EVM: Beyond SPI & CPI
September 22, 2014 Charlene Thompson, PE PMP EVP PSP
![Page 2: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/2.jpg)
Beyond SPI & CPI
OK, so you routinely calculate and report SPI and CPI for your projects, but what other information does the EVM chart tell us? Let’s take a detailed look at the information provided by our Earned Value calculations and chart, what the chart shows (and what it doesn’t). Are you really measuring the right things? Are there elements of your project schedule or cost/spending plan that skew the data?
![Page 3: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/3.jpg)
Baseline Schedule Early Dates, Late Dates or ? Resource Loading Cost Loading
Earned Value Measurement Requirements
PV Planned Value
EV Earned Value
AC Actual Cost
SPI Schedule Performance Index
= EV/PV CPI Cost Performance Index = EV/AC
Earnings Rules
0% or 100%
25% - 50% - 75% - 100%
Actual progress (WIP)
![Page 4: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/4.jpg)
Earned Value Measurement
![Page 5: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/5.jpg)
Earned Value Chart – “S” Curve
![Page 6: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/6.jpg)
Are we measuring the right things . . . right?
![Page 7: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/7.jpg)
Are we measuring the right things . . . right?
![Page 8: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/8.jpg)
Are we measuring the right things . . . right?
Are we really >$1MM behind?
![Page 9: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/9.jpg)
Are we measuring the right things . . . right?
![Page 10: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/10.jpg)
Progress against the baseline
![Page 11: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/11.jpg)
EVM Chart with Progress
![Page 12: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/12.jpg)
SV = EV – PV; SPI = EV/PV SV = -$512,500; SPI = 0.89
EVM Chart with Progress
![Page 13: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/13.jpg)
Schedule Performance
SV = EV – PV; SPI = EV/PV SV = -$512,500; SPI = 0.89
![Page 14: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/14.jpg)
CV = EV – AC; CPI = EV/AC CV = -$75,000; CPI = 0.98
Cost Performance
![Page 15: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/15.jpg)
Trending
![Page 16: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/16.jpg)
Trending
![Page 17: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/17.jpg)
0.82 0.84 0.86 0.88 0.90 0.92 0.94 0.96 0.98 1.00 1.02 1.04 1.06 1.08 1.10 1.12 1.14 1.16 1.18
1.18
1.16
1.14
1.12
1.10
1.08
1.06
1.04
1.02
1.00
0.98
0.96
0.94
0.92
0.90
0.88
0.86
0.84
0.82Behind Schedule – Over Budget
Behind Schedule – Under Budget
Ahead of Schedule – Over Budget
Ahead of Schedule – Under Budget
Schedule Performance Index
Cos
t Per
form
ance
Inde
x
EAC
1
2
3
4
Today
5
6
Date of Last Rebaseline: mo/yrNumber of Rebaselines:Date of Next Rebaseline: mo/yr
Date of Last Award Fee: mo/yrDate of Next Award Fee: mo/yr
Tota
l Spe
nt
$0M
$110M EAC
$100M TAB
$90M BAC
$50M ACWP
Total Schedule ElapsedMo/Yr
EstimatedEnd
Mo/Yr
Baseline End
Contract Award
Mo/Yr Mo/Yr
CurrentDate
TCPI = 0.76CV = $2.0MSV = $2.9M
Communicate?
0.82 0.84 0.86 0.88 0.90 0.92 0.94 0.96 0.98 1.00 1.02 1.04 1.06 1.08 1.10 1.12 1.14 1.16 1.18
1.18
1.16
1.14
1.12
1.10
1.08
1.06
1.04
1.02
1.00
0.98
0.96
0.94
0.92
0.90
0.88
0.86
0.84
0.82Behind Schedule – Over Budget
Behind Schedule – Under Budget
Ahead of Schedule – Over Budget
Ahead of Schedule – Under Budget
Schedule Performance Index
Cos
t e
oa
ce
de
EAC
1
2
3
4
Today
5
6
Date of Last Rebaseline: mo/yrNumber of Rebaselines:
Date of Last Award Fee: mo/yrDate of Next Award Fee: mo/yr
Tota
l Spe
nt
A
ota Sc edu e apsedo/
d
o/
ase e d
a d
o/ o/
Cu e tate
![Page 18: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/18.jpg)
Forecasting
![Page 19: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/19.jpg)
How much is it really going to cost?
CV = EV – AC; CPI = EV/AC CV = -$75,000; CPI = 0.98
EAC = AC+(BAC-EV)
$6,825,000
![Page 20: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/20.jpg)
How much is it really going to cost?
CV = EV – AC; CPI = EV/AC CV = -$75,000; CPI = 0.98
EAC = BAC/CPI
$6,868,076
![Page 21: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/21.jpg)
How much is it really going to cost?
CV = EV – AC; CPI = EV/AC CV = -$75,000; CPI = 0.98
EAC = AC+(BAC-EV)/(CPI*SPI)
$7,167,576
SV = EV – PV; SPI = EV/PV SV = -$512,500; SPI = 0.89
![Page 22: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/22.jpg)
Can we recover?
TCPI = 1.03 Is that good or bad?
Be careful – if you use the EAC: TCPI = (BAC-EV)/(EAC-AC) TCPI = 1.00 You’ve changed the target!
![Page 23: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/23.jpg)
Earned Value based on Manhours
![Page 24: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/24.jpg)
Earned Value based on Manhours
![Page 25: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/25.jpg)
Earned Value based on Manhours
![Page 26: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/26.jpg)
Earned Value based on Manhours
SPI = 0.98 CPI = 0.96
![Page 27: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/27.jpg)
?
How long is it really going to take?
?
![Page 28: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/28.jpg)
Earned Schedule
![Page 29: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/29.jpg)
Earned Schedule
SPI(t) = 0.88 CPI(t) = 0.91
![Page 30: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/30.jpg)
Earned Schedule
![Page 31: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/31.jpg)
Earned Schedule
![Page 32: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/32.jpg)
Earned Schedule
SPI(t) = 0.82 CPI(t) = 0.88
![Page 33: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/33.jpg)
Other Considerations
• Self-performing vs. Contracting • Type of contract
• Large expenditures
• Accrue?
• Level of Effort • Management Costs • Operation Costs
• Software
• Calculation Options
![Page 34: EVM: Beyond SPI & CPI - kcpmichapter.org · EVM: Beyond SPI & CPI . September 22, 2014 . Charlene Thompson, PE PMP EVP PSP](https://reader034.vdocument.in/reader034/viewer/2022042302/5ecd97c904b50f0d86396887/html5/thumbnails/34.jpg)