evm in project cost control.pdf

Upload: anonymous-ugk4dtsin

Post on 07-Aug-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/20/2019 EVM in Project Cost Control.pdf

    1/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Professional Development Webinar Series

    Earned Value Management System

    Feb 27, 2016

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Agenda

    Introduction to 3FOLD Education Centre

    Definition

    Context

    Project Cost Management

    EVM Metrics

    Cost Control Formula

  • 8/20/2019 EVM in Project Cost Control.pdf

    2/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Introduction

    PMI Registered Education Provider & AACEI Approved

    Education Provider.

    We are also approved by KHDA.

    Trained more than 6000 students.

    Branches in UAE and Qatar.

    Our flagship preparation courses are PMP and CCP.

    Contact us: [email protected]

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Definition

    Introduction to Earned Value Management

  • 8/20/2019 EVM in Project Cost Control.pdf

    3/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Definition

    Earned Value Management. A methodology that combines

    scope, schedule, and resource measurements to assess

    project performance and progress.

    Earned Value (EV). The measure of work performed

    expressed in terms of the budget authorized for that work.

    Earned Value is also known as Budgeted Cost of Work

    Performed (BCWP).

    * These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) - Fifth

    Edition, Project Management Institute, Inc., 2013.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Context

    Earned Value Management in Project Management

  • 8/20/2019 EVM in Project Cost Control.pdf

    4/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Project Cost Management

    As per the PMBOK® Guide 5th Edition, “Project Cost

    Management includes the processes involved in planning,

    estimating, budgeting, financing, funding, managing, and

    controlling costs so that the project can be completed within

    the approved budget.”

    • Plan Cost Management

    • Estimate Costs

    • Determine Budget

    • Control Cost

    Project Management Institute, A Guide to the Project Management Body of Knowledge, ( PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013, Page 193.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    What is a Process ?

    A systematic series of activities directed towards causing an

    end result such that one or more inputs will be acted upon to

    create one or more outputs.

    * These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) - Fifth

    Edition, Project Management Institute, Inc., 2013.

    Project Management Institute, A Guide to the Project Management Body of Knowledge, ( PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013, Figure 7-10, Page 215.

  • 8/20/2019 EVM in Project Cost Control.pdf

    5/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Process Interaction

    Project Management Institute, A Guide to the Project Management Body of Knowledge, ( PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013, Figure 7-11, Page 217.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Project Cost Management Processes

    Plan Cost Management—The process that establishes the policies,

    procedures, and documentation for planning, managing, expending,

    and controlling project costs.

    Estimate Costs—The process of developing an approximation of the

    monetary resources needed to complete project activities.

    Determine Budget—The process of aggregating the estimated costs

    of individual activities or work packages to establish an authorized

    cost baseline.

    Control Costs—The process of monitoring the status of the project

    to update the project costs and managing changes to the cost

    baseline.

    * These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) - Fifth

    Edition, Project Management Institute, Inc., 2013.

  • 8/20/2019 EVM in Project Cost Control.pdf

    6/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    1. Plan Cost Management

    The process that establishes the policies, procedures, and

    documentation for planning, managing, expending, and

    controlling project costs.

    * These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) - Fifth

    Edition, Project Management Institute, Inc., 2013.

    Project Management Institute, A Guide to t he Project Management Body of Knowledge, ( PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013, Figure 7-2, Page 195.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Cost Management Plan - Content

    Units of measure

    Level of precision

    Level of accuracy

    Organizational procedures link

    Control thresholds

    Reporting formats

    Rules of progress measurement – this is where Earned valuemanagement (EVM) rules of performance measurement areset.

  • 8/20/2019 EVM in Project Cost Control.pdf

    7/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    2. Estimate Costs

    Estimate Costs is the process of developing an approximation

    of the monetary resources needed to complete project

    activities.

    * These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) - Fifth

    Edition, Project Management Institute, Inc., 2013.

    Project Management Institute, A Guide to t he Project Management Body of Knowledge, ( PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013, Figure 7-4, Page 200.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Contingency Reserve

    Cost estimates may include contingency reserves (sometimes

    called contingency allowances) to account for cost

    uncertainty.

    Contingency reserves are the budget within the cost baseline

    that is allocated for identified risks, which are accepted and

    for which contingent or mitigating responses are developed.

    Contingency reserves are often viewed as the part of the

    budget intended to address the “known-unknowns” that can

    affect a project.

  • 8/20/2019 EVM in Project Cost Control.pdf

    8/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Management Reserve

    Estimates may also be produced for the amount of

    management reserve to be funded for the project.

    Management reserves are an amount of the project budget

    withheld for management control purposes and are reserved

    for unforeseen work that is within scope of the project.

    Management reserves are intended to address the “unknown

    unknowns” that can affect a project.

    The management reserve is not included in the cost baselinebut is part of the overall project budget and funding

    requirements.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    3. Determine Budget

    Determine Budget is the process of aggregating the estimated

    costs of individual activities or work packages to establish an

    authorized cost baseline.

    * These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) - Fifth

    Edition, Project Management Institute, Inc., 2013.

    Project Management Institute, A Guide to t he Project Management Body of Knowledge, ( PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013, Figure 7-6, Page 208.

  • 8/20/2019 EVM in Project Cost Control.pdf

    9/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Cost Baseline

    The cost baseline is the approved version of the time-phased

    project budget, excluding any management reserves, which

    can only be changed through formal change control

    procedures and is used as a basis for comparison to actual

    results.

    It is developed as a summation of the approved budgets for

    the different schedule activities.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Project Budget Components

    Project Management Institute, A Guide to t he Project Management Body of Knowledge, ( PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013, Figure 7-8, Page 213.

  • 8/20/2019 EVM in Project Cost Control.pdf

    10/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    S-curve

    Since the cost estimates that make up the cost baseline are directly tied to

    the schedule activities, this enables a time-phased view of the cost

    baseline, which is typically displayed in the form of an S-curve

    Project Management Institute, A Guide to t he Project Management Body of Knowledge, ( PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013, Figure 7-9, Page 214.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    4. Cost Control

    Earned Value Management

  • 8/20/2019 EVM in Project Cost Control.pdf

    11/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    4. Control Costs

    Control Costs is the process of monitoring the status of the

    project to update the project costs and managing changes to

    the cost baseline.

    * These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) - Fifth

    Edition, Project Management Institute, Inc., 2013.

    Project Management Institute, A Guide to the Project Management Body of Knowledge, ( PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013, Figure 7-10, Page 215.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Cost Control Tools and Techniques – on focus

    1. Earned Value Metrics

    2. Progress Measurement

    3. Performance Measurement

    4. Forecasting

    5. To-complete performance index (TCPI)

    6. Variance At Completion

  • 8/20/2019 EVM in Project Cost Control.pdf

    12/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    1. EVM Metrics

    Planned Value, Actual Cost, Earned Value

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    EVM Metrics

    EVM develops and monitors three key dimensions for each

    work package and control account:

    • Planned value

    • Actual cost

    • Earned Value

  • 8/20/2019 EVM in Project Cost Control.pdf

    13/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Planned Value

    Planned value (PV) is the authorized budget assigned to scheduled

    work.

    It is the authorized budget planned for the work to be accomplished

    for an activity or work breakdown structure component, not

    including management reserve.

    This budget is allocated by phase over the life of the project, but at

    a given moment, planned value defines the physical work that

    should have been accomplished.

    The total of the PV is sometimes referred to as the performancemeasurement baseline (PMB). The total planned value for the

    project is also known as budget at completion (BAC).

    * These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) - Fifth

    Edition, Project Management Institute, Inc., 2013.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Actual Cost

    Actual cost (AC) is the realized cost incurred for the work

    performed on an activity during a specific time period.

    It is the total cost incurred in accomplishing the work that the

    EV measured.

    The AC needs to correspond in definition to what was

    budgeted in the PV and measured in the EV (e.g., direct hoursonly, direct costs only, or all costs including indirect costs).

    The AC will have no upper limit; whatever is spent to achieve

    the EV will be measured.

    * These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) - Fifth

    Edition, Project Management Institute, Inc., 2013.

  • 8/20/2019 EVM in Project Cost Control.pdf

    14/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Earned Value

    Earned value (EV) is a measure of work performed expressed interms of the budget authorized for that work. It is the budgetassociated with the authorized work that has been completed.

    The EV being measured needs to be related to the PMB, and the EVmeasured cannot be greater than the authorized PV budget for acomponent.

    The EV is often used to calculate the percent complete of a project.

    Progress measurement criteria should be established for each WBScomponent to measure work in progress.

    Project managers monitor EV, both incrementally to determinecurrent status and cumulatively to determine the long-termperformance trends.

    * These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) - Fifth

    Edition, Project Management Institute, Inc., 2013.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Earned Value

    Earned Value = % completed x Budget

    Progress measurement technique measures the percent

    complete which will assist in calculating the earned value. The

    budget is the budgeted cost of the measured component

    which could be a work package, control account, or the

    project.

  • 8/20/2019 EVM in Project Cost Control.pdf

    15/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    2. Progress Measurement

    Units completion, Start/Finish, Incremental

    Milestone, Supervisor Opinion, Cost Ratio and

    Equivalent Units/Weighted Average

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Units Completion

    Formula

    x 100

  • 8/20/2019 EVM in Project Cost Control.pdf

    16/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Start/Finish (Fixed Formula)

    30% 100%

    Start Finish

    This method is applicable to tasks that lack

    readily definable intermediate milestones or

    those for which the effort/time required is

    very difficult to estimate.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Incremental Milestone

    30%

    Start Finish

    60% 80% 100%

    This method is applicable

    to any control account that includes subtasks

    that must be handled in sequence.

  • 8/20/2019 EVM in Project Cost Control.pdf

    17/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Supervisor Opinion

    In this method, the supervisor

    simply makes a judgment of

    percent complete.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Cost Ratio

    This method is applicable to tasks that involve a long period of

    time or that are continuous during the life of a project, and

    which are estimated and budgeted on bulk allocations of

    dollars and work hours rather than on the basis of production.

     

    x 100

  • 8/20/2019 EVM in Project Cost Control.pdf

    18/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Weighted or Equivalent Units

    This method is applicable when the task being controlled

    involves a long period of time and is composed of two or

    more overlapping subtasks, each with a different unit of work

    measurement.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Allowed

    CreditSubtask Total U/M Total Qty To-Date Qty Earned Tons

    0.02run foundation bolts each 120 120 12.00

    0.03shim % 100 100 18.00

    0.06shakeout % 100 100 36.00

    0.04columns each 80 70 21.00

    0.12beams each 987 230 16.78

    0.12cross braces each 780 0 0.00

    0.17girts and sag roads bay 40 0 0.00

    0.08plumb and align % 100 0 0.00

    0.31connection each 3000 90 5.580.05punch list % 100 0 0.00

    1Steel Totals Ton 600 109.36

    Earned Quantity = (allowed credit)*(summary quantity)*

    Earned Tons Columns

    =

    .04 x 600 x7

    8

    21 Tons

    Percent Complete

    =109.36

    600

    18.23%

    Equivalent Units

  • 8/20/2019 EVM in Project Cost Control.pdf

    19/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Earned Value Calculation

    Wall 1

       W   a    l    l   2

    Wall 3

       W   a    l    l   4

    Schedule Plan

    Schedule: To complete the work in 4

    weeks – work is equally distributed

    Budgeted Cost

    USD 10,000 per side

    Status at the end of week 3

    Wall 1 – 100% - $ 12000

    Wall 2 – 100% - $ 13000

    Wall 3 – 50% - $ 7000

    Wall 4 – 0% - $ 0

    Calculate BAC, PV, AC and EV

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Solution

    Work

    Package

    Planned

    Value

    Actual Cost Progress Earned

    Value

    Wall 1 10000 12000 100 % 10000

    Wall 2 10000 13000 100 % 10000

    Wall 3 10000 7000 50 % 5000

    Wall 4 10000 0 0 % 0

    Total 40000 32000 25000

  • 8/20/2019 EVM in Project Cost Control.pdf

    20/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    3. Performance Measurement

    Cost Variance, Cost Performance Index, Schedule

    Variance, Schedule Performance Index

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Performance Measurement

    Cost Performance

    Cost Variance Cost Performance Index

    Earned Value – Actual Cost 

      Positive = Under planned cost

    Neutral = On planned cost

    Negative = Over planned cost

    Greater than 1.0 = Under planned cost

    Exactly 1.0 = On planned cost

    Less than 1.0 = Over planned cost

    Schedule Performance

    Schedule Variance Schedule Performance Index

    Earned Value – Planned Value  

    Positive = Ahead of Schedule

    Neutral = On schedule

    Negative = Behind Schedule

    Greater than 1.0 = Ahead of schedule

    Exactly 1.0 = On schedule

    Less than 1.0 = Behind schedule

  • 8/20/2019 EVM in Project Cost Control.pdf

    21/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Cost Performance

    Cost Variance Cost Performance Index

    25000 – 32000 = (7000) 25000 / 32000 = 0.781

    Schedule Performance

    Schedule Variance Schedule Performance Index

    25000 –

    30000 = (5000) 25000 / 30000 = 0.833

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    4. Forecasting

    Estimate At Completion & Estimate To Complete

  • 8/20/2019 EVM in Project Cost Control.pdf

    22/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    BAC = $ 40,000 PV = $ 30,000 AC = $32,000 EV = $ 25,000 CPI = 0.781 SPI = 0.833

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Estimate At Completion

    Estimate At Completion

    EAC EAC

    AC + (BAC – EV)

    CPI is expected to be the same for the remainder of

    the project

    Future work will be accomplished at the planned rate

    EAC EAC

    AC +( −)

    ( )AC + Bottom up ETC

    CPI and SPI inf luence the remaining work Initia l plan is no longer va lid

  • 8/20/2019 EVM in Project Cost Control.pdf

    23/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Estimate At Completion

    EAC EAC

    .= 51216 32000 + (40000 – 25000) = 47000

    CPI is expected to be the same for the remainder of the

    project

    Future work will be accomplished at the planned rate

    EAC EAC

    32000 + ( −)(. .)

    = 55055 32000 + Bottom up ETC

    CPI and SPI influence the remaining work Initial plan is no longer valid

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Estimate To Complete

    Estimate To Complete

    ETC ETC

    EAC – AC Re-EstimateAssumes work is proceeding on plan. Re-estimate the remaining work from the bottom up.

  • 8/20/2019 EVM in Project Cost Control.pdf

    24/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Estimate To Complete

    ETC ETC

    51216 – 32000 = 19216CPI is expected to be the same for the remainder of the project. Re-Estimate

    Assume s work is proceeding on plan. Re-estimate the rema ining work from the bottom up.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    5. TCPI

    To Complete Performance Index

  • 8/20/2019 EVM in Project Cost Control.pdf

    25/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    To Complete Performance Index

    To Complete Performance Index

    TCPI TCPI

    (BAC – EV)/(BAC – AC) (BAC – EV)/(EAC – AC)

    The efficiency that must be maintained in order to

    complete on plan.

    The efficiency that must be maintained in order to

    complete the current EAC.

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    To Complete Performance Index

    TCPI TCPI

    (BAC – EV)/(BAC – AC)

    (40000-25000) / (40000-32000)

    1.875

    (BAC – EV)/(EAC – AC)

    (40000-25000) / (51216-32000)

    0.781

    The efficiency that must be maintained in order to

    complete on plan.

    The efficiency that must be maintained in order to

    complete the current EAC.

  • 8/20/2019 EVM in Project Cost Control.pdf

    26/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    6. Variance At Completion

    VAC

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    Variance At Completion

    Variance At Completion

    VAC

    BAC – EAC

    The estimated difference in cost at the completion of the project.

  • 8/20/2019 EVM in Project Cost Control.pdf

    27/27

    OLD Education Centre 2/28/2

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    CPI = 0.781 SP I = 0.833 EAC = $ 51216 ETC = $ 19216

    Variance At Completion

    VAC

    BAC – EAC

    40000 – 51216 = (11216)

    The estimated difference in cost at the completion of the project.

    BAC = $ 40,000 BCWS = $ 30,000 ACWP = $32,000 BCWP = $ 25,000

    Earned Value Management System

    PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

    © 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.pmexamstudy.com . www.3foldtraining.com . PMP® Exam Review

    End of the Seminar

    Thank you