Excavations OSHA 1926 Subpart P Jeff Stachowiak Director of Safety Training

Upload: others

Post on 07-May-2021

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Excavations OSHA 1926 Subpart P

Jeff Stachowiak Director of Safety Training

Page 2: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Welcome The intent of this presentation is to give you a basic understanding of excavation safety and some of the rules and regulations issued by OSHA that dictate how to protect employees from death and serious injury.

Page 3: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Introduction This sub-part applies to any open excavations including trenches, pits, shafts, and any other cut made in the earth’s surface.

It does not matter if this cut is formed with an excavator, a shovel, a backhoe, a bulldozer. . . Or ?

Page 4: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Competent person means one who is • capable of identifying existing and predictable hazards in

the surroundings, • or working conditions which are unsanitary, hazardous,

or dangerous to employees, and • who has authorization to take prompt corrective

measures to eliminate them. In order to be a competent person for the purpose of this standard one must have had specific training in, and be knowledgeable about, soils analysis, the use of protective systems, and the requirements of this standard.

Introduction

Page 5: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

• Conducts tests for soil classification • Understand standards and any data provided • Determines proper protective system Recognize and

reclassify soil after changing conditions • Determines if damage to trench safety equipment

renders it inadequate for employee protection • Conducts air test for hazardous atmosphere • Designs structural ramps • Locate underground installations and utilities • Monitors water removal equipment and its operation • Performs daily inspections • Keeps written records

Competent Person

Page 6: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Excavation Facts • An average of 53 workers are killed in

excavation cave-ins each year. • An average of 300 are injured. • Workers that are killed are male, 18 to 30 years

of age, with no training. • 79% of deaths occur in trenches 5 feet to 15

feet in depth. • Deaths and injuries are caused by suffocation,

crushing, loss of circulation, and falling objects

Page 7: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Excavation Facts • Excavation and trenching are

among the most hazardous construction operations.

• The Fatality rate for excavation work is 112% higher than the rate for general construction

• One cubic foot of soil weighs between 90 to 130 pounds.

• One cubic yard of soil about a front buck of a backhoe weighs as much as a small pickup truck.

Page 8: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present
Page 9: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Excavation Standards

Page 10: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Recognize the Hazard

Page 11: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Recovery

Page 12: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present
Page 13: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Definitions Collapse or Cave-in: • The separation of a mass of soil or rock

material from the side of an excavation, • or the loss of soil from under a trench shield or

support system, • and its sudden movement into the excavation, • either by falling or sliding, in sufficient quantity

so that it could entrap, bury, or otherwise injure and immobilize a person

Page 14: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Definitions Protection System: • a method of protecting employees from cave-

ins, from material that could fall or roll from an excavation face or into an excavation,

• or from the collapse of adjacent structures. • Protective systems include support systems,

sloping and benching systems, shield systems, and other systems that provide the necessary protection.

Page 15: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Definitions Sloping: • a method of protecting employees from cave-

ins by excavating to form sides of an excavation that are inclined away from the excavation so as to prevent cave-ins.

• The angle of incline required to prevent a cave-in varies with differences in such factors as the soil type, environmental conditions of exposure, and application of surcharge loads.

Page 16: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Definitions Hazardous atmospheres 1926.651(g)(1)(i)

Where oxygen deficiency (atmospheres containing less than 19.5 percent oxygen) or a hazardous atmosphere exists or could reasonably be expected to exist, such as in excavations in landfill areas or excavations in areas where hazardous substances are stored nearby, the atmospheres in the excavation shall be tested before employees enter excavations greater than 4 feet in depth

Page 17: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Definitions Hazardous atmosphere: • An atmosphere which by reason of being

• explosive, • flammable, • poisonous, • corrosive, • oxidizing, • irritating, • oxygen deficient, • toxic, or • otherwise harmful, may cause death, illness or

injury

Page 18: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Hazardous Atmosphere

Page 19: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present
Page 20: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Hazardous Atmosphere 1926.651(g)(2) Emergency rescue equipment 1926.651(g)(2)(i) Emergency rescue equipment, such as breathing apparatus, a safety harness and line, or a basket stretcher, shall be readily available where hazardous atmospheric conditions exist or may reasonably be expected to develop during work in an excavation. This equipment shall be attended when in use.

Page 21: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Definitions Excavation: • Any man-made cut, cavity, trench or

depression in an earth surface, formed by earth removal

Page 22: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Is the excavation more than 5 feet in depth?

Is the excavation entirely in stable rock?

Excavation may be made with vertical sides.

Excavation must be sloped, benched, shored, or shielded.

Is there a potential for a cave-in ?

NO YES

YES

YES

Sloping, benching selected

Shoring or shielding selected

Go to Figure 2 Go to Figure 3

FIGURE 1

Preliminary Decisions

NO

NO

Page 23: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

SLOPING IS SELECTED

Will soil be classified in accordance with 1926.652 (b)

YES

FIGURE 2

SLOPING OPTIONS

NO

Excavation must comply with 1926.652 (b) (1) Which requires a slope of 1 1/2 to 1 or 34 degrees

Excavation must comply with one of the following three options

Option 1: Sec. 1926.652(b)(3) which requires Appendices A and B to be followed

Option 2 Sec. 1926.652(b)(3) which requires other tabulated data

Option 3: Sec. 1926.652(b)(4) which requires the excavation to be designed by a registered professional engineer

Page 24: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

FIGURE 3 SHORING or SHIELDING OPTIONS

Soil Classification is required when shoring or shielding is used. The excavation must comply with one of the following four options:

Option 1: Sec. 1926.652(c)(1) which requires Appendices A and C to be followed (e.g. timber shoring).

Option 2: Sec. 1926.652(c)(2) which requires manufacturers data to be followed (e.g. hydraulic shoring, trench jacks, air shores, shields). |

Option 4: Sec. 1926.652(b)(4) which requires the excavation to be designed by a registered professional engineer

Option 3: Sec. 1926.652(c)(3) which requires tabulated data (see definition) to be followed (e.g. any system as per the tabulated data

Page 25: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Sloping

Page 26: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Benching

Page 27: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Shielding

Page 28: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Shielding

Page 29: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Underground Utilities

Page 30: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present
Page 31: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

(c) Access and egress 2. A stairway, ladder, ramp or other safe

means or egress shall be located in trench excavations that are 4 feet or more in depth so as to require no more than 25 feet of lateral travel for employees

Access Egress

50’ long trench, Ladder placed in the middle

Page 32: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

(c) Access and egress 2. A stairway, ladder, ramp or other safe

means or egress shall be located in trench excavations that are 4 feet or more in depth so as to require no more than 25 feet of lateral travel for employees

Access Egress

52’ long trench, Two ladders, one at each end

Page 33: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Traffic General Requirements 1926.651(d) Exposure to Vehicular Traffic

Always check with your states Department of Transportation for their specific guidelines for traffic diversion and control

Page 34: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

(e) Exposure to falling loads • No employee shall be permitted underneath

loads handled by lifting or digging equipment. • Employees shall be required to stand away from

any vehicle being loaded or unloaded to avoid being struck by any spillage or falling materials.

Falling objects loads

Page 35: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

• Employees shall not work in excavations in which there is accumulated water, or in excavations in which water is accumulating, unless adequate precautions have been taken to protect employees against the hazards posed by water accumulation.

Water

Page 36: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Hazards?

Page 37: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Spoil Pile 2’ minimum, 4’ recommended

Page 38: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Engineered

Page 39: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Trench Shields

Page 40: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

For instance, the chart below compares soil removal quantities and costs for a two-mile trench that is five feet wide and 15 feet deep.

Cubic Yards

Cost @ $1.00 CU yard

Cost @ $1.50 CU Yard

No Sloping 29,333 $29,333 $44,000 Type A Slope 95,333 $95,333 $143,000

Type B Slope 117,333 $117,333 $176,000

Type C Slope 161,333 $161,333 $242,000

Costs

Page 41: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Equipment • Steel trench shields • Bedding boxes • Manhole shields • Aluminum hydraulic shoring • Steel road plates

Operational & service training available

Protective Systems

Page 42: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Protective Systems Hydraulic Shields

Page 43: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

The length of the shield is determined by the length of the pipe being installed. The shield needs to be at least 4’ longer than the pipe. This will protect the workers when they are working on the ends of the pipe in case of a cave-in.

Protective Systems

Page 44: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Always ask about required pipe clearance Protective Systems

Page 45: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Protective Systems

Page 46: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Protective Systems Stacking Applications

Page 47: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Height Adaptors

• Many of today’s job require pipe with larger diameter than the standard 64” will allow.

• Pipe clearance can be increased by using height adaptors

Protective Systems

Page 48: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Protective Systems

Page 49: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Pit Boxes

Protective Systems

Page 50: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Protective Systems

Page 51: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Steel Road Plates: • Range in size from 4’ x8’-8’x20’ • One inch thick • Will handle heavy construction site loads • Lifting eyes insert installed on all road plates for

easy handling

Road Plates

Page 52: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Pump Capabilities Equipment • Quiet Flow™ sound attenuated diesel

trash pumps 4”–18” • Diesel trash pumps 3”–24” • Hydraulic submersible pumps 3”–12” • Electric submersible pumps 2”–12” • High head pumps • Air diaphragm • Double diaphragm • Pipe, hose, HDPE pipe, pipe plugs

and more!

Page 53: Excavations OSHA 1926 Subpart P · 2018. 4. 4. · • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors the entire project, keeps records, always present

Summary REQUIRED • OSHA Regulations 1926 Subpart P • Competent Person Training, trained, monitors

the entire project, keeps records, always present while work is being conducted.

• Why?

• Because not following these regulations can be deadly.