executive summarymovement of heavy vehicles for earth moving and to move the equipment like dozers...
TRANSCRIPT
EXECUTIVE SUMMARY
FOR THE
“PROPOSED CEMENT MANUFACTURING PLANT”
(13.24Acres)
[Project termed under Schedule (3b) Category ‘b’ – Cement Plants as per EIA Notification
2006 and it’s Amendments]
AT
VILLAGE: VAYALUR
THESIL: KRISHNARAYAPURAM
DISTRICT: KARUR
STATE: TAMILNADU
PROPOSED BY
V. V. CEMENTS PRIVATE LIMITED.
9/454 – 4 KUMARAN NAGAR, VENUS SCHOOL BACKSIDE,
C.A.K. ROAD, KARUR – 639001
REPORT PREPARED BY
(NABET Accredited vide Certificate No: NABET/EIA/1618/SA0015 &
MoEF Recognized lab vide F.No Q-15018/29/2007-CPW)
HUBERT ENVIRO CARE SYSTEMS PVT LTD, CHENNAI.
SEP 2017
EXECUTIVE SUMMARY
1. INTRODUCTION
M/s. V. V. Cements Pvt. Ltd proposes to install 0.2 MTPA cement Manufacturing unit in
Vayalur village, Krishnarayapuram taluk, Karur District in the state of Tamil Nadu, consisting
of a 13.24 Acre land proposed with related infrastructures. It is proposed to manufacture
Ordinary Portland Cement (OPC) in the proposed plant. The proposed project cost is Rs.40
Cr.
The proposed cement production capacity of the plant is 600 TPD. The limestone
requirement of the unit is 0.255 MTPA which will be met from Imported (Limestone from
Oman).The proposed project under Category – B as per Environmental Impact Assessment
(EIA) Notification SO 1533, of 14-09-2006 which necessitates obtaining the Environmental
Clearance from Ministry of Environment, Forests & Climate Change (MoEF&CC), New
Delhi.
2. DESCRIPTION OF PROJECT
Project Location
The proposed site is located at Sy.Nos: 411/9, 411/10, 416/1, 417/4, 417/3, 413/2B and
413/2A at Vayalur Village, Krishnarayapuram Taluk, in Karur district of Tamilnadu. The site
is falls in 58J/5 of SOI Topo sheet and spatial location of the site is 100 51’ 31.21” N to 100
51’ 42.18” N and 780 20’ 24.47” E to 780 20’ 33.93” E. The site is strategically situated at
11.75 Km SSW of Kulithalai town.
Figure 0. Satellite View of proposed project site location
Table 1 Project details & Environmental Settings
S.No Item Details
1. Name of the Project Proposed 600TPD Pyro Process Cement Plant
2. Schedule and Category of Project 3(b) , Category B
3. Proposed total area 13.24Acres
4. Location
Plot/Survey/Khasra No. Sy.Nos: 411/9, 411/10, 416/1, 417/4, 417/3, 413/2B and 413/2A
Village Vayalur
Tehsil Krishnarayapuram
District Karur
State Tamilnadu
5. Nearest Railway Station/Airport Lalpet Railway station –10.16KmTrichy International Airport -41.5 Km
6. Nearest Town, City, District Town: Lalpet -9.5 KmCity: Karur-28.0 KmDistrict Hq: Karur-28.0 Km
7. Nearest habitat Nadupatti Village –0.4 Km
8. Inland water bodies Vayalur Tank - 0.170 Km NEPanjapatti Lake - 5.7 Km SW
9. Elevation 114 m
10. Project Cost Rs.4000 Lakhs
11. Present Land use Barren
12. Presence of Any Sensitive Areas Nil
13. Nearby Industries Nil
14. Environmental Consultants Hubert Enviro Care Systems Pvt. Ltd.
Land Requirement
Currently the project land is predominantly barren, the site is relatively flat on the northern
side and therefore the property has been identified as land suitable for Factory
Development. Out of the 13.2 acres total site area, 5.58 acres land area will not be used for
development and will be retained as open space.
Error! Reference source not found. – Project Site Land Use Breakup
S.No Description Area (Sq.mt) Area (Acre)
1 Factory Coverage Area 4364.58 1.0785
2 Road area 3121.54 0.7714
3 Raw Material Storage 3762.57 0.9298
4 Greenbelt (33%) 18217.26 4.5016
5 Parking 464.51 0.1148
6 Quarters 618.73 0.1529
7 Utilities 232.25 0.5739
8 Vacant Area 22613.06 5.5878
Total 53580.34 13.24
Raw Material Requirement
The major raw material for manufacture of cement is Limestone. The limestone will be
imported from Oman through ships and will be conveyed to proposed plant through trucks.
The other raw materials required for the cement manufacture are Bauxite, Iron ore, Fly ash
and Gypsum. Coal is used as fuel for combustion in the kiln.
S.No Raw Material Quantity per day (MT)
1 Lime stone 900
2 Gypsum 30
3 Fly ash 400
4 Coal 60
Water Source and Requirement
In this project water will be used for domestic and greenbelt purposes. Total fresh water
demand is 55.5 KLD and the domestic water requirement is 12.5KLD. Water will be sourced
from local panchayt water supply.
Error! Reference source not found. – Water Demand Calculation
S.No Description Fresh Water
Demand (KLD)
Treated Water
Demand (KLD)
Total Water
Demand
(KLD)
1 Domestic - Factory 3.75 - 3.75
2 Flushing - Factory 3.0 - 3.0
3 Domestic - Quarters 3.0 - 3.0
4 Washing & Flushing - Quarters 2.0 - 2.0
5 Visitors –Factory
(Domestic & Flushing)
0.75 - 0.75
6 Gardening 43 11 54
Total 55.5 11 66.5
Man Power Requirement
Total Man power requirement of this project is around 150 nos. The semi skilled and non skilled
man powers are recruiting from the nearest villages.
Power Supply Requirement
The total power requirement of this project is 3.5 MWA which is sourced from TANGEDCO. A
stand by Diesel Generator of 125KVA capacity with 20 liters per hour diesel consumption is also
used.
Manufacturing Process
The manufacturing process basically comprise of the following operation:
Cement is typically made from limestone and clay or shale.
These raw materials are extracted from the quarry crushed to a very fine powder and
then blended in the correct proportions.
This blended raw material is called the ’raw feed1 or ’kiln feed’ and is heated in a rotary
kiln where it reaches a temperature of about 1400 C to 1500 C.
In its simplest form, the rotary kiln is a tube up to 200 metres long and perhaps 6 metres
india meter, with a long flame at one end.
The raw feed enters the kiln at the cool end and gradually passes down to the hot end,
then falls out of the kiln and cools down.
The material formed in the kiln is described as ’clinker’ and is typically composed of
rounded nodules between 1mm and 25mm across.
After cooling, the clinker may be stored temporarily in a clinker store, or it may pass
directly to the cement mill.
The cement mill grinds the clinker to a fine powder.
A small amount of gypsum - a form of calcium sulphate - is normally ground up with the
clinker. The gypsum controls the setting properties of the cement when water is added.
Figure – 2: Process Flow Diagram
3. BASE LINE ENVIRONMENTAL STATUS
The baseline data for ambient air quality, surface and ground water quality, noise, and soil
quality was collected and analyzed for various parameters. The analysis results show that the
values are within the prescribed limits for ambient air quality and stack emissions. The water
quality of the area is found to be within the prescribed limits for drinking water. The fluoride
levels of the ground water samples are within prescribed limit. The noise levels are found to be
within limits. The soils are having good pH and have good water holding capacity.
4 IDENTIFICATION AND QUANTIFICATION OF IMPACTS
The major contributions of pollution in the proposed plant are emissions from the kiln, apart from
emissions from utilities, and fugitive emissions from handling, transfer and storage of minerals
and coal. The impact assessment report identified various sources of pollution, quantified the
pollution loads and identified the technologies to be adopted for the mitigation and control of the
same. The impacts on air quality due to the project are emissions from the kiln, raw mill, apart
from fugitive emissions during transfer of raw materials and solid wastes. The major pollutant is
suspended particulate matter followed by sulfur dioxide and oxides of nitrogen generated due to
combustion in the kiln at high temperature. The air quality impacts are quantified using
AERMOD, The results indicate marginal increase in the ambient air quality parameters and the
cumulative concentrations of predicted values and baseline data are within the prescribed limits
of National Ambient Air Quality standards. The required water shall be drawn from panchayat
water. The noise levels may increase due to the motors, DG set and other activity. The solid
wastes generated mainly contain dust from the control equipment, while the hazardous wastes
from DG sets contain recyclable materials like spent oil, used lead acid batteries. The fly ash
from the captive power plant is reused in cement mill. There are no endangered flora and fauna
in the impact area. Employment generation and socio economic development of the local area
is the major benefit of this project. The area which has low industrial density and medium
agricultural activity will have positive benefits due to this project.
5 ENVIRONMENT MANAGEMENT PLAN
The management plan is drawn in consultation with the project proponents, technical
consultants after evaluating various technologies available for mitigation and control of pollution.
The environment management plan is drawn to address the impacts monitored, identified and
predicted.
Construction Stage
The potential of pollution during the construction phase will be less compared to the operational
stage. During the dry season it is necessary to mitigate uplift of dust during the excavation,
levelling and transportation by spraying water in the paths, and along the temporary roads. The
clearing of plants, shrubs and trees will be kept to the minimum so as to leave sufficient space
for erection of mechanical units and for few civil constructions. The facilities like toilets, drinking
water and proper shelter for the persons staying in the construction site will be provided with
utmost importance. The toilets will be attached to septic tank so as to minimize the percolation
and to control the subsequent impact on the environment. The construction activity may involve
movement of heavy vehicles for earth moving and to move the equipment like dozers and
cranes, etc. The vehicles and equipment will be maintained periodically so as to minimize the
emissions from exhaust. The hazardous wastes of waste oil and used batteries will be sold to
authorized recyclers. The construction wastes shall be used for levelling purpose.
Operation Stage
Air Pollution
The atmospheric emissions from the cement plant constitute of flue gases from raw mill/Kiln and
DG sets, emissions from other plant operation of Crusher, Raw Mill, cement mill, packer, and
flue gases of Boiler used for captive power generation and emissions from transfer points and
transport of materials. The major emission is particulate matter from all operations, while. SO2
and NOx are generated from the kiln, Boiler, DG sets and transport vehicles.
Electrostatic precipitators are provided to the cooler stack to control/mitigate emissions from the
kiln and Boiler. The ESP has interlocking mechanism with kiln and boiler operation. Bag House
is provided to the raw mill/kiln, while bag filters are mainly used as control equipment for the
cement mills, crushers, packers and transfer points. The electrostatic precipitator and all other
control equipment shall limit the outlet dust concentration to 50 mg/Nm3. Sulphur dioxide (SO2)
originates from cement raw materials and fuel (coal); however calcium compounds bind most of
the sulphur into the clinker. Thus, the conditions within the cement kiln essentially "scrub out"
the majority of potential SO2 emissions from cement manufacturing. Emissions monitoring have
shown that SO2 emissions generally are at very low levels. The cement dust collected in the
pollution control devices is recycled back to the cement manufacturing process.
The following measures are adopted to mitigate and control fugitive emissions based on CPCB
guidelines; the transfer points of material handling section is enclosed, airborne dust at all
transfer operations/points is controlled either by spraying water or by extracting to bag filter, all
conveyor systems are closed, feeding and discharge points of conveyor belts provided with skirt
boards to avoid spillage, coal storage area is clearly earmarked, the pathways in coal yard for
vehicle movement are paved, coal is stored in covered shed, closed clinker silo system and bag
filter for clinker hoppers, regular dust suppression with water sprinkler on the haul roads, plant
roads and approach roads are made of bitumen/concrete, raw materials/Cement is fully covered
during transportation to/from the site by road/rail, open areas within the plant premises and
along the boundary of the plant premises are provided with plantation.
Noise Level Mitigation
Plant machinery like Crusher, raw mill, cement mill, compressors etc are the major sources of
noise and vibration. The following are the noise control measures under taken to ensure low
noise levels; all rotating items are well lubricated and provided with enclosures to reduce noise
transmission, extensive vibration monitoring systems are provided to check and reduce
vibrations, in general, noise-generating items such as fans, blowers, compressors, pumps,
motors etc. are specified as to limit their speeds to less than 1500 rpm to reduce noise levels,
static and dynamic balancing of equipment are carried out periodically, provision of acoustic
dampeners in foundations and insulators in the interiors.
The employees working near noise generating equipment shall be provided with personal
protective equipment like ear plugs and ear muffs. The noise levels are monitored periodically
within the plant area to check the exposure levels. The occupational safety with respect to noise
levels is evaluated periodically to ensure compliance with occupational safety standards. The
density of greenbelt around the plant boundary shall be enhanced to act as noise attenuator.
Solid Wastes
In cement manufacturing, there is no solid waste generation. The dust collected in the air
pollution control equipment is recycled in the process at the respective stage. The spent oil, oil
sludge and used batteries are collected from various sections and stored in the designated
place. The spent oil and oil sludge are co-incinerated in the Kiln. The used batteries are sent to
authorize recycler. The fly ash from CPP plant will be used in cement manufacturing process.
Wastewater
No wastewater is generated from cement manufacturing process. The main waste water is from
the domestic usage, which will be sent to sewage treatment plant. The treated wastewater is
reused for the development of green belt. Domestic wastewater of 13 KLD shall be sent to STP.
The proposed STP Capacity of 25 KLD is sufficient even after expansion.
6 OCCUPATIONAL SAFETY AND HEALTH
Occupational health centre is provided. All employees will undergo check-up on recruitment and
periodically during employment. Standard operating procedures for all occupations and
operations with respect to occupational safety and health are provided. The management and
Occupational hazards control team shall follow the hierarchy of; hazard elimination, risk
reduction at source, isolation of people from the hazard, controlling the risk by other means, and
provision of personal protection equipment.
7 PREVENTION, MAINTENANCE AND OPERATION OF ENVIRONMENT
CONTROL SYSTEM
The pollution control equipment and the waste water treatment systems are monitored
periodically and checked for their performance. Pro-active maintenance is adopted. The
environmental monitoring results are evaluated to identify the problems/under performance of
the equipment. Necessary steps are taken to rectify the identified problems/defects. The
management agrees to evaluate the performance of pollution control measures and
occupational safety measures to arrive at their efficiency and agrees to adopt mitigate measures
for efficient pollution control. All pollution control equipments are adequately designed and it is
ensured that the operating staffs of APC’s have good experience in the operation and
maintenance of the equipment. Interlocking system is provided at all critical equipment like raw
mill, kiln and cooler. Preventive maintenance is done as per the schedule to avoid breakdown.
8 TRANSPORT SYSTEMS
The raw materials and finished products are mainly transported by trucks. Trucks transporting
raw materials from the vendor yards/place to plant are covered so as to reduce emissions to the
surrounding environment. Sufficient truck parking spaces will provide near the gate, and traffic
signs are placed in the battery limit. The entry for raw material transport vehicles is kept
separate as well as exit trucks.
9 SOCIO ECONOMIC ENVIRONMENTS - CORPORATE SOCIAL RESPONSIBILITY
The V.V.Cements (Pvt.) Ltd will take responsibility for CSR activities and other social
development programs in the surrounding areas. The company has been involved in social
development activities like provision of infrastructure to schools and hospitals, provision of
toilets in schools, provision of toilets in village peoples, provision of drinking water facility in
surrounding villages, campaign for health, savings and social awareness about social evils like
dowry etc. The company employs locals as employees based on suitability. It will helps in the
upliftment of the socioeconomic status of the area.
10 GREEN BELT DEVELOPMENT
Green belt is recommended as one of the major components of Environmental Management
Plan. The industry will proposed the green belt area of 4.50 acres (33%) in the plant area. The
plant species shall be selected from CPCB guidelines of green belt development, to enhance
environmental quality through; mitigation of emissions, attenuation of noise levels, balancing
eco-environment, consumption of treated wastewater, prevention of soil erosion, and creation of
aesthetic environment.
11 POST PROJECT MONITORING
Environmental monitoring for water, air (both ambient air quality and stack emissions), noise
and soil quality shall be conducted periodically either by the proponent or a third party. The
frequency of monitoring and the quality parameters shall be as suggested by the Ministry of
Environment and Forests, Government of India as explained in the environmental monitoring
chapter. The monitoring results are assessed periodically to identify compliance related
deviations if any, to be informed to the site head and corporate environment division to take
immediate remedial action.
12 ENVIRONMENT MANAGEMENT CELL
The environment management is headed by the Manager who is assisted by EHS Head. EHS
Head interacts with Manager and other staffs in the respective unit’s environment management
cells. The responsibility of the environment management cell includes monitoring overall
environmental performance with respect to compliance, policy decisions in case of
deviations/violations, identification alternative technologies, fuels, cement constituents etc. The
environment management cell at the plant level is headed by plant head who is assisted by
environment officer, safety officer and medical officer. The chief function of each of these
officers is to monitor the compliance with the statutory regulations, and to monitor the safety,
health and environmental aspects of the plant activity. The pollution control equipment
maintenance and operation is supervised by GM (Production) who will report to plant head.
13 COST ESTIMATE FOR ENVIRONMENT MANAGEMENT
The cost estimate for the environment management proposed is presented in the following
table;
S. No. Purpose Capital Cost Lakhs (INR) Recurring Cost Lakhs (INR)
1. Greenbelt development 5 0.5
2. Solid waste Management 0.20 0.1
3. Housekeeping 0.5 0.5
4. Air Pollution Control 1.50 0.4
5. Noise Pollution Control 0.2 0.02
6. Water Pollution Control 0.5 1
7. Environmental Monitoring 1.0 0.5
Total Capital Cost 8.9 3.02
14 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN
Hazard analysis involves in the identification and quantification of the various hazards (unsafe
conditions) that exist in the proposed Cement manufacturing plant. On the other hand, risk
analysis deals with the recognition and computation of risks, the equipment in the plant and
personnel are prone to, due to accidents resulting from the hazards present in the plant.
Risk analysis follows an extensive hazard analysis. It involves the identification and assessment
of risks the neighbouring populations are exposed to as a result of hazards present. This
requires a thorough knowledge of failure probability, credible accident scenario, vulnerability of
population etc. Much of this information is difficult to get or generate. Consequently, the risk
analysis is often confined to maximum credible accident studies are discussed in detail in the
EIA report.
15 PROJECT BENEFITS
• The proposed project will create employment opportunities for the surrounding
populations directly or indirectly during and after development, which will enhance the
overall socio-economic growth of the surrounding regions.
• This cement manufacturing unit will create indirect employment for loading, unloading,
transportation and other peripheral activities like, shops and small hotels around the
area.
• Contribute to increase GDP (Gross Domestic Product).
• Socio-economic benefit to the local population as it would provide employment during
construction and in operation phase
• The project will undertake CSR activities that will additionally benefit to the
development of the population living in the area.
16 SUMMARY & CONCLUSION
VVC strongly believes in the concept of Eco friendly industrialization. This has been amply
demonstrated in the operation of cement plant in Vayalur as per standard prescribed by the
State and Central pollution Control Boards. Apart from eco-friendly operations, various socio
economic development activities have been undertaken to bring about overall socio economic
development in the area.
With the same commitment and dedication, VVC will commission the new cement plant in
Vayalur village, Krishnarayapuram Taluk, Karur District in Tamilnadu.