EXECUTING LARGE EPC/EPCM PROJECTS USING SCRUM VALUES AND PRINCIPLES
$BILLION AGILE
$BILLION AGILE
ABOUT ME
▸ CSM in 2004; CEC since 2010
▸ PMP since 2003; P.Eng. since 1987
▸ Agile Leadership Network National Board Member 2011-12
▸ I’ve been coaching individuals, teams and organizations in the use of Scrum since 2004
▸ Software Domains: oil and gas, financial services, insurance, medicine, transportation, workflow, digital voting
$BILLION AGILE
SESSION OUTLINE
▸ Background on Gas Plants, EPC/M projects, and WHY Scrum?
▸ Applying Scrum to a Large ($1B) EPC Project
▸ Scrum Values, Roles, Artefacts, Events
▸ Results
▸ Applying Scrum to a Large ($3B) EPCM Program
▸ Approach to Multiple Organizational Cultures and Concurrent Projects
▸ Results
▸ Taking it another step
NATURAL GAS PROCESSING PLANTS AND LARGE EPC/EPCM PROJECTS
BACKGROUND
$BILLION AGILE
WHAT’S A GAS PLANT?
▸ Processing of Natural Gas
▸ Takes feed stock from surrounding wells and removes water, sand, sulphur and other hydrocarbons
▸ 400 million cubic feet per day
… times ~5 … every HOUR
$BILLION AGILE
$BILLION AGILE
ENGINEERING, PROCUREMENT, & CONSTRUCTION PROJECT
Engineering: Deliverables are detailed design and resultant drawings for equipment procurement and construction
Procurement: Deliverables are POs resulting in materials on site when they are needed
Construction: Deliverable is an operating gas processing plant built safely
$BILLION AGILE
COST OF DELAY
▸ Delays in Reviews/Approvals
▸ things don’t get engineered or purchased fast enough
▸ therefore they don’t arrive on time
▸ therefore less time for construction
▸ higher risk of delayed ROI
$BILLION AGILE
WHAT PROBLEMS NEED SOLVING?
▸ Unclear priorities, roles, silos
▸ Lack of visible progress on what’s important and why
▸ Lack of accountability to each other
▸ Lack of understanding of true state of project
3 PILLARS OF SCRUM
SOUNDS LIKE THE …
BUILDING A $B GAS PLANT
APPLYING SCRUM TO AN EPC PROJECT
$BILLION AGILE
APPLYING SCRUM VALUES
STACK RANK PRIORITIZATION OF ISSUES AND MINIMIZING WIPFOCUS
REGULAR FEEDBACK LOOPS ON HOW WE WORK TOGETHER
COURAGE
OPENNESS
TRANSPARENT ITERATIVE PLANNING AND INSPECTION
WORKING AGREEMENTS
RESPECT
COMMITMENT TO GOALS / OUTCOMES NOT PARTICULAR SOLUTIONS
COMMITMENT
$BILLION AGILE
APPLYING SCRUM ROLES
AN EXISTING ROLE CALLED THE PROJECT MANAGER RESPONSIBLE FOR REGULARLY ESTABLISHING THE PRIORITIES AND CONTEXT FOR THE TEAM
PRODUCT OWNER
$BILLION AGILE
A NEW ROLE WE CALLED A TEAM FACILITATOR INITIALLY RESPONSIBLE FOR HELPING THE TEAM KEEP AN AGILE MINDSET AND COORDINATING THE TRANSPARENCY OF GOALS, PROGRESS AND IMPEDIMENTS.
SCRUM MASTER
$BILLION AGILE
A GROUP OF MULTIDISCIPLINARY SPECIALISTS JOINTLY RESPONSIBLE FOR PRODUCING VALUABLE DELIVERABLES TO BE CONSUMED BY THE CONSTRUCTORS
DELIVERY TEAM
$BILLION AGILE
$BILLION AGILE
APPLYING SCRUM ARTEFACTS
▸ Product Backlog
▸ Sprint Backlog
▸ Product Increment
$BILLION AGILE
Monthly update to integrated Project schedule
12-week Look Ahead
3-week Look Ahead
Iteration plan Task Execution Daily review of Iteration plan
Weekly review of 3-week Look Ahead
Monthly review of 12-week Look Ahead
Tangible progress informs
informs
informs
informs
❖ Daily standup ❖ Task burndown ❖ Roadblocks
❖ ID priorities/goals/KPI’s/owners ❖ ID/Plan and estimate tasks
Team Retrospective
Team Infrastructure
Traditional Management
informs
informs
THE PRODUCT BACKLOG
SPRINT BACKLOG
‘PRODUCT’ INCREMENT
$BILLION AGILE
APPLYING SCRUM EVENTS
▸ Sprint
▸ Sprint Planning
▸ Daily Scrum
▸ Sprint Review
▸ Sprint Retrospective
$BILLION AGILE
SPRINT
Monthly update to integrated Project
schedule
12-week Look Ahead
3-week Look Ahead
Iteration plan Task Execution Daily review of Iteration plan
Weekly review of 3-week Look Ahead
Monthly review of 12-week Look Ahead
Tangible progress informs
informs
informs
informs
❖ Daily standup ❖ Task burndown ❖ Roadblocks
❖ ID priorities/goals/KPI’s/owners ❖ ID/Plan and estimate tasks
Team Retrospective
Team Infrastructure
Traditional Management
informs
informs
SPRINT PLANNING
DAILY STAND-UP
$BILLION AGILE
SPRINT REVIEW
▸ What we accomplished, what has been actualized in the schedule
$BILLION AGILE
SPRINT RETROSPECTIVE
$BILLION AGILE
RESULTS
▸ We were able to gauge progress based on empirical evidence … rather than “it’s on track until it’s not”
▸ We were able to ensure that the team regularly understood what the project priorities were that superseded their respective discipline priorities
▸ Transferred techniques to site for Turnover
$BILLION AGILE
RESULTS
▸ Priority issue cycle time was reduced by a factor of 3.
▸ Reduced the overall Project Cycle time by 5-10%
▸ The project management team was able to maintain the original project schedule and complete construction on time.
BUILDING A PROGRAM OF EPCM GAS PLANTS
APPLYING SCRUM TO EPCM
$BILLION AGILE
APPROACH TO CULTURE
▸ Started as Traditional-based Execution and Scrum-based Oversight … NOPE
▸ Attempt to shift to a new culture … Mission, Vision, Values … Patrick Lencioni
▸ Transition ownership of Scrum approach to EPC
$BILLION AGILE
APPROACH TO COMMUNICATION
▸ Scrum of Scrums approach to Program priorities / roadblocks
▸ Applying lessons to successive projects in program sprint to sprint
▸ 24 hr rule
▸ Excel, screen sharing, telephone … still not as good as situation room
$BILLION AGILE
APPROACH TO WORK PRODUCT
▸ Iterative ‘just enough’ model reviews
▸ Breakdown/breakthrough model
▸ Seeing the gap between what is predictable and what is desired
▸ Challenging the status quo
▸ Committing to exceed
“THE RESULT OF APPLYING AGILE AND BREAKDOWNS IS THE REALIZATION THAT CHALLENGING THE STATUS QUO AND USING NON-LINEAR THINKING IS REQUIRED FOR SUCCESS. THIS DOESN’T SHOW UP IN A GANTT CHART.”
Team Survey commentary
$BILLION AGILE
$BILLION AGILE
RESULTS
▸ Priority issue cycle time are being reduced by a factor of 3.
▸ Reducing the overall Project Cycle time by 10-15%
▸ Currently on pace to deliver ahead of schedule and under budget.
THE FUTURE OF AGILITY IN EPC/M PROJECTS
$BILLION AGILE
THE FUTURE IS MINDSET OVER MECHANICS
$BILLION AGILE
AN AGILE MINDSET MIGHT ALLOW US TO …
▸ Automate the schedule progress update process to minimize the time it takes to understand progress [this is akin to continuous integration/testing]
▸ Iteratively review and update the schedule logic to ensure it is current and reflects today’s reality [this is akin to release planning]
▸ Use a floating and fluctuating end date (as scope is usually fixed) to allow the impacts of changes to be seen immediately [this is akin to release planning]
$BILLION AGILE
DECLARATION OF INTERDEPENDENCE
Agile and adaptive approaches for linking people, projects and value
–We increase return on investment by making continuous flow of value our focus.
–We deliver reliable results by engaging customers in frequent interactions and shared ownership.
–We expect uncertainty and manage for it through iterations, anticipation, and adaptation.
–We unleash creativity and innovation by recognizing that individuals are the ultimate source of value, and creating an environment where they can make a difference.
–We boost performance through group accountability for results and shared responsibility for team effectiveness.
$BILLION AGILE
CONTACT ME
▸ Simon Orrell, P.Eng. PMP CEC
▸ (403) 630-6442
▸ www.snowdolphin.com
▸ @snowdolphin
$BILLION AGILE
AGILE MANIFESTO
We are uncovering better ways of delivering projects by doing it and help others do it. Through this work we have come to value:
–Individuals and interactions over processes and tools –Completed deliverables over comprehensive reporting –Customer collaboration over contract negotiation –Responding to change over following a plan
That is, while there is value in the items on the right, we value the items on the left
$BILLION AGILE
12 PRINCIPLES
• Our highest priority is to satisfy the customer through early and continuous delivery of value.
• Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage
• Deliver value frequently, from a couple of weeks to a couple of months, with a preference to the shorter timescale.
• Business people and technical teams must work together daily throughout the project.
• Build projects around motivated individuals. Give them the environment and support they need, and trust them to get the job done.
• The most efficient and effective method of conveying information to and within a project team is face-to-face conversation.
$BILLION SCRUMTEXT
12 PRINCIPLES
• Completed deliverables are the primary measure of progress. • Agile processes promote sustainable development. The sponsors,
Technical teams, and users should be able to maintain a constant pace indefinitely.
• Continuous attention to technical excellence and good design enhances agility.
• Simplicity--the art of maximizing the amount of work not done--is essential.
• The best solutions, requirements, and designs emerge from self-organizing teams.
• At regular intervals, the team reflects on how to become more effective, then tunes and adjusts its behaviour accordingly.