exide cleanup project public meeting · 4/25/2018 · slide: 11 last edit: 4/30/2018. project...
TRANSCRIPT
Slide: 1
Last Edit: 4/30/2018
EXIDE CLEANUP PROJECT PUBLIC MEETING
Wednesday, April 25, 20186:00PM – 8:00PM
Project Hotline:1-844-225-3887
DTSC Commerce Office6119 E. Washington Blvd. #120
Commerce, CA 90040
Slide: 2
Last Edit: 4/30/2018
EXIDE FACILITY CLOSURE, PHASE I
Matt Wetter, PE, QEP
Senior Hazardous Substances Engineer
Site Mitigation and Environmental Restoration Program
Slide: 3
Last Edit: 4/30/2018
Closure, Phase 1 - Overview
• Began Nov 2017, scheduled through Fall 2020 • Approximately 34 months
• Removal of Regulated Units• Removal of Containment Buildings and some
ancillary buildings• Conduct soil sampling• Develop plan for Phase 2 to address soils and
foundations• Will be coordinated with ongoing corrective action to
characterize extents of contamination
Slide: 4
Last Edit: 4/30/2018
Site Layout
Slide: 5
Last Edit: 4/30/2018
Additional Background Informationhttp://www.dtsc.ca.gov/HazardousWaste/Projects/ExideClosure.cfm
Slide: 6
Last Edit: 4/30/2018
Work Completed to Date (Nov 2017 to Present)
• Preconstruction Activities• Mobilize and set up equipment• De-energize and/or reroute electrical lines
• Sump and crack sealing (Industrial Level Caulking)• Dry decontamination (HEPA vacuuming)• Wet decontamination (pressure washing)• Off-site shipment/disposal of waste and
equipment• Preparation for Full Enclosure Unit, aka Haki
System (Scaffolding Setup)
Slide: 7
Last Edit: 4/30/2018
Regulated Unit Status
Slide: 8
Last Edit: 4/30/2018
Regulated Unit Status (RMPS Only)
Slide: 9
Last Edit: 4/30/2018
Full Enclosure Unit Construction
• Scaffolding• For support of full
enclosure unit
Slide: 10
Last Edit: 4/30/2018
Four Month Look Ahead
• Wet and dry decontamination of Regulated Units
• Decontaminate and deconstruct Regulated Units for recycling, disposal, or transfer
• Full enclosure unit (HAKI) system mobilization and complete construction
Slide: 11
Last Edit: 4/30/2018
Project Contacts
• Matt Wetter, PE, QEPSenior Hazardous Substances EngineerDTSC Closure - Project Manager [email protected]
• Dionne FaulkAssociate Government Program AnalystDTSC Closure - Public Participation [email protected]
Slide: 12
Last Edit: 4/30/2018
OFFSITE PROPERTIESWITHIN THE PRELIMINARY INVESTIGATION AREA (PIA)
By: Hortensia Muniz, P.E. Residential Cleanup Project Manager
Slide: 13
Last Edit: 4/30/2018
Offsite Properties within the Preliminary Investigation Area
Slide: 14
Last Edit: 4/30/2018
Properties Sampled
As of April 19, 2018:• 8,503 properties with
Unique Assessor Parcel Numbers (APNs) Sampled
Slide: 15
Last Edit: 4/30/2018
Properties Cleaned Up
As of April 19, 2018:
• 270 Parcels cleaned up• 186 cleaned up by Exide in the Initial Assessment
Area• 84 cleaned up by DTSC’s zone contractors • 50 in 2016 by Parsons • 34 Time Critical Removal Actions (28 in 2017 and 6 2018)
Slide: 16
Last Edit: 4/30/2018
Slide: 17
Last Edit: 4/30/2018
Cleanup Activities:• take place across
7 zones • have safeguards
to protect the health of community members and workers.
Slide: 18
Last Edit: 4/30/2018
Cleanup Activities Will:
• use of low-emission trucks and equipment,
• air monitoring, • dust suppression, • visible flags on trucks
carrying contaminated soil,
• specific routes identified in Traffic Management Plan, and
• other safeguards to protect the health of community members and workers.
Slide: 19
Last Edit: 4/30/2018
Contact Information
Hortensia Muniz, P.E. Residential Cleanup Project Manager [email protected]
Exide Project Hotline:1-844-225-3887