excavations and peripheral walls in urban space case study … · multi-anchored walls in retaining...
TRANSCRIPT
![Page 1: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/1.jpg)
- 1 -
Excavations and Peripheral Walls in Urban Space
Case Study – Palácio dos Condes de Murça Inês Oliveira
Department of Civil Engineering, Instituto Superior Técnico, Universidade Técnica de Lisboa, Portugal
Abstract: The increasing occupation of the urban underground space has consequences for existing buildings, which often are not
properly assessed when projects involving excavations and peripheral walls are carried out. This paper is intended as a contribution to
the study and analysis on this issue. Therefore it is presented a case study using the technique of King Post Walls, which was adopted
for the peripheral contention of the project “Palácio dos Condes de Murça”, in Lisbon. Based on data collected in the field and the
monitoring of the construction works, a comparative analysis of the instrumentation was made, relating it to the main events
witnessed in the field, including the implementation of mitigation measures, which were required due to the ground movements
observed. It was also carried out a numerical modeling of part of the retaining structure, using the finite element software Plaxis 2D,
in order to assess the quality of results, compared to data from topographic instrumentation, and a back analysis. This study showed
that the analyzed ground had higher secant stiffness than the one originally adopted in the modeling, as well as lower friction angle
and cohesion. The study demonstrated that when using King Post Walls, the ground movements around excavations are essentially
affected by the constructive sequence, soil’s stiffness and strengthness, weather conditions and their influence on the ground’s
behavior. The ground movements are transmitted to neighboring buildings, whose response depends on their building type and pre-
existing damage.
KEYWORDS: Excavation and peripheral walls, urban space, King Post Walls, ground movements, instrumentation, modeling, back
analysis.
Introduction
Now, when building construction industry is experiencing a
severe crisis in terms of new projects, it’s becoming more and
more frequent the use of the already built urban space, leading
to the use of underground space, in order to maximize the
building areas. Those projects often occur near old and
sensitive structures; therefore, the necessary interventions
require extra care to prevent any damages.
In Portugal, King Post Walls are often used on an
empirical knowledge basis, which leads its constructive
sequence being modified, without taking into account the
excessive ground movements during the excavation process.
Without adequate instrumentation and monitoring, the un-
prediction of excessive ground movements may result in
damage to nearby buildings, or even incidents with severe
consequences for people and goods.
In this specific case there was a follow-up of the
construction works on the ground, which included the
observation of the constructive procedures used during the
excavation and peripheral wall execution, so that the urban and
geological environment could be better understood during the
process. Based on the visits carried out, the aim was to
compare the designed solution with the executed one,
regarding both the constructive sequence, and the
Instrumentation and Observation Plan. It was also carried out a
comparative analysis between the instrumentation results and
the main construction events and excavation stages, seeking
cause and effect relations, with more focus on the ground and
wall movements and their negative impacts.
The case-study analysis was complemented with a FE
modeling, using Plaxis 2D, where the objectives were to
evaluate the initial modeling, and to add a new model that
included the implemented mitigation measures during the
excavation process, comparing the results. The goal was also
to make a retro-analysis of the final solution, as an attempt to
bring as close as possible both the displacement values
provided by the instrumentation and the initially expected ones
in the design phase. That analysis was accomplished by
amending the model’s geotechnical parameters using the
Hardening Soil Model.
Excavations and Peripheral walls in urban space
The analysis on retaining structures has so far been based on
an equilibrium analysis, combined with an elasto-plastic soil
analysis, in order to estimate the horizontal stresses that form
behind the wall [1]. In the specific case of multi-anchored
walls however, other hypothesis must be considered in the
analysis, because the assumption of an active state behind the
wall leads to displacements that are incompatible with the ones
observed in those structures. The appearance and development
of the FE software’s has enabled a better resolution of these
problems, approaching the numerical analysis with actual wall
displacements.
The multi-anchored wall’s anchors work mainly by
the stress field change induced in the soil, meaning that there’s
an increase of the horizontal stress in the wall (and a deviatoric
stress increase) with the anchors prestressing, with a
consequent decrease in the deformation, as a preparation for
the next excavation stages; then, the retained soil’s horizontal
stress decreases again, and there’s the consequent movement
increase [2].
Multi-anchored walls
In retaining structures projects located in urban space it is
necessary to evaluate the predicted displacements before the
beginning of the construction works, i.e. during the design
phase. Before the existence of FE software’s that evaluation
was only based on previous experiences in similar projects
with similar soils. Yet, to model a retaining structure using
FEM software, a high number of parameters is required for the
analysis, so that the simulated excavation’s behavior can be
close to the real one. These parameters are determined
experimentally, or empirically, which doesn’t dispense a
![Page 2: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/2.jpg)
- 2 -
rigorous monitoring of the construction works, to confirm the
assumed geological conditions.
Ground movements around excavations may occur
due several factors, such as drilling, grouting, groundwater
changes, excessive excavation, inadequate support, timing,
unpredicted surcharge, etc. Those movements are caused by
changes in the stress field in the surrounding soil, mainly due
to the horizontal and vertical stress relief. Ground movements
can be divided into horizontal movements, due to horizontal
displacement of the wall (because of the horizontal stress
relief), vertical ground movements (settlements behind the
wall), or heaving of the bottom of excavation, due to the
vertical stress relief in that area [3].
In King Post Walls the critical phase for excessive
displacements is the panel’s excavation phase, and the time
that goes between the concreting phase and anchor stressing or
propping. After this, the displacements above the excavation
level come to depend essentially on the anchor’s prestressing,
and their stiffness and soil interaction, knowing that the
displacements occurred are substantially lower at this stage.
Excavation’s supporting systems
There are three main excavation’s supporting systems used in
urban space: props, prestressed anchors, and more recently, a
support system achieved by reinforced concrete framing
executed at each excavation level; besides the top-down
system, which is not addressed in this paper.
Despite the economic advantage, both in materials
and labor, and the short execution periods, the use of prop as a
supporting system in peripheral walls has also significant
limitations: large work space occupation, especially when big
section stays, or steel profiles, are needed to achieve larger
spans without buckling or bending problems. Still, there are
situations in which props represent a better option compared to
ground anchors: there’s no need to invade the adjacent
underground space, which induces fewer disturbances; or
when the firm layer lies too deep so it doesn’t pay off the
execution of ground anchors. It’s also possible to pre-stress the
large section struts, which allows a more effective supporting
system, with less wall and ground movements.
The most used supporting system in urban
excavations is still pre-stressed anchoring, because of its
advantages if compared with other systems: due to pre-stress,
there’s a significant decrease of horizontal displacements at the
top of the wall, and the consequent ground settlement decrease
behind the wall; it’s a safer process compared to struts
installation, for these can be damaged during the excavation
works by the circulating equipment’s; ground anchors don’t
cause space constraints during excavation. However, there are
some limitations: they’re less economic and require larger
execution periods; need specific equipment and specialized
labor; their design is limited by nearby underground existing
structures (utilities, tunnels, basements), with changes in the
tilt angle and consequent efficiency loss; cement injection for
the grout body can damage adjacent structures, caused by lack
of geological knowledge, or lack of control in the injection
process (excessive pressures); there’s a large waste of material
that is lost in the ground, for interim anchors; comparing to the
supporting system with structural elements, ground anchors
induce more disturbances in the surrounding soil, with
consequent larger wall displacements and ground movements
that may damage the nearby buildings.
The excavation supporting system by structural
elements (reinforced concrete framing) consists in the
execution of concrete slab band frames at each level of current
excavation, which will be part of the definitive structure.
Although still not widely used in peripheral walls supporting,
this method has significant advantages in urban sites: more
safety and lower soil decompression during excavation,
compared to props and anchors, as it’s necessary to dig a
smaller soil portion to execute the slabs; there’s a wide
availability of space inside the working enclosure, since the
slab bands have only the minimum sufficient width to
accommodate earth pressures; there’s no invasion of the
underground space, minimizing the negative impacts on
existing buildings; it doesn’t cause the decrease of stiffness
and strengthness of the wall, since it’s not necessary to drill the
retaining structure itself; there’s a good compatibility between
the temporary and the definitive buried elements, since the
slabs are already a part of the final structure. Still, there are
also some disadvantages: less space below the executed
supporting slabs, which interferes and delays the digging
works; additional vertical elements are needed, to brace the
slab bands, usually micro piles or steel profiles, executed from
the surface and before the excavation.
Excavation’s influence in nearby structures
Ground movements induced by excavations grow
progressively like waves, reaching adjacent structures and
spreading over them, as the excavation proceeds. As it is quite
difficult to establish direct relations between the
excavations’/walls movements with the displacements in the
building, the common practice consists in limiting the wall’s
displacement, as an indirect control method to prevent any
damage to structures adjacent to excavations. That
displacement limiting criteria should be applied at an early
design phase, and even contribute to the choice of the
peripheral contention method. The displacement limits must be
adequate for each situation and monitored during the
construction works.
Damages in structures adjacent to excavations are
much more due to differential settlement than to the absolute
values of settlements. The initial stress field is sometimes
underestimated, and not always the results are conservative. It
is also difficult to establish soil parameters related with time
[4].
Ground movement’s transmitted to adjacent buildings
make these to have rotation and translation movements,
distortion, and possible damage, when the maximum
deformation capacity is reached. Small vertical and horizontal
displacements and rigid body translation usually don’t affect
the safety of the buildings, but affect their serviceability
functioning due to some local damage. Distortions are induced
by differential displacements from different parts of the
structure: differential horizontal displacements cause
horizontal compression or extension distortion; differential
vertical displacements of a structure can cause bending and
shear distortion. When evaluating the response of buildings to
ground movements, rigid body deformations should be
separated from distortions, otherwise the analysis can be too
conservative, particularly when the assessed building’s
foundations can absorb a part of the horizontal strain [5].
Design graphics and field experience are helpful tools
to obtain initial displacement limits, and even to compare with
the results provided by numeric calculation methods, like FE.
![Page 3: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/3.jpg)
- 3 -
This method has given good results, since it uses constitutive
soil models that take into account its non-linear and continuous
behavior. They are able to simulate the multiple stages
involved in the construction process, and the interface between
wall and soil. However, the displacements calculated by those
methods are often more accurate predicting wall displacements
than the associated ground movements. Despite the increasing
development of these calculation methods, it’s still necessary
to define boundary conditions and a high number of
parameters for the complex constitutive soil models. The
uncertainties associated with these predictions are mostly
compensated by the adopted safety factors in the design of
retaining structures, and by the investment on instrumentation
and monitoring, which controls the appearance of cracking and
excessive displacements.
King Post Walls
Given his economic advantages and relatively easy execution,
this type of constructive method has been used in Portugal ever
since the 70’s in both peripheral and retaining walls. However,
more recently, King Post Walls have been replaced by other
more effective retaining structure techniques, such as
diaphragm walls or bored pile walls, as these induce less soil
decompressions, as well as shorter execution periods. To
design King Post Walls, one can assume the behavior of a
flexible multi-anchored, or braced, retaining wall, which is
characterized for its high deformability during the excavation
and construction phases, being also highly influenced by the
soil-structure interaction.
Case Study: Palácio dos Condes de Murça
The case-study presented in this paper is the excavation and
peripheral contention for the execution of the underground
floors planned in the project “Palácio dos Condes de Murça”,
located in Santos, Lisboa, (Fig. 1). Fig. 2 shows a diagram
with some reference adopted points and respective side views
of the working enclosure.
The Excavation and Peripheral contention design was
carried out by “JetSJ” and was based on the permit design,
elaborated by “AfaConsult”. The construction technique
suggested by the initial design has undergone some changes, in
order to optimize costs, as far as local constraints allowed [6].
Fig. 1. Building area of the project [7]
Fig. 2. Side views of the working enclosure (adapted from [8])
Geologic-geotechnical and vicinity constraints
In order to define the geology of the “Palácio dos Condes de
Murça” neighboring northwest area, some support jobs were
carried out: drilling of 10 mechanical boreholes, 10
foundation’s observation wells, installation of standard
piezometers in 4 boreholes, and water sample collecting to
perform lab analysis. From the interpretation of the described
field tests, it was possible to establish the existence of three
geological units, which were formed by landfill deposits (L.D.)
on the surface, deposited on two Miocenic stratums (M1 and
M2). One of the geological profiles drawn based on the bored
holes information is displayed in Fig. 3.
Fig. 3. Geological profile no. 8 (adapted from [9])
The three geological units are described by:
Landfill deposits: very variable thickness, consisting of
pebbles and fragments of scattered limestone, ceramics
and some organic contamination, such as roots and plant
debris; dominant clay matrix, and considering the
obtained SPT test results of 3 to 10 strokes, with a loose to
medium compactness;
Layer M1: composed of red clay with erratic limestone
fragments, until 6 to 10 m;
Layer M2: limestone, whitish color, appearing generally
very fragmented, but with high recovery rates, and some
signs of carsification, but not enough to classify the solid
as karst, rather than compact; displayed in sub-horizontal
benches interspersed with relatively thin clay veins.
Based on the geological description of the formations
found, it was made the following geotechnical zoning (Table.
1):
![Page 4: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/4.jpg)
- 4 -
Table. 1. Geotechnical parameters for each zone [10]
Nspt γ
(kN/m3)
Φ'
(º)
c'
(kPa)
E
(MN/m2)
Cu
(kPa)
Landfills <10 18 30 - 6-8 -
M1 10-
30 18-19 25 5-10 15-30
50-
100
M2 >30 22-24 50 50-
100 100-200 150
Due to the impermeability of the superior clay
fraction, it was determined that the Miocenic limestone
structure was not conducive to feeding and maintenance of
groundwater levels; therefore, the measured groundwater
levels were considered negligible [9].
The intervention was done in a densely urbanized
area, with old surrounding buildings, and sensitive stone
masonry structures. The working enclosure was bounded by
streets, and several adjacent buildings that had to be preserved
[10].
Construction solution and Monitoring Plan
Given the geological described scenario, the chosen
construction technique for the peripheral wall’s execution was
King Post Walls, because it was the most suitable for the type
of soil crossed by the excavation. The wall would be composed
by reinforced concrete panels, temporarily supported by steel
HEB profiles, and also anchored or braced.
During the excavation works and underground floors
construction, the proposed Monitoring Plan was intended to
allow the measurement of the values described in Table. 2 (1st
column), which would be measured by the installed devices
also described in Table. 2 (2nd
column). Based on the adopted
construction technique, it was possible to estimate the criteria
described in the same table (columns 3 and 4), for each value,
to be confirmed during the project execution.
Table. 2. Aspects of the Monitoring Plan (adapted from [10])
Values to measure Measuring devices Alert limits Alarm limits
Horizontal and vertical
displacements of the retaining
structures
Topographic targets to measure the three-
dimensional displacement of retaining structures
(min. 37 units)
Horizontally,
maximum
displacements of 20mm/10 meters of
excavation height, and
vertically, maximum
displacements of 15mm/10m
Horizontally,
maximum
displacements of 30mm/10 meters of
excavation height,
and vertically,
maximum displacements of
30mm/10m
Horizontal and vertical
displacements of the adjacent structures
Topographic targets to measure the three-
dimensional displacement of adjacent structures (min. 25 units)
Vertical displacements of
pavements and surrounding
ground surface
Topographic marks for measuring vertical
displacements of the floors and the surrounding
ground surface (min. 2 units)
Load measurement of the ground
anchors
Load cells installed on the ground anchors to
load measurement (min. 9 units) - -
Measurement of the allowable
peak vibration velocity
Piezometric accelerometers for measuring the
allowable peak vibration velocity (min. 6 units)
maximum particle
velocities of 2.5 mm/s
in the Church zone, and
of 5.0 mm/s on other sites
maximum particle
velocities of 3.5
mm/s in the Church
zone, and of 7.0 mm/s on other sites
The mitigation measures initially planned in case of the
alert and alarm limits were reached, should be analyzed
individually, and consisted, among others, in [10]:
Increasing the vertical load capacity of the retaining wall,
by installing additional vertical steel profiles or micro
piles;
Strengthening of horizontal support of the retaining wall,
by additional execution of ground anchors or props,
eventually with a bigger free length and steeper
inclination;
Partial excavation’s support through structural slab
elements – reinforced concrete frames;
Additional drainage devices on the retaining wall;
Treatment of the decompressed soil located behind the
retaining wall.
Once that abnormal crack opening of pre-existing cracks
in adjacent buildings were observed, 5 fissurómetros, type
“Gauge 1.1” (adequate to measure cracks in the same
plan/frame), were installed, on December 20th.
Construction’s works evolution
Work’s observation on site
Some observation visits were made in order to follow
up the progress of the works, and also to observe the execution
of the constructive processes involved in King Post Walls. One
could observe closely some constructive aspects mentioned
before, that may have contributed to the excessive ground
movements in some areas.
It’s shown in Fig. 4 a situation where it may have
been some disregard of the constructive sequence, which may
have caused the soil to decompress, given the excavation
height and the non-cohesive type of soil. Being the first area to
be excavated and functioning as a double primary corner panel,
the corner area should have been treated with special attention,
and concreted after primary panels, unlike what happened.
This may have induced some stress relief in the soil, which as
shown in the figure, appears to be somewhat inconsistent when
excavated, and therefore, the displacements that were
measured on the topographic targets installed in the adjacent
building.
![Page 5: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/5.jpg)
- 5 -
Fig. 4. Opening of the 3rd level panels on the corner “I”
Several steel vertical profiles over the side view FG
aimed as a vertical support to the retaining wall, while the
excavation didn’t get to the foundation elevation height, got
bent, as shown in Fig. 5. Their positioning outside the wall
definitely contributed to the occurrence of buckling of the
profiles, which was exacerbated by the impacts suffered during
the digging works caused by heavy circulating equipment.
Fig. 5. Bent vertical profiles along the side view FG
This situation probably led to a deficient transmission
of the vertical loads to the firm ground, and the consequent
increase of settlements. In this case, the consequences were not
severe, for a stratum of rock had already been reached, which
allowed a good embedding of the wall, and in some areas the
excavation had reached the footing elevation. Moreover, this
behavior was being monitored by instrumentation, and the
displacements observed didn’t reach the alert and alarm limits,
so the worker’s safety was controlled; still, there were slight
damages to the adjacent structures.
Instrumentation’s evolution
Based on the results observed from the 15 topographic targets
initially installed (Table. 2, column 2), it became clear that,
from the beginning of the construction works, in the end of
September 2010, until December there were no problems
related with the excavation’s movements.
However, by January 10
th 2011, increasing crack openings
were observed in adjacent buildings in FG side view (at the
“F” corner), belonging to the Belgium Embassy [11]. That was
happening in an area where the digging and panels concreting
works were very active. The cracks originated from ground
movements generated by several factors in the area: some
probably related to disturbances caused by an adjacent wall
collapsing in EF side view; the excavation at the “F” corner
did not respect the constructive sequence (simultaneous panels
opening); intense precipitation; also the fact that several
consecutive panels in the “F” corner area were already
concreted, but still without the ground anchors executed.
So, it’s been decided to adopt mitigation measures: to
strengthen the areas where the adjacent buildings were
degraded, through the execution of concrete wall sections
above the top tie beam, complemented by the extension of the
vertical steel profiles and their connection between the new
sections and the existing wall, using steel connectors, to
provide a better support of the adjacent building’s façades; the
rigid bracing of the “F” corner with structural slab elements in
reinforced concrete, instead of the steel corner prop initially
planned.
It was done a comparative analysis between the
results of the topographic measurements and the fissurometers
measurements. In the Belgium’s Embassy area, one of the
topographic targets that had larger displacements was no. 8,
located on this building’s façade (Fig. 6). After 15
fissurometers measurements (Fig. 7) the cracks were repaired
and the devices were installed again. As time went on, no new
crack openings were observed, indicating that the
reinforcement measures functioned well.
The evolution of the displacements registered on
target no. 8 showed some variations along M and Z axes over
time. Despite the apparent stabilization of the displacements in
mid-January, from then until mid-April those displacements
increased again towards the interior of the excavation (-M),
and with increasing settlements (-Z). After mid-April, the
displacements continued to increase slightly, but at a lower
rate. Knowing that by this time the extension of the peripheral
wall in this area had already been executed, as well as the first
two levels of the “F” corner’s support, it makes sense that the
movements have stabilized or tend to stabilized, which is also
an indication that these mitigation measures succeeded. This
reaction was not immediate probably because the ground was
heavily decompressed at the beginning of the digging works,
and the soil had worse stiffness and strengthness than initially
assumed. The disturbances caused in the adjacent building’s
foundations were spreading to the upper levels of the structure,
as the excavation progressed.
It’s possible to establish a relation between the target
no. 8 and Gauge 1.1, for these devices are in the same location
in ground view. Looking at the evolution of these
fissurometers measurements in Fig. 7 it’s possible to see that
the crack opening began to stabilize by the end of January,
early February. Given that by this time the implementation of
the reinforcement measures was being carried out, it is
reasonable to establish a relation between the two events. As
the new concrete support was being done in the “F” corner,
with the 1st slab level being finished around the 7
th of February,
the 2nd
level by the 20th of February, and the 3
rd level in early
May, an almost complete stabilization of the crack opening in
this area was being achieved.
Shortly after abnormal cracks opening in buildings
attached to the Belgium Embassy, the same started to happen
in the kindergarten buildings, located on side view IH.
Therefore, four more fissurometers were installed in this
building to monitor the cracks (Fig. 8).
![Page 6: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/6.jpg)
- 6 -
Fig. 6. Displacements registered on topographic target no. 8 (adapted from [12])
Fig. 7. Crack openings registered on the fissurometers placed in the Embassy buildings
Fig. 8. Crack openings registered on the fissurometers placed in the Kindergarten building
Possibly due to the end of the digging works on side
view GH and the temporary suspension of the same, in side
view IH, after the execution of the top tie beam, the monitored
cracks had a relatively stable behavior, and Gauge 1.1 even
closed to 0.5 mm. However, after the excavation works started
again in side IH, Gauges 1.1 and 1.2 began to register some
strains. This same behavior can also be seen in Fig. 9, which
shows the displacements measured in topographic target no.
14, located on the kindergarten building. During February, the
digging and concreting works were suspended again, in order
to allow the ground to stabilize, stopping the damage in the
adjacent building. And by the middle of the month new targets
were installed on the working field, some located on the
kindergarten’s building façade, at several levels, and on the top
tie beam.
With the data available it’s not possible to establish a
linear relation between the target displacements, the
fissurometer values, and the excavation stages, because works
affect the buildings in a complex way, which depends on
building’s response to ground movements, based on their
foundations and structural system. Still, it is possible to detect
a trend of stabilization from May, which probably corresponds
to the end of the excavation and anchor tensioning in this area,
and subsequent landfill with the excavated material. This trend
is also visible in Fig. 9 and the greater increase of the
displacements inwards the excavation occurred between March
and May, when the digging, panels concreting and tensioning
works, moved faster, stabilizing in the edge of the alert limit
(9.45 mm for settlements, and 12.6 mm for horizontal
displacements). The remaining targets installed later in this
façade (nos. 24 to 28, and 44) showed the same trend, with
larger displacements on the top of the building rather than in
the top tie beam, which explains the cracks in the
Kindergarten, located on the superior floors.
-2-101234567
15-Dec-10 4-Jan-11 24-Jan-11 13-Feb-11 5-Mar-11 25-Mar-11
Crack opening (mm)
Gauge 1.1
Gauge 1.2
Gauge 1.3
Gauge 1.4
Gauge 1.5
-0,5
-0,25
0
0,25
0,5
0,75
1
13-Jan-11 17-Feb-11 24-Mar-11 28-Apr-11 2-Jun-11 7-Jul-11
Crack opening (mm)
Gauge 1.1
Gauge 1.2
Gauge 1.3
Gauge 1.4
![Page 7: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/7.jpg)
- 7 -
Fig. 9. Displacements registered on topographic target no. 14 (adapted from [12])
These results also support the fact that in this area the
soil was very sensitive to any disturbances, as well as the
foundations of the adjacent buildings, showing negative
responses very quickly when the digging works occurred. The
fact that the panels remained without support (tensioned
ground anchors) too long after concreting, may have
contributed to the soil decompressions referred above. There
were some difficulties in the constructive sequence
coordination because the equipment and the specialized labor
for drilling and tensioning the ground anchors weren’t always
available on the field.
Solution’s modeling
A numerical FE software, Plaxis 2D, was used in the design of
the peripheral wall. This software is a calculation tool widely
used in modeling of geotechnical problems, because it allows
recreating approximately the mechanical behavior of soil and
underground structures, also allowing an analysis of the soil-
structure interaction.
Initial Solution
Six sections in various locations were analyzed in the project
solution’s modeling, which were considered to be the most
representative and conditioning for the design. One of these
sections, no. 4, located on FG side view, near corner “F” and
the Embassy buildings, is briefly described; the other sections
followed similar principles, only changing the geometry of the
site and their constructive solution. The final look of section
no. 4 is shown in Fig. 10.
Fig. 10. Model’s geometry of section no. 4
For the definition of the soil characteristics Plaxis has
the option of various constitutive soil models that simulate the
behavior of materials. The chosen model was the Hardening
soil model. This model recreates the behavior of different
types of material assuming a non-linear stress-strain path. As
the soil is subjected to increasing shear stresses, the stiffness
decreases and there are plastic irreversible deformations. For a
good characterization of each material, the model requires the
definition of some parameters; the parameters used for the
soils dealt with during the excavation are presented in Table. 3,
based on the Geotechnical-Geological report.
Table. 3. Soil parameters
Parameters
Geothecnical zones
Landfill
deposits M1
Improved
M1 M2
γ [kN/m3] 18 18 18 19
[kN/m2] 8000 25000 35000 100000
[kN/m2] 8000 25000 35000 100000
[kN/m2] 24000 75000 105000 300000
cref [kN/m2] 0.1 30 30 100
ϕ [°] 30 35 35 40
ψ [°] 0 0 0 0
νur 0.2 0.2 0.2 0.2
K0nc 0.5 0.426 0.426 0.357
After the calculation phase it was possible to see in
the software’s output the deformed mesh, as well as the
displacements and stresses on the ground, and forces and
displacements of the wall. For this section, the deformed mesh
and the obtained horizontal and vertical displacements are
shown in Fig. 11, Fig. 12 and Fig. 13, respectively.
Fig. 11. Deformed mesh for the initial modeling on section no. 4
![Page 8: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/8.jpg)
- 8 -
Fig. 12. Horizontal displacements for the initial modeling on
section no. 4
Fig. 13. Vertical displacements for the initial modeling on
section no. 4
Solution including reinforcement measures
It was carried out a new modeling of the same section (no. 4),
but including one of the mitigation measures, the bracing of
the “F” corner, in order to observe the differences at the final
excavation phase, in terms of wall and ground movements. As
the Plaxis version used only allows a bi-dimensional analysis,
it was not possible to model the slab supporting system with
their real triangular shape. Therefore, it was necessary to adopt
some simplifications to obtain the maximum approximation of
the existing solution. Instead of ground anchors, formed by
free length and grout body, fictional props on two excavation
levels were used (Fixed-end anchor elements). As the length
of the concrete fictional props is variable (since they’re
triangular), it was adopted a medium equivalent length, and the
normal stiffness of a reinforced concrete element 0.25 m thick
and 1 m width (per meter of prop). Finally, the adopted
solution for the new supporting system was a couple of
concrete struts 8.6 meters long, with normal stiffness of
8.25E6 kN/m2 and spaced by 1 m. After running the model the
results are shown in Fig. 14, Fig. 15 and Fig. 16.
Comparing the previous picture to Fig. 11, it’s
possible to see that the ways the wall deforms with a 4 ground
anchor supporting system and with a 2 concrete props system
are quite different, and that the second alternative allows a
better control on deformation. Fig. 15 shows the expected
horizontal displacements, and comparing to Fig. 12, it’s visible
that the soil mass affected by the excavation is much larger
with the anchor solution, and the area where the displacements
are maximum (around 5 mm) is also wider than in the new
solution, where the displacements are also lower, reaching a
maximum value of about 3.5 mm in the area between the 1st
and 2nd
concrete props.
Fig. 14. Deformed mesh on section no. 4, including mitigation
measures
Fig. 15. Horizontal displacements on section no. 4, including
mitigation measures
Fig. 16. Vertical displacements on section no. 4, including
mitigation measures
Analyzing the occurred settlements, the wall’s
behavior with the new supporting system is also significantly
better (Fig. 13 and Fig. 16). In addition to the values of
displacements being lower, in about 1 mm against 3 mm in the
![Page 9: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/9.jpg)
- 9 -
anchor’s solution, the affected area is also much smaller in
size, and is located further away from the excavation site.
Back-analysis
The back analysis was based on the results given by
instrumentation, mainly from the topographic target
displacements. The parametric analysis was performed for
each geotechnical zone and for each soil parameter, using the
results obtained for section no. 7, in particular from target no.
25, placed on the top tie beam, in side view IH. The back
analysis was also carried out using the data of the topographic
target no. 25. Only the horizontal displacements were
analyzed. There was no back-analysis on vertical
displacements because it has been observed that these can’t be
approximated to the real ones; where the analysis predicts soil
heave, there are actually settlements, due probably to a
numerical problem of Plaxis for this situation. Fig. 17 shows a
chart with the displacements progress on target no. 25, and the
ones predicted by the software, throughout the excavation
phases.
Fig. 17. Horizontal displacements predicted on Plaxis, and registered on Target no. 25
It’s possible to see from the chart above that the pace
of displacements is similar, until the first level anchor’s
tensioning, where the movements provided by Plaxis suffer a
rather sharp decrease (movements outside the excavation),
which was not observed in reality with such intensity. In the
following stages the two curves show differences of about 4.5
mm, but with a very similar pace and increasing movements
inwards the excavation, with a lower rate. It is thus quite
plausible to infer that the differences between calculated and
reached horizontal displacements come from the first level
anchors tensioning. For the final stage, the software predicted
that the analyzed point would be placed outside the excavation,
while in reality the opposite situation had happened, albeit
with a difference of a few millimeters, and without reaching
any alert or alarm limits. However, these variations may have
triggered differential displacements in the adjacent building,
where the crack opening occurred.
After a first stage of parametric analysis, where only
the secant stiffness and cohesion were changed, another way
was chosen, since the results weren’t leading to realistic
displacements. Several combinations of the geotechnical
parameters chosen before, plus the friction angle, with a 50%
variation, were made. The results obtained, displayed on the
charts of Fig. 18 and Fig. 19, allowed the drawing of some
conclusions about the influence of the geotechnical parameters
analyzed:
Changing the secant stiffness controls how the field reacts
to the ground anchors tensioning: for higher stiffness, it
looks like the movements due to stress field change
induced by the pre-stress are substantially higher than the
situation in which this parameter is lower. This
phenomenon had already been seen before in the analysis
of the influence of the stiffness, alone.
A decrease in the stiffness together with cohesion induces
the greatest soil decompressions in the initial excavation
stage. This is worsened when decreasing also the friction
angle. However, in both cases there are large
deformations outwards the excavation (when the first
anchor level is tensioned) which are not so intense when
the friction angle is increased simultaneously with the
other parameters.
Increasing the friction angle results in an increase in
wall’s deflection outwards the excavation during the
anchor’s tensioning. This behavior is opposed to the effect
caused by changing the stiffness.
The extreme situation for maximum displacements
inwards the excavation was obtained for the combination
of a 50% increase on both the friction angle and the
cohesion, simultaneously. And the maximum
displacements to the opposite direction were obtained for
the reverse combination, i.e., decreasing the same
parameters by 50%. It follows that for this range of values
the parameters with more influence on the wall’s
deflection are the friction angle and the cohesion,
simultaneously, which define Mohr-Coulomb rupture
criteria.
Based on the results obtained from the parametric analysis it
was possible to estimate the changes to be made to the initial model, so that the deformations predicted could get closer to
those actually observed. Knowing that higher stiffness lead to
larger deformations outwards the excavation at the anchors tensioning stage, it has been decided to increase that
parameter. The decrease in the friction angle also causes the
same reaction, as well as an increase in horizontal movements inwards the excavation, during the digging stages: so, another
change was to decrease the friction angle. It has also been decided to lower cohesion, because this change along with the
decrease in friction angle induced superior horizontal
movements, closer to reality. Several iterations were then carried out in order to approximate the results, whose the most
relevant are displayed in
Fig. 20.
-8
-6
-4
-2
0
2
4
16-Mar 26-Mar 5-Apr 15-Apr 25-Apr 5-May 15-May 25-May 4-Jun
Def. [mm]
Ux_targetno. 25Ux_Plaxis
1st
panel Landfill Partial landfill and
superstructure 2nd
panel 3rd
panel
![Page 10: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/10.jpg)
- 10 -
Fig. 18. Horizontal displacements obtained from changing the parameters E50
ref, cref and φ’ by 50%, of the M1 layer, in combinations of 2
Fig. 19. Horizontal displacements obtained from changing the parameters E50
ref, cref and φ’ by 50%, of the M1 layer, in combinations of 3
Fig. 20. Comparison between the back analysis results and the displacements given by instrumentation
The chart shows that a relatively good approximation
was achieved, particularly in the early stages of the excavation
sequence. From then on, the displacement’s pace along the
constructive stages is largely controlled by the first anchor
level tensioning on the ground, and it hasn’t been achieved an
ideal situation between the displacements. For a 25% increase
in stiffness, and a 25% decrease in friction angle and cohesion,
the final values were quite similar, but the curve pace was
different. In situations where the parameters were changed by
40% and 35%, the tensioning stage was better approximated,
but the final displacements overestimated.
Yet, this trend wasn’t maintained when the
parameters were changed by 50%. This shows once again that
this analysis is of a non-linear type, due to the interdependence
of geotechnical parameters in the constitutive model adopted.
In order to bring the results closer, it was made a new attempt,
which consisted in the increasing of stiffness by 50%,
maintaining friction angle and cohesion at 25%, aiming the
reduction of the horizontal displacements outwards the
excavation due to the tensioning stage, and keeping the
horizontal movement during the digging stage. However, the
results were remarkably similar to the previous iteration
(25%), meaning therefore that by changing those parameters a
better approximation would not be achieved. Thus, considering
the results obtained, and assuming that the remaining
parameters chosen for the model are similar to the real ones, it
follows that the stiffness values are actually higher than those
-18-16-14-12-10
-8-6-4-202468
6 8 10 12 14 16 18 20 22 24
Def. [mm]
Excavation stages
InitialmodelingE+50, c+50
E-50, c-50
E+50, φ+50
E-50, φ-50
c+50, φ+50
c-50, φ-50
-12-10
-8-6-4-202468
6 11 16 21
Def. [mm]
Excavation stages
Initialmodeling
E+50, c+50, φ+50
E-50, c-50, φ-50
-8
-6
-4
-2
0
2
4
6
16-Mar 26-Mar 5-Apr 15-Apr 25-Apr 5-May 15-May 25-May 4-Jun
Def. [mm]
Target no. 25
Initial modeling
E+50, c-50, φ-50
E+40, c-40, φ-40
E+35, c-35, φ-35
E+25, c-25, φ-25
1st
panel Landfill Partial landfill and
superstructure 2nd
panel 3rd
panel
![Page 11: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/11.jpg)
- 11 -
adopted in the initial modeling, and the friction angle and
cohesion values are lower.
In addition to the high level of uncertainty associated with
the parameters assumed in the calculation process and their
relative randomness, there are several possibilities to explain
the discrepancies between reality and numerical results:
The problem’s modeling is made in a bi-dimensional
mode, so it’s not possible to recreate the behavior of the
ground during the execution of the King Post Walls. This
happens because this technique takes advantage precisely
on the arc effect created by the soil benches, which is a
tri-dimensional phenomenon.
The very constructive sequence cannot be perfectly
simulated by the software, which is more suitable for
retaining walls built from the surface and before the
excavation stage, such as diaphragm walls or bored pile
walls;
The carried out modeling didn’t consider several aspects
concerning the timeline along the constructive stages
observed on the field, such as the waiting periods before
the ground anchors tensioning, and the periods during
which the excavation works were temporarily suspended
in side view IH, due to movements measured in the
adjacent building;
The modeling also didn’t consider the fact that there was
heavy rainfall by the initial stage, and it wasn’t possible to
pump all the accumulated water, which may have induced
more movements in the superficial soil layers, due to loss
of the strength and stiffness characteristics;
Insufficient vertical equilibrium, resulting from a deficient
functioning of the vertical profiles, which should support
the wall vertically. A pattern situation was observed, in
which the sides where the vertical profiles were placed
outside the concrete wall, had higher than expected
settlements, unlike what happened on the other sides.
The adopted surcharge in the design stage, used to
simulate the weight of adjacent buildings, may also have
contributed to inaccuracies, for it’s almost impossible to
ascertain the actual surcharges, caused by lack knowledge
about the structural constitution of the buildings and their
foundations.
Damage risk assessment
A brief damage risk assessment to neighboring buildings was
done. The option was to analyze only one of the modeled
sections with an adjacent building – in the middle of side view
IH, near the kindergarten building. Based on the design project
plants, it was assumed that the building is 12.5 m wide inside
the non-excavated area.
This analysis was based on the method described by
Boscardin and Walker [5], and also on a method presented by
Son and Cording [13], suggested by Rankin [14]. A “slight”
damage level was assumed as being reasonable, and given the
aim of this study, the final excavation stage was held as the
most unfavorable one.
1st Method
For a final horizontal deformation of the ground surface of 4.6
mm and vertical deformation of 2 mm, which corresponds to
an horizontal strain (εh) of 0.37x10-3
and an angular distortion
of 0.16x10-3 (for a reference length of 12.5 m), the resulting
damage would be “negligible”. Knowing that the maximum
crack opening in this building was of 0.75 mm, which
according to Son and Cording [13] corresponds to “very slight”
damage, the prediction based on this method is not accurate,
and it wouldn’t be necessary to carry out a more elaborated
risk assessment.
However, it happened that the solution’s modeling
underestimated these deformations, and the real maximum
horizontal and vertical displacements registered in the
kindergarten building (on topographic targets nos. 14 and 26,
installed on the building’s façade) was actually 14 mm inwards
the excavation and a settlement of 10 mm. Using this values,
the horizontal strain would be thus 1.15x10-3
and the angular
distortion thus 0.8x10-3
, and the expected damage level would
be “slight”, which corresponds to the registered damages. It
must be noted that the correct procedure would have been to
use the deformations registered on the ground (with
measurements taken for instance by inclinometers), rather than
measured displacements along the building’s façade, which
may have tampered with the damage predictions; still, this
results show that the damage criterion turned out to be correct,
but their results were tampered by the numerical modeling
discrepancies.
2nd
Method (vertical deformations)
For a 2 mm maximum final settlement on the building base,
and assuming the same 12.5 m wide, the building would have a
predicted slope of 1/6250, which according to Rankin [14]
should lead to “negligible” risk, with unlikely superficial
damage. This prediction underestimates the damages that
actually occurred, although these have been “slight”.
Despite the registered settlements on the topographic
targets were higher (than 2 mm), reaching a maximum of 10
mm, the corresponding slope was from 1/1250, still in a
“negligible” risk range. These discrepancies can be explained
by the fact that the used criterion should be applied to less
sensitive structures, given that this particular building had
already some visible cracks. Assuming the limit cracking
values from differential settlements in buildings, suggested by
Bauduin [4], it was observed that these limit values are in fact
lower: for a deflection ratio of 1, the limits are 1/2500 for
sagging and 1/5000 for hogging. Even without the data needed
to perform a detailed analysis of the settlement profile, it was
clear that the real slope exceeded this limit, leading to crack
opening, as registered on the fissurometers.
This short assessment points out once again the important role
played by a good FE model adequacy to reality, as well as by
the damage criterion chosen for the analysis.
Conclusions
The monitoring of the construction’s works enhanced the
importance to evaluate the on-site conditions, particularly the
neighborhood constraints, involving nearby sensitive buildings,
associated with the ground’s heterogeneity and geological
variability. It also became clear that the constructive sequence
was hard to execute at some points, due to logistical issues,
which are a constant challenge in large projects. Thus, the
instrumentation and its interpretation played a crucial role in
the improvement of the wall movement’s performance,
through the implementation of mitigation measures, which
prevented major damages on the adjacent buildings. Still, the
implementation of a more rigorous Instrumentation and
Monitoring Plan, with a higher number of topographic targets
![Page 12: Excavations and Peripheral Walls in Urban Space Case Study … · Multi-anchored walls In retaining structures projects located in urban space it is necessary to evaluate the predicted](https://reader036.vdocument.in/reader036/viewer/2022080723/5f7c09f196da5654467b4996/html5/thumbnails/12.jpg)
- 12 -
installed on the wall in depth, and including inclinometers and
topographic marks, would have made possible a better
assessment on the expected ground movements.
The analysis of instrumentation’s results showed that
the excessive settlements measured in some topographic
targets were due to several factors: changes in the constructive
sequence, particularly the extended waiting times between the
panels concreting phase and the anchor’s tensioning;
placement of steel profiles outside the concrete retaining wall,
and consequent deficient vertical loads transmitted to the
bedrock; non-consideration in design of the high precipitation
levels experienced during the initial excavation phases, which
may have decreased the stiffness and strengthness of the
excavated soil, comparing with the geotechnical parameters
assumed initially; non-modeling of adjacent buildings due to
their unknown structural system, which made impossible to
analyze the response to the ground movements induced by the
excavation; differences between the geotechnical parameters
adopted in the modeling and the real ones on the ground, due
to the uncertainty associated with their determination, even
with the lab and field test’s results. However, despite the
ground’s excessive displacements observed, and the cracking
measured in some adjacent buildings, it was visible that over
time, with the execution of the reinforcement measures, the
deformations stabilized until the conclusion of the construction
works.
Regarding the simulation of peripheral walls with the
technique of King Post Walls, there are some limitations
associated with the use of Plaxis in two dimensions, because it
can’t exactly re-create the arc effect originated by the soil
benches when opening the primary panels, and their positive
influence on the induced ground movements. The back
analysis demonstrated that the discrepancies between the
displacements predicted and the actual measurements given by
the instrumentation where probably explained by the fact that
the M1 stratum had a higher secant stiffness than the one
assumed in the initial modeling, and lower friction angle and
cohesion values.
Instrumentation and Monitoring Plan play a key role
in this type of projects involving geotechnical works, and
particularly in the analyzed Case Study, being an important
tool, essential for the implementation in due time, of the
mitigation measures needed to ensure the execution of the
project and its maintenance, as well as an adequate control on
the surrounding structures, in safe and economic conditions.
Acknowledgments
The author acknowledges the Project Owner, Artepura, for the
permission to develop and publish this paper. The support of
Prof. Alexandre Pinto, the scientific tutor, is greatly
appreciated. The author also points out the important role of
the companies involved in the Project, Concreto Plano, JetSJ,
Geofix, Kerpro, Geofix.
References
[1] Hansen, J. B., Earth pressure calculation :
application of a new theory of rupture to the calculation
and design of retaining walls, anchor slabs, free sheet
walls, anchored sheet walls, fixed sheet walls, braced walls,
double sheet walls and cellular cofferdams, Danish
Technical Press [for] the Institution of Danish Civil
Engineers, Copenhagen, 1961.
[2] Guerra, N. M. C., Estruturas de Suporte,
Apontamentos da cadeira de Estruturas de Suporte, do
Mestrado para Engenharia Civil, IST, 2003.
[3] Kempfert, H., Gebreselassie, B., Excavations and
Foundations in Soft Soils, © Springer-Verlag Berlin
Heidelberg, Netherlands, 2006.
[4] Bauduin, C., Uncertainties and their relevance for
the design of deep excavations near existing structures, XIII
European Conference on Soil Mechanics & Geotechnical
Engineering Conference, pp.445–449, Prague, 2003.
[5] Boscardin, M., Walker, M., Ground Movement,
Building Response, and Protective Measures, Reprinted
from Effects of Construction on Structures, American
Society of Civil Engineers, Boston, Massachusetts, October,
1998.
[6] Afonso, F., Memória Descritiva e Justificativa de
Escavação e Contenção Periférica para Licenciamento,
Palácio dos Condes de Murça – Lisboa, Afaconsult –
Consultadoria, Engenharia e Projectos, Vila Nova de Gaia,
Junho de 2010.
[7] Vista aérea do Bird’s eye:
http://www.bing.com/maps/, visitada em 22 de Agosto de
2011.
[8] Pita, X., Pinto, A., Peças desenhadas do Projecto de
Execução de Escavação e Contenção Periférica do Palácio
dos Condes de Murça, JetSJ Geotecnia, Lda, Dezembro de
2010.
[9] Tavares, A. J. C., Silva, R. P. A., Palácio dos Condes
de Murça, Reconhecimento Geológico-Geotécnico, Proc.
15110, Geoma Geotecnia e Mecânica dos Solos, Lda, Sta.
Maria da Feira, Abril de 2010.
[10] Pita, X., Pinto, A., Memória Descritiva e Justificativa
do Projecto de Execução de Escavação e Contenção
Periférica do Palácio dos Condes de Murça, JetSJ
Geotecnia, Lda, Dezembro de 2010.
[11] Pita, X., Pinto, A., Relatórios de Análise aos
Resultados da Instrumentação, JetSJ Geotecnia, 2011.
[12] Palácio dos Condes de Murça, Santos, Lisboa,
Relatórios de instrumentação topográfica, Geofix –
fundações e geotecnia, Lda, Lisboa, 2010-2011.
[13] Son, M., Cording, E. J., Estimation of Building
Damage Due to Excavation-Induced Ground Movements,
Journal of Geotechnical and Geoenvironmental Engineering
© ASCE, Vol. 131, No. 2, pp. 162-177, February, 2005.
[14] Rankin, W. J., Ground movements resulting from
urban tunneling: Predictions and effects, Engineering
geology of underground movements, Bell, F. G, Colshaw,
M. G., Cripps, J. C., Lovell, M. A., eds., Geological
Society, London, pp. 79-92, 1988, Apud [32].