Expansion of Link 16 and Coalition Networking (EL16CN)
Kevin Coyne
NAVSEA Dam [email protected]
Tele + 1 757 492-7656
Mobile +1 757 672-1767
Fax +1 757 492-6522
Robin Talbot
CDSA Dam [email protected]
Tele + 1 757-492-7500
Mobile +1 757-646-4369
Fax +1 757 492-6229
Steve May
SPAWAR [email protected]
Tele + 1 619-553-8002
Mobile +1 619 887-6736
Fax +1 619 553-9096
Dr. Darren J. Sutton
RAN Scientific [email protected]
Tele +61 2 6265 5010
Mobile +61 (0) 411 257 096
Fax +61 2 6265 6628
Presented by:
Daniel D. Thomas
NAVSEA [email protected]
Tele + 1 540-653-6941
Top Level Objectives: Coalition
• Architecture– Demonstrate the ability to perform testing with coalition participants
using land based test sites in a DEP/JDEP architecture. – Verify Multi Level Security (MLS) system does not functionally
degrade Link 11/16 coalition network performance. • Data Latency • Data Assurance • Data Accuracy
– Validate ability to run and transmit a centralized simulation involving coalition participants.
– Verify that CFBLnet can be used as a viable tool to expand JDEP functionality to coalition participants.
• Combat Systems– Measure and assess the ability to act as a force in a Joint/Coalition
environment – Verify joint/coalition system performance:
• Processing and receiving of force orders • Drop tracks • Joint/Coalition ID taxonomy
Test Objectives: Coalition (Cont.)
• RIMPAC Workup– Demonstrate JDEP/DEP via CFBLnet can be used for event execution
and analysis of coalition activities in preparation for RIMPAC 06. – Utilize ASTi to communicate in an operationally realistic environment in
the JDEP network with coalition participants. – Demonstrate JDEP/DEP network can be used to validate potential MMD
requirements and objectives. – Familiarize AT S&T/Training community with RIMPAC 06 scenarios and
platform representation for both US and AT platform participants. • Realized Benefits
– Provide a roadmap for integrating coalition partners into US tactical networks without compromising the security requirements of either party.
• Coalition Networking Attributes– Assess the long term feasibility of involving coalition partners in future
distributed networking events.
Participating Systems and Organizations
• Lead Organization - NSWCDN – Training & Readiness Branch (F21)
• POC Organizations:– CDSA Dam Neck – Test Planning/Execution – SPAWAR SSC – TSR SE, Link 11/16 Data Disclosure– RAN/DSTO – AT Test Planning/Execution
XCAOCCombat Air Operations Center (CAOC)
XE-2C Grp II HWILSpace and Naval Warfare Systems Center (SSC)
XAEGIS 7.1.1 HWILWallops Island (SCSC)
XTAOM/TPS-59 HWILCamp Pendleton (MCTSSA)
XANZAC HWILHMAS Watson
XLHD HWILCDSA Dam Neck
XE-2C HE2K HWILPatuxent River (NAWC)
XAWACS HWILBoeing – Seattle (AIL)
AEGIS 5.3.8.2 HWILNSWC Dahlgren (ATRC) X
DesiredRequiredNodeSite
Notional EL16CN Network Architecture
Link 11
Link 16
AWACS30/35 w/RSIP (E15)
LHDACDS BLK1 B/L
2.1.9 P/L25
E-2C Hawkeye3.02.07
TAOM / TPS - 59AN/TYQ-23v4
US Aegis (DF)7.1.1
AUS ANZAC2.3Link 16
Link 11
CEC
CEC
US Aegis5.3.8.2
CAOC
DG/RODG
Test Execution Schedule
Activities
AT Date/Time(GMT+10:00)
US Date/Time(EST)
Test Period 5Test Period 4Test Period 3Test Period 2Test Period 1
RIMPAC 06 Workup
•Site check-in• Pre-Brief• System initialization• Status checks• Modify network as necessary.•Train AT sailors for console operations.• Data transfer
Combat System
•Site check-in• Pre-Brief• System initialization• Status checks• Modify network as necessary.• Run Armageddon scenario overlaid with the TACOPS scenario to fully exercise TSR.• Test force order processing• Data transfer
Combat System
• Site check-in• Pre-Brief• System initialization• Status checks• Modify network as necessary.• Run Armageddon scenario.• Test force order processing• Data transfer
Architecture
•Site check-in• Pre-Brief• System initialization• Status checks• Modify network as necessary.• Run TACOPS scenario.• Data transfer
Architecture
• Establish voice communications.• Site check-in• Pre-Brief• System initialization• Status checks• System performance validations• Run Seven Track Scenario for gridlock and data registration purposes.• Measure latency.• Correlate• Run TACOPS scenario.• Data transfer
Day 5 (Friday)0900 - 1700
Day 4 (Thursday)0000 – 0800
Day 3 (Wednesday)0000 – 0800
Day 2 (Tuesday)0000 – 0800
Day 1 (Monday) 0000 – 0800
Day 5 (Thursday)1600 – 2400
Day 4 (Wednesday)0700 – 1500
Day 3 (Tuesday)0700 – 1500
Day 2 (Monday)0700 – 1500
Day 1 (Sunday)0700 - 1500
Current Status
• Event Planning Underway– Test Planning Beginning Discussions
• Procedures Based On Bi-Lateral Requirements– Data Analysis Beginning Discussions
• Defining Common Formats And Methods– Engineering Discussions To Determine Network Connectivity
• CFBL Connectivity & Availability
• Conflicts With Shared Assets Have Impacted Schedule– Original December Timeframe Not Available– In Processes Of Identifying a New Period Of Availability
• Documentation Underway– PA In Progress– Security Documentation Being Generated