R A N T ( N O R T H W E S T )
5 3 6 0
S I T E S E E D I N G& L A N D S C A P I N G
4 4 1 0
C H E M W E S T A L U M S T O R / SM I S C P P G & E Q : S E A L W A T E R
6 1 3 0
C H E M W E S T 3 R D F L R / SF E E D P U M P S & T A N K S
3 5 3 0
P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o P A R A P E T
3 5 2 0
P R E - O Z O N E C O N T A C TB A S I N M A S O N R Y t o 2 8 0
3 3 7 0
C H E M B L D G E A S T M A S O N R Y T O 2 6 5
4 0 5 0
C H E M W E S T S O G@ 2 4 6 / 2 4 6 . 6 7
1 1 4 0
C L E A R W E L L / O Z O N EE L E V S L A B @ 2 5 0 + / -
1 1 1 5
O Z O N E B A F F L E W A L L St o 2 4 2 . 2 5 / 2 4 7 . 5 0
1 1 1 0
O Z O N E W A L L S t o 2 4 8 . 5 0
1 1 0 0
C L E A R W E L L / O Z O N E S O G @ 2 2 7
3 1 5 5
F L O C B A S I N ( N , S , W ) W A L L t o 2 6 1 . 5 8 / 2 6 4
3 4 1 5
P R E - O Z O N E C . B . E X T W A L Lt o 2 6 1 . 8 3 / 2 6 8 . 3 3 / 2 6 9 . 3 3
3 3 4 5
C H E M B L D G E A S T S T OA R E A E L E V S L A B @ 2 5 0
R 1 7 6 0
C H E M E A S T G L A Z E DS T R U C T U R A L T I L E
2 5 0 5
F I L T E R # 1 - 6 B E A M S @2 6 4 . 6 7 [ P R E C A S T = 1 5 d a y s ]
6 3 1 0
S E D B A S I N M I S CP P G & E Q U I P
R 2 6 2 7
F I L T E R O P E R A T I N GR O O M I N S T R U M E N T A T I O N
4 4 5 5
C H E M W E S T R / S 1 5 "P V C & S A M P L E L I N E S
5 3 5 0
S I T E F I N EG R A D I N G
R 4 5 1 0
S I T E W O R K - D E M O@ P R O P A N E T A N K S
4 4 2 0
C H E M W E S T A L U M S T OR / S I N S T R U M E N T A T I O N
R 2 6 3 5
F I L T E R S - P . G .S A M P L E P U M P S
2 6 0 0
P U M P S T A M I S CP P G & E Q U I P
4 1 8 0
C H E M W E S T R / SP O L Y P H O S P H A T E B A T C H T A N K
4 3 0 0
C H E M W E S T R / SP O L Y P H O S P H A T E T A N K
4 3 0 5
C H E M W E S T I N S T LA L U M S T O T A N K S
4 1 8 5
C H E M W E S T R / SF I L T E R A I D B A T C H T A N K
2 2 0 0
G A C A R E A M I S CP P G & E Q U I P
4 5 0 5
C H E M W E S T B L O W E R R O O M R / S 6 " 8 " 1 2 " A I R P P G
R 5 4 2 5
N O R T H B R A N C HI N T A K E - P A I N T I N G
R 5 4 2 0
N O R T H B R A N C H I N T A K E- I N S T R U M E N T A T I O N
4 5 1 5
C H E M W E S T B L O W E R R O O M R / S M I S C P P G & E Q U I P
6 3 0 5
S E D B A S I N R / S S E D I M E N T A T I O NC O L L E C T O R E Q U I P
R 1 4 1 5
C H E M W E S T 3 r dF L O O R C . M . U .
3 0 6 5
S E D B A S I N / F L O CB A S I N R O O F I N G
3 1 1 0
P I P E G A L L E R Y I N S T LS M P P G & V A L V E S
R 1 4 5 0
C H E M W E S T 2 n d F L O O RD O O R S & W I N D O W S
6 4 2 5
N O R T H B R A N C H R E P L A C EP U M P S # 1 & # 2 & P P G
5 2 1 0
G A R A G E F T GF D N @ 2 4 4
1 5 0 0
O P E R A T I O N A LP U N C H L I S T
R 1 3 3 0
C H E M W E S T 2 n d F L O O RE P O X Y T E R R A Z Z O
R 2 6 2 5
F I L T E R S - P . G .I N S T R U M E N T A T I O N R E V I E W
6 3 0 0
S E D B A S I NR / S 6 " 8 " P P G
4 1 2 6
C H E M W E S TM A S O N R Y T O 2 8 8
4 2 0 0
C H E M W E S T 8 "D E C K P A N E L S @ 2 8 9
1 2 0 0
1 S T F L A R C HI N T E R N A L M A S O N R Y
1 3 3 5
2 N D F L A R C H M I L L W O R K
R 1 1 2 5
C H E M W E S T D I PP L A N T S E R V I C E
1 5 1 0
P R O C E S SP A I N T I N G
5 2 0 5
G A R A G EE X C A V t o 2 4 3
1 5 1 5
I N I T I A L M E C H P E R F T E S T 4 8 H R P L A N T O P E R A T I O N
R 1 3 2 1
I N S T A L L S O F T W A R E& D E B U G S Y S T E M
4 4 6 5
C H E M W E S T R / SM I S C P P G & E Q U I P
R 1 4 4 5
C H E M W E S T 1 s tF L O O R D O O R S
4 1 2 7
C H E M W E S T M A S O N R YT O P A R A P E T
4 1 6 0
C H E M W E S T R / SL I M E S T O S I L O S
4 1 6 5
C H E M W E S T R / SL I M E F E E D E R H O P P E R S
R 1 4 9 5
C H E M W E S TC A S T S T O N E
4 2 0 5
C H E M W E S T R O O F I N G@ 2 8 0 . 6 7 / 2 8 9
R 1 1 1 5
C H E M W E S T C O P P E RW A T E R L I N E S
1 5 2 0
I N I T I A L M E C H P E R FT E S T P U N C H L I S T
1 5 2 5
F I N A L M E C H P E R F T E S T4 8 H R P L A N T O P E R A T I O N
6 1 9 0
C H E M W E S T 3 R D F I L T E RA I D M I S C P P G & E Q U I P
4 1 7 0
C H E M W E S T R / S L I M ED U S T C O L L E C T O R S
4 1 9 5
C H E M W E S T - L I M E S T O R / S 6 " 8 " 1 0 " P P G
R 2 6 0 5
F I L T E R S - P . G .M I S C . P I P E
R 1 3 2 2
C H E M W E S T 3 r d F L O O RI N S T R U M E N T A T I O N R E V I E W
5 2 0 0
G A R A G E D E M O E X G1 6 " W A T E R M A I N
5 2 1 5
G A R A G E S O G@ 2 4 3 . 8 3
R 1 3 3 5
C H E M W E S T 2 n d F L O O RC E R A M I C T I L E F L O O R S / W A L L S
R 3 3 0 5
G A C C O N T A C T O R -I N S T R U M E N T A T I O N R E V I E W
4 1 3 5
C H E M W E S T S T R S T LB E A M S @ 2 8 8 . 3 3
R 4 8 0 5
A S S O R T E D R O O F T O P W O R KC H E M W E S T 3 r d F L O O R
R 1 3 2 5
C H E M W E S T 1 s t F L O O RR U B B E R T I L E F L O O R
5 2 2 0
G A R A G E F T G W A L L St o 2 4 7 . 2 7 + / -
5 2 2 5
G A R A G E B F I L L
R 1 3 7 5
C H E M W E S T 2 n d F L O O RA C O U S T I C A L W A L L T R E A T M E N T
1 2 0 5
1 S T F L A R C HC A R P E N T R Y / D R Y W A L L
4 2 1 0
C H E M W E S TR / S E L E V A T O R
1 3 5 5
2 N D F L A R C H P A I N T I N G
5 2 3 0
G A R A G ES O G @ 2 4 8
5 2 3 5
G A R A G EM A S O N R Y
4 3 4 5
C H E M W E S T R E C I R C M I S CP P G & E Q : S E A L W A T E R S Y S
4 4 0 0
C H E M W E S T A L U M S T O R / SA L U M T R A N S F E R P U M P
5 2 4 0
G A R A G E S T RS T L @ 2 6 0 + / -
5 2 5 0
G A R A G E 8 " D E C KP A N E L S @ 2 6 2 . 6 7
4 4 0 5
C H E M W E S T R / SA i r , A . F . , A . V . P P G
4 4 3 0
C H E M W E S T R / S R A WW A T E R S A M P L E P U M P
5 2 5 5
G A R A G ER O O F I N G
5 2 6 0
G A R A G EA R C H D E T A I L S
4 5 4 0
C H E M W E S T L I M E S T O M I S C P P G & E Q U I P
6 1 1 5
C H E M W E S T F E E D ( L I M E ) M I S C P P G & E Q U I P
R 5 0 2 5
G A R A G E - F / R / PS E T T L I N G B A S I N S
5 2 9 0
G A R A G E B U I L D I N GP U N C H L I S T
1 3 9 0
A R C H I T E C T U R A L &F I N A L P U N C H L I S T
R 5 0 2 0
G A R A G E - F / R / PC O N C R E T E P A D S
R 1 4 1 0
C H E M W E S T 3 r d F L O O RG L A Z E D S T R U C T U R A L T I L E
R 1 3 8 5
C H E M W E S T 2 n d F L O O RA C O U S T I C A L T I L E C E I L I N G
R 5 0 5 5
G A R A G E -C O I L I N G D O O R S
R 1 3 9 5
C H E M W E S T 2 n d F L O O RG Y P S U M B O A R D C E I L I N G
R 1 3 9 0
C H E M W E S T 2 n d F L O O RM E T A L C E I L I N G
R 1 0 5 5
C H E M W E S T 1 s t F L O O RI N S T R U M E N T A T I O N R E V I E W
1 3 2 5
2 N D F L A R C H F L O O R I N G
P l o t D a t e 1 5 F E B 9 5D a t a D a t e 1 0 M A Y 9 1P r o j e c t S t a r t1 0 M A Y 9 1P r o j e c t F i n i s h2 6 N O V 9 3
( c ) P r i m a v e r a S y s t e m s , I n c .
A c t i v i t y B a r / E a r l y D a t e sa c t i d S U M M A R Y R O L L - U P
P . S . C O N C R E T E C . W . / O Z O N E / G A C C O N C R E T ES . B . / F L O C C C O N C R E T E F L U M E / F I L T E R / P . G . C O N C R E T EC H E M E A S T C O N C R E T E C O N T A C T B A S I N C O N C R E T EC H E M W E S T C O N C R E T E L / C C O N C R E T ES T R U C T U R A L S T E E L M A S O N R YR O O F D E C K M E C H E Q U I P M E N T
W 0 0 X P a g e 1 o f 1
1 9 9 1 1 9 9 2 1 9 9 3 1 9 9 4 1 9 9 5
M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N
1 0 1 0
C L E A R W E L L / O Z O N E E X C A Vt o 2 2 4 . 7 5 / 2 1 8 . 7 5
1 1 0 5
C L E A R W E L L W A L L S t o 2 5 0
1 1 3 5
C L E A R W E L L / O Z O N E I N S T L 7 2 x 4 8 S L U I C E G A T E S
2 0 6 5
G A C P P G G A L L E R YE L E V S L A B @ 2 6 9 . 6 7
R 3 3 9 5
G A C C O N T A C T O RP A R A P E T M A S O N R Y
4 1 3 5
C H E M W E S T S T R S T LB E A M S @ 2 8 8 . 3 3
4 1 2 5
C H E M W E S T M A S O N R Y T O 2 8 0
3 4 0 0
P R E - O Z O N E C O N T A C T B A S I N E X C A V t o 2 4 0 . 2 5
1 0 7 5
F L O C B A S I NF O O T I N G @ 2 4 0 . 2 5
1 0 5 5
C L E A R W E L L / O Z O N E 2 S O G @ 2 2 1
1 0 5 0
C L E A R W E L L / O Z O N EI N S T L R O C K A N C H O R S
1 0 1 5
P U M P S T A T I O NE X C A V t o 2 1 9 . 5 0
1 0 6 5
P U M P S T AS O G @ 2 2 2
2 3 3 5
P U M P S T A T I O N W A L L S t o 2 4 8 . 6 7
1 1 2 5
O Z O N E W A L L S &C A S C A D E t o 2 4 3 . 2 5
3 3 1 5
C H E M B L D G E A S T B E A M4 4 , 4 5 , S L A B @ 2 4 7 . 5 0 , P I L A S @ 2 5 0
4 0 3 0
C H E M W E S T W A S T E W A T E RS U M P G R A D E B E A M # 1 7 & 1 8
2 1 8 5
G A C A R E A 8 "D E C K P A N E L @ 2 8 4
R 4 8 0 3
A S S O R T E D R O O F T O PW O R K C H L O R I N E B U I L D I N G
6 0 4 5
C H E M E A S T C L 2 S T O R / S M O N O R A I L
3 3 7 1
C H E M B L D G E A S TM O N O R A I L S U P P O R T S T E E L
2 1 6 0
O Z O N E / T R A N S F O R M E RE L E V S L A B # 1 @ 2 6 4 . 6 7
3 3 4 5
C H E M B L D G E A S T S T OA R E A E L E V S L A B @ 2 5 0
3 4 1 0
P R E - O Z O N E C O N T A C T B A S I N S O G @ 2 4 2 . 5 0
3 0 1 5
S E D B A S I N ( N , S , E ) W A L L t o 2 6 4
1 0 6 0
P U M P S T A I N S T LR O C K A N C H O R S
1 0 2 0
S E D B A S I NE X C A V t o 2 3 6 . 1 5
1 0 7 0
S E D B A S I NS O G @ 2 3 6 . 4 0
1 1 0 0
C L E A R W E L L / O Z O N E S O G @ 2 2 7
1 1 1 0
O Z O N E W A L L S t o 2 4 8 . 5 0
3 1 8 5
F L O C B A S I NW A L K W A Y S @ 2 6 4 . 6 7
2 5 0 0
F I L T E R # 1 - 6 I N S T LF I L T E R U / D R A I N
2 5 0 5
F I L T E R # 1 - 6 B E A M S @2 6 4 . 6 7 [ P R E C A S T = 1 5 d a y s ]
4 5 0 5
C H E M W E S T B L O W E R R O O M R / S 6 " 8 " 1 2 " A I R P P G
2 4 5 0
P U M P S T A M A S O N R Y t o 2 8 3
3 0 8 0
P I P E G A L L E R Y S O G @ 2 4 2 . 5 0
2 3 2 5
F L U M E F I L T 1 - 2 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5
2 3 1 5
F L U M E S / P U M PS T A S O G @ 2 2 7
2 3 0 0
F L U M E S E X C A Vt o 2 2 4 . 7 5
3 0 0 0
S E D B A S I N S O G@ 2 4 0 . 4 0 / 2 4 2 . 7 5
2 3 5 0
F L U M E F I L T 1 - 2 W A L L t o H A U N C H t o 2 4 8 . 6 7
2 4 2 5
P U M P S T A E L E V S L A B @ 2 5 0
4 3 2 0
C H E M W E S T / S E T T L E D / M I X E D B Y P A S S 4 8 " 5 4 " 6 6 " P P G
5 0 5 0
L O B B Y / C O N F E R E N C EC A S T S T O N E & G R A N I T E
R 1 1 2 5
C H E M W E S T D I PP L A N T S E R V I C E
5 0 9 0
L O B B Y / C O N F R O O F I N G
R 4 1 1 5
L O B B Y / C O N F E R E N C EM E T A L C E I L I N G S Y S T E M
6 1 1 5
C H E M W E S T F E E D ( L I M E ) M I S C P P G & E Q U I P
R 1 2 1 5
C H E M W E S TL I M E F E E D E R S
R 3 1 1 5
O Z O N E E Q U I P M E N T B L D G .C A S T S T O N E / B R I C K
2 4 5 5
P U M P S T A M E Z Z P O U RW A L K W A Y @ 2 6 4 . 6 7
3 3 2 0
C H E M B L D G E A S T S T OA R E A W A L L S t o 2 4 9
2 4 3 5
P U M P S T A M E Z Z E R E C TS T R U C S T E E L t o 2 8 3
1 1 2 0
O Z O N E I N L E T O R I F I C ET R O U G H W A L L S & S U P P W O R K
3 0 2 0
P I P E G A L L E R Y S T R U C B F I L L
1 0 8 0
F L O C B A S I N F O O T I N GW A L L t o 2 4 7
3 0 0 5
S E D B A S I N S U M P S W A L L t o 2 4 1 . 1 7
2 0 0 0
C L E A R W E L L @ G A C P P G G A L L E R Y W A L L & S L A B @ 2 3 9 . 9 2
3 0 8 5
P I P E G A L L E R Y W A L L t o 2 5 4 . 8 3
4 0 4 5
C H E M W E S T F T GW A L L b e l o w 2 4 6
1 2 0 0
1 S T F L A R C H I N T E R N A L M A S O N R Y
R 1 4 4 5
C H E M W E S T 1 s tF L O O R D O O R S
3 0 3 1
S E D B A S I N W A T E R T E S T
2 1 8 0
G A C A R E A M A S O N R Y
3 1 0 5
P I P E G A L L E R Y A R E A W A L L S t o 2 6 3 . 8 4
2 0 5 0
G A C A R E A W A L L S & E L E V S L A B t o 2 6 8 . 6 7
3 0 3 0
S E D B A S I N E L E VS L A B @ 2 6 4 . 6 7
3 0 2 5
S E D B A S I N L A U N D E R C O L S W A L L S B E A M S
1 1 5 0
F L O C B A S I NC O N C F I L L t o 2 4 7
2 4 1 5
P U M P S T A P I P E A R E AW A L L S 2 3 6 t o 2 4 8 . 6 7
2 3 5 5
F L U M E F I L T 1 - 2 W A L L t o 2 6 4 . 6 7
4 0 0 5
C H E M W E S T R / S4 2 " U / S F U T P P G
2 3 9 5
F L U M E W A L Lt o 2 6 3 . 8 3
3 1 1 5
P I P E G A L L E R Y A R E A E L E V S L A B @ 2 6 4 . 6 7
4 1 7 2
C H E M W E S T - L I M E S T OR / S L I M E C O N V B L O W E R S
4 4 3 0
C H E M W E S T R / S R A WW A T E R S A M P L E P U M P
4 2 0 5
C H E M W E S T R O O F I N G@ 2 8 0 . 6 7 / 2 8 9
4 1 9 5
C H E M W E S T - L I M E S T O R / S 6 " 8 " 1 0 " P P G
4 1 2 0
C H E M W E S TE L E V S L A B @ 2 7 6
2 0 6 0
G A C P P G G A L L E R Y I N S T L P P G & S U P P @ 2 5 0
2 0 2 0
C L E A R W E L L @ G A C P P GG A L L E R Y W A L L S t o 2 4 8 . 5 0
3 1 5 0
F L O C B A S I N S O G @ ~ 2 4 9I N C L G R A D E B E A M
2 3 3 0
F L U M E F I L T 3 - 6 W A L L S t o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5
6 3 0 5
S E D B A S I N R / S S E D I M E N T A T I O NC O L L E C T O R E Q U I P
3 1 0 0
P I P E G A L L E R YE L E V S L A B @ 2 5 6
6 3 1 0
S E D B A S I N M I S CP P G & E Q U I P
4 1 0 0
C H E M W E S T S T R S T LC O L S / B E A M S t o 2 7 5 . 3 3 / 2 8 8 . 3 3
R 1 4 1 5
C H E M W E S T 3 r dF L O O R C . M . U .
4 1 2 7
C H E M W E S T M A S O N R YT O P A R A P E T
5 2 0 5
G A R A G EE X C A V t o 2 4 3
4 2 0 0
C H E M W E S T 8 "D E C K P A N E L S @ 2 8 9
4 1 6 5
C H E M W E S T R / SL I M E F E E D E R H O P P E R S
2 2 2 5
O Z O N E / T R A N S F O R M E R8 " D E C K P A N E L S @ 2 7 8
4 1 6 0
C H E M W E S T R / SL I M E S T O S I L O S
4 0 5 0
C H E M W E S T S O G@ 2 4 6 / 2 4 6 . 6 7
3 4 1 5
P R E - O Z O N E C . B . E X T W A L L t o 2 6 1 . 8 3 / 2 6 8 . 3 3 / 2 6 9 . 3 3
3 1 5 5
F L O C B A S I N ( N , S , W ) W A L L t o 2 6 1 . 5 8 / 2 6 4
1 1 4 0
C L E A R W E L L / O Z O N E E L E V S L A B @ 2 5 0 + / -
4 3 1 0
C H E M W E S T / R A W W A T E R 4 8 " P P G w / P R E C O N T A C T B Y P A S S
6 3 3 5
Y A R D P P G T R E A T E D W A T E RM E T E R P I T I N T P P G
R 1 1 4 0
C H E M W E S TS . S . A I R L I N E S
4 1 9 0
C H E M W E S T R / SS P A R E B A T C H T A N K
1 5 2 5
F I N A L M E C H P E R F T E S T4 8 H R P L A N T O P E R A T I O N
5 2 1 0
G A R A G E F T GF D N @ 2 4 4
5 2 2 0
G A R A G E F T G W A L L St o 2 4 7 . 2 7 + / -
1 5 1 5
I N I T I A L M E C H P E R F T E S T 4 8 H R P L A N T O P E R A T I O N
1 5 1 0
P R O C E S SP A I N T I N G
4 1 8 5
C H E M W E S T R / SF I L T E R A I D B A T C H T A N K
1 3 0 0
2 N D F L A R C H I N T E R N A L M A S O N R Y
3 4 0 5
C H E M B L D G W E S T ( N O R T H ) 2 4 " 3 6 " 4 2 " 6 " U / S P P G
2 3 8 0
F L U M E W A L L &S L A B t o 2 5 0 . 1 6
3 0 7 5
P I P E G A L L E R Y 2 4 "3 6 " 6 " 8 " U / S P P G
3 0 4 0
S E D B A S I N C O L S & B E A M S t o 2 7 7 . 3 3
3 0 6 0
S E D B A S I N M A S O N R Y t o 2 8 0 . 5 0
4 1 7 5
C H E M W E S T R / SK M n O 4 F E E D E R
6 1 3 5
C H E M W E S T 3 R D F L I N S T A L LB A T C H T A N K M I X E R S
5 1 5 5
L O B B Y / C O N F F I N I S H E S ,F U R N I S H I N G S & S P E C I A L T I E S
R 1 3 2 0
C H E M W E S T C O M P U T E RR O O M E Q U I P M E N T
R 1 3 1 0
C H E M W E S T L A BI N S T R U M E N T A T I O N
R 4 6 6 0
Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( S . E . )
R 4 6 6 5
5 2 9 0R 4 5 1 5
S I T E W O R K -D R I V E " A "
5 2 4 0
G A R A G E S T RS T L @ 2 6 0 + / -
5 2 1 5
G A R A G E S O G@ 2 4 3 . 8 3
R 1 3 2 1
I N S T A L L S O F T W A R E& D E B U G S Y S T E M
R 1 3 0 5
C H E M W E S T L A BE Q U I P M E N T / F U R N I T U R E
5 3 1 5
Y A R D P P G I N S T A L LC O N T A I N M E N T T A N K & P P G
2 2 3 0
O Z O N E / T R A N S F O R M E R R O O F I N G
2 5 3 0
P I P E G A L L E R Y / F I L T E R R O O F I N G
2 5 2 5
P I P E G A L L E R Y / F I L T E R 1 2 " D E C K P A N E L S
2 5 2 0
P I P E G A L L E R Y / F I L T E R S T R S T L t o 2 7 7
2 5 1 0
F I L T E R # 1 - 6 W A L K W A Y @ 2 6 5 . 3 3 [ P R E C A S T = 1 5 d a y s ]
3 3 1 0
C H E M B L D G E A S TW A L L t o 2 4 3 / / 2 5 0
1 1 1 5
O Z O N E B A F F L E W A L L St o 2 4 2 . 2 5 / 2 4 7 . 5 0
3 3 0 0
C H E M B L D G E A S T I N T L5 4 " U / S P P G @ 2 2 5 . 2 5
3 3 0 5
C H E M B L D G E A S T S O GS T E P F T G S @ 2 3 0 / / 2 4 0 . 5 0
3 3 2 5
C H E M B L D G E A S T C O L S t o 2 6 4 . 6 7
3 3 6 0
C H E M B L D G E A S T B E A M S4 3 , 4 6 , 4 7 & S L A B @ 2 6 4 . 6 7
3 3 7 0
C H E M B L D G E A S T M A S O N R Y T O 2 6 5
R 3 3 2 0
G A C C O N T A C T O R -P L A N T S E R V I C E L I N E S
R 3 3 1 0
G A C C O N T A C T O R -P . G . S A M P L E P U M P S
R 2 6 2 7
F I L T E R O P E R A T I N GR O O M I N S T R U M E N T A T I O N
R 1 3 1 5
C H E M W E S TL A B P I P I N G
R 5 4 2 0
N O R T H B R A N C H I N T A K E- I N S T R U M E N T A T I O N
5 2 5 0
G A R A G E 8 " D E C KP A N E L S @ 2 6 2 . 6 7
5 2 2 5
G A R A G E B F I L L
1 5 2 0
I N I T I A L M E C H P E R FT E S T P U N C H L I S T
R 1 0 3 5
C H E M W E S T C O N C R E T E P A D S& C U R B S - 3 R D F L O O R
R 1 7 4 0
C H E M B L D G E A S T C L 2 A R E A 8 " D E C K P A N E L S @ 2 6 6
5 0 3 0
L O B B Y / C O N F M A S O N R Y
2 6 0 0
P U M P S T A M I S C P P G & E Q U I P
2 3 9 0
F L U M E U - S H A P Et o 2 5 4 . 8 3 / 2 5 8 . 3 3
2 3 4 0
F L U M E F I L T 1 - 2 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5
2 3 4 5
F L U M E F I L T 1 - 2E L E V S L A B @ 2 4 6 . 4 2
4 0 4 0
C H E M W E S T C O L S
4 0 6 0
C H E M W E S T B E A M S & S L A B S t o 2 6 4
3 3 7 5
C H E M B L D G E A S T M A S O N R Y T O 2 8 0
6 1 8 0
C H E M W E S T F I L T E R A I D M I S C P P G & E Q U I P
5 2 3 0
G A R A G ES O G @ 2 4 8
5 2 5 5
G A R A G E R O O F I N G
5 2 6 0
G A R A G EA R C H D E T A I L S
5 2 3 5
G A R A G EM A S O N R Y
R 4 8 0 5
A S S O R T E D R O O F T O P W O R KC H E M W E S T 3 r d F L O O R
R 1 7 4 1
C H E M B L D G E A S T E L E C A R E A 8 " D E C K P A N E L S @ 2 8 0 . 6 7
3 0 9 0
P I P E G A L L E R Y I N S T L L G P P G
2 3 7 0
F L U M E F I L T 3 - 6 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5
2 3 7 5
F L U M E F I L T 3 - 6E L E V S L A B @ 2 4 6 . 4 2
4 0 5 5
C H E M W E S T W A L L S t o 2 6 3
4 0 8 0
C H E M W E S T I N S T LC O N T A I N M E N T L I N E R
4 1 4 5
C H E M W E S T / S K Y L I G H T F R A M I N G R O O F I N G i n c S K Y L I G H T
4 1 2 9
C H E M W E S T M A S O N R Y T O 2 7 7
4 6 1 5
C H E M W E S T W E S T O FC L # 3 W A L L S T O 2 6 3
6 3 0 0
S E D B A S I N R / S 6 " 8 " P P G
R 1 4 9 5
C H E M W E S T C A S T S T O N E
1 5 0 0
O P E R A T I O N A LP U N C H L I S T
R 1 2 4 5
C H E M W E S TF I L T E R A I D L I N E S
3 0 6 5
S E D B A S I N / F L O CB A S I N R O O F I N G
R 1 7 6 0
C H E M E A S T G L A Z E DS T R U C T U R A L T I L E
3 5 0 5
P R E - O Z O N E C O N T A C T B A S I N E L E V S L A B @ 2 6 9 . 3 3
4 3 0 5
C H E M W E S T I N S T LA L U M S T O T A N K S
2 1 7 0
G A C A R E A R O O FF R A M I N G S T E E L
4 1 2 6
C H E M W E S TM A S O N R Y T O 2 8 8
4 4 0 0
C H E M W E S T A L U M S T O R / SA L U M T R A N S F E R P U M P
R 2 6 3 5
F I L T E R S - P . G .S A M P L E P U M P S
3 5 2 5
P R E - O Z O N E C O N T A C T B A S I N 8 " D E C K P A N E L S @ 2 8 0 . 6 7
3 5 2 0
P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o 2 8 0
5 0 4 5
L O B B Y / C O N F S T R S T Lt o 2 8 6 . 6 5 - P A R T I A L
R 4 8 0 0
A S S O R T E D R O O F T O P W O R KF L O C C . / S . B . / F I L T E R / O Z O N E
4 1 8 0
C H E M W E S T R / SP O L Y P H O S P H A T E B A T C H T A N K
4 1 7 0
C H E M W E S T R / S L I M ED U S T C O L L E C T O R S
4 3 0 0
C H E M W E S T R / SP O L Y P H O S P H A T E T A N K
2 4 6 5
P U M P S T A 8 "D E C K P A N E L S @ 2 8 4
R 4 8 0 1
A S S O R T E D R O O F T O PW O R K H . S . P . S .
3 5 3 0
P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o P A R A P E T
4 5 4 0
C H E M W E S T L I M E S T O M I S C P P G & E Q U I P
3 3 9 0
C H E M B L D GE A S T R O O F I N G
R 4 8 0 4
A S S O R T E D R O O F T O P W O R KE L E C T R I C A L R O O M / C . B .
R 4 8 0 2
A S S O R T E D R O O F T O PW O R K G A C C O N T A C T O R
R 1 4 1 0
C H E M W E S T 3 r d F L O O RG L A Z E D S T R U C T U R A L T I L E
P l o t D a t e 1 5 F E B 9 5D a t a D a t e 1 F E B 9 5P r o j e c t S t a r t1 0 M A Y 9 1P r o j e c t F i n i s h3 1 J A N 9 5
( c ) P r i m a v e r a S y s t e m s , I n c .
A c t i v i t y B a r / E a r l y D a t e sa c t i d S U M M A R Y R O L L - U P
P . S . C O N C R E T E C . W . / O Z O N E / G A C C O N C R E T ES . B . / F L O C C C O N C R E T E F L U M E / F I L T E R / P . G . C O N C R E T EC H E M E A S T C O N C R E T E C O N T A C T B A S I N C O N C R E T EC H E M W E S T C O N C R E T E L / C C O N C R E T ES T R U C T U R A L S T E E L M A S O N R YR O O F D E C K M E C H E Q U I P M E N T
R 8 U 1 P a g e 1 o f 1
As-Planned v. As-Built Summary
As-Planned v As-Impacted v As-Built
As-Plan of Significant Acitivities
As-Built of Significant Activities
CHANGE ORDERS IMPACTING CRITICAL WORK & IMPACT TO WORK DURATIONS
Actual Actual Crit. # of BasePCO'sPCO TF
But the duration of each activityin the CPM is only an estimateExpected Duration is -15%/+20%
As-Planned
As-Built
204 Change OrderCausative Events
As-Impacted
What is the Expected Completion,compared to Calculated Finish?
Intrinsic Unreliability of CPM
• 10 + 10 + 10 ≠ 30
• Leveled Schedule ≤ 2 x Optimal Schedule
Risk and Monte Carlo Simulation
Project Duration ≈ 31⅔
LATEST DATE 5 JUN 6 EXPECTED DATE 31 MAY 6 EARLIEST DATE 26 MAY 6 TARGET DATE 30 MAY 06
Plot Date 10FEB06 (c) Primavera Systems, Inc.
MONTE CARLO TEST #2Title
Finish Date of Project
MC02MPRJ.MC Sheet 1 of 1
Date Revision Checked Approved
0
10
20
30
40
50
60
70
80
90
100
%
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
%
26 27 28 29 30 31 32 33 34 35 36DAY
A 10±2B 10±2C 10±2D 10±2 ≈ 40
Estimating
A 10±2
B 10±2
C 10±2
D 10±2
Scheduling
Excerpt from page 142 of CPM in Construction Management
Excerpt from page 142 of CPM in Construction Management
A 10±2
B 10±2
C 10±2
D 10±2
State of the Art Analysis?
LATEST DATE 23 SEP 93 EXPECTED DATE 5 AUG 93 EARLIEST DATE 16 JUN 93 TARGET DATE 14 JUN 93
Plot Date 24NOV08 (c) Primavera Systems, Inc.
N PENN and N WALES WATER AUTHORITYFOREST PARK WATER TREATMENT PLANT
TitleFinish Date of Project
W00VMPRJ.MC Sheet 1 of 1ALLAN A. MYERS, INC. -- ENPROMAC, INC.
Date Revision Checked Approved
0
10
20
30
40
50
60
70
80
90
100
%
0
1
2
3
4
%
14
JUN
93
21
JUN
93
28
JUN
93
5
JUL
93
12
JUL
93
19
JUL
93
26
JUL
93
2
AUG
93
9
AUG
93
16
AUG
93
23
AUG
93
30
AUG
93
6
SEP
93
13
SEP
93
20
SEP
93
LATEST DATE 23 SEP 93 EXPECTED DATE 5 AUG 93 EARLIEST DATE 16 JUN 93 TARGET DATE 14 JUN 93
Plot Date 24NOV08 (c) Primavera Systems, Inc.
Not Named WATER AUTHORITYNot Named WATER TREATMENT PLANT
Initial Schedule Submittal (As-Planned)Finish Date of Project
W00VMPRJ.MC Sheet 1 of 1ALLAN A. MYERS, INC. -- ENPROMAC, INC.
Date Revision Checked Approved
0
10
20
30
40
50
60
70
80
90
100
%
0
1
2
3
4
%
14
JUN
93
21
JUN
93
28
JUN
93
5
JUL
93
12
JUL
93
19
JUL
93
26
JUL
93
2
AUG
93
9
AUG
93
16
AUG
93
23
AUG
93
30
AUG
93
6
SEP
93
13
SEP
93
20
SEP
93
ACTIVITY IDACTIVITY
DESCRIPTIONORIGDUR
ActualDuration
EARLYSTART
EARLYFINISH PCO1 PCO2 Z1TF
1991 1992 1993 1994 1995MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB
1000 NOTICE TO PROCEED 1 1 10MAY91A 10MAY91A 0
1005 MOBILIZATION 10 10 10MAY91A 23MAY91A 0
1020 SED BASIN EXCAV to 236.15 5 24 24MAY91A 27JUN91A 005 1 0
1070 SED BASIN SOG @ 236.40 15 38 12JUL91A 4SEP91A 005 1 0
3000 SED BASIN SOG @ 240.40/242.75 44 50 15JUL91A 23SEP91A 0
3015 SED BASIN (N,S,E) WALL to 264 64 84 5SEP91A 3JAN92A 009 1 0
1075 FLOC BASIN FOOTING @ 240.25 5 5 14NOV91A 20NOV91A 0
1080 FLOC BASIN FOOTING WALL to 247 5 5 21NOV91A 27NOV91A 0
1150 FLOC BASIN CONC FILL to 247 1 1 29NOV91A 29NOV91A 0
3150 FLOC BASIN SOG @~249 INCL GRADE BEAM 40 25 2DEC91A 7JAN92A 022 1 0
3155 FLOC BASIN (N,S,W) WALL to 261.58/264 50 48 2JAN92A 9MAR92A 022 2 0
3415 PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33 40 73 21APR92A 2OCT92A 053 1 0
3305 CHEM BLDG EAST SOG STEP FTGS @ 230//240.50 6 8 18JUN92A 29JUN92A 029 1 58
3310 CHEM BLDG EAST WALL to 243//250 22 22 1JUL92A 31JUL92A 008 1 58
4050 CHEM WEST SOG @ 246/246.67 30 16 26OCT92A 16NOV92A 0
3315 CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250 16 22 5AUG92A 3SEP92A 058 1 58
4055 CHEM WEST WALLS to 263 30 230 13JUL92A 27AUG93A 045 1 0
3360 CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67 25 28 17DEC92A 27JAN93A 093 2 58
4310 CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS 4 120 10AUG92A 28JAN93A 0
4320 CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG 10 158 27AUG92A 9APR93A 0
4060 CHEM WEST BEAMS & SLABS to 264 50 52 16SEP92A 8MAR93A 084 3 0
3370 CHEM BLDG EAST MASONRY TO 265 10 26 22MAR93A 26APR93A 097 2 58
R1760 CHEM EAST GLAZED STRUCTURAL TILE 10 6 19APR93A 26APR93A 58
3371 CHEM BLDG EAST MONORAIL SUPPORT STEEL 2 4 21APR93A 27APR93A 131 2 66
R1795 CHEM EAST CAST STONE/BRICK 10 67 20APR93A 25JUL93A 330
R1740 CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266 2 8 28APR93A 7MAY93A 58
3375 CHEM BLDG EAST MASONRY TO 280 10 16 8MAY93A 1JUN93A 58
R1741 CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67 2 3 2JUN93A 4JUN93A 58
3385 CHEM BLDG EAST MASONRY TO PARAPET 5 36 5JUN93A 27JUL93A 63
4100 CHEM WEST STR STL COLS/BEAMS to 275.33/288.33 6 12 19MAR93A 5APR93A 0
4120 CHEM WEST ELEV SLAB @ 276 24 30 29MAR93A 7MAY93A 121 5 0
4125 CHEM WEST MASONRY TO 280 10 176 19OCT92A 27JUN93A 187 1 0
R1415 CHEM WEST 3rd FLOOR C.M.U. 8 36 16JUN93A 5AUG93A 29
3525 PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67 5 3 2JUN93A 4JUN93A 0
R4804 ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B. 10 30 4JUN93A 16JUL93A 117 1 0
4126 CHEM WEST MASONRY TO 288 15 15 5JUN93A 27JUN93A 1
3530 PRE-OZONE CONTACT BASIN MASONRY to PARAPET 3 10 17MAY93A 28MAY93A 7
2525 PIPE GALLERY/FILTER 12" DECK PANELS 5 20 21APR93A 18MAY93A 47
3390 CHEM BLDG EAST ROOFING 8 25 28JUL93A 31AUG93A 079 2 0
3535 PRE-OZONE CONTACT BASIN ROOFING 8 9 19AUG93A 31AUG93A 63
4160 CHEM WEST R/S LIME STO SILOS 1 1 23DEC92A 23DEC92A 1
4135 CHEM WEST STR STL BEAMS @ 288.33 10 13 28JUN93A 15JUL93A 150 1 7
4165 CHEM WEST R/S LIME FEEDER HOPPERS 1 4 17MAY93A 20MAY93A 1
4170 CHEM WEST R/S LIME DUST COLLECTORS 2 2 13MAY93A 14MAY93A 1
R6155 ELECTRICAL ROOM MISCELLANEOUS WORK 88 84 16APR93A 13AUG93A 0
4172 CHEM WEST - LIME STO R/S LIME CONV BLOWERS 2 3 10MAY93A 12MAY93A 1
4195 CHEM WEST - LIME STO R/S 6" 8" 10" PPG 10 36 20MAY93A 12JUL93A 1
4200 CHEM WEST 8" DECK PANELS @ 289 20 19 21JUL93A 16AUG93A 1
4127 CHEM WEST MASONRY TO PARAPET 10 11 17AUG93A 31AUG93A 1
R4805 ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR 10 6 24AUG93A 31AUG93A 117 1 21
R1495 CHEM WEST CAST STONE 20 98 1MAR93A 8SEP93A 141 2 1
4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT 8 7 31AUG93A 9SEP93A 21
1300 2ND FL ARCH INTERNAL MASONRY 25 200 19OCT92A 30JUL93A 148 2 1
1200 1ST FL ARCH INTERNAL MASONRY 20 195 26OCT92A 30JUL93A 145 2 17
R6090 2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING 30 33 15JUL93A 30AUG93A 9
4205 CHEM WEST ROOFING @ 280.67/289 8 9 2SEP93A 15SEP93A 1
4505 CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG 5 123 28DEC92A 18JUN93A 10
R1410 CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE 7 42 16JUN93A 13AUG93A 28
R2675 FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS 1 1 30APR93A 30APR93A 65
1320 2ND FL ARCH ELEC R/I 10 214 16NOV92A 17SEP93A 9
R6000 1st FLOOR CHEM WEST PIPING & PANELS 15 15 1AUG93A 21AUG93A 6
R6095 2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS 10 10 1SEP93A 15SEP93A 0
R6115 S.B./FILTERS/FLOCC. PULL FEEDERS 15 17 22AUG93A 15SEP93A 5
R6040 CHEM EAST/PUMP STATION PULL FEEDERS 15 15 1OCT93A 21OCT93A 10
R6140 3rd FLOOR CHEM WEST PULL FEEDERS 10 11 22OCT93A 5NOV93A 15
R1320 CHEM WEST COMPUTER ROOM EQUIPMENT 5 6 25MAR94A 1APR94A 14
R6005 1st FLOOR CHEM WEST PULL FEEDER WIRE 10 10 21AUG93A 5SEP93A 6
R6100 2nd FLOOR CHEM WEST/C.B. BRANCH WIRING 30 54 15SEP93A 30NOV93A 0
R6120 S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS 25 25 16SEP93A 20OCT93A 5
R6045 CHEM EAST/PUMP STATION PULL BRANCH WIRING 20 22 22OCT93A 22NOV93A 10
R1315 CHEM WEST LAB PIPING 2 5 23MAY94A 30MAY94A 4
R6010 1st FLOOR CHEM WEST PULL BRANCH WIRING 15 18 6SEP93A 30SEP93A 6
R1310 CHEM WEST LAB INSTRUMENTATION 5 5 23MAY94A 30MAY94A 4
R6050 CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT 20 21 1APR94A 30APR94A 10
R1305 CHEM WEST LAB EQUIPMENT/FURNITURE 5 6 15FEB94A 22FEB94A 4
R6015 1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT 10 11 1OCT93A 15OCT93A 6
R6125 S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT 15 19 5APR94A 30APR94A 5
R6105 2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE 20 21 1DEC93A 30DEC93A 0
R6165 ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS 30 35 1MAR94A 18APR94A 191 1 0
1500 OPERATIONAL PUNCHLIST 25 36 1MAY94A 21JUN94A 161 2 15
R1321 INSTALL SOFTWARE & DEBUG SYSTEM 20 42 18APR94A 15JUN94A 165 4 0
1510 PROCESS PAINTING 20 21 15APR94A 15MAY94A 15
1505 INITIAL MECH PERF TEST OPER TESTING & TRAINING 20 65 1MAR94A 31MAY94A 156 3 0
1515 INITIAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 201 7 0
1520 INITIAL MECH PERF TEST PUNCHLIST 5 5 20JUN94A 24JUN94A 0
1525 FINAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 0
5205 GARAGE EXCAV to 243 2 0 17AUG94A 22AUG94A 204 1 0
END1 880 DAY PART A COMPLETION 1 0 24JUN94A 24JUN94A END 33
5215 GARAGE SOG @ 243.83 4 0 1SEP94A 8SEP94A 0
5210 GARAGE FTG FDN @ 244 3 108 29AUG94A 31AUG94A 1
5220 GARAGE FTG WALLS to 247.27 +/- 4 0 9SEP94A 16SEP94A 0
5225 GARAGE BFILL 1 0 16SEP94A 19SEP94A 0
5230 GARAGE SOG @ 248 5 0 21SEP94A 29SEP94A 0
5235 GARAGE MASONRY 5 20 3OCT94A 28OCT94A 214 1 0
5240 GARAGE STR STL @ 260 +/- 2 0 18OCT94A 20OCT94A 0
5250 GARAGE 8" DECK PANELS @ 262.67 5 6 21OCT94A 28OCT94A 214 1 0
5255 GARAGE ROOFING 8 31 31OCT94A 13DEC94A 0
5260 GARAGE ARCH DETAILS 2 14 3JAN95A 20JAN95A 204 1 0
5290 GARAGE BUILDING PUNCHLIST 10 5 15JAN95A 20JAN95A 0
1390 ARCHITECTURAL & FINAL PUNCHLIST 20 63 1NOV94A 31JAN95A 190 3 0
1395 OWNER ACCEPTANCE 1 63 1NOV94A 31JAN95A 0
END2 1065 DAY PART B COMPLETION 1 0 31JAN95A 31JAN95A 0
NOTICE TO PROCEED
MOBILIZATION
SED BASIN EXCAV to 236.15
SED BASIN SOG @ 236.40
SED BASIN SOG @ 240.40/242.75
SED BASIN (N,S,E) WALL to 264
FLOC BASIN FOOTING @ 240.25
FLOC BASIN FOOTING WALL to 247
FLOC BASIN CONC FILL to 247
FLOC BASIN SOG @~249 INCL GRADE BEAM
FLOC BASIN (N,S,W) WALL to 261.58/264
PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33
CHEM BLDG EAST SOG STEP FTGS @ 230//240.50
CHEM BLDG EAST WALL to 243//250
CHEM WEST SOG @ 246/246.67
CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250
CHEM WEST WALLS to 263
CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67
CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS
CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG
CHEM WEST BEAMS & SLABS to 264
CHEM BLDG EAST MASONRY TO 265
CHEM EAST GLAZED STRUCTURAL TILE
CHEM BLDG EAST MONORAIL SUPPORT STEEL
CHEM EAST CAST STONE/BRICK
CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266
CHEM BLDG EAST MASONRY TO 280
CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67
CHEM BLDG EAST MASONRY TO PARAPET
CHEM WEST STR STL COLS/BEAMS to 275.33/288.33
CHEM WEST ELEV SLAB @ 276
CHEM WEST MASONRY TO 280
CHEM WEST 3rd FLOOR C.M.U.
PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67
ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B.
CHEM WEST MASONRY TO 288
PRE-OZONE CONTACT BASIN MASONRY to PARAPET
PIPE GALLERY/FILTER 12" DECK PANELS
CHEM BLDG EAST ROOFING
PRE-OZONE CONTACT BASIN ROOFING
CHEM WEST R/S LIME STO SILOS
CHEM WEST STR STL BEAMS @ 288.33
CHEM WEST R/S LIME FEEDER HOPPERS
CHEM WEST R/S LIME DUST COLLECTORS
ELECTRICAL ROOM MISCELLANEOUS WORK
CHEM WEST - LIME STO R/S LIME CONV BLOWERS
CHEM WEST - LIME STO R/S 6" 8" 10" PPG
CHEM WEST 8" DECK PANELS @ 289
CHEM WEST MASONRY TO PARAPET
ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR
CHEM WEST CAST STONE
CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT
2ND FL ARCH INTERNAL MASONRY
1ST FL ARCH INTERNAL MASONRY
2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING
CHEM WEST ROOFING @ 280.67/289
CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG
CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE
FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS
2ND FL ARCH ELEC R/I
1st FLOOR CHEM WEST PIPING & PANELS
2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS
S.B./FILTERS/FLOCC. PULL FEEDERS
CHEM EAST/PUMP STATION PULL FEEDERS
3rd FLOOR CHEM WEST PULL FEEDERS
CHEM WEST COMPUTER ROOM EQUIPMENT
1st FLOOR CHEM WEST PULL FEEDER WIRE
2nd FLOOR CHEM WEST/C.B. BRANCH WIRING
S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS
CHEM EAST/PUMP STATION PULL BRANCH WIRING
CHEM WEST LAB PIPING
1st FLOOR CHEM WEST PULL BRANCH WIRING
CHEM WEST LAB INSTRUMENTATION
CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT
CHEM WEST LAB EQUIPMENT/FURNITURE
1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT
S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT
2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE
ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS
OPERATIONAL PUNCHLIST
INSTALL SOFTWARE & DEBUG SYSTEM
PROCESS PAINTING
INITIAL MECH PERF TEST OPER TESTING & TRAINING
INITIAL MECH PERF TEST 48 HR PLANT OPERATION
INITIAL MECH PERF TEST PUNCHLIST
FINAL MECH PERF TEST 48 HR PLANT OPERATION
GARAGE EXCAV to 243
880 DAY PART A COMPLETION
GARAGE SOG @ 243.83
GARAGE FTG FDN @ 244
GARAGE FTG WALLS to 247.27 +/-
GARAGE BFILL
GARAGE SOG @ 248
GARAGE MASONRY
GARAGE STR STL @ 260 +/-
GARAGE 8" DECK PANELS @ 262.67
GARAGE ROOFING
GARAGE ARCH DETAILS
GARAGE BUILDING PUNCHLIST
ARCHITECTURAL & FINAL PUNCHLIST
OWNER ACCEPTANCE
1065 DAY PART B COMPLETION
Target Date 10MAY91Plot Date 15FEB95Data Date 1FEB95Project Start10MAY91Project Finish31JAN95
(c) Primavera Systems, Inc.
inactiveALLAN A. MYERS, INC. - COMBINED WORKING SCHEDULE
Date ApprovedCheckedRevision
As-Built v As-Impacted v As-Planned
FOREST PARK WATER TREATMENT PLANT
N PENN and N WALES WATER AUTHORITYSheet 1 of 1
As-BuiltAs-PlannedAs-Impacted
nProMaC, Inc
Probability of completion on timeis less than one percent
Why?
Completion by 05AUG93has only 50% chance
Completion by 27AUG93has only 90% chance
59%-15%/+20%
A 10±2
B 10±2
C 10±2
D 10±2
Why is the probability for 14JUN93 so low?
41%
PCT PREDECESSOR REL PCT FREE ACTIVITY DESCRIPTION CRIT ACTIVITIES DESCRIPTION TYPE CRIT FLOAT ----------- ---------------------------------------- ---- ----------- ---------------------------------------- ------- ---- ------ 2230 OZONE/TRANSFORMER ROOFING 59 2225 OZONE/TRANSFORMER 8" DECK PANELS @ 278 FS 0.0 59 0.0 75307 ROOFING- FAB AND DELIVER FS 0.0 0 215.8 1300 2ND FL ARCH INTERNAL MASONRY 100 2190 GAC AREA ROOFING FS 0.0 0 17.6 2230 OZONE/TRANSFORMER ROOFING FS 0.0 59 3.8 2470 PUMP STA ROOFING FS 0.0 0 124.3 2530 PIPE GALLERY/FILTER ROOFING FS 0.0 0 92.7 3065 SED BASIN/FLOC BASIN ROOFING FS 0.0 0 40.1 3390 CHEM BLDG EAST ROOFING FS 0.0 0 127.5 3535 PRE-OZONE CONTACT BASIN ROOFING FS 0.0 0 31.6 4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc FS 0.0 0 20.0 4205 CHEM WEST ROOFING @ 280.67/289 FS 0.0 41 7.4 1305 2ND FL ARCH CARPENTRY/DRYWALL 100 1300 2ND FL ARCH INTERNAL MASONRY FS 0.0 100 0.0 79007 CAULKING - FAB AND DELIVER FS 0.0 0 286.1 81107 HOLLOW METAL DOORS - FAB AND DELIVER FS 0.0 0 254.5 81207 ALUMINIUM DOORS - FAB AND DELIVER FS 0.0 0 254.5 85207 ALUMINIUM WINDOWS - FAB AND DELIVER FS 0.0 0 254.5
100%
Alternate Probable Critical Paths
Evidence Issues for any CPM• CPM may be less certain than generally believed
• Certainty of the proffered CPM should be questioned
• Understanding of the “expert” relating to Risk is fair game
59%
41%
100%
PCT PREDECESSOR REL PCT FREE ACTIVITY DESCRIPTION CRIT ACTIVITIES DESCRIPTION TYPE CRIT FLOAT ----------- ---------------------------------------- ---- ----------- ---------------------------------------- ------- ---- ------ 2230 OZONE/TRANSFORMER ROOFING 59 2225 OZONE/TRANSFORMER 8" DECK PANELS @ 278 FS 0.0 59 0.0 75307 ROOFING- FAB AND DELIVER FS 0.0 0 215.8 1300 2ND FL ARCH INTERNAL MASONRY 100 2190 GAC AREA ROOFING FS 0.0 0 17.6 2230 OZONE/TRANSFORMER ROOFING FS 0.0 59 3.8 2470 PUMP STA ROOFING FS 0.0 0 124.3 2530 PIPE GALLERY/FILTER ROOFING FS 0.0 0 92.7 3065 SED BASIN/FLOC BASIN ROOFING FS 0.0 0 40.1 3390 CHEM BLDG EAST ROOFING FS 0.0 0 127.5 3535 PRE-OZONE CONTACT BASIN ROOFING FS 0.0 0 31.6 4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc FS 0.0 0 20.0 4205 CHEM WEST ROOFING @ 280.67/289 FS 0.0 41 7.4 1305 2ND FL ARCH CARPENTRY/DRYWALL 100 1300 2ND FL ARCH INTERNAL MASONRY FS 0.0 100 0.0 79007 CAULKING - FAB AND DELIVER FS 0.0 0 286.1 81107 HOLLOW METAL DOORS - FAB AND DELIVER FS 0.0 0 254.5 81207 ALUMINIUM DOORS - FAB AND DELIVER FS 0.0 0 254.5 85207 ALUMINIUM WINDOWS - FAB AND DELIVER FS 0.0 0 254.5
-15%/+20%
A 10±2
B 10±2
C 10±2
D 10±2
59%
41%
100%
PCT PREDECESSOR REL PCT FREE ACTIVITY DESCRIPTION CRIT ACTIVITIES DESCRIPTION TYPE CRIT FLOAT ----------- ---------------------------------------- ---- ----------- ---------------------------------------- ------- ---- ------ 2230 OZONE/TRANSFORMER ROOFING 59 2225 OZONE/TRANSFORMER 8" DECK PANELS @ 278 FS 0.0 59 0.0 75307 ROOFING- FAB AND DELIVER FS 0.0 0 215.8 1300 2ND FL ARCH INTERNAL MASONRY 100 2190 GAC AREA ROOFING FS 0.0 0 17.6 2230 OZONE/TRANSFORMER ROOFING FS 0.0 59 3.8 2470 PUMP STA ROOFING FS 0.0 0 124.3 2530 PIPE GALLERY/FILTER ROOFING FS 0.0 0 92.7 3065 SED BASIN/FLOC BASIN ROOFING FS 0.0 0 40.1 3390 CHEM BLDG EAST ROOFING FS 0.0 0 127.5 3535 PRE-OZONE CONTACT BASIN ROOFING FS 0.0 0 31.6 4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc FS 0.0 0 20.0 4205 CHEM WEST ROOFING @ 280.67/289 FS 0.0 41 7.4 1305 2ND FL ARCH CARPENTRY/DRYWALL 100 1300 2ND FL ARCH INTERNAL MASONRY FS 0.0 100 0.0 79007 CAULKING - FAB AND DELIVER FS 0.0 0 286.1 81107 HOLLOW METAL DOORS - FAB AND DELIVER FS 0.0 0 254.5 81207 ALUMINIUM DOORS - FAB AND DELIVER FS 0.0 0 254.5 85207 ALUMINIUM WINDOWS - FAB AND DELIVER FS 0.0 0 254.5
-15%/+20%
A 10±2
B 10±2
C 10±2
D 10±2A 10±2
B 10±2
C 10±2
D 10±2
Specific Flaws of this CPM• Frye Credential Test• Daubert Theory Test
and Roberson Factor Analysis
• Testimony by Expert• Ultimate Conclusion
Analytical Gap Test
Specific Flaws of this CPM
• Is the As-Planned a CPM or only a bar-chart?• Logic network from one start end to one finish end – no other open ends!
• Every activity must have a physical methodology predecessor & successor
• Activities Placed by Logic Restraints – NOT Date Constraints
• Proper Logic May Be Restated in “ADM” Finish-to-Start-no-Lag Format
• Resource (preferential) Logic Not Fully Probative for Delay Analyses• But how do we distinguish Physical from Resource Logic?
• How reliable is this CPM to establish a claim of delay or disruption?
Primavera Scheduling and Leveling Calculations -- Scheduling Report Page: 1 This Primavera software is registered to EnProMaC. Start of schedule for project 367B. Serial number...19123456 User name FRED .
Open end listing -- Scheduling Report Page: 11 ---------------- Activity 100.000000 has no predecessors Activity 100.000100 has no predecessors Activity 100.000200 has no predecessors Activity 100.000210 has no predecessors Activity 100.000300 has no predecessors Activity 100.000400 has no predecessors Activity 100.000520 has no predecessors Activity 100.000530 has no predecessors Activity 100.000572 has no predecessors Activity 100.000573 has no predecessors Activity 100.000574 has no predecessors Activity 100.000575 has no predecessors Activity 100.000577 has no predecessors Activity 100.000600 has no predecessors Activity 100.000690 has no predecessors Activity 100.009999 has no successors Activity 121.130007 has no successors Activity 121.130010 has no predecessors Activity 121.130010 has no successors Activity 121.130013 has no successors Activity 121.130014 has no successors Activity 121.130015 has no successors Activity 121.130031 has no successors Activity 121.130032 has no successors Activity 121.130046 has no successors Activity 121.130057 has no successors Activity 121.130060 has no successors Activity 121.130095 has no successors
Scheduling Statistics for Project 367B: Schedule calculation mode - Progress override Schedule calculation mode - Contiguous activities Float calculation mode - Use finish dates Schedule run on Thu Dec 25 14:07:26 2008 Run Number 485.
Number of activities.................. 2161 Number of activities in longest path.. 30 Started activities.................... 0 Completed activities.................. 0 Number of relationships............... 4024 Percent complete...................... 0.0 Number of hammocks ................... 41 Number of expected finish activities.. 3 Number of early constraints........... 44 Number of late constraints........... 2
Data date............................. 01MAR96 Start date............................ 01MAR96 Imposed finish date................... Latest calculated early finish........ 02JUL97
As-Planned Logic?
Contractor v U.S. NavyReview using P3 diagnosticCheck for Open EndsCheck for ConstraintsCheck for Critical Path
As-Planned Logic?
Contractor v U.S. NavyReviewing detail of each activity
Why do all predecessors of a critical activity have float?
How does critical path startten months into project?
Checking Logic of Critical & Near Critical Paths
RDM Analysis of the As-Planned Logic
• check for hidden open ends• check for misunderstood logic SS 5
FF 5
A
B 10
C
A 10
C 10
need never finish
may start anytime
Day 10
A 20
B 10
FF5
SS5
SS5 C 10
interruptible duration
RDM Analysis of the As-Planned Logic
• check for hidden open ends• check for misunderstood logic• check for physical v resource logic
Day 10
A 20
B 10
FF5
SS5
SS5 C 10
interruptible duration continuous duration
A 20
B 10
FF5
SS5
SS5 C 10
Day 20ES = EF – Dur ?
R eason/W hy Codes
Steel required before elev floor slabs
SubcHandoff CraftChange TowerSame FloorSame
Steel required before eForm crew moves to floSlab required before ro
R eason/W hy Codes
Steel required before elev floor slabs
SubcHandoff CraftChange TowerSame FloorSame
Steel required before eForm crew moves to floSlab required before ro
RDM Analysis of the As-Planned Logic
• check for hidden open ends• check for misunderstood logic• check for physical v resource logic• check for physical-logic-only open ends• check if the as-planned is a CPM or merely a bar-chart
R eason/Why Codes
Steel required before elev floor slabs
SubcHandoff CraftChange TowerSame FloorSame
Steel required before eForm crew moves to floSlab required before ro
R eason/Why Codes
Steel required before elev floor slabs
SubcHandoff CraftChange TowerSame FloorSame
Steel required before eForm crew moves to floSlab required before ro
Our Example Today
The CPM Schedule
The Bridge Hotels and Casino
Entitlement to Total Delay
_____ 226
Direct ExaminationTestimony for the Contractor
attacking the report
• set the predicate for a proper CPM• every activity (other than first) must have a predecessor• every activity (other than last) must have a successor• the finish of every activity (other than last) must have a successor• if these rules not followed the logic network will have open ends• what is wrong with open ends?• this required logic must be methodology (physical), not just resource • non-physical resource restraint example – crew from tower to tower• if non-physical resource restraints are removed – more open ends?
• does CPM used for this analysis meet these criteria?
Cross-Examination
attacking the report
attacking the report
attacking the report
attacking the report
bars look good!
attacking the report
logic not so good!
attacking the report
with Pertmaster RDCPMignored resource logicmakes logic looks bad!
Decision Time
_____ 226
Evidence Issues for this CPM
• The As-Planned Schedule Logic may be flawed
• Distinguishing Methodology from Resource Logic is key
• Understanding of the “expert” relating to Logic is fair gameACTIVITY ID
ACTIVITYDESCRIPTION
ORIGDUR
ActualDuration
EARLYSTART
EARLYFINISH PCO1 PCO2 Z1TF
1991 1992 1993 1994 1995MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB
1000 NOTICE TO PROCEED 1 1 10MAY91A 10MAY91A 0
1005 MOBILIZATION 10 10 10MAY91A 23MAY91A 0
1020 SED BASIN EXCAV to 236.15 5 24 24MAY91A 27JUN91A 005 1 0
1070 SED BASIN SOG @ 236.40 15 38 12JUL91A 4SEP91A 005 1 0
3000 SED BASIN SOG @ 240.40/242.75 44 50 15JUL91A 23SEP91A 0
3015 SED BASIN (N,S,E) WALL to 264 64 84 5SEP91A 3JAN92A 009 1 0
1075 FLOC BASIN FOOTING @ 240.25 5 5 14NOV91A 20NOV91A 0
1080 FLOC BASIN FOOTING WALL to 247 5 5 21NOV91A 27NOV91A 0
1150 FLOC BASIN CONC FILL to 247 1 1 29NOV91A 29NOV91A 0
3150 FLOC BASIN SOG @~249 INCL GRADE BEAM 40 25 2DEC91A 7JAN92A 022 1 0
3155 FLOC BASIN (N,S,W) WALL to 261.58/264 50 48 2JAN92A 9MAR92A 022 2 0
3415 PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33 40 73 21APR92A 2OCT92A 053 1 0
3305 CHEM BLDG EAST SOG STEP FTGS @ 230//240.50 6 8 18JUN92A 29JUN92A 029 1 58
3310 CHEM BLDG EAST WALL to 243//250 22 22 1JUL92A 31JUL92A 008 1 58
4050 CHEM WEST SOG @ 246/246.67 30 16 26OCT92A 16NOV92A 0
3315 CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250 16 22 5AUG92A 3SEP92A 058 1 58
4055 CHEM WEST WALLS to 263 30 230 13JUL92A 27AUG93A 045 1 0
3360 CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67 25 28 17DEC92A 27JAN93A 093 2 58
4310 CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS 4 120 10AUG92A 28JAN93A 0
4320 CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG 10 158 27AUG92A 9APR93A 0
4060 CHEM WEST BEAMS & SLABS to 264 50 52 16SEP92A 8MAR93A 084 3 0
3370 CHEM BLDG EAST MASONRY TO 265 10 26 22MAR93A 26APR93A 097 2 58
R1760 CHEM EAST GLAZED STRUCTURAL TILE 10 6 19APR93A 26APR93A 58
3371 CHEM BLDG EAST MONORAIL SUPPORT STEEL 2 4 21APR93A 27APR93A 131 2 66
R1795 CHEM EAST CAST STONE/BRICK 10 67 20APR93A 25JUL93A 330
R1740 CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266 2 8 28APR93A 7MAY93A 58
3375 CHEM BLDG EAST MASONRY TO 280 10 16 8MAY93A 1JUN93A 58
R1741 CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67 2 3 2JUN93A 4JUN93A 58
3385 CHEM BLDG EAST MASONRY TO PARAPET 5 36 5JUN93A 27JUL93A 63
4100 CHEM WEST STR STL COLS/BEAMS to 275.33/288.33 6 12 19MAR93A 5APR93A 0
4120 CHEM WEST ELEV SLAB @ 276 24 30 29MAR93A 7MAY93A 121 5 0
4125 CHEM WEST MASONRY TO 280 10 176 19OCT92A 27JUN93A 187 1 0
R1415 CHEM WEST 3rd FLOOR C.M.U. 8 36 16JUN93A 5AUG93A 29
3525 PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67 5 3 2JUN93A 4JUN93A 0
R4804 ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B. 10 30 4JUN93A 16JUL93A 117 1 0
4126 CHEM WEST MASONRY TO 288 15 15 5JUN93A 27JUN93A 1
3530 PRE-OZONE CONTACT BASIN MASONRY to PARAPET 3 10 17MAY93A 28MAY93A 7
2525 PIPE GALLERY/FILTER 12" DECK PANELS 5 20 21APR93A 18MAY93A 47
3390 CHEM BLDG EAST ROOFING 8 25 28JUL93A 31AUG93A 079 2 0
3535 PRE-OZONE CONTACT BASIN ROOFING 8 9 19AUG93A 31AUG93A 63
4160 CHEM WEST R/S LIME STO SILOS 1 1 23DEC92A 23DEC92A 1
4135 CHEM WEST STR STL BEAMS @ 288.33 10 13 28JUN93A 15JUL93A 150 1 7
4165 CHEM WEST R/S LIME FEEDER HOPPERS 1 4 17MAY93A 20MAY93A 1
4170 CHEM WEST R/S LIME DUST COLLECTORS 2 2 13MAY93A 14MAY93A 1
R6155 ELECTRICAL ROOM MISCELLANEOUS WORK 88 84 16APR93A 13AUG93A 0
4172 CHEM WEST - LIME STO R/S LIME CONV BLOWERS 2 3 10MAY93A 12MAY93A 1
4195 CHEM WEST - LIME STO R/S 6" 8" 10" PPG 10 36 20MAY93A 12JUL93A 1
4200 CHEM WEST 8" DECK PANELS @ 289 20 19 21JUL93A 16AUG93A 1
4127 CHEM WEST MASONRY TO PARAPET 10 11 17AUG93A 31AUG93A 1
R4805 ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR 10 6 24AUG93A 31AUG93A 117 1 21
R1495 CHEM WEST CAST STONE 20 98 1MAR93A 8SEP93A 141 2 1
4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT 8 7 31AUG93A 9SEP93A 21
1300 2ND FL ARCH INTERNAL MASONRY 25 200 19OCT92A 30JUL93A 148 2 1
1200 1ST FL ARCH INTERNAL MASONRY 20 195 26OCT92A 30JUL93A 145 2 17
R6090 2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING 30 33 15JUL93A 30AUG93A 9
4205 CHEM WEST ROOFING @ 280.67/289 8 9 2SEP93A 15SEP93A 1
4505 CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG 5 123 28DEC92A 18JUN93A 10
R1410 CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE 7 42 16JUN93A 13AUG93A 28
R2675 FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS 1 1 30APR93A 30APR93A 65
1320 2ND FL ARCH ELEC R/I 10 214 16NOV92A 17SEP93A 9
R6000 1st FLOOR CHEM WEST PIPING & PANELS 15 15 1AUG93A 21AUG93A 6
R6095 2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS 10 10 1SEP93A 15SEP93A 0
R6115 S.B./FILTERS/FLOCC. PULL FEEDERS 15 17 22AUG93A 15SEP93A 5
R6040 CHEM EAST/PUMP STATION PULL FEEDERS 15 15 1OCT93A 21OCT93A 10
R6140 3rd FLOOR CHEM WEST PULL FEEDERS 10 11 22OCT93A 5NOV93A 15
R1320 CHEM WEST COMPUTER ROOM EQUIPMENT 5 6 25MAR94A 1APR94A 14
R6005 1st FLOOR CHEM WEST PULL FEEDER WIRE 10 10 21AUG93A 5SEP93A 6
R6100 2nd FLOOR CHEM WEST/C.B. BRANCH WIRING 30 54 15SEP93A 30NOV93A 0
R6120 S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS 25 25 16SEP93A 20OCT93A 5
R6045 CHEM EAST/PUMP STATION PULL BRANCH WIRING 20 22 22OCT93A 22NOV93A 10
R1315 CHEM WEST LAB PIPING 2 5 23MAY94A 30MAY94A 4
R6010 1st FLOOR CHEM WEST PULL BRANCH WIRING 15 18 6SEP93A 30SEP93A 6
R1310 CHEM WEST LAB INSTRUMENTATION 5 5 23MAY94A 30MAY94A 4
R6050 CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT 20 21 1APR94A 30APR94A 10
R1305 CHEM WEST LAB EQUIPMENT/FURNITURE 5 6 15FEB94A 22FEB94A 4
R6015 1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT 10 11 1OCT93A 15OCT93A 6
R6125 S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT 15 19 5APR94A 30APR94A 5
R6105 2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE 20 21 1DEC93A 30DEC93A 0
R6165 ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS 30 35 1MAR94A 18APR94A 191 1 0
1500 OPERATIONAL PUNCHLIST 25 36 1MAY94A 21JUN94A 161 2 15
R1321 INSTALL SOFTWARE & DEBUG SYSTEM 20 42 18APR94A 15JUN94A 165 4 0
1510 PROCESS PAINTING 20 21 15APR94A 15MAY94A 15
1505 INITIAL MECH PERF TEST OPER TESTING & TRAINING 20 65 1MAR94A 31MAY94A 156 3 0
1515 INITIAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 201 7 0
1520 INITIAL MECH PERF TEST PUNCHLIST 5 5 20JUN94A 24JUN94A 0
1525 FINAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 0
5205 GARAGE EXCAV to 243 2 0 17AUG94A 22AUG94A 204 1 0
END1 880 DAY PART A COMPLETION 1 0 24JUN94A 24JUN94A END 33
5215 GARAGE SOG @ 243.83 4 0 1SEP94A 8SEP94A 0
5210 GARAGE FTG FDN @ 244 3 108 29AUG94A 31AUG94A 1
5220 GARAGE FTG WALLS to 247.27 +/- 4 0 9SEP94A 16SEP94A 0
5225 GARAGE BFILL 1 0 16SEP94A 19SEP94A 0
5230 GARAGE SOG @ 248 5 0 21SEP94A 29SEP94A 0
5235 GARAGE MASONRY 5 20 3OCT94A 28OCT94A 214 1 0
5240 GARAGE STR STL @ 260 +/- 2 0 18OCT94A 20OCT94A 0
5250 GARAGE 8" DECK PANELS @ 262.67 5 6 21OCT94A 28OCT94A 214 1 0
5255 GARAGE ROOFING 8 31 31OCT94A 13DEC94A 0
5260 GARAGE ARCH DETAILS 2 14 3JAN95A 20JAN95A 204 1 0
5290 GARAGE BUILDING PUNCHLIST 10 5 15JAN95A 20JAN95A 0
1390 ARCHITECTURAL & FINAL PUNCHLIST 20 63 1NOV94A 31JAN95A 190 3 0
1395 OWNER ACCEPTANCE 1 63 1NOV94A 31JAN95A 0
END2 1065 DAY PART B COMPLETION 1 0 31JAN95A 31JAN95A 0
NOTICE TO PROCEED
MOBILIZATION
SED BASIN EXCAV to 236.15
SED BASIN SOG @ 236.40
SED BASIN SOG @ 240.40/242.75
SED BASIN (N,S,E) WALL to 264
FLOC BASIN FOOTING @ 240.25
FLOC BASIN FOOTING WALL to 247
FLOC BASIN CONC FILL to 247
FLOC BASIN SOG @~249 INCL GRADE BEAM
FLOC BASIN (N,S,W) WALL to 261.58/264
PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33
CHEM BLDG EAST SOG STEP FTGS @ 230//240.50
CHEM BLDG EAST WALL to 243//250
CHEM WEST SOG @ 246/246.67
CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250
CHEM WEST WALLS to 263
CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67
CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS
CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG
CHEM WEST BEAMS & SLABS to 264
CHEM BLDG EAST MASONRY TO 265
CHEM EAST GLAZED STRUCTURAL TILE
CHEM BLDG EAST MONORAIL SUPPORT STEEL
CHEM EAST CAST STONE/BRICK
CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266
CHEM BLDG EAST MASONRY TO 280
CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67
CHEM BLDG EAST MASONRY TO PARAPET
CHEM WEST STR STL COLS/BEAMS to 275.33/288.33
CHEM WEST ELEV SLAB @ 276
CHEM WEST MASONRY TO 280
CHEM WEST 3rd FLOOR C.M.U.
PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67
ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B.
CHEM WEST MASONRY TO 288
PRE-OZONE CONTACT BASIN MASONRY to PARAPET
PIPE GALLERY/FILTER 12" DECK PANELS
CHEM BLDG EAST ROOFING
PRE-OZONE CONTACT BASIN ROOFING
CHEM WEST R/S LIME STO SILOS
CHEM WEST STR STL BEAMS @ 288.33
CHEM WEST R/S LIME FEEDER HOPPERS
CHEM WEST R/S LIME DUST COLLECTORS
ELECTRICAL ROOM MISCELLANEOUS WORK
CHEM WEST - LIME STO R/S LIME CONV BLOWERS
CHEM WEST - LIME STO R/S 6" 8" 10" PPG
CHEM WEST 8" DECK PANELS @ 289
CHEM WEST MASONRY TO PARAPET
ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR
CHEM WEST CAST STONE
CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT
2ND FL ARCH INTERNAL MASONRY
1ST FL ARCH INTERNAL MASONRY
2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING
CHEM WEST ROOFING @ 280.67/289
CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG
CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE
FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS
2ND FL ARCH ELEC R/I
1st FLOOR CHEM WEST PIPING & PANELS
2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS
S.B./FILTERS/FLOCC. PULL FEEDERS
CHEM EAST/PUMP STATION PULL FEEDERS
3rd FLOOR CHEM WEST PULL FEEDERS
CHEM WEST COMPUTER ROOM EQUIPMENT
1st FLOOR CHEM WEST PULL FEEDER WIRE
2nd FLOOR CHEM WEST/C.B. BRANCH WIRING
S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS
CHEM EAST/PUMP STATION PULL BRANCH WIRING
CHEM WEST LAB PIPING
1st FLOOR CHEM WEST PULL BRANCH WIRING
CHEM WEST LAB INSTRUMENTATION
CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT
CHEM WEST LAB EQUIPMENT/FURNITURE
1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT
S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT
2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE
ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS
OPERATIONAL PUNCHLIST
INSTALL SOFTWARE & DEBUG SYSTEM
PROCESS PAINTING
INITIAL MECH PERF TEST OPER TESTING & TRAINING
INITIAL MECH PERF TEST 48 HR PLANT OPERATION
INITIAL MECH PERF TEST PUNCHLIST
FINAL MECH PERF TEST 48 HR PLANT OPERATION
GARAGE EXCAV to 243
880 DAY PART A COMPLETION
GARAGE SOG @ 243.83
GARAGE FTG FDN @ 244
GARAGE FTG WALLS to 247.27 +/-
GARAGE BFILL
GARAGE SOG @ 248
GARAGE MASONRY
GARAGE STR STL @ 260 +/-
GARAGE 8" DECK PANELS @ 262.67
GARAGE ROOFING
GARAGE ARCH DETAILS
GARAGE BUILDING PUNCHLIST
ARCHITECTURAL & FINAL PUNCHLIST
OWNER ACCEPTANCE
1065 DAY PART B COMPLETION
Target Date 10MAY91Plot Date 15FEB95Data Date 1FEB95Project Start10MAY91Project Finish31JAN95
(c) Primavera Systems, Inc.
inactiveALLAN A. MYERS, INC. - COMBINED WORKING SCHEDULE
Date ApprovedCheckedRevision
As-Built v As-Impacted v As-PlannedFOREST PARK WATER TREATMENT PLANTN PENN and N WALES WATER AUTHORITY
Sheet 1 of 1
As-BuiltAs-PlannedAs-Impacted
nProMaC, Inc
RD CPM®
Compliance Certified
RD CPM®
Compliance Certified
LATEST DATE 5 JUN 6 EXPECTED DATE 31 MAY 6 EARLIEST DATE 26 MAY 6 TARGET DATE 30 MAY 06
Plot Date 10FEB06 (c) Primavera Systems, Inc.
MONTE CARLO TEST #2Title
Finish Date of Project
MC02MPRJ.MC Sheet 1 of 1
Date Revision Checked Approved
0
10
20
30
40
50
60
70
80
90
100
%
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
%
26 27 28 29 30 31 32 33 34 35 36DAY
50% probable finish date
CPM finish date
RP-50R-06Schedule Forecasting by Trend
Analysis
“technological advances and the use of computers to devise work schedules and chart progress on a particular project have facilitated the court’s ability to allocate damages.” 1978 ►►► 2010
Q&Aa copy of this slideshow may be downloaded at